Date post: | 23-Apr-2017 |
Category: |
Documents |
Upload: | ukesh-shrestha |
View: | 224 times |
Download: | 5 times |
Presented By: Ukesh Shrestha069MSR519
AThesis Proposal presentation on
A Study on Techno-Economic Analysis of Utility Scale Solar PV Power Plant ( A case
study on proposed area of one hydropower plant
of NEA)
IntroductionProblem StatementObjectiveLiterature ReviewMethodologyTime and ScheduleBudgetExpected OutcomeReferences
Overview
Energy Demand increment day by day causing energy crisis in world
Above 80% of Energy from fossil fuel in world Increasing cost of fossils fuels and dependency
on its import ,GHG emission is big challenge Necessitated an urgent search for alternative
energy sources to meet up the present day demands
Renewable energy is the next step to fill out the gap of energy crisis in the future
Introduction
Nepal a victim of energy crisisNepal rich in renewable energy potential and poor
in fossil fuel resources but heavy import of fuel causing heavy imbalance
Major electricity source hydropower and rest fossil fuel
The story of power position in Nepal is that of highest potential and lowest consumption and generation.
Nepal a land lock country and here the import of fossil fuel is a big problem ,cost increasing day by day
Introduction Contd…
Country Per capita kwhr electricity consumption
Nepal 93India 644Bangladesh 279Srilanka 445Pakistan 457China 2942
Introduction Contd..
Nepal has the lowest per capita electricity consumption in asia. It is the index for development which signifies nepal lags energy.
Introduction Contd..
Todays ScenarioElectrical Energy Demand 2013 5900 GWhrElectrical Energy Supply 2013 4200 GWhrPeak Demand 1100 MWInstalled capacity 800 MW (For Monsoon)Projected Loadshedding hrs 14 hr
Introduction Contd..
Electricity is pillar of development800 MW capacity with 39 MW Multifuel and 14 MW
diesel plant but peak demand 1070 MWThermal plant are Costlier and cause of GHG emission although fast erectionHydropower plant highInitial cost and take longTime to complete with Delays.Purchase from India is limitedTo 100 MW due to Tr Lines
Introduction contd…
Wind energy possibility to rural areas far fromINPS grid Solar energy is availaible in every areas with good insolation average
of 4.7 Kwhr/m2.Solar power plant can be erected in low time Solar energy is free and no GHG emission only problem is that its
initial cost is heavy and hard to finance. Solar energy can be converted to electricity by solar thermal power
plant and solar PV power plant Cost of generation is lower for Solar PV power plant than thermal Germany getting half of insolation has increased installation from 6
GWp to 32 Gwp in 5 years Solar PV grid tied system have been feasible in many countries as its
overall cost has been decreasing Its time for study on large scale PV plant and implementation as
technology is becoming mature day by day with decrease in cost of panels and increase of efficiency.
Introduction Contd…
Introduction Contd..
Introduction Contd…
Introduction Contd..
Introduction Contd….
Overview of utility solar power plant
Why Utility Grid Tied Solar PV plant?Currently nation facing severe Loadshedding even at day big
impact to industrialist and institution and offices.Grid Tied Rooftop revolution is yet to take place due to lack of
appropriate rules,policies,subsidiesNEA is only the service oriented utility responsibile to tackle
energy crisis should have a proper energy mixHydropower taking longer period than expected,Thermal plant
causing huge loss to nationFaster Installation, Lower maintenanceNo GHG emissions as compare to diesel and Multifuel plantDevelop appropriate professionalism in Solar PV sectorCost effective in comparison to thermal plantCan be controlled easily thus more reliable and safe operation.
Introduction Contd…
Energy demand increasing at faster pace than Energy AvailaibilityLoadshedding hours of previous year was 18 hrs which decrease to
13 hrs this year and expected to increase in forthcoming yearsWe are bearing load shedding even at day when we have plenty of
solar energy potentialProper energy mix and use of renewable energy is must to solve the
problem To increase energy availability at a quick rate ,large scale Solar
grid tied PV would be fruitful as it has lower time of installation. Solar PV power plant can be utilized to fulfill energy demand and
decrease use of diesel generator to extent.Major significant cost in erection of PVplant is the high cost of land and availaibility of land near load center which increase cost per unit.
Hydropower area may be suitable for minimising overall cost.
Problem Statement
To carry out techno-economic feasibility analysis of grid connected utility scale solar PV system (selected area – NEA hydropower project).
Other objective Site Selection of NEA hydropower project area for utility solar PV plant
installation Considering grid capability,amount of insolation,area possesed for >=1MWp)
Estimate the grid capability to inject solar photovoltaic power in selected site
Financial analysis of the project and check requirement of subsidy from government to make feasible
To model the complete grid connected solar PV system for selected area using PVSYST
To suggest scheme for connecting solar based plants with thestation electric supply system for hydro electric power plants.
Recommend possible tasks for mitigation of day load shedding
Objective
Problem FormulationLiterature ReviewData collection,consult teacherSite Selection,Scheme SelectionField SurveyData compilation DesignAnalysis conclusion and recommendationThesis writing submission
Methodology
The Grid connected PV has been studied and implemented successfully in many countries specially developed countries like Germany, Japan, Italy,Greece etc. In context of Nepal the Grid connection of PV power has just been beginning.
Grid connected PV system without storage has lower cost as batteries have become more expensive
Grid connected system of 1 kwp was installed for R&D purpose in CES , 3 kwp in NEA center and 1 kwp with battery backup in RIDS office.
Research shows their feasibility in terms of economics and safety as well.
In large scale only grid tied solar plant is 680.4 Kwp at sundarighat at KUKL premises.It is fully operational. Loss of energy is occuring due to load shedding
As Grid connected PV system only works when grid is functional for safety purpose.
Literature Review
D. Chianese, D. Pittet, J.N. Shrestha, D. Sharma, A. Zahnd, N. Sanjel, M. Shah and M. Uphadyaya present a paper on Feasibility study on Grid connected PV system in Nepal . Paper concludes climatic conditions of Nepal ideal for solar energy technology. Initial investment high but paid off by a high production and by cost of 19.6NRs/kWh is by far less than produced by systems at use in households during load shedding periods (inverter-batteries: 54.0NRs/kWh;genset: 55.4 NRs/kWh), or by thermal power plant (ca. 30NRs/kWh).
A thesis on “Study on grid connected PV in Nepal” by N. Bhattarai, Pulchowk Campus, 2004 has studied the grid connection with solar panels and STAC research focused on the Energy opportunities of BIPV system at CES where loss of energy (excess energy after charging battery) have been considered. Economic analysis of four different scenarios have been determined and solar grid connected system with some subsidy has been found to be feasible.
Literature Review Continued
A thesis on” Performance analysis of one kilowatt grid connected solar photovoltaic (PV) electric system.” by Ajay Bhattarai, Pulchowk Campus, 2069 performs analysis for 1kWp grid connected solar PV system at (CES),Performance grid tied solar PV by calculating different performance indices like performance ratio, different yields and eficiencies. The effect of solar irradiance on PV array output and inverter efficiency analyzed . The analysis of data indicates that the average final yield was 2.31kWh/day; array yield was 2.64 kWh/day and performance ratio of 0.488 under the normal load shedding. The financial analysis was done for current load shedding pattern and the condition without the load shedding.Per unit cost of electricity was found to be NRs 16.63.
A thesis on” Techno – Economic Analysis of Grid Connected Rooftop Solar PhotovoltaicSystem (A case study of Pulchowk Campus) by Reena Shrestha, Pulchowk Campus, 2069 presents studies on PV grid connected systems in roof top of pulchowk campus. Per unit cost of the project was found to be 10.3 cents without considering project area land cost. If we considered land cost too, per unit cost could be greater that this value. Total cost of the project will be returned in 11 years if the discount rate is considered as 9 % and PPA rate is taken as 23 cents with 2% escalation rate.
Literature Review Contd..
Time and Schedule
BUDGETResearch work includes extensive data collection, system
design and economic analysis. The cost for collection of energy consumption data, field visit cost and the cost for preparing report are major cost research work. The estimated cost for carrying research work is about Rs. 70,000.
EXPECTED OUTCOMEMonthly ,yearly generation from plant ,cost of
generation,cost per unit generated,levelised cost of electricity,calculation of financial indicator and recommendations for rapid development of solar pv power and technologies and GHG reduction potentials outcomes of research work.
Budget and outcome
Nabraj Bhattarai ,2004,"Study on Grid-Connected PV Systems in Nepal",M Sc Thesis,Department of Mechanical Engineering, Pulchowk Campus,Tribhuvan University.
“Design Optimization and Simulation of the Photovoltaic Systems on Buildings in Southeast Europe, "by Florin Agai, Nebi Caka, Vjollca Komoni, Faculty of Electrical and Computer Engineering, University of Prishtina, Prishtina, Republic of Kosova.
Hand book for Solar Photovoltaic System; from Energy Market Authority given at www.ema.gov.sg
D. Chianese, D. Pittet, J.N. Shrestha, D. Sharma, A. Zahnd ,N. Sanjel, M. Shah and M Uphadyaya ,2009,"Feasibility study on Grid connected PV system in Nepal" ,Institute for Applied Sustainability to the Built Environment, University of Applied Science of SouthernSwitzerland – SUPSI NSES and Center for Energy Studies, Institute of Engineering, Tribhuvan University RIDS-Nepal (NGO) and Kathmandu University
Ajay Bhattarai, 2069 ,"Performance analysis of one kilowatt grid connected solar photovoltaic (pv) electric system.” M Sc Thesis,Department of Mechanical Engineering, Tribhuvan University
Reena shrestha ,2069 ” Techno – Economic Analysis of Grid Connected Rooftop Solar
PhotovoltaicSystem (A case study of Pulchowk Campus) “ , M Sc. Thesis ,Department of Mechanical Engineering,Pulchowk campus,Tribhuvan University.
http://www.pv-tech.org Wikipedia
References
User’s guide PVsyst Contextual Help downloaded from website www.pvsyst.com Grid-connected solar PV systems, No battery storage, Design Guidelines for
Accredited Installers 2013, developed by Clean Energy Council, Australia; https://www.cleanenergycouncil.org.au
Solar Photovoltaic System Design Manual For Solar Design Engineers, July 2003, Center for Renewable Energy, Kathmandu, Nepal.
Study of Harmonics and its Impacts on Power Quality in PV Grid Connected System Modeling” (Raut, 2012)
"Grid-Connected Solar Electronics", Mervin Johns, Hanh-Phuc Le and Michael Seeman, University of California at Berkeley Department of Electrical Engineering and Computer Sciences
. Technical note “Potential and viability of grid-connected solar PV system in Bangladesh” by Md. Alam Hossain Mondal , A.K.M. Sadrul Islam, Center for Development Research (ZEF), University of Bonn, Walter Flex Str. 3, 53113 Bonn, Germany, Department of Mechanical & Chemical Engineering, Islamic University of Technology, Gazipur, Bangladesh
Techno-economicanalysisofsolarphotovoltaicpowerplant for garmentzoneofJaipurcity$ Mevin Chandel,G.D.Agrawal,SanjayMathur,AnujMathur
References Contd…