Protocol Revision Subcommittee. Sandy Morris December 6, 2010. Summary of PRRs and NPRRs. 1 NPRRs for Approval 3 NPRRs for Parking Deck Considerations 1 SCR for Approval (See ROS agenda item) 0 Rejections 0 Withdrawals (PRRs). Items for a Vote. Unanimous Recommendations - PowerPoint PPT Presentation
Popular Tags:
15
Protocol Revision Subcommittee Sandy Morris December 6, 2010
Transcript

Protocol Revision Subcommittee

Sandy Morris

December 6, 2010

2

Summary of PRRs and NPRRs

1 NPRRs for Approval

3 NPRRs for Parking Deck Considerations

1 SCR for Approval (See ROS agenda item)

0 Rejections

0 Withdrawals (PRRs)

3

Items for a Vote

• Unanimous RecommendationsNPRR295, Synchronization of Protocol for Generation Resource Designation as Mothballed or Decommissioned

4

Items for a Vote

• Non-unanimous RecommendationsNPRR260, Providing Access to MIS Secure Area to MIS Registered Users

NPRR282, Dynamic Ramp Rates Use in SCED

NPRR293, Requirement to Post PTP Obligation Quantities Awarded in DAM (formerly “Requirement to Post CRR Option and Obligation Quantities Cleared in DAM or Taken to Real Time”)

NPRR295, Synchronization of Protocol for Generation Resource Designation as Mothballed or Decommissioned

Purpose

(ERCOT)

This NPRR synchronizes the Nodal Protocols with zonal Protocol Section 6.5.9.3, Generation Resource Return to Service Updates, regarding return-to-service of Mothballed or Decommissioned Generation Resources. In addition, a clarification was made for removal of Decommissioned Generation Resources from ERCOT registration systems.

Market Impact No Impacts

System Change No

PRS Vote On 11/18/10, PRS unanimously voted to recommend approval of NPRR295 as submitted and to forward NPRR295 and the Impact Analysis to TAC.

Effective Date/Priority

February 1, 2010

Item Reviewed DescriptionNoImpact

Credit Monitoring/Liability

Budget

Staffing

Computer Systems

Business Functions

Grid Operations

Impact

NPRR295, Synchronization of Protocol for Generation Resource Designation as Mothballed or Decommissioned

NPRR260, Providing Access to MIS Secure Area to MIS Registered Users

Purpose

(Crescent Power)

This NPRR adds "Independent Market Information System Registered Entity (IMRE)" to Section 2.1 and Section 22, Attachment A. By doing so, the Standard Form Market Participant Agreement would bind IMREs to the Nodal Protocols and, in particular, provisions in Section 16.12, Use Security Administrator and Digital Certificates.

Market Impact Impact Analysis will be conducted at a future date

System Change TBD

PRS Vote On 10/21/10, PRS voted to recommend approval of NPRR260 as amended by the 9/17/10 ERCOT comments and as revised by PRS. There were three abstentions from the Consumer, IPM, and Independent Generator Market Segments. On 11/18/10, PRS voted to endorse and forward the 10/21/10 PRS Report as revised by PRS and Impact Analysis for NPRR260 to TAC and to assign NPRR260 a priority of Medium. There was one abstention from the Independent Generator Market Segment.

Effective Date/Priority

Upon System Implementation – Priority Medium

NPRR282, Dynamic Ramp Rates Use in SCED

Purpose

(Calpine)

This NPRR proposes revisions that are intended to result in more reasonable Dispatch of Generation Resources when a telemetered Base Point requires the Resource to employ technologies that in turn change the Resource’s ramp rate

Market Impact Impact Analysis will be conducted at a future date

System Change TBD

PRS Vote On 10/21/10, PRS voted to recommend approval of NPRR282 as amended by the 10/18/10 Luminant comments. There was one abstention from the Municipal Market Segment. On 11/18/10, PRS unanimously voted to endorse and forward the 10/21/10 PRS Report and Impact Analysis for NPRR282 to TAC and to assign NPRR282 a priority of Critical.

Effective Date/Priority

Upon System Implementation – Priority Critical

NPRR293, Requirement to Post PTP Obligation Quantities Awarded in DAM (formerly “Requirement to Post CRR Option and Obligation Quantities Cleared in DAM or Taken to Real Time”)

Purpose

(Luminant)

This NPRR adds language to specify the need for ERCOT to post quantities of Point to Point (PTP) Obligations that were awarded in the Day-Ahead Market (DAM).

Market Impact Impact Analysis will be conducted at a future date

System Change TBD

PRS Vote On 11/18/10, PRS voted to recommend approval of NPRR293 as amended by the 11/17/10 Luminant Energy comments and as revised by PRS; to assign NPRR293 a priority of High; and to forward NPRR293 to TAC. There was one abstention from the Independent Generator Market Segment.

Effective Date/Priority

Upon System Implementation – Priority High

10

NPRRs Withdrawn or Rejected

• Withdrawn PRRs– None

• Rejected NPRRs– None

11

Nodal Parking Deck – Prioritization Guidelines

PriorityPriority DefinitionDefinition

Critical

Required by Statute, PUCT Order, NERC compliance or critical reliability of:• Grid Operations• IT Infrastructure• Commercial Settlement

High High value for a majority of market segments or ERCOT

High / MediumHigh value to one or two segments, orMedium value for a majority of market segments or ERCOT

Medium Medium value for only one segment

12

Nodal Parking Deck – Approved by ERCOT Board

SourceSource TitleTitle PriorityPriority Approval DateApproval Date

NPRR208Registration and Settlement of Distributed Generation (DG) Less Than One MW Critical BoD Approved 7/20/2010

NPRR219Resolution of Alignment Items A33,A92,A106,A150 - TSPs Must Submit Outages for Resource Owned Equipment & Clarification of Changes in Status of Transmission Element Postings

Critical BoD Approved 10/19/2010

NPRR285Generation Resource Base Point Deviation Charge Corrections Critical BoD Approved 11/16/2010

NOGRR050 Resolution of Reporting Issues Related to NPRR219 Critical BoD Approved 10/19/2010

SCR756 Enhancements to the MarkeTrak Application Critical BoD Approved 7/20/2010

NPRR131 Ancillary Service Trades with ERCOT High BoD Approved 1/19/2010

NPRR146 ICCP Telemetry Information Submittals High BoD Approved 6/15/2010

NPRR181 FIP Definition Revision High BoD Approved 1/19/2010

NPRR207 Unit Deselection High BoD Approved 7/20/2010

NPRR210 Wind Forecasting Change to P50, Synch PRR841 High BoD Approved 6/15/2010

NPRR222 Half-Hour Start Unit RUC Clawback High BoD Approved 7/20/2010

On Parking Deck due to resource impact only. Separately funded on 2011 PPL.

page 1 of 3

13

Nodal Parking Deck – Approved by ERCOT Board

SourceSource TitleTitle PriorityPriority Approval DateApproval Date

NPRR251Sync of PRR845, Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned

High BoD Approved 9/21/2010

NPRR272Definition and Participation of Quick Start Generation Resources High BoD Approved 11/16/2010

SCR759acLineSegment Name Length Increase in Information Model Manager

High BoD Approved 9/21/2010

NPRR240 Proxy Energy Offer CurveHigh /

MediumBoD Approved 9/21/2010

NPRR244 Clarification of Other Binding DocumentsHigh /

MediumBoD Approved 10/19/2010

NPRR257Synchronization with Nodal Operating Guide Section 9, Monitoring Programs

High / Medium

BoD Approved 11/16/2010

NPRR258Sync with PRR824 and PRR833 and Additional Clarifications

High / Medium

BoD Approved 11/16/2010

NPRR153 Generation Resource Fixed Quantity Block Offer Medium BoD Approved 1/19/2010

NPRR164 Resubmitting Ancillary Service offers in SASM Medium BoD Approved 1/19/2010

page 2 of 3

14

Nodal Parking Deck – Approved by ERCOT Board

SourceSource TitleTitle PriorityPriority Approval DateApproval Date

NPRR241Aggregate Incremental Liability (AIL) Calculation and Credit Reports Publish Corrections

Medium BoD Approved 9/21/2010

NPRR256Sync Nodal Protocols with PRR787, Add Non-Compliance Language to QSE Performance Standards Medium BoD Approved 11/16/2010

NOGRR034Rescind Telemetry Performance Calculation Exclusions

Medium BoD Approved 9/21/2010

SCR755 ERCOT.com Website Enhancements Medium BoD Approved 2/16/2010

page 3 of 3

15

Nodal Parking Deck – Pending

SourceSource TitleTitle Suggested Suggested PriorityPriority Current StatusCurrent Status

NPRR260Providing Access to MIS Secure Area to MIS Registered Users Medium

Pending at TACPRS Approved 11/18/2010

NPRR282 Dynamic Ramp Rates Use in SCED CriticalPending at TAC

PRS Approved 11/18/2010

NPRR290 ERCOT Publication of DAM PSS/E Files TBD Pending at PRS

NPRR293Requirement to Post CRR Option and Obligation Quantities Cleared in DAM or Taken to Real Time High

Pending at TACPRS Approved 11/18/2010

SCR760Recommended Changes Needed for Information Model Manager and Topology Processor for Planning Models Critical

Pending at TACPRS Approved 11/18/2010

Total Pending = 5

The following item was removed from the Parking Deck in the past month: NPRR281 – Replace 7-Day Forecast Requirement for QSEs Representing WGRs