QUARTERLY PROGRESS REPORT 1 First Quarter 2009 1. Country: Cook Islands, Fiji, Kiribati, Nauru, Niue, Papua New Guinea, Samoa, Solomon Island, Tonga, Tuvalu and Vanuatu 2. UNDP Award ID: 00044633 3. Project Title: Pacific Islands Greenhouse Gas Abatement through Renewable Energy Project (PIGGAREP) 4. Implementing Partner: Secretariat of the Pacific Regional Environment Programme (SPREP) 5. GEF Implementing Agency: United Nations Development Programme (UNDP) 1 This report is based on the PIGGAREP 2009 work plan and budget that was developed at the First Multipartite Review Meeting of November 2008.
Transcript
Page 1: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

QUARTERLY PROGRESS REPORT1 First Quarter 2009

1. Country: Cook Islands, Fiji, Kiribati, Nauru, Niue, Papua New Guinea, Samoa, Solomon Island, Tonga, Tuvalu and Vanuatu

2. UNDP Award ID: 00044633 3. Project Title: Pacific Islands Greenhouse Gas Abatement through Renewable

Energy Project (PIGGAREP) 4. Implementing Partner: Secretariat of the Pacific Regional Environment Programme

(SPREP) 5. GEF Implementing Agency: United Nations Development Programme (UNDP)

1 This report is based on the PIGGAREP 2009 work plan and budget that was developed at the First Multipartite Review Meeting of November 2008.

Page 2: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

6. Period Covered: 1st January – 31st March 2009 7. Summary of Overall Project Progress: This is the first progress report on the 2009 Work Plan, attached as Annex 1, a work plan that has been designed based on the experiences with the slow delivery rate on the 2008 work plan. The multipartite review (MPR) meeting of November 2008 agreed that all PICs must only have an average of five activities each for the 2009 work plan but with the flexibility to increase or decrease based on capacity and delivery. The general progress during the quarter was satisfactory. The difficulty of drafting the Project Activity Summary (PAS) was identified during the MPR as a key constraint to the delivery of the 2008 work plan. The first activity for the quarter was therefore a regional workshop on drafting PAS and project proposals. Of the eleven (11) activities for the quarter, implementation of two were completed, the PAS for four (4) were endorsed by the project steering committee (PSC) and are at their early stages of implementation, four (4) were drafted and reviewed and will be finalised for PSC endorsed next quarter and the PAS for only one (1 – Kiribati Public Awareness Campaigns) of the activities has not been developed. Notable progress was made in the implementation of baseline activities. These include Fiji’s Energy Legislation, biogas development as well as solar photovoltaic programmes. Good progress was also noted in the implementation of the IUCN / Italian-funded projects in the Solomon Is, Tonga, Tuvalu and Vanuatu. In some activities, e.g PNG 09-2: Biofuel Research, the progress in the co-financing activities is much faster than the incremental activities. Some PICs are eager to implement all their five (5) activities as soon as possible and then to implement extra activities. These PICs have drafted PAS for activities in the third and fourth quarters and have indicated their desire to move the implementation of those projects forward. Fiji introduced two (2) new activities (FJ 09-New 1 on hydro resource assessment and FJ 09-New 2 on biofuel) in which the implementation of their co-financing activities are progressing very quickly. The general progress in the implementation of the 2009 work plan can be seen in Table 1 below. Baseline and Incremental Activities implemented in 2008 are also included for completeness purposes. The general progress per PIC can be seen below:

Page 3: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Cook Is

No updates received for the quarter despite repeated requests.

Fiji Fiji’s co-financing activities include the following: 1) Energy Legislation The project will develop a comprehensive Energy Bill that takes into account existing Regulations, Policies (Charters) and Acts (Laws) related to the energy sector. This Bill will be guided by the existing Government policies to ensure that energy sector developments contribute meaningfully to the overall socio-economic development goals of improving the livelihood of all the people. The TOR for the work has been developed and tenders were called. Five tenders were received as follows:

• Enzen Technologies, Bangalore, India • Fiji Institute of Applied Studies, Suva, Fiji • Prem Narayan Barristers and Solicitors, Suva, Fiji • Jagjit Singh, Lecturer, University of the South Pacific, Fiji • ARD Power Plants Company Limited, Sigatoka, Fiji

The Department of Energy when analysing the tenders needed further clarification from one of the bidders, Enzen Technologies on project costs and time frame for completion and thus a request was sent to them. Once this information is received, the Department will complete its evaluation and prepare a submission to the Tender Board for approval. The Department anticipates that the project will be completed by December 2009. 2) Biogas Programme Ten biogas digesters will be installed in suitable farms to produce gas for cooking and heating purposes. Prior to the construction of the 10 digesters, we carried out a training of trainers in 2008. The training which was for one month was attended by 20 participants. The participants constructed a digester at the Ministry of Agriculture’s Koronivia Research Station, as part of the training. A consultant from S. Africa was contracted by the Department to conduct the training. This aspect of the project was funded from the Department's allocation. The trainees who have undergone the training will be engaged in the construction of the ten digesters. After the completion of the first training, there was a need for these trainees to undergo further training in building digesters so that they can be well acquainted with the construction work and be recognised (through certification) in building biogas digesters. It is to be noted that there is very limited skills available in-country for building digesters and it is important for the

Page 4: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

sustainability of the project that while constructing the biogas digesters, capacity building is also taken into consideration. Thus the Biogas Certification Training is an important aspect of the Biogas Program. This year the Department of Energy continued with its certification training – four sites have been assessed and selected, the builders have been identified and four teams that ranges from two to five builders have been selected; materials purchased and transported to the four sites, and the actual construction work has commenced at Queen Victoria School, Ratu Kadavulevu School, Wainiyabiya Settlement and Namatakula village. The works are expected to be completed by June. The following are the details from the schools: Queen Victoria School The school requested for a biogas digester so they can use methane gas for cooking at the school dining hall. Currently the boarding school has about 700 students and they have been using LPG for cooking which costs $2,000 per month. The school has a cattle farm as source of milk for the school’s needs and a piggery farm as food source. There are some 200 pigs kept in a well maintained concrete shed. A 15m3 digester is currently being constructed at the school. QVS Piggery Pen & Kitchen

15m3 Digester - QVS

Page 5: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Ratu Kadavulevu School Similar to QVS, RKS also requested the biogas digester to assist in the reduction of use of LPG for cooking of student meals. In the past years they have been spending thousands of dollars per month for the purchase of LPG. The school has a roll of 700 students all of which are borders. RKS also has a piggery farm with a total of 300 pigs. A 15m3 digester is currently being constructed at the school. Kitchen – RKS

Piggery Pen Construction Site

Wainiyabiya Project A family in Wainiyabiya settlement, Serua with eight members requested a biogas digester for cooking purposes and also as a means of proper disposing of pig wastes. They have a total of 8 pigs in a well maintained pen. The distance between the house and the piggery pen is about 35 meters. A 8m3 digester is currently being constructed at the site.

Page 6: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Piggery Pen Excavation site

Namatakula Project 8m3 Digester- Namatakula

The Namatakula biogas site is located in Namatakula village, Nadroga and very close to the Queens highway. The household consist of seven people and the biogas will be used for cooking in the kitchen. The distance between the biogas site and the kitchen is about twenty meters. A 8m3 digester is currently under construction at the site. Constraints The major constraint in the initial phase of the project is the wet weather condition affecting the Fiji Group. The delay in the timely delivery of building materials to the four project sites also affects the construction works. 3) Biofuel Standards The long-term aim is to provide an enabling environment for the eventual establishment of a sustainable National Biofuels Programme, aimed at the widespread application of the technology in all sectors of the country. Although biofuels are used in other countries, utilization in Fiji is sporadic and minimal. The work on Biofuels Standards component of the project can be divided into two parts:

Page 7: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

i) Quality Standards for liquid biofuels: ethanol, bio-diesel and coconut oil. ii) Testing of vehicles with the Biofuels blends that will form a part of the National Mandate

such as: (a) E-10 which is blend of 10% ethanol + 90% gasoline; (b) B-5 which is blend of 5% biodiesel + 95% diesel.

Quality Standards The draft standards for ethanol and bio-diesel were drawn up on the basis of quality standards for these two fuels that have been declared in Brazil, India, Europe and USA. The draft standards for coconut oil were prepared by Dr Gilles Vaitilingom of the French national organization CIRAD who is a leading international expert on the use of pure coconut oil in diesel engines. The coconut oil standards will be finalized after testing coconut oil of different qualities in diesel engines. Costs for equipment required to measure the parameters in the standards, for testing the coconut oil in diesel engines and confirming the final coconut oil standards for diesel engines are presently being estimated. Blend Testing Vehicle data from the Land Transport Authority has been analysed and the number of vehicles on Fiji’s roads sorted out according to their year of manufacture. A summary of the information is provided below. The figure shows the number of vehicles for different fuel types registered with Land Transport Authority, Fiji from 1st January 2008-29th April 2009. It is clear that Diesel and Petrol run vehicles comprise 98% of the total registered vehicles in Fiji. A report on the vehicle information is being prepared and will be finalised by the end of May.

Fuel Types against Number of Vehicles till 29/04/09

Different Fuel TypesDiesel Electric Gas Multiple N/A Other Petrol Solar Steam Unknown

Num

ber o

f Veh

icle

s

0

10000

20000

30000

40000

37,141

33

1089 89

604

921

36951

12

6 326

Page 8: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

4) Solar Home Systems We currently have about 1000 solar home systems in the rural communities and we continue to maintain these systems. Each system comprises of 40 W of fluorescent lights and a power point for a small radio; 100 Wp of PV; 100 Ah, 12 V deep cycle battery with 8 A charge controller. The SHS program is designed such that the:

• Technical design, purchasing, and system ownership by FDoE

• Users will be self-selected and clustered in groups of a size that is appropriate for economically reasonable periodic maintenance by the RESCO

• Users will be required to pay a monthly fee that covers a portion of the capital cost of the installed system and the full cost of operation, maintenance and repair of the systems

• Maintenance and repair services are to be provided by private contractor RESCO operators with technical support, evaluation, certification and regulation by the FDoE.

• Financial controls and technical controls will be put into place and administered by the FDoE to ensure continuing financial and technical responsibility by the RESCO contractors

This year we commenced with the installations of 142 solar home systems in Vanua Levu and the details are provided as follows. Name of Community Province No. of houses Progress Malawai Settlement Macuata 31 Systems have been energized.

Project completed Muanidevo Settlement Macuata 15 Systems have been energized.

Project completed Korokadi Settlement Macuata 22 Systems have been energized.

Project completed Vunivere Settlement Macuata 21 Installation in progress Nabiti village Macuata 3 Installation has been

completed. Systems to be energised

Visoqo village Macuata 3 Installation in progress Matanidoi village Macuata 8 Installation in progress Nabubu village Macuata 7 Installation in progress Saolo village Cakaudrove 12 Installation in progress Nakawakawa village Cakaudrove 11 Installation in progress Daria village Cakaudrove 5 Installation in progress Nawaisomo village Cakaudrove 4 Installation in progress

Page 9: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Kiribati 1) Implementation Plan The development of an implementation plan for Kiribati’s National Energy Policy (KNEP) in the Gilbert & Linnix Islands is awaiting Cabinet endorsement of KNEP. This KNEP is expected to be endorsed during the second quarter of 2009. 2) Solar Water Pumps The funds for this Italian-funded project has been received and the implementation is anticipated to start on the second quarter of 2009 and to be followed by the PIGGAREP-funded incremental activities which will include training for water technicians and the recipient communities. 3) RESCO Manager. The UNDP Project Document (baseline) has been approved. Awaiting signing of the Face form for processing payment of the second quarter budget. Bio-fuel feasibility study in Kiritimati Island This project has been approved for funding by the Italian government pending a final revision based on comments received on the Project Document.

Nauru Arrival of the wind monitoring equipments at Nauru is expected to be in the send quarter and for the installation to be followed shortly thereafter.

Niue The installation of the 35 – 55 kW grid connected PV system has been delayed until July due to a change in the arrival dates of the PV equipment at Niue. This is expected to be in late May and therefore the associated PIGGAREP-supported training will be conducted on the third quarter. A PAS was developed on Strengthening Niue’s National Renewable Energy Power Production Capacity. This has been commented upon and has not been revised.

PNG Progress for this quarter has been slow again. PNGSEL and ATCDI were not successful in securing donor co-financing to start up some projects. PNGSEL has identified a new project and ATCDI continued to source co-financing possibilities. PNG Sustainable Energy Ltd There was no progress on the other projects discussed in the last quarter. PNGSEL has now selected a new hydro project for a PAS to be prepared. This project is the 2 MW Togarao hydro

Page 10: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

power project located in the Autonomous Region of Bougainville. This project was not included in the 2009 PIGGAREP project matrix. A PAS has been prepared by PNGSEL and this will be submitted to PSC for consideration as the project sponsor has given the approval for its development. ATCDI Progress has been slow since the last quarter report. ATCDI has been informed that the Italian Government funding will not cover activities in PNG. The biodiesel PAS with comments from the PSC was given to Professor John Pumwa who is coordinating the biodiesel project to revise. The revision has not been completed. ATCDI has been looking for co-financing partners for sometime without success. A technical report on the 4.5 kW pico hydro power unit using the “pump as turbine” system for Paruparu village, which is a mountain community in Bougainville, was completed and sent to the donor and other stakeholders. The proposal on the O & M training has not been undertaken yet due to other work. The plan is to prepare a PAS to PIGGAREP to assist with co-financing of the training.

Samoa Final consultations were carried out in the month of February with two of the villages identified for monitoring sites as part of the Hydro Data Collection Programme. This was an opportunity to seek permission from the village councils to install monitoring (water level gauges) at the pre-identified sites. These consultations were followed by site surveys to identify suitable locations to install the water level gauges A Memorandum of Understanding between the Electric Power Corporation and the Ministry of Natural Resources and Environment is being finalised and this will help guide the implementation of this project. The shipment of water level monitoring equipment has been finalised and paid for by ADB and it is expected to arrive in the country in the next quarter.

Page 11: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Consultation with one of the villages identified for hydro monitoring. Sites that have been identified for the installation of the wind masts were revisited to re-engage the villages in a consultation process and to determine the amount of civil works required for each site. Most of the equipment for the wind monitoring equipment have arrived which have been paid for by PIGGAREP and installation is expected to start early in the next quarter. The Upolu Wind Resource Assessment report has been completed and a site has been identified as having potential for a commercial wind farm. However more data collection must be carried out in order to confirm the results of the assessment.

EPC staff carrying out assessments of the sites earmarked for installation of wind monitoring equipment in Savaii. The Final Project Document and Investment Plan for the Preparatory Phase of the Solar (PV) Rural Electrification Programme has been completed. EPC will now be looking for donor funding to implement this project. EPC has now increased the percentage of its Coconut Oil Blending trials to 5% after the successful 2% trial (2% Coconut Oil: 98% Diesel). It is anticipated that the successful outcome of this trial will lead to a further increase in the blend percentages.

Page 12: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Solomon Is The first quarter of 2009, was a slow start for Solomon Islands, in terms of implementing it RE activities. Though slow, due to financial constraints imposed by the Ministry of Finance and Treasury, the following RE activities or Projects progressed:

i) Power needs Assessments and Installation of Solar PV Systems in Community High

Schools funded by the Italian and Turkish Governments; ii) Building of the RE Information Center iii) Update Feasibility Study for the Huro and Rualae Mini-Hydropower Schemes

(Government had just allocated funds for the implementation) iv) Bio-fuel Development and Expansion in SI

Power needs Assessments and Installation of Solar PV Systems in Community High School In the first quarter of 2009, power needs assessments were done at the following secondary schools:

i) Adaua Provincial Secondary School (Malaita Province) - Italy ii) Pawa Provincial Secondary School (Makira Province) - Turkey iii) Su’umoli Community High School (Makira Province) - Turkey iv) Rokera Provincial Secondary School (Malaita Province) - SIG v) Buruku Adventist Community High School (Western Province) - Turkey

Of these assessed schools one school had been installed with Solar PV system. That is Buruku Adventist Community High School. Currently, Energy Technicians are currently doing the solar PV installations at Adaua Provincial Secondary School. The system at Buruku Adventist Community High School had a total capacity of 1.515 kW. The set consists of stand-alone systems installed in classrooms; dormitories; administration block and staff houses. The total capacity for Adaua Provincial Secondary School solar PV system is about 2.0kW. That comprises of individual stand-alone systems for the administration block; dormitories; classroom and other amenities. RE Information Center The construction of the Renewable Energy Information Center is progressing well. So far most of the main structural works are near completion and the final touches would be followed. This will go along with the installation of the RE Equipment and the laboratory furnishing.

Side view of the building from where the biodiesel generator will be set-up

Page 13: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Bio-fuel Development and Expansion in SI The Government (Cabinet) approved the setting of a Task force to spearhead the Bio-fuel development Program in March this year (2009). A Task Force was appointed already which comprise stakeholders from relevant Government Ministries like the Ministry of Agriculture, Ministry of Commerce, Ministry of Environment and Conservation and Ministry of Planning and Aid Coordination; Statutory bodies (Commodity Export Marketing Authority); SIEA; private sector and the Central Bank of Solomon Islands. This Task Force will convene its inception meeting in two weeks’ time, upon which another Cabinet Paper will be presented before the Cabinet on the full mandate of the Task Force, which will reflect upon the final budget allocation for the Bio-fuel Program. Other Activities under the Rural Electrification Program The following activities were completed in the first quarter of 2009:

i) Installation of Aola Rural Health Centre Hybrid system (in Guadalcanal Province). This hybrid system comprises of 1.7kW solar PV system and a 6 kW biodiesel generator set.

A Hybrid System installed at AOLA Rural Health Centre (North Guadalcanal)

View of where the pico-hydro turbine will be installed

Page 14: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

ii) b) Power needs assessment of Rokera Provincial Secondary School. This is to look at options of replacing the diesel generator with a bio-diesel generator-solar PV Hybrid system. Funding will come from the SIG

Tonga Rehabilitation of the Mango and Mo’unga’one PV project The report on the technical, institutional, environment and economic impacts assessment of the Mango and Mo’unga’one Solar Photovoltaic Rehabilitation Project was completed and distributed among the key stakeholders during the quarter. Solar Street Lighting The Chinese Government through the Nuku’alofa Township Reconstruction Development project has endorsed solar street lighting to be installed all over the Nuku’alofa area. The institutional setup is still being worked out but the Energy Division has been approached to assist in catering for the training needs of these projects. The suppliers/installers of solar street lighting and solar water pumping equipment will participate together with PV operators/caretakers/technicians from Village Solar Water Committees. Grid-connected Photovoltaic Systems A team of 6 from Chinese Shanghai Construction (Group) General CO and the Energy Division will conduct a study during the first week of May to survey the infrastructure requirements to assist them to make recommendations to the Government regarding the development of large scale photovoltaic grid connected electrification in Tonga. This project will be funded from the AusAid fund being managed and coordinated by the Cabinet Sub Committee on Renewable Energy. The grid connected PV pilot project being proposed for Saint Andrew High School has been approved for funding by the NZAID. A total capacity of around 3kWp is expected to be installed sometime soon.

Tuvalu Tuvalu Photovoltaic Electricity Network Integration Project (TPVENIP) The purpose of the Tuvalu Photovoltaic Electricity Network Integration (TPVENIP) is to decrease the cost of electricity production and reduce greenhouse gas emissions by integrating photovoltaic electricity generation into the electricity power networks on the island of Vaitupu. The TPVENIP is funded by the Italian Government and include the installation and commissioning of a 40 kW grid-connected solar PV system with battery storage and is expected to bring about a reduction of 184 tonnes of CO2. In September 2008, the Consultant was recruited to carry out the scoping mission to Vaitupu Island. The Consultant found that the original project concept consisting of a grid-connected (grid parallel) solar system in the order of 40 kW peak should be dropped as the load pattern of

Page 15: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Vaitupu shows extended periods of 40 kW during the daytime. During the period from June to September 2008, the loads during the day even dropped below 40 kW occasionally. Under such conditions a small grid parallel PV system of 40 kW is clearly not feasible. Even reducing the system size to 20 kW would still risk instability and poor power quality in the system. The spiky load pattern which involves instantaneous switching of large loads in relation to the system load exacerbates the problem. From the above mentioned reasons the Consultant and the taskforce agreed for the project to be dedicated for the only Government School named Motufoua Secondary School with a total capacity of 46 kW. This will provide the school with 24/7 of solar PV power supply. The system is to be tied-in to the main grid. Tender was called and closed on 13th March 2009. Five tenders were received i) CBS-Fiji ii) Solargex / Solar World Singapore iii) Eco-Kinetics iv) Solar and Alternate Energy / Greenzone Singapore v) Arnold Jensen / MH Power Australia vi) Clay Engineering The taskforce evaluated the tender and unanimously agreed to award the contract to Eco-Kinetics. The taskforce required clarifications from Eco-Kinetics to reduce its tender price. Eco-Kinetics was able to reduce its tender price by approximately 20%. The taskforce also acknowledged the assistance and support of PIGGAREP in providing the financial assistance to meet the costs of the training component of the project. The training contract has been drafted by PIGGAREP and a few small issues remain to be sorted out with Eco-Kinetics. The Supply, Installation and Commissioning contract is under review by the Attorney General’s Office and anticipate for the two separate contracts to get signed before the end of May 2009. 40 kW Grid-Connected PV at Funafuti The project has been working very well since its commissioning in February 2008. One minor problem faced by the project, the frequent tripping of the inverters caused by excessive heat in the 20 feet container, where the inverters were installed. The problem has been rectified by installing a new air-conditioning unit. In the 14 months of the project has been in operation it was noted that significant savings were achieved as shown in Annex 1.

Page 16: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Vanuatu EU Energy Facility Biofuel Project Vanuatu has been fortunate in having three of its project funded under the EU Energy Facility Call for proposals in 2006. The projects are: (i) Provision of renewable energy to 2 villages in TORBA Province using locally produced coconut oil, (2) Provision of renewable energy to 3 villages in PENAMA Province using locally produced coconut and (3) Provision of renewable energy to 4 villages in MALAMPA Province using locally produced coconut oil. These three projects have been bundled into one big biofuel project. Awareness activities have been completed on all the project sites including the three provinces and by August 2008, the 9 plots of land which the projects are to be situated were all marked and surveyed. The technical designs for the generation and distribution was already completed by UNELCO including tender for the supply of generators and transmission lines. The tender is now awaiting evaluation sometimes very soon. During the quarter, Mr. Leo Moli, the Director of Energy was appointed as the Project Manager. Sarakata Hydropower Project The installation of the third phase of the Sarakata hydropower project was completed and commissioned on 8th January 2009.The capacity of the hydropower has now been increased from 600 kW to 1200 kW. The rehabilitation of the water canal and the painting of the power house is currently underway. The official handing over ceremony of the Sarakata hydropower will be on 25th May 2009. A team comprised of the Environment Unit, Forestry Department, Water Resource Department, Fisheries and Energy Unit will be conducting a hydro risk awareness and consultation meeting with the communities living close to the vicinity of the hydropower project. Also a technical, economic, environment and social evaluation study is scheduled for January 2010, a year after the commissioning of the project. Energy Ecosystems and Sustainable Livelihoods Initiative (EESLI) Under this project, there are three components:

− Wind Resource Monitoring − Solar PV Rehabilitation − Talise Hydropower Project

There has been some delays in implementing this project. However, USD13,100 has already been disbursed into the Vanuatu Government to start implementing some of the activities. The advertisement for the Project Coordinator has been made with the recruitment expected to be made in June. Scoping missions to 6 provinces to identify sites for installing the wind monitoring equipments will commence in June. There is already request for extra funds to carry out scoping missions to Santo and Malekula for the solar rehabilitation component. GHD team and two officers from the Ministry of Land and Energy will be travelling to Maewo from 16 – 22 May to carry out a feasibility study on the Talise hydropower project. The study is also to cover the potentials of other renewable energy projects there. The final report for this study is expected in August 2009. From this report, a realistic budget for constructing the hydropower plant can be determined and if the funds provided under the EESLI is inadequate, then the Government of Vanuatu can source for extra funding from other potential donors.

Page 17: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Regional / PMO Completed conducting the Project Activity Summary (PAS) / Project Proposal Writing Workshop at Auckland, NZ on 19 – 23 January. Following the workshop, more than 20 PAS were drafted to be further reviewed and finalised for the consideration of the Project Steering Committee. As a result of the workshop and through the participation of the REEEP, three national project proposals (Solomon Is, Tonga and Tuvalu) worth 300,000 Euros were developed and submitted to the Renewable Energy and Energy Efficiency Partnership’s 7th Programme Cycle. A regional energy proposal worth 9 million Euros was jointly developed with SOPAC and the CROP Energy Working Group and submitted for the consideration of the European Commission. A planned 5th Project Steering Committee teleconference did not take place due to technical problems in the phone hook up. This meeting was then conducted virtually through emails. A short summary of the 5th PSC virtual meeting is attached s Annex 2. The project manager was heavily involved in the preparations for the Regional Energy Meeting / Pacific Energy Ministers’ Meeting (REM / PEMM) to be held at Tonga in April. The Climate Change Negotiations and the Opportunities for Renewable Energy, Energy Efficiency and Adaptation in the Pacific Island Countries. This was not only in terms of being in a core committee that review and vet meeting papers but also in terms of preparing two papers for the PEMM. One paper was on Renewable Energy and the other on The Climate Change Negotiations and the Opportunities for Renewable Energy, Energy Efficiency and Adaptation in the Pacific Island Countries. 8. Specific Outputs/Results Achieved (As per quarter work-plan): The Specific Outputs / Results achieved during the quarter, as per the overall PIGGAREP Immediate Objectives / Outcomes and Indicators are covered in Table 1 below. Table 1 also shows the achievement of the project to date:

Page 18: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

TABLE 1: SUMMARY REPORT ON THE IMPLEMENTATION OF THE 2009 WORK PLAN 1 QTR 09 Activities 2-4 QTR 09 Activities 2008 Activities

Work Plan Activities 1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

IMMEDIATE OBJECTIVES/OUTCOMES 1: Improved knowledge about RE resources potential and increase the number of successful commercial RE applications on the ground CI 08-1: Topographic and geotechnical survey of the Rarotonga Kiikii wind power site

Completed the topographic survey at a cost of about USD 28,000. Given the outcome of the topographic survey, it was recommended and agreed to by all the parties not to proceed to the geotechnical survey.

CI 09-1: Mangaia Power System Upgrade

A PAS is yet to be developed. A 3 QTR 09 activity with a budget of USD 10,000

CI 09-2: Wind Power Feasibility Study

A PAS for USD 70,000 was drafted to install wind monitoring systems at a ‘hot spot’ site on each of the three islands, Mitiaro, Mauke and Atiu. PAS will be finalised and submitted for PSC endorsement on 2 QTR 09.

A 4 QTR 09 activity with a budget of USD 50,000 but has been advanced to 2 QTR 09

FJ 09-1: Technical, economic & environmental evaluation of solar home systems project

5,000 Installations of 142 solar home systems in 4 Settlements and 8 villages in Vanua Levu have commenced. Each system comprises of 40 W of fluorescent lights and a power point for a small radio; 100 Wp of PV; 100 Ah, 12 V deep cycle battery with 8 A charge controller.

A PAS for USD 75,000 was endorsed via PSC 5 during the quarter. Letter from SPREP to Dept of Energy confirming financial support was sent 25/3/09. Activity include a review consultancy and study tour.

The big difference in the budget approved in the 2009 workplan and that in the PAS is noted.

FJ 09-New 1: Hydro Resources Assessment at Nacomoto Village, Kadavu and Sese Village, Cakaudrove

Survey of eight hydro sites (Waivaka; Wainawaqa, Nauluvatu, Nacula, Vugalei, Nabalasere, Namalata, Namako.

Installation of monitoring station and

A PAS for USD 20,000 was endorsed via PSC 5 during the quarter. Letter from SPREP to Dept of Energy confirming financial support was sent 25/3/09. The equipments have been ordered from

This activity was not on the 2009 work plan but has been introduced as a priority activity. Fiji DoE to provide an

Page 19: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities 1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

monitoring of hydro resources for 3 years Detail designing of 2 micro hydro Projects (Buca & Naikorokoro)

NIWA in NZ. update on the baseline / co-financing activities.

FJ 09-New 2: Biofuel Standards

The work involves (i) Quality Standards for liquid biofuels: ethanol, bio-diesel and coconut oil and (ii) Testing of vehicles with the biofuels blends that will form a part of the National Mandate. The draft standards for ethanol and bio-diesel were drawn up on the basis of quality standards for these two fuels that have been declared in Brazil, India, Europe and USA. Vehicle data from the Land Transport Authority has been analyzed and the number of vehicles on Fiji’s roads sorted out according to their year of manufacture.

Incremental activity includes the study tour to Vanuatu’s biofuel development (see REG 09-2: Technical visits to RE developments in Vanuatu).

KI 09-1: National Training for Trainers in PV maintenance & Trouble Shooting

A PAS is yet to be developed. A USD 45,000 activity for the 4 QTR 09.

NA 08-1: Nauru Wind power feasibility study

More than 20 AusAID-funded wind and solar for wireless internet and mobile phones were installed in 2008.

Contract was awarded second half of 2008. Monitoring equipments have been purchased and are expected in Nauru on 2 QTR 09. Installation is expected to begin late 2 QTR 09.

NA 09-1: PV training A solar grid-connected system with capacity of 40 kWp was installed at Nauru College in October 2008.

A PAS is yet to be developed. A USD5,000 activity for 3 QTR 09.

Page 20: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities 1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

60 stand-alone solar home systems each with 130 Wp panels was installed in 2008 through funding from Taiwan.

NI 09-1: RE training in solar water heaters and other relevant RE technologies

Completed the installation of 240 solar water systems as part of the REP-5 programme.

A PAS is yet to be developed. A USD10,000 activity with USD 5,000 each for 2 QTR and 4 QTR respectively.

NI 09-2: Network and System Modelling for the Grid Stability

Contract for the supply and installation of a 52 kW grid- connected PV system under REP-5 was awarded. Installation is planned for 3 QTR 09.

A PAS was developed and endorsed by the PSC in 2008. The tender was issued and the offers were all above USD 100,000. A new PAS merging NI 09-2 & NI 09-3 was drafted and reviewed. Final version is yet to be submitted to be circulated for PSC endorsement.

A USD 50,000 activity for 2 QTR 09. Now merged with NI 09-3.

PNG 09-1: Feasibility Study for the rehabilitation of Sohun hydro, Telefomin hydro and Yagusa Hydro (PNGSEL)

Expected Provincial Govt support and funding are not forthcoming.

A PAS is yet to be developed. A USD 50,000 activity for 3 QTR 09. PNGSDP has given the approval to PNGSEL to study and construct the 2 MW Togarao mini-hydro Project in the Autonomous Region of Bougainville. A new PAS will be prepared replace this activity.

PNG 09-2: Biofuel research/study into coconut oil as a substitute fuel for diesel engines (ATCDI/UniTech)

USD 54,009 of co-financing has been received. The literature survey is in progress. Two 2-kW Diesel Engines have been purchased for comparative performance testing. An order has been placed for the purchase of the exhaust

A PAS was drafted and commented on. Final version to be circulated for PSC endorsement has yet to be received.

A USD 50,000 activity for 3 QTR 09.

Page 21: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities 1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

gas analyzer. A site for the experimental set-up has been identified within the University.

SA 09-1: Hydro data collection programme

Final consultations were carried with two of the villages identified as monitoring sites. These were followed by site surveys to identify suitable locations to install the water level gauges The shipment of water level monitoring equipments have been finalised and paid for by ADB and they are expected to arrive in the country in 2 QTR 09.

EPC and MNRE entered into a MoU regarding cooperation on hydro-related data collection, analysis and management. EPC is recruiting a Technical Supervisor to be based at MNRE, paid by PIGGAREP, to collect, analyse and manage hydro data

Project was endorsed by the PSC in 2008 and USD 81,000 was committed in 2008 for this.

SA 09-2: Wind resources assessments

The Upolu Wind Resource Assessment report has been completed and a site has been identified as having potential for a commercial wind farm. However more data collection must be carried out in order to confirm the results of the assessment. EPC has finalised arrangements for a wind engineer to assist in the installation of the monitoring equipments.

The monitoring equipments were ordered and most have been received with installation planned for 2 QTR 09.

Project was endorsed by the PSC in 2008 and USD 33,000 was committed in 2008 for this.

SI 09-1: Workshop /Training for users (schools) of the installed Solar PV systems

3,000 Power needs assessments were conducted at 4 secondary schools. Started with the installation of a 1.515 kW solar PV systems at Buruku Adventist Community High School. Conducted the power needs assessment of Rokera Provincial Secondary School.

A PAS for USD 20,000 was endorsed via PSC 5 during the quarter. Letter from SPREP to Dept of Energy confirming financial support was sent 25/3/09. The request for proposals and the ToR is expected to be finalised and issued during 2 QTR 09.

SI 09-2 : Re-do feasibility Solomon Is govt co-financing of USD A PAS for USD 20,000 was endorsed via A USD 21,000 activity with

Page 22: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities 1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

study for HURO and RUALAE Hydropower schemes

55,000. PSC 5 during the quarter. The request for proposals and the ToR is expected to be finalised and issued during 2 QTR 09.

USD 7,000 for each quarter 2 – 4 QTR 09.

TO 09-1: Review and Evaluation of the Niuafo’ou SEIS

A PAS is yet to be developed.

TO 08-1: Feasibility Study of the rehabilitation of the Mango and Mo’unga’one PV projects

Findings from the study were used as inputs into the supply tender documents.

The feasibility study report was finalised and distributed during 1 QTR 09. 4 locals participated in the study for capacity building and exposure / training purposes.

With a budget of USD 18,000

TO 09-2: Technical evaluation of the solar installations in Mango & Mo’unga’one

3,000 Tender for the supply contract was awarded. Installation is expected for the second week of May or as soon as the last lot of equipment arrives in the Kingdom.

A PAS was drafted and commented upon but yet to be finalised and circulated for PSC endorsement.

TO 09-3: Awareness Training for solar water pumping and Solar Street lighting

The villages of Lakepa, Nakolo, Ha’alalo, Fu’amotu in Tongatapu (capacity of around 500kWp) and also Leimatu’a, Holonga and Pangaimotu in the Vava’u Group and Pangai, Hihifo and Ha’ato’u in the Ha’apai have been installed with solar water pumps. Fahefa, Niutoua, Holopeka and Faleloa are in the queue. The Chinese Government through the Nuku’alofa Township Reconstruction Development project has endorsed solar street lighting to be installed Around the Nuku’alofa township.

A PAS has been drafted, reviewed and finalised and will be circulated for PSC endorsement during 2 QTR 09.

A USD 11,000 activity for the 2 QTR 09.

TV 09-1: Support to TEC’s Completed the installation of a e8- Funafuti project costed

Page 23: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities 1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

outer island grid-connected renewable energy project

funded 40 kW grid-connected PV system at Funafuti in 2008. Tender for the supply, installation and training with respect to the 46 kW system at Motufoua Secondary School was issued. Separate contract with PIGGAREP on the training. Evaluation and offer of contracts are planned for 2 QTR 09.

A PAS for USD 55,000 was endorsed via PSC 5. Activities include monitoring and training support to both the Funafuti and Vaitupu grid-connected PV systems, study tour and participation at the Niue grid-connected PV system workshop.

approximately USD 412,000.

TV 09-2: Studies of wind potential in the outer-islands

Completed the wind monitoring assessment at Funafuti. The tower and anemometer supplied under PIEPSAP will be shifted and used in the outer island – see TV 09-4.

A PAS was drafted and reviewed and will be finalised for circulation among the PSC in 2 QTR 09.

A USD 10,000 activity for 2 QTR 09.

VA 09-1: Technical training on the O&M of the Sarakata hydropower project

3,000 The additional 600 kW of hydropower capacity was commissioned in January. The official handing over ceremony of the Sarakata hydropower will be on 25th May 2009.

Training was completed in January. Trainee has yet to submit his training report. 2 PAS for an awareness / consultation training on the risks to the Sarakata hydropower project and a social, economic and technical evaluation of the project in Jan 2010 have been drafted.

VA 09-2: Review of the 2002 Talise Mini Hydro Feasibility Study

50,000 The baseline are in 3 components: − Wind Resource Monitoring − Solar PV Rehabilitation − Talise Hydropower Project The recruitment process for a local expert as Project Coordinator has commenced with the appointment expected to be made in June.

The consultancy contract for the Talise feasibility study was awarded to GHD of Australia for a maximum of USD 88,387 (may vary according to actual costs). 2 local experts will participate and receive exposure training in the study. The Inception Report will be finalised

The big difference in the budget approved in the 2009 workplan and the successful tenderer’s offer is noted.

Page 24: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities 1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

Scoping missions to 6 provinces to identify sites for installing the wind monitoring equipments will commence in June.

next in May and the field mission will take place in May too.

VA 09-3: Feasibility Study of the Lowanau River (Tanna) hydro resource potential

A PAS is yet to be developed. A USD 20,000 activity with USD 10,000 each for 3 & 4 QTR 09.

VA 09-4:Community Training on Biofuel at NE Malekula, Saratamata and Vanualava

A PAS is yet to be developed. A USD 10,000 activity with USD 5,000 each for 3 & 4 QTR 09.

REG 08-1: Conduct training workshop on RET Application in Small Is States

Partly funded by Taiwan Workshop completed and was attended by 27 people. Final report produced an distributed.

RE 09- 1: REP-5 / PIGGAREP Workshop on grid-connected PV at Niue (Linked to NI 09-02 & TV 09-2)

A follow-up to REG 08-1 & 2. Completed PPA-e8 RE workshop in Nov 2008. Selected outstanding participants from workshop to come to Niue. Contract for the supply and installation of a 52 kW grid- connected PV system under REP-5 was awarded. Installation is planned for 3 QTR 09.

Workshop programme has been drafted with REP-5. Participants have been selected.

A USD 35,000 activity for 2 QTR 09. Activity has been moved to 3 QTR due to late arrival of the PV equipment in Niue.

Page 25: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Achievements to Date in relation to the Outcome Indicators

Output and Impact Indicators Achievements to Date

i) 10 completed monitoring studies by 2012 ii) 4 RET application projects developed by 2015 iii) 10 completed feasibility studies (FS) iv) 7 FS leads to an approved, financed and implemented RET application

projects by 2012 v) 5 completed demo projects that received TA from PIGGAREP by 2012 vi) 221 kW installed and integrated into existing and new power systems by

2012 vii) 2 ESCOs / IPPs engaged in the RET demo projects by 2012 viii) 16,000 additional people in PICs served with RE through the demo

projects by 2012 ix) 4 PURE projects designed and implemented by 2012 x) 10 additional social services (schools, health centres,

telecommunication, etc) in PICs using RE by 2012 xi) 10 completed training courses / workshops by 2012 xii) 200 trained people on RE assessments and RE system design,

installation and O&M by 2012 xiii) 2 trained people establish own RE business by 2012 xiv) 5 RET application projects designed, implemented, operated and

managed by local RE experts by 2012 xv) 2 draft quality and technical standards on grid-connected solar PV

system components and installations xvi) 1 standard approved by 2012

i) 8 hydro surveys in Fiji, wind and hydro surveys finalised to begin in Samoa, wind surveys finalised to begin in the Cook Is and biofuel surveys finalised to begin in PNG and the SI.

ii) 2 micro hydro projects currently under design (Buca and Naikorokoro - Fiji) iii) 2 (Nauru wind & Vanuatu Talise) feasibility studies finalised to begin in 2 QTR iv) v) 3 Demo projects identified (Tonga, Tuvalu and Vanuatu) vi) 22 kW of installed solar home systems (14.2 Fiji and 7.8 Nauru), 40 kW of grid

connected PV installed at Funafuti, Tuvalu and 1.7 kW of PV and 6 kW of biodiesel installed in the SI. 6 kW of solar home systems for Tonga, 1.5 kW in the SI, 52 kW of grid-connected PV are still being finalised for Niue and Tuvalu (46 kW) for installation later in the year.

vii) viii) xxx people at Santo served with RE from the new additional Sarakata capacity ix) 3 Demo projects identified (Tonga, Tuvalu and Vanuatu) x) 1 health centre (Aola in SI) and 1 school (Nauru College) installed with a grid

connected RE system. 1 school (Buruku Adventist School in the SI installed with solar home systems. 4 schools are to receive biogas digesters in Fiji. Schools in Kiribati will be installed with solar water pumps with Italian funding.

xi) RET Application workshop for SIS completed, training of trainers on biogas completed in Fiji. National training workshops in Kiribati, Tonga, Tuvalu (Motufoua) and the SI as well as the regional grid-connected workshop at Niue are in the 2009 work plan and are at various stages of being finalised to be carried out.

xii) 27 participants in the RET Application workshop for SIS. 20 participants in the Fiji biogas workshop.

xiii) xiv) xv) xvi)

Page 26: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities 1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

IMMEDIATE OBJECTIVES/OUTCOMES 2: Expansion of the market for RET applications FJ 09-2: Establishment of the Biogas market

Ten biogas digesters will be constructed by locals under this Biogas Programme. Training of 20 local trainers in biogas construction completed. A biogas certification training programme has been put in place as part of the program. Four sites have been assessed and selected, the builders have been identified and four teams that ranges from two to five builders have been selected from the trained trainers; materials purchased and transported to the four sites, and the actual construction work has commenced at Queen Victoria School, Ratu Kadavulevu School, Wainiyabiya Settlement and Namatakula village. The works are expected to be completed by June.

A PAS has been drafted but not yet finalised.

A 3 QTR 09 activity with a budget of USD 10,000 Queen Victoria School (QVS) QVS is a boarding school with a roll of about 700 students. It has been using LPG for cooking which costs $2,000 per month. The school has a cattle farm as source of milk for the school’s needs and a piggery farm as food source. There are some 200 pigs kept in a well maintained concrete shed. A 15m3 digester is currently being constructed at the school.

SI 09-3 : Biofuel Development and Expansion

SI government co-financing of USD 100,000. Cabinet in March approved the setting up of a Task force to spearhead the bio-fuel development program.

The PAS was endorsed by the PSC via PSC 5 for USD 39,000. Activity include consultancy study and study tours. The request for proposals and the ToR

A USD 20,000 activity with 2 QTR (7,500), 3 QTR (7,500k) and 4 QTR (5,000)

Page 27: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities 1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

Task Force will have its inception meeting in QTR 09 and will submit is mandate and budget to Cabinet.

is expected to be finalised and issued during 2 QTR 09.

Achievements to Date in relation to the Outcome Indicators

Output and Impact Indicators Achievements to Date

i) 5 technically feasible RE projects in the PICs identified and studied by 2012

ii) 2 financially and commercially viable RE projects in the PICs designed and prepared for donors, financiers and investors by 2012

iii) 8 funded and implemented RE projects by 2012 iv) USD 13 million of investments in new RE installations by 2012 v) 2 completed training courses/workshops on the manufacturing and

repair of RET system components by 2012 vi) 50 trained people on manufacturing and repair of RET system

components by 2012 vii) 30 trained people engaged in the manufacture and repair of RET

systems components by 2012 viii) 2 RET application projects in the PICs employing locally manufactured

components by 2012 ix) 1 commercially viable equipment manufacturers/fabricators and

suppliers of RET system components in the PICs by 2012 x) USD 50,000 of sales of locally manufactured/fabricated RE system

components in the PICs by 2012 xi) 3 power utilities in the PICs that have RE Advisers/Units by 2012 xii) 1 power utility with corporate-approved business plans that include RE

utilization and marketing activities by 2012 xiii) 3% increase in the financing for incorporation of RE in power

generation in the PICs by 2012

i) 1 study has been completed (Motofoua grid-connected PV project at Vaitupu, Tuvalu) and 1 has been finalised to being 2 QTR 09 (Talise hydropower project in Vanuatu is being studied).

ii) iii) 3 proposals (SI, Tonga and Tuvalu) submitted to the REEEP 7th Programme

Cycle and 1 proposal (Action Fiche) to the EU-funded EDF 10. iv) The Fiji Electricity Authority (FEA) and the Chinese Development Bank (CDB)

signed a F$132.45 million (US$70 million) loan agreement to commence the construction of the Nadarivatu Hydropower project.

v) 1 completed workshop in Fiji on the construction and maintenance of biogas digesters

vi) 20 people trained in Fiji on the construction and maintenance of biogas digesters. vii) 20 trained biogas technicians in Fiji are now engaged in the construction of 4

digesters in 4 schools viii) ix) x) xi) xii) PPA has commenced the recruitment process for a RE Adviser to work for the

member power utilities. The Electric Power Corporation of Samoa recruited a Renewable Energy Officer in 2008. Completed study for the establishment of a RE & EE Unit at the Tuvalu Electricity Corporation. Tuvalu’s proposal to the REEEP 7th Programme Cycle was to fund a RE Adviser.

Page 28: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Output and Impact Indicators Achievements to Date

xiv) 1 commercially viable RESCOs in the PICs by 2012 xv) 5 completed training courses/workshops on basic O&M of RET system

installations and components by 2012 xvi) 80 trained rural residents on basic O&M of RET system installations

and components by 2012 xvii) 6 trained rural residents that are actually operating and/or maintaining

RET system installations and components in rural areas in the PICs by 2012

xiii) xiv) xv) Workshops on basic O&M of RET system installations and components planned

for Kiribati, SI, Nauru, Niue, Tonga and Tuvalu. Workshops on risks / hazards awareness relating to the Sarakata Hydropower Project is planned for Vanuatu.

xvi) xvii)

Work Plan Activities

1 QTR 09 Budget (USD)

Status of baseline activities Status of incremental activities Comment

IMMEDIATE OBJECTIVES/OUTCOMES 3: Enhancement of institutional capacity to design and implement RE FJ 09-3: Technical Assistance (through consultancy) for strengthening the management of the Energy Information System

5,000

A PAS was drafted and reviewed. Awaiting final version to be circulated for PSC endorsement by 2 QTR 09.

KI 09-2: Review of KSEC, Restructure, On the Job Business Training, Strategic Planning, Project Preparation, Management, Monitoring and Evaluation

A PAS is yet to be developed. A USD 15,000 for 2 QTR 09.

Page 29: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities

1 QTR 09 Budget (USD)

Status of baseline activities Status of incremental activities Comment

KI 09-3: Migrating RESCO Manager to an open source platform.

UNDP has approved a project proposal on Maintaining Renewable Energy Systems in Kiribati through Technical Training for USD 35,000. Awaiting signing of Face form for processing payment.

A PAS was developed and endorsed by PSC in 2008. PMO awaiting clarifications on the ToRs, the operationalisation of the consultancy contracts and the complementarity with the co-financing activities. Linkages

A USD 60,000 activity for 2 (10,000), 3 (20,000) & 4 QTRs (30,000) 09.

NA 09-2: Energy Database

10,000 SOPAC assisted Nauru to put establish its Energy Data Base

A PAS was drafted requesting mostly the purchase of computers. Advise was provided to Nauru to redesign PAS in order for the PIGGAREP to provide database training and other related activities.

NA 09-3: Training needs assessment for RE

PPA has advertised the consultancy to conduct raining needs assessment in its member power utilities, including Nauru’s.

A PAS is yet to be developed. A USD 40,000 activity for 2 QTR 09.

TV 08-1: Study the best ways to establish a RE and EE Unit at the Tuvalu Electricity Corporation.

Tuvalu’s REEEP proposal in Outcome 7 is to operationalise the RE and EE Unit. t

Completed in Sept 2008 for approximately USD 46,000. Report finalised and endorsed by the TEC Board.

TO 09-4: Technical Assistance to the Tonga Energy Roadmap: 2010 – 2020

The Tonga govt has set a target of achieving 50% of grid-based electricity from RE within 3 years. The World Bank and Tonga are drafting an Interim Energy Sector Technical Report to be discussed in Sept 09 leading to drafting of the final Road Map to be completed by Feb 2010.

A PAS is yet to be developed. To include relevant TA to the EDF 10 project too. A USD 15,000 activity for 3 QTR 09.

Page 30: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Achievements to Date in relation to the Outcome Indicators

Output and Impact Indicators Achievements to Date

i) 2 PICs that have National Energy/Climate Change Plans and Energy Laws and Policies in place and enforced by 2011

ii) 2 PICs have set GHG emissions reduction and/or RE utilization targets by 2011

iii) 3 PICs that annually prepare their national energy balance based on regularly collected energy supply and consumption data by 2010

iv) 1 PIC with annual earmarked budget allocations for RET-related training in national energy plans starting 2009

v) 3 PICs with established national coordination system & mechanism on energy matters that include the private sector by 2010

vi) 3 proposed energy policies and laws in each PIC each year that were deliberated through the established national energy coordinating system and mechanisms starting 2010

vii) average of 3 energy policies and laws in each PIC each year that were approved and enforced through the established national energy coordinating system and mechanisms by 2012

viii) 8 competitive procurement processes each year for goods & services in the context of national energy activities where relevant national focal points are represented starting 2008

ix) 1 RET projects/programs with parallel funding and/or cost sharing by 2012;

x) 2 completed training courses/workshops on energy planning and energy project coordination and management (EP&EPC/M) by 2012

xi) 6 trained people on EP&EPC/M by 2012 xii) 6 trained people that work on EP&EPC/M either in the government or in

the private sector in the PICs by 2012 xiii) 6 successfully implemented energy projects, in general, and RET system

application projects, in particular that were planned, coordinated, or managed by trained EP & EPC/M people in the PICs by 2012

xiv) 3 PICs with well-staffed Energy Offices with clear mandates by 2010 xv) 3 PICs with EOs equipped with updated databases for planning and

policy making by 2010 xvi) 3 PICs with EOs coordinating the implementation of their respective

i) Kiribati has finalised its National Energy Policy and submitted for Cabinet endorsement. Niue Cabinet has approved the drafting of a Climate Change Policy. SPREP has been approached to help, PIGGAREP is willing to support and is awaiting a ToR from Niue in order for a consultant to carry out this work.

ii) Tonga in 2008 adopted a RE target of 50% within 3 years. PIGGAREP RE paper to the PEMM will highlight importance of having voluntary and achievable targets.

iii) Nauru is assisted by SOPAC to establish its Energy Database. Energy Supply and Consumption Data collected for the GHG inventory chapter of the PICs’ UNFCCC National Communications.

iv) v) SI Cabinet approved the formation of a Biofuel Task Force. A Cabinet sub-

committee on RE established in Tonga in March 2008, following the revival of the National Energy Committee in 2008.

vi) Regulations for the Tonga RE Act are planned to be finalised through the National Energy Committee.

vii) Tonga’s National Energy Committee was the final clearing house for Tonga’s RE Act before submission to Parliament. The Act was approved by Parliament in 2008.

viii) ix) TERI and SOPAC are planning a regional energy planning workshop for 3

QTR 09. x) xi) xii) xiii) xiv) xv) xvi) Tonga Energy Division is coordinating the implementation of the kingdom’s

national energy / climate change mitigation plan xvii) xviii) 3 Energy Planner and 3 Energy Officer positions established and filled at the

Page 31: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Output and Impact Indicators Achievements to Date

country’s national energy/climate change mitigation plan by 2010 xvii) Average of 3 energy policies formulated each year by the EO in each

PIC starting 2010 xviii) 8 additional EO positions funded by national budgets by 2012 xix) 2 national energy databases reviewed and revised by 2010 xx) 3 PICs maintain and use their national energy database every year

starting 2009 xxi) 2 completed workshops on energy data gathering system and operation

and maintenance of the energy database xxii) 2 implemented energy policies and projects in the PICs that were based

on the information in the energy database by 2012 xxv) 1 national energy balances prepared by 2012 xxvi) 3 national energy balances updated by 2012 xxvii) 1 completed regional synthesis reports of energy sector GHG emission

inventory by 2012 xxviii) 33% reduction in regional energy sector GHG emissions (compared to

that in 2005) in 2015.

Tonga Energy Division in early 2009. xix) Samoa’s energy database reviewed and revised by SOPAC in 2008. xx) Fiji is recruiting a data entry clerk to support its data base work. xxi) xxii) xxiii) xxiv) xxv) xxvi) xxvii) Energy Supply and Consumption Data collected for the GHG inventory

chapter of the PICs’ UNFCCC National Communications. xxviii)

Page 32: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities 1 QTR 09 Budget (USD)

Status of baseline activities Status of incremental activities Comment

IMMEDIATE OBJECTIVES/OUTCOMES 4: Improvement of the availability of funding for existing and new RE projects NI 09-3: RE and Existing Tariff Study

Contract for the supply and installation of a 52 kW grid- connected PV system under REP-5 was awarded. Installation is planned for 3 QTR 09.

A USD 40,000 activity for 4 QTR 09. A new PAS merging NI 09-2 & NI 09-3 was drafted and reviewed. Final version is yet to be submitted to be circulated for PSC endorsement.

Now merged with NI 09-2.

Achievements to Date in relation to the Outcome Indicators

Output and Impact Indicators Achievements to Date

i) Completed study report on the real cost of electricity and other RE resources by 2010

ii) 1 PIC utilizes the energy pricing tool and the knowledge about the real cost of energy in their energy policy and decision making processes by 2012

iii) 11 government-supported RE-based rural productivity projects in 2012 iv) 5 RET application projects specifically designed to improve productivity

and income in rural areas by 2012 v) 5 private sector entities investing in PURE and/or SURE projects in rural

areas of the PICs by 2012 vi) 5 financial/banking institutions that participated in the regional

workshop on RE investments vii) 50% of banks and financial institutions in the region that have

committed financial support to RET application projects by 2012 viii) 1 training course for the banking/financial institutions in the PICs

designed and conducted each year starting 2010 ix) 20% of targeted financial institutions in the PICs that committed to

support RET application projects by 2012 x) 5 applicable RE financing schemes identified and designed by mid-2010 xi) 2 identified and/or designed applicable innovative financing schemes

that are acceptable to banks and financial institutions in the PICs by end 2010

i) 2 base tariff studies were completed by PIEPSAP in 2007 for the SI Electricity Authority and the Tuvalu Electricity Corporation.

ii) Tuvalu Electricity Corporation approved setting up a RE and EE Unit based on the base tariff study recommendations

iii) iv) 5 RET application projects specifically designed to improve productivity and

income in rural areas by 2012 v) vi) vii) viii) ix) x) Samoa is setting up a Clean Energy Fund as part of its ADB Power Expansion

Project xi) xii) xiii) Samoa is setting up a Clean Energy Fund as part of its ADB Power Expansion

Project xiv) xv) xvi) xvii) Samoa is setting up a Clean Energy Fund as part of its ADB Power Expansion

Page 33: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Output and Impact Indicators Achievements to Date

xii) 2 banks and financial institutions in the PICs that have adopted innovative financing schemes developed under the PIGGAREP by 2012

xiii) 1 existing operational funds in the PICs reviewed by end 2009 xiv) 2 committed seed fund contributors to a regional/national RE Fund

(REF) by end 2012 xv) USD .5 million of confirmed seed funds for the REF by mid-2011 xvi) 2 completed and PICs-approved design of REF including the associated

IRRs by end 2011 xvii) 1 operational regional/national REF supporting the implementation of

RET application in the PICs by 2012

Project

Work Plan Activities

1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

IMMEDIATE OBJECTIVES/OUTCOMES 5: Strengthened legal and regulatory structures in the energy and environmental sectors FJ 09-4: Technical Support to the development of energy legislation

Tenders were invited for this consultancy. Five tenders were received and further clarifications are being sought from the bidders. Once this information is received, the Department will complete its evaluation and prepare a submission to the Tender Board for approval. The Department anticipates that the project will be completed by December 2009.

A PAS is yet to be developed. An activity with USD 18,000 support from the PIGGAREP (2 QTR- 5,000, 3 QTR-8,000 & 4 QTR – 5,000)

KI 09-4: Consultations on the National Energy Policy and drafting of an Action Plan

7,000 The KNEP has been drafted with the assistance of SOPAC. It has been submitted to Cabinet for endorsement.

A PAS was drafted and reviewed during the PAS workshop in January. PAS is yet to be finalised.

Activity is to cover travel of 3 officers to Christmas Is to conduct consultation meetings. Kiribati advised to prepare a draft Action Plan in Tarawa to base the consultation on.

Page 34: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities

1 QTR 09

Budget (USD)

Status of baseline activities Status of incremental activities Comment

TV 09-3: Support implementation of Policy and Strategic Action plan

A PAS is yet to be developed. A USD 12,500 activity with USD 6,250 each for 3 & 4 QTR 09 respectively.

Achievements to Date in relation to the Outcome Indicators

Output and Impact Indicators Achievements to Date

i) 11 PICs with endorsed national energy / RE policy ii) 5 strategic energy action plans have RE activities that are costed and

financed iii) 5 RE policy studies conducted each year in each PIC starting 2009 iv) 1 formulated RE policies (including PURE/SURE policies and fiscal

incentives) proposed to the government in each PIC annually starting 2009

v) an average of 1 proposed RE policies (including PURE/SURE policies and fiscal incentives) that are approved and adopted annually in each PIC starting 2010

vi) average of 1 sets of policy IRRs (inclusive of the legislation) that are approved in each PIC annually starting 2010

vii) 2 completed comprehensive energy pricing studies by 2012 viii) 2 PICs utilizing the pricing studies in their national energy planning and

policy making by 2012 ix) 2 RE policies (including PURE/SURE) that are based on the

comprehensive energy pricing studies by 2012.

i) Kiribati’s national energy policy submitted for Cabinet endorsement ii) The PAS for the Kiribati energy action plan has been drafted and reviewed iii) iv) v) vi) vii) The PAS for Niue’s electricity pricing study drafted and reviewed viii) ix)

Page 35: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities

1 QTR 09 Budget (USD)

Status of baseline activities Status of incremental activities Comment

IMMEDIATE OBJECTIVES/OUTCOMES 6: Increased awareness and knowledge about RE among key stakeholders CI 09-3: RE / Green Award Programme for the tourism sector

A PAS is yet to be developed. A 4 QTR 09 activity for USD 5,000

FJ 09-5: Technical visits to RESCO business operations in Kiribati (Kiribati Solar Energy Company).

See FJ 09-1 above under Outcome 1 This activity is included in the PSC-endorsed PAS for FJ 09-1: Technical, economic & environmental evaluation of solar home systems project (see Outcome 1). Preliminary contacts and planning have been made with the Solar Energy Company Ltd of Kiribati.

A USD 15,000 and USD 10,000 for 2 QTR 09 and 3 QTR 09 respectively.

KI 09-5: Public awareness campaigns

3,000 A PAS is yet to be developed. A USD 12,000 activity for the year with USD 3,000 quarterly. The big difference in the budget approved in the 2009 workplan and that in the PAS is noted.

NI – Awareness programs on all sectors radio /TV / local newspaper / ¼ly / weekly bulletins

A PAS is yet to be developed. A USD 15,000 with USD 5,000 each for 2, 3 & 4 QTR 09 respectively.

SA 08-1: National energy awareness campaign day

Completed at a cost of USD 9,000 and with the participation of about 400 students. Activity has been evaluated, documented and posted to the PIGGAREP web page.

SA 09-3: National energy awareness campaign day

A PAS was drafted and reviewed but not yet finalised to be circulated for PSC endorsement.

A USD 10,000 activity for 2 QTR 09.

SI 09-4: RE Training for students at

2,000 Completed the installation of Aola Rural Health Centre Hybrid system (in

A PAS is yet to be developed.

A USD 8,000 activity with USD 2,000 quarterly.

Page 36: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities

1 QTR 09 Budget (USD)

Status of baseline activities Status of incremental activities Comment

Willies and SICHE on Electrical Trade

Guadalcanal Province). This hybrid system comprises of 1.7 kW solar PV system and a 6 kW biodiesel generator set. 12 RE technicians recruited by the Energy Division.

A PAS for USD 36,000 (20k for training and 16k for the RE Information Centre – SI 09-5) was endorsed via PSC 5 during the quarter. Letter from SPREP to Dept of Energy confirming financial support was sent 25/3/09.

The big difference in the budget approved in the 2009 workplan and that in the PAS is noted.

SI 09-5: Setup of RE Information and Exchange Centre

Construction of the Renewable Energy Information Centre is well underway. Most of the main structural works are near completion and the final touches would be followed. This will go along with the installation of the RE equipment and the laboratory furnishing.

A PAS for USD 36,000 (16k for the RE Information Centre and 20k for training and – SI 09-4) was endorsed via PSC 5 during the quarter. Letter from SPREP to Dept of Energy confirming financial support was sent 25/3/09. The request for proposals and the ToR is expected to be finalised and issued during 2 QTR 09.

TV 09-4: Analysis of wind data and Preparation of a wind fuel savings project for Funafuti Island

Completed 1 year of wind monitoring assessment at Funafuti under the PIEPSAP.

A PAS was drafted and reviewed and will be finalised for circulation among the PSC in 2 QTR 09.

A USD 50,000 activity for the 3 QTR 09. Equipments will be shifted and installed in an outer island – see TV 09-2.

TV 09-5: Public demonstration of Biodiesel, todi ethanol, gasification production Dissemination of biogas technology introduced by PIEPSAP Education tool for children in Tuvaluan, USP & high school classes

The construction of the Amatuku Training Centre on Renewable Energy with a new piggery and biogas digester was completed in late 2007. Completed awareness workshop attended by more than 80 people. Production and Airing of daily radio series covering RE from Environment Day, June 5th – October 6th 2007. Printed and distributed 200 copies of the Our Planet Under Water comic in the Tuvalu language.

A PAS is yet to be developed. A USD 10,000 activity with USD 5,000 each for the 3 & 4 QTR 09 respectively. ALOFA Tuvalu activities.

Page 37: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities

1 QTR 09 Budget (USD)

Status of baseline activities Status of incremental activities Comment

Picture exhibition attended by more than 500 Tuvaluans. DVD distribution of events relating to environment and renewable energy in Tuvalu.

VA 09-5: Technical visits / study tour to community based pico/micro hydros in Solomon Is, Fiji and / or PNG

A PAS is yet to be developed. A USD 25,000 activity with USD 10,000 for 2 QTR 09 and USD 15,000 for 3 QTR 09.

REG 08-2: Regional RE training workshop

e8-PPA workshop completed in Nov 2008 and attended by 24 participants from the power utilities.

PIGGAREP funded the participation of a participant each from the Kiribati and Tonga solar utilities.

REG 09-2:Technical visits to RE developments in Vanuatu

Linked to the PSC-endorsed PAS by Fiji (FJ 09-1), Solomon Is (SI 09-3) and Tuvalu (TV 09-1). PAS for other interested PICs has not been developed and / or yet to be endorsed by the PSC. Date has been fixed with the Vanuatu Energy Office for July 27 – 31. Interested PICs have been requested to send specific needs to assist in the planning and coordination of the event.

A USD 40,000 activity for 3 QTR 09.

REG 09-3: Study tour of the Ha’apai Solar Electricity Inc.

Linked to the PSC-endorsed PAS by Fiji (FJ 09-1), Solomon Is (SI 09-3) and Tuvalu (TV 09-1). PAS for other interested PICs has not been developed and / or yet to be endorsed by the PSC.

A USD 40,000 activity for 4 QTR 09.

Page 38: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Achievements to Date in relation to the Outcome Indicators

Output and Impact Indicators Achievements to Date

i) Average of 1 RE/RET awareness raising and promotion programs designed and carried out in each PIC each year starting 2009

ii) 10 power utilities in the region that are using RE in their power generation and/or operations by 2012

iii) 300 households in rural areas are using RE for their electricity and non-electricity needs by 2012

iv) 4 study tours conducted on RET applications and other non-conventional energy systems by 2012

v) 10 additional PIC nationals with a Certificate, Diploma, and/or university degree on the technical aspects of RE by 2012

vi) No of demonstration projects that achieved set technical and financial performance (e.g., MWh generation, CO2 emission reduction, payback period, IRR) targets by 2012

vii) 300 copies of the demonstration project report disseminated by 2012 viii) 20 project developers that utilize the report as reference for their RET

application projects by 2012 ix) 2 RET application projects that replicate the demo projects by 2012 x) 2 established and operational RE Information Units in the region by

2012 xi) an average of 30 requests for information by other organizations (local

and abroad) served by each RE Information Unit starting 2010 xii) 80% of clients of each RE Information Unit that are satisfied with the

services provided starting 2010 xiii) 10 public and private entities in the region that are using RE to meet

(fully or partly) their energy needs starting 2012 xiv correctly identified collective CO2 emission reductions realized each

year by the top 3 awardees starting 2010 xv) 300 visits to the PIGGAREP webpage each year starting 2009 xv) 80% of website users each year are satisfied with information contained

in website starting 2009 xvi) 12 SPREP monthly articles on energy / climate change distributed each

year starting 2009 xvii) 10 people and institutions that are familiar with the PIGGAREP each

i) 2 PICs (Kiribati & Samoa) have awareness activities in their 2009 work plan. ii) 7 power utilities (Fiji, Nauru, PNG, Samoa, SI, Tuvalu and Vanuatu) have RE

integrated into their grid. Niue will have grid connected RE power on 3 QTR 09.

iii) 142 households in Fiji are being installed with SHS. XXX households in Santo get electricity from the newly commissioned Sarakata hydropower expansion. Sixty households at Mango and Mo’unga’one at the Ha’apai Group of Tonga will be installed with SHS 2-3 QTR 09.

iv) 1 study tour by Fiji to Kiribati is planned. 1 study tour by Fiji, SI, PNG, SI, Samoa and Tuvalu to Vanuatu is planned for 3 QTR 2008. 1 Study tour to the Ha’apai Solar Electricity Inc. is planned for 4 QTR 09.

v) 12 trainees in the SI are to undergo electrical certificates training with Willies Electrical. 1 student from the Fiji Dept of Energy currently doing MSc on Energy Planning and Policy. 1 student from the Tonga Energy Division is currently doing PhD on renewable energy at the Uni. of NSW.

vi) vii) viii) ix) x) Construction of the SI RE Information Unit is currently underway and lab

equipments and RE equipments have been ordered xi) xi) xvii) 1 health centre (Aola in SI) and 1 school (Nauru College) installed with a grid

connected RE system. 1 school (Buruku Adventist School in the SI installed with solar home systems. 4 schools are to receive biogas digesters in Fiji. Schools in Kiribati will be installed with solar water pumps with Italian funding.

xiv) xv) Still not able to put in a counter on the PIGGAREP page! xvi) 2009 is SPREP’s Year of Climate Change with various promotional activities,

including some on renewable energy

Page 39: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Output and Impact Indicators Achievements to Date

year starting 2009 xviii) 80% of the stakeholders/target groups in the PICs fully understand the

PIGGAREP by 2011

xvii) Anyone seriously working on RE in the region will come across PIGGAREP is discussions with others in and outside of the region.

xviii) There is more and more appreciation of the PIGGAREP from its publicity work, tenders on joint activities with IUCN, REEEP publications and newsletters, etc.

Work Plan Activities

1 QTR 09 Budget (USD)

Status of baseline activities Status of incremental activities Comment

IMMEDIATE OBJECTIVES/OUTCOMES 7: Effective Management of the PIGGAREP INDICATOR: Project Activities are implemented within budget and on time, in close collaboration with other related and parallel activities in the PICs. RE 09-4: Regional Workshop on writing Project Activity Summary / Project Proposals

40,000 Completed and other than Nauru, 10 PICs attended. A workshop report has been produced.

Effective Project Management

Completed PSC 5 virtually. Report is yet to be produced.

Effective Project Management

Assisted in an EU audit of SPREP. Assisted with the audit of the PIGGAREP’s 2008 activities and accounts.

New funding for RE in the PICs

Completed a joint SOPAC-SPREP EDF 10 Identification Fiche (IF) for 9 million Euros. IF has been submitted via the Regional Authorising Officer (RAO) to Brussels.

New funding for RE in the PICs

Assisted Solomon Is, Tonga and Tuvalu will developing their proposals, each 100,000 Euros, for the REEEP’s 7th Programme Cycle.

Regional and International Cooperation and Partnerships

Participated in the first meeting of the Lead Authors for the IPCC Special Report on Renewable Energy.

Costs were paid for by WMO / IPCC.

Page 40: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Work Plan Activities

1 QTR 09 Budget (USD)

Status of baseline activities Status of incremental activities Comment

Regional and International Cooperation and Partnerships

Participated in the SOPAC-SPREP discussions on the Regional Institutional Framework.

EWG meeting and EDF 10 IF development coincided with the Suva RIF discussions.

Regional and International Cooperation and Partnerships

Participated in the REEEP-selected Steering Committee that shortlisted project concept for the REEEP’s 7th Project Funding Cycle.

Done virtually by phone and email.

Regional and International Cooperation and Partnerships

Participated in the CROP Energy Working Group preparatory meetings for the Regional Energy Meeting / Pacific Energy Ministers’ Meeting (PEMM). Drafted 2 papers relating to renewable energy for the PEMM.

Regional and International Cooperation and Partnerships

Coordinated the conduct of a Capacity Building Workshop on the Clean Development Mechanism on 2 QTR 09.

A 4 year EU-funded programme through UNEP.

Page 41: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

9. Challenges/Issues Encountered There is a marked improvement in the number of PAS being drafted and developed in relation to the 2009 work plan. Some national energy offices continue to show lack of interests in advancing their PIGGAREP activities but show keen interests in travel related activities. The number of PIGGAREP supported activities on the ground has advanced to the “take off” stage and where extra manpower support to the PMO is now justified. There are indications already from the first quarter’s performance that the work plan for 2009 is more realistic than 2008’s, however, the work plan must remain flexible to accommodate changes in direction and focus in the PICs. This flexibility must also take into account of the fact that a lot of achievements in relation to the project indicators are taking place but they are not listed as co-financing in relation to the activities in the 2009 work plan. For instance, a member of the Tonga Energy Office is currently doing his PhD on renewable energy and this directly relates to the indicator 10 additional PIC nationals with a Certificate, Diploma, and/or university degree on the technical aspects of RE by 2012 but the PhD study is not used by Tonga as a co-financing activity. It is to be noted from Table 1 that there are a many activities in relation to Immediate Objectives / Outcomes 1 (Technical), 3 (Institutional), 5 (Policy) and 6 (Awareness) while there are only 2 under Market and 1 under Financial. It is however to be noted to that even though there are only a few activities under Market and Finance, the level of achievements on both is satisfactory. There are some indicators will corresponding blank achievements. Some of these can only be achieved through regional interventions. Examples include activities relating to indicators such as:

• 2 completed training courses/workshops on the manufacturing and repair of RET system components by 2012

• 1 training course for the banking/financial institutions in the PICs designed and conducted each year starting 2010

• 2 completed training courses/workshops on energy planning and energy project coordination and management (EP&EPC/M) by 2012

• 2 completed workshops on energy data gathering system and operation and maintenance of the energy database

10. Solutions Applied (to address issues and challenges) Given that there has been no further development in the joint IUCN / PIGGAREP position, PIGGAREP should use the opportunity to build capacity in the PICs through various short term attachments for specific tasks averaging 2 weeks to a month. These may include updating the PIGGAREP web page and designing the above workshops, among others. The workshops mentioned in #9 above will be incorporated into the 2010 and future work plans. On this same approach, PICs should be encouraged to look at the indicators as a guide for

Page 42: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

designing their co-financing and incremental activities and for the reporting of their quarterly achievements. 11. Recommendations for Future Action/Work Plan Quarter 2/2009 Please see the 2 QTR 09 column of the 2009 Work Plan, attached as Annex 1.

12. Project Finance The Combined Delivery Report for 2008 was finalized during the quarter and is attached as Annex 2. The financial report for the quarter was done in UNDP’s new Funding Authorization and Certificate of Expenditures (FACE) format, as attached in Annex 3. The total budget for the quarter was USD 185,000. Total expenditures were USD 151,839 (or 82% of the budget) with USD 31,407 (21%) being PMO-related costs and USD 120,432 (79%) being for PICs project activities and participation in regional activities. An analysis of the project finance to the end of the quarter can be seen in the following graphs.

Figure 1: Budget vs. Expenditures

-

200,000

400,000

600,000

800,000

1,000,000

1,200,000

3 QT R 07 4 QT R 07 T otal 07 1 QT R 08 2 QT R 08 3 QT R 08 4 QT R 08 T otal2008

1 QT R 09

Quarters

US$

BudgetTotal Expenditures

Page 43: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Figure 2: Delivery Rate (expenditures / budgets)

56%60%

17%

29%

48%

79% 82%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

3 QTR 07 4 QTR 07 1 QTR 08 2 QTR 08 3 QTR 08 4 QTR 08 1 QTR 09

Quarters

Figure 3: PICs vs. PMO Expenditures

-

100,000

200,000

300,000

400,000

500,000

600,000

3 QTR 07 4 QTR 07 Total 07 1 QTR 08 2 QTR 08 3 QTR 08 4 QTR 08 Total 2008 1 QTR 09

Quarters

US$

PMO Expenditures

PIC Expenditures

Page 44: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Figure 4: Expenditures by PICs for 1 QTR 09

2159 1536 3602 2334 4662 2818 5014 2310 5180

90819

0

10000

20000

30000

40000

50000

60000

70000

80000

90000

100000

Cook Is Fiji Kiribati Nauru Niue PNG Samoa SI Tonga Tuvalu Vanuatu

PICs

US$

Figure 5: Expenditures by PICs to end 1 QTR 2009

52023

372612675

72995

9024 13661

125555

12043

32310

69575

96423

0

20000

40000

60000

80000

100000

120000

140000

Cook Is Fiji Kiribati Nauru Niue PNG Samoa SI Tonga Tuvalu Vanuatu

PICs

US$

The financial report for the quarter is attached as Annex 3. 13. Report Prepared By: Solomone Fifita Project Manager 19 May 2009

Page 45: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Annex 1: 2009 Work Plan and Budget

Proj. Code Year 1 Quarters 2009 Total

Activity Outcome

Lead / Collaborating Agencies

1 2 3 4 Comments

1 Mangaia Power System Upgrade

Technical

French and Aust govts, SOPAC and MIC

10,000 10,000

2 Wind Power Feasibility Study

Technical

Energy / TAU 50,000

50,000

3 RE / Green Award Programme for the tourism sector

Awareness

Energy / Tourism 5,000

5,000

Sub-total Cook Is 0 0 10,000 55,000 65,000 1 Technical, economic

& environmental evaluation of solar home systems project

Technical

DoE 5,000

5,000

5,000

5,000

20,000

2 Establishment of the Biogas market

Market DoE 10,000 10,000

3 Technical Assistance (through consultancy) for strengthening the management of the Energy Information System

Technical

DoE 5,000 10,000 5,000 20,000

4 Technical Support to the development of energy legislation

Policy DoE 5,000

8,000

5,000

18,000

5 Technical visits to RESCO business operations in Kiribati (Kiribati Solar Energy Company).

Institutional

DoE 15,000

10,000

25,000 Moved from 1 QTR to begin 2 QTR 09.

Sub-total Fiji 10,000 35,000 38,000 10,000 93,000 1 National Training for

Trainers in PV maintenance & Trouble Shooting

Technical

SEC 45,000

45,000

2 Review of KSEC, Restructure, On the Job Business Training, Strategic Planning, Project Preparation,Management, Monitoring and Evaluation

Technical

SEC 15,000

15,000

Business training will be carried out by the TA and will be conducted at KSEC HQs to Senior Management staff for one week plus one week preparation

3 Migrating RESCO Manager to an open source platform.

Technical

SEC 10,000 20,000

30,000

60,000

Programming and Launching of the RESCO Manager V3 (Web - based). Changed to begin 2 QTR 09.

4 Consultations on the National Energy Policy and drafting of

Policy EPU, MELAD, MISA

7,000

7,000

Workshops, awareness, stakeholders

Page 46: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

an Action Plan

5 Public awareness campaigns

Awareness

SEC 3000 3000 3000 3000 12,000

Awareness raising activities linking RE projects to mitigating potential to climate change, and their benefits to environment and economy

Sub-total Kiribati 10,000

28,000

23,00

0

78,00

0

139,000

1 PV training Capacity building

NUA 5,000

5,000 EU-REP5

2 Energy Database Institutional

NUA/CIE 10,000

10,000 SOPAC

3 Training needs assessment for RE

40,000

40,000

Sub-total Nauru 10,000 40,000 5,000 0 55,000 1 RE training in all

sector Awareness

NPC -

5,000

-

5,000

10,000 NPC Electricians/Private Sector

2 Network and System Modelling for the Grid Stability

Technical

Consultant 50,000

-

-

50,000 Impact on any size RE connected to the Grid

3 RE and Existing Tariff Study

Technical

Consultant 40,000

40,000 Impact of the 52 kW PV Grid Connected system

4 Awareness programs on all sectors radio/tv/local news paper/1/4ly weekly bulletins

Awareness

NPC/Private Sector

-

5,000

5,000

5,000

15,000 Workshops/Monthly Programs

Sub-total Niue 0 60,000 5,000 50,000 115,000 1 PNG: PNG: Feasibility Study for the rehabilitation of Sohun hydro,

Telefomin hydro and Yagusa Hydro (PNGSEL/PIGGAREP) 50,000 50,000

2 PNG: Biofuel research/study into coconut oil as a substitute fuel for diesel engines (ATCDI/Unitech & PIGGAREP)

15,000 15,000

Sub-total PNG 0 0 50,000

15,000

65,000

1 Hydro data collection programme

Technical

EPC (lead) Energy Division, energy stakeholders, EPC, MNREM, SWA,

0 The 73,605 is deleted as this has been committed and reported in 4 QTR 08.

2 Wind resources assessments

0 EPC (lead), Energy Division, Energy Stakeholders, SWA, MNREM,

0 The 12,000 is deleted as this has been committed and reported in 4 QTR 08.

Page 47: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

0 3 National energy

awarenss campaign day

Info & Awareness

Energy Division (lead), energy stakeholders, MNREM, MWCSD, MAF, MWTI, MESC, RDIS, NUS, EPC, SSC, SAA, STA, Oil companies, gas companies, SUNGO, SAME, COC, MEDIA

10,000

10,000

Sub-total Samoa 0 10,000 0 0 10,000 1 RE Training for

students at Willies and SICHE on Electrical Trade

Technical

SIG, SICHE, SITAFE

2,000

2,000

2,000

2,000

8,000

2 Re-do a feasibility studies for HURO and RUALAE Hydropower schemes

Technical

SIG, SIEA 7,000

7,000

7,000

21,000

3 Bio-fuel Development and Expansion in the Solomon Islands

Market SIG, Private Sector, SIEA

7,500

7,500

5,000

20,000

4 Workshop/Training for users (schools) of the installed Solar PV systems

Technical

SIG, Private Sector

3,000

3,000

3,000

3,000

12,000

5 Setup of RE Information and Exchange Centre

Institutional

SIG, Private 20,000

20,000

Sub-total Solomon Is 5,000 39,500 19,500 17,000 81,000 1 Review and

Evaluation of the Niuafo'ou SEIS

Institutional

EPU 10,000

10,000

2 Technical evaluation of the solar installations in Mango & Mo'unga'one

Technical

EPU, HSES 3,000

3,000 The whole installation must be evaluated and set platform for commissioning

3 Review and confirm the EDF 10's feasibility study 15,000 4 Awareness Training

for solar water pumping and TONGATAPU Solar Street light villages (Nakolo(NZ community FUND -install in DEC 2008), villages of the Tatakamotonga Districts

Awareness

EPU 11,000

11,000 The installation of solar street lights in Nakolo in December 2008 funded by NZ Nakolo Committee is the Baseline Activity. Changed to begin 2 QTR 09.

5 REM/FEMM 2009 20,000

20,000 Support the hosting of the REM/FEMM 2009 in Tonga

Sub-total Tonga 3,000

41,000

15,000

-

59,000

1 Support to TEC’s outer island grid-connected renewable energy project

Technical

TEC 20,000

20,000

Page 48: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

2 Studies of wind potential in the outer-islands

Awareness 10,000

10,000

3 Support implementation of Policy and Strategic Action plan

Policy Institutional

Energy 6,250

6,250

12,500

4 Analysis of wind data and Preparation of Wind Fuel savings project for Funafuti Islands

Institutional

TEC 50,000

50,000

5 Public demonstration of Biodiesel, todi ethanol, gasification production Dissemination of biogas technology introduced by PIEPSAP Education tool for children in tuvaluan, USP & high school classes

Awareness

Alofa Tuvalu, Tuvalu Maritime Training Institute, PM Office, Environment, energy, home affairs, media, TCS, TCTC, TEC, USP

5,000

5,000

10,000

Sub-total Tuvalu 0 10,000 81,250 11,250 102,500 1 Technical training on

the O&M of the Sarakata hydropower project

Institutional

EU & Unelco 3,000 3,000

2 Review of the 2002 Talise Mini Hydro Feasibility Study

Market Energy Unit, Consultant

50,000 50,000

3 Feasibility Study of the Lowanau River (Tanna) hydro resource potential

Technical

EU, TA 10,000 10,000 20,000 Utilising a local consultant to carry out the feasibility study

4 Community Training on Biofuel at NE Malekula, Saratamata and Vanualava

Awareness

UNELCO, Energy Unit, Provincial govts

5,000 5,000 10,000 Site Management training

5 Technical visits/study tour to community based pico/micro hydros in Solomons, Fiji and/or PNG

Institutional

EU 10,000 15,000 25,000 Can it be to just one PICs?

Sub-total Vanuatu 53,000 10,000 30,000 15,000 108,000

Sub-total National Activities 91,000 273,500 276,750

251,250 892,500

Regional Activities:

2 Regional Workshop on writing project proposals and PAS on 3rd week of January 2009

40,000 40,000

1 REP-5 / PIGGAREP Workshop on grid-connected PV

35,000 35,000 Changed to begin 2 QTR 09

3 Technical visits to RE developments in Vanuatu 40,000 40,000 Changed to begin 3 QTR 09

4 Study tour of the Ha'apai Solar Electricity Inc - Fiji, Kiribati, PNG, Vanuatu, Tuvalu, SI, Samoa.

40,000 40,000 Changed to begin 4 QTR 09

Page 49: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Sub-total Regional Activities 40,000 35,000 40,000 40,000 155,000

PMO Costs International Consultants (PM) 30000 30000 30000 30000 120,000 Local Consultant - PA 4000 4000 4000 4000 16,000 Local Consultant - APA 1000 1000 1000 1000 4,000 Administration Fess 5000 5000 5000 5000 20,000 Contractual Services - Ind 1000 1000 1000 1000 4,000 Travel, Audits and Reviews 10000 10000 10000 60000 90,000 Contractual Services - Co 1000 1000 1000 1000 4,000 Equip and Furniture 0 0 0 0 - Comm & Audio Equip 0 0 0 0 - Supplies 500 500 500 500 2,000 Info Tech Equip 1000 1000 1000 1000 4,000 Audio Visual and Print Prod 500 500 500 500 2,000 Total for PMO

54,000

54,000

54,000

104,000

266,000

GRAND TOTAL FOR 2009 185,000 362,500 370,750 395,250 1,313,500

Page 50: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking
Page 51: QUARTERLY PROGRESS REPORT1 First Quarter 2009archive.iwlearn.net/sprep.org/climate_change/documents/1...The school requested for a biogas digester so they can use methane gas for cooking

Recommended