Real World Performance Benchmarking Oracle Transportation Management/Global Trade Management August 2012
3 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Safe Harbor Statement
• The preceding is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material, code, or functionality, and should not be relied upon in making purchasing decisions. The development, release, and timing of any features or functionality described for Oracle’s products remains at the sole discretion of Oracle.
4 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Agenda
• Internal Exa-data/Exa-logic Certification Testing • Customer Exa-data/Exa-logic POC • Other Performance Activities • Performance Benchmarking Advice
5 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Exalogic/Exadata Performance Update
• The OTM Exadata/Exalogic performance comparisons were captured as part of the OTM Certification testing for Exadata/Exalogic. These tests were not intended to be a true benchmark for directly comparing Exa/non-Exa hardware alternatives. In the future OTM may perform a true set of benchmark tests to capture this data.
6 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
OTM/GTM Exadata/Exalogic Certification • Certification Scenarios
• Basic Regression Test • Multi-stop Planning • Multi-leg Planning • “End-End” Orders through Shipments • FTI Initial ETL using ODI
• Baseline OTM 6.2.5 • Exadata/Exalogic OTM 6.2.6
7 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
OTM Certification Deployment Exalogic and Exadata
15X 5X
OTM WebTier
Web Server
OTM App Tier
App Server
8 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Exalogic
9 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Certification Scenario #1 • Certification of OTM version 6.2 • Test Description
• Multi-leg Planning • 5,000 Orders • Building into 20,000 Shipments
• OTM Settings • 120 Planning Threads • 16 GB Heap
10 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Certification Scenario #1 Hardware Comparison Database EXADATA
Hardw are Exadata X2-2 Half Rack (4 nodes, 48 physical cores) 2x Intel Xeon, 3 GHz processors (12 cores), 96GB 1.3Ghz RAM per node
Softw are OEL 5.5 Oracle Database 11gR2 Enterprise Edition Release 11.2.0.2
Storage
4x 512GB SSD for read cache (“Readzilla”, 2TB total) 4x 18GB SSD in disk shelf for w rite cache 20x 2TB 7200 rpm SAS HDD in disk shelf – RAID-1
Application Server
EXALOGIC
Hardw are Exalogic X2-2 (1 node, 12 physical cores) 2x Intel Xeon, 3GHz processors (12 cores), 96GB 1.3Ghz RAM per node
Softw are OEL 5.5 Oracle Weblogic Server 10.3.4
Database BASELINE
Hardw are Dell 2950 2 x 3.1 GHz processors (4 cores), 32GB RAM
Softw are OEL 5.5 Oracle Database 11gR2 Enterprise Edition Release 11.2.0.2.
Storage
Direct Attached Storage 8 arrays 800GB each RAID 10=800GB
Application Server
BASELINE
Hardw are Dell 2950 2 x 3.1 GHz processors (4 cores), 32GB RAM
Softw are OEL 5.5 Oracle Weblogic Server 10.3.4
11 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
RuntimeRuntime
Certification Scenario #1 Exalogic and Exadata for OTM 6.2
• Improved Engine Performance: – 4.7x Faster Bulk Plan Runtime*
• Higher Through-put – 8x Improvement in Shipment Persistence* – 7.5 ms per shipment
* Some changes made could benefit baseline scenario
OTM Shipment Persistence 8x Faster Performance
8X
OTM Bulk Plan
4.7x Faster Performance
4.7X
47minutes
10 minutes
Baseline
Exalogic and Exadata
60ms
7.5ms
12 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Certification Scenario #2 • Test Description
• 5,000 inbound transmissions, generating workflow resulting in: • 5,000 Order Releases • 10,000 Order Movements • 10,000 Shipments • 10,000 Invoices • 5,000 Tender Offers • 25,000 Outbound Transmissions
• OTM Settings • 36 threads each for various dataqueue and worker thread groups • 16 GB Heap
13 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Certification Scenario #2 Hardware Comparison Database EXADATA
Hardw are Exadata X2-2 Half Rack (4 nodes, 48 physical cores) 2x Intel Xeon, 3 GHz processors (12 cores), 96GB 1.3Ghz RAM per node
Softw are OEL 5.5 Oracle Database 11gR2 Enterprise Edition Release 11.2.0.2
Storage
4x 512GB SSD for read cache (“Readzilla”, 2TB total) 4x 18GB SSD in disk shelf for w rite cache 20x 2TB 7200 rpm SAS HDD in disk shelf – RAID-1
Application Server
EXALOGIC
Hardw are Exalogic X2-2 (1 node, 12 physical cores) 2x Intel Xeon, 3GHz processors (12 cores), 96GB 1.3Ghz RAM per node
Softw are OEL 5.5 Oracle Weblogic Server 10.3.4
Database BASELINE
Hardw are HP DL360 2 x 2.8 GHz processors (6 cores), 32GB RAM
Softw are OEL 5.6 Oracle Database 11gR2 Enterprise Edition Release 11.2.0.2.
Storage
Direct Attached Storage 8 arrays 800GB each RAID 10=800GB
Application Server
BASELINE
Hardw are HP DL360 2 x 2.8 GHz processors (6 cores), 32GB RAM
Softw are OEL 5.6 Oracle Weblogic Server 10.3.4
14 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Runtime
Certification Scenario #2 Exalogic and Exadata for OTM 6.2
OTM Overall Processing Time 9x Faster Performance
9x
2 hr 35 m
16 minutes
• Improved Performance: – 9x reduction in processing time*
* Some changes made could benefit baseline scenario
Baseline
Exalogic and Exadata
15 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Certification Details • Worked closely with
• Java team to fix contentions observed in JRE • Database team to fix an obscure bug in SDP protocol • OEL and Hardware team to measure/tweak OS and hard disk
performance • Of course, OTM team to
• Make ExaLogic specific changes • Certifying OTM with newer releases of the stack (weblogic, jdbc,
OEL, Database)
16 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Future • Explore Advanced Exadata Capabilities
• SDP over InfiniBand – High Performance Network Connection, in lieu of TCP/IP
• Smart Scan – Indexing Feature to Enhance Full Table Scan Performance
• Exadata Hybrid Columnar Compression – Advanced Feature for High Performance Data Compression
• Smart Flash Cache – Flash Memory Cache for Reduced i/o
17 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Agenda
• Internal Exa-data/Exa-logic Certification Testing • Customer Exa-data/Exa-logic POC • Other Performance Activities • Performance Testing Advice
18 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Analyzed Process
• Bulk Plan Order Release : To Buy Side Shipments – Average planning of 6,000 orders in 20 minutes, resulting in 250 shipments
19 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
© 20102Oracle Corporation
• Hardware
• Software
Produto Server GPA Server PoC
Weblogic Server 10.3.1 10.3.1
OTM 6.1 6.1
Database Server 11gR2 11gR2
JVM Software 1.6 JRockit 1.6 JRockit
SO Software Oracle Linux 5.5 Oracle Linux 5.5
Server Server GPA Server PoC
Application Tier
Intel Linux - 2 x 2 Intel quad core 64 GB (cluster) - 1 x 16 cores 64 GB (fail over)
Exalogic Half Rack - 4 Compute Nodes HA setup - Used just 1 Compute Node*
* 1 Compute Node = 2 Intel 6 cores 96 GB
Database Tier Exadata Quarter Rack - 2 Db Nodes HA
Exadata Quarter Rack - 2 Db Nodes HA
20 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Results
Date Bulk Plan ID Orders Shipments Total Time
22/11/2011 - 08h54m 20111122-0001 3,512 156 5 minutes
21/11/2011 - 19h17m 20111121-0007 5,114 215 9 minutes
22/11/2011 - 11h55m 20111122-0004 10,028 392 22 minutes
22/11/2011 – 20h10m 20111122-0006 15,342 565 32 minutes
• Bulk Plan Order Release : To Buy Side Shipments
Reference from PROD
Orders 6,000
Shipments 250
Total Time 20 minutes
21 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Agenda
• Internal Exa-data/Exa-logic Certification Testing • Customer Exa-data/Exa-logic POC • Other Performance Activities • Performance Testing Advice
22 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Other Performance Activities
• UI Benchmark on Sun OEL – Goal: Prove linear scalability on web tier for UI processing – Result: Achieved linear scalability, response degraded after 300 auto
users, linearity returned by adding a second web server – Other benefits: identified and corrected some single threaded web
functions
• Order XML Benchmark on Sun OEL – Goal: Process XML integration through order creation in 1 sec per – Result: 16 orders / second (24 orders / second scaled) – Other benefits: Provided new data queue feature in 6.2
23 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Other Performance Activities (Continued)
• Client Integration prepare for Go-Live – Goal: Process 200,000+ i_transmissions per hour – Result: 230,000+ achieved (limited by sending system) – Other Benefits: Improved Object Locking, lessons learned re database
contention and ways to alleviate
24 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Agenda
• Internal Exa-data/Exa-logic Certification Testing • Customer Exa-data/Exa-logic POC • Other Performance Activities • Performance Testing Advice
25 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Performance Testing Advice
• Types of Performance Testing – Load Testing – 1x, 2x, – Stress Testing – Extreme Load, Testing for Breakage, not
Performance – Endurance Testing – Sustained Volume w/ Consistent
Performance – Spike Testing – Peak Volume (# users, transactions, etc.)
26 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Performance Testing Advice
• Follow a Methodical Process – Ramp up Tests Starting from a Point of Success – Increase Volume to Failure Point – Tune to Address Failure Point – Repeat
27 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Performance Testing Advice
• What to Monitor – CPU, Memory Utilization on all tiers – OTM Diagnostic Servlets
• Event Diag • Cache Diag
– Database AWR/ADDM Reports
• Note: What to Collect When Performance Problems Start to Exist in OTM? (Doc ID 887885.1)
28 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Performance Testing Advice
• Tuning Options – Planning Parameters – Data Cache Sizes – OTM Event Threads – JVM Memory – Number of CPUs – Database: Queries, Indexes, Init.ora Params – Servers (Web, App, DB RAC)
29 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Performance Testing Advice
• Common Mistakes – Failure to monitor all systems, including upstream and
downstream servers – Jumping to solutions, rather than analyzing data – Not leaving enough time to address issues – Using unrealistic test data – Throttling test w/ too much wait time
30 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
Performance Testing Advice
• Sustaining Performance – Create a Baseline for Comparison – Compute DB Statistics Regularly – Purge/Archive Unnecessary Data – Institute a Change Control Process
31 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.
32 Copyright © 2012, Oracle and/or its affiliates. All rights reserved.