©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
Forensics of the Fukushima Dai-ichi Accident
at RIC 2018
Recent Examination Results From Fukushima Dai-ichi
Takashi Hara
Deputy General Manager
Tokyo Electric Power Company Holdings, Washington Office
March 15,2018
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.1
Fukushima Daiichi D&D roadmap phase definition
current statusTarget:commencement
of fuel debris retrieval
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.2
Six Technical Programs at Fukushima Daiichi D&D
Pool Fuel Removal Fuel Debris Retrieval
Contaminated Water Management
Waste Management
On-site land management& Work environment
improvement
Urgent issue Long term issue
Complemental issue
Intermediate targetImmediate target
Waste generation, Fuel Debris storage
Fuel storage
Secondary waste(Sludge, Adsorbent,Storage tank, etc.)
On-site Dose and Dust Control, Area Management
Basic step
Unit 5,6 Decommission
Today’s Presentation Focus Area
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
3
Unit 3: Investigation inside the Primary Containment (July.2017)
The investigation inside the pedestal was conducted using a submersible remotely
operated vehicle in July 2017.
Diagram of the investigation
Basement
Submersible ROV
Control Rod Drive (CRD)replacement rail
Pedestal opening
Platform
Control RodDrive (CRD)housing
Opening (slot)
PCV penetration pipewhere submersibleROV was inserted(X-53 penetration)
PCV accumulatedwater level
Access hatchfor workers
PCV wall surface
Propulsion thruster
Light
Cable
Rear camera
Light
Up and down thruster
Front Camera
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.4
[Ref.] Structures/Components inside Reactor Building
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
5
Unit3: Investigation inside the Primary Containment (July.2017)
A structure that is assumed to be the CR guide tube was found near the CRD housing.
Melted objects solidified and are attached to the CRD housing brackets.
Photograph area A3 <Camera angle:Upward> Photograph area A4 <Camera angle:Horizontal
RPV center
Platform
Pedestal
180°
Photograph area A3
90°
CRD railCylindrical structure(assumed to be CR guide tube)
Melted objects that have solidified.
0°
270°
Photograph area A4
CRD housing bracket support bar.
CRD housing flange
<Camera angle:All Upward>
CRD housing brackets before the accident(Unit 3)
CRD housing bracketsupport bar
PIP cable
CRD housing brackethangar rod
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.6
[Ref.] Structures/Components inside Reactor Pressure Vessel
CR guide tubes
PedestalCRD housing
Control Rods
Reactor Pressure Vessel
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
7
Unit3: Investigation inside the Primary Containment (July.2017)
Disturbances on the water surface at ①~④ suggest the possibility that there is damage
on the periphery of the RPV as well as at the center of the bottom of the RPV.
①
③
②
①
③②
0°
90°
270°
④
Pedestal
180°
④
Platform
CRD rail
Assumed damage at the bottom of the RPV
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
8
Unit3: Investigation inside the Primary Containment (July.2017)
Deposits resembling sand, pebbles and clumps were found.
Access hatch was not visible. (Deposits were found nearby)
Lower part inside pedestal
Deposit(granular)
Photograph area C1<Camera angle:Downward>
Photograph area C2<Camera angle:Horizontal>
Photograph area C4<Camera angle:Downward>
Fallen object 0°
Photograph area C3<Camera angle:Upward>
Clump deposit Direction toward the Access hatch for workers
DepositClump deposit
Photograph
area C5
Photograph area C4
Photograph area C2
Photograph area C1
Deposit(pebble form)
90°
Access hatch for workers
180°
270°
Circling rail bracket
Platform frame
Photograph area C5 <Camera angle:Downward>
Grating
Photograph
area C3
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
9
Photograph area C2<Camera angle:Horizontal>
Fallen object
Grating
[Ref.] Control rod falling speed limiter
This fallen object could not be identified for certain since the unique umbrella-
shaped part of the structure could not be found.
However some characteristics shape and estimated dimension are very similar to
control rod falling speed limiter.
Slit
Rollershape
Assumed to be a socket
・Control rod falling speed limiter
In case of an accident involving a control rod drop, this part generates resistance thereby slowing the
increase in speed of the fall and preventing drastic reactivity level changes inside the reactor.
Deposit
CR falling speed limiter
Slit
RollerControl Rod
Direction of the core=CR insertion direction
Directionof falling CR
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
The area underneath the platform, where fuel debris may exist, was investigated.
Telescopic device , which has a hanging mechanism with camera, dosimeter and
thermometer, was used.
CRD
X-6Opening
CRD replacement
railOpening of Pedestal
PCV
RPV
Pedestal
X-6Opening
10
Area whereequipment waslowered duringthis investigation
PlatformAlternative
shield
Isolation
valvePedestal
Control Rod Drive
Extendableconcentriccylinders withdifferentdiameters
Tip bendcontrol box
Guide pipe
(Φ110mm)
Cabledrum
PCV penetration
pipe (X-6
penetration)
Lower part of CRD
Cable Feed Machinery Cable
OverheadCamera
Investigate Unit
Pan Tilt Camera ,Light
Telescopic investigation device
Platform
Unit2: Investigation inside the Primary Containment (Jan.2018)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.11
Worker access
opening
Bottom of
pedestal
垂直断面図
Telescoping
investigation device
CRD housing
Fallen
grating ①
Fallen
grating②(no holes)
CRD rails
No holes
Middle work
platform
Cable tray
CRD replacement
mechanism
Platform
Area that the
investigation unit
accessed during
this investigation
[Ref.] PCV Internal investigation location
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
12
Fuel assemblycomponent
Unit2: Investigation inside the Primary Containment (Jan.2018)
Photos provided by: IRID
Platform
CRD housing
Fallengrating①
CRD rails
Worker access openingBottom of the pedestal
Cable tray
No Holes
Middle work platform
Telescopic investigation device
No Holes
Fallengrating②
CRD replacementmechanism
The entire bottom of the pedestal was found
to be covered with sandy and clay-like
deposits.
Some fuel assembly components have fallen
to the bottom of the pedestal and deposits
thought to be fuel debris were found in the
vicinity of these fallen components.
Affixed deposits.
Fallen Object
Deposits.
Inner wall of pedestal.
Sandy deposits.
Tie Plate
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
13
Unit2: Investigation inside the Primary Containment (Jan.2018)
Platform
CRD housing
Fallengrating①
CRD rails
Worker access openingBottom of the pedestal
Cable tray
No Holes
Middle work platform
Telescopic investigation device
No Holes
Fallengrating②
CRD replacementmechanism
Inner wall of pedestal
No significant damage was seen on the
inner wall of pedestal.
No significant damage was seen to existing
structures inside the pedestal (CRD
replacement mechanism).
Near the worker access opening (estimated)
CRD replacement mechanism
CRD housing support fitting support bar
CRD housing support fitting hanger rod
PIP cable
Photos provided by :IRID
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
14
Unit2: Investigation inside the Primary Containment (Jan.2018)
Worker access opening
Bottom of pedestal
垂直断面図
Telescoping investigation device
CRD housing
CRD rails
Middleworkplatform
Cabletray
CRDreplacement mechanism
Platform
Measurement point a
Measurement point b
Measurement point c
Measurement point d
Approx. 0.3m
Approx. 0.4m
Approx. 1.0m
Approx. 0.6m
Platformtop
Bottom surface ofpedestal
Approx. 3.2m
Fallen grating①
Fallen grating②
Dose and temperature were
approximately the same regardless
of the height at which measurements
were taken.
And, dose rates tended to be higher
outside the pedestal than inside.
Measurement
point
Dose rate*1,2
(Gy/h)
Temp.*2
(℃)
a 7 21.0
b 8 21.0
c 8 21.0
d 8 21.0
【Reference ; Outside the pedestal*3】
Dose rate: Max. 42 [Gy/h]
Temp.:Max. 21.1[℃]
※1:Calibrated with Cs-137 radiation source※2:Error: Dosimeter: ±7%
Temp. Gauge: ±0.5℃※3:Reference value because the measurement
equipment is housed inside the survey unit
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
15
[Ref.] Reference dose rate measurement locations
Reference measurement location (this investigation) ※1
2017 investigation measurement location (estimated from camera screen static)
2017 investigation measurement location (calculated usingintegral dosimeter
19Gy/h
Measurement location (this investigation) ※1:Reference value because the measurementequipment is housed inside the survey unit
Less than approx. 10Gy/h
ScaffoldingApprox. 70Gy/h
Approx. 80Gy/h
Approx. 70Gy/h
Less than approx. 10Gy/h
PCV
X-6 penetration
Approx. 0.7m
CRD rails
Pedestal
Platform
Lifting beam
7Gy/h (Measurement
point a)
7Gy/h(Fallen grating ① top)
7Gy/h(Fallen grating ② top)
CRD housing
15Gy/h
Approx. 6.8m
Approx. 0.9m Approx. 0.9m
28Gy/h42Gy/h
Approx. 2.6m Approx. 1.2m
Approx. 0.4m
20Gy/h
Dose rates tended to be higher
outside the pedestal than
inside.
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
16
[Ref.] Data/Information obtained (Reactor Building) (1/2)
Data/Information obtained through D&D
activities (R/B)
Potential insights
1 Photos/videos of damaged walls and structures
(1F1,1F3 and 1F4)
Seismic integrity, Characteristic
of hydrogen explosion
2 Radiation dose surveys in Reactor Bldg. (1F1,
1F2, and 1F3)
Characteristic of contamination,
FP transport into Bldg, Potential
leakage path e.g. pipe
penetration seal or containment
top head seal. Potential damage
by exposure to harsh
environment.
3 Radiation dose surveys around DW Concrete
Shield in Refueling floor. (1F1, 1F2, and 1F3)
4 Isotopic evaluations of obtained samples from
Reactor Bldg. e.g. floor concrete, building
debris, etc. (1F1,2,3)
5 Observations of water leakage and
Photos/videos at appropriate locations near
identified leakage points (1F1,2,3)
e.g. 1F1 (vacuum breaker, sand cushion drain),
1F3 PCV leakage points (bellows of Main
Steam pipe penetrations)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
17
[Ref.] Data/Information obtained (Reactor Building) (2/2)
Data/Information obtained through D&D
activities (R/B)
Potential insights
6 Photos/videos and radiation dose surveys on
containment hardpipe venting pathway,
standby gas treatment system and associated
reactor building ventilation system
(1F1-4)
Behavior of wetwell venting gas
flow, back flow via SGTS, inter-
unit back flow via shared
exhaust stack.
7 Examinations of 1F1 RCW (Closed Cooling
Water system) surge tank; water level and
radiation dose measurements.
FP transport via RCW line due to
molten core interaction in the
sump in DW floor.
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
18
[Ref.] Data/Information obtained (PCV)
Data/Information obtained through D&D
activities (PCV)
Potential insights
1 Ex-vessel inspections and operability
assessments of in-vessel and ex-vessel
sensors and sensor support structures (1F1-3)
Sensor availability under harsh
environment during Severe
Accident and post-SA
monitoring strategy.
2 Photos/videos of PC coatings (1F1-3, so far
only DW inside wall)
Characteristic of PC coating
exposed to harsh environment.
3 Radiation dose surveys in PCV (1F1-3) Characteristic of contamination,
FP transport in PCV.
4 Photos/videos of TIP tubes and SRV/IRM
tubes outside the RPV (so far 1F2, 3)
In-vessel and Ex-vessel core
melt progression.
5 Isotopic evaluations of samples of water, mud,
sand from DW, as well as water samples from
outside of PCV (1F1-3)
Characteristic of FP transport in
PCV. Long term FP and water
chemistry.
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
19
[Ref.] Data/Information obtained (RPV)
Data/Information obtained through D&D
activities (RPV)
Potential insights
1 Remote mapping of core through shroud wall
from annular gap region (muon tomography)
(1F1-3)
Rough image of fuel debris
distribution.
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.
20
[Ref.] Links of Data/Information from TEPCO and Japan webpages
TEPCO Holdings Webpages
Decommissioning Plan of Fukushima Daiichi Nuclear Plant (main Fukushima Daiichi D&D
website, photos and video)
http://www.tepco.co.jp/en/decommision/index-e.html
TEPCO’s News Room (prompt reports, handouts at press conferences)
http://www.tepco.co.jp/en/decommision/news/index-e.html
The Council for the Decommissioning of TEPCO's Fukushima Daiichi Nuclear Power
Plant(updated monthly)
http://www.tepco.co.jp/en/nu/fukushima-np/roadmap/conference-e.html
Progress Report on the Investigation and Examination of Unconfirmed and Unresolved Issues on
the Development Mechanism of the Fukushima Daiichi Nuclear Accident (last update; coming
soon: Update No. 5 in English)
http://www.tepco.co.jp/en/press/corp-com/release/2015/1264602_6844.html
Other Japan Webpages
The Mid and Long Term Roadmap towards the Decommissioning of TEPCO's Fukushima Daiichi
Nuclear Power Station (updated non-regularly)
http://www.meti.go.jp/english/earthquake/nuclear/decommissioning/pdf/20170926_01a.pdf
Technical Strategic Plan 2017 for Decommissioning of the Fukushima Daiichi Nuclear Power
Station of Tokyo Electric Power Company Holdings, Inc (updated annually)
http://www.dd.ndf.go.jp/en/strategic-plan/index2017.html
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.6
Thank you for your
kind attention