+ All Categories
Home > Documents > Project Prospectus and Design Acceptance Package ( and a little more) Alan Lively Project Delivery...

Project Prospectus and Design Acceptance Package ( and a little more) Alan Lively Project Delivery...

Date post: 16-Dec-2015
Category:
Upload: rosaline-waters
View: 215 times
Download: 2 times
Share this document with a friend
Popular Tags:
21
Project Prospectus and Project Prospectus and Design Acceptance Package Design Acceptance Package ( ( and a little more) and a little more) Alan Lively Project Delivery Specialist January 30, 2009
Transcript

Project Prospectus and Design Project Prospectus and Design Acceptance PackageAcceptance Package

((and a little more)and a little more)

Alan Lively

Project Delivery Specialist January 30, 2009

ODOT Project Development ProcessODOT Project Development Process

• Project Selection - Draft STIP

• Design Acceptance Package - DAP

• Advance Plans and Specifications

• Plans, Specifications, and Estimate PS&E

Project Selection - Draft STIPProject Selection - Draft STIP

• Projects are selected from various funding programs like HBP, TE or STP

• Draft Scope, Schedule, Budget, (Prospectus) and Intergovernmental Agreement (IGA) are developed

PROSPECTUSPROSPECTUS

• The project prospectus is a tool to convey information about a project to various organization inside and outside of ODOT

• It starts the process of identifying the problem to be solved and presents ideas on how to solve it

PROJECT PROSPECTUSPROJECT PROSPECTUS

• It contains information on the Project:

– Costs– Funding sources– Funding years– Right of Way impacts– Environmental impacts

Its Divided into Three PartsIts Divided into Three Parts

• Part 1 - Project Request

• Part 2 – Project Details

• Part 3 – Project Environmental Class

• The project location• Overview of the project• Problem statement• Proposed solution• Cost estimates for PE, CE, Right of Way,

and construction

Part 1 provides information Part 1 provides information on:on:

• Who is responsible for completing the different categories of the project design

• Base design requirements• Roadway element widths• Structure size and cost• Right of Way information

Part 2 defines:Part 2 defines:

• Details environmental impacts

• Environmental baseline information

• Require permits, reports and clearances

Part 3 – Environmental Part 3 – Environmental details:details:

This milestone is a critical point of decision- making that establishes the geometric boundaries of the project footprint, and allows the concurrent right-of-way (ROW), permitting, and construction contract document activities to move forward

Design Acceptance PackageDesign Acceptance Package

Design Acceptance also provides for environmental and land use requirements, and subsequently how they affect permitting and the development of construction contract documents

Design Acceptance PackageDesign Acceptance Package

– It occurs at the end of the initial design phase and requires all project disciplines to review the design for balance of context with standards and policies.

– It is the primary opportunity for both technical and non-technical stakeholders to review design elements according to their specific interests. Deliverables include

Design Acceptance PackageDesign Acceptance Package

DAP DeliverablesDAP Deliverables

• Environmental Documentation (e.g., NEPA CE, EA, EIS)

• Design Narrative and/or Bridge Type, Size, and Location (TSL)

• Plan Sheets• Current Schedule• Current Estimate/Budget

Advance Plans and SpecificationsAdvance Plans and Specifications

• This is a key interim step of the contract document phase, and requires all project disciplines to review draft contract documents for completeness and accuracy. It is the primary opportunity for technical staff to provide quality control review of the project plans, specifications, and estimate as a package.

Deliverables include Deliverables include

• Project Plan• Project Special Provisions• Current cost estimates and Bid Items• Draft Construction Schedule • Insurance Risk Assessment Form

PS&EPS&E

• Plans

• Spec.’s

• Estimate

• Kelli Sparkman

Contact InformationContact Information

Alan LivelyProject Delivery SpecialistODOT Local Government Section355 Capitol Street, NESalem, OR [email protected]


Recommended