+ All Categories
Home > Documents > Progress towards the ERLP at Daresbury

Progress towards the ERLP at Daresbury

Date post: 19-Jan-2016
Category:
Upload: nam
View: 55 times
Download: 0 times
Share this document with a friend
Description:
Progress towards the ERLP at Daresbury. Neil Bliss. ESLS Workshop 15-16 th November 2004. Contents. Aims & Objectives of Project Timescales Collaborations Technical priorities Progress on Design & Construction Funding Opportunities Acknowledgements. - PowerPoint PPT Presentation
Popular Tags:
63
Neil Bliss ESLS Workshop 15 - 16 th Nov 04 Progress towards the ERLP at Daresbury Neil Bliss ESLS Workshop 15-16 th November 2004
Transcript
Page 1: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Progress towards the ERLP at Daresbury

Neil Bliss

ESLS Workshop 15-16th November 2004

Page 2: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Contents

• Aims & Objectives of Project

• Timescales

• Collaborations

• Technical priorities

• Progress on Design & Construction

• Funding Opportunities

• Acknowledgements

Page 3: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Research, Development and Design

• Timescale April 03 – March 07• £14 million• Project Manager – Professor Elaine Seddon• Project Sponsor – Professor Colin Whitehouse, Director of Daresbury Laboratory

Four years of funding for the research, development and design work needed to address the key challenges of the 4GLS facility.

establish and operate 4GLS ERL prototype facility

undertake 4GLS underpinning physics studies

collaborate where other international efforts are directed at addressing problems of common interest

Aims: To enable the development of core skills and to gain ‘hands on’ experience to meet the 4GLS challenge

Page 4: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

4GLS: The Vision

A world-leading synchrotron radiation facility to enable internationally outstanding science

by the ‘low-energy’ community in the UK

4GLS combines, for the first time, superconducting ERL, SR and FEL technology in a multi-source facility

Page 5: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Timescales

Case prepared for 4GLS Investment Decision

Page 6: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Funded*

Not yet funded

Timescales

Case prepared for 4GLS Investment Decision

Page 7: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

• Answer key questions defining layout Dec 04– FEL layout options– 180 Bend– Beamline layouts

• Engineering Layouts start Jan 05• Further questions resolved Mar 05

– Switching– High current operation

Timescales

Page 8: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

• 4GLS User Meeting April 05• First review of costs July 05• Detailed design for CDR April 05 to Nov

05• Revise Layout & Costs Dec 05• Produce Project Plan Jan 06• Produce CDR Document Feb 06• CDR Published end Feb 06• TDR to follow …

Timescales

Page 9: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

In October John Wood signed MoUs with SLAC Jefferson Laboratory

The agreements cover a broad spectrum of activities from accelerator studies through fast pulse diagnostics to scientific exploitation of FEL sources.

Already have links with DESYLinks with FZ Rossendorf (ELBE) developinge2v

Collaborations

Page 10: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Technical Priorities for the ERL Prototype

1. Demonstrate energy recovery

2. Operate a superconducting linac

3. Produce and maintain bright electron bunches from a photo-gun

4. Produce short electron bunches from a compressor

5. Demonstrate energy recovery with an insertion device that significantly disrupts the electron beam

6. Have an FEL activity that is suitable for the synchronisation needs

7. Produce simultaneous photon pulses from a laser and a photon source of the ERL Prototype that are synchronised at or below the 1ps level

Page 11: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Parameters

• Nominal Gun Energy 350keV• Booster Energy Gain 8 MeV• Injector Energy 8.35 MeV• Linac Energy Gain 26.65 MeV• Circulating Beam Energy 35 MeV• Linac RF Frequency 1.3GHz• Bunch Duty Factor-1 16• Bunch Repetition Rate 81.25 MHz• Bunch Spacing 12.3 nS• Max Bunch Charge 80 pC• Particles per Bunch 5 E+08

Page 12: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Parameters at long Pulse mode

• Average Current 13 mA• Peak Current 6.5 mA• Average Power at Injector Energy108.6 W• Average Power at Full Energy 455 W• Peak Power at Injector Energy 54.3 kW• Peak Power at Full Energy 227.5 kW

Page 13: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

ERLP Building Layout

Page 14: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Accelerator Layout

Page 15: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

1

2

3

4

Booster to FEL

Elegant

FEL to Dump

Elegant

FEL Interaction

GENESIS

8.35/35MeV 35/8.35 MeV250k particles

Gun to Booster

ASTRA

0 to 8.35MeV250k particles 250k particles106 particles

First case of modelling an ERL together with a FEL and energy recovery

Start-to-end Simulations

Page 16: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

ERLP output

Page 17: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

ERL Prototype Photoinjector

Page 18: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

LASER ROOM

ACCELERATORHALL

Shield wall

Optical Table

DC GunBased on

Jlab design

Commercial 500kV(350kV)8mA DC Power Supply(Glassman Europe)Power supply and gun enveloped by 0.8 Bar SF6 environment

Booster Cavity

Laser Beam Transport System

ERL Prototype Photoinjector

Page 19: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Cathode material Cs:GaAs

Electron bunch charge 80 pC

Bunch length 20 ps

Bunch repetition rate 81.25 MHz

Pulse train length 1 bunch and 20-100 s

Pulse train repetition rate Single shot and 1-20 Hz

Cathode efficiency 1 %

Laser wavelength 532 nm

Laser pulse energy at cathode

20 nJ

Average power at cathode <4 mW

Pulse length <20 ps

Beam diameter at cathode 2-6 mm (FWHM)

Nd:Vanadate Laser material

- -

- -

81.25 MHz Pulse repetition rate

- -

Cw mode-locked Pulse train rep. rate

- -

1064 / 532 nm Laser wavelength

61.5 nJ532nm output energy per

pulse

5 W Average power

7 ps Pulse length (FWHM)

0.6 mm Beam diameter output

Laser

The commercial solutionRequirements

Page 20: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Laser System Layout

Cho

pper

f=1750mm

laserf=610mm

2

f=762mm

f=793mm1102mm

1846.06mm

1802mm 290

.94

mm

Shu

tterP

ocke

lscel

lA

naly

ser

Diagnostics

Dia

gnos

tics

Cho

pper

f=1750mm

laserf=610mm

2

f=762mm

f=793mm1102mm

1846.06mm

1802mm 290

.94

mm

Shu

tter

/2 plate

Poc

kelsc

ell

Ana

lyse

r

Diagnostics

Dia

gnos

tics

Plan View Schematic of Optical Table Layout

Page 21: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

2-6 mm beam size on the cathode

Gaussian on day 1

Flat top in later phase

Beam Transport System

Page 22: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

ChopperChopper• To generate 60-140 s long trains of pulses

with 100 Hz repetition rate• To decrease the thermal load on the electro-optic

modulator (Pockels cell)

Mechanical shutterMechanical shutter• To select pulsetrains with 1-20 Hz• To decrease the thermal load on the Pockels cell

PockelsPockels cellcell•To clean up the rising and falling edges•To select down to single pulse

Pulse Structure

Page 23: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Light Box

Cathode

Vacuum Valve

Light Box

Page 24: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Gun Assembly

XHV

Ceramic

Cathode SF6Vessel removed

Cathode ball

Stem

Electrons

laser

Anode Plate

Page 25: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Ceramic

• Controlled Resistivity Ceramic – WESGO

• Surface Resistivity 105 -1013 W/sq• Surface Resistivity 1010 -1012 W/sq• Dielectric Strength 27 DC kV/mm• Colour Black• Material Al970CD• Delivery End of Jan 05• Cost £36K

Page 26: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Buncher Cavity

FZ Rossendorf DesignBuncher cavity being manufactured by Vacuum Generators UK, available for testing end of November 04.

70 mm

• Single Cell• 1.3 GHz• Longitudinal bunch

compression• No Acceleration• Zero-phase crossing angle

Page 27: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Booster & Linac Modules

Page 28: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Liquid helium vessel 2 K

Helium transfer line

Accelerating module

100 W Shield at 80 K

FZ Rossendorf Module

Booster & Linac Modules

Page 29: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Booster & Linac Modules

ELBE Type Cryostat with dual Tesla Linac Sections

Order placed in March 04 – on Accel

• FZ Rossendorf Module – two TESLA cavities

• Energy Gain 26.65 MeV

• Independent control of Qext

• Independent control of cavity phase

• Delivery of module 1 (booster) due 28/11/05

• Delivery of module 2 (linac) due 6/3/06

• Cost £1.7m

Tesla 9-cell cavity

Page 30: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Cryogenics

  StaticDuty

Dynamic

Duty

TotalDuty

Time Averaged

 

TOTAL SYSTEM  

Cavities 45.1 161.3 206.4 litres / hour

Main transfer lines 24.4 24.4 litres / hour

Other equipment 12.8 12.8 litres / hour

Total consumption 82.3 161.3 243.6 109 litres / hour

  1650 974 2620 litres / day

Page 31: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Cryogenics

Order placed on Linde (TCF50)

• Delivery due in May 05

• Cost £1.26m

Page 32: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Inductive Output Tubes

• Higher frequency than standard IOT

– High Frequency IOT – 1.3GHz & 1.5GHz

• Cathode - grid transit time effects

– Grid gap required – 0.125mm

– Standard IOT – 0.18mm

– Grid process capability

– Cathode – grid gap setting

• Integral output cavity

– Ability to set / maintain the required frequency

RF to be supplied by IOTs that are being developed by the RF group in collaboration with e2v

50KV DC Power supply commissionedIOT’s available Now

Page 33: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

IOT 116LS Test Results

Frequency 1.2986 1.2986 1.2986 GHzBeam Voltage 24.9 24.9 27.7 kVBeam Current 0.91 0.84 1.1 AGrid Voltage -104 -122 -109 VDrive Power 220 260 260 WOutput Power 12.4 12.4 16.3 kW-1dB bandwidth 2.4 2.4 3.6 MHz-3dB bandwidth 4.4 4.8 5.7 MHzEfficiency 54.7 59.3 53.5 %Gain 17.5 16.8 18.0 dB

Page 34: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Magnets

• Being procured on a Performance Based Specification

• Preliminary modelling has taken place with FEA codes; minimal engineering design

• Field quality is responsibility of supplier. Magnets accepted on basis of magnetic measurements

• Large quantity (40%) of the magnets being loaned from JLAB

• 66 magnets in total required, 39 to procure• 9 Dipoles• 26 Quadrupoles• 4 Sextupoles

• + 28 H/V Correctors• Tender Notice published OJEU 16th September• Return Date 3rd November• Bids received from 3 companies• Currently evaluating bids• Contract cost approx. £350K• Two delivery stages planned

– Stage 1 (TL2) end of May 05– Stage 2 (Arcs & Dump) end of July 05

Dipole A Good field:+/- 1x10-4 over +/- 33mm

Quad D Good gradient:+/- 1x10-3 over +/- 42.5mm

Page 35: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

ERLP Layout

New Magnets (39 off) JLAB Magnets (27 off)

Page 36: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Power Converter Ratings & Performance

Family Numberof

magnets

RatedVoltage(Volts)

RatedCurrent(Amps)

Dipole A 3 20 10

Dipole B 4 6.3 40

Dipole C 2 5.75 40

Dipole D 6 20 75

Dipole E 4 7.5 90

Quad A 8 8 5

Quad B/C 16 18 10

Quad D 12 12 10

Quad E 3 16.6 20

Quad F 4 12 5

Sext A 4 12 5

Total 66 Plus 28 Bipolar Corrector power converters.

• Quantity - All 66 magnets are individually powered.

• Unipolar – Dipoles fitted with changeover circuit.

• Interface – Remotely operated with analogue control.

• Standardisation – Magnet ratings matched to reduce converter spares.

• Operating range - 0 to 100% rated O/P current.

• Stability - ± 100 ppm long term, measured at ± 20ppm over 4 hrs.

• Reproducibility - ± 200 ppm over a 24 hr period.

• Resolution – 16 bit (15ppm)

Page 37: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Beam position monitor (¾ )- beam position- longitudinal bunch structure- current measurement- beam loss reference

measurement.Unit A: H& V Slits/ pepper pot/

viewer- beam size directly - emittance measurement. Transverse kicker cavity- longitudinal characterisation of

the beam.Analyser magnet- energy and energy spread

Units B: Viewer and vertical slit- emittance - image the beam- energy spread measurement.Unit C/E: Viewers- energy spread measurements- emittance measurements at the

position of the first accelerating cell

Faraday Cup- temporal structure of the pulse- total charge in the pulse- energy and energy spread

Diagnostics Summary

Page 38: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Diagnostics Summary

• 14 Optical Transition Radiation (OTR’s) Beam Viewers

• 3 Florescent Screens (YAG’s)• Stripline EBPM 14 locations• Button EBPM 12 locations• Faraday Cup (in TL 2)• Total Current Monitor• Electro–optic sampling monitor

OTR

Al foil

Beam impedance screen

Pneumatic operated mechanism

Page 39: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Stripline EBPM / Corrector coils

Section

Corrector Coils

Page 40: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Arc EBPM

EBPMs

Arc Dipole Magnet

Page 41: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Building Work Progress

• Renovation of old SF6 tanks for gaseous He

• Laser room approaching completion

• Ventilation system for control and diagnostics rooms being installed

• Rack room well advanced

• Bulk internal shielding complete (more than 2000 tonnes of concrete moved)

• Plinths for external labyrinths laid

Page 42: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Laser & Diagnostics Rooms

Page 43: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Assembly Building

Page 44: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Magnet Test Room

Page 45: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Module 1 - Transfer Line 2

Girder

Support PedestalIon Pump

Quadrupole Magnet OTR

Corrector Coil and EBPM Assembly

Dipole Magnet

Lifting Points

• Modular

• Majority of vacuum joints made in clean room

• Services can be fitted

• Modules can be built in parallel

Page 46: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Module 4 - Injection Chicane

Injection Chicane VesselCamera

Tube

DV Magnet DU Magnet

OTR

Ion Pump

Page 47: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Module 16 - Compression Chicane

Bolt on castors for use in assembly

area

Port for OTR

Compression Chicane Chamber

Dipole Magnet DWQuadrupole Magnet

Chamber Support

Magnet Support

Page 48: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Assembly Philosophy, Supports and Adjustment Systems

This philosophy ensures that the magnetic centres of all the magnets are accurately positioned with respect to each other.

1st position the Magnets in their modules in the assembly building.

4 survey points per magnetPosition of survey points to magnetic centre accurately known.

2nd Locate and drill pedestals in the Tower – position not critical

3rd Survey modules into position in the towerSurvey grid as global reference4 survey points per girder

Magnet Adjustment

Survey points

Girder adjustment

Pedestal

Page 49: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Survey Equipment

Faro Laser Tracker

Repeatability 1m +1 m /m

Accuracy 10 m + 0.8 m /m

Uncertainty ≈ 10 m /m

Portable

Robust

Spatial Analyzer Metrology Software

Error Simulations

Multiple instruments/types

Automation

Page 50: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

± 0.05 mR/m measuring length± 0.5 mR for 150 mm long quadrupoles

Yaw

Roll± 0.2 mR

Pitch

± 2.5 mm± 0.5 mmY

± 0.5 mm± 0.1 mmTransverse X, Z

Globalwithin ± 15m

Local zonewithin ± 2.5m

ERLP Positional Tolerances

Y X

ZYaw

Pitch

Roll

Co-ordinate System

Page 51: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

ERLP – 1st Grid Simulation

1st Simulation of proposed reference grid in SA

76 Grid reference points

40 Instrument positions

Each point measured by a minimum of 3 instruments

Faro Tracker

Grid reference points

Page 52: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

ERLP – Simulation Results

Most points can be surveyed to within +/- 50 m

Worst point within +/- 82 m

Instruments reference multiple points, worst Instrument position +/-13 m

Page 53: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Vacuum Vessels Arc

Dipole chambers

OTR chambers

Straight chambers

Taper transition

Bellows

OTR chambers

Page 54: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Rectangular to Circular Transition

Taper

Arc rectangular aperture80 mm hor. X 42 mm vert.

Bellows circular cross-sectionDiameter 50 mm - NO RF SCREENING

Page 55: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

General Considerations

• Build up of contaminant layers on optically-reflecting surfaces.

• Cryodeposition of contaminant layers on the cold surfaces of superconducting cavities

• System particles by:

– using low particle production components

– particle control measures during preparation and installation.

To minimise the following:

Page 56: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Class 100 (ISO 5) Clean Room

LASAIR II Model 310/510Particle sizing sensitivities from 0.3 – 25 microns

Clean Room Monitoring

LASAIR II Model 110Particle sizing sensitivities from 0.1 – 5 microns

Vacuum Chamber Monitoring

Page 57: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

ERLP Vacuum Regions

Region Pressure/mbar Pumps Diagnostic

Gun 1x10-11 IONP/NEG EXT/RGA

TL1 1x10-10 IONP/NEG IMG/RGA

Booster 1x10-10 Cryo/IONP IMG/RGA

TL2/BTS 5x10-8 IONP PENG/RGA

Linac 1x10-10 Cryo/IONP IMG/RGA

OCFM 5x10-8 IONP* PENG*

OCBM 5x10-8 IONP* PENG*

Page 58: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Example Pressure Profile

•Numerical Method Using MathCad and/or Molflow to Generate Pressure Profiles

–Input data includes dimensions and vacuum surface performance

Page 59: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Control System - Options

• SRS control system (based on CERN ISOLDE)

• Very familiar design and techniques

• Re-use of some hardware and software from SRS

• Not supported outside of DL

• EPICS – DL work on DIAMOND

• Specifically designed for accelerator control systems

• free and widely supported (used at JLAB)

• Can re-use designs and systems developed for Diamond

• SCADA (several systems)

• Quick and easy to get going

• Expensive licensing

• More suited to process control applications & standalone systems

Page 60: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Control System - Overview

•The control system will use EPICS, VME and PC Consoles

•Re-use designs already developed for SRS and Diamond

•Limit control and monitoring of devices to a minimum

•Ensure maximum flexibility and low development cost

•Combine general control system with stand-alone and proprietary systems where necessary

ClientOperator Interface

LAN

ServerInput Output Controllers

Equipment Being Controlled

Page 61: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

EU funding to help support the underpinning physics studies…

EUROFEL, FP6 Design Studies Call, awarded, EU 9 M single pan European FEL bid on underpinning technical activities (top in Peer Review)

North West Science Fund…. £4 M outline bid successful: detailed bid submitted Sept 17th

Hope to hear in Dec 2004

Current Funding Opportunities

Page 62: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

NW Science Fund bid: £4.036M

If funded:

• 3 year programme starting 2005

• X-ray generation by Thomson scattering

• Laser-SR synergy

• THz and tissue culture facility

Other things were considered but were rejected – disruption to ERLP too great

Page 63: Progress towards the ERLP at Daresbury

Neil Bliss ESLS Workshop 15 - 16th Nov 04

Acknowledgments

• All the team working on the Project• 4GLS IAC• Collaborators

e-mail [email protected]://www.4gls.ac.uk


Recommended