CHAPTER 4
PROJECT ALTERNATIVES
Quantum Power Ghana Gas Limited 4-i Knight Piésold Consulting
Environmental and Social Impact Assessment
TABLE OF CONTENTS
4 CONSIDERATION OF PROJECT ALTERNATIVES ................................................................. 4-1
4.1 INTRODUCTION ........................................................................................................................ 4-1
4.2 BACKGROUND .......................................................................................................................... 4-1
4.3 ANALYSIS OF LOCATION ALTERNATIVES ............................................................................. 4-1
4.3.1 Methodology ............................................................................................................................... 4-2
4.3.2 Study Assumptions ..................................................................................................................... 4-3
4.3.3 Alternatives and Facilities Included in the Analysis .................................................................... 4-4
4.3.4 Comparing Location Alternatives ................................................................................................ 4-6
4.4 LNG TERMINALCONFIGURATION ALTERNATIVES ............................................................. 4-11
4.4.1 Option 1: FSRU on Soft Yoke Mooring ..................................................................................... 4-11
4.4.2 Option2: FSRU and LNGC on Double Berth Jetty.................................................................... 4-12
4.4.3 Option 3: FSRU on Spread Moor and LNGC on Single Berth Jetty ......................................... 4-13
4.5 OFFSHORE PIPELINE ROUTE ALTERNATIVES ................................................................... 4-14
4.5.1 Option 1 (Base Case) ............................................................................................................... 4-14
4.5.2 Option 2 .................................................................................................................................... 4-16
4.5.3 Option 3 .................................................................................................................................... 4-17
4.6 PIPELINE INSTALLATION METHOD ALTERNATIVES ........................................................... 4-20
4.6.1 Pull Pipeline Ashore from Pipelay Vessel (Preferred Case) ..................................................... 4-20
4.6.2 Pull Ashore Using Onshore Return Sheave ............................................................................. 4-20
4.6.3 Fabricated Pipeline Onshore .................................................................................................... 4-20
4.6.4 Directional Drilling ..................................................................................................................... 4-21
4.6.5 Tunnel and Shaft Construction (Microtunneling or Pipe Jacking) ............................................ 4-21
4.7 LNG VAPORISATION TECHNOLOGY ALTERNATIVES ........................................................ 4-26
4.7.1 Seawater (SW) Heating ............................................................................................................ 4-26
4.7.2 Fuel Gas (FG) Heating ............................................................................................................. 4-27
4.7.3 Ambient Air Heating .................................................................................................................. 4-28
4.7.4 Intermediate Fluid Heating ........................................................................................................ 4-30
4.7.5 Heat Integration with Power Plant ............................................................................................ 4-32
4.7.6 COMPARISON OF VAPORISER OPTIONS ............................................................................ 4-33
4.7.7 Rankings of LNG Vaporisation Technology Alternatives .......................................................... 4-37
Quantum Power Ghana Gas Limited 4-ii Knight Piésold Consulting
Environmental and Social Impact Assessment
4.8 NO-GO ALTERNATIVE ............................................................................................................ 4-37
LIST OF TABLES
Table 4-1: Summary of Alternative Ratings ................................................................................ 4-8
Table 4-2: LNG Terminal Location Alternative Analysis ............................................................. 4-9
Table 4-3: Route Options (Pros and Cons) .............................................................................. 4-18
Table 4-4: Advantages and Disadvantages of Various Pipeline Installation Methods ............. 4-24
Table 4-5: Qualification Comparison for LNG Vaporisation Options ........................................ 4-34
Table 4-6: Vaporiser Rankings for Ambient above 18°C .......................................................... 4-36
LIST OF FIGURES
Figure 4-1: The proposed offshore localities of the mooring facilities ........................................ 4-5
Figure 4-2: FSRU on Soft Yoke Mooring .................................................................................. 4-12
Figure 4-3: FSRU and LNGC on Double Berth Jetty ................................................................ 4-13
Figure 4-4: FSRU on Spread Moor and LNGC on Single Berth Jetty ...................................... 4-14
Figure 4-5: Import Pipeline Route – Option 1 (Base Case) ...................................................... 4-15
Figure 4-6: Import Pipeline Route – Option 2 ........................................................................... 4-16
Figure 4-7: Import Pipeline Route – Option 3 ........................................................................... 4-17
Figure 4-8: TBM Located in Thrust Shaft ................................................................................. 4-23
Figure 4-9: Open Rack Vaporiser Flow Scheme ...................................................................... 4-27
Figure 4-10: Submerged Combustion Vaporiser ...................................................................... 4-28
Figure 4-11: Typical Ambient Air Vaporiser .............................................................................. 4-29
Figure 4-12: Glycol-water Intermediate Fluid Vaporiser Integration with Different Heat
Sources ..................................................................................................................................... 4-31
Figure 4-13: IFV LNG Vaporisers in Rankine Cycle ................................................................. 4-32
Figure 4-14: SCV Power Plant Integration ............................................................................... 4-33
Quantum Power Ghana Gas Limited 4-1 Knight Piésold Consulting
Environmental and Social Impact Assessment
4 CONSIDERATION OF PROJECT ALTERNATIVES
4.1 INTRODUCTION
This section describes and analyses the most important features of the components of
alternatives that were evaluated to select the optimal project location, taking into account
environmental, social and economic variables. This analysis is aimed at comparing, based
on a set of previously established criteria, the best feasible alternatives in order to identify
the one causing the least impact and allowing to determine the optimal option for the Project
location. This analysis does not consider the unselected alternative as unviable, but only
presents it as the least favourable with respect to the other options.
Selection of criteria to qualify an alternative is important and specific for each case; thus, a
set of criteria generated for a specific Project cannot be applied to another without properly
studying the characteristics of each case. It should be clear that the criteria to be
established will depend on the project type and duration, as well as the environmental,
social and cultural conditions of the zone where it will be developed.
4.2 BACKGROUND
QPRGG proposes to build Tema LNG Terminal of the coast of Ghana. The LNG terminal
capacity is 250mm SCFD with the target uptime of 85% or greater.
QPRGG is developing an LNG import facility for Ghana as an alternative to light crude oil
(LCO) currently used for power generation. In December 2013, HR Wallingford was
commissioned by QPRGG to carry out review and advisory services in connection with the
project, including the review of an initial feasibility study carried out by Worley Parsons.
The terrestrial components associated to the Project, specifically land-based facilities are
considered as fixed (i.e. their location has already been established). The analysis of
alternatives was carried out only for location of marine components. Following is an
analysis of the Do-nothing, technology, installation method and Location (analysed in detail)
alternatives.
4.3 ANALYSIS OF LOCATION ALTERNATIVES
Project components include:
1. Offshore Mooring and Support for Floating Units (FSRU as well as LNG Supply
Vessels),
2. Floating Storage and Regasification Unit (FSRU),
3. Subsea Gas Pipelines and
4. Landing Facilities and Distribution, which will be located on land.
The analysis of the LNG Terminal location will not include evaluation of land-based facilities
since they will be a constant for every option to be analysed. Also, the analysis will include
a series of technical, environmental and social criteria; development of this procedure is
described below.
Quantum Power Ghana Gas Limited 4-2 Knight Piésold Consulting
Environmental and Social Impact Assessment
4.3.1 Methodology
This analysis comprises comparison of viable options from a technical viewpoint, so that
evaluated alternatives do comply with conditions required for location of infrastructure.
Based on this selection, the best alternative is chosen after a more detailed technical-
economic analysis considering environmental and socio-cultural aspects.
Once criteria have been established and depending on the decision making logic, the
analysis of alternatives may be completed in this case using a semi-quantitative process,
which selects the best option by weighting of criteria.
The initial stage of this process usually consists of selecting preliminary alternatives as well
as applying criteria in order to reduce the number of these alternatives. The final stages
comprise comparison of alternatives, selecting among them the best one from the technical-
economic, environmental and social viewpoints.
After determining the set of criteria to be used in the alternative analysis process, it is
necessary to establish the analysis method to be applied. This study has used a modified
version of the Multiple Count Matrix (MCM) process (Kerr et. al., 2003). The methodology
considers a series of main criteria or counts (technical-economic, environmental and
socioeconomic aspects), each of which has a weighting value. Since each count may be
influenced by factors, it is in turn divided into sub-criteria or sub-counts (e.g. considerations
for the construction, operation, closure stages, among others). Each sub-count also has a
weighting value and includes indicators of determining factors specific for the components
(e.g. operation ease, positions and perceptions, among others), each of which also has a
weighting value. The reason for dividing and sub-dividing each count is to define a base for
the analysis of alternatives that will allow following the logic of the MCM analysis authors.
The weighting of each count, sub-count and indicator in the analysis of alternatives takes
into consideration that some factors become more important than others. It should be noted
that, even with the incorporation of quantitative values, this is a subjective process since
weightings and counts are determined based on the evaluator’s experience and professional
judgment. However, it allows for a systematic procedure that can be replicated by different
interested parties. The weighting scale must be defined by the evaluator considering the
possible values that each indicator may take. Scales used in the present MCM are as
follows:
For the count and sub-count levels:
0.2 = low value
0.4 = moderately low value
0.6 = moderate value
0.8 = moderately high value
1.0 = high value
For the indicator level:
1 = low value
Quantum Power Ghana Gas Limited 4-3 Knight Piésold Consulting
Environmental and Social Impact Assessment
2 = mid-low value
3 = mid value
4 = mid-high value
5 = high value
After indicators have been established and their weighting values have been determined, a
value is assigned to each option. This Multiple Count Matrix considers a value scale that
weights positive and negative effects for different alternatives.
The scale is as follows:
3 = positive option
2 = moderately positive option
1 = slightly positive option
0 = neutral option
-1 = slightly negative option
-2 = moderately negative option
-3 = negative option
After establishing values for counts, sub-counts and indicators, count values are multiplied
by weightings in order to obtain a total value.
To prevent bias associated to with the use of different numbers of sub-counts and indicators
per considered aspect, the total value obtained for each aspect (technical, environmental
and social) was divided by the number of sub-counts. This operation allowed standardizing
or placing under the same conditions each one of the considered aspects.
Weighted values for each indicator are subsequently added up. The resulting higher value
is considered to be the best alternative.
A text description is included for each indicator and its corresponding value in order to
provide a value basis.
4.3.2 Study Assumptions
It is very important to identify the starting assumptions in each analysis of alternatives. This
allows putting in perspective the analysis limitations according to its relevance. The analysis
cannot be considered valid if after it has been completed, the project objectives change or if
there are significant changes in the project development. The assumptions included in the
analysis of alternatives for this study are as follows:
The economic model parameters, such as fuel and consumables prices will not change
to the extent that a radical change in the Project design and requirements would be
required.
Quantum Power Ghana Gas Limited 4-4 Knight Piésold Consulting
Environmental and Social Impact Assessment
Design of facilities as presented corresponds to the Project design to be used. Should
there be any design changes, they shall not significantly impact the project
requirements.
There are no conflicts in the use of marine areas between QPRGG, the government
and the communities located in the vicinity of Tema.
This evaluation does not disqualify some of the alternatives proposed for the
establishment of infrastructure since it is only a relative comparison of areas under
technical, economic, environmental and socio-cultural criteria based on the LNG
Terminal specific requirements.
The environmental and social conditions for this study are representative of the area
and, therefore, they have been considered as the basis for the analysis of alternatives.
4.3.3 Alternatives and Facilities Included in the Analysis
Determination of the location of the LNG Terminal will take into account the components
within the maritime area which were mentioned in Section 4.3 including: i) FSRU,
ii) Offshore mooring and support for floating units, and iii) Subsea gas pipeline. As
previously mentioned, location of the land facilities will not be evaluated.
As a result, the scope of the alternative assessment will involve the determination of the
optimal location of the FSRU and mooring, including the configuration of the gas pipeline.
Location of this infrastructure was evaluated in the following zones:
Alternative 1: Point 1 (up to 20 m deep).
Alternative 2: Point 3 (up to 40 m deep).
Figure 4-1 shows the location of Alternatives 1 and 2.
Quantum Power Ghana Gas Limited 4-5 Knight Piésold Consulting
Environmental and Social Impact Assessment
Figure 4-1: The proposed offshore localities of the mooring facilities
Below is the analysis of the technical, environmental, and socio-cultural implications of the
infrastructure location presented in these two alternatives, including a brief description of
their main characteristics.
4.3.3.1 Alternative 1: P1 (~ 20 m deep)
Location: The referential location proposed in Alternative 1 corresponds to the coordinates
165 088m E and 618 839m N (UTM 31N WGS84), at a distance of approximately 4.2 km
from the coast of the Gulf of Guinea. The zone reaches a depth of approximately 20 m.
Additionally, the distance between P1 and the port of Tema is approximately 4.8 km.
Technical Aspects: The subsea gas pipeline will require approximately 5 km piping of 24-
inch over the seabed for the transport of regasified LNG from the offshore facility (FSRU) to
the coast, close to Tema city.
Environmental Aspects: As previously mentioned, Alternative 1 is located in the marine
area. For this reason, the environmental aspects of greater importance are those associated
with oceanographic conditions including the wind behaviour, which is prioritized in the wind
and wave analysis. Winds in the zone are predominately in the southwest direction.
Approximately, 1.9% of waves have a height exceeding 2.5 m. Peak wave periods longer
than 12 s occur approximately 38% of the time. Waves with heights greater than 2 m with
periods longer than 12 s occur approximately 4.8% of the time.
Social Aspects: The communities that could be affected in the land area are the following:
the Tema Metropolis District, the Kpone Katamanso District, and the Ningo Prampram
Quantum Power Ghana Gas Limited 4-6 Knight Piésold Consulting
Environmental and Social Impact Assessment
District. Of these, the District of Tema, specifically the capital city of Tema, would be
considered the main area of influence.
The local economy of Tema is comprised of agriculture, industry, and commerce/services.
However, the industrial and service sectors constitute the backbone of the local economy,
as they employ the majority of the workforce. Additionally, a part of the population works in
agriculture and fishing. Furthermore, Tema has commercial and fishing ports; the latter is
the larger of the two seaports in Ghana.
The area of direct influence of the project includes the maritime area of the project
infrastructure location, including the gas pipeline. It is probable that the project
implementation will involve interaction with the maritime activities that are developed in the
area. It is important to emphasize that the distance between P1 and the port is 4.8 km.
4.3.3.2 Alternative 2: P3 (~ 40 m deep)
Location: The location proposed by Alternative 2 corresponds to the following coordinates:
P3 174 247 m E and 622 816 m (UTM 31N WGS84), at a distance of approximately 5.45 km
from Alternative 1 (SE direction) and 9.2 km from the coast. In addition, the distance
between P3 and the Tema port is approximately 9.5 km.
Technical Aspects: The subsea gas pipeline will require 10 km piping of 24-inch over the
seabed for the transport of regasified LNG from the offshore facility (FSRU) to the coast,
close to Tema.
Environmental Aspects: Similar to Alternative 1, Alternative 2 is also located in the marine
area. The winds in the zone are predominately in the southwest direction. Approximately
1.3% of waves have a height exceeding 2.5 m. Peak wave periods longer than 12 s occur
approximately 33% of the time. Waves with heights greater than 2 m with periods longer
than 12 s occur approximately 2.2% of the time.
Social Aspects: The coastal area of influence for Alternative 2 (P3) is the same as
Alternative 1. The city of Tema is the main area within the zone.
Similarly, the area of direct influence of the project corresponds to the maritime area of the
project infrastructure location, including the gas pipeline. It should be emphasised that the
distance between P3 and the port is 9.5 km.
4.3.4 Comparing Location Alternatives
The following is a comparison of the technical, economic, environmental, and socio-cultural
aspects of Alternatives 1 & 2.
4.3.4.1 Technical-Economic Aspects
With regard to technical aspects, Alternative 1 was more optimal mainly due to the shallower
zone depth which provides greater advantages regarding the infrastructure location. It also
requires less piping and, therefore, a shorter construction, installation and work time. By
contrast, Alternative 2 has a more profound depth and requires a larger number of works
due to the greater length of piping.
Quantum Power Ghana Gas Limited 4-7 Knight Piésold Consulting
Environmental and Social Impact Assessment
The distance to the port of Tema also involves advantages with respect to the transportation
of personnel, materials, and inputs. As such, Alternative 1 (located at an approximate
distance of 4.8 km) is more beneficial than Alternative 2, which requires greater time and
transport distances (P3 is found at an approximate distance of 9.3 km from the port).
On the other hand, a greater depth facilitates the manoeuvring of oceangoing vessels. For
that reason, Alternative 2 would be more beneficial due to its greater depth.
In general terms, these results allow for reaching a preliminary conclusion that technically,
Alternative 1 has more advantages in relative terms when compared to Alternative 2.
However, Alternative 2 also presents conditions that could be advantageous. Finally, if an
economic comparison is performed, Alternative 2 would require greater investment than
Alternative 1.
4.3.4.2 Environmental Aspects
In regards to environmental aspects, both alternative 1 and alternative 2 have similar
climatic ratings.
In relation to waves, Alternative 2 could be more beneficial as there is a lesser frequency of
waves with a height greater than 2 and 2.5 m, which facilitates the manoeuvring for
operations as well as transportation and construction. It would also support construction and
engineering works, and better wave conditions would result in fewer environmental risks (for
example, spills).
Consequently, Alternative 2 presents fewer complications in terms of environmental
management due to the nature of the site.
4.3.4.3 Social Aspects
With regard to social aspects, Alternative 1 presents fewer advantages due to its proximity
to the commercial and fishing ports, involving potential interference with fishing and
commercial vessels which could generate, among other issues, expectations in the
fishermen population or the risk of interference with fishing and commercial vessel routes.
From the perspective of the landscape, Alternative 1 is visually accessible so its impact
would be greater in comparison to Alternative 2, taking into account that the distance of
Alternative 1 to the coast is around 4.2 km. Alternative 2 represents the less complex option
for managing social impacts due to its remoteness from the coast and port.
4.3.4.4 Final Balance
Table 4-2 presents the alternative analysis matrix for the location of the LNG Terminal. The
two proposed alternatives were compared based on the results of the analysis of the
technical-economic, environmental, and social aspects under consideration. Table 4-1
presents a summary of the results obtained, based on the calculation of the assigned values
and weights presented in Section 4.3.1.
Quantum Power Ghana Gas Limited 4-8 Knight Piésold Consulting
Environmental and Social Impact Assessment
Table 4-1: Summary of Alternative Ratings
Considerations Alternative 1 Alternative 2
P1 P3
Technical – Economic Aspects 4.5 3.8
Environmental Aspects 4.0 6.0
Social Aspects 8.0 12
Accumulative Total 16.5 21.8
According to these results, Alternative 2 is the best choice for the LNG Terminal location, as
it has a relatively higher score than Alternative 1. This analysis consisted of a process in
which the two areas were relatively compared according to technical, environmental and
social criteria.
Quantum Power Ghana Gas Limited 4-9 Knight Piésold Consulting
Environmental and Social Impact Assessment
Table 4-2: LNG Terminal Location Alternative Analysis
Considerations Alternative 1
P1 Alternative 2
P3
Counting Counting Weighting
Sub-counting Indicator Indicator
Weighting Value Description Value Description
Technical & Economic Aspects
0.8
Closeness to Solid Ground
Distance to coastline 3 3 Distance: 4.2 km
approx. 2
Distance: 9.2 km approx.
Sub-counting Value
9
6
Closeness to Tema port
Distance to port 4 3 Distance: 4.8 km
approx. 2
Distance: 9.5 km approx.
Sub-counting Value
12
8
Underwater Pipeline
Requirement
Pipe Length: 24’’ 4 4 Length: 5 km
approx.. 2
Length: 12km approx.
Sub-counting Value
16
8
Vessel Manoeuvrabil
ity
Depth of the alternative 4 2 20 m 4 40 m
Sub-counting Value
8
16
Counting Value
45
38
Weighted Counting
4.5
3.8
Quantum Power Ghana Gas Limited 4-10 Knight Piésold Consulting
Environmental and Social Impact Assessment
Considerations Alternative 1
P1 Alternative 2
P3
Counting Counting Weighting
Sub-counting Indicator Indicator
Weighting Value Description Value Description
Environmental Aspects
1
Wave Condition
Frequency of waves higher than 2 and 2.5 m
4 2 Higher frequency 3 Lower frequency
Sub-counting Value
8
12
Counting Value
8
12
Weighted Counting
4
6
Social Aspects
1
Interference with Small-
Scale Fishing Activities &
Minor Vessel Traffic
Distance to the small-scale fishing Tema port
4 2
Distance: 4.8 km approx., which increases interference potential
3
Distance: 9.5 km approx., with a lower interference potential
Sub-counting Value 8
12
Interference with
Commercial port activities
Distance to the small-scale fishing Tema port
4 2
Distance: 4.8 km approx., which increases interference potential
3 Distance: 9.5 km approx., with a lower interference potential
Sub-counting Value
8
12
Counting Value 16 24
Weighted Counting 8 12
Cumulative Total 16.5
21.8
Quantum Power Ghana Gas Limited 4-11 Knight Piésold Consulting
Environmental and Social Impact Assessment
4.4 LNG TERMINALCONFIGURATION ALTERNATIVES
An uptime assessment was undertaken to consider three options for the LNG terminal
configuration.Three mooring types were then analysed with regard to uptime (average annual %
time that facility could be operational, undisturbed by ocean conditions and there is gas demand
and gas is exported) for each of the remaining localities. These include;
Option 1: FSRU on soft yoke mooring.
Option 2: FSRU and LNGC on double berth jetty.
Option 3: FSRU on spread moor and LNGC on single berth jetty.
4.4.1 Option 1: FSRU on Soft Yoke Mooring
This configuration is based on an FSRU with a soft yoke mooring system. The system is used in
shallow water and the soft yoke provides softness in the mooring system – this reduces the
loads on the mooring tower from wave action on the FSRU. A typical mooring layout is shown in
Figure 4-2. The soft yoke mooring system comprises the following components:
A soft yoke structure attached to the FSRU which provides restoring forces to “move” the
FSRU back to its equilibrium position.
A mooring tower connected to the soft yoke structure on the FSRU. The mooring tower
essentially holds the FSRU on site and allows the FSRU to weathervane to the prevailing
weather conditions (compliant system), in particular the wind conditions.
The interface between the mooring tower and soft yoke structure comprises of swivel bearings
and high pressure gas swivels. The vaporised natural gas travels from the FSRU through gas
piping, high pressure gas swivels, piping on the mooring tower towards the subsea pipeline to
shore.
The soft yoke mooring system permanently moors the FSRU on site and is not designed to be
disconnected on a regular basis. The LNG is transferred onto the FSRU using side-by-side
offloading; in this scenario, the LNGC berths alongside the FSRU and LNG transfer is carried
out using loading arms on the FSRU. The pros for this option are:
Higher gas availability due to permanently moored FSRU and gas export equipment as a
part of the soft yoke mooring tower.
Cost and schedule effective mooring system, no mooring dolphins or piles.
Weathervaning (compliant) mooring system.
Needs to be in around 18m to 40m water depth (works for both considered site locations)
The cons for this option are:
Requires side-by-side offloading operations to transfer LNG from LNGCs to FSRU.
Quantum Power Ghana Gas Limited 4-12 Knight Piésold Consulting
Environmental and Social Impact Assessment
Soft yoke mooring tower needs careful design to avoid mooring tower overrun and is
typically limited to around Hs=5m 100 year return condition and around 30 m/s wind and
2knots of current.
Figure 4-2: FSRU on Soft Yoke Mooring
4.4.2 Option2: FSRU and LNGC on Double Berth Jetty
The double berth jetty mooring system is oriented to be aligned with the predominant swell
direction (i.e. N to S orientation) with the FSRU/LNGC bows towards the South. FSRU is
berthed on the west side of the Jetty and the LNGC is berthed on the east side. This mooring
layout is shown in Figure 4-3. The jetty includes mooring/fendering structures to moor the FSRU
and LNGC, loading arms for LNG transfers from the LNGC to the FSRU. High pressure loading
arm(s), also on the jetty, transfer natural gas from the regasification unit on the FSRU to the
jetty; the gas then flows in a riser down the jetty substructure to a subsea PLEM, and via
subsea pipeline to shore.
LNG is transferred from the LNGC to the FSRU via low pressure loading arms and piping on the
platform. A separate set of high pressure loading arms and piping then transfers the vaporised
gas from the FSRU to the jetty, and into a subsea pipeline to shore.
The jetty mooring system is a disconnectable mooring system. The FSRU will need to
disconnect and sail to safety during extreme weather events.
The pros for this option are:
Utilises standard jetty for LNGC berthing and offloading and therefore allows any LNG
supplier to use the terminal.
The cons for this option are:
Lower gas availability due to disconnectable FSRU.
Not cost and schedule effective mooring system; requires mooring dolphins and piles.
Needs to be in 15m to 20m water depth.
Quantum Power Ghana Gas Limited 4-13 Knight Piésold Consulting
Environmental and Social Impact Assessment
Figure 4-3: FSRU and LNGC on Double Berth Jetty
4.4.3 Option 3: FSRU on Spread Moor and LNGC on Single Berth Jetty
After initial consideration, it was decided to add a third option to the previous two. This option
consists of a FSRU permanently moored with a spread mooring system in the close proximity
and parallel to the single berth jetty where LNGC is berthed to perform LNG offloading. Both the
single berth jetty and the spread mooring systems are oriented to be aligned with the swell (i.e.
N to S orientation) with the FSRU/LNGC bows towards the South. The FSRU on spread moor is
positioned west of the single berth jetty. This mooring layout is shown in Figure 4-4.
LNG is transferred from LNGC to jetty via loading arms and from jetty to FSRU via LNG aerial
hoses (as proposed by Hoegh and Excellerate for a Canadian FLNG terminal).
High Pressure (HP) gas is transferred from FSRU to jetty via HP hoses, then down the jetty
substructure to a subsea PLEM, and via subsea pipeline to shore, as used for the West Java
FSRU.
The pros for this option are:
Higher gas availability than double berth jetty due to permanently moored FSRU.
Utilizes standard jetty for LNGC berthing and offloading and therefore allows any LNG
supplier to use the terminal.
Cost and schedule effective mooring system, by minimising mooring dolphins and piles.
The cons for this option are:
Only works in highly directional met-ocean condition as encountered offshore Ghana and
Nigeria, etc.
Needs to be in around 21m to 28m or better 40m water depth (i.e. long piles for jetty) to
avoid clashing of spread mooring lines with moored LNGC and during berthing of LNGC.
Quantum Power Ghana Gas Limited 4-14 Knight Piésold Consulting
Environmental and Social Impact Assessment
Requires LNG and HP hose transfer via aerial hoses to span approximately 30m to a jetty
platform, the latter all technologies are available and have been used in similar conditions.
However, in a permanently moored application, lifecycle costing requires assessment due
to frequent replacement of LNG hoses.
A spread mooring in close vicinity of a platform requires careful design and analysis to
avoid clashing with infrastructure and is limited to around Hs=5m 100 year return condition
and around1.5knot of current.
Figure 4-4: FSRU on Spread Moor and LNGC on Single Berth Jetty
Based on the LNG Terminal Configuration Assessment, Option 3: FSRU on spread moor and
LNGC on single Berth Jetty was selected as the base case for the Tema LNG project.
4.5 OFFSHORE PIPELINE ROUTE ALTERNATIVES
Pipeline route alternatives were identified and evaluated to determine whether or not alternative
alignments could avoid or reduce the impacts identified. The Pipeline Route Alternatives are
based on specific design data and routing restrictions mentioned in Chapter 2 (Project
Description). Three route options were discussed with Option 1 selected as the base case for
the FEED stage. The various options are described in the sections below, with their pros and
cons presented in Table 4-3.
4.5.1 Option 1 (Base Case)
This option considers the FSRU to be located inside the exclusion zone on the east side of the
WAGP pipeline as illustrated in Figure 4-5. PLEM is located on the eastside of the FSRU; a tie-
in spool approximately 100m in length connects the PLEM to the import pipeline.
From the spool tie-in (KP 0) the import pipeline routes north towards the corridor of exclusion
zone. The FSRU mooring anchors are located near the exclusion zone having a minimum of
50m exclusion zone at each anchor location. To avoid crossing the exclusion zone around
anchors the import pipeline is routed outside the fishing and anchoring exclusion zone before
Quantum Power Ghana Gas Limited 4-15 Knight Piésold Consulting
Environmental and Social Impact Assessment
routing back inside the corridor. A pipeline lay radius of 800m is considered while routing which
will allow minimum pipeline outside the exclusion zone. A total of 525m length of import pipeline
falls outside the exclusion zone and extends out of exclusion zone by 43m.
The import pipeline once inside the exclusion zone routes north-west towards the WAGP
pipeline. At approximately KP 5.6 it curves around the existing SPM exclusion zone to align for
landfall tie-in point. The pipeline route maintains a minimum 50m separation between WAGP
pipeline from approximately KP 10 to landfall tie-in section which is required to be trenched and
backfilled.
Figure 4-5: Import Pipeline Route – Option 1 (Base Case)
Quantum Power Ghana Gas Limited 4-16 Knight Piésold Consulting
Environmental and Social Impact Assessment
4.5.2 Option 2
This option considers the FSRU to be located inside the exclusion zone on the east side of the
WAGP pipeline. PLEM is located on the eastside of the FSRU on seabed, a tie-in spool
approximately 100m in length connects the PLEM to the import pipeline.
From the spool tie-in (KP 0) the import pipeline routes under the FSRU and runs north-west
towards the WAGP pipeline. Around the existing SPM exclusion zone the pipeline curves to
align for landfall tie-in point as shown in Figure 4-6.
Figure 4-6: Import Pipeline Route – Option 2
Quantum Power Ghana Gas Limited 4-17 Knight Piésold Consulting
Environmental and Social Impact Assessment
4.5.3 Option 3
This option considers the FSRU to be located inside the exclusion zone on the west side of the
WAGP pipeline. PLEM is located on the eastside of the FSRU on seabed; a tie-in spool
approximately 100m in length connects the PLEM to the import pipeline.
From the spool tie-in (KP 0) the import pipeline routes north east and crosses the WAGP
pipeline. The import pipeline then curves 90 degree and aligns to reach the landfall tie-in
location as a straight route (see Figure 4-7).
Figure 4-7: Import Pipeline Route – Option 3
Quantum Power Ghana Gas Limited 4-18 Knight Piésold Consulting
Environmental and Social Impact Assessment
Table 4-3: Route Options (Pros and Cons)
ROUTE OPTIONS PROS CONS
Option 1 (Base Case)
FSRU moored bow to south on the east side of
WAGP with riser hang offs on right side.
Preferred arrangement for LNG offloading
Pipeline not entirely within WAGP exclusion zone
No crossing of WAGP pipeline Additional pipeline protection [outside WAGP
exclusion zone required]
Route Option 2
FSRU moored bow to south on the east side of
WAGP with riser hang offs on right side. And the
pipeline is routed under the FSRU to route it on
seabed on other side of FSRU. PLEM is located
on right side of FSRU.
Offshore import pipeline routing is simple and
straight route almost parallel to existing WAGP
pipeline.
Routing the pipeline under FSRU would have
highest risk to safety of FSRU in an event of
pipeline damage.
Not preferred by FSRU Operator.
Pipeline lengths would be reduced.
Supply vessels will be operating directly above
the pipeline route.
No need to extend the existing WAGP exclusion
zone.
Independent HAZID and HAZOP will need to be
carried out to assess the risks associated before
this option could be confirmed as acceptable.
-
Additional protection of the pipeline under FSRU
would be required.
- Pipeline must be installed before FSRU on station
Quantum Power Ghana Gas Limited 4-19 Knight Piésold Consulting
Environmental and Social Impact Assessment
Route Option 3
FSRU to be located on the west side of the
WAGP pipeline at about 40m WD contour.
May be able to route the pipeline inside the
exclusion zone.
Import pipeline will need to cross over existing
WAGP pipeline.
- Longer length of pipeline.
-
Supply vessels will need to ferry on top of the
WAGP pipeline.
Quantum Power Ghana Gas Limited 4-20 Knight Piésold Consulting
Environmental and Social Impact Assessment
Option 2 has a direct safety risk to FSRU and hence is not considered viable. Option 3 will need
to cross over existing WAGP pipeline and will also have supply vessels ferrying over both
WAGP and import pipeline routes subsea, and hence is not carried forward at this stage.
Option 1 has the benefit of being away from all existing subsea assets. It also allows favourable
mooring of delivery vessels to FSRU. From the above assertions, Option 1 is selected as a
base case at the FEED stage. But a further review of the exclusion zone co-ordinates and as-
built position of the existing WAGP pipeline should be carried out to confirm the Option 1 route.
4.6 PIPELINE INSTALLATION METHOD ALTERNATIVES
The Tema LNG project design considers five basic methods to install the landfall pipeline, with
option 1 as the preferred case. These installation methods with their advantages and
disadvantages are also presented in Table 4-4.
1. Fabricate pipeline on lay vessel stationed offshore and pull the pipeline ashore using
winches installed at beach head;
2. Pipelay vessel stationed offshore with return sheath anchored at beach head; pipeline
fabrication on lay vessel and winched ashore by return pull-in wire using A&R or anchor
winch located on the pipelay vessel;
3. Fabricate pipeline onshore either in strings or as a single length and pull offshore using
winches installed on a pulling barge; and
4. Directional horizontal drilling (HDD)
5. Tunnel and Shaft (Microtunneling or Pipe Jacking).
4.6.1 Pull Pipeline Ashore from Pipelay Vessel (Preferred Case)
An onshore pull method requires the installation of an onshore winch spread to facilitate pulling
a pipe-string to the beach from a pipelay vessel which would be positioned offshore.
This is the proposed method for the successful installation of the Quantum gas pipeline and is
discussed in more detail in Section 2.5.5 (Proposed landfall construction & pipe installation
method).
4.6.2 Pull Ashore Using Onshore Return Sheave
This method is similar to the above installation except the pulling winch setup is located on the
pipelay vessel with a sheave block anchored onshore. Once the lay vessel is in position
offshore the pull wire will be run from the lay vessel and passed around the onshore return
sheave and then run back to the lay vessel for attachment to the pulling head of the pipeline.
The vessel will then commence a conventional pipelay installation with winch pulling the pipe off
the lay vessel as the welding of each pipe section is completed.
The sheave block should be capable of sustaining double the load of the beach anchor.
4.6.3 Fabricated Pipeline Onshore
This scheme requires the pipeline to be fabricated onshore either as a continuous pipe-string or
as a number of short pipe-strings and a pulling vessel/lay barge will be setup offshore.
Quantum Power Ghana Gas Limited 4-21 Knight Piésold Consulting
Environmental and Social Impact Assessment
The continuous pipe-string method may only be used if the construction site is sufficiently long
so that the pipe-string maybe fabricated in one length on level ground and supported on rollers.
A pipe launch ramp along the route of the pipeline would be constructed down to the shoreline.
A winch will be located at the rear of the pipe-string in line with the launch ramp to act as a
control brake during pulling operations. Once the pulling vessel is in position offshore a pull wire
will be run from the vessel to shore where it will be attached to the pull head of the pipeline. The
vessel mounted winch will pull the pipe-string offshore to a defined point and leave it on the
seabed with a marker buoy attached to the pullhead. After the pulling vessel has been de-
mobilised, a pipelay vessel will retrieve the pullhead from the seabed and pipe layaway
operations shall commence.
Alternatively, a short pipe-string method can be used; it is very similar to the method described
above except in this case the pulling sequence is carried out multiple times depending on
workspace for string lengths.
4.6.4 Directional Drilling
The method uses a drill rig that drills a hole at a very shallow angle to the horizontal. A pilot hole
is drilled in the first instance with a rig situated on either land or a vessel. More common is to
have the rig on land and to punch out of the seabed reducing vessel costs. The formation is
then typically reamed with a hole opener to achieve the size hole required. For small diameter
pipelines reaming is often not required and the required size can be achieved with the pilot drill.
The formation is stabilized during drilling operations with bentonite clay slurry, which is pumped
down the hole from the rig site.
The pipeline may then be pulled back through the hole from an offshore barge or pushed
through by feeding the pipe string into the formation. A pipelay vessel will retrieve the end of the
pipeline from the seabed and pipe layaway operations commence.
Installation requires pipelines to be coated with a durable anti-corrosion coating such as
polypropylene or similar to avoid damage during pull back as there is no requirement for
concrete weight coating.
For a directional drilling operation, a detailed ground investigation will be required to ensure that
the ground conditions are suitable in order that the drill hole will remain open and the ground
has sufficient strength to prevent a bentonite blow-out. The ground conditions best suited to the
technique are clean clays and alluvial deposits (e.g. silty sand). The presence of gravel, cobbles
or boulders within clay creates difficulties whilst gravel or cobble strata render the technique
unfeasible. Drilling fluid is not really suited for the stabilisation of large cohesionless materials
due to loss of fluid pressure.
4.6.5 Tunnel and Shaft Construction (Microtunneling or Pipe Jacking)
Microtunneling is an underground method of constructing pipelines using a sophisticated,
remotely controlled, laser guided, steerable boring machine. It utilizes remotely controlled
equipment that does not require personnel to work underground.
Pipe jacking involves installing a pipeline by pushing pipe sections through the ground with
hydraulic jacks assembled in a jacking frame located in a shaft excavation called the jacking pit.
Quantum Power Ghana Gas Limited 4-22 Knight Piésold Consulting
Environmental and Social Impact Assessment
Pipe jacking also involves the machine operator and other personnel to perform much of the
work at the tunnel heading and inside the pipe string.
Excavation is carried out using a microtunneling machine in front of the lead pipe section as the
pipeline is pushed forward from the jacking pit. After pushing a full pipe section into the ground,
a new pipe section is lowered into the jacking pit with a crane and connected to the previous
pipe section and the process is repeated until the machine reaches the receiving pit.
4.6.5.1 Shaft Construction
The shaft can be installed as a caisson or built in-situ by under pinning, or by other methods.
The top of the shaft can be located a safe distance back from the top of the cliff to allow for its
construction and for any projected future erosion of the cliff. The shaft diameter should be of
sufficient diameter to provide access for construction of the horizontal tunnel out to the beach
and constructing the pipeline. Typically, a shaft diameter of 5m is necessary for access of
personnel and equipment. All spoil will be placed in a stockpile within the working area.
Stockpiled material will be subsequently removed on a regular basis to minimise on-site storage
areas. If material is suitable then it may be dumped on the foreshore, but any spoil that maybe
contaminated due to construction works will be disposed of at approved disposal sites.
Upon completion of the shaft construction a reinforced concrete base slab will be cast in-situ to
seal the bottom of the shaft to prevent the ingress of water.
4.6.5.2 Tunnel Construction
At the base of the shaft a thrust pit will be established and the tunnels pipe-jacked towards the
beach. As the tunnel face is excavated the tunnel lining rings will be installed at the shaft base
and jacked forward on the required alignment. The tunnels will be driven towards the beach and
any groundwater will be pumped to the top of the shaft for disposal. The water shall be
disposed by filtering it through a soak away; however, if the water is contaminated then it will be
collected and transported to a licensed disposal site.
The disposal of spoil from the tunnels shall be treated in the same manner as per the spoil from
the shaft.
At the beach, the tunnels will be driven into the tunnel reception pit / cofferdam.
Quantum Power Ghana Gas Limited 4-23 Knight Piésold Consulting
Environmental and Social Impact Assessment
Figure 4-8: TBM Located in Thrust Shaft
Quantum Power Ghana Gas Limited 4-24 Knight Piésold Consulting
Environmental and Social Impact Assessment
Table 4-4: Advantages and Disadvantages of Various Pipeline Installation Methods
METHOD TYPE
SCHEME ADVANTAGES DISADVANTAGES
1 Pull Pipeline Ashore From Pipelay Vessel
Most common construction method using pull
winch(s).
Winch set-up onshore
Pipe joints transported directly to lay vessel
Small land-take for construction
Short pull length
Pipeline layaway operations would commence once
pipeline has been landed ashore and made secure
Pulling operation requires several days window
due to the welding of pipe joints on lay vessel.
Risk of weather deterioration can also delay
operations.
Large pull force may result in complicated winch
set up onshore.
Addition and removal of buoyancy aids, if used
Reduced on-bottom stability of pipeline for
period of installation.
Volume of dredging to accommodate pipelay
vessel access can be a problem
2 Pull Ashore Using Onshore Return Sheave
Winch set-up on pipelay vessel
Pipe joints transported directly to lay vessel
Simple set up of sheaved anchor onshore
Pull operation controlled on lay vessel
Pipeline layaway operations would commence once
pipeline has been landed ashore and made secure
Same as method 1 above
3 Fabricated Pipeline Onshore
Fabrication of pipe-string can be completed before
arrival of lay vessel
Pre-test fabricated pipe-strings.
Once pipeline has been installed pipeline layaway
Pipe joints have to be transported to onshore
construction site
Delay in pulling operation due to phased
addition of pipe-spool wielding to form pipe
Quantum Power Ghana Gas Limited 4-25 Knight Piésold Consulting
Environmental and Social Impact Assessment
METHOD TYPE
SCHEME ADVANTAGES DISADVANTAGES
operations would commence string
Onshore temporary works
Open trench has to remain open for long period
Tow operation can be a risk
Buoyancy and control aids required for tow
operation
Detailed survey of tow route required
Finding suitable site for fabrication of pipe-
spools
4 Directional Horizontal Drilling
Limited disturbance to surface and nearby
infrastructure
Concrete weight coating not required
Inshore trenching not required
Drill paths can be constructed with a wide fanned
arrangement from beach
If the ground is not self-supporting a drift hole
may collapse
Risk of frac out / bentonite break out
Presence of large cobble/rock may make this
option unfeasible
Drilling normally suited to clay soils.
5 Tunneling
Concrete weight coating not required
Inshore trenching not required
Buoyancy and control aids not required
May not be cost effective
Quantum Power Ghana Gas Limited 4-26 Knight Piésold Consulting
Environmental and Social Impact Assessment
4.7 LNG VAPORISATION TECHNOLOGY ALTERNATIVES
As described in Section 2, LNG must be warmed from a liquid to a gaseous state (vaporised)
before it can be transported as natural gas in the send-out pipeline. A number of technologies
for vaporising LNG were evaluated. The focus on conceptual selection was on using seawater
or air as the “cold sinks” rather than combustion gases as these technologies have proven to be
more simple and can be applied to both floating and fixed storage and re-gasification systems.
The analysis for various vaporisation technologies were based on studies conducted by Patel et
al., 2013,regarding LNG vaporiser selection at locations where site ambient conditions are
warmer (i.e. above 18 oC).
Typical types of vaporisers that have been used worldwide for LNG regasification are:
Open Rack Vaporisers (ORV)
Submerged Combustion Vaporisers (SCV)
Ambient Air Vaporisers (AAV)
Intermediate Fluid Vaporisers (IFV)
Open rack vaporisers (ORV) and submerged combustion vaporisers (SCV) are the most
common vaporisation methods in existing regasification terminals, which have generally been
located in the subequatorial region. Recent LNG receiving terminal activities have been shifting
to the tropical/equatorial region where the weather is warmer, and the use of intermediate fluid
vaporisers (IFV) is found to be attractive. Important factors that should be considered in the
LNG vapouriser selection process are:
Site conditions and plant location
Availability and reliability of the heat source
Customer demand fluctuation
Emission permit limits
Regulatory restrictions with respect to the use of seawater
Vaporiser capacity and operating parameters
Safety in design
Operating flexibility and reliability
Capital and the operating cost.
4.7.1 Seawater (SW) Heating
LNG receiving terminals are generally located close to the open sea for ease of access to LNG
carriers. Seawater is generally available in large quantities at low cost as compared to other
sources of heat, and is the preferred heat source. The opposition is mainly from the
Quantum Power Ghana Gas Limited 4-27 Knight Piésold Consulting
Environmental and Social Impact Assessment
environmental sensitive regions for the concerns on the negative impacts on marine life due to
the cold seawater discharge and the residual chemical contents.
Open Rack Vaporiser (ORV)
An Open Rack Vaporiser (ORV) is a heat exchanger that uses seawater as the source of heat.
ORVs are well proven technology and have been widely used in Japan, Korea and Europe LNG
terminals. The preferred seawater temperature for ORV operation is above 5°C.
ORV units are generally constructed of aluminum alloy for mechanical strength suitable to
operate at the cryogenic temperature. The material has high thermal conductivity which is
effective for heat transfer equipment. The tubes are arranged in panels, connected through the
LNG inlet and the regasified product outlet piping manifolds and hung from a rack (Figure 4-9).
ORVs require regular maintenance to keep the finned tube surface clean.
The panel arrangement feature provides ease of access for maintenance. Depending on the
design of the units, it is also possible to isolate sections of the panels and vary the load on the
units. The unit can be turned down to accommodate fluctuations in gas demand, gas outlet
temperature and seawater temperature.
Figure 4-9: Open Rack Vaporiser Flow Scheme
4.7.2 Fuel Gas (FG) Heating
LNG vaporisation using fuel gas for heating typically consumes approximately 1.5 % of the
vaporised LNG as fuel, which reduces the plant output and the revenue of the terminal.
Because of the high price of LNG, SCVs are sometimes used during winter months to
supplement ORV, when seawater temperature cannot meet the regasification requirement.
They can also be used to provide the flexibility in meeting peaking demands during cold
seasons. The SCV burners can be designed to burn low pressure boil-off gas as well as
letdown send-out gas.
Submerged Combustion Vaporisers (SCV)
Quantum Power Ghana Gas Limited 4-28 Knight Piésold Consulting
Environmental and Social Impact Assessment
A typical SCV system is shown in Figure 4-10. LNG flows through a stainless steel tube coil that
is submerged in a water bath which is heated by direct contact with hot flue gases from a
submerged gas burner.
Since the water bath is always maintained at a constant temperature and has high thermal
capacity, the system copes very well with sudden load changes and can be quickly started up
and shutdown.
The bath water is acidic as the combustion gas products (CO2) are condensed in the water.
Caustic chemical such as sodium carbonate and sodium bicarbonate can be added to the bath
water to control the pH value and to protect the tubes against corrosion. The excess
combustion water must be neutralized before being discharged to the open water.
To minimize the NOx emissions, low NOx burners can be used to meet the 40 ppm NOx limit.
The NOx level can be further reduced by using a Selective Catalytic Reduction (SCR) system to
meet the 5 ppm specification if more stringent emission requirements are needed, at a
significant cost impact.
SCV units are proven equipment and are very reliable and have very good safety records.
Leakage of gas can be quickly detected by hydrocarbon detectors which will result in a plant
shutdown. There is no danger of explosion, due to the fact that the temperature of the water
bath always stays below the ignition point of natural gas.
SCVs are compact and do not require much plot area when compared to the other vapouriser
options.
Figure 4-10: Submerged Combustion Vaporiser
4.7.3 Ambient Air Heating
Air is another source of "free" heat and would avoid the use of fuel gas and the generation of
greenhouse gas from SCVs. In the environmental sensitive parts of the world, the use of sea
water may not be allowed and could also be difficult to permit. In this case, the use of ambient
air heat is the next best choice.
Quantum Power Ghana Gas Limited 4-29 Knight Piésold Consulting
Environmental and Social Impact Assessment
Ambient Air Vaporisers (AAV)
Direct ambient air vaporisers are used in cryogenic services, such as in air separation plants.
They are vertical heat exchanger and are designed for icing on the tube side and require
defrosting. Automatic switching valves are installed to allow automatic defrosting using timers.
When compared to other vapouriser options, they require more vapouriser units and more real
estate.
A typical AAV design configuration is shown in Figure 4-11. AAV consists of direct contact, long,
vertical heat exchange tubes that facilitate downward air draft. This is due to the warmer less
dense air at the top being lighter than the cold denser air at the bottom. Water condensation
and melting ice can also be collected and used as a source of service/potable water.
To avoid dense ice buildup on the surface of the heat exchanger tubes, deicing or defrosting
with a 4-8 hour cycle is typically required. Defrosting requires the exchanger to be placed on a
standby mode, and can be completed by natural draft convection or force draft air fans.
Fog around the vapouriser areas can pose a visibility problem, which is generated by
condensation of the moist air outside. The extent of fog formation depends on many factors,
such as the separation distances among units, wind conditions, relative humidity and ambient
temperatures.
Ambient air heater is advantageous in hot climate equatorial regions where ambient
temperature is high all year round. In the cooler subequatorial areas, where winter temperature
is lower, supplementary heating may be required to meet the sales gas temperature.
Figure 4-11: Typical Ambient Air Vaporiser
Quantum Power Ghana Gas Limited 4-30 Knight Piésold Consulting
Environmental and Social Impact Assessment
4.7.4 Intermediate Fluid Heating
This LNG vaporising via intermediate fluid utilizes Heat Transfer Fluid (HTF) in a closed loop to
transfer heat to vapourise LNG. Three types of Heat Transfer Fluids are typically utilised for
LNG vapourisation:
Glycol-Water
Hydrocarbon Based HTF (Propane, Butane or Mixed Refrigerant)
Hot Water
Glycol-water Intermediate Fluid Vaporiser (IFV)
This system typically uses glycol-water as an intermediate heat transfer fluid. Ethylene glycol or
propylene glycol or other low freezing heat transfer fluids are suitable for this application. Heat
transfer for LNG vaporisation occurs in a shell and tube exchanger. Warm glycol-water flows
through the intermediate fluid vaporisers where it rejects heat to vapourise LNG.
A simplified process sketch of these various heating options is shown in Figure 4-12.
Currently, glycol-water intermediate fluid LNG vaporisers account for a small fraction (around
5%) of total LNG regasification markets worldwide. Some of the operating plants utilize air
heater and reverse cooling tower as the source of heat.
There are several options to warm the glycol-water solution prior to recycling it back into the
shell and tube LNG vaporisers, such as:
Air heater
Reverse cooling tower
Seawater heater
Waste heat recovery system or fired heater.
Using air for heating will generate water condensate, especially in the equatorial regions. The
water condensate is of rain water quality which can be collected and purified for in-plant water
usage and/or export as fresh raw water. Similarly, the reverse cooling tower design, which
extracts ambient heat by direct contact with cooling water via sensible heat and water
condensation, would require an intermediate fluid. The heat of the cooling water can be
transferred to the intermediate fluid by a heat exchange coil.
Seawater may be also be used. However, the use of seawater is more prone to exchanger
fouling, and the exchanger (plate and frame type) need to be cleaned periodically. The plate
and frame exchangers are very compact and low cost. Typically, spare seawater exchangers
are provided for this option.
Fired heater may be used at the costs of fuel expense. For environmental compliance related to
CO and NOx emissions, a selective Catalytic Reduction System can be fitted into the flue gas
duct of the fired heater.
Quantum Power Ghana Gas Limited 4-31 Knight Piésold Consulting
Environmental and Social Impact Assessment
Figure 4-12: Glycol-water Intermediate Fluid Vaporiser Integration with Different Heat
Sources
Intermediate Fluid (Hydrocarbon) in Rankine Cycle
This system uses propane, butane or other hydrocarbon refrigerant as an intermediate heat
transfer fluid (HTF). The use of a hydrocarbon avoids the potential freezing problems
encountered with seawater. This vapouriser arrangement allows the use of cold seawater as
low as 1°C to minimize fuel consumption in the downstream trim heater.
LNG heating is achieved using two heat exchangers operating in series: a first evaporator
exchanger that uses the latent heat of propane condensation to partially heat LNG, and a
second heat exchanger using seawater to further heat the LNG to the final temperature. The
second exchanger is also used to vapourise propane that is recycled to the first exchanger.
Since the heating by seawater only occurs in the second exchanger, it avoids direct contact with
cryogenic LNG, and hence freezing of seawater can be avoided. For this reason, seawater
close to freezing can be used in this configuration. The basic flow arrangement is illustrated in
Figure 4-13.
Propane or butane can also be used as a working fluid for power production with the addition of
a propane gas expander. The expanded gas is cooled which needs to be reheated with
seawater to meet the pipeline temperature.
Quantum Power Ghana Gas Limited 4-32 Knight Piésold Consulting
Environmental and Social Impact Assessment
For a typical LNG terminal, the power generated by the Rankine cycle and gas expansion can
be used to reduce or even eliminate power import. The power can be generated without any
fuel input or emissions which are very attractive for most terminals.
Figure 4-13: IFV LNG Vaporisers in Rankine Cycle
4.7.5 Heat Integration with Power Plant
Where the regasification facility is located close to a power plant, a hybrid type system using the
waste heat from the power plant and SCVs for trim heating can increase the thermal efficiency
and improve the economics of the regasification process.
The conceptual heat integration scheme is shown in Figure 4-14. The hot exhaust gases from
the gas turbine in the power plant pass through a direct contact heating tower with the exhaust
heat to increase the temperature of a closed hot water circuit. This hot water is then circulated
and injected to the water bath of the SCVs transferring the heat to the LNG.
The returned chilled water from the SCVs can be recycled back to pick the heat in the heating
tower or can also be used to lower the gas turbine inlet temperature. A lower gas turbine inlet
temperature can significantly increase the power output from the turbine. Typically, for each
degree centigrade drop in air temperature, power output can be increased by about 1%. Aero-
derivative turbine is more sensitive to change in air temperatures.
Depending on the available waste heat from the power plant, the fuel gas consumption in the
SCVs can be reduced or even eliminated. In addition to energy savings, there is also reduction
in CO and NOx emissions from the facility.
This SCV hybrid configuration offers flexibility in operation. It can be operated as a standalone
submerged combustion unit, or it can use the warm water from the power plant for LNG
regasification, without the submerged burner operating.
Quantum Power Ghana Gas Limited 4-33 Knight Piésold Consulting
Environmental and Social Impact Assessment
Figure 4-14: SCV Power Plant Integration
4.7.6 COMPARISON OF VAPORISER OPTIONS
The optimum choice of an LNG vaporisation system is determined by the terminal’s site
selection, the environmental conditions, regulatory limitations and operability considerations. It
has to comply with the LNG industry’s requirements for minimizing life cycle costs. The
selection should be based on an economic analysis in maximizing the net present value while
meeting the local emissions and effluent requirements.
Table 4-5 and Table 4-6 compare the six vapouriser options in term of their applications,
operation and maintenance, utility and chemical requirements, environmental impacts and
relative plot sizes.
The six options considered in this analysis are:
Option 1 uses ORV as in existing regasification terminals
Option 2 uses propane as the intermediate fluid with seawater as the heat source.
Option 3 uses glycol water as the intermediate fluid with air as the heat source.
Option 4 uses glycol water as the intermediate fluid with seawater as the heat source.
Option 5 uses SCV using fuel gas and waste heat from cogeneration plant
Option 6 uses ambient air vaporiser (AAV).
Quantum Power Ghana Gas Limited 4-34 Knight Piésold Consulting
Environmental and Social Impact Assessment
Table 4-5: Qualification Comparison for LNG Vaporisation Options
OPTIONS 1 2 3 4 5 6
HEATING MEDIUM Seawater (SW) Propane (C3) /
Seawater (SW)
Glycol-water (GW) /
Air
Glycol-water (GW) /
Seawater
Hot Water (HW)
Fuel Gas (FG))
/Waste Heat (WH)
Air
FEATURE Direct LNG
vaporisation using
sea water
Indirect LNG
vaporisation by
condensing propane
which is heated by
seawater
Indirect LNG
vaporisation by
glycol which is
heated by air fin
exchanger
Indirect LNG
vaporisation by
glycol which is
heated by seawater
Indirect LNG
vaporisation by hot
water which is
heated by waste
heat and SCV
Direct LNG
vaporisation using
air
MAJOR
APPLICATION
70% base load
plants use ORV
Cold climate
application and
avoid freezing of
seawater
For warm climate
application. IFV
makes up 5 % of
base load plants
Similar to Option 3
except seawater is
used as the source
of heating
For energy
conservation with
use of waste heat.
SCV is used in 25%
of base load plants
For warm climate
application, peak
shavers and where
real estate is not a
constraint.
OPERATION &
MAINTENACE
Seawater pumps
and filtration system
Maintenance of
vaporisers and
cleaning of
exchangers
Similar to Option 1
with addition of a
glycol loop and
propane system
Similar to Option 2
with a glycol loop
and use of air as the
source of heat
More complex,
requiring
coordination with
power plant.
More complex
control. Need to
balance waste heat
and fuel gas to
SCVs. Require
coordination with
power plant
operation
Cyclic operation,
requiring adjustment
of the defrosting
cycle according to
ambient changes
UTILITIES Seawater and Seawater and Electrical power only Seawater and Fuel gas and Electrical power only
Quantum Power Ghana Gas Limited 4-35 Knight Piésold Consulting
Environmental and Social Impact Assessment
OPTIONS 1 2 3 4 5 6
HEATING MEDIUM Seawater (SW) Propane (C3) /
Seawater (SW)
Glycol-water (GW) /
Air
Glycol-water (GW) /
Seawater
Hot Water (HW)
Fuel Gas (FG))
/Waste Heat (WH)
Air
REQUIRED electrical power electrical power electrical power electrical power
CHEMICALS Chlorination for
seawater treatment.
Similar to Option 1
but lower
chlorination
None Similar to option 1
but lower
chlorination
Neutralization
required for pH
control and NOx
reduction by SCR
None
EMISSION &
EFFLUENTS
Impacts on marine
life from cold
seawater and
residual chloride
content
Impacts on marine
life from cold
seawater and
residual chloride
content
No significant impact
on environment
except dense fog
Impacts on marine
life from cold
seawater and
residual chloride
content
Flue gas (NOx, CO2)
emissions and acid
water condensate
discharge
No significant impact
on environment
except dense fog
SAFETY Leakage of HC from
ORV to atmosphere
at ground level
Leakage of HC to
atmosphere at
ground level.
Operating a propane
liquid system is
additional safety
hazard
Leakage of HC to
glycol system which
can be vented to
safe location via
surge vessel
Leakage of HC to
glycol system which
can be vented to
safe location via
surge vessel
Leakage of HC to
water system which
can be vented to
safe location via the
SCV stack and
surge vessel
Leakage of HC from
AAV to atmosphere
at ground level
PLOT PLAN Medium Size Medium Size Large Size Medium Size Small Size Large Size
Quantum Power Ghana Gas Limited 4-36 Knight Piésold Consulting
Environmental and Social Impact Assessment
Table 4-6: Vaporiser Rankings for Ambient above 18°C
Option Vaporiser / Heat Transfer
Fluid
Environmental Operability Maintainability Total Rank
1 ORV (SW) 4 3 3 10 3rd
2 IFV (C3/SW) 5 5 5 15 5th
3 IFV (GW/Air) 2 1 1 4 1st
4 IFV (GW/SW) 3 4 4 11 4th
5 SCV (HW (FG) /WH) 6 6 6 18 6th
6 AAV (Air) 1 2 2 5 2nd
Quantum Power Ghana Gas Limited 4-37 Knight Piésold Consulting
Environmental and Social Impact Assessment
4.7.7 Rankings of LNG Vaporisation Technology Alternatives
In warm ambient locations, as that of the Tema LNG project, where site ambient temperature
stays above 18°C, the ambient air vaporisers or the air heated intermediate fluid type vaporiser
units can provide the full LNG vaporisation duty without trim heating. In addition, there is
potential revenue to be gained by collecting and marketing the water condensate from the air.
The 6 options in Table 4-6 are ranked for their performance in terms of environmental impacts,
system operability and maintenance requirement. The ranking system is based on a score of 1
to 6, with 1 being the most desirable and 6 the least desirable. These scores are summed and
the one with the lowest score is considered the most desirable option. The rankings are divided
into two regions.
For the hot climate zone, the environmental score for air heating is the top two most desirable
(option 3 and 6) followed by seawater options (1 and 4). Option 5 uses fuel gas for heating in
the SCV generating emissions and hence the least desirable. The use of propane as an
intermediate fluid (Option 2) requires an additional propane system which is not required in a
warm climate region and is also ranked low in the rating.
For operability and maintainability, air heating (option 3 and 6) is the simplest to operate and
maintain. Option 3 using an intermediate fluid with the air heater, which eliminates the cyclic
defrosting operation required for AAV and is ranked the most desirable. For this reason, option
3, the use of glycol and air heating is considered the most desirable. However, the score is only
marginally higher than the AAV option. The final selection depends on other factors, such as
plot space requirement, capital and operating costs.
Open-loop water-based systems are typically used as the heating medium where warm water is
available in sufficient amounts throughout the year. In the case of the Tema LNG Project,
seawater is available in unlimited quantities compared to other sources of heat, and is therefore
the preferred heat source. Detailed description of the preferred regasification process is
presented in Chapter 2 (Project Description).
4.8 NO-GO ALTERNATIVE
The No-Go alternative considers non-construction of Project, which would entail gas supply
deficiencies for independent power providers (“IPP”) and industrial consumers in the area of
Tema and surroundings.
While the Tema local economy comprises agriculture, industry and commerce/services, the
industrial and services sectors employ the majority of labour force. Therefore, the project non-
construction would lead to the slowing down of the economic growth in the area as well as
energy supply deficiencies in some sectors.
If the proposed LNG Regasification Project is not developed, the predicted energy shortfall in
Ghana is likely to be accounted for by the increased reliance on LCO. The cost associated with
LCO is much greater than LNG1. Emissions from LCO combustion can contribute to
1 Energizing Economic Growth in Ghana: Making the Power and Petroleum Sectors Rise to the Challenge, World Bank, 2013
Quantum Power Ghana Gas Limited 4-38 Knight Piésold Consulting
Environmental and Social Impact Assessment
deterioration of air quality in Tema and Takoradi. Natural gas is a less carbon-intensive fuel
(meaning less CO2 is emitted per unit of energy production) than the LCO fuels currently burnt
for electricity production from thermal plants2. Not only is the project less carbon intensive than
industrial processes reliant on LCO, but it will also assist in alleviating the emissions of key air
pollutants such as oxides of sulphur, particulate matter and oxides of nitrogen in the region.
The proposed LNG re-gasification Project therefore provides a more sustainable solution to
meet the expected increase in energy demand than the ‘do-nothing’ option.
2 Guide to Natural Gas Development in Ghana by the Resource Centre for Energy Economics and Regulation, University of Ghana, 2006