+ All Categories
Home > Documents > Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams...

Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams...

Date post: 14-Mar-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
15
Rehabilitation of Aging Flood Control Dams Amanda S. Pennington, PE DCR Division of Soil and Water Conservation District Engineering Services Manager Area I JED November 14, 2017
Transcript
Page 1: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Rehabilitation of Aging

Flood Control Dams

Amanda S. Pennington, PE

DCR Division of Soil and Water Conservation

District Engineering Services Manager

Area I JED

November 14, 2017

Page 2: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Where are we now?

• In 2016, the District Dam Rehabilitation

Committee reconvened

• October 31, 2016 an interim report was

submitted to:

– Governor McAuliffe

– Senator Hanger (Co-Chairman, Senate Finance

Committee)

– Senator Norment (Co-Chairman, Senate Finance

Committee)

– Delegate Jones (Chairman, House Appropriations

Committee)

Page 3: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Interim Report

• Outlined the five tasks required to complete a

final report

• Resources needed:

– Staffing

– Funding

• Final report will include:

– Prioritized list of High Hazard Dams in need of

rehabilitation

– Staffing levels/contractors needed to implement dam

rehabilitations

– Estimated cost of rehabilitations

Page 4: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Even the biggest jobs have to

start somewhere!

• First, we need to know what we are

dealing with:

– Virginia has new Probable Maximum

Precipitation (PMP) values

– Most of these 46 dams have not had

Incremental Damage Analysis conducted,

either for reduction in Hazard Classification

or reduction in SDF

Page 5: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

One step at

a time!

Page 6: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Task 1-Evaluate New PMP

values

• Has the PMP for the dam watershed increased

or decreased (or even stayed the same!)?

• How significant in the reduction in PMP?

Page 7: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Task 2-ACER-11 Analysis

• ACER-11 is a Hazard Classification

document published by the Bureau of

Reclamation

• An Incremental Damage Analysis

approach to Hazard Classification

• Not all dams will qualify for this analysis

Page 8: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Task 3-IDA for SDF Reduction

• Virginia Impounding Structure

Regulations allow the use of an

Incremental Damage Analysis for

reduction in SDF

• Would be done concurrently with Task 2

• Not all dams would qualify

Page 9: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Task 4-Dam Prioritization

• Will be done using the Priority Ranking System

for Rehabilitation of Aging Watershed Dams,

developed by the USDA-Natural Resources

Conservation Service

• Considers threat to downstream public

analyzing a number of factors

Page 10: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Task 5-Preliminary Engineering

• Hydraulics and Hydrology

• Alternatives Analysis

• Geotechnical Analysis

• Survey

• Result in 35% design

• Would only be done for the top prioritized

dams, used to get a more accurate cost

estimate

Page 11: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Aren’t Government studies just

a way to kick the can down the

road?

Page 12: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

You could say that, but the

legislature is not in the business

of handing out money, unless

you show a need. And even

then…

Page 13: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

2017 Progress Report

• List of dams reduced from 66 to 63

• Hired Project Manager

– David Warriner, PE

• Hired Modeler

– Aaron Bish, EIT

Page 14: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

2017 Progress Report

• Completed preliminary analysis of new

PMP values

• 9 dams identified as potentially benefitting

from lower PMP values

• 11 dams identified as potentially

benefitting from ACER 11/IDA analysis

• 3 dams are getting new DBIZ studies

Page 15: Rehabilitation of Aging Flood Control Dams · Precipitation (PMP) values –Most of these 46 dams have not had Incremental Damage Analysis conducted, either for reduction in Hazard

Questions?


Recommended