+ All Categories
Home > Documents > Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254...

Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254...

Date post: 05-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
32
Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River New Milford, Connecticut Thursday, October 5, 2017 at 7:00 pm John Pettibone Community Center 2 Pickett District Road New Milford, CT
Transcript
Page 1: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Public Information Meeting

State Project No. 095-254Rehabilitation of Bridge No. 00901

U.S. Route 202/Route 67Over Housatonic River

New Milford, Connecticut

Thursday, October 5, 2017 at 7:00 pmJohn Pettibone Community Center

2 Pickett District RoadNew Milford, CT

Page 2: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Project Location MapProject Location Map

N

Page 3: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

IntroductionsIntroductions

• Connecticut Department of Transportation–Rabih Barakat – Transportation Principal Engineer

-Andrew Cardinali – Transportation Supervising Engineer

-Dobieslawa Kania– Transportation Project Engineer

• Hardesty & Hanover–Steven Harlacker – Principal Associate

• CME Associates, Inc.–Donald Wurst – Department Manager

–Mark Gardner – Project Engineer

• Connecticut Department of Transportation–Rabih Barakat – Transportation Principal Engineer

-Andrew Cardinali – Transportation Supervising Engineer

-Dobieslawa Kania– Transportation Project Engineer

• Hardesty & Hanover–Steven Harlacker – Principal Associate

• CME Associates, Inc.–Donald Wurst – Department Manager

–Mark Gardner – Project Engineer

Page 4: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Department’s RoleDepartment’s Role

• Systematically inspect bridges for deficiencies and schedule the rehabilitation of structures

• Oversee the development of technical drawings and bid documents on projects

• Administration and inspection during construction

• Systematically inspect bridges for deficiencies and schedule the rehabilitation of structures

• Oversee the development of technical drawings and bid documents on projects

• Administration and inspection during construction

Page 5: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Project Needs and GoalsProject Needs and Goals

• Maintain a safe crossing over the Housatonic River for vehicles traveling on US Route 202/Route 67

• Rehabilitation and strengthening of bridge to extend service life

• Minimize disturbance for the traveling public during construction

• Improve roadway ride-ability for traveling public

• Maintain a safe crossing over the Housatonic River for vehicles traveling on US Route 202/Route 67

• Rehabilitation and strengthening of bridge to extend service life

• Minimize disturbance for the traveling public during construction

• Improve roadway ride-ability for traveling public

Page 6: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Project OverviewProject Overview

• Project is in preliminary design stage

– We are looking for your input

• Rehabilitation of bridge to repair deteriorated elements

• Strengthening of deficient truss connections to rate for HL-93 loading

• Preventive maintenance to ensure extended service life

• Project is in preliminary design stage

– We are looking for your input

• Rehabilitation of bridge to repair deteriorated elements

• Strengthening of deficient truss connections to rate for HL-93 loading

• Preventive maintenance to ensure extended service life

Page 7: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Bridge No. 00901(Veterans Memorial Bridge)

Bridge No. 00901(Veterans Memorial Bridge)

• Built in 1953

• Major rehabilitation project in 2000– full deck replacement,

substructure/superstructure repairs, sidewalk and railing replacement, full painting

• Gusset plate strengthening completed in 2011

• Single-span steel through truss structure supported by two abutments

• Built in 1953

• Major rehabilitation project in 2000– full deck replacement,

substructure/superstructure repairs, sidewalk and railing replacement, full painting

• Gusset plate strengthening completed in 2011

• Single-span steel through truss structure supported by two abutments

Page 8: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Existing Geometry

• Total Structure Length = approx. 332’

• Bridge curb-to-curb width = 30’-0” (13’ lanes, 2’ shoulders)

• Min. Vertical Clearance above Roadway: 15’-5” (centerline)

• ADT (2014): 30,700 vehicles per day

– 4% Truck Traffic

– 13,000 Eastbound and 17,700 Westbound

Existing Condition Ratings

• Deck: “7” Good

• Superstructure: “4” Poor

• Substructure: “6” Satisfactory

• Structure Evaluation: “4” Poor

Structure Appraisals

• Deck Geometry: “4”

• Approach Roadway Alignment: “6”

• Scour Critical: “8” (Stable)

• Waterway Adequacy: “6”

Existing Geometry

• Total Structure Length = approx. 332’

• Bridge curb-to-curb width = 30’-0” (13’ lanes, 2’ shoulders)

• Min. Vertical Clearance above Roadway: 15’-5” (centerline)

• ADT (2014): 30,700 vehicles per day

– 4% Truck Traffic

– 13,000 Eastbound and 17,700 Westbound

Existing Condition Ratings

• Deck: “7” Good

• Superstructure: “4” Poor

• Substructure: “6” Satisfactory

• Structure Evaluation: “4” Poor

Structure Appraisals

• Deck Geometry: “4”

• Approach Roadway Alignment: “6”

• Scour Critical: “8” (Stable)

• Waterway Adequacy: “6”

Bridge No. 00901(Veterans Memorial Bridge)

Bridge No. 00901(Veterans Memorial Bridge)

Page 9: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

South Elevation

Bridge No. 00901(Veterans Memorial Bridge)

Bridge No. 00901(Veterans Memorial Bridge)

West Approach (Looking East)

Note: Sidewalk along North Fascia

Page 10: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Typical Bridge Curb and Railing

Bridge No. 00901(Veterans Memorial Bridge)

Bridge No. 00901(Veterans Memorial Bridge)

Typical Overlay

Page 11: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Typical Leaking at Deck Panel Joints

Note: Active Rust on Stringer and Beam

Bridge No. 00901(Veterans Memorial Bridge)

Bridge No. 00901(Veterans Memorial Bridge)

Typical Underside of Deck and Truss

Page 12: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Communication Conduits – North Fascia

Bridge No. 00901(Veterans Memorial Bridge)

Bridge No. 00901(Veterans Memorial Bridge)

Typical Rocker Bearing (West Abutment)

Page 13: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Northeast Wingwall (Typical)

Bridge No. 00901(Veterans Memorial Bridge)

Bridge No. 00901(Veterans Memorial Bridge)

East Abutment

West Abutment

Page 14: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Proposed Rehabilitation Measures:

• Structural steel repairs to truss members, gusset plates, and portal bracing

• Clean and paint all bearings

• Field touch-up painting of steel at repair locations and localized areas of missing paint

• Patch the reinforced concrete deck and sidewalk

• Placement of waterproofing membrane and new 3” thick overlay

• Deck joint replacement

• Replace bridge rail to meet new standards

• Repair pedestrian rail as necessary

• Anchor superstructure to substructure to resist stream flow forces and debris accumulation

• Mill and pave the approach roadways

• Clean the scuppers/drainage system

• Substructure patching

Proposed Rehabilitation Measures:

• Structural steel repairs to truss members, gusset plates, and portal bracing

• Clean and paint all bearings

• Field touch-up painting of steel at repair locations and localized areas of missing paint

• Patch the reinforced concrete deck and sidewalk

• Placement of waterproofing membrane and new 3” thick overlay

• Deck joint replacement

• Replace bridge rail to meet new standards

• Repair pedestrian rail as necessary

• Anchor superstructure to substructure to resist stream flow forces and debris accumulation

• Mill and pave the approach roadways

• Clean the scuppers/drainage system

• Substructure patching

Bridge No. 00901(Veterans Memorial Bridge)

Bridge No. 00901(Veterans Memorial Bridge)

Page 15: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Bridge No. 00901:Roadway Plan

Bridge No. 00901:Roadway Plan

Page 16: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Bridge No. 00901:Elevation

Bridge No. 00901:Elevation

Page 17: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Bridge No. 00901:Sections

Bridge No. 00901:Sections

Page 18: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Impacts to traffic on U.S. Route 202/67:

• Bridge work will occur in 4 stages of off-peak lane closures• The four stages of off-peak lane closures will involve the closure of

the four quadrants (northeast, southeast, northwest, southwest) and stages will be fully complete before next stage is started.

• Uniformed flagmen or local police will control alternating one-way traffic

• Three full closures will be required of the entire bridge• Full closure required for: milling, waterproofing membrane, and

paving

• All closures will occur overnight

• Shoulder closures will be required to repair the bridge rail.

Bridge No. 00901:Maintenance & Protection of Traffic

Bridge No. 00901:Maintenance & Protection of Traffic

Page 19: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Bridge No. 00901: Maintenance & Protection of Traffic (cont.)

Bridge No. 00901: Maintenance & Protection of Traffic (cont.)

Page 20: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Advanced signage will be placed to urge traffic to use the following detours:

• Traffic will be directed to Still River Drive over the Housatonic River then North on Grove Street to Bridge Street.

• There will be a signed passenger vehicle detour for traffic originating from/going to US Route 7 North of the bridge

• Boardman Rd to Housatonic Ave to Young’s Field Rd

• Low railroad bridge on Boardman Rd

Bridge No. 00901:Detour for Overnight Bridge Roadway

Closures

Bridge No. 00901:Detour for Overnight Bridge Roadway

Closures

Page 21: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Bridge No. 00901 –U.S. Route 202/67 over Housatonic

River

Detour Plan

Bridge No. 00901 –U.S. Route 202/67 over Housatonic

River

Detour Plan

Page 22: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Bridge No. 00901 –U.S. Route 202/67 over Housatonic

River

Detour Plan

Bridge No. 00901 –U.S. Route 202/67 over Housatonic

River

Detour Plan

Note: Passenger vehicles only because of low clearance bridge on route

Page 23: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Department of TransportationDivision of Rights of Way

(ROW)

Department of TransportationDivision of Rights of Way

(ROW)

Michelle MillerProject Coordinator

2800 Berlin TurnpikeP.O. Box 317546

Newington, CT 06131-7546

Michelle MillerProject Coordinator

2800 Berlin TurnpikeP.O. Box 317546

Newington, CT 06131-7546

Page 24: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

FunctionFunction

• Acquire all property/property rights necessary for transportation projects.

• Acquire all property/property rights necessary for transportation projects.

Page 25: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Statutory References Statutory References

• State of Connecticut

C.G.S. Sections 13a-73 & 13a-98e

• Federal

Uniform Relocation Assistance and Real

Properties Acquisition Act of 1970, as amended.

• State of Connecticut

C.G.S. Sections 13a-73 & 13a-98e

• Federal

Uniform Relocation Assistance and Real

Properties Acquisition Act of 1970, as amended.

Page 26: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Property Impacts Property Impacts

• Total Acquisitions

• Partial Acquisitions

• Easements

• Construction Easements

• Rights

* Note: Specific impacts are subject to change as the design progresses.

• Total Acquisitions

• Partial Acquisitions

• Easements

• Construction Easements

• Rights

* Note: Specific impacts are subject to change as the design progresses.

Page 27: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

ROW Acquisition ProcessROW Acquisition Process• Letter of Intent to Acquire

• Valuation

• Offer of Just

Compensation

• Negotiation

• Acquisition• Agreement

• Eminent Domain/Condemnation » 6 month appeal period

• Letter of Intent to Acquire

• Valuation

• Offer of Just

Compensation

• Negotiation

• Acquisition• Agreement

• Eminent Domain/Condemnation » 6 month appeal period

Page 28: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Timing for Acquisitions Timing for Acquisitions

• All property rights must be acquired by the Project Advertisement Date

• Current Project Advertisement Date: 2/27/2019

• All property rights must be acquired by the Project Advertisement Date

• Current Project Advertisement Date: 2/27/2019

Page 29: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Right-of-Way ImpactsRight-of-Way Impacts

Anticipated Impacts to Adjacent Properties

• Construction easement need for storage of materials and equipment at southwest corner and access for barge at northeast corner

Anticipated Impacts to Adjacent Properties

• Construction easement need for storage of materials and equipment at southwest corner and access for barge at northeast corner

N

Page 30: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Utility ImpactsUtility Impacts

The following utilities will require protection within the project limits:

• Overhead communication wires along the north side

• Electrical conduits and gas main mounted to lower chord of the south truss

• Communication conduits under sidewalk on north side

The following utilities will require protection within the project limits:

• Overhead communication wires along the north side

• Electrical conduits and gas main mounted to lower chord of the south truss

• Communication conduits under sidewalk on north side

Page 31: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Project Cost and ScheduleProject Cost and Schedule

Schedule

• Construction Start: Spring 2020

• Completion: Fall 2020

Cost

• Total construction cost for the project is currently

estimated at $3,400,000

• Rehabilitation of this bridge will be undertaken using

State and Federal Funds under the “National

Highway Performance” Program and “Surface

Transportation Program – Other Urban” Program.

The cost and schedule are preliminary and are subject

to change.

Schedule

• Construction Start: Spring 2020

• Completion: Fall 2020

Cost

• Total construction cost for the project is currently

estimated at $3,400,000

• Rehabilitation of this bridge will be undertaken using

State and Federal Funds under the “National

Highway Performance” Program and “Surface

Transportation Program – Other Urban” Program.

The cost and schedule are preliminary and are subject

to change.

Page 32: Public Information Meeting · 2017-10-10 · Public Information Meeting State Project No. 095-254 Rehabilitation of Bridge No. 00901 U.S. Route 202/Route 67 Over Housatonic River

Contact InformationContact Information

Thank You

Questions and Comments

Dobieslawa Kania – Transportation Engineer

Connecticut DOT

2800 Berlin Turnpike

P.O. Box 317546

Newington, CT 06131

Email: [email protected]

Phone:860-594-3389

Thank You

Questions and Comments

Dobieslawa Kania – Transportation Engineer

Connecticut DOT

2800 Berlin Turnpike

P.O. Box 317546

Newington, CT 06131

Email: [email protected]

Phone:860-594-3389


Recommended