ELI -DC and the future ELI-ERIC: structure, status, current plans and current unknowns Wolfgang Sandner Director General, ELI Delivery Consortium AISBL HEPTech Workshop on Building an ELI-Centric Academia-Industry Ecosystem Prague, April 7, 2014. Project supported by:. - PowerPoint PPT Presentation
Popular Tags:
30
Project supported by: ELI-DC and the future ELI-ERIC: structure, status, current plans and current unknowns Wolfgang Sandner Director General, ELI Delivery Consortium AISBL HEPTech Workshop on Building an ELI-Centric Academia-Industry Ecosystem Prague, April 7, 2014
Transcript
Page 1: Project supported by:

Project supported by:

ELI-DC and the future ELI-ERIC:structure, status, current plans and current unknowns

Wolfgang SandnerDirector General, ELI Delivery Consortium AISBL

HEPTech Workshop on Building an ELI-Centric Academia-Industry EcosystemPrague, April 7, 2014

Page 2: Project supported by:

ELI’s essential characteristics

ELI will be the world’s first international laser research infrastructure,

providing unique science and research opportunities for international users

“The CERN of laser research”

a distributed research infrastructure based initially on 3 facilities in CZ, HU and RO

the first ESFRI project to be implemented in the new EU Member States

pioneering a novel funding model combining structural funds (ERDF) for the implementation and contributions to an ERIC for the operation

Page 3: Project supported by:

ELI‘s Roadmap

ELI-PPESFRI

ELI-NP

ELI-Beamlines

ELI-ALPS

joint operationinitiation

20172011 2013

ELI-DC International Association

parallel implementation

2008

ELI

ELI- ERIC

ELI

initiationinitiationparallel

implementationinitiationjoint

operationinitiationjoint

operationinitiationjoint

operationinitiation

PP MoU ELI- ERIC

Page 4: Project supported by:

Financial structure

20172011 2013

ELI-DC International Association

2008

PP MoU ELI- ERIC

joint operation

parallel implementationinitiation

~ 6 M€Prep. Phase

~ 850 M€ totalEU Structural Funds

(CZ, RO approved / HU applied for)

60-80 M€ /aELI-ERIC(pending)

ERIC negotiations

Page 5: Project supported by:

Project supported by:

Brief overview over science and status of the ELI project

in the three host countries

Page 6: Project supported by:

Attosecond Laser Science, will capitalize on new regimes of time resolution (ELI-ALPS, Szeged, HU)

• High-Energy Beam Facility, responsible for development and application of ultra-short pulses of high-energy particles and radiation (ELI-Beamlines, Prague, CZ)

• Nuclear Physics Facility with ultra-intense laser and brilliant gamma beams (up to 19 MeV) enabling novel photonuclear studies (ELI-NP, Magurele, RO)

•Ultra-High-Field Science centred on direct physics of the unprecedented laser field strength (ELI 4, to be decided)

New and complementary science,unique research opportunitites

?

Page 7: Project supported by:

Structural Funds approved in Sept. 2012

Projected completion date: IV 2017

Building under construction

Scientific Director appointed, Technical Director tba;

staff hiring in progress (~50)

Major equipment procured (two 10PW lasers)

Tender for Gamma sourcein progress

ELI Nuclear Physics in Romania

Page 8: Project supported by:

Structural Funds expected to be approved in IV 2013

Projected completion date: IV 2017

Building contract to be concluded

Scientific Director appointed, staff hiring in progress (~25)

Major workpackages contracted to

international laboratories

Major equipment procurement under preparation (SYLOS, HF)

Final Technical Design Reportunder preparation

ELI Attosecond Physics in Hungary

Page 9: Project supported by:

Structural Funds approved in April 2011

Projected completion date: IV 2017(phasing negotiations in progress)

Building under construction

Project Delivery Manager (AS) appointedLarge local organisation and staff (~200)

Major equipment procured/under construction(diode-pumped, 10Hz PW laser L3 / L1)

Tender for 10PW laser L4 in progress, Second PW laser L2 in preparation

ELI Beamlines in the Czech Republic

Page 10: Project supported by:

ELI is pioneering a novel funding model by combining the use of structural

funds (ERDF) for the implementation and formation of an ERIC for the

operation

Why doing it?How can it ever work?

What is the consequence for future ELI strategies and policies?

Page 11: Project supported by:

Why doing it?

• Structural funds are allocated at the national level through 3 separate processes and grant agreements

- ELI construction proceeds faster than through an ERIC!

- “lean ELI-ERIC” for later operation only

• Grant beneficiaries (ELI-Hu, IoP, IFIN-HH) are individually responsible for the implementation of the 3 ELI facilities

“lean governance” model for constructing a distributed RI

• ERDF: introduces additional objectives of socio-economic development for the hosting regions (besides RI objectives)

- added value for both the ERA and regional development

- return of investment for the host country

Page 12: Project supported by:

How can it work?Any examples?

ELI-PPESFRI

ELI-NP

ELI-Beamlines

ELI-ALPS

joint operationinitiation

20172011 2013

parallel implementation

2008

ELI

ELI- ERIC

ELI

initiationinitiationparallel

implementationinitiationjoint

operationinitiationjoint

operationinitiationjoint

operationinitiation

Page 13: Project supported by:

1) The biggest remaining challenge:

“Selling” the product to an international ERIC Consortium for sponsoring and operating ELI-ERIC after the implementation phase (after 2017)

Page 14: Project supported by:

2) If it works: The governance, strategies and policies of ELI-ERIC during the operational phase will be completely different from those of the construction phase. Apart from basic principles they are yet unknown.Neither predictions nor any commitments can be made at the present stage.

Page 15: Project supported by:

ELI-PPESFRI

ELI-NP

ELI-Beamlines

ELI-ALPS

Single unified governance under

yet unknown contractual rules

initiation

20172011 2013

ELI-DC International Association

National SF contracts

plus ELI-DC

2008

ELI

ELI- ERIC

ELI

initiationinitiationinitiationinitiationConsensusBasedInitiation & preparation

PP MoU ELI- ERIC

Three legal lives of a project

Page 16: Project supported by:

Future ELI-ERIC’s basic principles

Joint operation of the ELI facilities under a unified legal entity and governance

• Financially sustainable operation based on contributions from the host countries and other countries

• One legal entity, ELI-ERIC, governing the operation of all three research centres => finding a new balance between national and international responsibilities, while still observing the legal commitments from ERDF

• Common policies for operation, access, data management, dissemination, quality control etc

• Operation as a single user facility, open for international access with world-class research opportunities, highest scientific standards and high-quality scientific output

Page 17: Project supported by:

Why is ELI different from other international research infrastructures

in that respect?

Remember: ELI is pioneering a novel funding model combining the use of structural funds

(ERDF) for the implementation and formation of an ERIC for the operation

Page 18: Project supported by:

Structural funds for a distributed RIA “clash of cultures”?

DG Research & Innovation: RIs are “Tools for science”

“RIs are a key instrument to look for solutions to many of the problems society is facing today. RIs offer unique research services to users from different countries, attract young people to science, and help to shape scientific communities.”

DG Regio: Research excellence per se is no objective for Cohesion Policy, but just a tool for competitiveness and growth “The Structural Funds and the Cohesion Fund are the financial instruments of European Union (EU) regional policy, which is intended to narrow the developmentdisparities among regions and Member States.”

Page 19: Project supported by:

They must be integral part of strategies, not "cathedrals in the desert" & large-scale budget absorbers

They must be dentified in an entrepreneurial discovery process, not just desired by academia & researchers

Research excellence per se is no objective for Cohesion Policy, but just a tool for competitiveness and growth

Key RI should be designed / transformed into crystallisation points for economic change and growth: clusters, technology parks, incubators, firm cooperation

Importance of international attractiveness & connectedness: private investors & brain-gain

Evaluation, evaluation, evaluation!

Research infrastructures in support of RIS3

Katja ReppelCC smart and sustainable growthDG Regional and Urban Policy

DG Regio’s political view

Page 20: Project supported by:

Management challenge

Page 21: Project supported by:

Management challengeduring implementation

• Several layers of responsibilities and interests to protect and combine:

• Pan-European dimension, scientific excellence and global scientific competitiveness under unified governance – the ESFRI objective

versus• Legal responsibility of the sites during the implementation plus• Emphasis on socio-economic benefits and national

development within the hosting countries due to ERDF commitments

• Political and administrative obstacles:• No synchronisation of operational programmes (OP) in different

countries

• Conflict with SF time frames imposed by EC (“cash flow versus quality”?)

• Non-uniform priorities in the science-economy balance

Page 22: Project supported by:

• Risk of a loss of larger international commitment during implementation

• Need for coordination between implementation teams to prepare joint and high-quality operation and ensure overall scientific coherence

• Preparation of ERIC negotiations in parallel with implementation

• Staged approach to ERIC: at some point a clear transition of responsibilities and governance from national authorities towards ERIC has to take place (“disruptive transition”).

=> Need for an interim structure at the European level to address these challenges and risks:

Specific risks and needs

Page 23: Project supported by:

The ELI Delivery ConsortiumInternational Association AISBL

• Legal form: international non-profit association under Belgian law (AISBL), established Juli 2013 and operational since September.

• Open to all interested countries besides the ELI Host Countries

• Main missions:• Promoting the effective development and visibility of ELI as a

single pan-European project• Supporting the implementation of the existing and future ELI

research centres and their coordinated preparation of operation• Preparing and coordinating the establishment of the ELI-ERIC

parallel to the implementation process

• Decentralised organisation with staff “embedded” in the three implementation teams and use of cutting-edge e-infrastructure solutions for virtual collaboration

Page 24: Project supported by:

ELI-DC Organisation

Page 25: Project supported by:

Membership statusI / 2014

Members of the ELI-DC AISBL

Membership under consideration

Expressions of interest

Page 26: Project supported by:

Summary and lessons learned

Page 27: Project supported by:

Structural Funds appear, in principle, to be an excellent funding model for the swift construction of ESFRI RIs, for strengthening the ERA and for fostering synergies between the socio-economic and scientific objectives.

In addition, Structural Funds are a well-established funding mechanisms for large-scale projects on both the national and the EC level.

Structural Funds

Page 28: Project supported by:

However:

High-risk projects such as world-class research infrastructures are a new and different class of Structural Funds "clients" and require substantial (!) adaptation of procedures and cultures - both on the EC and national levels - in order not to fail.

Structural FundsStructural Funds

Page 29: Project supported by:

In addition:

Concepts for the transition between the construction phase, dominated by national governance and ERDF regulations, and the operation phase, dominated by unified governance under an ERIC agreement, need to be developed.

This includes scientific, operational, financial and legal concepts, as well as concepts for academia-industry liaisons.

Transition towards ERIC

Page 30: Project supported by:

Conclusion

• ELI is unique in many respects, particularly pioneering the combination of scientific excellence with socio-economic objectives across national borders. Hence, the development of concepts towards an ELI-centric academia-industry ecosystem is timely and appropriate.• On a national level such ecosystems can be implemented immediately. One must observe, however, that the governance of the ELI pillars will be handed over to ELI-ERIC after 2018.

• Any trans-national activity at the ELI-ERIC level, shall it be sustainable beyond 2017, requires integration into the trans-national governance model and, hence, early integration into ELI’s negotiations towards the ELI-ERIC.