+ All Categories
Home > Documents > Production Capacity Enhancement of Writing and Printing Grades...

Production Capacity Enhancement of Writing and Printing Grades...

Date post: 17-Jun-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
11
Transcript
Page 1: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was
Page 2: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was

Production Capacity Enhancement of Writing and Printing Grades of Paper from 100 TPD to 140 TPD

at 7th K.M. Stone, Moradabad Road, Kashipur, District Udham Singh Nagar, Uttarakhand– 244713.

Draft EIA / EMP Report

M/s. Naini Tissues Ltd. 1

EXECUTIVE SUMMARY

1.0 PROJECT DESCRIPTION

1.1 Introduction

M/s. Naini Tissues Limited is a part of Naini Group of Industries, situated at 7th K.M. stone

from Kashipur on Moradabad Road. The Plant was commissioned in Year 2005 with a

production capacity of 100 TPD writing & Printing grades of paper. To comply with the CREP

conditions, the soda recovery plant was installed in March, 2004 commonly for Naini Tissues

Limited and Naini Papers Limited.

1.2 Type of Project

M/s Naini Tissues Ltd. has proposed for an enhancement in production capacity of writing &

printing grade of paper from 100 TPD to 140 TPD within the existing premises at 7th K.M.

Stone, Moradabad Road, Kashipur – 244713 (Dist. Udham Singh Nagar), Uttarakhand.

As per the EIA Notification the project falls in Category “A” Project activity S. No.-5(i)- (3),

further the project site lies within 10 km radius of interstate boundary (Uttarakhand-Uttar

Pradesh) hence it requires Environmental Clearance from MoEF, New Delhi.

The project was considered by EAC (M) for TOR approval on 05th April, 2013 and

Reconsideration presentation for ToR was held on 27th August, 2013. Terms of Reference

(TOR) have been issued by MoEF, New Delhi for preparation of EIA/EMP report vide its F. No.

J-11011/58/2013-IA-II (I) letter dated 13th November, 2013.

1.3 Need for the Project

In India, the demand for paper is set up to far surpass supply, with the growing emphasis on

education and alternative uses of paper.

The demand for paper is influenced by various macro-economic factors like national

economic growth, industrial production, promotional expenditure, population growth and the

Governments allocation for the educational sector. Domestic demand for paper is expected to

grow at a CAGR of 6-7%. India’s paper demand is expected to touch 8 million TPA by 2010. A

leading global paper industry consultant projects a shortage of about 0.70 million TPA by

2010.

In view of country’s growth, M/s. Naini Tissues Ltd. project will be substantially added to

enhance economy and for the company it would be another milestone project.

Page 3: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was

Production Capacity Enhancement of Writing and Printing Grades of Paper from 100 TPD to 140 TPD

at 7th K.M. Stone, Moradabad Road, Kashipur, District Udham Singh Nagar, Uttarakhand– 244713.

Draft EIA / EMP Report

M/s. Naini Tissues Ltd. 2

1.4 Brief Description of the Project

TABLE – 1

Brief Description of the Project

S. No. Particulars Details

A. Nature of project Enhancement of Production Capacity of Writing & Printing

Grades of Paper from 100 TPD to 140 TPD.

B. Size of project

(i) Plant Area � Total plant area is 20.92 ha (51.7 acres).

� Proposed expansion will be done within the existing

plant premises

� 7.69 ha (18.99 acres) i.e. 36.75 % of Total Area under

Green belt/Plantation

(ii) Proposed Production capacity Expansion of Production Capacity of Writing & Printing

Grades of Paper (From 100 TPD to 140 TPD) From Agro-

Based Residues Raw Material

C. Project Location

(i) Villages 7th K.M. Stone, Moradabad Road

(ii) Tehsil Kashipur

(iii) District Udham Singh Nagar

(iv) State Uttarakhand

(v)

Latitude &

Longitude

Latitude Longitude

29011’57’’N 78053’43’’E

D. Environmental Setting Details (with approx. aerial distance & direction from the mining

lease boundary)

(ii) Nearest Town/City o Thakurdwara at a distance of 2 km (SW direction)

o Kashipur at a distance of 5.2 km (E direction)

(iii) Nearest National Highway o SH-41 adjacent to plant boundary

o NH-74 (4.5 km in ENE direction)

o NH-121 (6.4 km in ENE direction)

(iv) Nearest Railway Station Kashipur Railway Station (6.5 Km in ENE direction)

(v) Nearest Airport Pant Nagar Airport (59 Km in ESE direction)

Interstate Boundary Interstate Boundary (Uttarakhand- UP) lies at a distance of

0.2 km in west direction.

(vi) National Parks, Wild Life Sanctuaries,

Biosphere Reserves etc.

There is no National Park, Wild Life Sanctuary, Biosphere

Reserve, Tiger / Elephant Reserve, Wildlife Corridor,

Reserved Forest (RF) / Protected Forest (PF) etc. within

10 km radius

(viii) Nearest Water Body Dhandi Nallah (Adjacent the project boundary)

Dhela river, (2.2 km in SE direction)

(ix) Seismic Zone Zone - IV as per IS: 1893 (Part-I) : 2002

E. Cost Details

(i) Total Project Cost Rs. 1514 Lakhs

(ii) Cost for Environmental Protection Capital Cost- Rs. 390 Lakhs

Page 4: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was

Production Capacity Enhancement of Writing and Printing Grades of Paper from 100 TPD to 140 TPD

at 7th K.M. Stone, Moradabad Road, Kashipur, District Udham Singh Nagar, Uttarakhand– 244713.

Draft EIA / EMP Report

M/s. Naini Tissues Ltd. 3

Measures Recurring Cost- Rs. 13.96 Lacs per Annum on additional

production

F. Requirements for the project

(i) Land requirement Proposed expansion will be done within the existing plant

premises.

(ii) Water requirement Existing

Requirement

Additional

Requirement

for Expansion

Total

Requirement

after Expansion

6000 m3/day 1595 m3/day 7595 m3/day

Source: Ground water

(iii) Manpower requirement Existing

Requirement

Additional

Requirement for

Expansion

Total

Requirement

after Expansion

280 persons 50 persons 330 persons

(iv) Power requirement Existing

Requirement

Additional

Requirement

for Expansion

Total

Requirement

after

Expansion

97,000 kWh 30,400 kWh 1,27,400 kWh

Source: Hydel (UPCL)

4 DG sets of 1500 KVA as stand by.

(v) Steam Requirement Existing

Requirement

Additional

Requirement

for Expansion

Total

Requirement

after

Expansion

600 MT/day

(6 MT/ton of

paper)

240 MT/day

840 MT/Day

(6 MT/Ton of

Paper)

Source: The unit is already having 1 no. Boiler, having 24

Ton/hour capacity at 12 Kg/cm2 pressure. To fulfill the

additional steam requirement, one more boiler of 22 TPH

capacity at 12 Kg/cm2 pressure will be installed.

(vi) Fuel

• Rice Husk

• Bagasse pith

Existing

Requirement

Additional

Requirement

for Expansion

Total

Requirement

after

Expansion

140 TPD

( Rice husk :84

TPD + Bagasse

pith : 56 TPD)

55 TPD

(Rice Husk: 33

TPD + Bagasse

Pith : 22 TPD)

195 TPD

(Rice Husk: 117

TPD + Bagasse

Pith : 78 TPD)

Source: Rice husk- Nearby area & Bagasse pith- In-

house

Source: Site Visit & Pre-feasibilty Report

1.5 Location Map

Page 5: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was

Production Capacity Enhancement of Writing and Printing Grades of Paper from 100 TPD to 140 TPD

at 7th K.M. Stone, Moradabad Road, Kashipur, District Udham Singh Nagar, Uttarakhand– 244713.

Draft EIA / EMP Report

M/s. Naini Tissues Ltd. 4

Page 6: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was

Production Capacity Enhancement of Writing and Printing Grades of Paper from 100 TPD to 140 TPD

at 7th K.M. Stone, Moradabad Road, Kashipur, District Udham Singh Nagar, Uttarakhand– 244713.

Draft EIA / EMP Report

M/s. Naini Tissues Ltd. 5

1.6 PROCESS DESCRIPTION

Pulping Process

� Raw material preparation

� Cooking in Continuous Digester

� Unbleached Pulp washing , refining , screening and cleaning

� Oxygen De-lignification

� Bleaching & Washing

� Wood Pulp Slushing and broke slushing & cleaning

Stock Preparation

Different types of pulp are mixed in different proportion as per the quality of paper.

Other additives like AKD, PAC, whitening agents, dyes, wet end additives and fillers

are also added in the pulp.

Paper Making

� The prepared stock from stock preparation is pumped to paper machine head box after

diluting it with back water. This dilute suspension of fibers and water is spread over

synthetic forming fabric uniformly through head box. This synthetic forming fabric is

endless perforated/ messed belt. It remains rotating according to machine speed

resulting in sheet formation.

� In proceeding stage water is removed from paper web by pressing and drying.

� Calendaring & winding

Converting/Finishing

� Paper Converting in the form of sheet or reels on sheet cutter and rewinder respectively

as per customer requirement.

� Sorting of cut sheets manually.

� Packing of sheets (sheets rims) and reels for dispatch.

1.6.2 Raw Material Requirement

S.

No.

Particulars Units Existing

Requirement

Additional

Requirement

Total

requirement

Source Mode of

transport

Storage

facility

(A) Raw material consumption

i. Bagasse &

Wheat

Straw

Tonne 185.5 71.5 257 Nearby

area

By Road Open

Yard

ii. Imp. Wood

pulp

Tonne 3.44 1.26 4.7 Import By Sea

/Road

Shed

(B) Chemical Consumption

Page 7: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was

Production Capacity Enhancement of Writing and Printing Grades of Paper from 100 TPD to 140 TPD

at 7th K.M. Stone, Moradabad Road, Kashipur, District Udham Singh Nagar, Uttarakhand– 244713.

Draft EIA / EMP Report

M/s. Naini Tissues Ltd. 6

i. Caustic

Soda

Tonne 26.5 10.1 36.6 Vendor By Road Tanks

ii. Oxygen Gas Tonne 1.65 1.35 3.0 Self

generation

- Vessel

iii. Hydrogen

Peroxide

Tonne 0.660 0.243 0.903 Vendor By Road Tank

iii. Lime Tonne 0.810 0.036 0.846 Vendor By Road Godown

iv. AKD Tonne 1.10 0.44 1.54 Vendor By Road Tank

v. Soap Stone Tonne 15.6 9.4 25 Vendor By Road Godown

(C) Other Chemicals Required

i. OBA Tonne 0.15 0.06 0.21 Vendor By Road Godown

ii. Starch Tonne 0.50 0.20 0.70 Vendor By Road Godown

iii. DSR Tonne 0.35 0.14 0.49 Vendor By Road Godown

iv. PAC Tonne 0.35 0.14 0.49 Vendor By Road Tank

v. U.F. Rosin Tonne 0.30 0.12 0.42 Vendor By Road Godown

vi. Anti Fluff Tonne - - - N.A. - -

2.0 DESCRIPTION OF THE ENVIRONMENT

2.1 Presentation of Results (Air, Noise, Water & Soil)

Baseline study of the study area was conducted during Summer Season, 2013.

Ambient Air Quality Monitoring reveals that the concentrations of PM10 & PM2.5 for all the 8

AAQM stations were found between 65.8 to 96.0 µg/m3 and 27.5 to 45.0 µg/m3 respectively.

As far as the gaseous pollutants SO2 and NO2 are concerned, the prescribed CPCB limit of 80

µg/m3 has never surpassed at any station. The concentrations of SO2 were found to be in the

range of 7.5 to 15.0 µg/m3. The concentrations of NO2 were found to be in range of 18.4 to

28.0 µg/m3.

Ambient noise levels were measured at 8 locations around the project site. During the

baseline study it was seen that in day time noise level varies from 51.8 to 57.4 Leq. dB (A) in

day time and in night time 42.3 to 49.5 Leq. dB (A). Noise levels at all locations were

observed to be within the prescribed limits.

The ground water analysis for all the 8 sampling stations shows that pH varies from 7.48 to

7.73 total hardness varies from 116.56 to 349.28 mg/l & total dissolved solids varies from

258 to 571 mg/l. Alkalinity as CaCO3 varies from 245.79 to 387.06 mg/l.

The analysis results for soil shows that soil is slightly alkaline in nature as pH value ranges

from 6.69-7.38 & is silty loam in texture. The concentration of Nitrogen has been found to be

in good amount in the soil samples.

Page 8: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was

Production Capacity Enhancement of Writing and Printing Grades of Paper from 100 TPD to 140 TPD

at 7th K.M. Stone, Moradabad Road, Kashipur, District Udham Singh Nagar, Uttarakhand– 244713.

Draft EIA / EMP Report

M/s. Naini Tissues Ltd. 7

2.2 Biological Environment

Flora: species which are most commonly found in the study area are Pipal (Ficus religiosa),

Kathber (Zizyphus xylopyra), Bargad (Ficus bengalensis), Babul (Acacia arabica), Imli

(Tamarindus indica), Dhak (Butea monosperma), etc.

Fauna: Commonly found animal in the study area are Langur (Prubytis entellus), Chuchundar

(Crosidora murria), Bagula (Ardea cineria), Kabutar (Columba livia), Green Girgit (Calotes

versicalor), etc.

2.3 Socio-Economic Environment

The population as per 2011 Census records is 482628 (for 10 km radius buffer zone).

Scheduled Caste population of the study area (10 km) is 16.93% and Scheduled Tribe is

0.14%.

Percentage of literacy is 74.04% and that of workers those actually engaged in occupation is

31.96%. Total no. of household in the area is 87379.

3.0 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

� Impact on Air Environment - The key air emissions from the plant activities

(loading/unloading, transportation and storage of raw materials) are Particulate Matter,

Oxides of Nitrogen (NOx) and Sulphur dioxide (SO2). Gaseous emissions are being/will

be generated from boilers and transportation of vehicles. Use of proper mitigation

measures are being/will be taken like installation of air pollution control systems, water

sprinkling during transport activities & development of green belt along the road sides

to control fugitive emissions.

� Impact on Water Environment - There is/will be minimal discharge of liquid effluent

from the plant site. All the effluent will be treated in the Effluent Treatment Plant and

the treated effluent after secondary treatment will be utilized partially in pulp mill,

green belt development, dust suppression and only surplus water after tertiary

treatment will be discharge into Dhandi Drain. Therefore, very little impact on surface

water bodies is anticipated due to discharge of treated effluents.

� Impact of Noise - During construction phase, noise will be generated from vehicle

movement for transfer of construction materials, operation of heavy equipment and

machinery like vibrators, cranes, welding machines etc. However, the impact will be of

short term duration. The plantation and the green belt around the plant boundary also

mitigate noise in the surrounding areas.

Page 9: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was

Production Capacity Enhancement of Writing and Printing Grades of Paper from 100 TPD to 140 TPD

at 7th K.M. Stone, Moradabad Road, Kashipur, District Udham Singh Nagar, Uttarakhand– 244713.

Draft EIA / EMP Report

M/s. Naini Tissues Ltd. 8

� Impact on Land Environment – No adverse impact on the surrounding land is

anticipated and no additional land will be required. It will be ensured that there would

be very little effluent discharge from the plant during operation and management will

adopt and practice best measures to minimize release of pollutants after taking control

measures outside the plant premises.

4.0 POST PROJECT ENVIRONMENTAL MONITORING PROGRAMME

TABLE 3

S. No. DESCRIPTION FREQUENCY OF MONITORING

1. Meteorological Data Daily

2. Ambient Air Quality at site Half Yearly

3. Ground Water Quality Half Yearly

4. Waste Water Quality Daily

5. Noise Level Monitoring Half Yearly

6. Soil Quality Yearly

5.0 ADDITIONAL STUDIES

The Additional Studies as per the Terms of References issued vide MoEF letter no. F. No. J-

11011/58/2013-IA-II (I) letter dated 13th November, 2013 are covered in Draft EIA/EMP

Report.

6.0 PROJECT BENEFITS

The proposed expansion project activity will help in meeting the growing demand of Paper

hence will help in the economic growth of the country. It will result in growth of the

surrounding areas by increasing direct and indirect employment opportunities in the region

including ancillary development and supporting infrastructure.

7.0 ENVIRONMENT MANAGEMENT PLAN

7.1 AIR QUALITY MANAGEMENT

� NTL has efficient air pollution control devices in existing boilers (Treema cyclone & wet

scrubber) for achieving stack emission norms prescribed by the Pollution Control

Board.

� Green belt around the periphery and within premises has been developed.

Page 10: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was

Production Capacity Enhancement of Writing and Printing Grades of Paper from 100 TPD to 140 TPD

at 7th K.M. Stone, Moradabad Road, Kashipur, District Udham Singh Nagar, Uttarakhand– 244713.

Draft EIA / EMP Report

M/s. Naini Tissues Ltd. 9

� Ambient air quality and stack emissions are regularly monitored and effective controls

exercised, so as to keep the emission within the statutory limits and same will be

continued.

� The proposed boiler will be provided with adequate stack height and Air Pollution

Control Systems to achieve stipulated norms of 100 mg/Nm3.

7.2 WATER QUALITY MANAGEMENT

Total Fresh Water requirement for the proposed expansion project is 7595 m3/day which will

be met from ground water.

� The Company has installed a soda recovery unit for processing of black liquor to

valuable soda ash which is saleable to detergent & glass industries.

� Waste water generated will be treated in the existing ETP with capacity 10,000 KL/Day

which has been upgraded as per the CPCB Charter.

7.3 NOISE MANAGEMENT

� Time to time oiling and servicing of machineries is being/will be done

� Acoustic enclosures for D.G. sets are provided.

� The green belt development helps in absorbing noise.

� Earmuffs provided to workers while running the equipments of the plant.

� Periodic monitoring is being/will be carried out

7.4 SOLID WASTE MANAGEMENT

� ETP sludge is collected in RCC Platform inside the premises.

� Boiler ash is collected directly in trolleys & shifted for filling for low lying area.

� The Boiler ash is also taken by nearby farmers on request for use in fields as manure.

The Ash can also be given to Brick manufacturers.

� The generated traces of lime sludge from calcium hypochlorite preparation plant, is

being mixed with cement & mortar for repairing of building/plaster work.

� No Hazardous waste is generated at the plant except 3 MTPA of waste oil, which is

being/will be sold to recyclers authorized by CPCB.

� Black Liquor is being sent to Soda recovery plant which can handle 220 TPD of Black

liquor.

Page 11: Production Capacity Enhancement of Writing and Printing Grades …ueppcb.uk.gov.in/files/Naini-Tissue-Executive_Summary... · 2014-06-09 · Reconsideration presentation for ToR was

Production Capacity Enhancement of Writing and Printing Grades of Paper from 100 TPD to 140 TPD

at 7th K.M. Stone, Moradabad Road, Kashipur, District Udham Singh Nagar, Uttarakhand– 244713.

Draft EIA / EMP Report

M/s. Naini Tissues Ltd. 10

7.5 GREENBELT DEVELOPMENT AND PLANTATION PROGRAM

� The Green belt development has already developed in 36.75 % are all around and inside

the plant & will further carry on the plantation, which will help in to attenuate the

pollution level.

� Green belt is developed as per Central Pollution Control Board (CPCB) guidelines.

� The Avenue plantation will give priority to native species, and the periphery is devoted

to generation of green belt area.

� Green belt development in and around the project site will help in to reduce the

pollution level of air and noise.

7.6 SOCIO-ECONOMIC ENVIRONMENT

Better education facilities, proper health care, road infrastructure and drinking water

facilities are basic social amenities for better living standard of any human being. NTL has

conducted and provided such facilities to the nearby villagers and will further improve the

facilities in the area, which will help in uplifting the living standards of local communities.


Recommended