+ All Categories
Home > Documents > Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines...

Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines...

Date post: 30-Aug-2019
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
9
Railway Tender Conference Jarle Rasmussen Acting Project Director Construction Unit East Bane NOR 10 May 2017
Transcript
Page 1: Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines • The Gardermoen Line (1998/99) • Kleverud-Langset Joint Project with new E6

Railway Tender Conference Jarle Rasmussen Acting Project Director Construction Unit East Bane NOR 10 May 2017

Page 2: Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines • The Gardermoen Line (1998/99) • Kleverud-Langset Joint Project with new E6

Construction Unit East project responsibility

2 Information is correct as of 10 May 2017, but may be subject to change.

Page 3: Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines • The Gardermoen Line (1998/99) • Kleverud-Langset Joint Project with new E6

Already upgraded tracks on the Dovre and Østfold Lines • The Gardermoen Line (1998/99) • Kleverud-Langset

Joint Project with new E6 motorway (2015)

The Østfold Line:

• The Follo Line (ongoing, scheduled 2021) • Ski – Sandbukta (1996) • Såstad – Haug (2000)

3 Information is correct as of 10 May 2017, but may be subject to change.

Page 4: Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines • The Gardermoen Line (1998/99) • Kleverud-Langset Joint Project with new E6

Haug - Seut

• 17 km new double track railway, including new

station at Råde.

• Combination of day zone, short tunnels and bridges.

• Unstable ground conditions part of the distance

• Mostly agricultural and cultivated landscapes Prequalification expected: 2019 Construction phase: 2020-2024 Railway in operation expected: 2024

4 Information is correct as of 10 May 2017, but may be subject to change.

Page 5: Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines • The Gardermoen Line (1998/99) • Kleverud-Langset Joint Project with new E6

The Østfold Line

• Double track to Sarpsborg planned in operation from 2026 (NTP).

• Double track to Halden planned in operation from 2034.

• Probably divided into two separate projects

5 Information is correct as of 10 May 2017, but may be subject to change.

Page 6: Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines • The Gardermoen Line (1998/99) • Kleverud-Langset Joint Project with new E6

Seut - Sarpsborg and Sarpsborg - Halden

6 Information is correct as of 10 May 2017, but may be subject to change.

Page 7: Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines • The Gardermoen Line (1998/99) • Kleverud-Langset Joint Project with new E6

The Dovre Line

• Double track to Hamar planned in operation from 2024 (NTP).

• Double track to Lillehammer planned in operation from 2034.

• Probably divided into two or three separate projects.

7 Information is correct as of 10 May 2017, but may be subject to change.

Page 8: Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines • The Gardermoen Line (1998/99) • Kleverud-Langset Joint Project with new E6

Sørli - Brumunddal and Brumunddal - Lillehammer

8 Information is correct as of 10 May 2017, but may be subject to change.

Page 9: Railway Tender Conference - banenor.no · Already upgraded tracks on the Dovre and Østfold Lines • The Gardermoen Line (1998/99) • Kleverud-Langset Joint Project with new E6

Thank you

9 Information is correct as of 10 May 2017, but may be subject to change.


Recommended