+ All Categories
Home > Documents > Project System

Project System

Date post: 05-Mar-2016
Category:
Upload: sachin-patil
View: 216 times
Download: 0 times
Share this document with a friend
Description:
Project System
15
7/21/2019 Project System http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 1/15 COLLEGE OF ENGINEERING, PUNE (An Autonomous Institute of Government of Maharashtra) END ERM (ERP!"##$) Pro%e&t 'stems Proramme* PGDERP + #"-."! 'emester I Duration* / hrs Ma01 Mar2s* 3# Date* "#4""4#"- ime* *## 5m to !*##5m Section A (Each Question carries 1 Mark) 1 of 30 WBS structure provides a _____________ view of the project. Structural Functional Graphical All the options are correct 2 of 30 Where do we dene constraints (Basic date)? WBS Project defnition et!ork acti"it# All the options are correct 3 of 30 urin! the p"annin! phase# we entered $$$$$$$$$$$$$$$$ for WBS e"e%ents. Actual date Basic date Forecast date $atest date & of 30 We can enter conr%ation for interna" activit' ' %A&S 'ndi"idual %onfration %ollecti"e %onfration All the options are correct a!e 1
Transcript
Page 1: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 1/15

COLLEGE OF ENGINEERING, PUNE

(An Autonomous Institute of Government of Maharashtra)

END ERM

(ERP!"##$) Pro%e&t 'stems

Proramme* PGDERP + #"-."!

'emester I

Duration* / hrs Ma01 Mar2s* 3#

Date* "#4""4#"- ime* *## 5m to !*##5m

Section A (Each Question carries 1 Mark)

1 of 30

WBS structure provides a _____________ view of the project.

• Structural

• Functional

• Graphical

• All the options are correct

2 of 30

Where do we dene constraints (Basic date)?

• WBS

• Project defnition

• et!ork acti"it#

• All the options are correct

3 of 30urin! the p"annin! phase# we entered $$$$$$$$$$$$$$$$ for WBS e"e%ents.

• Actual date

• Basic date

• Forecast date

• $atest date

& of 30

We can enter conr%ation for interna" activit' '

• %A&S

• 'ndi"idual %onfration

• %ollecti"e %onfration

• All the options are correct

a!e 1

Page 2: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 2/15

* of 30

We can user +,-S to enter conr%ations for production orders. State whether thestate%ent is true or fa"se.

• &rue

• False

of 30

What are the %ain features of WBS structure?

• Plannin

• Budetin

• E*ecution (Actual +ata)

• All the options are correct

/ of 30

+onr%ation is entered for

• E*ternal Acti"it#

• 'nternal Acti"it#

• %ost Acti"it#

• Ser"ice Acti"it#

of 30

 -he re"ationship etween WBS and ,ctivities is

• 1,

• , 1

• 1, 1

• one o- the options are correct

of 30

enera" +ost activit' has contro" e'

• PS.1

• PS./

• PS.0

• PS.

10 of 30

a!e 2

Page 3: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 3/15

+an we create ood 4eceipt for the %ateria" whose WBS is not 4e"eased? 5es or no.

•  2es

• o

11 of 30

Bi""in! p"an can e %aintained for

• S+ docuent

• WBS eleent

• Both S+ docuent and WBS eleent

• one o- the options are correct

12 of 30

4evenue e"e%ent for i""in! p"an is %entioned in ________.

• Plannin profle

Budet profle

• et!ork profle

• 'n"estent profle

13 of 30

+an we assi!n ,ccount assi!n%ent to roject denition? 5es or no.

•  2es

• o

1& of 30

6n project pro"e# we dene

• et!ork profle

• Paraeter -or net!ork profle

• WBS schedulin profle

• All the options are correct

1* of 30

a!e 3

Page 4: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 4/15

 ______________is used to ud!et the invest%ent project# and the ud!et va"ues arethen distriuted within the project.

• &he in"estent prora

• Project profle

• Plannin profle

• Budet profle

1 of 30

What 7perative indicators of WBS are 8a!!ed for ost of 4evenue?

• Plannin Eleent

• Account Assinent Eleent

• Billin Eleent

• All the options are correct

1/ of 30

We can dene ud!etin! currenc' in

• %ontrollin area currenc#

• &ransition currenc#

• 34ject currenc#

• All the options are correct

1 of 30

+o%%it%ents are created throu!h• Purchase order

• Good receipts

• 'n"oice receipts

• Purchase re5uisition

1 of 30

9or re"i%inar' procure%ent# we %ust use ite% cate!or'

• $

• M

• P

20 of 30

a!e &

Page 5: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 5/15

6f we choose direct procure%ent with ite% cate!or' :# we can choose etween twoprocure%ent t'pes. -he' are;

• Purchase re5uisition -or the net!ork 

• Purchase re5uisition -or WBS

• &hird6part# re5uisition -or the net!ork 

• Purchase re5uisition -or e*ternal acti"it#

21 of 30

6n wor force p"annin!# we can assi!n person to activit' fro%

• Work center

• &he project tea

• 78

• All the options are correct

22 of 30

When we conr% activit'

• %apacit# re5uireent increases

• 8educe %apacit# re5uireent9 update actual date9 and actual cost

• 'ncreases %apacit# re5uireent9 update actual dates9 and actual

cost

• one o- the options are correct

23 of 30

When 'ou create a contro""in! area# the s'ste% auto%atica""' creates a p"an $$$$$$$$$$for p"anned < actua" va"ue.

• :ersion .

• :ersion 1

• Both :ersion . and :ersion 1

• one o- the options are correct

2& of 30

=ow %an' sett"e%ent ru"es can e %aintained for a WBS?

• 0

• 1

• An# nu4er

2* of 30

a!e *

Page 6: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 6/15

 -he "in fro% various usiness transitions to the WBS e"e%ent < activit' areesta"ished '

• Account assinent

• 'te cateor#

• 'te roup

• 8e5uireent class

2 of 30

 -o stipu"ate that networ activities are schedu"ed without tain! account of WBSasic dates# 'ou use

• Profle -or WBS schedulin

• Profle -or et!ork schedulin

• Free schedulin

• All the options are correct

2/ of 30

,sset under construction is created auto%atica""' when WBS is re"eased ' settin!>ana!e ,sset @nder +onstructionA indicator in

• Settleent profle

• Project profle

• 'n"estent Profle

• et!ork profle

2 of 30

 -o create urchase reuisition with account assi!n%ent cate!or' C

• &he assined WBS in purchase re5uisition is al!a#s re5uired to 4e

defned as account assinent in the operati"e indicator o-

respecti"e WBS

• &he assined WBS need not 4e defned as account assinent in the

operati"e indicator o- respecti"e WBS

• &he assined WBS in purchase re5uisition is al!a#s re5uired to 4e

defned as plannin as the operati"e indicator o- respecti"e WBS

• one o- the options are correct

a!e

Page 7: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 7/15

2 of 30

4e"ated to S'ste% and @ser status;

• We can per-or transition e"en i- s#ste status prohi4its and user

status allo!s

• Both s#ste and user status should allo!9 onl# then can !e do the

transition

We can per-or the transition i- s#ste status allo!s e"en i- userstatus prohi4its

• one o- the options are correct

30 of 30

We can oo actua" cost at roject enition Deve"

•  2es

• o

Section B (Each Question carries 0 Marks9 Ans!er an# 1.)

a!e /

Page 8: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 8/15

What is the organizational structure of PS module? Explain.

31

 

a!e

Page 9: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 9/15

32 How would you integrate SAP Project System with other SAP odules?Explain.

MM,Purchasin, Purchase order9 oods receipt -or aterials andser"ices; 'n"entor# Manaeent, oods issue -or reser"ationsS+, +eli"er# -ro Project9 Milestone BillinPP, 8eser"ation Generated -ro PS -or independent 8e5uireents(8eser"ations) can 4e et throuh Production order;%3, 'nternal acti"it# allocation9 assined 'nternal orders9

Settleent to %3 34jectF', +o!n pa#ents9 pa#ents and Settleent to assets 9 78, Entr# o- !ork -or persons9 and postin as acti"it# confration

!! Explain the following"a. Settlement #ules

Experience has shown that manual settlement rule maintenance for verycomplex project hierarchy structures is very time-consuming and bringswith it the risk of inconsistent characteristics in settlement of customerprojects to the profitability segment. The system uses automaticgeneration to create the settlement rule and parameters, in accordancewith the strategy defined in the I!. The type of planning decides whichstrategy applies to which object"Plannin eleentAccount assinent eleentBillin eleent

WBS eleent !ith chane o- orani<ation re the superiorWBS eleent

$. #elationship

8elationships deterine the chronoloical se5uence o- the indi"idualacti"ities in a net!ork (or standard net!ork); 2ou can enter additionaldata (such as a tie inter"al or -actor# calendar) on the detail screen o-each relationship;

'n the net!ork structure raphic9 #ou can displa# relationships =tiedependentl#=9 in order to illustrate the loical se5uence o- e"ents; B#de-ault9 all relationships are displa#ed as FS relationships in thenet!ork structure raphic;

FS SS FF SF

a!e

Page 10: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 10/15

c. ilestone %illing

ilestones are an event with a special meaning. It can be used in a project todesignate significant events or the completion of a project phase.

These are used in the #roject $ystem"

%or progress analysis

&s release stop indicators

To trigger predefined functions and workflow tasks

%unction

In milestone billing, the following functions are carried out at item level"

'etermining billing document value on a percentage basis

'ates at header level are copied from all item billing plans assigned to that header.(hen you make changes at header level )e.g. new billing dates or changes topercentage rates*, the related items are automatically changed accordingly. Thesystem does not allow you to make changes at item level.

!& Explain the following operati'e indicatorsa. Acct. Assignment Element 

In assembly processing the cost object is either the sales order or theproject )(+$ element*. In most cases you use the project as the costobject. owever, if you do not want to work with projects, but want to usenetworks, you can use the sales order as the cost object.

$. Planning Element 

This indicator controls whether a cost planning is possible only in those (+$elements which were defined as planning elements.

If you do not set this indicator, you can carry out cost planning in any (+$element.If you check this indicator in the planning profile system will allow you to doplanning only for the (+$ elements that have the #lanning Element indicatorticked.Even the % help for the #lanning Element indicator in a (+$ element states thesame. 'o revert if you come across something different.

c. %illing Element 

Element on which evenues can be planned and posted.

!( Explain the )ollowing"a. *nternally Processed Acti'ity 

 2ou ust enter !ork data -or an acti"it# so that the s#ste can plancapacities -or a project and calculate costs -or acti"ities; 2ou needto speci-# the aount o- !ork in"ol"ed and the !ork center that isto per-or the !ork;

a!e 10

Page 11: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 11/15

Work is the output to 4e pro"ided 4# achines or personnel in orderto coplete an acti"it#;

$. Externally Processed Acti'ity 

 /ou can create externally processed activities in your network - forexample, if you award the contract for designing a machine to an

external design agency.

The system takes the data in the activity and creates a purchasere0uisition which is processed by the purchasing department. %orexternal processing purposes, you can refer to data from thepurchasing department - for example, to a purchasing info record. Thiscontains the prices and delivery times applying to external processing.

c. Ser'ice Acti'ity 

A ser"ice acti"it# triers a purchasin process siilar to the kindtriered 4# an e*ternall# processed acti"it#9 4ut can also contain ahierarch# o- planned ser"ices to 4e purchased -ro the "endor and "alueliits -or unplanned ser"ices;

&he =oods receipt= o- ser"ices in"ol"es t!o steps,

Entr# o- ser"ices per-ored

Acceptance o- ser"ices per-ored;

For ser"ice acti"ities9 #ou can aintain ser"ice specifcations -or "arious

ser"ices to 4e pro"ided 4# the ser"ice pro"ider (planned ser"ices); 2ou canuse "alue liits to restrict ser"ices that the ser"ice pro"ider has notplanned;

 2ou can create the link to the MM Ser"ice coponent (MM6S8:) 4#eans o- ser"ice acti"ities;

!+ Write short notea. Project Planning %oard

The project planning board has a central position in the #roject $ystem. Itsimplifies planning and controlling projects. The project planning board allows

integrated processing of your project, giving you a graphic overview of theproject objects. In the graphic interface you can create, edit and evaluate allthe data for a project. /ou can change the appearance of the project planningboard to suit your individual needs and taste.

(ith the project planning board•  2ou o4tain an o"er"ie! a4out the hierarch# and proress o-

#our project

a!e 11

Page 12: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 12/15

•  2ou can see interrelationships in the orani<ation and theschedule;

•  2ou can access all the iportant data in #our project9 and-or e*aple

$. ,apacity Planning

The economic use of resources is an objective for many areas of acompany. The component 12apacity #lanning1 is available in the 34$ystem for this purpose.2apacity planning supports planning in all its phases"

• lon6ter rouh6cut plannin• ediu6ter plannin• short6ter detailed plannin

c. Scheduling

In the project system you can plan various date types, such as basic datesand forecast dates. In this process, you plan basic dates only. To do this,you copy the scheduled dates of the activities into the dates of the (+$elements.

To carry out the scheduling, you call up the planning board from the#roject +uilder. The project planning board provides you with anoverview of the hierarchy and the se0uence of your project.It is subdivided into two areas"A ta4le area !ith in-oration a4out the o4jects (le-t side)A raphical representation o- the schedulin situation

(riht side) /ou can change the si5e of the individual areas by dragging theseparator lines.

!- Which parameters to $e congured under project prole?!/ What is settlement?

2osts and revenues are collected in projects only temporarily. They are settled to one or

more receivers as part of period-end processing.

 /ou use settlement to"• %apitali<e the 4alance -ro results anal#sis !hich is capa4le o-

capitali<ation in the 4alance sheet;

• 34tain detailed data in results anal#sis -or enterprise controllin;

• 'n capital6in"estent easures9 to settle the chare to assets under

construction !hich can or ust 4e capitali<ed;

• 'nclude actual costs -ro the project in actual price calculation in %ost

%enter Accountin;

a!e 12

Page 13: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 13/15

'nteration

 /ou cannot transfer settlement rules to simulation versions or maintain them there.

 /ou use the settlement profile to define the following for actual costs"

• Must 4e settled in -ull

• %an 4e settled

• Must not 4e settled

'epending on the settings in the settlement profile, you must settle the costs of an object

in full before you can archive it.

!0 Which parameters we congure under settlement prole?&1 What is ##%? Explain with example

An# copan# !ho 4ills there custoer accordin to resources consued

&1 What is scheduling?

In the project system you can plan various date types, such as basic datesand forecast dates. In this process, you plan basic dates only. To do this,you copy the scheduled dates of the activities into the dates of the (+$

elements.

To carry out the scheduling, you call up the planning board from the#roject +uilder. The project planning board provides you with anoverview of the hierarchy and the se0uence of your project.It is subdivided into two areas"A ta4le area !ith in-oration a4out the o4jects (le-t side)A raphical representation o- the schedulin situation

(riht side) /ou can change the si5e of the individual areas by dragging theseparator lines.

&2 Explain di3erence $etween %udgeting and Planning?

a!e 13

Page 14: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 14/15

&! What are the types of cost planning?

Plannin61) Eas# cost plannin

 /) Manual %ost Plannin (WBS)6 a)+etailed plannin

4)>nit cost

  c) hierarchial cost plannin

 0) Autoatic costin in et!ork?Acti"ities

 Eas# %ost Plannin 

The Easy 2ost #lanning tool enables you to plan costs at (+$ level, based on 0uantitiesand characteristics. E2# can also be used for Internal 6rders 7 &ppropriation e0uests.

 /ou use it to create 0uantity structures )possibly temporary* for the cost calculation,

starting from the project structure. The system valuates your entries using the prices andrates defined in the system, then distributes the costs in line with the basic dates for therespective (+$ elements.

 >nit %ostin 

a!e 1&

Page 15: Project System

7/21/2019 Project System

http://slidepdf.com/reader/full/project-system-56daf3fcaeb37 15/15

The Easy 2ost #lanning tool enables you to plan costs at (+$ level, based on 0uantitiesand characteristics. E2# can also be used for Internal 6rders 7 &ppropriation e0uests.

 /ou use it to create 0uantity structures )possibly temporary* for the cost calculation,starting from the project structure. The system valuates your entries using the prices andrates defined in the system, then distributes the costs in line with the basic dates for therespective (+$ elements.

&& What is di3erence $etween Project System and product?&( Explain the project phases?

a!e 1*


Recommended