Project implementation, changes, reporting
Edmunds Sniķ[email protected]
Joint Technical Secretariat 16 April 2012, Kuldīga
Project Implementation
2
Key aspects:
Application Form
Feasibility Study
Cost estimations
Technical Project
Specifications of equipment
Project results=
Project monitoring and control
Monitoring
3
Programme levelProgress reports every 6 months, Project visits
by the JTS, construction experts
Project LevelConstantly by the Lead Partner/periodically by
the Steering Group
Changes in projects Minor deviations that are not considered as
Project changes:
Changes in contact info, minor rescheduling, deviations from the spending targets, small deviations from specifications, changes between the costs of items within one budget line and work package.
Project have to make changes:
1. Project Partnership;
2. Budget Reallocation;
3. Project Activities and Outputs;
4. Modification of the Duration of the reporting Period;
5. Prolongation of the Project Duration.
4
Can be reported as „deviations‟ to the JTS
through the Progress Report
Request for changes procedure - www.latlit.eu,
section “How to Implement”
Budget rellocation
Requirements:
reallocation must be justified;
cannot request to increase the ERDF co-financing;
foster more efficient achievement of project objectives and results;
the project can reallocate the budget between the BLs and/or work packages up to 30% of the total eligible project budget;
as an exception, changes exceeding 30% reallocation between BLs/work packages are to be considered by the JMSC.
5
As a rule, the budget reallocation can be requested only once during the project implementation. Only in well justified cases, the project
can apply for subsequent budget reallocation.
Project Activities and Outputs
Following cases are possible:
increase/decrease amount of the existing project output, extension/reduction of range of the existing activity (considerable change of the project output/activity that was initially planned in the project application);
creation of a new project output and/or activity (inclusion of new output and/or activity that was not previously planned in the project application).
6
Project Changes Procedure
7
It is strongly recommended to consult with the JTS before submitting request for changes!
1. LP sends electronic version of the request for changes, AF, FS, technical documents, budget reallocation to the JTS
2.Harmonization of documents
3.LP sends paper version of harmonized documents
4.Decision taking process: JMSC, MA, JTS
5.Notification Letter to the LP
6.If changes are approved – LP sends updated Application Form and Feasibility Study
7.Addendum of Subsidy Contract is signed
Information to the JTS
9
According to the Subsidy Contract (Paragraph 5; Point 6.18.) Lead Partner is responsbile for submission of all the PPs’ calendars for the planned construction/renovation works to the responsible project manager of the JTS within 2 weeks after the contract on construction/renovation works is signed by including:
1.the start date of the works;
2.location;
3.deadlines;
4.Indicative payment plan.
Changes in construction works - 1
1. Small deviations from the works and amounts planned in the technical documentation as sub-items in the cost estimation for planned (re)construction works could be eligible if total amount for works does not exceed the planned in the project application:
LP/PP prepares acts on changes;
Submits acts to the first level controller;
in case there are any doubts if it is small deviation or additional (re)construction works JTS could be contacted for exhaustive explanation.
10
Changes in construction works - 2
2. Unexpected works:
During the (re)construction works, unexpected works are possible and such works are being evaluated by controllers on case by case bases (could be harmonised as deviations);
Acts, where justification of changes is described, should be submitted by PPs to controllers.
3. Additional works → If additional works have to be implemented by the project partners, LP shall submit Request for Changes in accordance with existing procedure (http://www.latlit.eu/eng/how_to_implement/project_changes).
11
Reporting Procedure
Six-months Reporting Periods (RP):
PP sends to the FLC Partner Reports: 10 days after the end of the RP
LP submits filled Progress Report to the FLC 2 weeks (latest) before deadline for submission to the JTS
In 3 months after the end of the RP the LP submits Progress Report to the JTS
1 November – 30 April 1 May – 31 October
1 November – 30 April 1 May – 31 October
12
Reporting Procedure
PP1
LP
PP2
FLC
FLC
FLC
10 working days
PP1
PP2
LP
Partner Reports to FLC
3 months
LP
Partner Reports to LPFLC
LP
JTS
First Level Control
Progress Report to JTS
Pre-filled PR form to LP
Consolidated Progress Report to FLC
JTS
End
of re
porti
ng p
erio
d
13
Reporting/ Payment Procedure
Lead Partner
PP 1
PP 2
PP 3
Pre-filled Reporting
FormWithin 3 months after the end of Reporting Period
Progress Report
Preparation of payment CA
Payment
JTS
AnswersFull check of PR
Max period for check &
clarification 6 months after submission
70% payment, if 1st check of PR is passed
Clarification
14
FormsForms: JTS sends out a pre-filled Progress Report form to LP Partner report, timesheet, list of participants form available
as attachment to FLC guidelines
15
ReportingLP sends the following documents to the JTS:
Original Certificate of Proficiency of the LP Controller Copies of Confirmations of all the PP’s controllers
Verified Progress Report: Signed by LP and FLC In electronic and paper version In English language
Information provided in the PR should be comparable with information provided in the AF.
16
Reporting
LP sends the following supporting documents to the JTS:
Events documents (e.g. agenda, list of participants with signatures for each day, photos, see full list in PM, 10.1.2)
Copies of outputs produced (e.g. studies, press articles, leaflets, pictures of infrastructure, recordings of TV or radio broadcasts, etc.)
17