QUANTITATIVE TECHNIQUESBusiness
Management of Projects
8/10/2019 Quantitative Lecture Pwu
2/42
What is a project?
DeadlineManagement
Manage toPlan
8/10/2019 Quantitative Lecture Pwu
3/42
Costs of ProjectFailure
Standish Group survey of US IT Systems Projects:
17% Met Target
50% Had to have targets changed
33% Cancelled
Cost to US Companies $80 Billion/Year
8/10/2019 Quantitative Lecture Pwu
4/42
Separating ObjectivesProject Objectives - the deliverableProject Management Objectives
Execution Costs/Time/Quality
8/10/2019 Quantitative Lecture Pwu
5/42
8/10/2019 Quantitative Lecture Pwu
6/42
Project PlanningWork Breakdown StructureResource EstimationLogical Dependencies
Project SchedulingCPA, Critical Path AnalysisPERT, Programme Evaluation and ReviewTechnique
Output - Gantt Charts & ResourceHistograms
8/10/2019 Quantitative Lecture Pwu
7/42
WBS Level NamesProgramProjectTask
Sub TaskWork PackageActivity
8/10/2019 Quantitative Lecture Pwu
8/42
Work Breakdown
Structures
8/10/2019 Quantitative Lecture Pwu
9/42
www.picassodlcf..com.uk/lecture
8/10/2019 Quantitative Lecture Pwu
10/42
2.995m Municipal Truck
Specification Changes:
Crew cab Interior TrimRear SeatsWide Access
Controls Change Speed
Engine 9 gm NoX
Brakes ABS
Chassis Framesides/XmbrSprings & Dampers
8/10/2019 Quantitative Lecture Pwu
11/42
WBS Task Level100 Concept Investigation200 Concept Approval D2300 Programme Definition400 Programme Approval D4500 Engineering Release Stage IV600 Methods Review
700 Build/Sign off Mock-up800 Prototype Build900 Test/Development1000 Stage V Sign off1100 Procure pre-prod materials1200 Sample Approval
1300 Pre-Production build1400 Issue material to lineside1500 Proof build1600 Job 1
8/10/2019 Quantitative Lecture Pwu
12/42
WBS Sub Task500 Engineering Stage IV Release
510 Change Speed520 Engine530 Chassis540 I nter ior Tri m
141 LHS Side Trim
142 RHS Side Trim143 Rear Seat144 LHS Doo r Step Kic ker Plate
8/10/2019 Quantitative Lecture Pwu
13/42
8/10/2019 Quantitative Lecture Pwu
14/42
Estimating ResourcesAn exact estimate is impossibleThe more experience there is of anactivity the easier it is to estimate.
If people are punished for failure theywill pad estimates.Project estimating assumes 50%probability estimates are used unless
specified otherwise.
8/10/2019 Quantitative Lecture Pwu
15/42
X X XX
onsensuaEstimating
Situation A
Time
E s t
i m a
t e 2
E s t
i m a t e
1
E s t
i m a t e
4
E s t
i m a
t e 3
E s t
i m a
t e 5
E s t
i m a t e 4
E s t
i m a t e 3
E s t
i m a t e 2
E s t
i m a t e 1
Situation B
TimeX X X X X
8/10/2019 Quantitative Lecture Pwu
16/42
8/10/2019 Quantitative Lecture Pwu
17/42
Activity Network(Activity on Node)
100 1100400300200 500
600
700 800 900
1000 16001500140013001200
8/10/2019 Quantitative Lecture Pwu
18/42
Programme Evaluation & ReviewTechnique - PERT
Distribution of activity times
Days LateDays Early
Probability
8/10/2019 Quantitative Lecture Pwu
19/42
PERTfor a Task
a = optimistic duration
b = likely durationc = pessimistic duration
Expected Time = a + 4 x b + c6
8/10/2019 Quantitative Lecture Pwu
20/42
PERTfor a Project:
Expected Project Duration is the sum of the expecteddurations of the activities on the critical path.
for an activity:
The standard deviation = a - c6
for a Project:Standard deviation = s 12+s 22+s 32.
8/10/2019 Quantitative Lecture Pwu
21/42
Gantt Chart
8/10/2019 Quantitative Lecture Pwu
22/42
Resource Histogram
8/10/2019 Quantitative Lecture Pwu
23/42
Schedule Computations(fixing the plan to a point in time)
Forward SchedulingBackward SchedulingResource Constraining
8/10/2019 Quantitative Lecture Pwu
24/42
Shortening the ProjectAdd ResourceReduce Scope (or eliminate scopecreep)
Change ProcessLook for activities that can be done inparallelReduce Quality
Project Managers Desk Reference J P Lewis
8/10/2019 Quantitative Lecture Pwu
25/42
Bottleneck
Float
Effect of Slippage
Critical
Slip
8/10/2019 Quantitative Lecture Pwu
26/42
Bottleneck
Float
Critical Chain Theorythings are more likely to go wrong than get better!
Buffer
Critical
Eli Goldratt Critical Chain
8/10/2019 Quantitative Lecture Pwu
27/42
ro ec e vera eReview
DesignDoes it Work?Can we make it?Is it still viable?
Risk
8/10/2019 Quantitative Lecture Pwu
28/42
ro ec anagemenReview
Current Project StatusFuture StatusStatus of Critical Tasks
Risk AssessmentInformation Relevant to otherProjectsLimitations of Review
8/10/2019 Quantitative Lecture Pwu
29/42
Project Team ReviewLeadershipDecision MakingProblem Solving
CommunicationsMeetingsPlanningGiving Feedback to Team
MembersConflict Management
8/10/2019 Quantitative Lecture Pwu
30/42
Final MessagesProject management challengeincreases with number ofcommunication interfaces
Estimating is difficultSoftware tools help to establish anachievable plan beware GIGOPlan to Manage Manage the Plan
8/10/2019 Quantitative Lecture Pwu
31/42
Causes of Perceived Project FailureInsufficient use of project/status reportsUse of superficial status reportsInadequate project management, administrative,human & technical skillsInsufficient project manager influence and authorityPoor co-ordination with clientLack of rapport with client/parent organisationClient disinterest in budget criteriaLack of project team participation in decisionmaking/Problem solvingExcessive structure within project teamJob insecurity within project teamLack of team spirit and sense of mission withinproject team
Appendix 1 1/2
8/10/2019 Quantitative Lecture Pwu
32/42
Causes of Perceived Project Failure
Parent organisation stable, non dynamic, lacking strategicchange
Poor co-ordination with parent organisation New type of project Project more complex than parent handled previously Initial underfunding/under resourcing Inability to freeze design early Inability to close out effort Unrealistic project schedules Inadequate change procedures
Appendix 1 2/2
8/10/2019 Quantitative Lecture Pwu
33/42
Review QuestionsProblem not clearly definedPlanning based on insufficient dataPlanning just performed by planning groupNo one is in chargeProject estimates are best guesses,made withoutconsulting historic dataResource planning is inadequateProject dont see them selves working as one team People are constantly pulled off project or reassignedwith no regard for impactThe project plan lacks detailThe project is not tracked to planPeople loose sight of the original goalSenior managers refuse to accept realityBallpark estimates become official targets
Appendix 2
8/10/2019 Quantitative Lecture Pwu
34/42
CASE STUDYNorth West Rail Link
The North West Rail Link is a priorityrail infrastructure project for the NSW
Government. Planning is well underway on the23km rail link to Sydney's growing North West
region.
Eight new railway stations are proposed at:Cherrybrook, Castle Hill, Hills Centre, Norwest, BellaVista, Kellyville, Rouse Hill and Cudgegong Road.Also planned are 4,000 commuter car parkingspaces.
8/10/2019 Quantitative Lecture Pwu
35/42
8/10/2019 Quantitative Lecture Pwu
36/42
The North West Rail Link will deliver savings of up to 3 hours a weekin journey times to the Sydney CBD as well as frequent,reliable, direct rail services between the North West and Macquarie Park,Chatswood, North Sydney and the city. The rail link includes 15km oftunnels between Bella Vista and Epping - the longest and deepest railtunnels ever built in Australia.
InfraSol Group was appointed by Transport for NSW in May 2011 towork as part of their inhouse project management team to deliver thefollowing Services for the Business Case Stage of the $9 Billion project.
8/10/2019 Quantitative Lecture Pwu
37/42
CASE STUDY
The National Gallery of Australia,Canberra - Stage 1 Extensions
A $100 million Stage 1 Extension to the NationalGallery of Australia was under construction on sitewhile the design was still being completed.
8/10/2019 Quantitative Lecture Pwu
38/42
One of the main sources of concern for the buildingcommittee, in charge of the delivery of theextensions to the existing National Gallery of
Australia(NGA) building, was the lack of finalisation ofthe architectural and engineering designs whilst atthe same time construction had already commenced.InfraSol Group was engaged by the NGA to help themovercome the following challenges in taking theproject to completion:
Provide strong Project Leadership through theProject Director role
Undertake a Quantitative Risk Assessment of theprojectEffectively Managing design to completionImplement a Testing and Commissioning
Management process for the Building Services
8/10/2019 Quantitative Lecture Pwu
39/42
1. Project Leadership
The InfraSol Group principal, John Barrow, wasbrought in to resolve the problems with theproject delivery.
John tackled the problem head on by doing thefollowing:Meeting with the building committee
Meeting with the construction management team
Meeting with the key design consultant
8/10/2019 Quantitative Lecture Pwu
40/42
With the benefit of the above background Johnwas able to prepare a project review
report which was presented to the buildingcommittee which resulted in the followingrecommendations being adopted to get theproject on track:
Install John as project director to over see the project andreport to the building committee
Implement managing of the design
Arrange for a quantitative risk assessment of the projectin terms of cost and time
Arrange for weekly meetings with the construction managerand his team along with regular design meeting
8/10/2019 Quantitative Lecture Pwu
41/42
The result of InfraSol Group's projectleadership was the successful delivery of theproject to meet the construction programme and tothe required quality and completeness.
8/10/2019 Quantitative Lecture Pwu
42/42
2. Quantitative Risk Assessment
The InfraSol Group Risk Manager , GrantHookway, was brought in to undertake aQuantitative Risk Assessment for the project.
Grant arranged and facilitated tworisk workshops which included all the relevantstakeholders and project team members. As a resultof the workshops, Grant was able to identify anumber of key risks on the project as follows:
Cost to completeTime to complete
--- Risk Management