+ All Categories
Home > Documents > RDA CENTRAL WEST & CENTROC Tranche was commissioned and overseen by RDA Central West. The study area...

RDA CENTRAL WEST & CENTROC Tranche was commissioned and overseen by RDA Central West. The study area...

Date post: 25-Apr-2018
Category:
Upload: doanhuong
View: 220 times
Download: 4 times
Share this document with a friend
17
1 25/04/2015 CLIENT ISSUE REVISED LIST SS RT SS 0 06/02/2015 CLIENT ISSUE SS RT SS REV NO. DATE DESCRIPTION OF REVISION BY REVIEWED APPROVED Lycopodium Rail Pty Ltd, ABN: 65 152 593 149, Level 3, 16a Bolton Street, Newcastle NSW 2300 RDA CENTRAL WEST & CENTROC CENTRAL WEST FREIGHT, LOGISTICS AND TRANSPORT INFRASTRUCTURE REGIONAL PRIORITIES 6046-REP-002 April 2015
Transcript

1 25/04/2015 CLIENT ISSUE – REVISED LIST SS RT SS

0 06/02/2015 CLIENT ISSUE SS RT SS

REV NO.

DATE DESCRIPTION OF REVISION BY REVIEWED APPROVED

Lycopodium Rail Pty Ltd, ABN: 65 152 593 149, Level 3, 16a Bolton Street, Newcastle NSW 2300

RDA CENTRAL WEST & CENTROC

CENTRAL WEST FREIGHT, LOGISTICS AND TRANSPORT INFRASTRUCTURE REGIONAL PRIORITIES

6046-REP-002

April 2015

CENTRAL WEST FREIGHT, LOGISTICS AND TRANSPORT INFRASTRUCTURE REGIONAL PRIORITIES

6046-REP-002

Table of Contents

Page

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

1.0 INTRODUCTION 2

2.0 BACKGROUND 2 2.1 Location 2 2.2 Freight Task 5

3.0 PURPOSE 6

4.0 METHODOLOGY AND APPROACH 7 4.1 Approach 7 4.2 Evaluation Matrix Input Sheet 8 4.3 Initial Workshop to Agree on Evaluation Matrix Methodology 9

5.0 CAPTURE OF PROJECTS AND DEVELOPMENT OF THE PROJECT LIST 9

6.0 EVALUATION OF PROJECTS 9

7.0 FREIGHT, LOGISTICS AND TRANSPORT PRIORITY RANKING 11 7.1 Top 25 Projects 11 7.2 Projects 26 – 73 12 7.3 Weighting 14 7.4 Comments on the Project Ranking 14

8.0 PROJECTS RANKED BY BANDING 15 8.1 Priorities Greater than $10M in Capital Investment 15 8.2 Priorities Between $5M-10M in Capital Investment 16

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

1.0 INTRODUCTION

Lycopodium Rail Pty Ltd (Lycopodium) were engaged to develop a list of regional freight, logistics

and transport priorities across the Central West of NSW, specifically across the 14 LGA’s within

CENTROC. In delivering the study Lycopodium reviewed the region’s current freight, logistics and

transport infrastructure priorities and plans, assessed the extent of the supporting evidence base,

identified opportunities according to defined criteria, and recommend priorities for the New South

Wales Central West region. This report documents the purpose, methodology, consultation

undertaken and the findings of the Central West Transport Infrastructure Priorities Study.

This project was jointly sponsored and project managed by RDA Central West and CENTROC on a

collaborative basis and through a joint steering committee (“the Committee”).

2.0 BACKGROUND

Regional Development Australia Central West (RDACW) and Central NSW Councils (CENTROC)

are in the process of reviewing and establishing the key infrastructure priorities for the New South

Wales Central West region.

This is Stage 2 of the NSW Central West - Regional Infrastructure Review and Assessment

Project. Where infrastructure priorities have been classified according to a number of tranches, this

component of the project addresses only Tranche 1 - Freight, Logistics and Transport.

This project provides regional stakeholders with clear articulation of those projects that are

considered to have the greatest relative merit and worthy of more detailed investigation.

This Tranche was commissioned and overseen by RDA Central West. The study area

encompasses the local government areas of Bathurst, Blayney, Boorowa, Cabonne, Cowra,

Forbes, Lachlan, Lithgow, Oberon, Orange, Parkes, Upper Lachlan, Weddin and Young.

2.1 Location

The following illustrations were generated during the study to outline the transport networks within

the study area.

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

Figure 2.1 – Study Area Boundaries against major interstate Transport Corridors

Figure 2.2 – Rail Network (CENTROC Boundaries)

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

Figure 2.3 – Road Network (CENTROC Boundaries)

Figure 2.4 – Combined Road and Rail Network (CENTROC Boundaries)

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

2.2 Freight Task

During the study the Freight Model developed for the recently completed Central West Freight

Study was updated to incorporate data for the 3 additional LGA’s of Boorowa, Upper Lachlan and

Young. The current freight task as illustrated below combines freight generation and consumption

at a commodity level and also at a modal level shown as Net Tonnes per annum. Road volumes

include freight flows from each direction and so volumes approximate net tonnes moved in both

directions. Rail volumes are also shown as the combination of both directions and derived from

gross tonnes per annum.

The following illustrates the freight task volumes on road and rail through the study area, which was

considered in evaluation of individual projects.

Figure 2.5 – Net Annual Freight Volumes on Road and Rail 2014 (CENTROC Boundaries)

Predicted Increase in the Total Freight Task

The Central West Freight Study adopted the projected increases in the total freight task across

NSW as well as the predicted growth rates for major commodities as depicted in the NSW Freight

and Ports Strategy.

To approximate freight flows on key routes across the Central West Region, growth rates in the

Central West Freight Model were applied to current tonnages for locally produced commodities and

then factored into current road/rail volumes allowing for existing through freight. Increases in

through freight (such as Melbourne – Brisbane road volumes, which are expected to rise by

approximately 80% over the next 20 years) were also approximated. The Central West Freight

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

Model was expanded to include the 3 additional LGA’s of Boorowa, Upper Lachlan and Young in

order to represent the freight volumes within the CENTROC Boundaries to assist in the

assessment of regional transport priorities.

The combined road and rail volumes approximated at 2034 are illustrated below:

Figure 2.6 – Net Annual Freight Volumes on Road and Rail 2034 (CENTROC Boundaries)

3.0 PURPOSE

There is an increasing trend at both a State and Federal level to link available program funding to

infrastructure projects, particularly where an economic benefit is able to be derived and where the

proposed projects are underpinned by a strong supporting evidence base. The amount of funding

available varies from program to program, as does the area of infrastructure emphasis.

Increasingly, the region needs to be ready to take advantage of opportunities to attract funding to

the region across the broad infrastructure spectrum.

In this context, readiness requires the following:

Up-to-date local and regional priorities for the respective categories of infrastructure;

Project proposals that vary according to degree of funding required and amount of overall

spend required;

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

Where appropriate, supporting business cases with benefit cost analyses and other

substantiation.

This purpose of this project was to undertake the preparatory work necessary to identify and

assess those freight, logistics and transport infrastructure projects with an anticipated regional

benefit which may be the subject of further, detailed analysis at a subsequent stage.

This project addresses the first of the following six tranches:

Tranche 1: Freight, Logistics and Transport;

Tranche 2: Water;

Tranche 3: Education and Health;

Tranche 4: Sporting and Cultural;

Tranche 5: Energy;

Tranche 6: Communications.

This tranche is to cover all infrastructure priorities and candidate projects relating to freight,

logistics and transport including but not limited to:

Road and highway networks including structures;

Rail infrastructure including structures, terminal facilities, level crossings, signalling and

communications;

Air infrastructure including air navigational systems and airport structures and facilities;

Logistics infrastructure including, but not limited to, intermodal terminals, warehousing,

truck driver interchanges, agriculture storage and distribution;

Public transport infrastructure (including community transport), bicycle paths, pedestrian

walkways, bridges and underpasses.

4.0 METHODOLOGY AND APPROACH

4.1 Approach

In delivering the study Lycopodium carried out the following:

Conducted a literature review relating to government strategy, policy, plans and programs

as well as plans and strategies available from local and regional stakeholders;

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

Conducted focus groups with stakeholders including Council engineers and others to

further inform the study;

Identified of a long list of possible projects;

Compiled information on projects provided in order to populate the evaluation matrix;

Developed an evaluation matrix calculation tool;

Evaluated each project against the defined criteria included in the Matrix;

Provided recommendations as to key follow up actions in order to better position projects

considered to have high potential or impact.

4.2 Evaluation Matrix Input Sheet

Stage 1 of the project developed a decision making matrix input sheet. The methodology and input

developed during Stage 1 has been used to assess infrastructure priorities as it offers:

A consistency of approach with regard to regional priorities;

Cross tranche comparison and prioritisation;

A point of difference to other infrastructure plans; and

A tool for member use for the future.

The evaluation matrix input sheet was prepared by MWH Global for CENTROC and RDA Central

West and was provided at the commencement of the study to be used in assessing individual

projects. The evaluation matrix covered the following key areas.

Economic Efficiency;

Economic cost;

Economic benefit;

Connection;

Grows Economy;

Equity;

Culture Heritage Impact;

Environmental;

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

Social;

Resilience;

Funding;

Risk.

Within each of the broad evaluation elements above a number of evaluation criteria exist.

Definitions of the abovementioned evaluation criteria are included in the glossary that accompanies

the matrix.

4.3 Initial Workshop to Agree on Evaluation Matrix Methodology

A workshop was convened on the 10th October 2014 by CENTROC and chaired by MWH Global to

review and agree on the evaluation matrix methodology and the evaluation criteria included in the

matrix. Some minor adjustments to the criteria and evaluation methodology were suggested at the

workshop and a final version of the evaluation matrix was provided on the 13th October.

5.0 CAPTURE OF PROJECTS AND DEVELOPMENT OF THE PROJECT LIST

Where possible, face to face consultation sessions were held with representatives from the LGA’s

within the study area. These sessions were conducted between the 23rd

October 2014 and the 28th

October 2014 and involved 4 days across the Central West. Subsequent phone hook-ups were

held where face to face meetings could not be arranged.

Information supporting projects in various forms was provided during and subsequent to these

sessions. The consultation forums were not used as a way of populating information into the

matrix, they were primarily held in order to discuss and determine local and regional freight,

logistics and transport projects and priorities. The project descriptions contained in the evaluation

matrix was later populated by Lycopodium based on information supplied as well as other

supporting information gathered during the study.

It is relevant to note that some projects score relatively poorly where limited information was

available to assess these projects against the matrix criteria. Through the assessment period

additional consultation has taken place with representatives within the LGA’s and where

substantiated through additional information some of the project in the list have been reassessed.

The matrix tool allows this process to continue into the future.

6.0 EVALUATION OF PROJECTS

After a period of reviewing the information supplied, relevant details on each project were captured

in the matrix to assist in the evaluation. Much of the text has been taken from previous reports

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

including the Western Roads plan. Each project was assessed against the 28 evaluation criteria

and in the majority of cases provided a score out of 10.

Some notes relevant to the scoring of projects are provided below:

Phase: Projects that are well scoped with detailed designs completed scored well in this

category and others that are in early stages suffered through lack of detailed information

Capital Costs: The matrix provides a high score to expensive projects, however this is

offset against avoided costs and potential revenue. Capital costs were derived from

previous reports, comments from LGA representatives or derived by Lycopodium;

Operating and Maintenance Costs: General industry benchmarks for maintenance of

road and rail infrastructure (per km) was used to derive costs for this criteria. The annual

net tonnage on the transport corridor was taken into consideration through the application

of varied costs per km to maintain. Whilst this methodology could be improved upon, it

provided a relatively effective way of ranking projects;

Service Levels and Utility: The assessment contains some subjectivity however all

projects were assessed against one another and so the assessment is considered

reasonable;

Revenue: Only projects such as new road, rail and airport infrastructure were considered

able to generate additional revenue. Revenue for these projects was calculated based on a

per km pa rate and then applied across the initial 10years of operation. Further information

on predicted revenue for projects should be used to update the matrix as business cases

are developed for projects;

Avoided cost: Projects that deliverer improved infrastructure such as road widening, road

pavement strengthening, upgrade from gravel to bitumen roads were seen as delivering

significant avoided costs. These avoided costs were calculated based on the cost of

operations/maintenance on the existing versus new infrastructure and based on a per km

pa rate factored to consider the net tonnage on the transport corridor.

Links to markets: Projects were assessed against the strategic role they play in providing

a link to domestic and international markets.

Other: It was difficult to separate the vast majority of projects against a number of the

evaluation criteria and particularly within the hourly estimated time for the study (which was

agreed to prior to receiving the evaluation matrix). In general strategic projects that are

very likely to generate large scale growth and employment in the region such as the Bells

Line of Road Upgrade and bypasses on the Newell Highway score well through the

majority of evaluation criteria whereas upgrades on rural roads with low annual volumes do

not score as well, apart from isolated criteria such as safety which may be a feature unique

to the project.

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

7.0 FREIGHT, LOGISTICS AND TRANSPORT PRIORITY RANKING

7.1 Top 25 Projects

RANK ACROSS REGION

OVERALL ASSESSMENT

PROJECT TITLE

1 98.4 BELLS LINE OF ROAD UPGRADE

2 94.6 CADIA ROAD RECONSTRUCTION

3 86.9 INLAND RAIL PROJECT

4 85.6 GREAT WESTERN HWY UPGRADE EAST

5 85.6 BATHURST HEAVY VEHICLE BYPASS

6 80.9 CADIA TO MITCHELL HWY STRATEGIC LINK

7 78.9 SOUTHERN FEEDER ROAD ORANGE

8 78.7 SOUTHERN RING ROAD PARKES

9 78.4 HEAVY VEHICLE ROUTE NORTH FORBES

10 76.7 WESTERN RING ROAD PARKES

11 76.2 GOULBURN RD. BATHURST TO GOULBURN VIA CROOKWELL

12 75.4 BLAYNEY TO DEMONDRILLE RAIL LINE - REOPENING

13 73.9 BELUBULA WAY - TRUNKEY CREEK TO CANOWINDRA

14 73.8 BOGAN GATE TO TOTTENHAM RAIL LINE

15 72.8 MARY GILMORE WAY - BARMEDMAN TO ORANGE

16 72.4 UPGRADING OF RAIL NETWORK TO SUPPORT MORE EFFICIENT PASSENGER AND FREIGHT TO SYDNEY

17 69.8 PARKES AIRPORT UPGRADE

18 68.4 ABERCROMBIE HILL (MAIN ROAD 256)

19 68.1 ORANGE BULLET (TRAIN SERVICE)

20 66.9 HEAVY VEHICLE TRAFFIC RELIEF ROUTE

21 66.5 PEISLEY ST RAIL OVERBRIDGE WIDENING

22 66.5 BATHURST AIRPORT UPGRADE

23 66.0 ORANGE AIRPORT UPGRADE

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

24 65.7 BEASLEY RD UPGRADE (LINKING TO FOREST RD)

25 65.5 GLEN DAVIS RD / GLEN ALICE RD

Table 7.1 – Projects 1 - 25

7.2 Projects 26 – 73

RANK ACROSS REGION

OVERALL ASSESSMENT

PROJECT TITLE

26 65.5 RANGE ROAD CONNECTING WEST TO CASTLEREIGH HWY

27 64.8 COL DREW DRIVE

28 62.6 COCKATOO HILL AT SOFALA

29 61.7 ELECTRIFICATION OF RAIL NETWORK TO BATHURST

30 60.6 YOUNG INNER CITY HEAVY VEHICLE ROUTE UPGRADE

31 60.3 HENRY LAWSON WAY - NAGS HEAD BRIDGE UPGRADE MR236

32 60.2 BANJO PATTERSON WAY, HANOVER BRIDGE UPGRADE

33 59.6 COWRA INTERMODAL HUB

34 59.3 MURRINGO RD YOUNG TO BOOROWA

35 59.1 YOUNG HEAVY VEHICLE BYPASS

36 58.8 MILVALE ROAD SHOULDER WIDENING: TEMORA TO YOUNG

37 58.5 57 NORTH (CONDO TO TULLAMORE)

38 58.2 ORANGE ROAD UPGRADE

39 58.1 TOTTENHAM AERODROME

40 58.0 348 - TULLAMORE TO PEAK HILL

41 57.9 COWRA AIRPORT UPGRADE

42 57.2 BOGAN WAY WIDENING

43 57.2 GUMBLE ROAD INITIAL SEAL

44 57.2 RENSHAW - MCGIRR WAY REALIGNMENT: PARKES TO WELLINGTON (MR233)

45 57.0 350 - TULLAMORE - BOGAN GATE - FORBES (BOGAN WAY)

46 56.8 GREENTHORPE TO BUMBALDRY B-DOUBEL UPGRADE

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

47 56.6 LACHLAN VALLEY WAY - OVERTAKING LANES

48 56.5 WOMBEYAN CAVES RD

49 56.2 LACHLAN AND DOG ROCKS RD

50 56.1 HEAVY VEHICLE BYPASS - COWRA

51 56.1 MORONGLA RD - FROM LACHLAN VALLEY WAY TO OLYMPIC WAY

52 56.0 MIDDLE TRUNDLE - PART SEALED

53 56.0 GRABINE RD - BIGGA TO WQYANGALA

54 55.3 LEEDS RD (INTERSECTION WITH NORTHERN DISTRIBUTOR) REST AREA

55 55.0 COLLECTOR RD - GUNNING TO COLLECTOR

56 54.9 DRIFTWAY ROAD

57 54.6 FROGMORE RD

58 54.6 BATTERY RD - GLENALLA QUARRY

59 53.7 HOBBY'S YARDS ROAD

60 53.5 LAGGAN RD EAST - LAGGAN TO TARALGA - GRAVEL SECTIONS

61 53.2 BURRAGA RD

62 53.2 REOPENING OF THE OBERON TO TARANA RAIL LINE

63 52.7 BEACONSFIELD ROAD (RESEALING / SHOULDER UPGRADES)

64 52.3 SAFETY BARRIER INSTALLATIONS

65 52.1 LACHLAN AND KENDAL ST REALIGNMENT TO CONNECT LACHLAN VALLEY WAY AND MID WESTERN HWY

66 52.1 BENNETT SPRINGS RD

67 51.9 REALIGNMENT OF ACCESS TO BLAYNEY SEALINK

68 51.6 CUNNINGAR RD

69 51.6 LACHLAN VALLEY WAY PASSING LANES

70 51.2 MAIN ROAD 253: EDITH RD

71 51.1 RUGBY ROAD – BOOWROWA TO CROOKWELL

72 51.0 NEWELL HWY REST AREA - WEST WYALOING TO FORBES

73 51.0 GUNNING ROAD - DEVILS ELBOW REALIGNMENT

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

74 50.9 JENOLAN CAVES ROAD

75 47.8 ORANGE CYCLEWAY NETWORK

Table 7.2 – Projects 26 - 75

0

10

20

30

40

50

60

70

80

90

100

OV

ERA

LL A

SSES

SMEN

T A

CR

OSS

REG

ION

PROJECTS

Rank in Region

Figure 7.1 – Chart of All Projects Ranked Across Region

7.3 Weighting

Note: the above represents the ‘un weighted’ ranking. The matrix evaluation tool allows weighting

of certain criteria to reflect their importance over other criteria, however it is recommended that any

weighting be applied specific to an application such as a specific government funding program.

7.4 Comments on the Project Ranking

Ranking of individual projects within an LGA across regional boundaries is a contentious exercise.

By utilising a standard matrix and agreed evaluation criteria, it is expected that the subjectivity of

any ranking process is reduced and projects can be assessed on a uniform and transparent basis.

The process used in this study is considered to be transparent however the variation comes from

the input data. Limited data was available for certain projects, making the assessment against

other projects more difficult. It is likely that stakeholders will identify projects that they believe to be

of significant merit and are under represented in the matrix. To this end it is recommended that

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

stakeholders have the opportunity to provide additional data to support projects that appear under

represented through the initial evaluation process.

8.0 PROJECTS RANKED BY BANDING

To assist stakeholders with future funding submissions the ranked projects in the following bands

have been outlined below.

8.1 Priorities Greater than $10M in Capital Investment

RANK ACROSS REGION

OVERALL ASSESSMENT

PROJECT TITLE

1 98.4 BELLS LINE OF ROAD UPGRADE

2 94.6 CADIA ROAD RECONSTRUCTION

3 86.9 INLAND RAIL PROJECT

4 85.6 BATHURST HEAVY VEHICLE BYPASS

6 80.9 CADIA TO MITCHELL HWY STRATEGIC LINK

7 78.9 SOUTHERN FEEDER ROAD ORANGE

10 76.7 WESTERN RING ROAD PARKES

12 75.4 BLAYNEY TO DEMONDRILLE RAIL LINE - REOPENING

14 73.8 BOGAN GATE TO TOTTENHAM RAIL LINE

16 72.4 UPGRADING OF RAIL NETWORK TO SUPPORT MORE EFFICIENT PASSENGER AND FREIGHT TO SYDNEY

19 68.1 ORANGE BULLET (TRAIN SERVICE)

23 66.0 ORANGE AIRPORT UPGRADE

25 65.5 GLEN DAVIS RD / GLEN ALICE RD

29 61.7 ELECTRIFICATION OF RAIL NETWORK TO BATHURST

35 59.1 YOUNG HEAVY VEHICLE BYPASS

50 56.1 HEAVY VEHICLE BYPASS - COWRA

53 56.0 GRABINE RD - BIGGA TO WQYANGALA

59 53.7 HOBBY'S YARDS ROAD

6046-REP-002

April 2015 Lycopodium Rail Pty Ltd

61 53.2 REOPENING OF THE OBERON TO TARANA RAIL LINE

71 51.1 RUGBY ROAD – BOOWROWA TO CROOKWELL

Table 8.1 – Projects Ranked Across Region Over $10M

8.2 Priorities Between $5M-10M in Capital Investment

RANK ACROSS REGION

OVERALL ASSESSMENT

PROJECT TITLE

4 85.6 GREAT WESTERN HWY UPGRADE EAST

8 78.7 SOUTHERN RING ROAD PARKES

20 66.9 HEAVY VEHICLE TRAFFIC RELIEF ROUTE

33 59.6 COWRA INTERMODAL HUB

43 57.2 RENSHAW - MCGIRR WAY REALIGNMENT: PARKES TO WELLINGTON (MR233)

48 56.5 WOMBEYAN CAVES RD

55 55.0 COLLECTOR RD - GUNNING TO COLLECTOR

65 52.1 LACHLAN AND KENDAL ST REALIGNMENT TO CONNECT LACHLAN VALLEY WAY AND MID WESTERN HWY

67 51.9 REALIGNMENT OF ACCESS TO BLAYNEY SEALINK

68 51.6 LACHLAN VALLEY WAY PASSING LANES

Table 8.2 – Projects Ranked Across Region between $5M and $10M


Recommended