+ All Categories
Home > Documents > PROGRAM APPRAISAL DOCUMENT -...

PROGRAM APPRAISAL DOCUMENT -...

Date post: 02-Sep-2019
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
76
DOCUMENT OF THE WORLD BANK FOR OFFICIAL USE ONLY Report No: 129798‐NP PROGRAM APPRAISAL DOCUMENT ON A PROPOSED CREDIT IN THE AMOUNT OF SDR 94.70 MILLION (US$133 MILLION EQUIVALENT) TO NEPAL FOR A SECOND BRIDGES IMPROVEMENT AND MAINTENANCE PROGRAM August 29, 2018 Transport Global Practice South Asia Region This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization.” Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
Page 1: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

DOCUMENT OF 

THE WORLD BANK 

FOR OFFICIAL USE ONLY  

Report No: 129798‐NP  

PROGRAM APPRAISAL DOCUMENT 

ON A 

PROPOSED CREDIT 

IN THE AMOUNT OF SDR 94.70 MILLION  (US$133 MILLION EQUIVALENT) 

TO 

NEPAL 

FOR A 

SECOND BRIDGES IMPROVEMENT AND MAINTENANCE PROGRAM 

August 29, 2018       

   Transport Global Practice South Asia Region  

 

This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization.” 

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

 

CURRENCY EQUIVALENTS (Exchange Rate Effective July 31, 2018) 

 Currency Unit  =  Nepalese Rupee (NPR) NPR 109.88  =  US$1 

US$ 1.41  =  SDR 1  

GOVERNMENT OF NEPAL FISCAL YEAR July 16  –  July 15 

 ABBREVIATIONS AND ACRONYMS 

AF  Additional Financing 

BIMP  Bridges Improvement and Maintenance Program 

BMS  Bridge Management System 

BoQ  Bill of Quantities 

BSMS  Bridge Site Monitoring System 

CE  Citizen Engagement 

CIAA  Commission for Investigation of Abuse of Authority 

CMS  Contract Management System 

COM  Communication and Outreach Mechanism 

CPF  Country Partnership Framework 

DATC  Design and Advanced Technology Cell  

DLI  Disbursement‐Linked Indicator 

DOR  Department of Roads 

DRO  Divisional Road Office 

EA  Environmental Assessment 

EIA  Environmental Impact Assessment 

ESMF  Environmental and Social Management Framework 

ESSA  Environmental and Social Systems Assessment 

FMIS  Financial Management Information System 

GBV  Gender‐Based Violence 

GDP  Gross Domestic Product 

GESI  Gender Equality and Social Inclusion 

GESU  Geo‐Environmental and Social Unit 

GLOF  Glacial Lake Outburst Flood 

GON  Government of Nepal 

GRM  Grievance Redress Mechanism  

GRS  Grievance Redress Service 

HMIS  Highway Management Information System 

IEE  Initial Environmental Examination 

INDC  Intended Nationally Determined Contributions 

IPCC  International Panel on Climate Change 

IPF  Investment Project Financing 

Page 3: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

 

LAPA  Local Adaptation Plans for Action 

LARRP  Land Acquisition, Resettlement, and Rehabilitation Policy 

MoF  Ministry of Finance 

MoPIT  Ministry of Physical Infrastructure and Transport 

NPC  National Planning Commission 

NVC  National Vigilance Center 

OCHS  Occupational and Community Health and Safety 

PAT  Performance Assessment Tool 

PDO  Program Development Objective 

PforR  Program‐for‐Results 

PPMO  Public Procurement Monitoring Office 

RSDP  Road Sector Development Project  

RSSP  Road Safety Support Project 

SEA  Sexual Exploitation and Abuse 

SIA  Social Impact Assessment 

SDC  Swiss Agency for Development and Cooperation 

SORT  Systematic Operations Risk Rating Tool  

SRN  Strategic Road Network 

TOR  Terms of Reference 

UNCAC  United Nations Convention against Corruption 

UNFCCC  United Nations Framework Convention on Climate Change 

WIM  Workers’ Influx Management 

   

Regional Vice President:  Hartwig Schafer Global Practice Vice President:  Makhtar Diop 

Country Director:  Qimiao Fan Country Manager:  Faris H. Hadad‐Zervos Practice Manager:  Karla Gonzalez Carvajal 

Task Team Leaders:  Dominic Patella / Oceane Keou 

Page 4: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

 

NEPAL 

Second Bridges Improvement and Maintenance Program 

TABLE OF CONTENTS   Page 

I.  STRATEGIC CONTEXT ....................................................................................................................... 1 

A.  Country Context .................................................................................................................................. 1 

B.  Sectoral and Institutional Context ....................................................................................................... 2 

C.  Relationship to Country Partnership Framework (CPF) and Rationale for Use of Instrument ........... 4 

II.  Program Description ....................................................................................................................... 4 

A.  Government program .......................................................................................................................... 4 

B.  Program Development Objective (PDO) and Key Results ................................................................... 5 

C.  PforR Program Scope ........................................................................................................................... 5 

D.  IPF Component: Consultancy Support and Institutional Development .............................................. 6 

E.  Disbursement Linked Indicators (DLIs) and Verification Protocol ....................................................... 7 

F.  Key Capacity Building and Systems Strengthening Activities .............................................................. 7 

III.  Program Implementation ................................................................................................................ 8 

A.  Institutional and Implementation Arrangements ............................................................................... 8 

B.  Results Monitoring and Evaluation ..................................................................................................... 9 

C.  Disbursement Arrangements .............................................................................................................. 9 

D.  Role of Development Partners .......................................................................................................... 10 

IV.  Assessment Summary ................................................................................................................... 10 

A.  Technical ............................................................................................................................................ 10 

B.  Fiduciary ............................................................................................................................................ 12 

C.  Environmental and Social Systems (including safeguards for IPF component) ................................ 13 

D.  Risk Assessment ................................................................................................................................. 17 

E.  Program Action Plan .......................................................................................................................... 18 

ANNEX 1. DETAILED PROGRAM DESCRIPTION ........................................................................................ 19 

ANNEX 2. RESULTS FRAMEWORK AND MONITORING ............................................................................ 25 

ANNEX 3. DLIs, DISBURSEMENT ARRANGEMENTS AND VERIFICATION PROTOCOLS ............................... 29 

ANNEX 4. SUMMARY TECHNICAL ASSESSMENT ..................................................................................... 38 

ANNEX 5. SUMMARY FIDUCIARY SYSTEMS ASSESSMENT ....................................................................... 46 

Page 5: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

 

ANNEX 6. ENVIRONMENTAL AND SOCIAL SAFEGUARDS ........................................................................ 49 

ANNEX 7. SYSTEMATIC OPERATIONS RISK RATING TOOL (SORT) ............................................................ 56 

ANNEX 8. PROGRAM ACTION PLAN ....................................................................................................... 57 

ANNEX 9. DETAILED FINANCING PLAN (PforR AND IPF COMPONENTS) .................................................. 62 

ANNEX 10. IMPLEMENTATION SUPPORT PLAN ...................................................................................... 64 

ANNEX 11. MAP (IBRD 39229) NEPAL’S BRIDGE NETWORK AT APPRAISAL OF BIMP I (2013) .................. 66 

ANNEX 12. MAP (IBRD 43444) NEPAL’S BRIDGE NETWORK AT APPRAISAL OF BIMP II (2018) ................. 67 

Page 6: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

PAD DATA SHEET 

NEPAL 

Second Bridges Improvement and Maintenance Program (BIMP II) 

PROGRAM APPRAISAL DOCUMENT 

South Asia Region Transport and ICT Global Practice 

Basic Information 

Date:  September 6, 2018   Sectors:  Roads and Highways (100%) 

Country Director:  Qimiao Fan  Themes:  Infrastructure Services for private sector  development (90%);  Governance and Institution Building (10%) 

Practice Manager  Global Practice Vice President: 

Karla Gonzalez Carvajal   Makhtar Diop 

   

Program ID:  P161929     

Team Leaders:  Dominic Patella  Oceane Keou 

   

Program Implementation Period: Expected Financing Effectiveness Date: Expected Financing Closing Date:  

Start Date:   

10/31/2018  

7/15/2023 

10/31/2018  End Date:  7/15/2023 

Program Financing Data 

[ ]  Loan  [ ]  Grant  [ ]  Other 

[ X]  Credit     

For Loans/Credits/Others (US$, millions): 

Total Program Cost: 

196.0  

Total Bank Financing: 

133.0  

Total Co‐financing: 

63.0  

Financing Gap:    

Page 7: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

ii 

Financing Source  Amount 

BORROWER/RECIPIENT  63.0 

IBRD/IDA  133.0 

Total  196.0 

Borrower: Nepal 

Responsible Agency: Ministry of Finance 

  Contact:  Mr. Shreekrishna Nepal  Title: Joint Secretary, International Economic Cooperation Coordination Division 

  Telephone No.:  +977 1 4211371  Email:  [email protected] 

Responsible Agency: Department of Roads, within Ministry of Physical Infrastructure and Transport 

  Contact:                Mr. Rabindra Nath Shrestha  Title:                   Director General, Department of Roads 

  Telephone No.:   +977 1 5529075  Email:    [email protected] 

Expected Disbursements (in US$, millions) 

Fiscal Year  19  20  21  22  23         

Annual   9.4    18.9   28.5    42.0   34.1         

Cumulative   9.4    28.3   56.8    98.9   133.0         

Program Development Objective(s) 

To provide safe, resilient, and cost‐effective bridges on Nepal’s Strategic Roads Network 

 

Compliance  

Policy 

Does the program depart from the CAS in content or in other significant respects? 

Yes  [ ]  No  [ X] 

Does the program require any waivers of Bank policies applicable to Program‐for‐Results operations? 

Yes  [ ]  No  [ X] 

Have these been approved by Bank management?  Yes  [ ]  No  [ ] 

Is approval for any policy waiver sought from the Board?  Yes  [ ]  No  [ ] 

Overall Risk Rating: High 

Legal Covenants 

Name  Recurrent  Due Date  Frequency 

Implementation Arrangements  x     

Description of Covenant 

Page 8: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

iii 

Schedule 2 Section I.A.1: “The Recipient shall maintain a Bridge Branch and Geo‐Environmental and Social Unit under DOR, with technical social and environmental safeguards, fiduciary and other Program related responsibilities for implementing the Program, all with powers, functions, capacity, staffing, and resources appropriate to fulfil their respective functions under the Operation.” 

Schedule 2 Section I.A. 3: “Recipient, through MOF, has maintained separate budget heads which shall provide for the expenditures under the Program.”  

Schedule 2 Section I. B.1:  “1.  The Recipient, through its National Planning Commission, shall:  (a)  appoint and thereafter maintain, at all times during the implementation of the Program, independent verification agents under terms of reference satisfactory to the Association (“Verification Agents”), to verify the data and other evidence supporting the achievement of one or more DLRs as set forth in the table in Section IV.A.1 of this Schedule 2 and the table in Annex to this Schedule 2.  (b)  (i) ensure that the Verification Agents carry out verification and process(es) in accordance with a detailed DLR verification protocol jointly endorsed by the Recipient and the Association; and (ii) submit to the Association the corresponding verification reports in a timely manner and in form and substance satisfactory to the Association.   (c)  In the event there is a need for verification services prior to the appointment of the Verification Agents in accordance with sub‐paragraph (a) above, put in place adequate interim arrangement satisfactory to the Association and approved in writing by the Association for verification of the DLRs.” 

Schedule 2 Section I.C: “1.  The Recipient shall ensure that: (a) all consultancy support under the Project, the application of whose results would have environmental or social implications, shall only be undertaken pursuant to terms of reference reviewed and found satisfactory by the Association; and (b) such terms of reference ensure that the consultancy support takes into consideration, and calls for application of, the Association’s safeguard policies and the relevant Recipient’s own laws relating to the environment and social aspects.  2.  The Recipient shall ensure that terms of reference for the feasibility studies, environmental and social studies and any other pertinent studies for the Potential Future Projects to be prepared under the Project, are prepared in a manner satisfactory to the Association, duly incorporate and take into consideration the requirements of the Association’s safeguard policies and environmental and health and safety guidelines and are disclosed to the Association and to the public through the Recipient’s DOR website for a duration of time satisfactory to the Association.” 

Team Composition 

Bank Staff 

Name  Title  Specialization  Unit 

Dominic Patella  Sr. Transport Specialist   Transport   GTD06 

Oceane Keou  Transport Specialist  Transport  GTD06 

Vishnu Shrestha  Consultant   Bridges  GTD06 

Bijendra Bade Shrestha  Consultant  Bridges  GTD06 

Shubu Thapa  Operations Analyst  Operations  GTD06 

Bibash Shrestha  Program Assistant  Administration  SACNP 

Shambhu Uprety  Sr. Procurement Specialist   Procurement  GGOPZ 

Ramesh Raj Bista  Consultant  Procurement   GGOPZ 

Page 9: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

iv 

Yogesh Bom Malla Sr. Financial Management Specialist 

Financial Management   GGOES 

Pradeep Kumar Shrestha 

Consultant   Financial Management  GGOES 

Jun Zen Sr. Social Development Specialist 

Social Development   GSU06 

Caroline Sage Sr. Social Development Specialist 

Social Development  GSU06 

Govind Bhatt  Consultant  Social Development  GTD06 

Annu Rajbhandari  Environmental Specialist   Environment  GEN06 

Drona Raj Ghimire   Sr. Environmental Specialist  Environment  GEN06 

Dron Pun  Consultant  Environment  GEN06 

Junko Funahashi  Lead Counsel  Country Lawyer  LEGES 

Satish Kumar Shivakumar 

Finance Officer  Financial Management  WFACS 

Page 10: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

NEPAL SECOND BRIDGES IMPROVEMENT AND MAINTENANCE PROGRAM 

I. STRATEGIC CONTEXT 

A. Country Context  

1. Over the past decade, Nepal’s economy has performed reasonably well. Growth averaged 4.3 percent (at market prices) over 2005–15. Although declining as a share in the economy, agriculture continues to play a large role, contributing 30 percent of value added. The service sector has grown in importance, accounting for half of value added in recent years. Industry, in general, and manufacturing, has grown more slowly and its relative share in the economy is falling. Similarly, exports continue to struggle, while imports are fueled by remittances. However, remittance as a share of gross domestic product (GDP) has recently been on a declining trend due to lower oil prices that have affected economic prospects in those countries with large Nepalese migrants. Inflation was in single digit for most of the past decade, with the peg of the Nepalese rupee to the Indian rupee providing a nominal anchor. Fiscal balances remained sustainable owing to strong revenue growth and modest spending. The incidence of poverty measured against the national poverty line fell by 19 percentage points between 2003/04 and 2010/11, and in 2010/111, 15 percent of the population was  counted  as  poor.  Most  multidimensional  indicators  of  poverty  also  showed  improvements  across regions in Nepal. However, these gains remain vulnerable to shocks and setbacks, as evidenced by the 2015 earthquakes which were followed by trade disruptions resulting in GDP growth of 0.6 percent in 2016, the lowest in 14 years. 

2. Data released by the Central Bureau of Statistic (consisting of a revision of the FY2017 growth rate and an updated estimate for FY2018) show that growth has been strong, despite the external shock from floods. In mid‐August 2017, the worst flood in decades destroyed 64,000 ha of standing crop, contributing to an estimated  reduction  in  the agriculture growth  rate  from 5 percent  to 2.8 percent  (in  FY2017 and FY2018, respectively). This contributed to a reduction in overall GDP growth from 7.9 percent in FY2017 to 6.3 percent in FY2018. Government revenue continued to perform well. However, spending also picked up significantly in FY2017 compared to previous years. Nevertheless, ambitious expenditure targets envisioned in the budget have not been met and the quality of spending has not improved with 60 percent of the capital spending occurring in the last quarter. Also, spending pressures have increased in the first half of FY2018 due to fiscal transfers and spending on elections, capital goods, and federalism. High inflation in the past two years has moderated sharply due to moderating inflation in India and improving supply‐side constraints. Inflation slowed to 4.2 percent (y‐o‐y) in December 2017 but increased to 6 percent (y‐o‐y) in March 2018 owing to a sharp uptick in vegetable prices. Meanwhile, credit growth slowed in early 2018 to 16.7 percent (y/y) compared to its peak of 31.9 percent in 2017; but deposits growth continued to decline, pushing up interest rates. On the external side, the cumulative effect of a sharp trade balance deterioration and a slow growth of remittances, is putting significant pressure on the current account. Economic activity, has been affected  by  the worst  floods  in  decades  particularly  affecting  agriculture  output.  This  contributed  to  a slowdown in growth from its peak of 7.9 percent in FY2017 to an estimated 6.3 percent in FY2018. 

3. A new government, backed by a historic majority in Parliament, took up office on February 15, 2018. This follows elections for all three tiers (local, state, and federal) of the state architecture defined by the new constitution, marking a protracted but successful conclusion of a political transition that began with the signing of the Comprehensive Peace Agreement in November 2006. State governments largely mirror 

1 Poverty data were last updated in 2010. The World Bank will be collaborating with the Central Bureau of Statistics to update national poverty estimates using the Annual Household Survey data (2013/14 – 2016/17) and prepare the next Nepal Living Standard Survey. 

Page 11: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

the coalition at the center. At the subnational level, funds, functions, and functionaries hitherto managed by the central, district, and village authorities are moving to the seven new states and 753 local governments for  which  new  legislation,  institutions,  and  administrative  procedures  are  being  formalized  as constitutionally  prescribed. Meanwhile,  the  central‐level  authority  is  being  streamlined with  a  focus  on oversight. These exercises at state restructuring are expected to result in improved outreach and service delivery but will likely take time before they become fully operational. 

B. Sectoral and Institutional Context  

4. Nepal’s physical and economic integration as a country depends on bridges along the Strategic Roads Network  (SRN)  that enable year‐round connectivity between  the  federal provinces. The SRN consists of 12,142 km of roads and 1,773 bridges. It carries the majority of passenger and goods transport throughout Nepal.  It also provides critical connections to  India, which  is Nepal’s  largest trading partner and primary conduit for third country trade. The bridges that stitch together different sections of SRN roads represent critical  infrastructure  for  Nepal’s  development  given  the  number  of  river  crossings  and  drainages  that Nepal’s Himalayan topography creates. Where bridges have yet to be built, or prove vulnerable to climatic conditions such as flooding, communities and entire sections of Nepal can lose connectivity to other internal regions, social services, and markets. Absent or lost connectivity impedes poverty reduction—particularly in Nepal’s rural areas. 

5. The SRN remains both incomplete and inadequate with respect to the transportation services that Nepal requires for poverty reduction and increasing shared prosperity. For example, only about 54% of SRN roads  feature  some  form  of  bituminous  surface.  Similarly,  there  are  372  identified  gaps  (totaling approximately18,861 meters) on SRN roads that require new bridge construction for improved all‐weather connectivity.  The  geographical  configuration  of  the  SRN  is  significant  to  Nepal’s  transport  connectivity challenges and national integration under the new federal structure. Nepal’s busiest highway, known as the East‐West Highway  traverses  “Terai”  districts  and  provides  a  transportation  link  that  runs  in  parallel  to Nepal’s southern border with India. This road crosses numerous large year‐round and seasonal rivers that drain hill and mountain catchments. As a  result, approximately 40% of Nepal’s existing bridge stock  (by meters) is found on the East‐West Highway. North‐south feeder roads branch off the East‐West Highway and provide access to the difficult topography of Nepal’s hill and mountain districts.  

6. SRN roads and bridges that comprise Nepal’s national road network provide the physical links that integrate Nepal as a single country. The maintenance and replacement of aging bridges along Nepal’s East‐West Highway is particularly critical to the reliability of this connectivity. The proposed operation will thus focus  on  the maintenance,  replacement,  and  new  construction  of  bridges.  The  Government  prioritizes interventions based on the Bridge Management System (BMS) that was mobilized under the IDA‐supported First  Bridges  Improvement  and Maintenance  Program  (BIMP  I).  This  system  allows  the  Government  to prioritize road links where bridge works are critical and expected to generate most impacts in terms of asset life, travel time, number of beneficiaries, and so on. Additionally, it is worth noting that the Association also supports  the  rehabilitation  of  the  road  network  through  other  complementary  projects  that  are  under implementation. 

7. Nepal’s  Department  of  Roads  (DOR)  within  the Ministry  of  Physical  Infrastructure  and  Transport (MoPIT) develops and maintains roads and bridges along the SRN. The SRN and its management is a national concern  with  resources  allocated  from  Nepal’s  Consolidated  Fund  through  the  national  budget. Implementation of SRN works is managed by 34 Divisional Road Offices (DROs) as well as Kathmandu‐based units that operate across divisions. A central Kathmandu‐based Bridge Branch within the DOR has overall jurisdiction over bridge assets and uses four regionally based Bridge Sectors to maintain field presence. It 

Page 12: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

directly manages complex bridge works using a dedicated engineering team. For less complex bridge works, DROs implement works under the Bridge Branch’s supervision and technical guidance.  

8. Monsoon flooding during the summer of 2017 demonstrated that many bridges in Nepal, particularly along the East‐West Highway are vulnerable to natural events. The International Panel on Climate Change (IPCC) suggests that Himalayan regions like Nepal will experience significant changes in weather patterns due to climate change. The World Bank’s Climate and Disaster Risk Screening tool also indicates high risks of extreme precipitation and landslides facing SRN roads and bridges. Strengthening the resilience of Nepal’s road and bridge network, particularly through greater consideration for resilient engineering designs will be important  for  adapting  to  whatever  eventualities  climate  change  will  bring  for  Nepal.  Strengthening maintenance systems is also essential for achieving greater resilience as well as cost effectiveness of Nepal’s SRN bridge investments. Regular bridge maintenance is critical to enhancing resilience and extending the useful life of assets at levels of costs that are typically well below bridge replacement. There is also a need to enhance the resilience considerations reflected in initial bridge designs that the DOR deploys in Nepal. 

9. SRN roads and bridges suffer from insufficient road safety features and the rate of road transport‐related  fatalities  in  Nepal  is  among  the  highest  in  the world.  In  part,  this  reflects  a  historical  focus  on prioritizing expansion of connectivity ahead of the quality and safety of that connectivity. Bridge rail, proper markings, approach barriers, and features to protect pedestrians and cyclists transport are typically basic and insufficient to provide for safety. The design and construction of bridges for inclusive and safe access is an area where Nepal can improve development results from bridge investments. 

10. Nationally, of the total number of people employed in the transport, storage, and communications sector  in Nepal, only 3.5 percent are women.2  This may  in part  reflect  cultural norms and preferences. Women are similarly unrepresented in Nepal’s engineering professions and the ministries or departments that manage the road networks, which represents a clear gender gap  in Nepal’s  transport sector. While there are provisions to support female and minority inclusion in the public service in Nepal, such initiatives remain at nascent stages. For example, the quota/target for female civil servants for the public service as a whole is 33 percent. There is a need to increase both the level of participation and level of inclusiveness of underrepresented groups. Rough estimates suggest that female engineers comprise about 6 percent of the DOR’s technical staff (that is, around 25 female engineers out of approximately 430). Despite being a low proportion overall, this may be slightly more than other roads sector institutions in Nepal. For example, in 2013 the Department of Local Infrastructure Development and Agricultural Roads reportedly employed only 7 female engineers (out of approximately 1,000).3 At present, there is only one female ‘class 1’ government officer4 assigned in the entirety of Nepal’s roads sector. A pilot survey of the DOR’s human resources that was conducted in March 2017 highlighted perceptions of gender bias with respect to promotion. Anecdotal evidence  also  suggests  that  female  engineers  within  road  sector  institutions  are  often  allocated organizational or administrative tasks rather than technical task which may reduce job satisfaction and limit opportunities  for  advancement.  Sourcing  more  female  engineers,  enhancing  their  technical  skills,  and elevating  their  role  in  technical  programs  can  help  strengthen  the  road  sector  institutions  of  the Government of Nepal (GON) and their ability to engage with different segments of Nepal’s population. This will be a key objective of the new Design and Advanced Technology Cell (DATC) that the proposed operation will support. Hiring and training of female engineers through the DATC will indeed help develop role models 

2 Based on International Labor Organization data, using a three‐year moving average. 3 https://blogs.adb.org/blog/meet‐nisha‐tripathee‐female‐engineer‐nepal. 4 ‘Class 1’ officers are able to hold the rank of Director General and Deputy Director General level posts. They are also potential candidates for Secretary‐level positions in Nepal’s ministries. 

Page 13: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

and bridge gender gaps, as DATC female engineers are later expected to hold various positions throughout their careers in the department. 

C. Relationship to Country Partnership Framework (CPF) and Rationale for Use of Instrument 

11. IDA’s  support  to  the  Program  aligns  with  Nepal’s  current  FY2019‐FY2023Country  Partnership Framework (CPF) dated July 10, 20185.    The CPF prioritizes the following areas: (i) Strengthening public institutions  for  effective  economic  management,  service  delivery,  and  public  investment  not  only  at national level, but at sub‐national levels.   (ii) Private sector led jobs and growth for generating more and better jobs through private sector‐driven growth, building on ongoing work to improve access to energy and  connectivity,  regulatory  environment  and  financial  sector  stability.    (iii)  Inclusion  and  diversity  to achieve greater inclusion for the poor, vulnerable, and marginalized groups, with greater resilience against climate change, natural disasters, and other exogenous shocks.   The proposed operation will contribute to Focus Area 1 and 2, through: (a) the increase of transportation connectivity in the country and with India; (b) the improvement of maintenance, safety, and quality of the infrastructure; and (c) the capacity building 

of key  institutions  in the transport sector. The proposed operation will also contribute to Focus Area 3 through the development of advanced bridge designs that provide for enhanced resilience and inclusion on non‐motorized modes.

12. The proposed operation is designed as a ‘hybrid’ operation, which includes both Program‐for‐Results (PforR) and Investment Project Financing (IPF) components. This choice of  instruments reflects  learnings from BIMP I and the Association’s long history of engagement in Nepal’s transport sector, which began in late 1970 (48 years ago). The PforR component of the hybrid operation (that is, PforR Program or Program) will  continue  to  build  on  the  successful  use  of  government  systems  achieved  under  BIMP  I.  The complementary IPF component of the hybrid operation will provide consultancy support and institutional development to the Program and the DOR with an overall aim of advancing the DOR’s design capabilities and major project planning capabilities. Pioneering design capabilities for enhancing both the resilience and inclusiveness of bridge designs will be key areas of focus for support under the operation’s IPF component. At  present,  the  DOR  does  not  have  a  government  program  that  focuses  on  pioneering  advanced technologies and the IPF instrument has been selected accordingly to lay the foundations for such a program in the future. 

13. The DOR has capacity to manage both IPF and PforR instruments in parallel and has experience of doing  so  while  also  maintaining  fiduciary  and  safeguards  policy‐related  separation  between  them  and complying with the Association’s relevant policies for each instrument. During the implementation period of the BIMP I, three parallel IPF operations were ongoing concurrently within the DOR. Of these, the Road Sector Development Project (P095977) provided consultancy support directly to the Bridge Branch which was highly effective. The design of BIMP II seeks to facilitate similar support with the added simplicity of housing both instruments under the same managing unit to enhance coordination. 

II. Program Description 

A. Government program 

14. The DOR’s program of bridge investment accounts for approximately US$60–70 million of spending per  year  (likely  US$300–US$350 million  over  the  next  five  years).  One  segment  of  this  larger  program concerns maintenance, rehabilitation, and replacement of 78,169 m of SRN bridges in addition to ongoing construction of 15,710 m of new SRN bridges. It also covers a further 18,861 m of gaps that require new 

5 CPF discussed in the Board on August 7, 2018

Page 14: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

SRN bridges over the near and medium‐term future. The BMS provides a basis for tracking bridge inventory and  gaps  that  require  future  bridges.  BMS  results  provide  prioritization  for  maintenance  and  new construction according to a multi‐criteria formula that considers need and criticality. Data from the BMS also provide an overall description of the DOR’s SRN bridge assets for planning and summary purposes. On average, bridges along the SRN are relatively short spanned and simple structures. Roughly two‐thirds of all SRN bridges are less than 40 m. Over 90 percent of all SRN bridges are less than 100 m long. Activities to be carried out under the PforR Program are detailed in section II.C (PforR Program Scope). Estimated PforR Program spending per year is indicated in annex 1. The PforR Program described in annex 1 was structured based upon analysis of BMS data and the delivery capacity of the DOR’s Bridge Branch. 

15. Beneficiaries of the Program include motorized road users, pedestrians and cyclists, and communities that derive benefits from reduced transportation costs. In Nepal this has been shown to benefit agricultural producers, which is significant because of agriculture’s role in employment and poverty reduction. A 2012 research paper illustrated how farms in hill districts that have closer proximity to Nepal’s major North‐South road links are more profitable.6 A similar study observed that, between 1997 and 2002, the likelihood of escaping  poverty  for  households  in  rural  communities  was  0.51  percent  higher  for  every  10  percent reduction in their travel time to access public services.7 

16. The  replacement  value  of  Nepal’s  existing  and  under‐construction  bridge  assets  that  the  DOR manages  stands  at  approximately  US$1.1  billion  (at  present  levels  of  cost  without  consideration  for depreciation). This is equivalent to 5.1 percent of Nepal’s 2016 GDP. The cost of building bridges along all identified gaps on the SRN is approximately US$216 million at present levels of cost, which is equivalent to a further 1 percent of Nepal’s 2016 GDP. It is important to note that these figures are not static as the SRN (and  hence  the  need  for  bridges)  continues  to  expand.  In  addition,  aging  bridges  increasingly  require maintenance  and  replacement.  There  are  also  needs  for  the  DOR  to  enhance  safety,  resilience, inclusiveness, and capacity offered by existing bridges to meet Nepal’s evolving development needs. 

B. Program Development Objective (PDO) and Key Results 

17. The PDO is to provide safe, resilient, and cost‐effective bridges on Nepal’s Strategic Roads Network. The three indicators listed in table 1 will serve to measure the PDO’s achievement.  

Table 1. PDO‐Level Results and Indicators 

PDO‐Level Result  PDO‐Level Indicator 

Safe bridges  PDO 1: Reduced likelihood of road departure crashes on Program bridges. 

Resilient bridges  PDO 2: Enhanced DOR capabilities for developing resilient bridge designs. 

Cost effective bridges  PDO 3: Estimated road user cost savings achieved by Program interventions. 

C. PforR Program Scope 

18. Developing and/or maintaining bridge infrastructure in the Strategic Roads Network under the Bridge Branch,  as  set  forth  in  the  Bridge  Policy  and  Strategy,  including:  (a)  providing  road  safety  upgrades  on existing bridges; (b) constructing new bridges; (c) completing bridges under construction; (d) major bridge maintenance; and (e) carrying out bridge designs, site assessments, feasibility studies, quality monitoring, 

6 Shrestha, Slesh A. 2012. “Access to the North‐South Roads and Farm Profits in Rural Nepal” University of Michigan. 7 Dillon, Andrew, Manohar Sharma, and Xiaobo Zhang. 2011. “Estimating the Impact of Access to Infrastructure and Extension Services in Rural Nepal.” International Feed Policy Research Institute. 

Page 15: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

environmental and social impact management, and providing logistics support, for the Program, as required for the preparation and supervision of civil works. 

19. The Recipient shall ensure that the Program excludes any activities which: (a) are likely to have significant adverse impacts that are sensitive, diverse, or unprecedented on the environment and/or affected people; (b) involve the procurement of: (1) works, estimated to cost $50,000,000 equivalent or more per  contract;  (2)  goods,  estimated  to  cost  $30,000,000 equivalent or more per  contract;  (3)  non‐consulting  services,  estimated  to  cost  $30,000,000  equivalent  or more  per  contract;  or  (4)  consultants’ services, estimated to cost $15,000,000 equivalent or more per contract;    (c) are  financed by any other financier or by the Association under any other loan, credit or grant; or (d) concern any backlog bridges that are not in compliance with the Program Fiduciary, Environmental and Social Systems. 

D. IPF Component: Consultancy Support and Institutional Development  

20. This  component will  support  the  following:  (a)  provision  of  consultancy  support  and  institutional development to the Recipient to prepare Potential Future Projects within the Strategic Roads Network, such as, including but not limited to, preparation of baseline assessments, engineering studies, feasibility studies, safeguard  assessments  and  technical  designs;  (b)  carrying  out  technical  audits  through  the  National Vigilance Center, identifying instances where implementation of works deviates from expected technical‐ and process‐related standards or  specifications;    (c) developing advanced bridge designs  to:  (i) enhance resilience  to  extreme  weather  or  seismic  events;  and  (ii)  include  pedestrians’  and  cyclists’  access;  (d) Provision of Training to develop the DOR staff and other stakeholders’ technical, social, environmental and fiduciary capabilities; (e) strengthening the institutional capacity of the Bridge Branch for the carrying out of supervision and oversight activities on the Strategic Roads Network under the Operation; (f) mobilizing, equipping and developing the Design and Advanced Technology Cell; (g) improving DOR’s occupational and community health and safety practices and its capacity to implement the Labor Act; (h) verification activities support. (i) collecting data for the impact evaluation of the Program. 

21. Table 2 summarizes financing for the hybrid operation’s PforR and IPF components. 

Table 2. Financing Summary8 

Component IDA (US$ million) 

GON US$ million) 

Total % of Total 

Amt. 

PforR Civil Works  113.09  63.01  176.10  90 

PforR Institutional Results  5.75  —  5.75  3 

Subtotal ‐ PforR component  118.84  63.01  181.85  93 

% of PforR component  65%  35%  —  — 

IPF: Consultancy Support and Institutional Development 

14.15  —  14.15  7 

Subtotal ‐ IPF component  14.15  —  14.15  7 

% of IPF component  100%  0%  —  — 

Total  132.99  63.01  196.00  — 

% of total hybrid operation  68%  32%  100.0%  — 

8 As per the “Bank Policy: Program-for-Results Financing”, the PforR Financing proceeds are disbursed upon the achievement of verified results specified as disbursement-linked indicators, and such disbursements are not dependent upon or attributable to individual Program transactions or expenditures. Therefore, the presentation in the financing summary in Table 2 and in the detailed financing plan in Annex 9 reflects GON’s anticipated internal budgetary presentation and is not meant to predetermine earmarking of the IDA PforR Financing to specific individual Program transactions or expenditures.

Page 16: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

E. Disbursement Linked Indicators (DLIs) and Verification Protocol 

22. Table 3 summarizes the DLIs and the amount of IDA financing associated with each that will apply to the PforR component. 

Table 3. DLIs, Target Quantities, and IDA Financing Amounts under PforR 

Item  Activity  Qty.  Units  US$ DLI unit rate  US$ DLI allocation 

DLI‐1  Major bridge maintenance  4,500  Meter  2,908  13,087,728 

DLI‐2  Road safety upgrades on bridges  8,000  Meter   2,181  17,450,304 

DLI‐3  New 2 lane bridge construction, rehab., and replacement of bridges 

4,000  Meter   8,822  35,288,393 

DLI‐4  New 4 lane bridge construction  2,000  Meter   12,603  25,205,995 

DLI‐5  Completion of backlog bridges under construction 

5,000  Meter   4,411  22,055,246 

DLI‐6  Improved fiduciary governance of design‐build contracting 

1  Each  2,000,000  2,000,000 

DLI‐7  BSMS (monthly monitoring system) use on Program worksites 

5,000  Meter   750  3,750,000 

Subtotal of IDA financing of PforR component DLIs  118,837,666 

F. Key Capacity Building and Systems Strengthening Activities 

23. The development and retention of  technical  specialists  remains a key challenge  for  the Program’s sustainability and effectiveness. This  is also an  impediment  to developing  capabilities needed  to deploy advanced  bridge  designs  that  can  enhance  resilience  and  inclusion.  The  Program Action  Plan  therefore envisages a new recruitment and training program for graduate engineers who would participate in a newly formed DATC within the Bridge Branch. This unit will derive support from the IPF component, including the mentorship of senior international engineers. The DATC will directly perform a portion of advanced design work ‘in house’ to develop the capacity of junior engineers. A similar approach has been used under the U.K. Department for  International Development‐supported Third Rural Access Program in Nepal and has shown promising results.  

24. A key requirement for the DATC is to recruit each year a cohort of 5 to 10 engineers. As part of an overall effort to enhance the role that female engineers play in the DOR’s programs, 33 percent or more of each engineering cohort recruited in the DATC are required to be female engineers. Over the life of the operation, the DATC is expected to provide experience to four to five different cohorts. Promotion activities related to the DATC’s creation,  including partnerships with relevant universities, will be  implemented to ensure a high level of participation from young engineers and specifically female engineers. Therefore, over the hybrid operation’s life, an estimated 7 to 17 female engineers will be hired and will receive advanced technical training/mentorship to build their capacity. They will also have practical opportunities to put those skills to use in the development of advanced bridge designs that will aim to achieve greater resilience and inclusion. 

Page 17: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

III. Program Implementation 

A. Institutional and Implementation Arrangements 

25. The DOR’s Bridge Branch will  lead Program  implementation as well  as  the  implementation of  the operation’s IPF component. Six other entities within the DOR will have key roles in supporting the Program’s functioning. Table 4 summarizes the roles of these different entities. 

Table 4. Roles/Responsibilities of Internal DOR Entities 

DOR Entity  Program role 

Bridge Branch (Lead entity for Program delivery) 

Overall stewardship of the BMS and Bridge Site Monitoring System (BSMS), management of BMS/BSMS data and software 

Implementation (including procurement and contract management) of complex works (for example high/long bridges, innovative designs, advanced maintenance, and repair methodologies) 

Oversight of implementation by DROs (for less complex works) 

Coordination of site supervision by independent consultants 

Management of design consultants and international experts  

Implementation of the IPF component of the hybrid operation on consultancy support, advanced resilience and inclusion designs, and institutional development 

Design approval, planning, monitoring, and development of Program investments 

Undertaking of quality monitoring and evaluation of worksites 

Coordination of all PforR Program and IPF activities and primary point of contact with the Association’s task team 

Results monitoring and evaluation 

Divisional Offices  Procurement and contract management of less complex works 

Bridge Sectors (Regional Directorates) 

Coordinating of monitoring and reporting to the Bridge Branch of bridge works by Divisional Offices within their respective geographical remits  

Direct monitoring and reporting to the Bridge Branch on Program bridge works within their respective geographical remits 

Planning Branch  Compilation of work plan and annual budget for the Program (which are subsequently proposed to Ministry of Finance [MoF] for consideration/inclusion in the national budget) 

Financial Administration Section 

Financial control and reporting for the Program within the DOR 

Geo‐Environmental and Social Unit (GESU)  

Lead overall management of environmental and social aspects of the Program 

Social and environmental assessments (EAs) and development of safeguards instruments in accordance with the DOR’s ESMF, and other legislative provisions of the GON 

Ensuring environmental and social consideration are adequately incorporated in project designs, bidding documents, bills of quantities (BoQs), contract monitoring systems, and other elements of contractual packages 

Environmental and social compliance assurances—including planning, implementation, monitoring, and supervisions; and seek/grant approvals/concurrences as applicable  

Page 18: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

DOR Entity  Program role 

Management of the DOR’s Grievance Redress Mechanism (GRM) complaints relating to social and environmental impacts 

Maintenance Branch 

Development of Annual Road Maintenance Plans (which also include bridges) 

26. There are six key GON  institutions  that have noteworthy  roles  relating  to different aspects of  the Program. These are summarized in Table 5. 

Table 5. Other GON Institutions and their Program Roles 

Implementation Role  Entity 

Line item budgeting and funding allocations 

MoF (both annual and medium‐term) 

Procurement oversight and complaints resolution mechanisms 

Public Procurement Monitoring Office (PPMO) 

Financial control of treasury single account system used for payments 

Finance Comptroller General’s Office 

Governance and anticorruption  NVC (technical auditing) 

Commission for the Investigation of Abuse of Authority (investigation and prosecution of suspected corruption) 

Financial auditing  Office of the Auditor General 

DLI verification  National Planning Commission (NPC) (with support from Swiss Agency for Development and Cooperation [SDC]) 

B. Results Monitoring and Evaluation 

27. The Bridge Branch will  lead and manage results monitoring and evaluation in accordance with the Program’s Results Framework in Annex 2. The BMS is directly managed by the Bridge Branch and will provide information on the location and physical condition of all bridges along the SRN. The BMS uses unique bridge identification  numbers  and  latitude/longitude  for  all  bridges.  It  also  stores  condition  photographs  and written comments from inspection events that are used for planning and prioritization purposes. The BMS has been tested under BIMP I and all condition data underwent revision and upgrade during 2017 such that it is ready to support the Program’s monitoring and evaluation needs. 

28. Alongside  the BMS,  the Bridge Branch will also use data  from the DOR’s GRM for monitoring and evaluation of Intermediate Results Indicator 4.1 (‘Responsiveness of DOR’s Grievance Redress Mechanism’). This was developed and launched under BIMP I, with support from the Association. The GRM provides a platform  for  registering  complaints  from  communities,  contractors,  department  staff,  and  the  general public.  The Association’s  team  is  also  able  to  validate  the GRM’s  function during  supervision using  test complaints. Aggregated complaints and response data  from the DRM are publicly disclosed through the DOR’s website. 

C. Disbursement Arrangements 

29. Per‐meter DLIs including DLI‐1, DLI‐2, DLI‐3, DLI‐4, and DLI‐5 will be scalable for bridges of different lengths with  rounding  to  the  nearest  one‐tenth  of  a meter  for  calculation  of  cumulative  disbursement amounts. However, disbursements against these DLIs will be ‘all or nothing’ for a single bridge. No partial disbursement  for  a  given  section  of  a  single  bridge  will  be  possible.  In  addition,  bridges  selected  for 

Page 19: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

10 

disbursement against DLI‐1 (major maintenance) and DLI‐2 (road safety) will be required to meet a full list of eligibility criteria (see Annex 3) to qualify for disbursement. Partial maintenance or partial achievement of road safety criteria will not be sufficient to pass verification unless site conditions render a full solution impossible. Any such exceptions to agreed verification criteria will be pre‐agreed on a case‐by‐case basis in writing  with  the  Association  before  the  start  of  works.  DLI‐7  relates  to  use  of  the  BSMS  that  aims  at facilitating and monitoring  site  supervision on Program worksites. Disbursement against  this DLI will  be made on the basis of complete and verified entries in the BSMS. Disbursements will be made to a Nepalese Rupee  account within  the Nepal  Rastra  Bank.  A  rolling  advance  of  up  to  25  percent  of  the  cumulative financing amount allocated to DLIs will be available to the GON as a means of supporting DLI achievement in advance of verification activities. 

30. Annex 3 lists the verification criteria that will apply to each DLI. The Bridge Branch will develop dossiers for completed physical works that will be proposed for verification. Dossiers will contain (a) documentation of  technical  specifications  and  engineering  designs,  (b)  social  and  environmental  assessments  and information on preparation/implementation of management plans, and (c) procurement documentation. For the purpose of verifying the fulfillment of the DLIs the National Planning Commission is responsible for appointing  and  maintaining,  at  all  times  during  the  implementation  of  the  Program,  independent verification agents (under terms of reference satisfactory to the Association). Verification reports submitted to the Association should be mutually satisfactory in form and substance to the Government of Nepal and the Association. The Bridge Branch will forward dossiers in batches to the NPC.  SDC will be funding and engaging independent technical advisers to work with the NPC during implementation on verification tasks. During verification, documentation in dossiers will first be reviewed to ascertain compliance with Program requirements. Field verification will  subsequently  follow on a  sample basis according  to  the proportions listed in Annex 3.  

31. DLI‐1, DLI‐2, DLI‐3, and DLI‐4 will apply to bridges with contract documents signed after April 26, 2018. DLI‐5 will apply to bridges with contract documents signed before April 26, 2018. Disbursement for prior results will be available under DLI‐5 up to 15 percent of the total IDA financing allocated toward this DLI to include those backlog bridges that have reached completion since the close of BIMP I and DLIs achieved after June 26, 2017. 

D. Role of Development Partners 

32. The Swiss Agency for Development Cooperation (SDC) will provide parallel financing to support (i) DLI verification activities under the National Planning Commission (NPC) for the Program’s initial three years; (ii) capacity development of the DOR  in  innovative bridge technology; and (iii) sound  implementation of OCHS measures and labor standards in bridge construction (see Program Action Plan).  

33. DLI verification will require funding from SDC to support technical advisers for undertaking verification activities. This arrangement was highly successful in supporting the NPC’s role in DLI verification under BIMP I. SDC’s support for the final two years will be sought by the GON. In the event that such support does not materialize, funding for the verification activities for the remainder of the Program’s implementation period will be provided under the IPF component of the operation.  

IV. Assessment Summary 

A. Technical 

34. The BIMP remains one of Nepal’s largest and most strategically relevant development initiatives due the critical role that the SRN and its bridges play in supporting economic activity. The DOR’s Bridge Branch 

Page 20: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

11 

has overall responsibility for the Program’s implementation and has demonstrated ability to achieve results under BIMP I. The Bridge Branch entails a central headquarters‐based technical office  in addition to five field‐based  Bridge  Sectors.  The  Bridge  Branch  leads  implementation  of  the  Program  works  that  are technically or contractually complex.  Simpler Program works  fall under  the  remit of  the DOR’s 34 DROs which  implement  activities  under  the  supervision  and  technical  guidance  of  the  Bridge  Branch.  The Program’s implementation arrangements have benefitted considerably from the first IDA‐supported BIMP I.  Most  notably,  under  BIMP  I,  the  Program  rapidly  expanded  its  technical  capabilities  for  designing maintenance remedies and significantly increased the level of expenditure on critical bridge maintenance works. BIMP  I also  restructured  the Program’s expenditure  framework  that enhanced  transparency and helped introduce prioritized investment planning of Program works. The Program’s expenditure framework entails  two budget headings  for Program expenditures  (currently 337320 and 337159  in Nepal’s budget document)  that  are  separate  from  the  larger  program  of  DOR  bridge  initiatives.  One  heading  supports capital investment. The other supports bridge design, site assessment, feasibility study, quality monitoring, Program  logistics  support,  and  environmental  and  social  impact  management.  The  MoF  will  similarly maintain separate budget headings for the Program’s expenditure framework under BIMP II. 

35. Despite positive past accomplishments, there is room to improve the Program’s performance further. Most  notably,  the  as‐built  quality  of  physical  works  remains  a  foremost  challenge.  Findings  from  the Association’s  technical  assessment have  identified  that quality deficiencies  are endemic  throughout  the process of bridge development and construction. One reason for this is inconsistent field‐level supervision of works. Under BIMP I, the Bridge Branch accordingly developed a new mobile monitoring application, the BSMS, that uses a tablet or smartphone interface to enable rapid reporting/sharing of site conditions and quality‐related issues. The BSMS also provides a means for Bridge Branch leadership to track the frequency of  field  visits  and  quality  of  observations  made  by  assigned  works  supervisors.  The  operation’s  IPF component  will  also  support  technical  auditing  of  Program  works  by  the  NVC  as  means  of  providing feedback on quality and one or more supervision and oversight consultancies to support the Bridge Branch with undertaking of spot checks and validation of site supervision. The Performance Assessment Tool (PAT) will be deployed as well under the Program to enhance contract monitoring. Other critical issues and areas for improvement highlighted in this technical assessment are related, among others, to the DOR’s technical capacity,  the  local  construction  industry  capacity,  and  DOR  employees’  professional  development  and performance management. 

36. Besides,  findings  from  the  technical  assessment  have  identified  opportunities  for  deploying international bridge engineering approaches to further improve the Program’s effectiveness. BIMP II will accordingly aim at deploying advanced technologies and inclusive design concepts that are not common to Nepal. However, a key learning from BIMP I is related to the challenges of integrating international expertise within  the  Program’s  implementation.  In  part,  this  reflected  the  inherent  difficulties  of  engaging international  experts  on  acceptable  terms  and  conditions  that  would  also  align  with  government expectations  and  systems.  The  complementary  IPF  component  will  therefore  support  this  agenda with engineering  inputs,  training  and  sharing  of  international  best  practices  regarding  climate  resilience  and OCHS in particular. The IPF component will indeed support the introduction of standard climate resilience mitigation  measures  in  the  engineering  designs  to  further  strengthen  the  resilience  of  Nepal’s  bridge network and decrease environmental impacts. 

Page 21: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

12 

B. Fiduciary 

PforR Component 

37. The experience of BIMP I and the team’s preliminary assessment suggest that the Program’s fiduciary systems are adequately robust to ensure that funds reach their intended purpose with due consideration for efficiency and economy. There are, however, noteworthy areas where the Program’s performance can improve to enhance performance as described below. 

38. The  Program’s  procurement  systems  are  broadly  adequate.  In  the  past,  the  Program  has  made extensive use of design‐build  contracts as a means  for accelerating  the delivery of works and capturing incremental efficiencies from the private sector. In principle, this approach has merits and was previously successful at accelerating the delivery of new bridge construction. However, there is a need to strengthen governance  around  design‐build  approaches  as  Nepal’s  institutional  and  regulatory  regimes  concerning design‐build contracting is developing. Specifically, Nepal’s Public Procurement Act (as amended in 2016 and reamended in 2017) envisages design‐build contracting but national regulations are silent with respect to the provisions that should apply to managing these types of contracts. There is also no standard design‐build contract template for implementing institutions to reference when engaging contractors for design‐build  modalities.  As  a  result,  BIMP  I  regularly  experienced  audit  objections  relating  to  its  design‐build contracts and specifically the payment of variations for which there were no governing national regulations. The Program’s DLIs therefore aim at improving both the DOR’s approach to design‐build contracting and Nepal’s overall regulatory regime for design‐build contracts. 

39. During BIMP I’s implementation, the Program experienced delays in financial and contract reporting and there were instances where the quality of reporting (trimester and audit reports specifically) required iterative improvements.  In addition, regular supervision and monitoring of active contacts and worksites was inconsistent and often weak. There has been a general reluctance to outsource supervision, monitoring, and quality management of works (for example, using a FIDIC model). Timely completion of contracts and quality  of  works  executed  under  those  contract  provisions  are  regular  concerns.  The  benefits  of  large investments can sometimes be compromised by lack of proper supervision, oversight, and monitoring which is both a fiduciary issue and related to the quality of works. There is a need to strengthen the Program’s contract and quality management systems and their application. With respect to fiduciary oversight and monitoring  of  contracts,  the  DOR  has  systems  that  should  be  generating  reporting  information automatically. These systems include the Contract Management System (CMS) and a Financial Management Information System (FMIS). However, their use is inconsistent across implementing units and data are often tabulated offline, which results in delays and errors. The Association’s final assessment has identified that the CMS and FMIS will benefit from enhanced user friendliness as well as upgraded information technology (IT) functionality. This is included in the Program Action Plan. However, it is also important to note that the underlying challenges facing CMS and FMIS may not be entirely technical in nature. As an interim measure, the Program Action Plan will seek to address contract management and reporting issues by using the PAT in parallel with CMS and FMIS to augment contract management and reporting capabilities. As part of BIMP II’s preparation, the Association has already provided training to the Bridge Branch on mobilizing the PAT. 

40. The Association has also observed that the Program may have an untapped potential to engage with and shape the market for bridge works. The DOR is the single largest purchaser of bridge works in Nepal and  is  uniquely  positioned  to  both  shape  that  market  and  drive  contractor  evolution  toward  more sophisticated  technical  capabilities  that  may  be  nationally  beneficial.  During  implementation,  the Association’s team will work with the Bridge Branch on slicing and packaging strategies for bridge works. These strategies will be used as a means for enhancing procurement efficiency and contractor performance 

Page 22: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

13 

during the Program. In parallel there is a need to better understand market participants, their constraints, and  the  opportunities  for  their  development.  The  Program Action  Plan  therefore  includes  a  contractor market assessment and strategic assessment of how the Program may seek to structure its procurement approach  accordingly  through  mechanisms  such  as  contract  bundling,  structuring  of  payments/other incentives, and incremental enhancements to technical solutions.  

41. The Program, like other public sector undertakings in Nepal, remains exposed to fraud and corruption risks. In addition to national systems under the Commission for Investigation of Abuse of Authority (CIAA), the MoPIT and the DOR also have policies and procedures covering complaints handling and redress relating to fraud and corruption as defined by the World Bank’s Guidelines on Preventing and Combating Fraud and Corruption for PforR Financing. These were included in the Financial Systems Assessment. Most notably, DOR’s GRS that was developed and approved under the IDA‐supported BIMP I operation captures and tracks complaints and responses relating to fraud and corruption (among others). Efforts to prevent and limit fraud and corruption risks facing the program will benefit from the strengthening of the DOR’s FMIS and CMS. The Program Action Plan accordingly  includes  these  items along with an action  to address and  reduce audit observations annually, which is important for eliminating financial irregularities that may be linked to fraud or corruption. 

IPF Component 

42. Under the operation’s IPF component, the procurement for goods and non‐consulting services will follow  the  Procurement  Regulations  for  IPF  Borrowers  (July  2016,  revised  November  2017).  Details  of procurement activities and procurement strategy have been prepared by the DOR using a simplified form of the Project Procurement Strategy for Development. An initial procurement plan covering the operation’s first 18 months for IPF component activities has been prepared by the DOR and reviewed by the Association. For financial management of the IPF components, the DOR will prepare a consolidated work program and budget for the IPF component’s related expenditures and will present them to the MoF annually for budget allocation and authorization to spend funds. The MoF will allocate annual budgets under a separate budget code to prevent comingling of expenditures between the Program under PforR and IPF activities. The DOR will issue budget authorization to respective cost centers. Separate expenditure accounts for the PforR and IPF  component  following  the  GON's  accounting  system  and  relevant  Financial  Procedure  Act  and Regulations will be maintained. The DOR will maintain records of consultant and suppliers, a loan register, a  program  ledger,  and  statements  of  expenditures.  Quadrimester  Implementation  Progress  Reports including Financial Monitoring Reports that differentiate between PforR and IPF‐related expenditures will be  submitted  by  the  DOR  within  45  days  of  the  end  of  each  quadrimester.  The  audit  report  with differentiation between the operation’s PforR and IPF components will be submitted within nine months of the end of the fiscal year for the PforR and IPF components. There are currently no outstanding audit reports for the MoPIT. The Program Coordinator and Accounts Officer within the DOR will be authorized signatories for  IDA disbursements.  The disbursement will  follow  reimbursement modality. Disbursement under  the hybrid operation’s IPF component will be report based. Disbursement under the hybrid operation’s PforR component will be based on achievement and verification of agreed results. 

C. Environmental and Social Systems (including safeguards for IPF component) 

PforR Component 

43. The Association conducted an Environmental and Social Systems Assessment  (ESSA) and reviewed BIMP I  lessons  learned. This has  identified that BIMP I managed the application of  the DOR’s ESMF  in a satisfactory manner overall. The ESMF is the DOR’s department‐wide framework for managing social and 

Page 23: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

14 

environmental impacts. It also includes a bridge‐specific addendum. Particularly encouraging achievements under BIMP I included (a) strengthening of GESU with a dedicated budget, additional human resources, and a greater role within the Program; (b) establishment of social and environmental screening approaches for bridges with  a  documentation  system  to  capture  assessments  and  actions within  a  ‘Bridge Dossier’  for verification purposes; (c) enhanced implementation supervision and monitoring of worksites; (d) integration of dedicated budget for environmental and social risk mitigations  in the Bill of Quantity (BoQ) for works contracts;  (e)  establishment  and mobilization  of  an  electronic  Grievance  Redress  Service  (GRS);  and  (f) inclusion of ESMF compliance within verification activities. 

44. The findings and recommendations of the ESSA were discussed with the DOR (including the Bridge Branch and GESU team members) as well as with wider stakeholders in a consultation workshop. The ESSA concludes that from policy and regulatory/legal perspectives, the borrower’s existing environmental and social management system for  the proposed scope and boundary of BIMP  II  is  consistent with  the core principles  and  elements  of  the  PforR  Financing  Policy.  The  ESSA  also  recommends  actions  for  further improving the system’s efficiency, performance, and effectiveness at operational levels. The proposed BIMP II will contribute to further strengthening the system with respect to environmental and social planning and impact management. 

45. The  DOR’s  ESMF  provides  a  comprehensive  framework  for  the  assessment  of  different  risks, development of safeguards documents, and overall management of  impacts  for  the activities envisaged under BIMP II’s PforR component. Nevertheless, there are important improvements that BIMP II can help achieve in how risks and impacts are managed in the DOR’s overall scope of works (including higher risk interventions that are beyond the scope of PforR‐financed activities). Most notably, there is a need to affect enhancements  to health and safety. A proposed partnership with an  international organization that has expertise in labor‐related risks and their management and is satisfactory to the Association is included under the  IPF  component.  This  partnership  will  accordingly  aim  at  enhancing  OCHS  practices  and  ensuring compliance with Nepal’s labor‐related laws and other provisions on key issues such as prohibition of child labor and workers’ rights. Other areas where the DOR can improve further include (a) improving focus on gender  equality  and  social  inclusion  (GESI)  and  vulnerable  community  development  initiatives  during implementation; (b) enhancing implementation of provisions on assistance to squatters; (c) improving the approach to land acquisition (discouraging land donation practices); (d) enhancing focus on capturing the beneficial impacts of bridge works beyond vehicular transportation access alone; (e) strengthening citizen engagement (CE), the communication and outreach mechanism (COM), and workers' influx management (WIM); (f) streamlining with the changes in the mandates and institutions due to restructuring of state under the  new  constitution;  and  (g)  enhancing/integrating  climate  and  disaster  resilience  and  responding  to emerging global trends in social and environmental management approaches. 

46. The hybrid operation’s PforR component supports maintenance and rehabilitation of existing bridges or construction of new bridges along existing roads. Environmental impacts are likely to be moderate and limited within the road right‐of‐way or its close vicinity. Typical environmental issues and impacts that are likely to include the following: (a) vegetation loss and reduced slope stability along bridge approaches; (b) degradation of river/stream water quality; (c) impacts on river/stream hydrology; (d) construction period disturbances  including noise, dust pollution, and spoil disposal; and  (e) OCHS  including compliance with standards on labor camps, safety gear, safe working practices, and so on. Proper engineering of approaches, abutments, and river training works is essential for impact mitigation. Similarly, proper disposal of excavated materials, location of drain outlets, drainage management, and management of quarrying operations and community  infrastructure,  cultural  heritages,  and  so  on  will  be  important.  Environmental specialists/consultants will be part of project preparation and implementation teams at each level. BIMP II will  follow  this  approach  to  ensure  implementation  and monitoring  of  environmental  compliances  and 

Page 24: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

15 

application  of  ESMF  provisions.  BIMP  I  successfully  deployed  screening  methodologies  to  guide  the development of social and environmental management plans as appropriate for specific site conditions. This approach will continue under BIMP II as a means for determining which provisions of the ESMF should apply to Program works. 

47. The Program is anticipating limited adverse social impacts that are most likely to occur in the vicinity of bridge works. Based on past experiences,  social  impacts  can  include  (a)  temporary  leasing of private assets (land and/or structures) for contractor operations; (b) permanent acquisition of private assets (land, structures, trees, crops, and so on) around bridge abutments or approaches; (c) potential impacts due to worker influx and/or underage workers; (d) exclusion and/or gaps in CE; and (e) livelihood impacts (business disruptions, disruption to agricultural operations, and so on). The DOR’s ESMF and the GON's broader legal and policy framework that applies to the Program include provisions for land acquisition, resettlement and rehabilitation  measures  for  the  adversely  affected  persons/families  with  special  focus  on  vulnerable communities  (Indigenous  Peoples).  These  include  the  (a)  Land  Acquisition  Act;  (b)  Land  Acquisition, Resettlement,  and  Rehabilitation  Policy  (LARRP);  and  (c)  National  Foundation  for  Development  of Indigenous Nationalities Act. The framework provided by the DOR’s ESMF and the GON’s other laws and policies has distinct provisions applicable to adversely affected non‐titleholders/squatters who occupy lands informally. The Association’s team is also working with the DOR to strengthen implementation of labor camp and child labor‐related provisions of the ESMF based on a recently completed independent assessment of labor risks across IDA‐supported worksites in Nepal’s transport sector. Social management personnel shall be part of project preparation and implementation teams at each level. Likewise, the social management approach of BIMP II will synergistically focus on further enhancing aspects such as CE (including mobilization of inclusively formed ‘local consultative forums’ throughout the project cycle as per DOR ESMF provisions for new bridge construction sites), GESI, COMs, Grievance Management Systems, child worker prohibition, and WIM. Where required, social and environmental management plans will be developed to manage the impact of works. 

48. The Program is exposed to key labor‐related risks that can threaten achievement of its development objective.  These  include  (a) worker  and  community  safety  on  and  around worksites,  (b)  child  labor,  (c) management of labor influx and camps, (d) workers’ rights and redress, and (e) gender‐based violence (GBV) and  sexual  exploitation  and  abuse  (SEA).  The  Program  will  follow  a  three‐tiered  approach  to  further strengthen the systems it deploys to manage such risk as contained in the Program Action Plan. Tier 1 will focus  on  policies  and  standard  guidelines.  Tier  2  will  focus  on  strengthening  implementation  of  those policies and guidelines. Tier 3 will focus on system validation to provide feedback and remedies as needed to ensure that labor‐related risks are being effectively managed in practice. DLI‐7 which relates to the use of the BSMS is also an important mitigation mechanism for labor‐related risks. The BSMS enables validation of field supervision activities and provides a means for assigning personal accountability to critical site visit and monitoring functions that can serve as early warnings regarding labor‐related risks. Enhanced contract provisions for Program works will also provide means for penalizing contractors financially when gaps in key labor‐related risk mitigations are spotted. 

49. A key learning regarding the Program’s environmental and social systems under BIMP I concerned the timing  of  assessments  and  the  integration  between  technical,  social,  and  environmental work  streams. There were instances during BIMP I when social and environmental work was not optimally phased relative to  parallel  engineering  work.  Specifically,  the  Association’s  supervision  identified  examples  of  designs advancing  and  proceeding  to  tender  before  social  and  EAs  completing  and  providing  inputs  relating  to mitigations  for  inclusion  in contract  terms  (bidding documents, and so on). This often  resulted  in costly contract variations or suboptimal mitigations being adopted in an ex post manner. In part, this reflected instances  of  poor  communication  between  the  Bridge  Branch  and  GESU  that  occasionally  arose  during 

Page 25: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

16 

particularly busy periods. It also reflected an unstructured approach to managing the preparation of bridge investments  from  concept  to  readiness  for  tender.  The  Program  Action  Plan  will  seek  to  mitigate  the likelihood of recurrence by adopting a codified system of stages and Gate Reviews for the development of Program works  packages. Gate  Reviews will  aim at  preventing works  packages  from advancing without required technical, social, and environmental preparations occurring in proper sequence. In addition, the Action  Plan  also  includes  the  implementation  of  key  enhancements  to  social  and  environmental  risk management as identified by the ESSA. 

IPF Component 

50. The  operation’s  IPF  component  includes  activities  such  as  feasibility  studies,  technical  studies, engineering design studies, and preparation of safeguards documents as part of the preparation of potential future projects. The actual implementation of those potential future projects is not part of the operation. It is likely that some of those future potential projects would be classified as ‘Category A’” for the purpose of the Association’s Environmental Assessment Policy. The category of each future potential project or bridge that will be prepared under the IPF component will be confirmed in accordance with the screening criteria as per OP 4.01 ‘Environmental Assessment’ as well as Nepal’s legislative requirements and the DOR’s ESMF that guides  their  implementation. Model Terms of Reference  (TORs)  for  the development of safeguards documents have been prepared, reviewed, cleared by the Association and publicly disclosed. Site‐specific assessment reports and prepared plans relating to ‘Category A’ projects will be reviewed and cleared by the Association, approved by the concerned GON authorities, and disclosed by the Association and the DOR for a  duration  of  time  that  is  satisfactory  to  the  Association  before  the  execution  of  assignments.  During implementation, model TORs will be customized to site‐specific interventions. Any site‐specific studies and safeguards documents for each Category A intervention will be reviewed and cleared by the Association.  

51. For  environmental  risk management, OP/BP  4.01  Environmental  Assessment, OP/BP  4.04 Natural Habitats,  OP/BP  4.36  Forests,  and  OP/BP  4.11  Physical  Cultural  Resources  are  triggered  for  the  IPF component because one or more of the bridges to be constructed with support from this component may have  adverse  consequences  relevant  to  those  aspects,  depending  on  the  location  and  details  of  the proposed  intervention/bridge.  For  social  impacts,  OP/BP  4.10  (Indigenous  Peoples)  and  OP/BP  4.12 (Involuntary Resettlement) are triggered. Safeguards documents will be prepared in accordance with these policies.  

52. Communities  and  individuals  who  believe  that  they  are  adversely  affected  as  a  result  of  a  Bank supported operation, as defined by the applicable policy and procedures, may submit complaints  to the existing program grievance redress mechanism or the World Bank’s Grievance Redress Service (GRS). The GRS  ensures  that  complaints  received  are  promptly  reviewed  in  order  to  address  pertinent  concerns. Affected communities and individuals may submit their complaint to the WB’s independent Inspection Panel which determines whether harm occurred, or could occur, as a result of WB non‐compliance with its policies and procedures. Complaints may be submitted at any time after concerns have been brought directly to the World Bank's attention, and Bank Management has been given an opportunity to respond. For information on how to submit complaints to the World Bank’s corporate Grievance Redress Service (GRS), please visit http://www.worldbank.org/GRS.  For  information  on  how  to  submit  complaints  to  the  World  Bank Inspection Panel, please visit www.inspectionpanel.org. 

Page 26: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

17 

D. Risk Assessment 

53. The  Program’s  overall  risk  rating  is High  primarily  on  account  of  political  and  governance  risks  in combination  with  risks  relating  to  sector  strategies  and  policies  (including  risks  relating  to  competing investment programs), and environmental and social risks.  

54. Political  and  governance  (High).  Political  and  governance  risks  are  rated High.  In  contrast  to  the frequent changes in government that characterized Nepal’s decade‐long transition to federalism, the new government enjoys a historic supermajority in Parliament. Along with new constitutional checks and a far fewer number of political parties, there is a much greater degree of optimism for stability  in the coming days.  However,  state  restructuring  on  this  scale  is  uncharted  territory  for  Nepal  and  smoothening  the transition from the previous unitary system to the new federal one will remain a daunting task. The new system, in principle, provides opportunities to decentralize development benefits and make service delivery more effective  and accountable. However,  the  risks of  jurisdictional  overlap between  the  three  tiers of government, lack of clarity and coherence between policies and devolved powers, and duplication of efforts will remain high during the coming few years. Key aspects of the new system require further definition and may continue to be contested by different population groups. 

55. Sector strategies and policies (High). There are similarly high risks relating to sector strategies and policies. There is currently no agreed approach to how Nepal’s road and bridge network will divide across federal and provincial  jurisdictions. The details of how the Program would operate as  federalism will be effectively implemented in Nepal in the next few years will likely need to be worked out during Program implementation. The Program currently functions as a national concern but entails both centrally managed works  and  works  that  are  managed  by  locally  based  Divisional  Offices  (which  are  currently  under  the national  government).  This  approach  straddles  potential  administrative  boundaries  that  federal restructuring  may  create.  Formal  changes  to  Program  implementation  arrangements  may  become necessary to accommodate altered institutional mandates and accountability structures which are yet to be defined. The process whereby such changes takes place may also be lengthy, circuitous, and iterative. While risks remain high, continuing the Program’s development is a way of supporting the GON to shape sound sector strategies and policies through the eventual transition. The Program only focuses on the SRN that is most likely to remain under the responsibility of the central government (specifically the DOR). This helps mitigate potential risks induced by the federalization process to some extent. 

56. There is also a high risk relating to the Program’s vulnerability to competing initiatives. Specifically, the DOR has historically been compelled  to construct bridges along  the  local  roads network. The DOR’s involvement in this subset of Nepal’s transport infrastructure stretched the department beyond its mandate and  available  resources. However,  the  strong  demand  for  local  transport  infrastructure  affects  political decisions to prioritize its delivery. The BIMP I Program was severely affected by bridge construction activities along the local roads network, particularly during years when political instability prevented the GON from defining clear and coherent priorities for road and bridge construction. 

57. Environment and social  (High). While  the Program’s environmental  impacts,  land acquisition, and resettlement activities are envisaged to be minor, environmental and social risks are rated High. This is due to  the  vulnerability  of works  to  natural  disasters  and  climate  change  as  confirmed by  the Association’s Climate and Disaster Risk Screening Tool. During Nepal’s 2017 monsoon season bridges along the East‐West Highway, including BIMP I sites, were affected by flooding. The risk of future, similar events remains high and is a key reason that the hybrid operation’s development objective includes a strong focus on resilience. The project also has potential exposure to child labor risks and risks associated with labor influx such as GBV and risk of SEA. The Program Action Plan includes a multi‐tiered approach that the Program will follow to 

Page 27: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

18 

further mitigate these risks. The Association’s Implementation Support Plan also includes a pillar on labor risk management. This will focus on monitoring enforcement of contract provisions relating to labor camps, workers’ conduct, prohibition of child labor, and access to resources for communities that may be affected. The Association is currently working with Nepal’s National Women’s Commission on improving knowledge and access to resources for individuals and communities affected by GBV/SEA. The Association’s team will integrate this work with the operation’s community outreach and engagement efforts led by GESU. 

58. Project preparation under the IPF component has the potential for links to significant adverse impacts that are sensitive, diverse, or unprecedented on the environment and/or affected people. This component is accordingly considered as a Category A activity and the following safeguards policies are triggered: (a) Environmental Assessment OP/BP 4.01, (b) Natural Habitats OP/BP 4.04, (c) Forests OP/BP 4.36, (d) Physical Cultural Resources OP/BP 4.11, (e) Indigenous Peoples OP/BP 4.10, and (f) Involuntary Resettlement OP/BP 4.12. The Bridge Branch will deploy the DOR’s ESMF that was updated and disclosed in 2013 under BIMP I to  include  bridge‐related  materials,  to  categorize  potential  impacts,  and  to  develop  associated  risk mitigations.  Screening  reports  along  with  TORs,  final  reports,  and  safeguards  documents  will  be subsequently disclosed on the DOR and World Bank websites. 

59. Fiduciary (Substantial). Government programs in Nepal remain vulnerable to fraud and corruption. There are accordingly ‘substantial’ fiduciary risks facing the Program, which could impede achievement of development  objectives.  For  bridge works,  key  concerns  relate  to  collusion  or manipulation  of  bidding processes,  fraudulent  claims  for payment  against quantity  items  (for  example,  earthworks,  aggregates), deficient  quality  combined with  inappropriate  payments  for  completed works,  and  erroneous  contract variations. The Program’s systems for mitigating fiduciary risks remain imperfect but will also benefit from additional  strengthening measures  in  the  Program  Action  Plan.  These  include  (a)  verification  of  Bridge Dossiers  and  physical  inspection  of  Program bridges  as  required  to  trigger  disbursements,  (b)  technical auditing by  the NVC and subsequent  referral of serious non‐compliances  to Nepal’s Commission  for  the Investigation of Abuse of Authority, (c) use of the BSMS which offers enhanced means of quality control on remote worksites, (d) deployment of the PAT to enhance contract monitoring and management, and (e) deployment of one or more supervision and oversight consultancies. 

E. Program Action Plan 

60. The  Program  Action  Plan  includes  strengthening  measures  relating  to  technical,  fiduciary,  and environmental/social performance. Key actions under each of these headings relate to (a) enhancing DOR’s ability to design resilient bridges, supervise their construction effectively, and root the overall Program in a sound  planning/policy  framework;  (b)  strengthening  DOR’s  fiduciary  control  over  bridge works;  and  (c) helping  the  DOR  to  leverage  technology  such  that monitoring  and  reporting  of  contracts  and  financial transactions becomes faster and more accurate; and (d) upgrading the DOR’s ability to plan, implement, and enforce mitigations to key social and environmental risks—the operation will deploy a new multi‐tiered approach to achieving this as defined in the Program Action Plan; and (e) ensuring that the DOR continues to attract, retain, and develop talented technical staff. This is a critical part of maintaining the DOR’s strength into the future as many senior engineers retire in the near future.   

Page 28: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

19 

ANNEX 1. DETAILED PROGRAM DESCRIPTION 

DLI‐1: Major bridge maintenance (US$13.1 million) 

1. The Program will support major maintenance interventions on approximately 90 bridges (4,500 m) to improve resilience, extend asset lives, and prevent failures. Many of Nepal’s bridges are 40–50 years old. While the IDA‐supported BIMP I and RSDP AF II have made progress against maintenance needs, additional support from BIMP II is necessary to continue the Program’s positive trajectory and to further the Bridge Branch’s experience of diagnosing and prescribing  remedies  to address  vulnerabilities  and aging assets. Bridge works  included  in  this  DLI  category  are  required  to  come  through  the  BMS’  prioritized  list  that considered data on condition, detour times, and beneficiary populations served.  

DLI‐2: Road safety upgrades on bridges (US$17.5 million) 

2. The Program will support approximately 8,000 m of road safety upgrades on existing bridges. Road safety upgrades will consist of the interventions listed in Annex 3, which include (a) bridge rail, (b) approach barriers and transitions, (c) pedestrian and cyclist safety, and (d) markings. Bridges that go for verification against agreed DLIs will need to meet full road safety criteria unless site conditions render partial solutions as  the  only  practicable  option.  Examples  of  justifications  could  include  topography  constraints  and/or structural limitations of bridges. These cases will be agreed with the Association in writing on a case‐by‐case basis before the start of works. 

DLI‐3: New 2 lane bridge construction, rehab., and replacement of bridges (US$35.3 million); and DLI‐4: New 4 lane bridge construction (US$25.2 million) 

3. There is a total of approximately 372 identified gaps (that is, 18,860 m) on the SRN. The Program will support the new construction, rehabilitation, or replacement of approximately 80 new 2 lane bridges (about 4,000 m) to address these gaps. In addition, there are bridges that require replacement and widening to accommodate  greater  traffic  volumes.  The  Program  will  accordingly  support  the  construction  of approximately 35 4 lane bridges (about 2,000 m). Bridges under DLI‐3 and DLI‐4 will be selected exclusively from  the  BMS‐generated  priority  list.  Backlog  bridges  with  contracts  signed  before  BIMP  II’s  date  of appraisal (April 26, 2018) will not be eligible for disbursement against either DLI‐3 or DLI‐4. All new 2 lane bridges proposed for disbursement against DLI‐3 must have estimated Average Annual Daily Traffic greater than 100 Passenger Car Unit (equivalent) according to the DOR’s Highway Management Information System (HMIS) at the time of verification. All 4 lane bridges proposed for disbursement against DLI‐4 must have an estimated Average Annual Daily Traffic greater than 3,000 Passenger Car Unit (equivalent) according to the DOR’s HMIS at the time of verification. 

DLI‐5: Completion of backlog bridges under construction (US$22.1 million) 

4. At present,  the DOR  is constructing 231 bridges  (14,959 m) on the SRN. The Program will provide funding to bring 92 bridges (about 5,000 m) to full completion. Bridges that will go for completion under this  DLI  will  require  complete  Bridge  Dossiers  that  evidence  compliance  with  Program  procurement, environmental, social, and technical standards. To be eligible for disbursement against this DLI, bridges will need to have contracts signed before April 26, 2018. 

DLI‐6: Improved fiduciary governance of design‐build contracting (US$2.0 million) 

5. At  present,  Nepal’s  national  legal  and  regulatory  framework  for  design‐build  contracting  remains under  development.  The  Public  Procurement  Act  (2007,  last  amended  2017)  envisages  design‐build 

Page 29: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

20 

contracting but Public Procurement Regulations are silent on this contracting modality. There are also no standard bid documents  for design‐build works. The Program has used the design‐build modality during BIMP I and intends to also do so under BIMP II. There is a need to develop the regulations and standard documents  including  environmental  and  social  aspects  required  to  ensure  the  effectiveness  of  this approach. This DLI will be eligible  for disbursement once  the DOR has drafted  regulations and standard documents for the Program and subsequently submitted them to Nepal’s Public Procurement Management Office for consideration as inputs to potential national regulations and standard documents. 

DLI‐7/BSMS (mobile monitoring system) use on Program worksites (US$3.75 million) 

6. The Program concerns many works contracts in dispersed geographical areas. Many sites are difficult to access form Kathmandu and the Bridge Branch often uses locally based supervision teams to monitor the execution  of  civil  works.  This  entails  inherent  challenges  for  overall  Program management  and  quality monitoring. The Bridge Branch has accordingly developed a BSMS that can be used on tablet devices and smartphones to capture photos, videos, and written entries form site supervisors. The BSMS is functional and the DOR is working to drive its use among all implementing units. This DLI will accordingly measure the use  of  the  BSMS  on  Program  sites.  One  or  more  substantive,  complete,  and  accurate  entries  per  site including environmental and social aspects within a single month will count as one unit of DLI achievement. Entries with timestamps falling within 12 hours of one another will be considered a single entry. Verification activities will sample entries to check for incomplete, redundant, or erroneous entries. The aim of this DLI is  to  ensure  that  site  supervision  is  occurring  regularly  and  is well  documented with  an  overall  aim  of enhancing the quality of built works. 

Bridge design, site assessment, feasibility study, quality monitoring, and environmental and social impact management 

7. The expenditure program for investments under the hybrid operation’s PforR component will include US$8.4 million for bridge design, site assessment, feasibility study, quality monitoring, and environmental and social impact management. This amount is equivalent to approximately 5 percent of the estimated civil works spending required to meet DLIs. This amount is shown here as a separate item at the request of the Bridge Branch for planning and budgeting for Program activities. 

8. Table  1.1  summarizes  the  activities  and  expenditure  program under  the  PforR  component  of  the operation.  

Page 30: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

21 

Table 1.1. Program Activities and Expenditures under PforR Component9 

SRN Bridge Program Activity 

Unit  Bklog  Year 1  Year 2  Year 3  Year 4  Year 5  Total 

                 

DLI‐1: Major bridge maintenance 

Program spend [US$, million]    1.5  3.4  4.8  5.3  2.4  17.5  

Number of bridges taken up    15  20  30  25  —  90  Number of bridges in progress in year    15  35  50  55  25  —  Number of bridges completed in year    —  15  20  30  25  90 

   Number of meters completed    —  750  1,000  1,500  1,250  4,500 

DLI‐2: Road safety upgrades on bridges 

Program spend [US$, millions]    1.9  4.8  6.1  6.8  3.6  23.3  

Number of bridges taken up    30  45  50  55  —  180  Number of bridges in progress in year    30  75  95  105  55  —  Number of bridges completed in year    —  30  45  50  55  180 

   Number of meters completed    —  1,333  2,000  2,222  2,444  8,000 

DLI‐3: New 2 lane bridge construction, rehab., and replacement of bridges 

Amount [US$, millions]    3.4  11.3  18.1  14.7  6.8  54.3 

 Number of bridges taken up    15  35  30  —  —  80  

Number of bridges in progress in year    15  50  80  65  30  —  Number of bridges completed in year    —  —  15  35  30  80 

   Number of meters completed    —  —  750  1,750  1,500  4,000 

DLI‐4: New 4 lane bridge construction 

Amount [US$, million]    1.5  8.1  12.9  11.4  4.8  38.8  

Number of bridges taken up    4  18  13  —  —  35  Number of bridges in progress in year    4  22  35  31  13   

 Number of bridges completed in year    —  —  4  18  13  35 

   Number of meters completed    —  ‐  229  1,029  743  2,000 

DLI‐5: Completion of backlog bridges under construction 

Amount [US$, million]    17.1  11.3  5.6  —  —  33.9 

 Number of bridges in appraisal 

backlog 92  92  61  30  ‐  —   

 Number of bridges completed in year    31  31  30  —  —  92  

Number of meters completed    1,685  1,685  1,630  —  —  5,000 

 PforR civil works spend  25.32  38.99  47.57  38.27  17.57  167.72 

PforR bridge design, site assessment, feasibility study, quality monitoring, Program logistics support, and environmental and social 

impact management 

1.27  1.95  2.38  1.91  0.88  8.39 

Estimated PforR Program spending/year (US$, millions)  26.59  40.94  49.95  40.18  18.44  176.10 

9 Note: Figures above pertain to capital spending only and do not include US$5.75 million for PforR institutional results, including (a) DLI-6: Improved fiduciary governance of design-build contracting (US$ 2.0 million) and (b) DLI-7: BSMS monthly monitoring on Program worksites (US$ 3.75 million). The total size of the PforR Program, which includes disbursements for institutional results, is US$181.85 million with US$118.84 million from IDA.

Page 31: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

22 

 

IPF Component: Consultancy support and institutional development (US$14.2 million): 

9. The operation’s IPF component will finance the following activities with indicative financing amounts described in table 1.2: 

IPF‐1: Preparations  for  future projects on  the Strategic Roads Network. There are several potential major projects that the GON may seek to develop on the SRN. However, consensus on which may benefit from international support has not crystalized. Financing under the IPF component will support initial stages of project preparation as high priority projects are agreed for further development. This subcomponent will finance baseline assessments, engineering studies,  site  assessments,  feasibility  studies,  and  technical  designs  and  other  project preparation tasks to prepare for future physical investments. 

IPF‐2:  Technical  audits  carried  out  by  NVC.  BIMP  I  included  similar  technical  auditing arrangements.  These  proved  particularly  useful  in  providing  a  feedback  mechanism  for identifying  quality  gaps  and  potential  future  improvements  to  address  them.  This subcomponent will finance the costs of technical auditors under the NVC who will assess and report  on  the  extent  to  which  works  under  the  PforR  Program  comply  with  design specifications and the Government’s procedures relating to the execution of works. Technical auditing is a key part of the effort to enhance the quality of civil works in Nepal. 

IPF‐3: Advanced bridge designs  for enhanced resilience and  inclusion. Similarly,  there  is a need to enhance the inclusion that the DOR’s bridge designs offer for pedestrians and cyclists. Deploying technologies that are new/less used in Nepal can help the DOR with both efforts. IPF  support  will  accordingly  help  the  DOR  develop  advanced  bridge  designs  initiatives (including  the  design  standards  and  guidelines,  as  well  as  actual  engineering  designs)  as required to take forward future investments that deploy those designs. 

IPF‐4: Training (domestic and international) and capacity development. There is a need for skills enhancement and for providing relevant training to the DOR staff and other transport sector  stakeholders  to  ensure  that  the  DOR’s  road  and  bridge  network  provides  the connectivity  needed  for  Nepal’s  development.  Technical,  social,  environmental,  fiduciary, federalism‐related capacity development will be eligible for support under the IPF component. In addition, this subcomponent will support the DOR to undertake annual staff surveys and to compile results as a starting point for broader organizational development objectives. 

IPF‐5: Supervision oversight consultancies. The Bridge Branch relies extensively on support from Divisional Offices and Bridge Sector offices for field supervision. Under BIMP I, there were instances where this supervision was inconsistent which has been identified as contributing to gaps in construction quality and safe working practices. This subcomponent will accordingly finance  one  or more  supervision  and  oversight  consultancies  that  will  support  the  Bridge Branch  to verify  field  supervision, enhance use of  the BSMS, and augment  the  intensity of supervision where needed to mitigate key risks to intended development outcomes. 

IPF‐6: Mobilization, equipage, and development of Design and Advanced Technology Cell. The DOR does not currently have an organizational approach to  identifying, absorbing, and deploying new or advanced technologies. There is also no program for the development of 

Page 32: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

23 

junior engineers. This results in missed opportunities—both in terms of civil works and staff capabilities. The IPF component will help mobilize a DATC that will lead the development of advanced bridge designs for enhanced resilience and inclusion. Specifically, this will  include equipment, software, facilities, training, support from external experts, and logistics support to  enable  the  DATC  to  function  at  a  high  level  of  technical  capability.  Cohorts  of  junior engineers  selected  for  the DATC will  include at  least 33 percent  female participation  in an effort to enhance the role that female engineers play in DOR programs. This subcomponent will also support the implementation of promotion efforts to ensure a high participation rate of young engineers and specifically female engineers in the DATC program. 

IPF‐7: Support for  improving OCHS and DOR implementing Nepal’s new Labor Act (2017). The implementation of BIMP I evidenced that OCHS standards and worksite practices in Nepal need  to develop  further. While  the DOR has made considerable  recent progress,  there are further opportunities to strengthen DOR systems that apply to OCHS and ensuring compliance with the provisions of Nepal’s new Labor Act (2017). This subcomponent will enable the DOR’s Bridge Branch to engage external support in these critical areas from one or more international organizations specialized  in  labor risk management. Support will be used to  implement the measures identified in Program Action Plan. 

IPF‐8:  Contingency  funding  for  verification  past  year  3.  During  the Program’s  initial  three years, SDC will provide support to the NPC for discharging its verification mandate under the program. However, the continuation of this support past year 3 is not guaranteed as of June 2018.  IPF‐8  will  accordingly  include  contingency  funding  to  ensure  that  the  NPC  (or  its successor following federal restructuring) can engage one or more private firms to undertake verification of DLIs as technical advisers. 

IPF‐9:  Program  impact  evaluation  data  collection.  This  subcomponent  will  pay  for  data collection for an impact evaluation that is currently under design with support from the World Bank Group’s Development Impact Evaluation team’s i.e. Connect program. The purpose of this  impact  evaluation  is  to  inform  the  Program’s  future  prioritization  strategy,  future investment initiatives, and strategy for donor involvement. Gender‐related considerations will form part of the impact evaluation’s scope with a view toward the complementary initiatives that  could  accompany  bridge  development  and  target  benefits  at  specific  groups  such  as lower‐income women. 

Page 33: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

24 

Table 1.2. IPF Component: Consultancy Support and Institutional Development 

Subcomponent  Description  Qty  Unit  Unit Cost  Amount 

IPF‐1  Preparations for future projects on the Strategic Roads Network 

1  Lump sum  5,000,000  5,000,000 

IPF‐2  Technical auditing by NVC  5  Years  100,000  500,000 

IPF‐3  Advanced bridge designs for enhanced resilience and inclusion 

10  Bridges  300,000  3,000,000 

IPF‐4  Training (domestic and international) and capacity development 

5  Annual  120,000  600,000 

IPF‐5  Supervision oversight consultancies  5  Annual  500,000  2,500,000 

IPF‐6  Mobilization, equipage, and development of Design and Advanced Technology Cell 

5  Annual  200,000  1,000,000 

IPF‐7  Support for OCHS and DOR implementation of Nepal’s Labor Act (2017) 

5  Years  200,000  1,000,000 

IPF‐8  Contingency funding for verification past year 3  2  Years  150,000  300,000 

IPF‐9  Program impact evaluation data collection  1  Lump sum  250,000  250,000 

 IPF Subtotal  14,150,000  

10. The decision to finance the above tasks under an IPF component reflects learnings from BIMP I and a view  that  several  activities  are  outside  the  Program’s  historic  practice.  Under  BIMP  I,  these  types  of initiatives were supported using parallel financing from the IDA‐supported RSDP’s TA component. The RSDP is expected to close in July 2019 and there is a need to ensure that IPF resources are aligned with the full duration of the PforR Program.   

Page 34: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

25 

ANNEX 2. RESULTS FRAMEWORK AND MONITORING 

Table 2.1. Results Framework 

Results Areas 

PDO Indicators  Intermediate Results Indicators  DLI #  Unit of Measurement Baseline (Year) 

End Target (Year) 

Safe bridges 

PDO 1: Reduced likelihood of road departure crashes on Program bridges 

      Number of upgraded bridges with visual signs or recorded incidents of prevented road departure crashes 

0 (year 1)  18 (year 5) 

   IRI 1.1: Road safety upgrades on Program bridges  DLI‐2  Meter  0 (year 1)  8,000 (year 5) 

Resilient bridges 

PDO 2: Enhanced DOR capabilities for developing resilient bridge designs 

      Number of advanced bridge designs prepared 

0 (year 1)  10 (year 5) 

   IRI 2.1: Design and Advanced Technology Cell created 

   One time  n.a.  DATC staffed/mobilized 

(year 2) 

  IRI 2.2: Mobilization of advanced design skills for improved resilience and inclusion 

  Number  0 (year 1)  10 (year 5) 

(Gender Indicator)  IRI 2.3: Female Engineers recruited in the Design and Advanced Technology Cell and given advanced skills training  

  %  6% (DOR average) (year 0) 

>33% (all years) 

Cost‐effective bridges 

PDO 3: Estimated road user cost savings achieved by Program interventions 

      NPR  0 (year 1)  > NPR 2,971 million 

   IRI 3.1: Implementation of high priority maintenance to extend asset lives 

DLI‐1  Meter  0 (year. 1) 

4,500 (year 5) 

   IRI 3.2: Completion of backlog bridges to reduce road user costs 

DLI‐5  Meter  0 (year 1)  5,000 (year 5) 

   IRI 3.3: Construction of new bridges to reduce road user costs 

DLI‐3 DLI‐4 

Meter  0 (year 1)  6,000 (year 5) 

Beneficiary feedback 

(Beneficiary Feedback)  IRI 4.1: Responsiveness of DOR’s Grievance Redress Mechanism  

  Calendar days (weighted average)  31.2 (year 0) 

10 (year 5) 

  (Beneficiary)  IRI 4.2: Anticipated beneficiaries of inclusive design concepts 

  Number of people  0 (year 1)  5,000 (year 5) 

Page 35: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

26 

Table 2.2. Indicator Description 

Indicator Name (#) Description (Clear 

definition and so on) Frequency  Data Source 

Methodology for Data Collection 

Responsibility for Data Collection 

DLIs 

Responsibility for Data 

Verification 

Scalability of Disbursement 

(Yes/No) 

PDO 1: Reduced likelihood of road departure crashes on Program bridges 

Number of Program bridges with road safety upgrades that show visual signs or have recorded incidents of prevented road departure crashes 

(i) Midterm review; and (ii) within 4 months of closing date 

Visual inspection and photos captured in BMS; or accident reports from Nepal Police; or community interviews 

Review of BMS entries, Nepal police reports, and/or community interviews 

Bridge Branch  n.a.  n.a. 

IRI 1.1: Road safety upgrades on Program bridges 

Meters of Program bridges with upgraded road safety features 

Annual updates 

Third Trimester Report of each fiscal year 

Trimester reporting 

Bridge Branch  NPC  Yes 

PDO 2: Enhanced DOR capabilities for developing resilient bridge designs 

Number of new bridge designs prepared that include advanced design features for enhanced resilience and inclusion. 

Annual updates 

Third Trimester Report of each fiscal year 

Trimester reporting 

Bridge Branch  n.a.  n.a. 

IRI 2.1: Design and Advanced Technology Cell created 

DOR to establish a DATC within the Bridge Branch, satisfactory to the Association, for insourcing a fraction of bridge‐related engineering tasks and developing the capacity of junior engineers. 

One time  MoPIT  Task Team verification of DATC's staffing and functionality 

Task Team  n.a.  n.a. 

Page 36: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

27 

Indicator Name (#) Description (Clear 

definition and so on) Frequency  Data Source 

Methodology for Data Collection 

Responsibility for Data Collection 

DLIs 

Responsibility for Data 

Verification 

Scalability of Disbursement 

(Yes/No) 

IRI 2.2: Mobilization of advanced design skills for improved resilience and inclusion 

Number of advanced bridge designs completed that incorporate enhanced resilience features 

Annual   Third Trimester Report of each fiscal year 

Trimester reporting 

Bridge Branch  Yes  Third Trimester Report of each fiscal year 

(Gender Indicator) IRI 2.3: Female Engineers recruited in the Design and Advanced Technology Cell and given advanced skills training 

Percentage of females employed in the engineering cohorts recruited in DATC and trained (target not less than 33%) 

Annual  Third Trimester Report of each fiscal year 

DOR staff records 

Bridge Branch  n.a.  n.a. 

PDO 3: Estimated road user cost savings achieved by Program interventions 

Modeled savings resulting from PforR Program investments 

(i) Midterm review; and (ii) within 4 months of closing date 

HDM‐4 HMIS data for demand by SRN road 

HDM‐4 model  Task Team  n.a.  n.a. 

IRI 3.1: Implementation of high priority maintenance to extend asset lives 

Meters of completed major bridge maintenance on Program bridges 

Annual updates 

Third Trimester Report of each fiscal year 

Trimester reporting 

Bridge Branch  NPC  Yes 

IRI 3.2: Completion of backlog bridges to reduce road user costs 

Meters of completed backlog bridges under the Program 

Annual updates 

Third Trimester Report of each fiscal year 

Trimester reporting 

Bridge Branch  NPC  Yes 

IRI 3.3: Construction of new bridges to reduce road user costs 

Meters of new 2 lane and 4 lane bridges completed under the Program 

Annual updates 

Third Trimester Report of each fiscal year 

Trimester reporting 

Bridge Branch  NPC  Yes 

(Beneficiary Feedback) IRI 4.1: Responsiveness of DOR’s Grievance Redress Mechanism 

Average response time to GRM entries received by DOR 

Annual updates 

GRM quarterly reports 

DOR GRM system (through DOR website) 

Bridge Branch  n.a.  n.a. 

Page 37: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

28 

Indicator Name (#) Description (Clear 

definition and so on) Frequency  Data Source 

Methodology for Data Collection 

Responsibility for Data Collection 

DLIs 

Responsibility for Data 

Verification 

Scalability of Disbursement 

(Yes/No) 

(Beneficiary) IRI 4.2: Anticipated beneficiaries of inclusive design concepts  

Number of beneficiaries expected to benefit from inclusive design concepts developed under IPF‐3 (advanced design bridges). Figure to be disaggregated by gender. 

One time per bridge site 

Safeguards assessment of advanced design bridges 

Safeguards documents 

Bridge Branch  n.a.  n.a. 

Page 38: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

29 

ANNEX 3. DLIS, DISBURSEMENT ARRANGEMENTS AND VERIFICATION PROTOCOLS 

Table 3.1. Disbursement Linked Indicator Matrix 

 Total 

Financing Allocated 

% of PforR 

Financing DLI Baseline 

Indicative Timeline for DLI Achievement and disbursement 

Year 1  Year 2  Year 3  Year 4  Year 5 

DLI‐1: Major bridge maintenance  [target of 4,500 m] 

   0  —  750  1,000  1,500  1,250 

Allocated amount (US$):  13,087,728  11  

—  2,181,288  2,908,384  4,362,576  3,635,480 

DLI‐2: Road safety upgrades on bridges  [target of 8,000 m] 

   0  —  1,333  2,000  2,222  2,444 

Allocated amount (US$):  17,450,304  15  

—  2,908,384  4,362,576  4,847,307  5,332,037 

DLI‐3: New 2 lane bridge construction, rehab., and replacement of bridges  [target of 4,000 m] 

     —  —  750  1,750  1,500 

Allocated amount (US$):  35,288,393  30  0  —  —  6,616,574  15,438,672  13,233,147 

DLI‐4: New 4 lane bridge construction  [target of 2,000 m] 

     —  —  229  1,029  743 

Allocated amount (US$):  25,205,995  21  0  —  —  2,880,685  12,963,083  9,362,227 

DLI‐5: Completion of backlog bridges under construction [target of 5,000 m] 

   0  1,685  1,685  1,630  —  — 

Allocated amount (US$):  22,055,246  19  

7,431,659  7,431,659  7,191,928  —  — 

DLI‐6: Improved fiduciary governance of design‐build contracting  [target to develop regulations and standard documents] 

   No 

guidelines or standard documents 

—  Standard documents 

and guidelines submitted to PPMO 

—  —  — 

Allocated amount (US$):  2,000,000  2    

2,000,000  —  —  — 

DLI‐7: BSMS (mobile monitoring system) use on Program worksites [target of 5,000 qualifying sites] 

   0  730  1,138  1,358  1,199  576 

Allocated amount (US$):  3,750,000  3  

547,500  853,500  1,018,500  899,250  432,000 

Total Financing Allocated (US$):  118,837,666    

7,979,159  15,374,831  24,978,647  38,510,888  31,994,892 

Cumulative disbursement against DLIs      

7,979,159  23,353,990  48,332,637  86,843,525  118,838,416 

Page 39: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

30 

Table 3.2. DLI Verification Protocol 

The Bridge Branch will develop dossiers for completed physical works that will be proposed for verification. Dossiers will contain (a) documentation of technical specifications and engineering designs, (b) social and environmental assessments and information on preparation/implementation of management plans, and (c) procurement documentation. For the purpose of verifying the fulfillment of the DLIs the National Planning Commission is responsible for appointing and maintaining, at all times during the implementation of the Program, independent verification agents (under terms of  reference  satisfactory  to  the  Association).  Verification  reports  submitted  to  the  Association  should  be mutually  satisfactory  in  form  and substance to the Government of Nepal and the Association. The Bridge Branch will forward dossiers in batches to the NPC.  SDC will be funding and  engaging  independent  technical  advisers  to  work  with  the  NPC  during  implementation  on  verification  tasks.  During  verification, documentation in dossiers will first be reviewed to ascertain compliance with Program requirements. Field verification will subsequently follow on a sample basis according to the proportions listed below. 

#  DLI Definition/Description of 

Achievement 

Scalability of Disbursements 

(Yes/No) 

Protocol to Evaluate Achievement of the DLI and Data/Result Verification 

Data Source/Agency Verification 

Entity Procedure 

DLI‐1  Major bridge maintenance 

Completion of one or more major maintenance works as defined in table 3.4 and physical verification of state of good repair (that is, BMS condition 7, 8, 9, or 10) for all elements listed in table 3.4 according to Bridge Branch inspection guidelines. All bridges requested for verification must originate from BMS priority list. 

Yes—to nearest one‐tenth meter of a single completed bridge. 

Bridge Dossiers assembled by Bridge Branch; and visual inspection on sample basis for verification 

NPC  All Bridge Dossiers to undergo review for completeness/compliance before verification.  

NPC to select random sample (not less than 50%) of completed bridges (by number) for physical verification.  Sample results will apply to entire DLI‐1 category works within the same disbursement request. 

100% physical verification of bridges where deviation from maintenance checklist has been agreed with the Association.  

For the avoidance of doubt, bridges eligible for DLI‐1 may also be included in DLI‐2. 

Page 40: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

31 

#  DLI Definition/Description of 

Achievement 

Scalability of Disbursements 

(Yes/No) 

Protocol to Evaluate Achievement of the DLI and Data/Result Verification 

Data Source/Agency Verification 

Entity Procedure 

DLI‐2  Road safety upgrades on bridges 

Completion of one or more road safety investments listed in table 3.5 at each bridge site and verification that all bridge‐related road safety elements in table 3.5 are in place unless site conditions render partial solutions as the only practicable option.  

Yes—to nearest one‐tenth meter of a single completed bridge. 

Bridge Dossiers assembled by Bridge Branch; and visual inspection on sample basis for verification 

NPC  All Bridge Dossiers to undergo review for completeness/compliance before verification.  

NPC to select random sample (not less than 50%) of completed bridges (by number) for physical verification.  Sample results will apply to entire DLI‐2 category works within the same disbursement request. 

100% physical verification of bridges where deviation from full road safety checklist has been agreed with the Association.  

New 2 and 4 lane bridges under DLI‐3 and DLI‐4 will not be eligible for disbursement against this DLI. 

DLI‐3  New 2 lane bridge construction, rehab., and replacement of bridges 

Completion of physical works for dual carriage way bridge meeting or exceeding GON Bridge Design Standards and road safety requirements as described in table 3.5. All bridges requested for verification must originate from BMS priority list and have contract signing dates after April 26, 2018. All new 2 lane bridges proposed for disbursement must come through BMS prioritized list. 

Yes—to nearest one‐tenth meter of a single completed bridge. 

Bridge Dossiers assembled by Bridge Branch; and visual inspection for verification 

NPC  All Bridge Dossiers to undergo review for completeness/compliance before verification.  

Physical verification to be applied to 100% of works covered by disbursement request. 

BMS list of priority bridges for each year to be posted on DOR website. 

For the avoidance of doubt, bridges eligible for DLI‐3 cannot count toward DLI‐2. 

Page 41: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

32 

#  DLI Definition/Description of 

Achievement 

Scalability of Disbursements 

(Yes/No) 

Protocol to Evaluate Achievement of the DLI and Data/Result Verification 

Data Source/Agency Verification 

Entity Procedure 

DLI‐4  New 4 lane bridge construction 

Completion of physical works for 4lane bridge meeting or exceeding GON Bridge Design Standards and road safety requirements as described in table 3.5. All bridges requested for verification must originate from BMS priority list and have contract signing dates after April 26, 2018. All 4 lane bridges proposed for disbursement must have estimated Average Annual Daily Traffic greater than 3,000 Passenger Car Unit (equivalent) according to the DOR's HMIS at the time of verification. 

Yes—to nearest one‐tenth meter of a single completed bridge. 

Bridge Dossiers assembled by Bridge Branch; and visual inspection for verification 

NPC  All Bridge Dossiers to undergo review for completeness/compliance before verification.  

Physical verification to be applied to 100% of works covered by disbursement request. 

Traffic data from DOR’s HMIS to provide the basis for verification of traffic volume. 

For the avoidance of doubt, bridges eligible for DLI‐4 cannot count toward DLI‐2. 

DLI‐5  Completion of backlog bridges under construction 

Completion of physical works for bridges with construction contracts signed before April 26, 2018. Completed bridges must meet or exceed GON Bridge Design Standards.  

Yes—to nearest one‐tenth meter of a single completed bridge. 

Bridge Dossiers assembled by Bridge Branch; and physical inspection on sample basis for verification 

NPC  All Bridge Dossiers to undergo review for completeness/compliance before verification.  

NPC to select random sample not less than 30% of competed bridges (by number) for physical verification.  

Sample results will apply to entire DLI‐5 category works within the same disbursement request. 

For the avoidance of doubt, bridges eligible for DLI‐5 may also be included in DLI‐2. 

DLI‐6  Improved fiduciary governance of design‐build contracting 

Drafting and endorsement by the MoPIT of the revised guidelines for design‐build contracts to be submitted to the PPMO for approval 

No  Official letter from MoPIT Secretary to PPMO 

NPC  Pass/fail criteria to apply based on completion of DLI target using desk‐based verification of outputs. 

Page 42: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

33 

#  DLI Definition/Description of 

Achievement 

Scalability of Disbursements 

(Yes/No) 

Protocol to Evaluate Achievement of the DLI and Data/Result Verification 

Data Source/Agency Verification 

Entity Procedure 

DLI‐7  BSMS (mobile monitoring system) use on Program worksites 

At least two complete and substantive BSMS entries for a single worksite per calendar month will constitute one unit of DLI achievement. Entries must date from the period between contract signing and beginning of defects and liability period for works and must include environmental and social aspects of works. Entries must be substantive, complete, and accurate. Entries with timestamps falling within 12 hours of one another will be considered a single entry. 

Yes  BSMS data export with sample audit of data entries for a selection of sites. 

NPC  Spreadsheet analysis of BSMS entries to provide basis for calculating DLI achievement based on time stamps and geo‐referenced location. 

Verification target of 10% on entries included in DLI calculation to check for completeness and to detect potentially fraudulent entries. 

Sample results will apply to entire DLI‐7 category results within the same disbursement request. 

Page 43: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

34 

Table 3.3. Disbursement Table 

#  DLI 

IDA financing 

allocated to the DLI (US$) 

Disbursement calculation formula 

Maximum number of meters on which 

disbursement can be based 

Of which Financing available for Prior results 

Deadline for DLI 

Achievement 

Minimum number of bridges required for 

disbursement to occur 

DLI‐1  Major bridge maintenance (approximately 90 bridges) 

13,087,728  US$2,908 per meter of completed bridges maintained 

4,500  0  Date of close  10 completed bridges per GON fiscal year across all DLI categories combined DLI‐2  Road safety upgrades on bridges 

(approximately 180 bridges) 17,450,304  US$2,181 per meter of completed 

bridges that have been upgraded 8,000  0  Date of close 

DLI‐3  New 2 lane bridge construction, rehab., and replacement of bridges (approximately 80 bridges) 

35,288,393  US$8,822 per meter of completed bridges that are constructed, rehabilitated, or replaced 

4,000  0  Date of close 

DLI‐4  New 4 lane bridge construction (approximately 35 bridges) 

25,205,995  US$12,603 per meter of completed bridge constructed, rehabilitated, or replaced 

2,000  0  Date of close 

DLI‐5  Completion of backlog bridges under construction (approximately 92 bridges) 

18,746,959  US$4,411 per meter of completed bridge 

5,000  2,812,044  Date of close 

DLI‐6  Improved fiduciary governance of design‐build contracting 

2,000,000  Disbursement = US$2,000,000 upon verified completion 

1  0  Date of close  n.a. 

DLI‐7  BSMS (mobile monitoring system ) use on Program worksites (5,000 validated bridge worksites) 

3,750,000  Disbursement = number of verified sites × US$750 

5,000  0  Date of close  n.a. 

Page 44: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

35 

Table 3.4. Elements for Major Maintenance of Program Bridges under DLI‐1 

Bridge Element  Example of Repair Intervention 

Bridge deck   Resurfacing 

Replacement with modular steel bridge sections 

Girders/other superstructure 

Crack/spalling location repair (for example, chemical grouting, weld repair, others) 

Reinforcement (for example, Carbon Fiber Reinforced Polymer or other means) 

Sand blasting and repainting 

Bearings  Jacking and replacement or refurbishment 

Abutments  Crack repair 

Provision or repair of access for maintenance 

Repair of cheek wall 

Approaches  Resurfacing and/or rehabilitation of road structure 

Drainage improvements to prevent siltation of bridge deck 

Expansion joint  Replacement or rehabilitation 

Piers  Jacketing 

Grouting (foundations) 

Placement of riprap or gabions to protect against scouring 

River training works  Check damns for scour prevention 

Gabion walls to provide guide banks 

Constructions of spurs 

Bridge rail  Repair of collision or other damage 

Note: Any exceptions to full maintenance solutions will be agreed in advance in writing with the Association. 

 

Page 45: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

36 

Table 3.5. Road Safety Checklist for Program Bridges under DLI‐2 

Item  Requirement 

Bridge rail  ‘F’ shape; or 

‘W’ shape; or 

Thrie‐beam; or 

Double or triple steel tube type;  

Transitions  ‘W’ shape terminal connector; or  

Thrie‐beam terminal connector; or 

Cable to ‘W’ beam or ‘F’ shape transitions  

Approach rail  ‘W’ shape; or 

‘F’ safety shapes; or 

Cable safety system; or 

Cement Rubble Masonry  

End treatments  Buried in slope; or 

Breakaway (various types); or 

Anchor block (for cable systems); or 

Energy absorbing; or 

Crash attenuator type solution. 

Pedestrian and bicycle right of way and railing. (note: required for new bridges that is, under DLI‐3 or DLI‐4 on any road without access control) 

Pedestrian parapets provided on both sides of bridge and segregated by bridge rail from traffic; and 

0.5 m minimum, 1+ m preferred for bridges outside of urban areas; or 

2 m minimum, 3+ m preferred for bridges in urban areas; and 

1.1 m or higher steel tube with 6” intermediate rails and rub rail for pedestrian/cyclist fall protection 

Markings  Lane delineation on approaches and bridge deck 

High visibility markings at approach and on barriers 

Warnings and restrictions as appropriate to location and loading control (if applicable) 

Note: Any exceptions to full solutions will be agreed in advance in writing with the Association. 

11. The Program will  support  the development of  guidelines  for  the  implementation of  road  safety works  consistently.  These  guidelines  should  feature  standard  designs  that  have  been  developed  and approved for use by the following international authorities (or any standard design that has undergone the Association’s review and received ‘no objection’): 

Federal Highways Administration (United States) and various U.S. state transportation agencies: 

o https://safety.fhwa.dot.gov/roadway_dept/countermeasures/reduce_crash_severity/listing.cfm?code=long 

o http://onlinemanuals.txdot.gov/txdotmanuals/rlg/rlg.pdf 

o http://www.oregon.gov/ODOT/Engineering/Pages/Drawings‐Bridge.aspx 

Page 46: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

37 

New South Wales: http://www.rms.nsw.gov.au/business‐industry/partners‐suppliers/document‐types/standard‐drawings/road/safety‐barriers.html 

New Zealand Transport Agency: http://www.nzta.govt.nz/roads‐and‐rail/road‐engineering/road‐safety‐hardware/standard‐drawings/ 

Alberta Transportation: http://www.transportation.alberta.ca/Content/docType30/Production/BridgeBarriersDrawings.pdf 

12. The  Bridge  Branch may  select  and  deploy  alternative  designs  or  solutions  for  Program  bridges provided that those alternatives have been tested and approved to the level required for a particular site application according to the American Association of State Highway and Transportation Officials Manual for Assessing Safety Hardware or equivalent standards. 

13. For the avoidance of doubt, it will be permissible for bridges to qualify for disbursement against DLI‐1 (major maintenance) and DLI‐2 (road safety upgrades) in instances where works contracts may include bundled maintenance and road safety interventions. In such instances, verification criteria for each DLI category will remain unchanged.  

Page 47: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

38 

ANNEX 4. SUMMARY TECHNICAL ASSESSMENT 

Summary 

1. The Program remains one of Nepal’s largest and most strategically relevant development initiatives due the critical role that the SRN and its bridges play in supporting economic activity. The DOR’s Bridge Branch  has  overall  responsibility  for  the  Program’s  implementation  and  has  demonstrated  ability  to achieve  results  under  BIMP  I.  Despite  positive  past  accomplishments,  there  is  room  to  improve  the Program’s technical performance further. Most notably, the as‐built quality of physical works remains a foremost challenge. Findings  from the present Association’s  technical assessment have  identified  that quality deficiencies are endemic throughout the process of bridge development and construction. One reason for this is inconsistent field‐level supervision of works. Under BIMP I, the Bridge Branch accordingly developed a new mobile monitoring application, BSMS,  that uses a  tablet or  smartphone  interface  to enable rapid reporting/sharing of site conditions and quality‐related  issues. The BSMS has been made operational in time for BIMP II and offers the means for Bridge Branch leadership to track the frequency of field visits and quality of observations made by assigned works supervisors. 

2. The experience of BIMP I has been positive overall. Particularly encouraging experiences relate to (a)  continuous  verification  of  actual  results  under  the  NPC  that  has  helped  manage  the  Program’s performance,  (b)  links between DLIs  and  continuous use of  the BMS which has helped  improve asset management and prioritize investments; and (c) convening of different DOR units and GON authorities by virtue of  relying on  government  systems  that has  helped quickly  address unforeseen  implementation challenges. Below are key technical learnings from BIMP I along with options for improvement under BIMP II. 

Expenditure Framework 

3. The  Program’s  expenditure  framework  entails  two  budget  headings  for  Program  expenditures (currently 337320 and 337159 in Nepal’s budget document) that are separate from the larger program of DOR bridge initiatives. One heading supports capital investment. The other supports bridge design, site assessment, feasibility study, quality monitoring, Program logistics support, and environmental and social impact management.  

4. The  Program’s  current  expenditure  framework  was  established  under  a  legal  covenant  in  the Financing Agreement for BIMP I which was upheld and found to be effective at enhancing transparency around the Program’s expenditures. The Financing Agreement for BIMP II reflects a similar legal covenant requiring  the MoF  to maintain  separate  budget  headings.  For  the  avoidance of  doubt,  the  Program’s budget  headings will  also  be  separate  and  distinct  from  the budget  heading  used  for  IPF  component expenditures. Annex 1 details Program expenditures. 

Technical Engineering Design and Quality Management of Bridges  

5. Under BIMP I, the Bridge Branch demonstrated a remarkable leap in capacity to design maintenance interventions and implement them effectively. This included the use of Carbon Fiber Reinforced Polymer repairs to strengthen degraded structural members as well as pressurized grouting to address foundation failures and epoxy‐based injection grouting to address cracking. These advanced techniques had never before  been  used  by  the  Program  and  they  succeeded  in  addressing  urgent maintenance  needs  at  a fraction of  likely bridge  replacement  costs. However,  there were also observed gaps  in  the quality of design for new bridge construction and in the quality of both new construction and maintenance works. 

Page 48: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

39 

These  gaps  appear  to  stem  from  multiple  root  causes  including  design  practice,  weak consultant/contractor  capacity,  inconsistent  site  supervision,  oversights  in  site  assessments,  and  the processes that develop designs for tendering. Moreover, digitalization of the Bridge Branch’s documents, specifically technical designs, has become critical to inform future maintenance programs. At present a key challenge of diagnosing maintenance needs is trying to figure out how an existing bridge was actually built. 

New Bridge Construction and Contractor Capacity 

6. Based on standard designs for prestress concrete bridges (25 m, 35 m, and 45 m span), the DOR effectively introduced long‐span concrete bridges in new construction works. It also introduced design and build contract options (around 50). In that regard, the capacity of the local construction industry has increased in response to the Bridge Branch’s leadership but remains a work in progress. Major delays are common during  contract  execution.  The Bridge Branch  faces many  challenges  in managing  contracts, including issues of contract management, quality enforcement, delays in the process of budget release, and OCHS on worksites. A key challenge faced during the implementation of new construction contracts stem from the fact that contractors happen to bid for different contracts expected to be implemented within the same time frame, without the adequate capacity to deliver on time.  

DOR’s Technical Capacity  

7. The Bridge Branch has a substantial workload. The Bridge Branch has noted difficulties in recruiting young engineers to support the Program on account of notoriously high workload, risks associated with approving  bridge  designs,  and  limited  professional  development  opportunities.  Similarly,  there  are concerns at the level of divisions regarding the Program’s ability to provide effective site‐level support and technical guidance in a constructive manner. The current staffing structure is based on a 20‐year‐old plan for the DOR which is no longer reflective of the Program’s current status. The Association is currently supporting the DOR to undertake a human resources survey and will subsequently support the DOR to develop a DATC to further enhance the Program’s capabilities. This  is being done through an e‐mailed survey instrument that the Association has assisted the DOR to prepare and distribute to its staff. 

8. Civil servants in Nepal are expected to transfer every two years, because staff tend to stay in one sector  for  their  entire  career.  The  two‐year  rule  for  transfers  affects planning  and  implementation of projects, which in turn causes delays. For example, staff from roads are transferred to bridges projects without ensuring the minimum technical skills. Support to newcomers is ad hoc. There is a perception that changes before two years also occur in response to different institutional and political pressures. A key means to coping with turnover will be the digitalization and electronic archiving of administrative and technical documents (designs, bidding and contract documentation, and other documents). This is needed to improve the DOR’s overall efficiency and the ability of new team members to come up to speed on assignments. The BMS is currently being upgraded to also handle document control which can be further developed under BIMP II’s consultancy support and institutional development. 

Internal Coordination 

9. Better coordination is required between the different entities responsible for the implementation and  monitoring  of  road  or  bridges  operations,  namely  the  DOR,  DROs,  and  GESU.  It  is  particularly important  to enhance GESU’s  field presence and  integration within  the process of designing  technical solutions. At present, the timing of GESU’s  inputs are often suboptimal and there  is a need to further mainstream social and environmental inputs in the development process of new works contracts. 

Page 49: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

40 

Economic Analysis 

10. As part of the Program’s technical assessment, the team carried out economic analysis to inform the design of IDA’s support to the Program. This considered the following four categories of bridges:  

Bridges which may fail in the absence of appropriate intervention. The bridges requiring major maintenance are in this category. So too are bridges judged to require safety upgrade work. Here, however, the risk of failure is low. The bridges requiring major maintenance are assumed to be at ‘medium’ risk of failure, that is, within the next 20 years with a probability of failure of 1 percent in any one year. Year by year, this probability will increase by 5 percent a year until at the 20th year probability approaches 100 percent. When a bridge becomes too weak to carry the projected traffic load and fails, two sets of costs may be incurred; the cost of providing a temporary crossing while the bridge is reconstructed (not considered in the present appraisal) and the costs of additional kilometers driven as a detour is found. 

Bridges  considered  for  a  road  safety  upgrade.  Some  of  the  activities  involved  will,  in addition to improving road safety, prolong the life of the bridges through avoided damage and thus benefits from avoiding failure are considered, although the probability of failure is put at no more than 0.65 percent in any one year. Again, this probability will increase by 5 percent  a  year over  a  20‐year period. Appraisal  of  the bridges  has  included  the  costs of accident reduction. At issue is the degree to which improving bridge safety will reduce such costs because data on accident causes do not reveal direct association with bridge condition. The team therefore tested a wide range of scenarios. 

New 2 lane bridge construction. This intervention is used to develop a missing bridge where installation of a new bridge reduces both distance and time costs of road use by shortening access distance and avoiding costs crossing the river by a ford. Time taken to negotiate a ford is longer than for even a single lane bridge and this has been considered.  

Development  of  4  lane  bridges.  This  intervention  is  used  where  the  capacity  of  2  lane bridges  is  inadequate. Delays  experienced  crossing  a  2  lane bridge are  largely  geometric delays—rising  from  the  need  to  reduce  speed when  crossing  the  bridge. Only with  very heavy traffic flows will congestion delay (the need to slow or stop because of an oncoming vehicle overtaking) become significant. To estimate such delays, an Erlang queuing model has been used. 

11. Potential interventions were appraised based on a sample of SNR bridges over a period to 2038. Both the rate of discount and the opportunity cost of capital were taken to be 12 percent. Where road user  costs  are  saved  by  an  investment,  these  have  been  calculated  using World  Bank  RED  software configured for HDM‐4 relationships. Traffic volumes used in different scenarios for the economic appraisal came from the DOR’s HMIS. The range of appraisal findings varies by intervention type and traffic volume. These are presented in the tables below. Key overall findings and implications include the following: 

Maintenance. Major maintenance works are economically justifiable in nearly every traffic scenario except for bridges with less than 100 Passenger Car Unit equivalent per day in traffic volume. Results of the sample and the Association’s experience of traffic growth during a bridge’s initial years of service suggest that a maintenance intervention on bridges of this category would be a rare occurrence on the SRN. Despite low likelihood of occurrence, the 

Page 50: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

41 

verification requirement for major maintenance (namely that Program interventions must come through BMS prioritized lists) mitigates the risk of supporting unviable investments. BMS  prioritizes  interventions  on  higher  traffic  roads  first  such  that  maintenance interventions  on  extremely  low  volume  SRN  roads would  be  unlikely  to  be  selected  for funding. 

New  2  lane  bridge  construction.  New  2  lane  bridge  construction  is  also  economically justifiable in nearly every traffic scenario except for along roads with less than 100 vehicles per day. There is comparatively greater risk of this occurring in the case of new construction when compared to maintenance interventions. SRN roads that lack bridges tend to be lower volume roads by not offering year‐round accessibility. Roads that lack bridges are also often feeder roads that have lower traffic volumes due to their place in Nepal’s road hierarchy. The  verification  criteria  for  new  2  lane  bridge  construction  require  that  all  (that  is,  100 percent) new 2  lane bridges must come through BMS prioritized  lists  (rather than the 80 percent allowed under BIMP I). 

Road  safety  upgrades.  Available  data  and  base  case  analysis  suggest  that  road  safety upgrades  may  be  less  economically  viable  on  roads  with  traffic  volumes  below  3,000 Passenger Car Units equivalent per day. However, the team notes three key issues with this analysis:  

o Available road safety data for Nepal that was used for this analysis are incomplete such that  injuries and fatalities are  likely understated which in turn reduces the modeled value for economic returns. For example, national statistics suggest that in 2013 Nepal experienced 1,744 road safety‐related deaths, whereas the World Health Organization estimated actual deaths were closer to 4,713 due to underreporting. There is also no available  data  on  the  road  departure  crashes  in  Nepal  that  involve  bridge infrastructure. 

o Findings from the IDA‐supported Road Safety Support Project (RSSP) Implementation Completion  and  Results  Report  showed  the  importance  of  developing  road  safety infrastructure  even  on Nepal’s  lower  volume  roads.  Like  RSSP  roads, Nepal’s  lower volume roads often traverse steep ravines by virtue of their geographical location in Nepal’s  road hierarchy.  Road departure  crashes  on  these  roads  can  therefore have severe multi‐fatality consequences due to precipitous drops. RSSP was successful at significantly reducing such incidents and achieved economic rates of return estimated between 23 percent and 50 percent despite traffic volumes below 3,000 Passenger Car Units per day. At the time of the RSSP’s close, a simplified impact evaluation based on observed barrier strikes and consultations showed that the RSSP’s crash barriers had prevented seven road departure crashes for multiple occupancy vehicles (each carrying 15–60 people). If not prevented, these would have likely resulted in multiple fatality incidents. One vehicle experienced a road departure crash on an RSSP road in March 2017 along a section that was not protected by crash barriers, which resulted  in 27 fatalities.  

o In  the absence of  robust data,  scenarios were  tested  for different  rates of  accident occurrence and severity. Findings suggested that economically viable rates of return were possible within credible levels of uncertainty around current data. 

Page 51: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

42 

In  light  of  the  above  there  is  no  traffic  volume‐related  verification  criteria  for  road safety upgrades of BIMP II bridges despite mixed results from the economic analysis. 

4 lane bridges. Results of the economic analysis suggest that 4 lane bridges are economically viable on roads with greater than 3,000 Passenger Car Units equivalent in daily traffic. The verification criteria for DLI 4 reflect this. 

12. Results of base case assumptions for different interventions are shown in table 4.1. 

Table 4.1. Base Case Economic Appraisal Results 

Item  Major Maintenance New 2 Lane Crossing 

Road Safety Upgrades 

4 Lane Bridges 

Traffic levels  100 to 3,000  100 to 3,000  1,000 to 3,000  >3,000 

No. of bridges in sample  91  60  60  15 

Economic internal rate of return range (%) 

38.5 to 141.4  16.5 to 41.4  4.8 to 61.8  22.9 

Emissions Reduction 

13. All four categories of intervention will result in savings of vehicle emissions over the appraisal period considered (20 years). The savings will result from reduction in detours necessary in the event of bridge failure in the case of major maintenance and safety upgrade (the latter intervention incorporates work which  has  the  effect  of  minor  maintenance)  and  in  detours  avoided  by  constructing  new  crossings. Emissions are saved when an intervention allows increased speeds. This is the case with developing 4 lane bridges. The modeling of emissions reduction used HDM‐4 as part of Program appraisal. A summary of emissions savings for the Program is included in table 4.2. Over the 20‐year appraisal period considered, the Program  is  expected  to  save approximately  1.3 million metric  tons of CO2 emissions  relative  to  a without‐Program scenario. 

 Table 4.2. Emissions Reduction by Vehicle Class over the Appraisal Period (metric tons) 

Pollutant/Vehicle  Motorcycle Light 

Vehicles Bus  Light Truck  Heavy Truck  Total 

Hydrocarbons  16,376  1,591  8,046  2,261  6,583  34,857 

Carbon monoxide  80,091  11,480  590  37,730  17,776  147,667 

Nitrous oxide  286  2,594  11,721  7,043  40,182  61,826 

Carbon dioxide  245,121  142,617  292,363  358,809  239,206  1,278,115 

Sulphur dioxide  28  18  78  120  90  334 

Particulates  —  2  23  22  29  76 

Lead  11,685  67,985  —  —  —  79,670 

Total  353,587  226,287  312,820  405,986  303,866  1,602,546 

Actions to Improve the Program’s Performance 

14. Key initiatives that will enhance the Program’s technical performance include the following: 

Increase  focus  on  sound  technical  design,  use  of  new  technologies,  and  the  quality  of engineering  processes  that  ultimately  shape  works  packages.  This must  be  linked  to  an 

Page 52: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

43 

overall  human  resources  strategy  for enhancing  the Program’s human capital.  It  is  a  key justification underpinning  the Program Action Plan  items relating  to  the DATC and cross‐cutting action for annual staff surveys to inform human resources strategies. 

Improve consideration for climate‐resilient designs and technologies as recent events are showing the limitations of traditional standards and approaches. The advanced designs and mobilization of the DATC that will be funded under the IPF component aim at achieving this along with the Program Action Plan item for revising the DOR’s Bridge Policy and Strategy to include resilience consideration.  

Tighten  the  Program’s  regime  of  field  supervision  through  enhanced  accountability  and stronger oversight. The Program makes extensive use of the recently developed BSMS to document field supervision tasks and to subsequently hold supervision engineers to account for the final quality of works based on their actions or inactions. DLI‐7 links disbursement to the use of the BSMS accordingly. 

Encourage thinking for the role of bridges beyond vehicular traffic. There is an opportunity to make bridge infrastructure more inclusive and amenable—particularly to pedestrians and cyclists. The IPF component’s support to advanced design concepts will help achieve this as will the DATC’s mobilization as required by the Program Action Plan. 

Climate Change Vulnerability and Co‐benefits (Resilience) 

15. Nepal’s unique topography, ranging from the high Himalayan range to the plains of the Terai region is,  according  to most  climate  change models,  likely  to  be  dramatically  affected  by  changing weather patterns.  In  terms of volumes,  the monsoon delivers about 80 percent of annual  rainfall  in  just  three months. The high Himalayas have historically played a unique role  in determining  the extent of water storage  as  ice  and  snow  and  provided  flows  of  water  and  sediment  through  perennial  rivers  in  the remaining  months  of  the  year.  These  mountain  ranges  have  also  determined  the  way  the  regional circulation of moisture‐bearing winds leads to temporal and spatial precipitation patterns.  

16. However, global climate change models project that increases in global temperatures along with changes in ocean currents will affect rainfall and cyclone patterns in Nepal. These models have been less reliable in predicting how the regional circulation of moisture‐bearing winds will affect precipitation and temperature in Nepal because the role played by the high mountain ranges on subregional circulation and precipitations  is  still  not  fully  understood.10  IPCC  suggests  that  that Himalayan  regions  like Nepal will experience significant changes in weather patterns due to climate change. 

17. A  recent  World  Bank  study  utilized  the  various  available  climate  change  models  to  identify ‘hotspots’ in the South Asia region that would be affected by changes in weather in terms of rainfall and temperature. A key overall conclusion was that adverse impacts on living standards would be severe by locational characteristics.11 An estimated 29 million people in Nepal are projected to be affected by these localized hotspots. 

10 See “4 Degrees Turn Down the Heat – Climate Extremes, Regional Impacts, and the Case for Resilience”; the World Bank by the Potsdam Institute for Climate Impact Research and Climate Analytics; June 2013. 11 See www.worldbank.org/southasiahotspots. 

Page 53: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

44 

18. Perhaps  of  greater  relevance  is  that  the  combination  of  global  (climate  change)  and  regional (presence of the high mountain ranges) anomalies will create temporal and spatial climate effects that could  involve not  only  the hotspots  but  also  other  geographic  areas  of Nepal  as well.12  For  example, changes in the ice and snow accumulation and more rapid runoffs from the high Himalayas will release significantly larger volumes of water and sediment in future through the river systems, which will disrupt natural ecosystems, infrastructure networks, and human habitats in downstream subregions—all served by the SRN system. A precursor already visible in Nepal is in the form of more frequent flash floods, more damage from monsoon runoffs from fast flowing rivers, particularly in the Terai region.  

19. A recent World Bank publication on flood risks in the Ganges‐Brahmaputra‐Meghna basins provides useful  insights on the scale and complexity of future floods scale‐up because of climate change. These events  will  require  (a)  improving  the  quality  of  vulnerability  assessments  of  SRN  roads  and  bridges, including prioritizing investments in bridges, which need to be designed to withstand 1:100 years or even higher flood events; (b) identifying priority bridges that need built‐in system redundancy because of the multiple functions they perform (in the event of catastrophic events, such as Glacial Lake Outburst Floods [GLOF], cloudbursts, earthquakes) that end up causing catastrophic damage to human settlements and surrounding  road  network  infrastructure;  (c)  tracking  continuously  of  enhancements  in  Bridge Design Standards that are necessary to mitigate vulnerability to unforeseen climate‐induced hazards; (d) using innovative materials and construction methods that build resilience of the bridges to natural disasters; and  (e)  strengthening monitoring  of  post‐incident  response,  in  case  a  bridge  is  damaged  because  of climate‐induced or other natural disasters.13 

Relevance of Operation’s Design to Building Adaptive Resilience 

20. Under  conditions  of  climate  uncertainty,  the  SRN  system  without  bridges  resilient  to  climate‐induced  weather  events  will  severely  disrupt  connectivity—from  social,  physical,  and  economic perspectives. Bridges therefore occupy a strategically important role in Nepal’s quest to eradicate poverty and boost shared prosperity. For example, monsoon flooding during the summer of 2017 demonstrated that many bridges in Nepal, particularly along the East‐West Highway, were vulnerable to natural events. The  Association’s  Climate  and  Disaster  Risk  Screening  Tool  further  confirms  high  risks  of  extreme precipitation and landslides facing SRN roads and bridges.  

21. Nepal’s  Intended Nationally Determined Contributions (INDC) states: “climate change has visible and pronounced impacts on snows and glaciers that are likely to increase the possibilities of Glacier Lake Outburst Floods (GLOFs). Nepal has suffered from the impacts of increased frequency of extreme weather events, such as landslides, floods and droughts resulting in the loss of human lives as well as high social and economic costs.”14 

12 See (a) Yi Loo, Yen, and Ajit Singh. 2015. ““Effects of Climate Change on Seasonal Monsoons in Asia and Impact on Variability of Rainfall in Southeast Asia”. Geoscience Frontiers 6 (6): 817–823. The analysis is mainly for Southeast Asia, but there are observations on South Asia as well; (b) “4 Degrees Turn Down the Heat – Climate Extremes, Regional Impacts, and the Case for Resilience”; the World Bank by the Potsdam Institute for Climate Impact Research and Climate Analytics; June 2013; and (c) World Bank. 2018. “South Asia's Hotspots: Impacts of Temperature and Precipitation Changes on Living Standards.” www.worldbank.org/southasiahotspots  13 Priya, Satya, William Young, Thomas Hopson, and Ankit Avasthi. 2017. “Flood Risk Assessment and Forecasting for the Ganges‐ Brahmaputra‐Meghna River Basins.” World Bank.  14 Quoted from Government of Nepal Ministry of Population and Environment; Intended Nationally Determined Contributions, page 2. Communicated to the UNFCCC Secretariat in February 2016. 

Page 54: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

45 

22. Strengthening  the  resilience  of  Nepal’s  road  and  bridge  network,  particularly  through  greater consideration for resilient engineering designs to insure against catastrophic weather‐related events will be  important for  tackling any  likely disruptions because of climate change. These  include not only the robustness to withstand catastrophic climate‐induced weather events for strategically important bridges but also in terms of ensuring adequate resilience to expedite recovery after a climate‐induced event has damaged other bridges. Strengthening robust maintenance systems is therefore essential for achieving greater resilience as well as cost effectiveness of Nepal’s SRN bridge investments. BIMP II has therefore committed  to  support  the DOR develop  the  institutional  capacity  for  tackling both  the  structural  and nonstructural aspects of adapting bridge design, construction, and operations and maintenance to climate change. 

Specific Activities Addressing Climate Resilience  

23. A key element of the operation is to build climate resiliency planning capacity for the bridges of strategic importance in the SRN. Adaptation to the adverse impacts of climate change is indeed one of the main priorities for the Government, as stated in the INDC, submitted to the United Nations Framework Convention on Climate Change (UNFCCC). The INDC states “Overall, Nepal is one of the most vulnerable countries to climate change, water‐induced disasters, and hydro‐meteorological extreme events such as droughts,  storms,  floods,  inundation,  landslides,  debris  flow,  soil  erosion  and  avalanches.  Based  on National  Adaptation  Programme  of  Action  (NAPA)  2010,  out  of  75  districts,  29  districts  are  highly vulnerable to landslides, 22 districts to drought, 12 districts to GLOFs, and 9 districts to flooding.”15 

24. The Nepal INDC highlights the national policy aimed at promoting Local Adaptation Plans for Action (LAPA)  to  ensure  integration  of  adaptation  and  resilience  from  the  local  to  the  national  planning processes. The objective of such an approach is to engage communities in carrying out vulnerability and adaptation assessment, such that either a stand‐alone LAPA could be formulated and/or integrated into a larger regional adaptation plan. However, as noted in the earlier sections, the effectiveness of such plans depends  critically  on  the  institutional  capacity  in  the  DOR  to  implement  resilient  design  innovations throughout the network. 

    

15 Nepal’s Intended Nationally Determined Contributions: Submission to UNFCC (February 2016), page 3. 

Page 55: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

46 

ANNEX 5. SUMMARY FIDUCIARY SYSTEMS ASSESSMENT 

Summary 

1. In  accordance with  the  PforR  Financing  Policy,  an  integrated  fiduciary  systems  assessment was carried out that evaluated the fiduciary systems pertaining to the Program to determine whether they provide  reasonable  assurance  that  the  Program  funds  will  be  used  for  their  intended  purpose.  The integrated fiduciary assessment comprised three separate sub‐assessments of the fiduciary risks relating to SRN Bridge Program: (a) procurement, (b) financial management, and (c) governance (including fraud and  corruption  risks).  The  objective  of  the  Integrated  Fiduciary  Systems  Assessment  is  to  provide  a reference  that  can  be  used  to  monitor  fiduciary  systems  performance  during  the  Program’s implementation  and  to  identify  actions,  as  needed,  to  enhance  those  systems.  Findings  from  the assessment conclude that the overall fiduciary framework is adequate to support implementation. Actions to enhance fiduciary systems will help ensure that the Program achieves its intended results. 

Program Financing and Expenditure Framework 

2. The Program’s funding comes through the GON’s annual budget to the DOR through the MoPIT. Under BIMP I, the MoF revised the Program’s expenditure framework to provide greater transparency and control over expenditures relating to SRN bridges. In the past, the Program’s capital budgets were comingled among a wider national program of bridge sector investment which includes urban and local road network bridges. This subjected the Program to funding volatility when competing initiatives could divert  funding  from the Program’s works. The present expenditure  framework mitigates  this  risk. The budget codes with the GON’s budget document are 337320 and 337159. Bridges that are excluded from the  Program  use  separate  budget  code(s).  The  Program  Financial  Statements  will  be  used  for reconciliation between disbursements and the Program expenditures at the time of Program closure. This will determine if any refund is to be made. 

Program Implementation Framework 

3. Implementation of the SRN Bridge Program will involve the DOR’s Kathmandu‐based Bridge Branch, along with four regionally based Bridge Sectors which look after 5 regions and 34 DROs. Divisional Offices have a role in implementing less complex works under supervision of the Bridge Branch. This approach relies  on  the  institutional  systems  that  govern  the  DOR’s  procurement  and  financial  management functions.  It  also  requires  a  strong  regime  of  oversight  to  ensure  that  Divisional  Offices  exercise appropriate fiduciary control. Nepal’s governance and fiduciary management systems may change due to federalization. The timing and likely impacts of such changes is not known at present. However, if there are any significant changes in responsibility for construction, maintenance, and safety upgrades of SRN bridges  due  to  federalization  such  changes  would  be  revisited  during  implementation  so  that  the Program’s fiduciary arrangements may be revised with mutual consent of the GON and the Association. 

Assessment of the Program Procurement Framework 

4. Procurement of Program investments will be governed under the Public Procurement Act (2007) and  Public  Procurement  Regulations  (2007),  as  well  as  the  associated  complaints,  investigation,  and reporting mechanisms applicable in Nepal. The Public Procurement Act requires open competitive bidding and provides procedures for reviewing the complaints related to the actions before and after the signing of agreements. The PPMO has issued standard bidding documents for large and small works contracts that  can  be  used  for  this  framework.  These  provide  adequate  guidance  for  applying  the  Public 

Page 56: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

47 

Procurement Act effectively. Introduction of e‐bidding in the DOR has resulted in significant increase in competition and has proved to be an effective measure to reducing collusion and coercion among bidders.  

5. At the same time, the DOR has capacity constraints relating to skills and competencies required for efficient and transparent procurement at its Divisional Offices. Most divisional office staff are qualified engineers with technical skill sets, but with little formal training on procurement or contract management. Even though there are rate fixation committees in every district, a lack of uniform standards in project costing  prevents  standardized  and  comparable  cost  structures  across  projects.  While  the  Public Procurement  Regulations  clearly  lays  out  the  procedures  for  contract  administration  (including  the timelines  for  contract  supervision  and  oversight)  there  are  gaps  in  its  practice.  Weaknesses  in  the monitoring  of  project  cost  and  time  overruns  result  in many  projects  remaining  incomplete  for  long periods of time. There are also gaps in the systems and practices for procurement record keeping and filing.  

Financial Management Assessment 

6. Nepal’s Financial Procedures Act (1998) and Financial Procedures Rules (2007) provide an adequate framework for the Program’s key financial management and budgeting systems. However, weaknesses and  gaps  in  the  implementation  of  this  framework  pose  fiduciary  risks.  There  are weaknesses  in  the application  of  internal  controls  procedures  that  pose  risks  to  the  transparent  and  efficient  financial management  at  the  implementation  level.  The  various  controls  procedures  and  directives  relating  to expenditure management are not codified and internal control system to be developed as per Financial Procedure Regulation, 2007, has not yet been developed and hence they are not readily available in a manner that facilitates effective management and oversight of program implementation at the divisional office level. The present arrangements for internal audit (carried out by the District Treasury Comptroller Office) need strengthening and will draw on support from the training and consultancy support offered by the hybrid operation’s IPF component. Monitoring of audit findings is generally weak, although BIMP I has made progress at ensuring that audit observations are resolved. The Program Action Plan includes several items aimed at addressing these gaps. In the short term, the Program will deploy the World Bank’s PAT that has proven effective at enhancing contract management and monitoring financial progress. In addition,  the  Program  Action  Plan  includes  enhancements  to  the  CMS  and  FMIS  to  further  improve contract management and financial control across the department. Last,  the Program Action Plan also targets  continued  improvement  from BIMP  I on addressing audit observations under  the DOR’s Audit Committee. 

Program Fraud and Corruption Risks 

7. The  Program  has  a  significant  but  manageable  exposure  to  potential  fraud  and  corruption  on account of  the  following weak areas:  (a)  implementation of procurement and contract administration procedures,  (b)  internal  control  systems  and  processes,  (c)  monitoring  and  oversight  of  project preparation  and  implementation,  and  (d)  the  transparency  and  accountability  regime.  Key  initiatives under  BIMP  II  to  mitigate  these  risks  include  (a)  a  program  of  technical  auditing  by  the  NVC,  (b) deployment  of  the  Association’s  PAT  to  enhance  contract  management,  and  (c)  donor  support  to verification activities which has proved to be highly effective under BIMP I. 

8. Nepal has a relatively strong legislative framework to deal with fraud and corruption that includes the  Commission  for  the  Investigation  of  Abuse  of  Authority  Act  (1991),  Prevention  of  Corruption  Act (2002), the Public Procurement Act (2007), and the Good Governance Act (2008). The lead institution for 

Page 57: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

48 

addressing fraud and corruption allegations is the CIAA which has a mandate which is enshrined in Nepal’s Constitution along with legal authority granted by subordinate legislation. The CIAA acts on all complaints that  it  receives  and may  investigate  any  person  holding  a  public  post. Not  all  complaints  lead  to  full investigations and the CIAA follows a multistage approach with preliminary reviews proceeding detailed investigations.  

9. Any  citizen may  file  a  complaint  with  the  CIAA  against  any  public  official  for  alleged  improper conduct  that  may  have  adversely  affected  public  interest.  Complaints  may  be  anonymous  and  the legislative framework provides protection for whistleblowers to mitigate the potential threat of reprisals. The  CIAA  provides  transparent  annual  reports  regarding  its  operations  that  include  summaries  of successful prosecutions. 

10. Despite the strength of Nepal’s  legislative  framework,  there are noteworthy weaknesses  in how public  agencies  implement  their  roles.  Following  support  from  BIMP  I,  the  DOR  now  has  a  GRS  in accordance  with  the  GON’s  Service  Delivery  Guidelines  (2008)  that  require  all  agencies  to  set  up mechanisms to handle administrative‐level public complaints/grievances. Intermediate Results Indicator 4.1  in  the Program Results Framework  (‘Responsiveness of DOR’s Grievance Redress Mechanism’) will measure this systems ability to field complaints and provide redress on time. Nepal has passed the Right to Information Act and has recently ratified the United Nations Convention against Corruption (UNCAC), which has created public awareness regarding the menace of corruption. As part of the implementation of UNCAC, the Government has drafted legislation pending parliamentary approval which will allow it to undertake joint investigations with other external agencies. The strong stance taken by Nepal’s judiciary in cases involving political and bureaucratic corruption is heartening. Tough sentencing may also act as a deterrent against  future  fraud and corruption. The Prime Minister’s Office has set up a dedicated cell (‘Hello Government’) to listen to suggestions and complaints from the public. 

   

Page 58: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

49 

ANNEX 6. ENVIRONMENTAL AND SOCIAL SAFEGUARDS  

PforR Component: Summary of ESSA 

1. The ESSA has been conducted by the World Bank for BIMP II in accordance with the World Bank’s Policy/Directive on ‘PforR Financing’. The overarching objective of the ESSA is to analyze consistency and applicability  of  the  Government’s  environmental  and  social  management  systems  as  applied  to  the Program with the six ‘core principles’ of the World Bank’s PforR Financing Policy.  

2. The ESSA focused on environmental and social management systems, as applied to the subset of bridges under the DOR in which IDA financing is envisaged through the proposed PforR component. The analysis was conducted by reviewing documents, assessing  institutional capacity of Program executing and implementing agencies (that is, the MoPIT and the DOR), reviewing experiences and lessons of BIMP I  implementation,  and  reviewing  Strengths‐Weaknesses‐Opportunities‐and‐Threats  of  the  Program’s management. The ‘weaknesses’ or gaps were considered on two levels: (a) defined systems as written in laws, regulations, procedures and (b) the application of those systems in actual practice. Implementation capacity was also considered as demonstrated by the performance of the institutions that are executing and implementing the Program. The ESSA found consistency between government systems as applicable in  the  PforR  component  and  PforR  ‘core  principles.’  It  has  also  recommended  measures  to  address identified gaps and to enhance performance during implementation of BIMP II.  

3. BIMP  I  has  substantially  achieved  its  objectives  with  ‘Satisfactory’  social  and  environmental safeguards  rating.  Key  accomplishments  in  improving  the  Program’s  environmental  and  social management systems under BIMP I include (a) issuance and enforcement of a bridge addendum to the DOR’s  ESMF,  (b)  increased  human  resources  and  financial  resources  (budget)  for  the  DOR’s  GESU improving the environmental and social management capacity of the GESU, and (c) improved social and environmental impact management, particularly of bridges, within the DOR. Consequently, a system is in place for environmental and social screening and preparing environmental and social management plans and documenting them, for integrating environmental and social mitigations in the engineering designs and bidding documents, for supervision and monitoring, and so on. Furthermore, coordination has been improved,  an  IT‐based  electronic  GRM  has  been  established,  and  third‐party  verification  of  the compliance with environmental and social requirements has been practiced under BIMP I.  

4. The  scope  of  BIMP  II  is  substantially  similar  to  that  of  BIMP  I  and  the  anticipated  adverse environmental and social issues and impacts are expected to be similar. The adverse impacts are likely to be limited in nature and are not expected to pose a significant risk as the activities are likely to be within or close vicinity of the existing road right of way and Category A activities are excluded from the boundary for PforR  financing.  Some potential  adverse  impacts of new bridge  construction,  for example,  include impacts  on  the  existing  vegetation  cover  (limited  to  the  bridge  abutment  locations),  impacts  on  the aquatic ecology (limited to a few hundred meters upstream and downstream of the bridge crossings), impacts arising from lack of compliance with mitigation measures during construction/civil works (such as those related to health and safety, sanitation, wastes, and labor camps), and limited land acquisition and resettlement (confined to the area near bridge works). Based on experiences, adverse social impacts are likely to be temporary during project works, such as temporary land leasing for the contractor operations. However, new bridge construction may require land acquisition for bridge and access road development purposes. They need to be given due attention during the selection of bridge site locations, designs, and implementation. 

Page 59: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

50 

5. The bridge program will benefit many communities, particularly those with no or little access and isolated in remote areas. This is particularly so with indigenous communities that are among the targeted beneficiaries of  the Program. However, bridge rehabilitation and construction activities may also have adverse  impacts  on  nearby  indigenous  communities  because  of  land  acquisition,  and  impacts  on livelihood,  public  health  and  traffic  safety  concerns,  and  community  facilities.  Such  impacts  will  be assessed and mitigation plans will be developed in accordance with the provisions of the ESMF. 

6. The Association executed a stocktaking of labor‐related risks across all IDA‐supported projects in Nepal during 2017 which also  informed the ESSA. This confirmed that existing risk mitigations on IDA‐supported  initiatives  (including BIMP I), while  imperfect, have proven reasonably effective and can be further enhanced to provide additional mitigation potential. Below is a brief summary of results from this study: 

Scope 

Field  assessment  and  quantitative  survey  of  eight  project  sites  where  demographic  and other  information on 131  laborers and 261 community members were collected through multiple survey instruments. Four of these project sites were related to the SNRTP and four other sites (one each per project) were related to the following IDA‐supported initiatives: (a) the Nepal‐India Regional Trade and Transport Project, (b) BIMP I, (c) the RSSP, and (d) the RSDP. 

Qualitative interviews/information gathering that included (a) 50 key informant interviews with workers, community members, a police official, and contractors; (b) 15 Focus Group Discussions,  of  which  7  entirely  comprised  female  participants;  (c)  7  semistructured interviews (informal) with workers; and (d)  informal conversations and observations with various individuals around project sites. 

Main Findings 

Child labor. Surveys with community members found that 26.1 percent of the respondents claimed that increased child labor was a common risk of transport sector projects in Nepal. The study team’s overarching findings suggest that contractors, community members, and laborers are well informed of the age limits for working on IDA‐supported transport projects. Despite awareness, results also showed a general social acceptance of child  labor among community members, laborers, and contractors alike due to poverty‐related considerations which may result in an underlying support for child labor. Despite positive findings relating to IDA‐supported projects, the study also highlighted the need for continuing to enhance mechanisms  that  can  keep  underage  persons  from  pursuing  labor  on  project worksites. These  should  include  strengthening  the contractual  recourse  that  can be used  to ensure contractor  compliance  as  an  additional  measure  to  strengthen  risk  mitigations.  Social awareness  and  ‘soft’ measures  to  influence  public  opinion  on  child  labor  are  areas  that require additional attention once contractual recourse is strengthened further. 

Migrant labor and camps. About 88 percent of workers observed by the study team were migrant  workers,  coming  from  other  regions  within  Nepal  or  neighboring  countries. Emigration of skilled laborers was cited as a key reason for this figure. There is a likelihood that  migrant  labor  will  continue  to  dominate  in  Nepal’s  transport  sector.  Proactive 

Page 60: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

51 

monitoring  of  labor  camps  and  community‐worker  interaction  are  therefore  critical  risk mitigations in Nepal. The organizational systems used to monitor migrant labor camps need upgrading in parallel with increased use of outside labor. 

Skills and training: Only 11 percent of workers who responded to the study team’s surveys reported  receiving  skills  training  related  to  their  employment.  This  highlights  a potential development opportunity IDA‐supported projects may be able to tap through skills training components which would potentially form part of community engagement initiatives. 

Workers’  rights and conditions:  The assessment documented  continued  lapses  in OCHS‐related performance across IDA‐supported worksites. In one instance, the study team found a  situation  where  a  contractor  had  arranged  to  receive  advanced  notification  of  site supervision activities so that personal protective gear could be hastily distributed to workers and subsequently recollected once supervision had completed. These findings highlight the need to enhance both OCHS guidelines and mechanisms such as the DOR’s GRS that can facilitate  reporting  of  implementation  gaps.  These  findings  also  highlight  the  need  for regular validation of reporting and monitoring systems to provide feedback on areas where they may have become compromised. 

Conclusion: Key ESSA Findings 

7. The ESSA concludes that the overall environmental and social management system of the DOR is acceptable  for  use  in  the  PforR  component  of  BIMP  II  in  the  bridge  sector.  The  Legal  and  regulatory framework  governing  the  bridge  planning  and  construction  is  generally  satisfactory.  The  potential environmental and social  impacts of PforR component of BIMP II are  low to medium. Summary of the ESSA findings in relation to PforR’s six core principles are as follows:  

Core  Principle  1:  Environmental  and  Social Management procedures  and processes  are designed  to promote environmental and social sustainability in Program design; avoid, minimize or mitigate against adverse impacts; and promote informed decision making relating to a program’s environmental and social effects. 

8. Country  system  requires  different  level  of  EA  of  a  proposed  project  depending  on  nature,  size, financial  threshold,  and  sensitivity  of  the  project  site.  The  road  and  bridge  sector  frameworks  and guidelines  promote  environmental  and  social  mainstreaming.  Screening  of  an  activity,  for  example, construction of a bridge, decides type of assessment. EA, in the form of Initial Environmental Examination (IEE),  is required for sizable bridges. The assessment requires information disclosure and consultations with  stakeholders.  The  EA/IEE  identifies  measures  to  mitigate  adverse  impacts.  Implementation effectiveness, monitoring, and enforcement, however, vary from activity to activity: it is generally better in donor‐supported activities compared to the government‐funded activities.  

Core  Principle  2:  Environmental  and  social management  procedures  and  processes  are  designed  to avoid, minimize, and mitigate against adverse effects on natural habitats and physical cultural resources resulting from the Program. 

9. EA is necessary for any activity located within sensitive sites, such as the protected area. In addition, prior approval of competent authority is required for activities within the recognized sensitive sites. The legal provisions and guidelines require analysis/study showing various alternatives for the operation to avoid and minimize the loss of forest area and resources. EA is carried out and prior approval is obtained 

Page 61: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

52 

for the bridges located in the protected areas, and location of a bridge in a physical cultural site is generally avoided.  

Core Principle 3: Program procedures ensure adequate measures to protect public and worker safety against  the  potential  risks  associated with  (a)  construction  and/or  operations  of  facilities  or  other operational  practices  developed  or  promoted  under  the  Program;  (b)  exposure  to  toxic  chemicals, hazardous wastes, and otherwise dangerous materials. 

10. The  ESMF  of  the  road  sector,  the  bridge  addendum  to  the  ESMF,  and  other  guidelines  have provisions related to workers’ health and safety as well as community health and safety. Experience in the road and bridge sector,  including recently completed BIMP, suggests  that effective  implementation of these provisions varies: these are implemented, partially in many cases.  

Core Principle 4: Land acquisition, displacement and loss of access to resources is avoided or minimized, and  affected  people  are  assisted  in  improving,  or  at  least  restoring,  their  livelihoods  and  living standards. 

11. The Land Acquisition Act, LARRP, Land Acquisition Rules, the DOR's ESMF, and so on have provisions and procedures regarding land acquisition, resettlement, and rehabilitation measures. However, the Land Acquisition  Act  does  not  recognize  non‐land‐related  impacts  nor  does  it  cover  people without  titles. Impacts  to  non‐titleholders  are  covered  in  the  LARRP,  the  DOR’s  department‐wide  ESMF,  and  other guidelines and manuals which emphasize avoiding, minimizing, and/ or mitigating the adverse impacts. The  LARRP  and  the  DOR’s  ESMF  specifically  require  that  all  those  adversely  affected,  including  non‐titleholders to land, particularly the poor and vulnerable households, will be recognized for assistance in their  livelihood  restoration  and  improvement.  In  the  case  of  land  titleholders,  the  land  acquisition provisions including compensations at market value are implemented. Implementation of the provisions related to the non‐titleholders varies: these are better implemented in donor‐supported activities.  

Core Principle 5: Due consideration  is  given  to cultural  appropriateness of,  and equitable access  to, program benefits, with special emphasis provided to rights and interest of indigenous peoples, as well as the needs or concerns of vulnerable groups. 

12. The LARRP and the DOR’s ESMF mandatorily require, as part of environmental and social screening and  assessment,  free,  prior,  and  informed  consultations/consent  with  the  indigenous  people  and vulnerable  groups  including  local  communities.  One  of  the  objectives  of  the  Program  is  to  provide connectivity,  hence  benefit,  to  communities  in  remote  and  isolated  areas  which  are  often  the underdeveloped areas. Indigenous Peoples and other poor and vulnerable communities are among the intended beneficiaries. The DOR, as part of its road and bridge planning and implementation, conducts consultations providing prior information to the project beneficiaries and adversely affected people and integrates relevant consultation outcomes into project designs and development of environmental and social  management  instruments.  This  is  better  implemented  in  projects  financed  by  international organization(s). 

Core Principle 6: Avoid exacerbating social conflict, especially in fragile states, post‐conflict areas, or areas subject to territorial disputes. 

13. It is unlikely that the Program would exacerbate social conflict. The predecessor Program (BIMP I) has  been  smoothly  implemented,  without  reports  of  social  conflicts.  Nepal’s  Good  Governance (Management and Operation) Act (2008) has applicable provisions aimed at avoiding and managing any 

Page 62: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

53 

conflicts relating to development initiatives. The Good Governance Act specifically aims at making public administration pro‐people, accountable, inclusive, and participatory. Moreover, Nepal’s legal framework provides for CE through the local consultative forums constituted for purpose, transparency, GESI, and so on. These will be applicable to BIMP II. The DOR has a functioning GRM available as a first line of conflict identification/resolution.  The  DOR’s  Divisional  Offices  can  also  receive  complaints  in  person  from individuals who lack information and communication technology connectivity. Groups and individuals also access  the  local  judiciary  system,  which  has  proven  effective  in  the  past.  Bridge  construction  and maintenance activities enjoy broad support and also have inherent multiple beneficial impacts. Areas of Nepal where Program works are envisaged do not have any territorial disputes.  

Proposed Strengthening Measures 

14. The ESSA concludes that the overall environmental and social management system of the DOR is acceptable for use under this hybrid operation’s PforR component in the bridge sector. Nevertheless, it identifies opportunities  for  further  strengthening  institutional  capacity  constraints,  improving  ground‐level  performance,  and  addressing  gaps  experienced  in  the  environmental  and  social  management system. This opportunity is recognized by the client, which has expressed interest and commitment to address the main recommendations of the ESSA.  

15. Findings of the ESSA indicate the following key actions for the proposed Action Plan:  

Continue strengthening GESU and elevating their profile within the DOR, as the mandated and responsible unit for the overall management of social and environmental impacts and associated processes. Strengthening measures should include (a) preparation and approval of GESU’s three‐year business plan, (b) provision of human resources and financial resources to  GESU  based  on  a  three‐year  business  plan,  (c)  provision  of  logistics  and  reference materials/documents,  and  (d)  capacity  building/training  on  new  areas/use  of  new technology for social and EA/monitoring. 

Update  the  DOR’s  ESMF  (in  whole  or  with  addendum)  to  include  enhanced  provisions relating  to  OCHS,  labor  camp  management,  and  prevention  of  child  labor.  This  should include the development of OCHS guidelines and associated tools for the road and bridge sector as well as tools to support  implementation. These could  include standard contract provisions, training modules, OCHS awareness materials aimed at Program teams, and other key stakeholders (for example, contractors, workers, and communities). The updated ESMF should seek to align with international lessons learned on protocols for CE, GESI, outreach and  communication,  WIM,  child  labor  prevention,  and  beneficial  impact  enhancement measures. 

Define improved process and procedures for integrating environmental and social aspects in planning and development of bridges under the proposed system of ‘Gate Reviews’. These milestones should ensure coordination, monitoring, enforcement, stakeholder engagement, and  disclosure  of  information  occur  in  proper  sequence with  technical  work  to  prepare packages for civil works.  

Implement enhanced multi‐tiered approach (see Program Action Plan items) to managing labor‐related  risks  that  spans  policies/procedures  all  the  way  to  implementation  and includes the following:  

Page 63: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

54 

o Develop policy and guidelines relating to OCHS and other aspects of labor management to guide application of the Labor Act 2017 according to the specific needs of Nepal’s road and bridges sector. 

o Strengthen  implementation  capabilities  of  the  DOR  for  planning,  supervising,  and becoming better at  labor management. This should  include organizational structure, training and capacity development, and reporting/monitoring of issues. 

o Revise bidding documents with distinct reflection of costs for OCHS in BoQs, as well as mechanisms  for  enforcing  OCHS  compliance  through  financial  incentives,  contract termination, and/or other actions against contractors. 

o Develop  and  deploy  an  approach  to  site  inspection  and  performance  validation defining  organizational  arrangements,  frequency,  and  responsibilities  for checking/monitoring and reporting compliance with relevant environmental and social mitigations  including compliance with/enforcement of OCHS at construction sites of the bridges. There should also be an approach for periodic external assessments of in‐practice functionality of systems and field‐level performance. 

Approach for IPF Component: Consultancy Support and Institutional Development 

16. The  IPF component does not  include construction of civil works. The  locations of  the  roads and bridges that would be the subjects of consultancy support activities under the  IPF component are not known at this stage but will be along the SRN, and in some cases, potentially in close vicinity of existing bridges.  

17. For environmental risk management, OP/BP 4.01 Environmental Assessment, OP/BP 4.04 Natural Habitats,  OP/BP  4.36  Forests,  and  OP/BP  4.11  Physical  Cultural  Resources  are  triggered  for  the  IPF component because one or more of the bridges to be prepared with support from this component may have  adverse  consequences  relevant  to  those  aspects,  depending  on  the  location  and  details  of  the proposed  intervention/bridge.  For  social  impact  management,  Indigenous  Peoples  OP/BP  4.10,  and Involuntary Resettlement OP/BP 4.12 are triggered. The existing ESMF of the DOR will be used as a guiding document in the development of specific safeguards documents  in accordance with the policies noted above.  

18. Model TOR. Model TORs for Environmental Impact Assessment (EIA) (and Social Impact Assessment [SIA]) and related plans for Category A interventions have been prepared, reviewed, cleared, and disclosed by the Association. During implementation of the IPF component, these TORs will be customized for the specifics  of  each  intervention.  The DOR will  thus  prepare  specific  TOR  for  each  IPF‐supported  design activity as required for preparing safeguards documents in accordance with the World Bank’s safeguards policies that have been triggered. Where such interventions are screened as Category A interventions, each Category A TOR relating to safeguards assessments and safeguards documents will be subject  to consultation  and disclosure  as well  as  clearance  from  the Association  as  required by  the World Bank safeguard policies.  

19. Integration  of  environmental  and  social  inputs.  Where  required,  environmental  and  social safeguard documents will be prepared during the implementation of the IPF component, in tandem with engineering  to  prepare  for  civil  works  (feasibility  studies,  engineering  designs,  and  detailed  project reports). The aim is for safeguards‐related steps and engineering steps to be carried out together so that 

Page 64: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

55 

there is good integration of outputs. All safeguards documents supported under the IPF component need to  comply with  the World Bank’s  safeguard policies  and Nepal’s  national  requirements.  The DOR will ensure coordination among the safeguards, technical feasibility, and detailed design process and teams. 

 

Page 65: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

56 

ANNEX 7. SYSTEMATIC OPERATIONS RISK RATING TOOL (SORT) 

Risk Category  Rating (H, S, M, L) 

Political and Governance  High 

Macroeconomic  Moderate 

Sector Strategies and Policies  High 

Technical Design of Project or Program  Moderate 

Institutional Capacity for Implementation and Sustainability  Moderate 

Fiduciary  Substantial 

Environment and Social  Substantial 

Stakeholders  Moderate 

Overall  High 

    

Page 66: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

57 

ANNEX 8. PROGRAM ACTION PLAN  

#  Action Description  Resp. Party  Deadline  Completion Measure 

T  Technical Actions       

T1  All Program implementing units equipped with mobile tablets and BSMS made operational in all Program implementing units including DROs, Bridge Sector Offices, and Bridge Branch Headquarters. 

Bridge Branch  Initial accomplishment within 9 months of effective date and subsequent use for duration of Program. 

Initial milestone: At least 5 complete BSMS reports filed per DRO and Bridge Sector office.  Measure of sustainable use: At least 2 reports per month per bridge site with active works contracts. Reports to include social and environmental aspects of works (including labor camps where applicable). 

T2  The DOR to establish a DATC within Bridge Branch, satisfactory to the Association, for insourcing a fraction of bridge‐related engineering tasks and developing the capacity of junior engineers, with a particular focus on training and developing female engineers. 

DOR’s office of the Director General 

First cohort (approximately 5–10 engineers or specialists) recruited within 18 months of effective date. Subsequent cohorts recruited annually with approximately 5–10 engineers or specialists per cohort. 

Measures for completion:  (a) Endorsement of DATC TOR by Secretary of MoPIT through official letter to all DOR units; (b) Initial and subsequently annual recruitment of the DATC cohort completed; and (c) Cohorts to target not less than one‐third female participants. 

T3  The DOR to update Bridge Policy and Strategy with additional focus on resilient systems approach and the principles that will be applied to achieving resilience in subsidiary plans. 

Bridge Branch  Within 24 months of effective date 

Official promulgation of updated Bridge Policy and Strategy by MoPIT Secretary. 

Page 67: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

58 

#  Action Description  Resp. Party  Deadline  Completion Measure 

F  Fiduciary Actions       

F1  The DOR to update CMS and FMIS software and to relaunch the updated CMS and FMIS. The Program’s contracts and financial transactions will use the CMS/FMIS. 

DOR’s office of the Director General 

Revised CMS/FMIS software launched within 18 months.  All contracts and transactions through the FMIS/CMS within 24 months of effective date 

Confirmation letter from MoPIT secretary regarding relaunch of the updated CMS and FMISs.  All Program contracts to be covered under the CMS/FMIS with all Program transactions made through the FMIS. 

F2  The Bridge Branch to operationalize the PAT for all Program contracts and to include summaries of all contracts in Trimester Reports. The PAT will be used until such time as the CMS and/or the BSMS are fully able to incorporate reporting on fiduciary, technical, and environmental/social performance of contractors (including OCHS). 

Bridge Branch  Within 12 months of effective date and continuously thereafter 

PAT outputs included in Trimester Reports. 

F3  DOR’s outstanding audit observations up to FY 2017/18 and each subsequent fiscal year are recorded annually and addressed as part of continuously monitored plan to reduce audit observations. 

DOR  Within 18 months of effective date and annually thereafter 

FMIS to record audit observations, spreadsheet tool to track action against addressing audit observations. 

F4  Contractor market assessment updated and recommended procurement strategy developed for future DOR bridge works (including those under potential major projects). 

Bridge Branch  Within 18 months of effective date 

Final report endorsed by the MoPIT and presented to the NPC and the MoF. Revised report approved by the NPC. 

ES  Environment and Social Actions       

ES1  Prepare and approve the business plan for GESU for the next three years. 

GESU  Within 12 months of effective date 

Business Plan approved by the DOR DG 

Page 68: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

59 

#  Action Description  Resp. Party  Deadline  Completion Measure 

ES2  Revise bidding documents with distinct reflection of costs for OCHS, environmental and social management mitigation cost in the BoQs, and inclusion of relevant provisions under the conditions of contract. 

DOR/Bridge Branch/GESU 

By end September 2018 

Revised bidding documents in practice 

ES3  The DOR’s ESMF updated (in whole or with addendum) to include enhanced provisions relating to OCHS, labor camp management, CE protocol, provisions on the prevention of child labor, provisions on prevention of GBV and SEA. 

MoPIT/GESU  Within 24 months of effective date 

Official approval of updated ESMF (in whole or with addendum) by the MoPIT Secretary and public disclosure thereafter. 

ES4  Effectiveness of GESU  GESU (lead), and the Bridge Branch may directly procure experts and second them to GESU if need be for implementation modality 

Within 12 months of effective date 

Confirmation from the DOR DG of: (a) Set up of functional team in GESU for OCHS and labor standards;  (b) Approved organizational structure for GESU; (c) TOR defined for specialists; and  (d) Specialists in post and performing daily functions. 

ES5  OHCS and labor management guidelines (bridge‐specific elements) developed and deployed on Program contracts. 

GESU and the Bridge Branch to develop with support from specialized United Nations agency or international organization satisfactory to the Association 

Interim guidelines endorsed by the DOR by end September 2018; and  Final guidelines endorsed by the MoPIT within 12 months of effective date 

Deployment of specific provisions for worksites to be included in contracts, BoQ items, and social and environmental documents;  Deployment of specific provisions to ensure control over subcontracted arrangements in the supply chain of goods works and services 

Page 69: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

60 

#  Action Description  Resp. Party  Deadline  Completion Measure 

ES6  The DOR OCHS and labor policy: Integrated OCHS and labor standards developed to align with national legislation (including Labor Act 2017) and matching updates to the DOR’s ESMF (or addendum to ESMF) to reflect DOR policy and OHCS and labor management guidelines. 

GESU and the Bridge Branch to draft standards and ESMF update/addendum with support from specialized United Nations agency or international organization satisfactory to the Association 

Within 24 months of effective date 

MoPIT endorsement/confirmation through letter of (a) Final OCHS and labor management policy; (b) Completion of stakeholder consultation on ESMF update; and  (c) Public disclosure of final updated ESMF (or addendum developed). 

ES7  OCHS management officers assigned to Program sites. 

Bridge Branch (assignment of engineers)  GESU (recruitment of support consultants) 

End July 2019 and continuously thereafter 

(a) DOR engineers assigned as OCHS management officers for all Program sites (Note: one engineer may cover multiple sites); (b) Consultants assigned to support officers with field monitoring and reporting; and (c) Assignment register developed, promulgated, and updated in each Trimester Report. 

ES8  OCHS capacity‐building program (training, awareness, and education) 

Road Sector Skill Development Unit (lead) and the Bridge Branch 

Within 12 months of effective date and annually thereafter 

Modules developed and delivered annually before the beginning of each construction season covering (a) Training for DOR engineers and consultants (including training of trainers); (b) Contractors compliance training; and  (c) Demand‐side awareness raising training initiative for workers 

ES9  OCHS system monitoring  GESU (lead) and the Bridge Branch 

Within 12 months of effective date and annually thereafter 

Documentation in BSMS of (a) Regular and unannounced site visits by OCHS management officers and support consultants to worksites and camps to ascertain actual performance at implementing OCHS standards; and  (b) Consultations with communities near Program worksites and/or camps.  Target is at least 1 visit per month during construction season. 

Page 70: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

61 

#  Action Description  Resp. Party  Deadline  Completion Measure 

ES10  OCHS system near miss and incident data collection. 

GESU with support from the Bridge Branch 

Within 12 months of effective date and continuously thereafter 

(a) Accidents and near misses documented and made public for use in awareness raising and education; (b) Worker grievances to be directed to the DOR GRM system; (c) Documentation in the BSMS and public disclosure of incidents as pdf through the DOR website; and (d) Injured workers to be engaged as trainers/speakers. 

ES11  OHCS independent system validation and corrective actions. 

Bridge Branch to coordinate   SDC support for system validation through parallel TA program 

Reports provided annually by end July of each fiscal year during implementation beginning in July 2019  Action plans to be in place by September of each year beginning in September 2019 

Independent assessments of in‐practice function of OCHS and labor standards to include field validation (ground truthing) and community consultation.  Executed by one or more external bodies (for example, private firms, development partner, nongovernmental organizations/civil society organizations).  Annual action plans developed/agreed with IDA in response to any shortcomings identified. 

CC  Crosscutting Actions       

CC1  Annual DOR staff surveys to be completed using questionnaire satisfactory to the Association. Annual staff survey results reports to be independently compiled and publicly disclosed. 

NPC  Within 12 months of effective date and surveys administered annually thereafter by December 31 of each calendar year 

Public disclosure of results reports on the DOR website. 

CC2  Bridge development process defined with specific Gate Reviews and input stages from key technical, social, and environmental work streams. 

Bridge Branch  Within 9 months of effective date and continuously thereafter. 

(a) Bridge development process endorsed by the MoPIT for initial use; and (b) Documentation and signoffs for Gate Reviews completed for each Bridge Dossier. 

CC3  Update of model bid document technical, fiduciary, and environmental and social provisions used for contracting Program works. 

Bridge Branch  End September 2018  Model bid document, satisfactory to the Association, adopted by Program for works contracts. 

Page 71: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

62 

ANNEX 9. DETAILED FINANCING PLAN (PforR AND IPF COMPONENTS) Item  Activity  Qty.  Units  Unit Cost  US$ IDA  US$ GON  Total                PforR Civil Works                   

DLI‐1  Major bridge maintenance  4,500  Meter  3,878  13,087,728  4,362,576  17,450,304 

DLI‐2  Road safety upgrades on bridges  8,000  Meter  2,908  17,450,304  5,816,768  23,267,072 

DLI‐3  New 2 lane bridge construction, rehab., and replacement of bridges  4,000  Meter  13,572  35,288,393  19,001,442  54,289,836 

DLI‐4  New 4 lane bridge construction  2,000  Meter  19,389  25,205,995  13,572,459  38,778,454 

DLI‐5  Completion of backlog bridges under construction  5,000  Meter  6,786  22,055,246  11,875,902  33,931,147  

Bridge design, site assessment, feasibility study, quality monitoring, environmental, and social impact management 

5%  Of works  8,385,841  —  8,385,841  8,385,841 

   Subtotal of PforR Civil Works  113,087,666  63,014,988  176,102,654 

PforR Institutional Results                   

DLI‐6  Improved fiduciary governance of design‐build contracting  1  Each  2,000,000  2,000,000  —  2,000,000 

DLI‐7  BSMS (monthly monitoring system) use on Program worksites  5,000  Sites  750  3,750,000  —  3,750,000 

   Subtotal of PforR Institutional Results  5,750,000  —  5,750,000 

   Total expenditure program of PforR   118,837,666  63,014,988  181,852,654  % of PforR component  65.3%  34.7% 

 

IPF Component: Consultancy Support and Institutional Development                

IPF‐1  Preparations for future projects on the Strategic Roads Network  1  Lump sum  5,000,000  5,000,000  —  5,000,000 

IPF‐2  Technical auditing by NVC  5  Years  100,000  500,000  —  500,000 

IPF‐3  Advance bridge designs for enhanced resilience and inclusion  10  Bridges  300,000  3,000,000  —  3,000,000 

IPF‐4  Training (domestic and international) and capacity development  5  Annual  120,000  600,000  —  600,000 

IPF‐5  Supervision and oversight consultancies  5  Annual  500,000  2,500,000  —  2,500,000 

IPF‐6  Mobilization, equipage, and development of Design and Advanced Technology Cell  1  Lump sum  1,000,000  1,000,000  —  1,000,000 

IPF‐7  Support for OCHS and DOR implementation of Labor Act (2017)  5  Years  200,000  1,000,000  —  1,000,000 

IPF‐8  Contingency funding for verification past year 3  2  Years  150,000  300,000  —  300,000 

IPF‐9  Program impact evaluation data collection  1  Lump sum  250,000  250,000  —  250,000 

   Total of IPF Component: Consultancy Support and Institutional Development  14,150,000  —  14,150,000 

  % of IPF component  100%  0%  

   Totals (PforR + IPF)  132,987,666  63,014,988  196,002,654 

  % of total hybrid operation  67.8%  32.2%  

Page 72: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

63 

Item  Activity  Qty.  Units  Unit Cost  US$ IDA  US$ GON  Total 

  See note16       

16 As per the “Bank Policy: Program-for-Results Financing”, the PforR Financing proceeds are disbursed upon the achievement of verified results specified as disbursement-linked indicators, and such disbursements are not dependent upon or attributable to individual Program transactions or expenditures. Therefore, the presentation in the financing summary in Table 2 and in the detailed financing plan in Annex 9 reflects GON’s anticipated internal budgetary presentation and is not meant to predetermine earmarking of the IDA PforR Financing to specific individual Program transactions or expenditures.

Page 73: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

64 

ANNEX 10. IMPLEMENTATION SUPPORT PLAN 

1. There are four primary elements to the operation’s Implementation Support Plan. These include  

Field presence by the Association’s team of engineering experts; 

Program management and strategy support to the Bridge Branch in Kathmandu; 

Support to GESU’s role in (a) applying the DOR’s ESMF on Program (PforR component) works, (b) ensuring compliance with safeguards requirements (IPF component), and (c) fulfilling the environmental and social requirements of national law; and 

Support  and  regular  monitoring  from  the  World  Bank’s  team  relating  to  GBV/  SEA prevention. 

2. Table 10.1 shows an indicative estimate for 12 months of implementation support to the operation in each of the areas above. 

 Table 10.1. Implementation Support Plan 

Item  Focus  Skills Needed Resource Estimate (US$) 

Field presence (12 months) 

Quality monitoring 

Technical support to field units 

Technical inputs to the DATC 

Validation of contract monitoring and management 

Civil engineering 

Quantity survey 

Contract management 

70,000 

Program management and strategy support (12 months) 

Investment planning 

Expenditure tracking and monitoring 

Procurement tracking and contract monitoring 

DLI and expenditure monitoring 

Support to Action Plan items 

Support to mobilizing the DATC 

Financial analysis 

Institutional development 

Policy/strategy 

Fiduciary 

50,000 

GESU support (12 months) 

Inputs to TOR for EIA/SIA/screening activities 

Site visits and on‐the‐job support to GESU staff and field‐based implementation units 

Spot checks of implementation performance (OCHS, social management plans, environmental management plans) 

Support to mobilize and enforce enhanced contract terms for managing labor‐related risks  

EA/impact management 

Social assessment/impact management 

CE/community mobilization and consultation 

GBV/SEA prevention 

50,000 

Page 74: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

65 

Item  Focus  Skills Needed Resource Estimate (US$) 

Labor risks management including GBV/ SEA prevention 

Integrate ongoing World Bank‐supported work with National Women’s Commission on GBV/SEA prevention with operation’s activities 

Regular monitoring to ensure enforcement of contract provisions relating to labor camp conditions, prohibition of child labor, and prohibition of GBV/SEA 

Gender analysis 

Community consultation 

GBV/SEA awareness raising and capacity development within the GON and civil society 

50,000 

   

Page 75: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

66 

ANNEX 11. MAP (IBRD 39229) NEPAL’S BRIDGE NETWORK AT APPRAISAL OF BIMP I (2013) 

    

Page 76: PROGRAM APPRAISAL DOCUMENT - documents.worldbank.orgdocuments.worldbank.org/.../Program-Appraisal-Document-PAD-disclosable... · support takes into consideration, and calls for application

67 

ANNEX 12. MAP (IBRD 43444) NEPAL’S BRIDGE NETWORK AT APPRAISAL OF BIMP II (2018) 

 


Recommended