+ All Categories
Home > Documents > Regional Connector Transit Corridor - Metro · Regional Connector Transit Corridor ... •...

Regional Connector Transit Corridor - Metro · Regional Connector Transit Corridor ... •...

Date post: 17-May-2018
Category:
Upload: trinhhanh
View: 220 times
Download: 0 times
Share this document with a friend
39
Regional Connector Transit Corridor Community Construction Update March 25, 2015-Little Tokyo Branch Library
Transcript

Regional Connector Transit Corridor Community Construction Update March 25, 2015-Little Tokyo Branch Library

• Project Overview

• Regional Connector Community Leadership Council

• Advanced Utility Relocation Update and Look-Ahead

• Design-Build Update and Look-Ahead

• Tree Removal and Replacement Overview

• Eat, Shop, Play

• Questions & Answers

Tonight’s Agenda

Project Overview

• Advanced utility relocation contractor started work February 2014

• Design/Build contractor: Skanska Traylor Bros. Joint Venture, Regional Connector Constructors (RCC):

Metro Board Approval: April 24, 2014

Notice to Proceed on July 7, 2014

Project Overview

1.9 mile underground light rail connecting the Metro Gold Line at 1st St/Alameda to 7th St/Metro Center.

3 underground stations:

• 1st St/Central Av

• 2nd St/Broadway

• 2nd Pl/Hope St

Connects Metro Gold Line, Metro Blue Line, and Expo Line

One seat ride from Azusa to Long Beach and East LA to Santa Monica

Project Overview

Project Overview

> Bulleted copy.

> Bulleted copy.

> An eight member advisory body appointed by Metro and divided by station area

> Provides community-based input to Metro, including feedback on the project's design, construction, and safe operation

> Liaison to a wider group of alignment stakeholders

> Advise and partner with Metro on actions necessary to implement the Mitigation Monitoring and Reporting Plan

> Involvement opportunities

Community Leadership Council (CLC)

Utility Relocation Construction Updates

Typical cross-section of underground utilities

Completed construction activities

• Power utility line relocation:

1st St/ Central Av

2nd Pl/Hope St

• LADWP power cutover, intercept, and cable work:

2nd Pl/Hope St

Flower St between 4th and 5th Sts

1st/Alameda

Advanced Utility Relocation Update

Images from 2nd

St vault installation

Completed construction activities

• Southern California Gas utility line relocation:

2nd Pl/Hope St

Flower St/Financial District

2nd St/Broadway

• AT&T: Flower St/Financial District & 1st/Central

• Time Warner Cable: 2nd/Broadway & 5th and Flower St

• MCI: Flower St/Financial District

• Level 3: Flower St/Financial District

3rd Party Utility Relocation Update

Utility Relocation Update

Current/ongoing construction activities:

• Power utility line relocation: 2nd St/Broadway

Flower St/Financial District

• Water utility line relocation: 1st St/Central Av

Flower St/Financial District

• LADWP Power cutover, intercept and cable work: Flower St/Financial District

• Installation of temporary water line by-pass: Flower St/Financial District

• Telecommunication cable pulling and splicing work: 1st St/Central Av

2nd St/Broadway

Flower St/Financial District

Upcoming construction activities

• Water utility line relocation: 2nd St/Broadway (anticipated Summer 2015)

• Storm drain utility line relocation: 1st St/Central Av (anticipated Spring 2015)

2nd St/Broadway (anticipated Spring 2015)

Flower St/Financial District (anticipated Fall 2015)

• LADWP Power cutover, intercept, and cable work: 2nd St/Broadway (anticipated April 2015)

Flower St between 5th and 6th (anticipated Spring 2015)

• Sewer utility line relocation: 1st St/Central Av (anticipated Summer 2015)

Utility Relocation Update

A construction worker drives a backhoe loader to excavate a trench on Hope St at 2nd St in preparation for LADWP utility relocation; another worker acts as a flagger to ensure safety.

Relocating utilities is a delicate process, requiring workers to work in deep and very tight places

Design Builder, RCC, Construction Updates

• Will be used throughout design-build construction

• Reconfiguration of mangrove parking facility

• Exploratory potholing

• Construction of electrical substation

• Installation of utility lines

• Installation of trailers

• Pile installation (location of tunnel boring machine pit)

Mangrove Yard Staging Site 1st St/Alameda St

> Bulleted copy.

> Bulleted copy.

Construction Staging – Mangrove Site

Ala

med

a S

treet

Ala

me

da S

treet

TBM

launch/

Insert

TBM

begins

• Pre-construction CCTV inspection of underground sewer and storm drain lines

• Acoustic leak detection testing of existing water mains

• Demolition of buildings at future 1st St/Central Av Station

• Metro begins mobilization of station staging yard

• Final project design in progress

1st St/Central Av Station What’s Happened So Far

Worker utilizes a hydrovac to carefully survey underground utilities on Central Av in preparation for the future 1st St/Central Av Station.

1st St/Central Av Station What’s Happened So Far

• Geotechnical investigation and vibration testing

• Pre-construction surveys

• Exploratory potholing at 1st St/Central Av station

• Pre-trenching work in preparation for pile installation (April 1, 2015)

• Installation of new 24” storm drain (April 6, 2015)

• Roadway widening of westbound 1st St (Alameda to Vignes) (April 2015)

• Final project design in progress

1st St/Central Av Station What’s Next: 90 Day Look - Ahead

What: • Exploratory trenching to confirm

existing utility locations in preparation for future support of excavation pile installation

Where: • 1st St/Alameda intersection; 1st St

between Central Av and Hewitt St; Alameda St, north and south of 1st St

When: • Wednesday, April 1, 2015

(anticipated start date)

• Work hours 7AM-3:30PM

• Duration: ~10 weeks

1st St/Central Av Station Pre-Trenching for Pile Installation

Traffic Control: • 8 phases

• Lane reductions on Alameda St

• Limited eastbound OR westbound directional closures on 1st St

What: • Roadway widening of westbound

1st St between Alameda St and Vignes St

Where: • Westbound 1st St between

Alameda and Vignes St

When: • Mid-April 2015

• Work hours 7AM-5:30PM

• Duration: 4 weeks

1st St/Central Av Station Westbound 1st St Roadway Widening

Traffic Control: • Installation of K-rail along

westbound 1st St between Alameda and Vignes St.

• Curb lane reduction on westbound 1st St between Alameda and Vignes St.

• K-rail installation will require a one-day westbound directional closure of 1st St between Alameda and Vignes St.

• Sidewalk restrictions

What: • Seven trees will be removed

because they are are in conflict with installation of new utility line and road widening.

Where: • North side of sidewalk on 1st St

between Alameda and Vignes Sts

When: • April 2015 (anticipated start date

pending City of L.A. permit approval)

• Work hours 7AM-4PM

Removal of Trees along Westbound 1st St between Alameda and Vignes Sts

Traffic Control: • Lane closures will be performed

per LADOT approved plans.

Permit Approval: • The Board of Public Works has

scheduled to hear the tree removal request for this location on Friday, March 27, 2015 at 10AM. Location: Los Angeles City Hall 200 N. Spring St, Room 350

Los Angeles, CA 90012

• Geotechnical investigation and vibration testing

• Pre-construction CCTV inspection of underground sewer and storm drain lines

• Acoustic leak detection testing of existing water mains

• Design-Builder (RCC) takes possession of station staging yard

• Exploratory potholing at 2nd St/Broadway station box perimeter began

• Final project design in progress

2nd St/Broadway St Station What’s Happened So Far

• Pre-construction surveys

• Exploratory potholing at 2nd St/Broadway station box perimeter

• Final project design in progress

• 2nd St 5-month Extended Full Closure (anticipated May 2, 2015): MCI telecommunication utility relocation

AT&T telecommunication utility relocation

City of LA storm drain utility relocation

LADWP water line relocation

Pre-trenching work in preparation for pile installation

Supportive of Excavation Pile Installation

Decking

2nd St/Broadway Station What’s Next: 90 Day Look - Ahead

What: • Utility relocations (MCI, AT&T,

LADWP, and storm drain)

• Pre-trenching in preparation for pile installation

• Support of excavation pile installation

• Decking

Where: • 2nd St between Spring St and

Broadway

2nd St/Broadway Station 2nd St 5-month Extended Full Closure

When: • Early May – late September, 2015

• Work hours: Monday through Friday: 7AM-11PM, Saturday: 8AM to 8PM.

• Seeking night variances for weekend closures during decking operations

Traffic Control: • Full closure of 2nd St between Spring St

and Broadway

• Weekend closures of 2nd and Broadway intersection during decking operations

• Geotechnical investigation and vibration testing

• Pre-construction CCTV inspection of underground sewer and storm drain lines

• Acoustic leak detection testing of existing water mains

• Exploratory potholing at 2nd Pl/Hope St station box perimeter began

• Final project design in progress

2nd Pl/Hope St Station What’s Happened So Far

• Pre- construction surveys

• Exploratory potholing at 2nd Pl/Hope St station box perimeter began

• 2nd Pl Bridge demolition

• Final project design in progress

2nd Pl/Hope St Station What’s Next: 90 Day Look - Ahead

• Geotechnical investigation and vibration testing

• Pre-construction CCTV inspection of underground sewer and storm drain lines

• Acoustic leak detection testing of existing water mains

• Utility potholing at Flower St/Financial District to support final design began

• Final project design in progress

Flower St/Financial District What’s Happened So Far

• Pre-construction surveys

• Utility potholing at Flower St/Financial District to support final design

• Utility relocations

• Final project design in progress

Flower St/Financial District What’s Next: 90 Day Look - Ahead

Tree Removal & Replacement Overview

• The Design-Builder retained an arborist and a landscape architect.

• Arborist has evaluated the condition, health, and size of the trees in the alignment.

• A tree mitigation plan has been created and submitted to the City’s Bureau of Street Services/Urban Forestry Division.

• Landscape architect is in the process of drafting the landscaping plan in accordance to City standards.

Overview

Pyrus calleryana on east 2nd St between San Pedro St and Central Av

• Estimated 118 trees need to be removed to support construction in the following locations (this number is based on 60% final design):

> Little Tokyo: approx. 42 trees

> 2nd St/Broadway: approx. 6 trees

> 2nd St/Hope: approx. 46 trees

> Flower St from 4th St to Wilshire Bl: approx. 24 trees

• Trees will be removed based on construction phasing: Spring and Summer 2015.

• Trees will be replaced at a minimum of 2 to 1 ratio.

• Tree replacement is determined through the landscape plan which is currently being prepared for the City.

Tree Removal and Replacement

Project-wide Tree Removal

Project Area

Number to be

Removed Reasons for Removals

Time Frame

of Removal Tree Species to be Removed Common Name

East 1st Street

(east of Alameda St)9

Roadway widening,

utilities excavation April, 2015

Handroanthus Impetiginosus Pink Trumpet

Handroanthus Impetiginosus Pink Trumpet

Prunus Serrulata Japanese Cherry

Persea Americana Avocado

Pyrus Calleryana Callery pear

Prunus serrulata Japanese Cherry

Ficus Microcarpa Indian laurel-leaf fig

Platanus Hispanica, London plane tree

Afrocarpus Falcatus Fern pine

Jacaranda Mimosifolia Jacaranda

Washingtonia Robusta Mexican fan palm

Pinus Canariensis Canary Island pine

Cupaniopsis Anacardioides Carrotwood

Hymenosporum Flavum Sweetshade

Ficus sp. Fig

Jacaranda Mimosifolia Jacaranda

Ficus Microcarpa Indian laurel-leaf fig

Magnolia Graniflora Southern magnolia

Washingtonia Robusta Mexican fan palm

Station excavation May, 2015

2nd St and San Pedro St 12Gorund improvement,

subsurface groutingJune, 2015

1st St and Central Ave

Station21

Flower St 24 utility excavation,

roadway widening

June -

August, 2015

2nd St and Broadway

Station6 Station excavation May, 2015

2nd St and Hope St

Station46

Station excavation,

roadway grade

modifications

May, 2015

• Final Environmental Impact Report (FEIR) outlines required landscape plan.

• Design-Builder will use city requirements and the City’s existing palate to create draft plan.

• Tree species are specifically proposed and approved by the City because of their success growing in the Los Angeles environment.

Landscape Plan Process

Platanus hispanica on

2nd St between Hill St and Main St

• Metro submitted tree removal permit application to Bureau of Street Services/Urban Forestry Division (UFD).

• UFD will submit report to Board of Public Works for approval.

• Tree removal process(for 3 or more trees) requires 30-day posting period to allow for public comment.

• Tree removal notification system

• http://bsspermits.lacity.org/treepostings/

• Trees will be removed based on construction phasing and pending City of Los Angeles permit approval.

City of Los Angeles Tree Removal Process

Conclusion of project-area discounts Introduction of new campaign: • Eat, Shop, Play (details to come) Other business promotional opportunities with Metro Fore more information, see Lily Liang

Metro Business Promotional Opportunities

• Next Construction Update Community Meeting: First week of June 2015

• Meeting venue will rotate along the alignment.

• Regional Connector Leadership Council Station Area Committees meet monthly to discuss station specific issues.

Future Community Meetings

Contact us

www.metro.net/regionalconnector

twitter.com/metroconnector

facebook.com/metroregionalconnector

213.922.7277

[email protected]


Recommended