+ All Categories
Home > Documents > Project Execution Planning for Building Information...

Project Execution Planning for Building Information...

Date post: 13-Mar-2018
Category:
Upload: buinhu
View: 219 times
Download: 4 times
Share this document with a friend
28
Project Execution Planning for Building Information Modeling A buildingSMART Alliance project sponsored by: The Charles Pankow Foundation Construction Industry Institute (CII) Penn State Office of Physical Plant (OPP) PACE Progress Meeting #5 – December 5 th , 2008
Transcript
Page 1: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Project Execution Planning forBuilding Information Modeling

A buildingSMART Alliance project sponsored by:• The Charles Pankow Foundation• Construction Industry Institute (CII)• Penn State Office of Physical Plant (OPP)• PACE

Progress Meeting #5 – December 5th, 2008

Page 2: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Conference Call Agenda

1. Introductions2. Review Project Goal3. Discuss BIM Execution Plan Contents4. Discuss Planning Process5. Future Task Discussion

Page 3: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Team Members

•Board of Advisory•Deke Smith – Executive Director of buildingSMART Alliance (Industry Champion)•Victor Sanvido – Ph.D., Senior Vice President, Southland Industries•Francois Grobler – Ph.D., US Army CERL and IAI ‐ North America•Steve Hagan – Project Knowledge Center, U.S. General Services Administration•Soad Kousheshi – President, AEC Strategy•Ed Gannon – Manager of Design Services, Penn State Office of Physical Plant•Mark Falzarano – Barton Malow Company•Mark Butler – HDR•Derek Cunz – Director of Project Development, Mortenson Construction• Mark Konchar‐ Vice President – Balfour Beatty Construction

• CIC Research Program Team Members• John Messner – Director of the CIC Research Program•Chimay Anumba – Professor and Head of Architectural Engineering•Sam Hunter – Assist. Professor of Psychology•Craig Dubler – PhD Student, Architectural Engineering (Construction)•Colleen Kasprzak –MS Student, Architectural Engineering (Operations)•Chitwan Saluja –MS Student, Architectural Engineering (Planning)•Nevena Zikic –MS Student, Architectural Engineering (Design)•Shane Goodman – BAE/MAE Student, Architectural Engineering

• Sponsor Represenatives•Bob Tener – Director, The Charles Pankow Foundation •Steve Thomas – Director of Research, The Construction Industry Institute

Page 4: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Project Overview

• Identify BIM methods and implementation strategies organized by project phase

• Planning, Design, Construction, Operations• Develop implementation guidelines and best practice methods• Disseminate the results

• BIM Execution Planning Guide• Interactive execution planning computer tool• Presentations at national conferences e.g. buildingSMART, AIA, AGC BIMForum, etc.

• Articles in industry and academic publications

Page 5: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Progress Report

• Continuously developing concept for BIM Execution Planning Process.

• Reviewing additional resources with similar scopes for collaborative efforts and/or additional value to our guide. 

• BIM Ex Class • Developed BIM uses on wiki through interviews 

and lit review• Wrapping up the case study projects 

Page 6: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Plan

Design

Construct

Operate

Design Communication

System Analysis Estimation Scheduling

Existing Conditions ModelingProgramming

Design AuthoringDesign Reviews 

(Constructability, 3D Design Coordination, Virtual Mock‐ups)

Site AnalysisEngineering Analysis 

(Structural, Energy, Lighting , CFD, IAQ Evaluation, Thermal Performance)Code Validation 

(Emergency Evacuation, Security Analysis)LEED Evaluation

Site SelectionPreliminary Cost         Estimation

Cost Estimation

Phase Planning

Phase Planning (Tenant Fit‐out)

3D MEP CoordinationDigital Fabrication3D Control and Planning

Record ModelAsset ManagementSpace Management/TrackingDisaster/EmergencyPlanning

3D System Design

Building Performance Analysis

Unit Price Estimating

Maintenance Cost Estimation

4D PlanningSite Utilization 

Planning

Building MaintenanceRenovation 

Coordination

Page 7: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

BIM USE from WIKI

CLICK HERE(Link to WIKI)

Page 8: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Operation Construction Design Planning

E SD S

First Pass = Use

Second Pass = Who creates it? What Platform?

Operation Construction Design Planning

E SD S E SD S E SD S

E SD S E SD S E SD S E SD S

Execution Planning Process Concept:“Begin with the End in Mind”

Page 9: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Execution Planning Process

•Manual review of BIM uses•Decision Support System to proceed from project characteristic to recommended BIM uses

BIM Use Identification

•Develop  a process specifically tailored to the project which includes tasks supported by BIM along with information exchanges between processes

BIM Process Planning

•Development of a detailed plan and procedure for each use and the information flow between  the uses

BIM Execution Plan 

Development

Project X

BIM Execution

Plan

Page 10: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Execution Planning Categories

•Critical project overview information, contractual requirements related to BIM, and key project contacts

Project Reference Information

•Document the underlying purpose for BIM implementation on the project and why key BIM use decisions where made

Project Goals /BIM Objectives

• Identification of the process for creating, reviewing and modifying the model.  Include information exchange requirements.

Model Development Process

• Include model elements by discipline, level of detail,  and specific attributesBIM Scope Definitions

•Define the roles of each organization along with responsibilities•Define contracting strategies for organizations

Organizational Roles and Responsibilities

•Electronic communication procedures•Meeting communication procedures

Communication Procedures

• Identify the methods to ensure model accuracy and comprehensiveness

Model Quality Control Procedures

Page 11: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

BIM Execution Plan Contents

Page 12: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

BIM Execution Plan Contents

Page 13: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

• Objective: Is to develop a model of the essential functions required to provide a facility to the end user. 

• Functions: Managing, planning, design, construction and operations of a facility.

• Modeling methodology to represent these processes: IDEF 0 was selected as the most appropriate modeling tool.

Schematic representation of the Function Box

An Integrated Building Process Model (IBPM)

Page 14: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Conduct Business

Page 15: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Provide Facility

Page 16: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Construct Facility

Page 17: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Process Protocol

• The process protocol map illustrates the design and construction process in terms of the various phases of the development, the main participants enacting the process, the deliverables of the process and the way in which the process is managed through the phase review process.

• Phases: There are 10 phases covering aspects of a project lifecycle from the demonstration and conception of need to the operation and maintenance of the constructed and/or refurbished facilities. Issues of decommissioning and demolition are considered at the front end of the process. 

Page 18: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Phase 0: Demonstrating the need

Page 19: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Phase 8: Construction

Page 20: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Planning Information Requirements

Task/Process

Who is responsible

What application(s)

InformationWhat Data

What Format(s)

Page 21: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Process Planning Concept

Quantity Takeoff

Generic Process

From Generic To Specific

METHOD 2

Innovaya Takeoff

Revit Takeoff

QTO Takeoff

Vico Takeoff

METHOD 1

METHOD 3

METHOD 4

Page 22: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

BIM Use Example: Generic Process Model

Node B: Develop Assembly Cost Estimate

Node B: Develop Assembly Cost Estimate

Page 23: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Node B1: Perform Quantity Takeoff

BIM Use Example: Project Execution Plan

Page 24: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Node B1 (a): Perform Quantity Take off (Method 1: Innovaya Takeoff)

Node B1 (b): Perform Quantity Take off (Method 2: Revit Takeoff)

BIM Use Example: Project Execution Plan

Page 25: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Node B: Develop Assembly Cost Estimate

Node B1 (a): Method 1

Node B1 (b): Method 2

Page 26: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

BIM Use

ProcessArchitect

Typical Methods

Landscape Designer

Architect

Typical Methods

Typical Methods

Typical Methods

Typical Methods

Structural Engineer Operator

Contractor

Record Model

BIM Project Execution Planning Process

BIM Use

ProcessStructural 

Eng.

BIM Use

ProcessElectrical Eng.

BIM Use

ProcessMechanical

BIM Use

ProcessCM

BIM Use

ProcessOperator

Page 27: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Three Month Look Ahead

• Develop detailed execution planning process method example

• Complete BIM Use definitions, and example process template for the BIM Uses

• Complete the draft list of content for the BIM Execution Plan

Page 28: Project Execution Planning for Building Information …bimex.wikispaces.com/file/view/Meeting5.pdf/57808880/...Project Execution Planning for Building Information Modeling A buildingSMARTAlliance

Thank You

Next Meeting Time?


Recommended