+ All Categories
Home > Documents > PT INDONESIA POWER GAS (LNG) UTILIZATION FOR...

PT INDONESIA POWER GAS (LNG) UTILIZATION FOR...

Date post: 23-Mar-2021
Category:
Upload: others
View: 4 times
Download: 1 times
Share this document with a friend
19
PT INDONESIA POWER GAS (LNG) UTILIZATION FOR POWER GENERATION 4 th Gas Forum Special Focus on Technology JUDI WINARKO Head of Primary Energy Division DIVISI ENERGI PRIMER PT INDONESIA POWER
Transcript
Page 1: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

PT INDONESIA POWER GAS (LNG) UTILIZATION FOR POWER GENERATION

4th Gas Forum Special Focus on Technology

JUDI WINARKO

Head of Primary Energy Division

DIVISI ENERGI PRIMER PT INDONESIA POWER

Page 2: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

Overview 35.000 MW Electricity Projects

Page 3: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

Indonesia Electricity System

Page 4: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

PLN - 35.000 MW Electricity Program

Page 5: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

New Additional Gas Power Plant (35.000 MW)

Page 6: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

LOCATION GAS POWER PLANT

Page 7: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

LNG Demand

KEY WORD : - LONG TERM SECURITY LNG SUPPLAY - LNG LOGISTIK SYSTEM & MID STREAM FACILITIES

Page 8: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

Gas infrastructure for electricity

Page 9: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

Indonesia Power

Contribution for 35.000 MW

Electricity Projects

Page 10: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

PT Indonesia Power

Page 11: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

Gas Supplier for IP Gas Power Plant (existing)

No Gas Power Plant Pipeline/LNG Gas Source (PSC) Contract Capacity

1. Priok CCGT Block 1-3 Pipeline Gas PHE ONWJ 100 bbtud

Pipeline Gas PGN 27-30 bbtud

LNG Bontang, Tangguh

150 bbtud

2. Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP

50 bbtud

Pipeline Gas KJG/PCML 116 bbtud

3. Grati CCGT Pipeline Gas Santos 75 bbtud

4. Dual Fuel Gas Engine Pesanggaran Bali

LNG PEL 40 bbtud

Page 12: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

12

FSRU West Java operated by PT Nusarantara Regas, deliver gas supply for Muara Karang dan Priok CCPPs (4000 MW) around 27 cargo per year

CNG Plant, Compressed Natural Gas (250 bar) and deliver gas at pickload time : CNG Plant Grati, cap. 15 bbtud operate by PT Energi Transportir Indonesia CNG Plant Tambak Lorok, cap. 17 bbtud operate by PT Pertadaya Gas

Page 13: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

IP Project in 35.000 MW Gas Power Plant

No Project Capacity (MW)

COD Remark

1. Perak CCGT (Peaker) DMN : 540 2019 21 BBTUD,Gas from Kangean Efficiency : 49.8 % - 60 %

2. Tambak Lorok Block III

700 2019 Gas from Kepodang (existing 116 BBTUD)

3. Grati Add on 150 2019 HRSG installment at Block II, Increase PP Efficiency from 32% - 48%

5. Clustering Barge Mounted Power Plant

350 (total) 2018 Cluster 1 : Sulbagsel, Lombok & Kalseltengtim • 1 Barge 120 MW • 3 Barge - @ 60 MW Cluster 2 : NTT, Maluku, Papua • 2 Barge - @ 25 MW

6. Tg Priok Block IV 740 2019 (est) O&M opportunity (PLN’s project)

7. Grati Block III 450 2019 (est) O&M opportunity (PLN’s project)

Page 14: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

Cluster 1 : Sulbagsel, Lombok & Kalseltengtim • 1 Barge 120 MW • 3 Barge - @ 60 MW

Cluster 2 : NTT, Maluku, Papua • 2 Barge - @ 25 MW

GOALS : (i) High Utilisation & Flexible for multi system (ii) For Demand & Reserved Margin

Sumatera Kalimantan

Sulawesi

Maluku

Papua

Nusa Tenggara Java-Bali

1

2

CLUSTERING BARGE MOUNTED POWER PLANT (Total ± 350MW)

Page 15: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

FSRU West Java operated by PT Nusarantara Regas, deliver gas supply for Muara Karang dan Priok CCPPs (4000 MW) around 27 cargo per year

CNG Plant, Compressed Natural Gas (250 bar) and deliver gas for pikeload time : - Grati, cap. 15 bbtud operate by PT

Energi Transportir Indonesia. - Tambak Lorok, cap. 17 bbtud operate

by PT Pertadaya Gas

Page 16: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

Floating Storage, Regas & Terminal LNG Benoa Bali, operated by PT Pelindo Energi Logistik.

Page 17: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

KONSEP FACILITAS MIDSTREAM GAS BALI

Page 18: PT INDONESIA POWER GAS (LNG) UTILIZATION FOR ...indonesiangassociety.com/wp-content/uploads/2016/06/PD-5...Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP 50 bbtud Pipeline Gas KJG/PCML

LNG Supplay Chain

1. LNG Plant Terminal • Size of Jetty • Facility Loading (Loading arm, Flexible hose) • LNG/Gas Quality

2. LNG Carrier • Vessel, Barge/LCT • Tank Type/Cargo Containment System

3. HUB • Size (standard, mini)

4. Receiving Terminal (Floating, Land base) • Size of Jetty • Unloading facility • Storage (Issotank, flat bottom) • Regas system (ambient, forced)

5. Gas Pipeline


Recommended