PMO implementation Accomplishment
Sylvain Gauthier B.eng, MBA , PMP
President
Program ManagementOffice (2008)
November 2008Business Plan summary
Set up a Program Management Office to identify and deliver cost reduction projects
Location Montreal, Canada
Industry Aerospace
PMO type Control – Link to P&L B/S
# Projects 23 in 2008
Project Management life cycle context
Stage gate process (Passport)
CR opportunity identification method
Lean (Kaizen)VAVE
Analysis tools Feasibility study, TCO, PBH contract -reliability
Results 10 times investment within a year
Air Canada technical Services
Program ManagementOffice (2007)
November 2008Business Plan summary
Support and enhance the Program Management Office to deliver projects in 3 areas , TV Broadcasting, International Sponsorship & Ticketing
Location Beijing, China
Industry Sports & entertainment
PMO type Support - repository
# Projects 27
Project Management life cycle context
Stage gate process
Issue resolution method SCRUM
Communication tools Dashboard & PMO Web base
Facilitation tools Open space
Results Best Game ever presented
Program ManagementOffice (2006)
November 2008Business Plan summary
Enhance a Project Management Office to include supplier relationship projects as part of the SRM program (supplier relationships management)
Location Shanghai, China
Industry Pharmaceutical
PMO type Support
# Projects 30
Project Management life cycle context
Internal Bayer methodologies
Analysis tools Portfolio segmentation, Pareto, Krajic, Cost breakdown analysis
Procurement process tools RFQ,IFB, SOW, Contract project management plan
Results Improved drastically relationships with chinese suppliers to ensure security of supply and cost improvements
Program ManagementOffice (2002-06)
November 2008Business Plan summary
Set up a Program Management Office to manage the deployment of F1 properties in China
Location Hong Kong, China
Industry Sports & Entertainment
PMO type Control
# Projects 3 from 2002-2006 2 from 2005-2006
Project Management life cycle context
TTM (Time to Market)
Stakeholder management China Gov., Sponsors, TV stations, FOM, Investors
Measurement tools Reach, TV ratings, demographics, Media value
Results 3rd most watched sports on TV by 2004Who works in F! book release 2005F1 Emotions release 2006
1. Television Broadcasting2. Book Publishing
Program ManagementOffice (2004)
November 2008Business Plan summary
Set up a Program Management Office to define and implement a strategy to deploy NHL hockey on television in China
Location Beijing, China
Industry Sports & Entertainment
PMO type Support
# Projects 1
Project Management life cycle context
Stage gate process (1st phase only)
Analysis tools Feasibility Study, Business case development
Results Recommendation of a business model using provincial tv stations. Implementation phase halted due to lockouts 2004-2005
1. Television Broadcasting
JV china ProjectManagement Office (2001-2002)
November 2008Business Plan summary
Set up a Program Management Office in the JV Guangdong Nortel in China for cost reductions
Location Guangdong, China
Industry Telecommunication
PMO type Control
# Projects 72
Project Management life cycle context
TTM (Time to Market)
PMO Management tools VAVE, Supplier CR, Design CR, TCO, business case
Measurement tools Material & labour cost %improvement yearly
Results 20% product margin improvements
Project ManagementOffice (1999-2000)
November 2008Business Plan summary
Support the deployment of a corporate Project Management Office to manage capital intensive type of projects
Location Montreal, Canada
Industry Media
PMO type Support
# Projects 14
Project Management life cycle context
Stage gate process
Analysis tools Feasibility Study, Business case development
Results More then 80% of the capital budget funds were allocated per justified projects for the year 2000
CBC – Radio Canada
Business CostManagement Office (1996-1999)
November 2008Business Plan summary
Set up many business cost Management Office in different locations of Nortel Networks
Locations US, France, Ireland, Canada, England
Industry Telecommunication
PMO type Support
# Projects Up to 300 globally
Project Management life cycle context
TTM (Time to Market)Adapted for CR program
PMO Management tools VAVE, Supplier CR, Design CR, TCO, business case
Measurement tools Material & labour cost %improvement yearly
Results 20% product margin improvements