+ All Categories
Home > Documents > Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2...

Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2...

Date post: 28-Jun-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
33
Realizing the Potential for Profitable Investment in Africa Férid Nandjee Managing Director Azito Energie Paper presented at the high-level seminar: Realizing the Potential for Profitable Investment in Africa Organized by the IMF Institute and the Joint Africa Institute Tunis, Tunisia, February 28 – March 1, 2006 The views expressed in this paper are those of the author(s) only, and the presence of them, or of links to them, on the IMF website does not imply that the IMF, its Executive Board, or its management endorses or shares the views expressed in the paper. R EALIZINGTHE P OTENTIALFOR P ROFITABLE I NVESTMENTIN A FRICA High-Level Seminar organized by the IMF Institute and the Joint Africa Institute T T U U N N I I S S , , T T U U N N I I S S I I A A, , F F E E B B R R U U A A R R Y Y2 2 8 8M MA A R R C C H H1 1 , , 2 2 0 0 0 0 6 6
Transcript
Page 1: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

Realizing the Potential for Profitable Investment in Africa

Férid Nandjee Managing Director

Azito Energie

Paper presented at the high-level seminar: Realizing the Potential for Profitable Investment in Africa Organized by the IMF Institute and the Joint Africa Institute Tunis, Tunisia, February 28 – March 1, 2006

The views expressed in this paper are those of the author(s) only, and the presence of them, or of links to them, on the IMF website does not imply that the IMF, its Executive Board, or its management endorses or shares the views expressed in the paper.

RREEAALLIIZZIINNGG TTHHEE PPOOTTEENNTTIIAALL FFOORR PPRROOFFIITTAABBLLEE IINNVVEESSTTMMEENNTT IINN AAFFRRIICCAA High-Level Seminar organized by the IMF Institute and the Joint Africa Institute

TTUUNNIISS,,TTUUNNIISSIIAA,,FFEEBBRRUUAARRYY2288––MMAARRCCHH11,,22000066

Page 2: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

1st March, 2006 présentation ABB CI 1

The AZITO ProjectA model of A model of independentindependent power production power production (B.O.O.T.) (B.O.O.T.) andand ofof publicpublic--privateprivate partnershippartnership

in subin sub--sahariansaharian AfricaAfrica

Seminar on « Realizing the Potential for Profitable Investment in Africa »Tunis, 28th February-1st March 2006

Férid Nandjee, Managing Director AZITO ENERGIE

Page 3: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 2

Summary1. Introduction1. Introduction

BOOT concept and project financingBOOT concept and project financingapproach from a developer for a BOOT projectapproach from a developer for a BOOT project

2. Context and specificities of the project2. Context and specificities of the projectObjectives of the projectObjectives of the projectThe Ivorian electricity sector and the position of The Ivorian electricity sector and the position of AzitoAzitoSchedule of the projectSchedule of the projectThe projectThe project

3. The contractual and financial structure3. The contractual and financial structureThe contractual structureThe contractual structureThe financial structureThe financial structure

4. The risks analysis 4. The risks analysis 5. Few milestones of the project construction5. Few milestones of the project construction6. Operation experience6. Operation experience7. Lessons of experience7. Lessons of experience

Page 4: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 3

1. INTRODUCTION

BOOT CONCEPT AND PROJECT FINANCINGBOOT CONCEPT AND PROJECT FINANCING

APPROACH FROM A APPROACH FROM A «« DEVELOPERDEVELOPER »» FOR A FOR A BOOT PROJECTBOOT PROJECT

Page 5: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 4

What do B.O.O.T and project financing mean?

Concession given by the Government of a country to a local Concession given by the Government of a country to a local private company in order to build, finance, operate and eventuaprivate company in order to build, finance, operate and eventually lly transfer to the host country, infrastructure projects (energy, transfer to the host country, infrastructure projects (energy, telecom, water, etc.)telecom, water, etc.)B.O.O.T. Concept (Build, Own, Operate, Transfer)B.O.O.T. Concept (Build, Own, Operate, Transfer)The loans are subscribed by the Project Company only, without The loans are subscribed by the Project Company only, without any corporate guarantee from the sponsors (non recourse or any corporate guarantee from the sponsors (non recourse or limited recourse financing)limited recourse financing)The debt service is therefore only paid by the cash flows The debt service is therefore only paid by the cash flows generated by the Project Companygenerated by the Project CompanyThus it is absolutely necessary to:Thus it is absolutely necessary to:

analyze the fundamentals of the project and its economic analyze the fundamentals of the project and its economic justificationjustificationidentify the risks and transfer them from the Project Company toidentify the risks and transfer them from the Project Company to the the other Project participantsother Project participantsHave a wellHave a well--designed, secure and balanced partnership between the designed, secure and balanced partnership between the public and private sectorpublic and private sector

Page 6: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 5

The approach from a « developer »

(Good partnership)(Good partnership)If yes, how has been the If yes, how has been the partnership between public partnership between public and private sector?and private sector?

((BNETD BNETD –– strong strong commitment from the commitment from the government)government)

Leadership engaged at the Leadership engaged at the government level?government level?

(yes, and the company (yes, and the company is private managed)is private managed)

Is the electricity production, Is the electricity production, transmission and transmission and distribution company distribution company interested in the project?interested in the project?

(a BOOT project already (a BOOT project already financed)financed)

Is there a precedent?Is there a precedent?

Is the project realistic? Is the project realistic?

Page 7: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 6

The approach from a « developer »

(all (all thethe necessarynecessaryresourcesresources are are availableavailable = = EPC/ O&M/ transmission EPC/ O&M/ transmission lineslines / / developmentdevelopment / / investmentinvestment / / insuranceinsurance/ / financialfinancial adviceadvice))

OtherOther advantagesadvantages ??

((yesyes, , veryvery active active sincesinceseveralseveral yearsyears))

EPC EPC contractorcontractorengagedengaged??

Are Are wewe competitivecompetitive??

((goodgood local local partnerpartner: IPS : IPS (West (West AfricaAfrica), a ), a subsidiarysubsidiaryofof AKFEDAKFED

Can Can wewe findfind solidsolidpartnerspartners??

((strongstrong representationrepresentation of of ABB in Côte dABB in Côte d’’Ivoire)Ivoire)

Our local Our local organizationorganization??

Do Do wewe have a local have a local presencepresence??

Page 8: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 7

2. THE CONTEXT AND SPECIFICITIES OF THE PROJECT

OBJECTIVES OF THE AZITO PROJECT OBJECTIVES OF THE AZITO PROJECT

THE IVORIAN ELECTRICITY SECTOR THE IVORIAN ELECTRICITY SECTOR AND POSITION OF AZITOAND POSITION OF AZITO

SCHEDULE OF THE PROJECTSCHEDULE OF THE PROJECT

THE PROJECTTHE PROJECT

Page 9: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 8

Objectives of the AZITO Project

Respond to the energy demand growthRespond to the energy demand growth

Use national natural gasUse national natural gas

Export electric energy in the subExport electric energy in the sub--regionregion

Page 10: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 9

The electricity sector in Côte d’Ivoireand position of Azito

19951997

19992001

2003

AZITO 3 AZITO 3 AZITO 3 AZITO 3 AZITO 3 AZITO 3 AZITO 3 AZITO 3 AZITO 3 AZITO 3 AZITO 3 AZITO 3

0

1000

2000

3000

4000

5000

6000

7000

AZITO 2AZITO 2AZITO 2AZITO 2AZITO 2AZITO 2AZITO 2AZITO 2AZITO 2AZITO 2AZITO 2AZITO 2

AZITO 1

Private Supply

Public Supply

GWh

Page 11: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 10

Schedule of the Project

•• International bidInternational bid•• Offers SubmissionOffers Submission•• Notification of the WinnerNotification of the Winner•• Signature of the Concession AgreementSignature of the Concession Agreement•• Beginning of the constructionBeginning of the construction•• Financial ClosingFinancial Closing•• Gas Turbine 1 operation (1st turbine)Gas Turbine 1 operation (1st turbine)•• Gas Turbine 2 operation (2nd turbine)Gas Turbine 2 operation (2nd turbine)

October 1996October 1996April 1997April 1997June 1997June 1997

Sept. 1997Sept. 1997--July 1998July 1998July 1998July 1998

February 1999February 1999January/March 1999January/March 1999

February 2000February 2000

Exceptional time schedule• for the financing of the project (June 1997 - February 1999)• for the completion of Phase 1 (GT1) (July 1998 - January 1999)• thanks to the strong partnership between all the government’s organization, the project company, the contractors and the sponsors

Page 12: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 11

The Project: Description

SiteSite:: AzitoAzito Village, Republic of Côte dVillage, Republic of Côte d’’Ivoire, near Ivoire, near EbriEbriéé lagoon, west side of Abidjan lagoon, west side of Abidjan Power PlantPower Plant:: 2 x 150 MW Gas turbines (ALSTOM GT 2 x 150 MW Gas turbines (ALSTOM GT 13E2) built on a turnkey basis (EPC contract).13E2) built on a turnkey basis (EPC contract).Energy Evacuation contractEnergy Evacuation contract:: A 225 kV Switchyard at A 225 kV Switchyard at AzitoAzito, an extension of the existing , an extension of the existing AboboAbobo switchyard switchyard and a 225 kV double circuit overhead transmission and a 225 kV double circuit overhead transmission line from line from AzitoAzito to to AboboAbobo (17 km) on a turnkey basis.(17 km) on a turnkey basis.

Page 13: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 12

The Project: Environmental and social aspects

The The AzitoAzito power plant was built in accordance with the power plant was built in accordance with the environmental guidelinesenvironmental guidelines

of the Ivorian lawof the Ivorian lawof the World Bankof the World Bank

Atmospheric emissions continuously measured at the Atmospheric emissions continuously measured at the stacks and noise levels are below the limit valuesstacks and noise levels are below the limit values

Triple certification (Quality, Security and Environment) Triple certification (Quality, Security and Environment) obtained by the Operator in 2004obtained by the Operator in 2004

Social impact of the project (employment during Social impact of the project (employment during construction, building of infrastructures in the construction, building of infrastructures in the AzitoAzito village village and continuous relationships kept with and continuous relationships kept with AzitoAzito villagers by villagers by having a social committee comprising of all the operators having a social committee comprising of all the operators present on the site)present on the site)

Page 14: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 13

3. THE CONTRACTUAL AND FINANCIAL STRUCTURE

THE CONTRACTUAL STRUCTURETHE CONTRACTUAL STRUCTURE

THE FINANCIAL STRUCTURE THE FINANCIAL STRUCTURE

Page 15: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 14

Concession Agreement (1/2)

Parties: Government of Côte dParties: Government of Côte d’’Ivoire (GOCI) & Ivoire (GOCI) & AzitoAzito EnergieEnergieDuration: 24 years, including the construction periodDuration: 24 years, including the construction periodObligations of Obligations of AzitoAzito EnergieEnergie ::

Respect of technical specifications (capacity, heat rate...)Respect of technical specifications (capacity, heat rate...)Commercial Operation of the Power plant at a fix dateCommercial Operation of the Power plant at a fix dateProvision to State of capacity and energy production Provision to State of capacity and energy production

Obligations of Government :Obligations of Government :Buy the energy on a "Take or Pay" basis (CIE)Buy the energy on a "Take or Pay" basis (CIE)““classicalclassical”” tariff formula:tariff formula:

Capacity charges componentsCapacity charges componentsEnergy charges componentEnergy charges component

Supply the gasSupply the gas

Page 16: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 15

Concession Agreement (2/2)

In case of problem:In case of problem:Details the events of defaults from Details the events of defaults from AzitoAzito EnergieEnergie / State/ StateDetails the Details the ““Force Force MajeureMajeure”” EventsEventsPossibilities of Possibilities of ““remedy"remedy"Possibilities of terminationPossibilities of terminationFinancial Treatment of terminationFinancial Treatment of termination

Miscellaneous Stipulations:Miscellaneous Stipulations:Insurance ObligationsInsurance ObligationsStabilization of fiscal taxes / "change in law"Stabilization of fiscal taxes / "change in law"Reserve account to be constituted by State (3 months)Reserve account to be constituted by State (3 months)““StepStep--inin”” rights for the Lendersrights for the Lenders

Page 17: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 16

Substation and Transmission LinesTurnkey Contract: “CCEM Contract”

Parties : Government of Côte dParties : Government of Côte d’’IvoireIvoire & & AzitoAzitoEnergieEnergieConcerns :Concerns :

Unit 1 : AZITO subUnit 1 : AZITO sub--station station and tieand tie--in on existing 225 kV linein on existing 225 kV lineUnit 2 : new 225 kV double circuit overhead Unit 2 : new 225 kV double circuit overhead transmission linetransmission line AzitoAzito--AboboAbobo, extension of , extension of AboboAbobo subsub--stationstation

General Principle : Turnkey Contract General Principle : Turnkey Contract Payments : Fix monthly amounts until Payments : Fix monthly amounts until December, 2010December, 2010

Page 18: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 17

Structure of the Azito Project

Shareholders• Cinergy Holding Company

(ABB EV + EDF)• Azito Energie Holding

(IPS + AKFED)• Globeleq

Government of Côte d’Ivoire

IFC A

IFC B

CDC Club

Société Générale

World Bank (IDA Partial Risk Guarantee)

IBRD

SociétéGénérale

CDC

DEG

FMO

AFDB

IFC

CDC

IFC

DEG

SeniorDebt

ConvertibleDebt

Non-Convertible Debt

Subordinated Debt

Contract for energyevacuation grid

Concession Agreement

100%

ABB EVEDF I

EPC Power Plant Consortium

Substation + Lines

EPC Consortium

O&M Contract

EPC Lot 1Contract

EPC Lot 2Contract

Azito Lenders

Letter of comfort

Page 19: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 18

Partial Risk Guarantee from IDA

Guarantees the PRG commercial loan (30 M.USD) against Guarantees the PRG commercial loan (30 M.USD) against payment defaults due to a default of the State (/CIE) payment defaults due to a default of the State (/CIE) visvis a a visvis AzitoAzito EnergieEnergie under the Concession Agreement (or the under the Concession Agreement (or the CCEM). In particular:CCEM). In particular:

-- Payment default of CIE / State on the amounts due Payment default of CIE / State on the amounts due under the concession agreement (monthly payments, under the concession agreement (monthly payments, termination payment)termination payment)

-- Nationalization, expropriation, transfer / convertibilityNationalization, expropriation, transfer / convertibility

Exclusions:Exclusions:Default of the Project Company (Default of the Project Company (““commercial riskcommercial risk””))““NaturalNatural”” Force Force MajeureMajeure (insurable)(insurable)

Page 20: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 19

Total cost of Azito Project:223 million US dollars

CDC Club loan

IFC B loan

IFC

IDA PRG loan

IFC A loan

Shareholders

68

3248

15

3030

Commercial LoansSociété GénéraleEuropean Commercial Banks

ABB/IPS/EDF/GLOBELEQ

subordinated debt

CDC/FMO/DEG/AfDB

Page 21: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 20

4. THE RISKS ANALYSIS

Page 22: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 21

Main risks

Construction riskConstruction riskConstruction DelayConstruction DelayOver Budget Over Budget

Operation riskOperation riskTechnical problems / technologyTechnical problems / technologyOver Budget Over Budget

Market riskMarket risk

Payment by CIE / StatePayment by CIE / State

Gas supplyGas supply

Exchange rate / Money TransferExchange rate / Money Transfer

Institutional risk/change in sector Institutional risk/change in sector organisationorganisation

Page 23: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 22

5. MILESTONES OF THE CONSTRUCTION

Page 24: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 23

Main milestones during construction of the Azito Power Plant

End of July, 1998 :Site leveling and civil works

January 15th, 1999 :

Phase 1 completedPhase 2 in construction

September 19th, 1998:

Arrival of gas turbine (340 tons) and generator (225

tons) of Phase 1 on the Azitosite

May 7th, 1999:

Arrival of the second turbine and

generator

February 2000

both 150 MW turbines are in operation

December 16th, 1998:Energizing of Azitoswitchyard and tie-in existing transmission line

Page 25: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 24

6. OPERATION EXPERIENCE

Page 26: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 25

Operation experience 1999-2005

Global country difficult situation since 2000Global country difficult situation since 2000Stressed financial situation of the electricity sector (2000Stressed financial situation of the electricity sector (2000--2005) but priority payment to the independent energy and 2005) but priority payment to the independent energy and gas producersgas producersA set of measures have been taken into account to ensure A set of measures have been taken into account to ensure the financial equilibrium of the electricity sector (in CIE the financial equilibrium of the electricity sector (in CIE concession contract renewal on October, 2005)concession contract renewal on October, 2005)

=>But=>But…… so far, no direct material impact on the Project :so far, no direct material impact on the Project :Plant always continuously operated and even produced Plant always continuously operated and even produced 22’’185 185 GWhGWh in 2005 (highest level)in 2005 (highest level)All the invoices have been paid All the invoices have been paid in fullin full and and on timeon time by the by the State (priority given by the State to support private State (priority given by the State to support private sector)sector)

Page 27: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 26

Operation data: actual capacitycompared to guaranteed capacity

144,

314

8,16

3

284,

829

4,8

279,

429

8,1

277,

929

4,51

1

277,

6

292,

851

277,

6

296,

391

277,

6

295,

076

277,

629

4,47

2

0

50

100

150

200

250

300

1999 2000 2001 2002 2003 2004 2005 2006

guaranteed capacity actual capacity

Page 28: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 27

Operation data: Azito power plant equivalent availability factor (%)

91,58

90

98,28

91

95,63

87,6

95,36

87,6

94,83

87,6

89,96

87,6

95,17

87,6

828486889092949698

100

1999 2000 2001 2002 2003 2004 2005actual availability contractual availability

Page 29: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 28

Operation data: Share of Azito Plant in the country energy production

0

1000

2000

3000

4000

5000

6000

GWh

2000 2001 2002 2003 2004 2005

Azito other producers

48674778 4915

41%

31%

33%

69%

67% 59

%

558053695064

33%

36%

39%

67% 64%

61%

Page 30: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 29

7. AZITO : LESSONS OF EXPERIENCE

Page 31: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 30

AZITO : a successful BOT experience and public-private partnership

As of to date, the most powerful power plant in West Africa As of to date, the most powerful power plant in West Africa (BOOT) (BOOT)

First Infrastructure Project in SubFirst Infrastructure Project in Sub--SaharianSaharian Africa, Africa, mobilizing a long term commercial debt (61 Mio USD on mobilizing a long term commercial debt (61 Mio USD on 10/12 years)10/12 years)

First project in an IDA country to benefit from a PRG (Partial First project in an IDA country to benefit from a PRG (Partial Risk Guarantee) from World BankRisk Guarantee) from World Bank

Project developed with an exceptionally short scheduleProject developed with an exceptionally short scheduleJune 1997June 1997 Consortium ABB / IPS WinnerConsortium ABB / IPS WinnerJanuary/March 1999January/March 1999 1st turbine in operation1st turbine in operationFebruary 2000February 2000 2nd turbine in operation2nd turbine in operation

Good and balanced publicGood and balanced public--private partnership contributed private partnership contributed to the success of the Projectto the success of the Project

Page 32: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

03/01/06 présentation ABB CI 31

Conclusion : What made it possible

Côte dCôte d’’IvoireIvoire’’s situation was better in 1998 when the project s situation was better in 1998 when the project was launchedwas launchedProjectProject’’s fundamentals were sounds fundamentals were sound

pressing need for powerpressing need for powerpower sector well managed and financially balancedpower sector well managed and financially balanced

Côte dCôte d’’Ivoire clearly engaged on the liberalization path and Ivoire clearly engaged on the liberalization path and already familiar with concessions / BOT concepts already familiar with concessions / BOT concepts State of Côte dState of Côte d’’Ivoire, Sponsors and Arrangers highly Ivoire, Sponsors and Arrangers highly committed to the Project (both at top and working level)committed to the Project (both at top and working level)Strong contractual framework (as far as the power sector Strong contractual framework (as far as the power sector and the project itself are concerned) and Strong financing and the project itself are concerned) and Strong financing structure (IDA PRG + IFC B loan)structure (IDA PRG + IFC B loan)

Page 33: Realizing the Potential for Profitable Investment in Africa · 03/01/06 présentation ABB CI 2 Summary 1. Introduction BOOT concept and project financing approach from a developer

1st March, 2006 présentation ABB CI 32

The Azito Project

Seminar on Seminar on ““Realizing the Potential for Realizing the Potential for Profitable Investment in AfricaProfitable Investment in Africa””

Tunis, 28th FebruaryTunis, 28th February--1st March 20061st March 2006


Recommended