IN DEGREE PROJECT MECHANICAL ENGINEERING, SECOND CYCLE, 30 CREDITS , STOCKHOLM SWEDEN 2018 QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING IMPROVEMENT OF TIGHTENING IN SCANIA’S CAB AS-SEMBLY AND IMPLEMENTATION INTO AN INDUSTRY 4.0 BASED SYSTEM CARLOS CERVANTES ESMAEIL NIK ARMAN KTH ROYAL INSTITUTE OF TECHNOLOGY SCHOOL OF INDUSTRIAL ENGINEERING AND MANAGEMENT
Transcript
Page 1: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

IN DEGREE PROJECT MECHANICAL ENGINEERING,SECOND CYCLE, 30 CREDITS

, STOCKHOLM SWEDEN 2018

QUALITY ASSURANCE THROUGH SMART ANGLE MONITORINGIMPROVEMENT OF TIGHTENING IN SCANIA’S CAB AS-SEMBLY AND IMPLEMENTATION INTO AN INDUSTRY 4.0 BASED SYSTEM

CARLOS CERVANTES

ESMAEIL NIK ARMAN

KTH ROYAL INSTITUTE OF TECHNOLOGYSCHOOL OF INDUSTRIAL ENGINEERING AND MANAGEMENT

Page 2: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

QUALITY ASSURANCE THROUGH

SMART ANGLE MONITORING

IMPROVEMENT OF TIGHTENING IN SCANIA’S CAB AS-

SEMBLY AND IMPLEMENTATION INTO AN INDUSTRY

4.0 BASED SYSTEM

CARLOS CERVANTES

ESMAEIL NIK ARMAN

Master of Science Thesis TPRMM 2018

KTH Industrial Engineering and Management

Production Engineering

SE-100 44 STOCKHOLM

Page 3: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

ii

Abstract

There is currently an increasing need for manufacturing companies to achieve flexible,

smart and reconfigurable processes in order to address a dynamic and global market (Santos,

et al., 2017). Scania being a worldwide truck manufacturer aims to bring its expertise in truck

production into an Industry 4.0 based system.

The bolt tightening process in the assembly workshop in Scania Oskarshamn presents

promising possibilities for implementation of an Industry 4.0 based system. By monitoring

angle during the tightening process the system is able to identify deviations occurring in the

process or machine (Bickford & Nassar, 1998). An accurate angle interval can be calculated

by studying the relationship between torque and angle using the linear regression method

(Pennsylvania State University, 2018). In this project the angle intervals have been improved

to be able to perform efficient monitoring.

The monitoring process creates the possibility for Scania to implement a smart system

able to identify, analyze and eliminate deviations in real time production. This is achievable

by performing Statistical Process Control (SPC) using the data obtained from production

(Gejdoš, 2015). In this project the Process Capability (Cpk) of the tightening process was im-

proved by 365%.

An actual smart process should be able to automatically perform the analysis of data,

monitor the life of the machine, identify deviations and support the decision making process

(Weihrauch, et al., 2018). To achieve this a proposal is presented to connect the tightening

machines to a statistical analysis software able to present data efficiently to involved person-

nel. The improvement of Cpk and analysis of life of the machine presented in this project

prove that it is possible to implement the torque control with angle monitoring technique into

an Industry 4.0 system.

Page 4: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

iii

Sammanfattning

Det finns för tillfället ett ökat behov för tillverkande företag att uppnå flexibla, smarta

och rekonfigurerbara processer för att kunna hantera en dynamisk och global marknad (San-

tos, et al., 2017). Scania är en världsomfattande lastbilstillverkare som strävar efter att för-

medla sin kompetens inom lastbilsproduktion till ett Industri 4.0-baserat system.

Skruvdragningsprocessen i monteringsverkstaden i Scania Oskarshamn erbjuder lovande

möjligheter att implementera ett Industri 4.0-baserat system. Genom att övervaka vinkeln un-

der åtdragningen, med hjälp av ett korrekt vinkelintervall, kan systemet identifiera avvikelser

som uppstår i processen eller maskinen (Bickford & Nassar, 1998). Ett exakt vinkelintervall

kan beräknas genom att studera förhållandet mellan vridmoment och vinkel med en linjär

regressionsmetod (Pennsylvania State University, 2018). I detta projekt har vinkelintervallet

förbättrats för att möjliggöra en effektiv övervakning.

Övervakningsprocessen skapar en möjlighet för Scania att implementera ett smart system

som kan identifiera, analysera och eliminera avvikelser i realtidsproduktion. Detta kan uppnås

genom att utföra statistisk processkontroll (SPC) med hjälp av data som erhållits från produkt-

ionen (Gejdoš, 2015). I detta projekt förbättrades processkapabiliteten (Cpk) för åtdragnings-

processen med 365%.

En smart process bör i praktiken automatiskt kunna analysera data, övervaka maskinens

livslängd, identifiera avvikelser och stödja beslutsprocessen (Weihrauch, et al., 2018). För att

uppnå detta, presenteras ett förslag för att ansluta åtdragningsmaskinerna till en statistisk ana-

lysprogramvara som kan presentera data effektivt för berörd personal. Förbättringen av Cpk

och analys av maskinens livslängd som presenteras i detta projekt visar att det är möjligt att

implementera momentstyrningen med vinkelövervakningsteknik i ett Industri 4.0-system.

Page 5: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

iv

Acknowledgments

First off we would like to thank all the people without whom this project would have not

been possible. We would like to extend our most sincere thanks and appreciation to Scania

CV AB in Oskarshamn as Södertälje for giving us the opportunity to perform this project.

We want to thank all the people from the MCEA department, maintenance personnel and

operators for supplying valuable information, taking their time to support us and making this a

great experience.

We want to thank everyone at the Department of Production Engineering (IIP) at the

Royal Institute of Technology (KTH) for the valuable knowledge that was provided to us and

which made the thesis possible.To our supervisor Jonny Gustafsson for his guidance during

the thesis.

Lastly we cannot thank enough our supervisor at Scania, Kerim Hakim without whom we

would not have had the opportunity to work this project. His support and knowledge has been

of great value to us and it has been excellent working together during the thesis.

Page 6: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

v

To my parents Blanca Barraza and Francisco Cervantes who have been the greatest sup-

port and without whom I would not be the person I am today. To my brothers, thanks for al-

ways being there for me. And to my oldest brother for his support in this journey of moving to

Sweden. Thank you all for everything.

Carlos Cervantes.

Page 7: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

vi

To Ferdos

whom this journey could not be possible without her pure and tremendous support.

To Liana, Diana and Mehrsam

for bringing joy and enthusiasm to my life, in a way I never experienced before.

Esmaeil Nik Arman

Page 8: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

vii

Nomenclature

NTG New Truck Generation

C joints Critical joints / Safety Critical Joints

L joints Legal Requirements / Legal Joints / Joints essential for function

ERP Enterprise Resource Planning

MES Manufacturing Execution System

SCADA Supervisory Control and Data Execution

HMI Human Machine Interface

PLM Product Lifecycle Management

PSB Plant Service Bus

DSS Decision Support System

SPCS Smart Process Control System

SPC Statistical Process Control

ANOVA Analysis of Variances

SNR Signal-to-Noise Ratio

OA Orthogonal Array

DOF Degrees of Freedom

Page 9: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

viii

Table of figures.

Figure 1. Representation of Scania’s position in the market and the possibilities to implement

its process into an Industry 4.0 based system. ......................................................................... 12

Figure 2. Graphical representation of the Torque control tightening technique. ................... 14

Figure 3. Graphical representation of the Torque control with Angle monitoring tightening

technique. Tolerance limits (red) are defined for Angle and Torque is controlled. ................ 15

Figure 4. Graph representing the Torque vs Angle curve of one tightening and the quadratic

relationship between the two. ................................................................................................... 16

Figure 5. Graphical representation of the deviations that occur in any process. And a

comparison of current condition to an improved situation. ..................................................... 17

Figure 6. Flowchart representing a customized procedure of the Taguchi method. ............... 18

Figure 7. Picture of a regular pistol machine. ......................................................................... 20

Figure 8. Picture of a regular Angle machine. ........................................................................ 21

Figure 9. Picture of a smart Angle machine. ........................................................................... 21

Figure 10. Picture of steering cabinets. ................................................................................... 22

Figure 11. Graphical representation of the tightening process in Scania and the tools

involved in the process. ............................................................................................................ 22

Figure 12. Graphical example of the Torque control with Angle monitoring technique, on the

left is a tightening that has achieved both the proper Torque and Angle, while on the right

only the proper Torque has been achieved. ............................................................................. 23

Figure 13. Representation of Scania’s Digital system PISA. Separated in different software

layers. ....................................................................................................................................... 24

Figure 14. Graph representing the spread of 50 tigthenings of the joint A. In red deviations

are represented. ........................................................................................................................ 27

Figure 15. Capability analysis calculations using the calculated Angle interval compared to

production data. ....................................................................................................................... 28

Figure 16. Ishikawa diagram, with a list of the possible causes defined during brainstorming

sessions. .................................................................................................................................... 30

Figure 17. Graphical representation of operators influence in the process. Two different

operators input is presented. In green a proper operation is presented and in red an operation

not following the standards. ..................................................................................................... 31

Figure 18. Results from a 5 Why? root cause analysis. ........................................................... 31

Figure 19. Main effects plot for Angle (SNR: Nominal-is-Best). ............................................. 34

Page 10: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

ix

Figure 20. Interaction plot for Angle. ...................................................................................... 35

Figure 21. Graph representing the spread of 50 tigthenings of the joint B. In red deviations

are represented. ........................................................................................................................ 37

Figure 22. Graph and results from capability analysis run onthe joint B compared to the

calculated Angle interval. This analysis was performed on tightenings after machine was

serviced. .................................................................................................................................... 38

Figure 23. Graphs from capability analysis run on the joint B. On the right is the Cpk

analysis with the calculated Angle interval. On the right the Cpk analysis with the Angle

interval defined by Scania. ....................................................................................................... 39

Figure 24. Flow of data in an ideal SPCS in Scanias tightening process. .............................. 41

Figure 25. Position of software involved in tightening within Scania’s architectural system. 42

Figure 26. Flowchart of the current flow of data in Scania’s tightening process. .................. 43

Figure 27. Flowchart of data flow of the tightening process considering proposal by Mahesh

et al (2017). .............................................................................................................................. 44

Figure 28. Flowchart representation of a proposed DSS into Scania’s system. ..................... 49

Figure 29. Graph showing programming conditions for the tightening tool. Retreived from

(Atlas Copco Industrial Technique AB, Publication Date Not Identified). .............................. 50

Figure 30. Flowchart of the process of calculating an Angle interval in Scania’s system. ..... 51

Table of tables.

Table 1. Experimental design using L8(2^4) orthogonal array using real level of parameters.

.................................................................................................................................................. 33

Table 2. Response table for Angle for SNR: Nominal-is-Best. ............................................... 34

Table 3. Analysis of variance for SNR (Angle). ...................................................................... 35

Table 4. List of necessary functions for a SPCS. ..................................................................... 40

Table 5. List of activities that a SPCS should perform. ........................................................... 40

Page 11: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

x

Table of contents

Abstract ...................................................................................................................................... ii

Acknowledgments ..................................................................................................................... iv

Nomenclature ............................................................................................................................vii

Table of figures. ....................................................................................................................... viii

Table of tables. ...........................................................................................................................ix

Table of contents ........................................................................................................................ x

1. Introduction .................................................................................................................. 12

1.1 Background ............................................................................................................ 12

1.2 Problem statement and delimitations ..................................................................... 13

1.3 Purpose and project deliverables............................................................................ 13

2. Literature review .......................................................................................................... 14

2.1 Tightening process ................................................................................................. 14

2.2 Calculating the Torque-Angle relationship (Linear Regression) ........................... 15

2.3 Statistical Process Control ..................................................................................... 16

2.4 Design of experiment ............................................................................................. 17

2.5 Industry 4.0 ............................................................................................................ 18

2.6 Conclusions ............................................................................................................ 19

3. Assembly process in Scania ......................................................................................... 20

3.1 Power tools ............................................................................................................. 20

3.2 Tightening process ................................................................................................. 22

3.3 Production Information System Architecture ........................................................ 24

3.4 Software related to the tightening process ............................................................. 24

4. Case of study 1: Joint A ............................................................................................... 26

4.1 Data collection ....................................................................................................... 26

4.2 Analysis and results ............................................................................................... 27

5. Case 2: Joint B .............................................................................................................. 37

5.1 Analysis and results ............................................................................................... 37

5.2 Capability Analysis ................................................................................................ 37

6. Proposal for Industry 4.0 .............................................................................................. 40

6.1 Smart process control system ................................................................................. 40

6.2 Current state analysis ............................................................................................. 42

6.3 Proposal .................................................................................................................. 43

7. Mindset Strategy. ......................................................................................................... 45

8. Limitations and challenges ........................................................................................... 46

Page 12: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

xi

9. Conclusions .................................................................................................................. 47

10. Future work. ............................................................................................................... 48

10.1 Decision Support System ................................................................................... 48

11. Appendix ................................................................................................................... 51

References ................................................................................................................................ 52

Page 13: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

12

1. Introduction

1.1 Background

There is currently an increasing need for manufacturing companies to achieve flexible,

smart and reconfigurable processes in order to address a dynamic and global market. To meet

these demands an initiative called Industry 4.0 has been presented by the German Federal

Government (Santos, et al., 2017). The goal of Industry 4.0 is to convert the regular machines

to self-aware and self-learning machines. In order to improve their overall performance and

maintenance management, real time data monitoring as well as to hold the instructions to con-

trol production processes (Santos, et al., 2017).

Scania is a world-leading provider of transport solutions, including trucks and buses for

heavy transport applications. Scania's production system aims to meet customer needs while

achieving increased profitability, growth and competitiveness (Scania, 2018). This is the rea-

son why Scania aims to bring its expertise in truck production into an Industry 4.0 based sys-

tem (Figure 1).

In Scania CV AB in Oskarshamn truck cabs are being produced. The cab factory consists

of four workshops: Press, Body, Paint and Assembly Workshops (Scania, 2018). The bolt

tightening process in the assembly workshop in Scania Oskarshamn presents promising pos-

sibilities for implementation of an Industry 4.0 based system.

In the assembly process, joints that are considered as a necessity for the safety and func-

tionality of the truck or are considered legal requirements are known as Critical and Legal

(C/L) joints, these are of outmost importance in the assembly process since any deviation can

lead to major costs for the company. C/L joints are tightened using “smart” machines, which

are able to control Torque and monitor Angle of turn of the bolt during the process.

Figure 1. Representation of Scania’s position in the market and the possibilities to implement its pro-

cess into an Industry 4.0 based system.

Page 14: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

13

To be able to efficiently monitor Angle in the tightening process, tolerances need to be

defined, a high and low tolerance creates what is known as an Angle interval. The Angle

monitoring data obtained from the process can be analyzed and deviations can be identified,

as it is explained in this thesis, consequently making it possible to provide real time feedback

of deviations to software and personnel. This creates the possibility to have a more proactive

and smart process.

1.2 Problem statement and delimitations

After conducting interviews and discussions with the tightening and maintenance per-

sonnel it is known that, control of the clamping force necessary for the Critical and Legal

joints is currently calculated through the Torque control and Angle monitoring method. An

Angle interval in Scania’s process is defined but it is too wide. While the tightenings are with-

in operational tolerances, the wide limits make the monitoring process unable to identify de-

viations and possible improvements.

Moreover the lack of an accurate monitoring process makes the work currently done

more active than proactive. The infrastructure and power tools currently used make it possible

for Scania to implement Angle monitoring into an Industry 4.0 based system. However the

possibilities, limitations, needs (in digital and physical infrastructure) and challenges must be

identified to make this a reality. This project was limited by certain aspects:

This project is focused on smart tools because only smart tools have sensors able to

monitor Angle during tightening.

It is not within the scope of the project to consider more tightening techniques other

than Torque with Angle monitoring.

It is not within the scope to consider thread forming joints.

This project is focused on C/L joints because only these joints use smart tools in their

process.

It is not within the scope of the project to perform design activities and the design

specifications must be followed.

1.3 Purpose and project deliverables

The goal of this project is to define a method for the calculation of an accurate Angle

interval. Identification of feasibility and benefits of the implementation of the Angle monitor-

ing process into an Industry 4.0 based system while involving relevant personnel into an In-

dustry 4.0 mindset.

1. Creation of a local method/tool for determination of accurate angular intervals, and a

plan for implementation into an Industry 4.0 based system.

2. Implementation of smart Angle monitoring and involvement of relevant personnel into

an Industry 4.0 based system.

Page 15: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

14

2. Literature review

This section will provide a summary and explanation of relevant concepts in the tighten-

ing of bolted joints and the importance of it in any assembly process. A comparison between

different tightening techniques is presented in order to demonstrate the importance of the

method developed in this project. Finally some concepts from Industry 4.0 that are relevant

for an implementation of smart Angle monitoring are also presented.

2.1 Tightening process

As explained by Bickford (1995). the tightening of bolted joints consists on the creation

of a force able to keep two or more parts together in order to permit the functionality or

movement necessary. This force is created by applying Torque into a bolt, which turns and

screws the two parts together. As the bolt reaches its designed Torque and Angle of turn val-

ues (which is referred to as Angle from now on) it elongates and creates tension which is also

known as clamping force. Therefore in order to avoid failure of the joint, and consequently

economic costs, a correct clamping force is necessary. The correct amount of clamping force

is achieved by a correct design but mostly by the tightening technique used in the process and

performed by the operator as has been concluded by Bickford et al. (1998).

The behavior and life of a joint depends very much on the magnitude and stability of the

clamping force (Atlas Copco, 2018). In automotive assembly tightening techniques of joints

are used to prevent the joints from separating while under service conditions. In current as-

semblies this process is done by an operator using a power tool that performs the job efficient-

ly and is also able to monitor the process.

2.1.1 Torque control

Torque control (Figure 2) is the most common way to control clamping force. A Torque

is defined and the power tool applies Torque on the bolt to create a clamping force. The pow-

er tool controls and measures Torque and tightens until the Torque is inside acceptable toler-

ances. The sole creator of the clamping force in this method is Torque and no other variable is

considered (ASSEMBLY Magazine, 2002).

Figure 2. Graphical representation of the Torque control tightening technique.

Page 16: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

15

Although Torque control performs a good enough job there is no way to be 100% certain

that the desired clamping force will be achieved. And as Bickford et al. (1998) concludes

Torque measurements that are not backed up with simultaneous Angle of turn measurement

cannot be totally relied upon.

2.1.2 Torque control with Angle monitoring

Figure 3. Graphical representation of the Torque control with Angle monitoring tightening technique.

Tolerance limits (red) are defined for Angle and Torque is controlled.

For C/L joints Torque must be controlled while the Angle of turn is monitored (Figure 3).

The monitoring of Angle will provide a check that the tightening process was performed cor-

rectly.

In this method Torque is applied and the sensors will measure the Angle through which

the bolt is turned. As the defined Torque value is achieved, the system will evaluate the final

value of the Angle. Tolerances for Angle are defined within an interval where the expected

clamping force is achieved.

If the final Angle value measured is found within the defined tolerances the tightening

will be considered as correct. However if deviations occur, the process will take far too much

(or too little) Torque to arrive within the specified tolerances. This will be defined by the

system as an incorrect tightening (Bickford, 1995).

When the importance of the joint being tightened is high one must assure that the clamp-

ing force achieved is the correct one. The most convenient tightening technique in these cases

is Torque control with Angle monitoring.

2.2 Calculating the Torque-Angle relationship (Linear Regression)

In order to calculate a correct clamping force several methods have been presented by

Bickford et al. (1998). One of them considers that the clamping force is being created as a

function of the increase in both Angle and Torque simultaneously. Therefore it is concluded

that by analyzing the Torque and Angle relationship, and calculating their contribution to the

process it is possible to calculate a correct Angle interval.

Page 17: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

16

Figure 4. Graph representing the Torque vs Angle curve of one tightening and the quadratic relation-

ship between the two.

From looking at Figure 4, where one measurement of Torque (x axis) against Angle (y

axis) during tightening was taken (directly from monitoring), it is observable that Angle pre-

sents a relationship with Torque. By using the linear regression method it is possible to quan-

tify the relationship.

This method tries to prove that a percentage of the variation in the “response Y or Angle”

is explained by the variation in the “predictor X or Torque”. Then an equation can be defined

which is used to calculate an Angle interval in which we will find, with a 95% certainty, the

nominal value of Torque (Pennsylvania State University, 2018).

By calculating an Angle interval using this method, the process should be able to identify

deviations from the optimal process. The deviations that occur in any process should be elim-

inated to achieve a high quality product as defined by Gejdoš P. (2015).

2.3 Statistical Process Control

Statistical Process Control or SPC states that the basic issue in a quality oriented process

is to what level we are able to satisfy customer’s expectations. A product which should be

suitable for use should be produced in a stable process (Gejdoš, 2015).

The basic principle of improving processes is based upon the assumption that the varia-

bility of quality index values have two types of causes as shown in Figure 5:

Page 18: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

17

Figure 5. Graphical representation of the deviations that occur in any process. And a comparison of

current condition to an improved situation.

● Random causes (common causes) are a permanent part of the process and influence all

process components. They create a wide variety of individually un-identifiable causes,

from which each slightly contributes towards overall variability.

● Assignable causes (special causes) are causes which are not a permanent part of the

process, they do not influence all process components but occur as a consequence of

specific circumstances (Gejdoš, 2015).

2.4 Design of experiment

The experiment can help to prioritize the cause of deviations and illustrates the best com-

bination of different levels of each cause (Dean, et al., 2017). Since the goals of the project

are valid and applicable improvement plans and not just statistical analysis of an isolated con-

dition, a complete cycle of planning, performing, analyzing data and interpreting the results is

required (Jiju & Jiju Antony, 2001).

The nature of the problem that is trying to be solved involves complicated causes of de-

viations with possible interactions, cross-relating different functional areas within the factory

which is another necessity for designing an experiment (Limon-Romero, et al., 2016). There

are different methods to design an experiment, including widely used factorial and fractional

factorial design and innovative methods of Taguchi design. In conditions where a large num-

ber of controllable and uncontrollable causes of deviations ( which now on we call parame-

ters) are involved. Factorial and fractional factorial design illustrate some drawbacks as (1)

they result to more time and cost (2) two design of the same experiment might show different

results (3) interpreting data can become difficult as there is no clear and standard instruction

on how to design an experiment (Roy, 2010). However the Taguchi design works on the basis

of calculating a specific measure called SNR (Signal-to-Noise Ratio) which demonstrates the

ratio between a process mean and its variation. Higher the value of SNR leads to lower devia-

tion in process aimed to be optimized.

Page 19: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

18

Figure 6. Flowchart representing a customized procedure of the Taguchi method.

Thus the Taguchi method serves the goal of reducing the deviation in tightening process,

re-tightenings and stop times. By selecting the most suitable combination of parameters ( both

controllable and uncontrollable) it helps to reduce the variation in Angle. Taguchi method

also employs specific set of orthogonal arrays (OAs) which is a table containing set of num-

bers where each set of number can be dedicated to a specific experimental design. learning

how to use OAs is the key to learn the Taguchi experimental design (Limon-Romero, et al.,

2016). The customized process of performing the Taguchi experiment is illustrated in the Fig-

ure 6 (Limon-Romero, et al., 2016) (Yusoff, et al., 2011).

2.5 Industry 4.0

Industry 4.0 is a current trend in manufacturing. It is based on the integration of technol-

ogies for the collection and analysis of real time data in order to increase the efficiency. This

is achieved through collaborative processes, services and human-machine interfaces (Santos,

et al., 2017).

Smart machines in any assembly process enable the rapid generation and collection of

process data into big databases. As proposed by Saurabh P. (2018) the data obtained from real

time processes can be analyzed to identify patterns. This makes the system able to detect de-

viations, perform health monitoring, prediction of failure and send live feedback to the ma-

chines in the process (Weihrauch, et al., 2018).

Page 20: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

19

For this purpose machine learning has had a great impact on monitoring systems for pat-

tern detection (Yusoff, et al., 2011). A recent trend in machine learning is Deep Learning

which has surfaced as a method for detection of patterns using raw signals as input data. Deep

learning is based on large data representations. Hinton et al. (1999) divides deep learning in:

● Supervised learning: A function is defined to map an input to an output based on ex-

ample input-output pairs this information is labeled as training data.

● Unsupervised learning: a function is inferred to describe an input to an output.

2.6 Conclusions

It is a fact that an accurate Angle interval should be able to measure if the tightening pro-

cess has been successful (Bickford, 1995). This creates the possibility to detect problems un-

noticeable by Torque control alone. Therefore an accurate Angle monitoring process and the

concept of SPC and Industry 4.0 provide guidelines to use Angle monitoring as a Smart Pro-

cess Control System (SPCS) (Weihrauch, et al., 2018). However the possibilities of imple-

menting a smart Angle monitoring system to improve Scania’s process need to be identified.

Page 21: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

20

3. Assembly process in Scania

Scania’s procedures and standards define that bolted joint is the most commonly used

bond type in Scania. Bolted joints must withstand both static and dynamic forces, and they

have to work for a long time in a difficult environment.

In Scania’s assembly plant in Oskarshamn, truck cab components are assembled by oper-

ators that perform the tightening operations according to instructions using hand held power

tools. The selection of bolts, tools, process plan and tightening control technique for each in-

dividual joint is done depending on design specifications and on the degree of importance

(C/L joints). All of this information is provided in internal standards that work as rules to se-

lect the proper specifications (Scania, 2017). Torque is calculated according to internal stand-

ard specifications, which provides the Torque interval values calculated by design for each

specific type of joint (C/L) and bolt.

3.1 Power tools

Most of the industries, including the automotive industry, use hand held power tools in

their assembly process. A power tool is a nutrunner that is driven by an external power source

such as air or electricity. It makes the workers perform their operations efficiently. Power

tools also provide the possibility of feedback from the process which makes them better than

manual tools (Desoutter Industrial Tools, 2018). Different types of electric hand-held tools are

used during the assembly process, depending on the importance of the joint. Here is a sum-

mary of the most common tools used in Scania’s process:

3.1.1 “Regular” pistol machine

A regular pistol machine (Figure 7) is only able to control Torque and cannot monitor the

process. These tools are only used for joints with low Torque demand, lower than 8 Nm

(Atlas Copco, 2018).

Figure 7. Picture of a regular pistol machine.

Page 22: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

21

3.1.2 “Regular” Angle machine

Figure 8. Picture of a regular Angle machine.

A regular Angle machine (Figure 8) only monitors Torque but unlike the regular pistol

machine this one is designed for a medium Torque, usually between 8 Nm and 24 Nm alt-

hough it can be used up to 40 Nm (Desoutter Industrial Tools, 2018).

3.1.3 Smart Angle machine

A smart Angle machine (Figure 9) is one that has strain gauges. It has programmable

speed and is capable of monitoring both Torque and Angle. Smart machines are more ergo-

nomic and enhance the quality of the joint. They are able to produce a higher Torque (up to 58

Nm) without affecting ergonomics (Atlas Copco, 2018).

Smart power tools used in Scania are always connected to a steering cabinet (Figure 10)

which sends feedback data from the tightening process to Toolsnet. Toolsnet is an Atlas Cop-

co software able to collect process data. It is also able to present statistics on the steering cab-

inet software using continuous data analysis. There exist a number of different manufacturers

who are producing such kind of tools. Major manufacturers include Bosch, Hitachi, Atlas

Copco, Desoutter, etc.

Figure 9. Picture of a smart Angle machine.

Page 23: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

22

Figure 10. Picture of steering cabinets.

Since this smart machines are the only machines available that can monitor Angle, all of

the research done in this work is based on the performance, operation and functions of this

type of machine.

3.1.4 Fixtured Spindle Machine

A fixtured spindle machine is a set of one or more smart machines integrated for applications

that require specific positioning on assembly, involve multiple fastening points or require a

Torque higher than the recommended Torque for a handheld smart machine (Atlas Copco,

2018).

3.2 Tightening process

In the current assembly process while most of the power tools can identify a OK/NOK tight-

ening, only smart machines are capable of connecting to Scania’s current digital framework.

Figure 11. Graphical representation of the tightening process in Scania and the tools involved in the

process.

Page 24: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

23

Before performing a tightening the operator must, as shown in Figure 11, scan the work

order (1) in each of the cabs. The scanner reads order specifications for the specific cab and

sends this specifications to the steering cabinet (2) which (according to programming) sends

commands to the smart machine (3) to perform the tightening.

The smart machine is programmed to send an OK/not OK (4) signal with colored lights

(green for OK red for not OK) for the operator to know if the tightening has been performed

correctly. If it is not performed correctly the operator knows to repeat the tightening and if

this takes more time than expected a line stop signal is activated by the operator.

The smart machine’s sensors that monitor the entire process send feedback to the steering

cabinet which stores it and sends process data to Toolsnet (5) which is able to analyze, store

and show data from the tightenings. Finally the tool can be programmed to send an alarm

each time a not OK tightening occurs.

3.2.1 Tightening control technique

As defined in Scania’s standards, most of the tightenings done in the assembly process

are controlled with the Torque control method, since it is the easiest to apply and almost all of

the tools available are capable of performing this method.

But when a joint is considered as C/L a Torque control with Angle monitoring method

(Figure 12) is the mandatory approach since Angle monitoring is necessary a smart machine

is the tool used by the operator to perform the tightening. The use of a smart tool and the deci-

sion of using the Torque with Angle monitoring technique are due to the necessity to assure a

better quality tightening in this type of joints.

Since currently there is no method inside Scania to calculate an Angle interval, the win-

dow for Angle monitoring is calculated by the maintenance department based on prior experi-

ence. To observe the performance of the process a bell curve is graphed using information

gathered from production. Higher and lower Angle limits are then defined so that the process

is able to operate at a high Process Capability (Cpk).

Figure 12. Graphical example of the Torque control with Angle monitoring technique, on the left is a

tightening that has achieved both the proper Torque and Angle, while on the right only the proper

Torque has been achieved.

Page 25: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

24

3.3 Production Information System Architecture

Figure 13. Representation of Scania’s Digital system PISA. Separated in different software layers.

Scania has named its digital system Production Information System Architecture (Figure

13). It is a hierarchical system used to structure information management from production

through four different levels of production-related IT systems:

The base level is the production equipment and functions, components and communica-

tions. The second level Supervisory Control and Data Execution (SCADA) is managed by

DIDRIK. DIDRIK adds functionalities such as production calendar, quality assurance, KPI

monitoring, tact display as well as visualization of the production system at the Human Ma-

chine Interface (HMI) level. This system builds an efficient automation layer and finds a way

to meet the requirements that are common. DIDRIK takes care of the communication and

real-time visualization of key parameters. The third, MES level inside Scania is managed by

EBBA. It is a platform for managing production order execution, presenting assembly instruc-

tions, deviation handling and production follow-up. MES is concerned with production, quali-

ty, inventory and maintenance. This level is also in charge of data management. In Scania it is

the connection between MONA and DIDRIK.

The final level is the ERP. It is the tool for PLM, inside Scania this is done through the

software named as MONA, which connects to EBBA. There are also some other independent

systems in this level like MAXIMO and ACTA. This is the way information is transferred

through each of the levels in Scania’s digital architecture (Mahesh & Umer, 2017). However

for the tightening process all of the smart machines are managed by software outside of Sca-

nia’s digital architecture.

3.4 Software related to the tightening process

From our research of the digital structure currently used in the assembly shop it is known that,

since the smart machines are product from the supplier, the software used to manage them is

Page 26: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

25

also a supplier’s product. A list of different software and their descriptions are presented as

follows.

3.4.1 Tools talk

Tools talk is an Atlas Copco software used in Scania for programming the controllers or steer-

ing cabinets of the tightening tools used in production. This software sends orders to the steer-

ing cabinet to follow. Speeds and tolerances for Torque and Angle are programmed through

this software (Atlas Copco, 2018).

3.4.2 Toolsnet

As mentioned in the tightening process the steering cabinets send monitoring information

from the process to a software known as Toolsnet. Toolsnet is an Atlas Copco software for

data collection and has some statistical analysis tools.

With this software historical data, statistics and capability indexes of Torque can be accessed

at any time via a standard web browser such as Microsoft Internet Explorer. This software

provides information on every tightening related to a specified period or product. It also pro-

vides a result database that provides access to critical information of final results in the pro-

duction (Atlas Copco, 2018).

3.4.3 Maximo

Maximo is a PLM system that supports the inventory and purchase of non-automotive prod-

ucts, including machines, spare parts, etc. It also works as the maintenance planner software

of machines at Scania. The system is used in all of Scania’s production units (Scania, 2017).

3.4.4 ACTA

ACTA is an offline tool used by the maintenance department to schedule and record calibra-

tion dates of the tightening tools used in the process. It is found only on one computer in the

assembly shop and can only be accessed by maintenance personnel (Scania, 2017).

Page 27: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

26

4. Case of study 1: Joint A

From our research of Scania’s assembly process it is known that the joint A is one of the

most important joints in the cab. It is considered a C/L joint. The assurance of a high quality

tightening for this joint is necessary to avoid deviations from happening.

The joint is tightened using a handheld “smart” Angle machine manufactured by Atlas

Copco which is connected to a steering cabinet that sends process data to Toolsnet. In toolsnet

it is possible to look at the behavior of the joints.

4.1 Data collection

We collected data from a six month period (approx 10000 tightenings) from Toolsnet.

The result report from the smart tool used in the joint A was extracted and from the report an

N number of tightenings were picked randomly (to assure reliability). N is defined with the

following empirical equation:

𝑵 = √𝟏𝟎𝒍𝒏 𝒙 𝟒

We created the equation based on the following considerations:

Variable 𝑥 represents number of tightenings performed. For ensuring that influ-

ence of random parameters including (but not limited to) operator shift, environ-

ment temperature, tightening machine battery drain and bolt batch are properly

reflected into calculations, we decided that minimum number of 400 tightenings

should have been performed before being able to use the equation.

The equation provides enough number of samples required to perform the analy-

sis (Johnson, et al., 2011).

Even if number of tightenings increases significantly, number of samples will in-

crease on much slower pace and remain on a limit to be easily processed by any

statistical software.

Then we extracted the trace analysis data for each of the N tightenings. From the behav-

ior of the tightening we are only interested in the elastic region of the tightening up until the

final Torque and Angle values [Angle >= 0 ; Torque >= nominal Torque]. Then we gathered

all the data into one Excel file containing three different columns of information: 𝐴𝑛𝑔𝑙𝑒,

𝑇𝑜𝑟𝑞𝑢𝑒 and 𝑇𝑜𝑟𝑞𝑢𝑒2.

All of these steps are done only to gather the information from the software and facilitate

the interface into Minitab which is the statistical analysis software used during this project.

The data collection process for this case of study took around two days because of the limita-

tions of software and access to data. It is important to explain the data collection process to

emphasize the need of automation and smart processes. Automation of this process is further

explained in Chapter 5 of this report.

(1)

Page 28: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

27

4.2 Analysis and results

4.2.1 Linear regression

We defined that Linear regression was the best option for the calculation of an accurate

Angle interval since it calculates the least error using other regression methods like the least

squares method. We then performed a linear regression analysis using the previously men-

tioned data of N tightenings. The result of the analysis shows that as Torque (T) increases

Angle (θ) also increases this relationship is better explained by:

𝜽 = 𝒃𝟎 − 𝒃𝟏 × 𝑻 + 𝒃𝟐 × 𝑻𝟐

All the values used for calculation and results we obtained from analysis are considered

as confidential within Scania, that is why no actual data is presented in this report.

After finding that the relationship between predictor and response exists it is possible to

predict with a 95% confidence that a determined “Torque” value will occur in a “Angle” in-

terval of:

[𝜽𝑳𝒐𝒘 ; 𝜽𝑯𝒊𝒈𝒉]

The prediction of an Angle interval using this method assures that the tightening process

will be performed as expected and increase the quality of tightenings currently performed in

the assembly process.

However during the linear regression analysis we also observed that although the rela-

tionship exists the process presents a substantial amount of deviations from optimal behavior

as observed in Figure 14.

Therefore we concluded that before being able to implement the calculated Angle inter-

val into production a capability analysis is necessary to define if the current process is able to

meet the customer demands within this tolerances.

Figure 14. Graph representing the spread of 50 tigthenings of the joint A. In red deviations are repre-

sented.

(2)

Page 29: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

28

4.2.2 Capability Analysis

Figure 15. Capability analysis calculations using the calculated Angle interval compared to produc-

tion data.

For the capability analysis (Figure 15) the previously gathered data of results reported

from Toolsnet is extracted into an Excel file, so that the statistical analysis software is able to

calculate Cpk using the calculated Angle interval values:

The capability analysis values and results are considered as confidential within Scania.

However in the graph we can notice that the process presents high number of variation from

the nominal Angle value. In an optimal process all of the bars in the graph should be found

inside the lower and higher values, showing a tighter curve.

From this analysis we concluded that the current process was not capable of performing

within the Angle interval, and that a high number of tightenings would be consider out of

specifications. This leads to an increase in stop time in the line. Thus it is necessary to per-

form further analysis of the deviations.

As we know from the literature review the high variability that is occurring in the process can

cause a decrease in quality. It is possible to ensure and improve quality of the tightening pro-

cess via operative quality management which includes all methods and activities focusing

upon monitoring processes and removing causes of non-conformity and defects (Gejdoš,

2015).

Page 30: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

29

4.2.3 Problem Solving

For the analysis of the deviations due to assignable causes Toyota’s 8 steps for practical

problem solving was chosen to be able to identify the root causes of the problem and assure

that the deviations do not occur again (Goldsmith, 2014).

1) Clarification of the problem

High number of deviations are happening in the tightening process, this means that the

process is not stable and complicates the implementation of a proper monitoring system

through Angle interval.

2) Breakdown of the problem

From a brainstorming session with involved Scania personnel the possible causes are

listed into an Ishikawa diagram as shown in Figure 16:

Based on feasibility, possibility to control, data availability and reach of the project, the

possible causes of deviations were narrowed down. Then an initial observation of the actual

process and cross reference to data indicated that the highest source of deviation in the pro-

cess comes from operator influence.

To investigate the causes of deviation in more detail a second observation was planned,

recording all actions of operator, in addition of recording the condition of the tightening tool,

joint parts and cab. During the observation, the unique identifier of each cab was recorded on

a log sheet, corresponding to the time of the tightening and the rest of the observation parame-

ters mentioned earlier. The second observation was performed on 138 cabs. Results were

transferred to an Excel file, categorized into two group of controllable and uncontrollable

causes and arranged by different causes and their subsequent levels. Finally they were ana-

lyzed with the Minitab statistical software.

Page 31: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

30

Figure 16. Ishikawa diagram, with a list of the possible causes defined during brainstorming sessions.

We chose ANOVA method to determine if causes of deviations are actually affecting the

Angle in the tightening process. Since causes of deviations appear randomly, the number of

observations were not the same for each cause. This led to choosing a one-way ANOVA

method (Durivage, 2015).

At the first step we did a normality test on the Angle data, resulting in a need of data

transformation into normal distribution (Johnson, et al., 2011). Johnson transformation was

chosen for this purpose (Minitab, 2018). The result of the one-way ANOVA indicates that all

of the controllable causes of deviations are statistically significant, and most of them are relat-

ed to how the operator holds the tool or how the joint reacts to the forces during the tighten-

ing.

We then concluded that the analysis performed for this joint should focus only on prob-

lems that occur because of operators influence (Figure 17). The first operator was able to per-

form within the specifications and following the standards and instructions defined. However

the operator two was not following the instructions and it is observable from the graph that

this lead to a substantial increase in the standard deviation of the process.

Page 32: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

31

Figure 17. Graphical representation of operators influence in the process. Two different operators

input is presented. In green a proper operation is presented and in red an operation not following the

standards.

3) Set the target

We determined that the standard deviation could be reduced by 40% and Cpk increased

by 200%.

From the root cause analysis (Figure 18) it is identified that there is a need for more

competent personnel in the tightening process of C/L joints, to have a more stable process.

4) Analyze the root cause

Figure 18. Results from a 5 Why? root cause analysis.

Page 33: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

32

5) Possible solutions

An optimal solution should result in the minimum variation in Angle. Considering the

time and cost limitations on any suggested improvement plan, it is also important to know

which controllable causes of deviations are more significant than others in order to efficiently

sequence and run the improvement plans and monitor the results. To satisfy the mentioned

requirements, we designed an experiment using Taguchi method. Which we defined as the

best methd since there are multiple variables affecting the process and there is no recorded

data on how much variation each of them create.

6) Implementation

Activities 1 and 2 in Taguchi design method (Figure 6) have already been done in steps 1

to 4 of the Toyota’s 8 steps problem solving method. Due to the nature of the production and

limited time available to run the experiment, we excluded uncontrollable parameters from the

experiment and only controllable parameters have been focused on.

Four controllable parameters were identified “Loose holding of the tightening tool”,

“shaft play during tightening”, “applying extra force on tightening tool at the end of tighten-

ing process” and “ Use of dirty gloves by the assemblers”. Also during the previous observa-

tions it we noticed that some parameters might interact with each other which is better to be

investigated in order to provide better insight about tightening process. possible interactions

are:

“Loose holding of the tightening tool” × “Shaft play during tightening”

“Loose holding of the tightening tool” × “applying extra force on tightening tool at the

end of tightening process”

Each of these parameters have 2 levels of “yes” and “no”. Orthogonal array calculated by

using Minitab 18 software resulted to the OA of L8(2^4) which means four parameters , each

in two levels resulting to 8 separate combinations of parameters (which we now call them

cases). The Taguchi design can be seen in Table 1.

Several factors playing a role on deciding how many cabs should be included in each

case. On one side there is an essential need for accuracy of data, especially comparing number

of cabs in each case to the total number of cabs produced on annual basis. On the other side

time constraint needs to be considered. The current number of cabs per each case is consid-

ered to serve both delimitations.

Page 34: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

33

Table 1. Experimental design using L8(2^4) orthogonal array using real level of parameters.

Another method to define the number of cases is by calculating the degrees of freedom.

Utilizing following procedure, we concluded the same number of cases (Neseli, 2014).

1- Index each parameter from 1 to 𝑛

levels of paramaters is represented by 𝐿 and we calculate 𝑃1 as:

𝑷𝟏 = ∑(𝑳𝒊 − 𝟏)

𝒏

𝒊=𝟏

2- Index each interaction from 1 to 𝑚 first, for each interaction we calculate 𝐼 as.

𝑰𝒎 = (𝑳𝒊 − 𝟏)(𝑳𝒊 − 𝟏)

then we calculate 𝑃2 as:

𝑷𝟐 = ∑ 𝑰𝒎

𝒎

𝒋=𝟏

3- Degrees of freedom can be calculated by equation 6:

𝑫𝑶𝑭 = 𝑷𝟏 + 𝑷𝟐 + 𝟏

7) Monitoring

When performing the experiment, we prepared the procedure and risk assessment and re-

ceived approval by the responsible personnel. Prior to the experiment we held a meeting with

the line operators to properly explain the purpose of experiment and calrify what is expected

from each operator to do in each of the cases.

Experiment procedure had been followed according to the plan, and we recorded required

data in a log sheet. We had to repeat he experiment on about 30 of the cabs due to uncertainty

of having the exact combination of controlled parameters as required.

For calculating SNR, three strategies are available: lower-is-better, higher-is-better and

nominal-is-best (Limon-Romero, et al., 2016). Since it is required to minimize the deviation

around mean Angle, we chose “nominal-is-best” strategy. Figure 19 show the result of SNR

analysis. Horizontal line illustrates no effect on process and with increase of the line slope, the

(3)

(4)

(5)

(6)

Page 35: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

34

magnitude of parameters importance increases. Additionally a response table can be included

to calculate rank of each parameter as in Table 2. Response table calculates Delta (∆). Higher

Delta value illustrates the higher importance and hence higher magnitude of parameter effect

of process performance.

Figure 19. Main effects plot for Angle (SNR: Nominal-is-Best).

Table 2. Response table for Angle for SNR: Nominal-is-Best.

Similar to the plot of SNR, the plot of standard deviation was generated illustrating the

same rank as in Table 2. In order to utilize SNR to study the interactions, interaction plot was

generated which is illustrated in Figure 20. For interpreting the interaction plot, parallelism of

lines is very important. If lines are crossing each other it illustrates significant importance of

the interaction. If lines are just nonparallel, it illustrates interaction, but not as significant as

crossed lines. Parallel lines means no interaction between parameters (Neseli, 2014). It can

then be concluded that there is strong interaction between the parameters that were initially

expected.

Page 36: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

35

Figure 20. Interaction plot for Angle.

Next activity was an ANOVA analysis. Since there are equal number of observations in

each case, multiple parameters (causes of deviations) affecting tightening Angle and interac-

tion between parameters is in our interest, multi-way ANOVA is required (Durivage, 2015).

First we performed a normality test on Angle data with satisfactory results. As it is illustrated

in Table 3 there is a strong interaction between “Loose holding of the tightening tool” and

“applying extra force on tightening tool at the end of tightening process”. The analysis also

indicates that most important parameters to consider are “applying extra force on tightening

tool at the end of tightening process” followed by “Loose holding of the tightening tool”.

Table 3. Analysis of variance for SNR (Angle).

As for comparing the experiment results with our target, we calculated standard deviation

of Angle and Cpk for all the cases. Caes 8 illustated the best values by reducing standard de-

viation by 66% (compared to 40% target) and increasing Cpk by 365% (compared to 200%

target).

8) Standardize

From a visit to the basic skills department the people in charge of training explained to us

the way training of the operators for the tightening process is performed. We then concluded

that the training performed is sufficient and covers all the points that have been identified as

critical. However it came to our attention that there is no monitoring on how the operator ac-

tually performs while working on the line. Moreover there is a lack of reinforcement of the

Page 37: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

36

training of operators and this is due to the mindset of the personnel and management. The

focus on producing as much as possible causes a lack of commitment on operator’s training

and causes the deviations occurring in the actual process.

We propose that a mindset strategy to involve operators and management into the tight-

ening process, explaining how tightening affects both quality and production, is implemented.

This would increase the conscience of the personnel on the importance of performing a proper

tightening, thus increasing the quality of the process and the product.

Page 38: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

37

5. Case 2: Joint B

The second case of focus for this project involved the joint B which uses a fixtured one

spindle machine. This machine was chosen because it is used in the tightening of the joint B

which is considered as a C/L joint because its role is essential for the functionality of the cab.

Recently the machine was serviced and the data for this period is available in Toolsnet data-

base. Because of the functionalities of the machine (theoretically) the operation of this ma-

chine is not affected by the operator’s influence unlike the joint A.

5.1 Analysis and results

The same data collection process as in the previous case was applied and analyzed in the

statistical software and the Angle interval was calculated.

[𝜽𝑯𝒊𝒈𝒉 ; 𝜽𝑳𝒐𝒘]

Linear regression analysis also showed that for this joint, the relationship is better and the

process is more stable compared to te joint A.

It is observable from the analysis and Figure 21 that this joint presents a better relationship

between Torque and Angle. It also shows how the process behaves without the operator’s

influence.

Although the process is more controlled in this joint, it still presents a high number of

deviations in the final Angle.

Figure 21. Graph representing the spread of 50 tigthenings of the joint B. In red deviations are repre-

sented.

5.2 Capability Analysis

From a preliminary capability analysis (Figure 22) using the calculated Angle interval it

was defined that a lower percentage, compared to the joint A, of tightenings would be consid-

ered as NOK if the calculated Angle interval was implemented.

Page 39: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

38

Figure 22. Graph and results from capability analysis run on the joint B compared to the calculated

Angle interval. This analysis was performed on tightenings after machine was serviced.

As in the previous case this information is classified for Scania so it was impossible for

us to share. However we can observe in the graph that although the behavior of the process is

more stable than the previous case there are still deviations from the process, and possible

improvements that can help lower the standard deviation and improve Cpk can be found.

5.2.1 Testing the calculated Angle interval

During the time we were working in the project there occurred a breakdown in this spe-

cific machine. We are not able to discuss the nature of the breakdown since this is considered

as confidential information. However this created the possibility for us to test how the previ-

ously calculated Angle interval would have been capable of identifying that there was a prob-

lem with the machine before the breakdown occurred. By doing a capability analysis of the

time prior to the identification of the breakdown of the machine it is possible to test how the

calculated Angle interval would have been able to identify the problem with anticipation in

Figure 23:

Page 40: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

39

Figure 23. Graphs from capability analysis run on the joint B. On the right is the Cpk analysis with

the calculated Angle interval. On the right the Cpk analysis with the Angle interval defined by Scania.

By comparing the two graphs and the values of Cpk and standard deviation we were able

to observe how the process would have performed when using the calculated Angle interval.

It was noticeable that a high number of deviations where occurring 2 weeks prior to the fail-

ure. Since the Angle interval defined by Scania [LSL ; USL] was too wide the process was

not able to identify that the standard deviation had doubled from the optimal process. Howev-

er if the calculated Angle interval was used the process would have automatically detected

this problem. From calculations we know that the defect rate would have increased by a 200%

this would have made it obvious for the involved personnel that the machine was not perform-

ing at its optimal conditions and service could have been scheduled before the breakdown

occurred which would have saved time and money for Scania.

We concluded from this second case that by using an efficient Angle interval it is possi-

ble to monitor the life of the machine and that it is possible to schedule service and calibration

dates from the Angle monitoring data.

Page 41: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

40

6. Proposal for Industry 4.0

In this chapter current state analysis and a proposal for implementation into an Industry

4.0 based system, considering that the next step in the project is to present ideas for the im-

plementation of the Angle monitoring process. Also enabling technologies, needs, possibili-

ties, advantages, disadvantages, limitations and future work are presented.

6.1 Smart process control system

In order to create a conceptual model for developing a Smart Process Control System

(SPCS) Scania’s requirements where identified and compiled in Table 4 by comparing current

and target implementation of a smart monitoring process. The suggestions from operators and

personnel involved in tightening were taken into consideration.

System necessary function

Calibration scheduling

Maintenance Scheduling

Feedback to operator

Deviation analysis

Quality checks

Feedback to tightening and maintenance personnel

Table 4. List of necessary functions for a SPCS.

Using the previously mentioned requirements a conceptual model for a Smart Process

Control System can be created considering Table 5:

SPCS

The system shall share data automatically

The system shall continuously analyze data and present results efficiently

The system shall identify deviations using SPC.

The system shall alert person responsible depending on the deviation that occurs.

The system shall schedule tool calibration and service automatically

The system shall trace products and link relevant process and quality data to it.

The system shall support the decision making process.

Table 5. List of activities that a SPCS should perform.

From this analysis two main goals are defined with the implementation of an Industry 4.0

based system in the Angle monitoring process. First to automate the process for the calcula-

tion of a proper Angle interval. Second to perform a continuous real-time smart monitoring of

the tightening process. For both goals there are two main activities, data collection and data

analysis.

As defined by Weihrauch et al. (2018) an efficient SPCS consists of four main features:

Data from the live virtual representation is used to generate manufacturing and quality rec-

ords. Algorithms for simulation and prediction of future states use data from and to determine

possible effects of events or decisions. The Decision Support System (DSS) finally uses data

from all sources to provide a holistic view of the current situation, past events and possible

future developments.

Page 42: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

41

Figure 24. Flow of data in an ideal SPCS in Scanias tightening process.

It is important to point out that although a live virtual representation of the process is a

main feature for an efficient SPCS, it is not considered in this report since there is no virtual

twin of the production and the creation of it is out of the research scope.

Now that the ideal SPCS has been defined, and with the system requirements, activities

and delimitations, it is possible to map the ideal process of correlations between involved

tools (Figure 24).

To be able to have a smart tightening process the system should be able to extract the

monitoring data from tightening tools. This data should be transferred automatically into a

software that is able to perform advanced statistical analysis. The next step is to run the statis-

tical analysis which varies depending on the goal. Next is a brief proposal of this system for

both goals: calculation of Angle interval and smart Angle monitoring.

6.1.1 Calculating the Angle interval

When calculating a proper Angle interval the data from the tightenings (Torque and An-

gle) needs to be analyzed by linear regression. Using the calculated Angle interval a capability

analysis needs to be run to evaluate feasibility of implementation. Deviations occurring in the

process are identified and analyzed to eliminate them (decision making process). Finally all

the data must be recorded into a database for future work. The process of Angle interval cal-

culation is better explained in Figure 31 in the appendix. It is good to clarify that we per-

formed this calculation for two joints. However Scania requires that this process is done for

each and everyone of the C/L joints found in the assembly line and also for new joints. This is

the reason why this process should be automatized.

6.1.2 Smart Angle monitoring

On the other hand, for real time process monitoring, data is being continuously analyzed

by a statistical software, so the data from tightenings must be extracted without delay into a

Page 43: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

42

statistical analysis software. The results from Statistical Process Control can then be analyzed.

Then a tool for automatic decision making is necessary. This tool should be able to, by look-

ing at results from SPC and maintenance (MAXIMO), calibration (ACTA) and quality rec-

ords, make decisions to finally make changes in production or alert people involved in the

process (team leader, tightening or maintenance departments) of possible deviations and solu-

tions.

Besides the previously mentioned things, maintenance (MAXIMO), calibration (ACTA)

and quality tools should be accessible by the decision making software which can then, after

SPC analysis, provide live feedback and make changes. This system should work as a loop to

assure continuous improvement and monitor performance of the system.

6.2 Current state analysis

Figure 25. Position of software involved in tightening within Scania’s architectural system.

As mentioned before all of the software involved in the programming, maintenance, cali-

bration and monitoring of the tightening processes in Scania work independently without a

connection to Scania’s system (Figure 25) or between each other, this is because the software

is made by the supplier of the machines (Atlas Copco). This is the reason why, as explained in

the data collection part of this report, data is extracted from Toolsnet into an Excel file, before

it is possible to do a statistical analysis of the process.

Toolsnet works as the database where all of the information that occurs during tightening

process is found. Although it is able to perform a capability analysis, it can only perform this

with Torque data. Even though Angle data is collected Toolsnet is not able to perform analy-

sis. Currently the analysis of Angle monitoring done is by looking at the Torque Angle curves

found in Toolsnet when a problem in production occurs.

The possibility of an SPCS implementation is limited by the lack of connections between

the tools used currently in Scania as shown in Figure 26.

Page 44: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

43

Figure 26. Flowchart of the current flow of data in Scania’s tightening process.

Most of the data transfer between the involved tools is currently performed manually and

there is no tool on PISA system that is able to collect and send relevant data to other tools.

Calibration, maintenance and quality checks scheduling are currently implemented using in-

dependent software solutions with no automated interface to the PISA system.

Finally, all decisions depend on a limited number of people who have enough knowledge

to interpret the monitoring, maintenance, calibration and quality data. No virtual representa-

tion or simulation data is used in the decision making process.

6.3 Proposal

There is an alternative approach proposed by the digital factories department in Söder-

tälje (Mahesh & Umer, 2017) to use a Plant Service Bus (PSB) system in order to establish

communication with the power tools. This connection makes it possible to extract data auto-

matically into a database which can connect to a statistical software for analysis of the data.

Finally after analyzing the data it can be presented in an efficient way to the involved person-

nel according to their needs.

6.3.1 Data gathering and statistical analysis

Data would then be extracted directly from the steering cabinets using the PSB service as

shown in Figure 27. Then another service which is able to subscribe to the PSB known as the

Hadoop data lake works as a database that is able to connect to Zeppelin. Zeppelin is a statis-

tical analysis tool that can perform SPC and present data efficiently for personnel to interpret

(Mahesh & Umer, 2017).

Page 45: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

44

Figure 27. Flowchart of data flow of the tightening process considering proposal by Mahesh et al

(2017).

1) Identification of needs

Since this kind of system has already been developed by Scania the needs for implemen-

tation would be mostly about infrastructure. The system requires that every steering cabinet is

connected to an adaptor able to send data to the database.

Other requirement is the training of personnel in this kind of software. This can be fixed

if Scania creates a tool easy to access by the involved personnel. However some level of train-

ing would still be necessary.

2) Economic analysis

The requirements previously mentioned would lead to some costs but the major costs that

have been identified are the major changes that need to be done in the actual production line.

Since every steering cabinet should have it’s own adapter the activity to perform this would

require people to perform, time and possibly stop time necessary.

Finally the IT department or someone involved in the process should also be able to con-

figure all the connections to make sure that everything is correct. Also the system should be

able to handle massive amounts of data (one day of production approx. 350 cabs).

Page 46: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

45

7. Mindset Strategy.

One of the main problems while implementing a new technology, system or making

changes into a current system is the involvement of personnel. It is the personnel involved in

the process who bring the system to life (Liker, 2013).

An Industry 4.0 based system focuses on the efficient use of all tools available in the pro-

cess to support the personnel involved to continuously improve their work (Vaidya, et al.,

2018). However as mentioned before there are some limitations for the implementation of a

smart Angle monitoring system.

From interviews with the involved personnel and research performed we know that the

greatest problem is the lack of involvement. We then defined that if this method is explained

to the management it would be easier to implement in the line. The personnel in the line is

open for an implementation of this kind of system. However, management needs to accept

this implementation plans. If the benefits and ease of implementation is explained, using as

example this project, the involvement of management will increase since it improves the

product and the brand as it helps improving Scania's core values of customer first and elimi-

nation of waste.

Moreover, as Scania's main objective is to "provide the customer with profitable and sus-

tainable transport solutions to contribute to the success of their businesses" the examples pre-

sented in this thesis prove that the implementation of a system like this eliminates both waste

of over working and increases the life of the truck, thus increasing customer's profitability.

Presenting all this benefits in this manner to the management would increase the interest

in involving all the personnel in an Industry 4.0 based system. Thus reducing the time in

which it would be possible to implement.

Page 47: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

46

8. Limitations and challenges

During the project several limitations where identified that are necessary to overcome be-

fore considering a successful implementation of an Industry 4.0 based system. The challenges

met during the project, considering Table 7 in chapter 6, are discussed below to provide an

insight on the feasibility of implementation of a smart Angle monitoring process.

To begin with, the biggest problem encountered was the fact that the tools connect direct-

ly to Toolsnet. Toolsnet provides some insight into the process. However it was insufficient

for the research performed during this project. Moreover, Toolsnet is unable to share data

automatically and the data extraction process, that needs to be done manually, is tedious and

time consuming. This makes personnel reluctant to work with the method presented in this

project and makes the involvement of personnel into a SPC driven system more difficult.

This same problem was encountered with several tools involved with the smart machines.

This makes the decision making process more difficult and makes it impossible to analyse the

behavior of the process during the occurrence of the events. Moreover the solutions to prob-

lems that previously occurred are not documented or are not accessible by all personnel. Most

of this information is only known by the personnel involved. The current system does not

efficiently support the decision making process.

There is no statistical analysis tool inside Scania’s PISA system. The lack of an analysis

tool makes the system dependent on external tools. If the proposed system were to be imple-

mented, a major restructuring of the assembly shop may be necessary.

Page 48: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

47

9. Conclusions

This paper is mainly focused on the calculation of an Angle interval. The research proves

that when properly calculated, the Angle interval works as an efficient monitoring tool that is

able to identify deviations from the process and monitor the life of the machine. The method

is a suitable base for the definition of calibration and maintenance times and it would help

Scania implement a continuous improvement system into the tightening process.

While the method defined here works for the calculation for the Angle interval. It is no-

ticeable that the process is not controlled (as shown in chapter 4) and before being able to

implement the calculated Angle interval into other joints an analysis of the deviations must be

performed by the involved personnel.

Results from the experiments performed during this project show that a eight step prob-

lem solving methodology is an effective way to identify and eliminate deviations in the pro-

cess. This allows for the Angle interval to perform a proper monitoring while increasing the

capability and quality of the process to finally reduce problems and costs for Scania overall.

In theory Angle monitoring can also be implemented into an Industry 4.0 based system.

However the research of Scania’s system done in chapter 5 shows that the main limitation for

an immediate implementation is the dependence on suppliers. Suppliers software and lack of

connections to other tools make the data collection and analysis process both tedious and time

consuming.

The automation of data extraction from Toolsnet would eliminate the aforementioned

challenges and the analysis would depend only on simple tasks in an statistical software

(Minitab). This kind of tools are able to present results and analysis efficiently enough for a

person with enough knowledge to interpret.

There is also the possibility for Scania to consider other options other than Toolsnet

which should be designed to fulfill Scania’s necessities. Moreover if Scania aims to eliminate

dependence on supplier software, tools inside the PISA system should be created. It is im-

portant to point out that tools are being developed to perform different purposes but there is

currently no tool inside PISA system able to perform statistical analysis or a DSS. The devel-

opment of proposed tools would give a great advantage to Scania CV AB, increasing process

capability, quality of tightenings, reduce time in problem solving, implement continuous im-

provement system and reduce workload on personnel involved.

The concept presented in chapter 4 (PSB) would seem, for the moment, as the most ap-

propriate approach to create a SPCS. If the interfaces are done correctly the involved person-

nel should only receive the data that concerns them and would make data interpretation and

decision making process easier. However the amount of time, personnel and resources that

need to be allocated for the implementation of a system like this may be too high for an im-

mediate implementation.

Another limitation with this approach is that the system needs to be capable of collecting

huge amounts of data and at the same time be able to connect without delay to the analysis

software. This may not be possible at the moment since the production in Scania Oskarshamn

is substantial and the amount of data gathered may be too much for the system to handle.

Page 49: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

48

10.Future work.

As mentioned before, if Scania aims for the implementation of an SPCS three main tools

have been identified for this purpose:

● Database: where relevant tightening data can be found and presented in effective man-

ner and can connect automatically to other tools.

● Statistical Analysis: Tool that can extract automatically data from the database and

perform continuous analysis.

● Decision support system: Tool to ease the process of decision making and in the future

even make decisions automatically.

The next step in the design of a SPCS is the creation of a DSS for automatic feedback

system. Since there is no virtual or simulation data, this is done by collecting information

from different activities that affect the process (maintenance, quality, calibration and process

data) and creating a database. A database can be used as the basis for a DSS by mapping the

necessary information for each department and involved tools e.g. MAXIMO.

10.1 Decision Support System

Previously in this paper, proposals for the first two tools have been identified but the

SPCS should also support the decision making process. For this purpose a Decision Support

System (DSS) is proposed as future work.

Information is the foundation of a robust decision making process and is a requirement

for efficient reaction on events. A decision making process requires (Weihrauch, et al.,

2018):

● A complete picture of the current situation in manufacturing to understand the event

and its context.

● Records of the past manufacturing process, as well as data about previously occurred

events.

Figure 28 shows a flow chart of a basic Decision Support System proposed for Scania

CV AB. The DSS monitors the process constantly and is searching for deviations. If a devia-

tion has been identified, the system decides if there is enough data to proceed with the DSS. If

enough data is not available the decision making process needs to be performed manually by

using a problem solving approach. If the system has enough data it analyzes the data and tries

to find similar situations that have occurred in the system before (decision alternatives) and

searches to see if there is a solution that is feasible for this specific deviation. This process

should also take into consideration data from MAXIMO and ACTA. When finding one feasi-

ble choice the DSS proposes preselected solutions, and the user selects one of the solution

alternatives or defines a new one. Finally, the decision is implemented by the system.

Page 50: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

49

Figure 28. Flowchart representation of a proposed DSS into Scania’s system.

The concept of machine learning proves that since the data measurement and analysis is

presented in statistics e. g. Cpk, SPC, Torque vs Angle curve, etc. this data can be analyzed to

identify patterns so the system is able to automatically detect faults (Fukunaga, 1990).

10.1.1 Pattern recognition

The proposal for the use of pattern recognition is based on the idea that recognition by a com-

puter is the process of generating an appropriate representation for information and transform-

ing it into another representation.

A pattern is any data received from the object by an input device and entered into a recogni-

tion system. Translated into tightening terms it is the data that has been extracted from the

machine and repeats itself over a time period (Fukunaga, 1990).

For the implementation of a pattern recognition tool two main algorithms are necessary:

● Algorithms for extracting the boundary and region of a pattern.

● Algorithms for recognizing the original object based on knowledge of the object, its

patterns, and how it is used.

Finally the concept of unsupervised learning (Hinton & Sejnowski, 1999) defines that after a

pattern has been recognized an output can be automatically mapped for that specific pattern

thus making it possible for the DSS to make a decision by itself without human input (Hinton

& Sejnowski, 1999).

Page 51: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

50

Figure 29. Graph showing programming conditions for the tightening tool. Retreived from (Atlas

Copco Industrial Technique AB, Publication Date Not Identified).

This concept can also be adapted into the tightening process. Results from experiments per-

formed in this project show that deviations occurring in the process present a certain behavior.

If every deviation that occurs in the production line is mapped, patterns can be recognized

over time. Then the smart tools used for C/L joints are able to send different alert signals de-

pending on the area of the curve where a NOK happens as seen in Figure 29.

If a pattern recognizes a deviation, the machine is able to send an alert directly to the per-

son involved or to the DSS and then a solution can be implemented without delay in the pro-

duction line.

In theory, the creation of a DSS is possible. But first there must be an improvement in

traceability of deviations and events occurring in the tightening process, (maintenance, cali-

bration, deviations and quality checks need to be properly recorded and studied). After acquir-

ing sufficient data a DSS based on pattern recognition will become a possibility.

In conclusion the research performed during this project proves that the monitoring pro-

cess presents promising possibilities and is suitable for an implementation into an Industry

4.0 based system. However, some organizational improvements need to be performed first. If

process, organization and personnel involvement is improved this implementation is most

definitely possible by using the tools and methodologies mentioned in this report. However, it

is important to mention that while the implementation is possible, it is a gradual process that

will occur over a long period of time.

Page 52: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

51

11 Appendix

Figure 30. Flowchart of the process of calculating an Angle interval in Scania’s system.

Page 53: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

52

References

ASSEMBLY Magazine, 2002. www.assemblymag.com. [Online]

Available at: https://www.assemblymag.com/articles/83305-choosing-the-optimum-fastening-

system

[Accessed March 2018].

Atlas Copco Industrial Technique AB, Publication Date Not Identified. Focus60/Focus61

User Guide, Publication Place Not Identified: Atlas Copco Industrial Technique AB.

Atlas Copco, 2018. Cordless Assembly Tools. [Online]

Available at: https://www.atlascopco.com/en-uk/itba/products/assembly-solutions/electric-

assembly-tools/cordless-assembly-tools

[Accessed March 2018].

Atlas Copco, 2018. Fixtured assembly solutions. [Online]

Available at: https://www.atlascopco.com/en-uk/itba/products/assembly-solutions/fixtured-

assembly-solutions

[Accessed March 2018].

Atlas Copco, 2018. ToolsNet 4000. [Online]

Available at: https://www.atlascopco.com/en-uk/itba/products/assembly-solutions/Error-

proofing-solutions/ToolsNet-4000

[Accessed May 2018].

Atlas Copco, 2018. ToolsTalk 2. [Online]

Available at: https://www.atlascopco.com/en-uk/itba/products/assembly-solutions/electric-

assembly-systems/toolstalk-2

[Accessed May 2018].

Bickford, J. H., 1995. An introduction to the design and behaviour of bolted joints. 3rd ed.

New York: Marcel Dekker.

Bickford, J. H. & Nassar, S. eds., 1998. Handbook of Bolts and Bolted Joints. New York:

Marcel Dekker.

Dean, A., Voss, D. & Draguljić, D., 2017. Design and Analysis of Experiments. 2nd ed.

s.l.:Springer.

Desoutter Industrial Tools, 2018. Electric Assembly Systems. [Online]

Available at: https://www.desouttertools.com/tools/2/electric-assembly-systems

[Accessed March 2018].

Durivage, M. A., 2015. Practical engineering, process, and reliability statistics. s.l.:American

Society for Quality (ASQ).

Fukunaga, K., 1990. Introduction to Statistical Pattern Recognition. 2nd ed. Boston:

Academic Press.

Gejdoš, P., 2015. Continuous Quality Improvement by Statistical Process Control. Procedia

Economics and Finance, Volume 34, pp. 565-572.

Page 54: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

53

Goldsmith, R. H., 2014. Toyota's 8-Steps to Problem Solving. s.l.:CreateSpace.

Hinton, G. & Sejnowski, T. J., 1999. Unsupervised learning: Foundations of neural

computation. Computers & Mathematics with Applications, 38(5-6), p. 526.

Jiju, A. & Jiju Antony, F., 2001. Teaching the Taguchi method to industrial engineers. Work

Study, 50(4), pp. 141-149.

Johnson, R., Freund, J. & Miller, I., 2011. Miller & Freund´s Probability and statistics for

engineers. 8th ed. Upper Saddle River, NJ: Pearson Prentice Hall..

Liker, J. K., 2013. The toyota way : 14 management principles from the world´s greatest

manufacturer, New York: McGraw-Hill.

Limon-Romero, J. et al., 2016. Application of the Taguchi method to improve a medical

device cutting process. The International Journal of Advanced Manufacturing Technology,

87(9), pp. 3569-3577.

Mahesh, B. & Umer, M., 2017. Smart Connected Power Tools; An Industrial Implementation

of Event Driven Architecture, Stockholm: s.n.

Minitab, 2018. Data transformations. [Online]

Available at: https://support.minitab.com/en-us/minitab/18/help-and-how-to/quality-and-

process-improvement/capability-analysis/supporting-topics/distributions-and-transformations-

for-nonnormal-data/data-transformations/

[Accessed April 2018].

Neseli, S., 2014. Optimization of process parameters with minimum thrust force and Torque

in drilling operation using Taguchi method. Advances in Mechanical Engineering, Volume

2014.

Pennsylvania State University, 2018. Regression Methods (STAT 501). [Online]

Available at: https://newonlinecourses.science.psu.edu/stat501/

[Accessed March 2018].

Roy, R. K., 2010. A Primer on the Taguchi Method. 2nd ed. Place of publication not

identified: Society of Manufacturing Engineers (SME).

Santos, C. et al., 2017. Towards Industry 4.0: an overview of European strategic roadmaps.

Procedia Manufacturing, Volume 13, pp. 972-979.

Scania, 2017. Internal Standards, Södertälje: Scania CV AB.

Scania, 2018. Om Scania Oskarshamn. [Online]

Available at: https://www.scania.com/productionunitoskarshamn/sv/home/om-scania-

oskarshamn.html

[Accessed May 2018].

Scania, 2018. Scania at a glance. [Online]

Available at: https://www.scania.com/group/en/scania-at-a-glance

[Accessed May 2018].

Page 55: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

54

Vaidya, S., Ambad, P. & Bhosle, S., 2018. Industry 4.0 – A Glimpse. Procedia

Manufacturing, Volume 20, pp. 233-238.

Weihrauch, D., Schindler, P. A. & Sihn, W., 2018. A Conceptual Model for Developing a

Smart Process Control System. Procedia CIRP, Volume 67, pp. 386-391.

Yusoff, N., Yusup, S. & Ramasamy, M., 2011. Taguchi's parametric design approach for the

selection of optimization variables in a refrigerated gas plant. Chemical Engineering Research

and Design, 89(6), pp. 665-675.

Page 56: QUALITY ASSURANCE THROUGH SMART ANGLE MONITORING1294100/FULLTEXT01.pdf · by studying the relationship between torque and angle using the linear regression method (Pennsylvania State

TRITA ITM-EX 2018:559

www.kth.se