1 PASALI Philippines
Agroforestry
Progress Report
Proponent PASALI Philippines Foundation, Inc.
Partner Agency Department of Agriculture Region XII
Beneficiaries Tri – People
Contact person Ma. Victoria P. Olegario, Manager
Project Title Rubber Farming and Sustainable Urban Gardening (
SUGa )
Prepared by Charles A. Ty
Agroforestry Facilitator
April 12, 2012
Reviewed by Ma. Victoria P. Olegario, Manager
Migrant’s initiative transforms
Community through technology
and Tri-people empowerment
_________________________________________________________________________________
2 PASALI Philippines
Delivery & Turn-over seedlings
Delivery
Hevea buddings / Rubber seedlings 1st delivery from Brgy.Kalaong,Maitum Sarangani
Province to Brgy. Milbuk, Palimbang Sultan Kudarat, on March 31, 2012
Unload 2,000 hills of rubber seedlings with the participation of youths.
Turn over
Received by Honorable Mohamad E. Aron, Kagawad and Committee chair on
Education and Ways & Means of Brgy. Napnapon, Palimbang Sultan Kudarat
accompanied by Honorable Dipatu Kabon, Kagawad and Committee chair on Peace &
Order on April 1, 2012 at Brgy. Milbuk, Palimbang Sultan Kudarat.
The image is the hand over from Brgy. Council representative Hon. Aron to the Tri –
People representative Chieftain Duma of Biao Brgy. Napnapon Palimbang Sultan
Kudarat.
It was hand over by Mr. Charles A. Ty, Agroforestry Facilitator the representative of PASALI
Philippines Foundation Inc, attested by the colleagues Mr. Salido M. Panalon, FSS-SRI
project coordinator and Mr. Junny U. Ansa, Technician and with the presence of
Indigenous People representative Chieftain Duma M. Bonifacio.
_________________________________________________________________________________
3 PASALI Philippines
The Chieftain hand over to the beneficiaries, such as:
Purok Kamantis with travel distance of estimated 10 kilometers from Milbuk
Purok Kaluplop with travel distance of estimated 12 kilometers from Milbuk
Purok Pampangi with travel distance of estimated 14 kilometers from Milbuk
Purok Mimacao with travel distance of estimated 15.5 kilometers from Milbuk
This 4 puroks are covered / within the vicinity of Biao Brgy. Napnapon Palimbang Sultan
Kudarat and are the site or location for the planting of hevea buddings/rubber seedlings
at 1 hectare/purok.
Farm to market road from Milbuk to Biao/Napnapon is not viable / accessible to transport
by trucks / vehicles and even motorcycles in a while and therefore the recommendation
to LGU’s for improvement and renovation are needed.
IP ( Manobo ) kid’s participation with the guidance of parents
_________________________________________________________________________________
4 PASALI Philippines
Hauling by means of horses
The image below is the other means of hauling:
Bayanihan
Due to lack of horses, the community initiatives comes in thru the essence of
“Bayanihan“. This is the acceptance of community, become pro-active and synergized,
their eagerness and dynamism shown on this aspect, the difficulties of transporting rubber
seedlings is not hindrance on achieving bright future and towards to the future of their
coming generation, struggling for the new development and become model community
as a challenge of long decade identified as isolated and almost forgotten community.
With this follow up intervention, for them on this community, they’ve seen the light at the
end of the tunnel, or on the other hand they’ve say that our dreams almost come thru.
_________________________________________________________________________________
5 PASALI Philippines
Sacrifice is the secret of the success
The reality goes on, the precious of transplanting these rubber seedlings is the benchmark
of their new life, considering on forest conservation, preservation of natural environment,
and contribute to the climate change. Please see the image belown:
Transplanting
April 10, 2012 1st purok kaluplop Biao Brgy. Napnapon,Palimbang Sultan Kudarat
Note: The 2nd delivery of 3,000 hills of rubber seedlings is scheduled on May 15, 2012