+ All Categories
Home > Documents > Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and...

Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and...

Date post: 28-Jun-2020
Category:
Upload: others
View: 10 times
Download: 1 times
Share this document with a friend
24
Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution Systems and Planning Training for Midwest Public Utility Commissions, January, 16-17, 2018 Joseph H. Eto
Transcript
Page 1: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1

Reliability Metrics and

Reliability Value-Based Planning

Lawrence Berkeley National Laboratory

Distribution Systems and Planning Training

for Midwest Public Utility Commissions January 16-17 2018

Joseph H Eto

January 12 2018 22

Overview of this presentation

Reliability Metrics

Major Events (IEEE Std 1366 definition)

Reliability Value-Based Planning

The Interruption Cost Estimate (ICE) Calculator

Considerations for Reliability Planning Emerging from Recent LBNL

Research

Bibliography

January 12 2018 33

Electricity reliability is measured by the annual average amount of time and frequency that the lights are out

System Average Interruption Duration Index

total duration of sustained customer

interruptions ( 5min each)

------------------------------------------------

number of customers served

SAIDI =

System Average Interruption Frequency Index

frequency of sustained customer

interruptions ( 5min each)

--------------------------------------------

number of customers served

SAIFI =

Customer Average Interruption Duration Index

SAIDI-------------------

SAIFICAIDI =

frequency of momentary customer

interruptions (lt 5min each)

--------------------------------------------

number of customers served

MAIFI =

Momentary Average Interruption Frequency Index

January 12 2018 44

IEEE Standard 1366Investor Owned

Cooperative Municipal

Number of utilities reporting 137 296 117

of US sales by type of utility 51 47 43

SAIDI with Major Events 237 302 115

SAIDI without Major Events 136 159 50

SAIFI with Major Events 14 28 09

SAIFI without Major Events 12 21 07

Information Reported to EIA for 2015

January 12 2018 55

IEEE Standard 1366

First developed in 1998 to define reliability indices amended in 2003 to

add a consistent approach for segmenting Major Event Days (amended

again in 2012 MED definition unchanged)

Uses 25beta to estimate a threshold daily SAIDI Tmed above which a

Major Event Day is identified

◼ Tmed = exp (α+25β)

◼ Beta = log-normal standard deviation

◼ Alpha = log-normal statistical mean

For a normal distribution

◼ Multiplying beta (the standard deviation) by 25 covers 99379 of the

expected observations (assuming a one-sided confidence interval)

◼ For a year of daily observations this translates to an expectation of 23 Major

Event Days per year

But utility daily SAIDI data are not ldquoperfectlyrdquo normally distributed

January 12 2018 66

Daily SAIDI for 5 years (2011-2015)

0000

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

January 12 2018 77

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

200

400

600

800

1000

1200

1400

1600

1800

00 10 20 30 40 50 60 70 80 90 100

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily SAIDI

Frequency

Cumulative

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

50

100

150

200

250

300

350

400

-75

-69

-63

-57

-51

-45

-39

-33

-27

-21

-15

-09

-03

03

09

15

21

27

33

39

45

Mo

re

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily Ln SAIDI

Frequency

Cumulative

Mean = -20Median = -20Std Dev = 13

Mean = 05Median = 01Std Dev = 27

Tmed = e(mean + (25std dev))

Daily SAIDI Re-Ordered from Lowest to Highest

Tmed = 34

January 12 2018 88

0000

1000

2000

3000

4000

5000

6000

7000

U1 Year 2016 Daily SAIDI

4 MEDs in year 20161 Feb 162 Jun 163 Jul 134 Aug 28

TMED = 34

Daily SAIDI for 2016 rarr 4 MEDs

January 12 2018 99

Introducing Reliability Value-Based Planning

The pace of electricity grid modernization efforts will be determined by

decisions made by electric utilities their customers and local

communitiesstates to adopt new technologies and practices

An important motivation for these actions will be maintaining or

improving the reliability and resiliency of electric service

From an economic perspective the justification for these actions will

therefore depend at least in part on

◼ The cost of the actions under consideration

◼ The impact they are expected to have on reliability or resilience and

◼ The value these impacts have to the utility its customers and the

communitystate

Better information will enable but does not guarantee better decisions

and rememberhellip we will never have perfect information

January 12 2018 1010

Value-Based Reliability Planning is a means for taking the cost of interruptions borne by customers into utility planning decisions

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 2: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 22

Overview of this presentation

Reliability Metrics

Major Events (IEEE Std 1366 definition)

Reliability Value-Based Planning

The Interruption Cost Estimate (ICE) Calculator

Considerations for Reliability Planning Emerging from Recent LBNL

Research

Bibliography

January 12 2018 33

Electricity reliability is measured by the annual average amount of time and frequency that the lights are out

System Average Interruption Duration Index

total duration of sustained customer

interruptions ( 5min each)

------------------------------------------------

number of customers served

SAIDI =

System Average Interruption Frequency Index

frequency of sustained customer

interruptions ( 5min each)

--------------------------------------------

number of customers served

SAIFI =

Customer Average Interruption Duration Index

SAIDI-------------------

SAIFICAIDI =

frequency of momentary customer

interruptions (lt 5min each)

--------------------------------------------

number of customers served

MAIFI =

Momentary Average Interruption Frequency Index

January 12 2018 44

IEEE Standard 1366Investor Owned

Cooperative Municipal

Number of utilities reporting 137 296 117

of US sales by type of utility 51 47 43

SAIDI with Major Events 237 302 115

SAIDI without Major Events 136 159 50

SAIFI with Major Events 14 28 09

SAIFI without Major Events 12 21 07

Information Reported to EIA for 2015

January 12 2018 55

IEEE Standard 1366

First developed in 1998 to define reliability indices amended in 2003 to

add a consistent approach for segmenting Major Event Days (amended

again in 2012 MED definition unchanged)

Uses 25beta to estimate a threshold daily SAIDI Tmed above which a

Major Event Day is identified

◼ Tmed = exp (α+25β)

◼ Beta = log-normal standard deviation

◼ Alpha = log-normal statistical mean

For a normal distribution

◼ Multiplying beta (the standard deviation) by 25 covers 99379 of the

expected observations (assuming a one-sided confidence interval)

◼ For a year of daily observations this translates to an expectation of 23 Major

Event Days per year

But utility daily SAIDI data are not ldquoperfectlyrdquo normally distributed

January 12 2018 66

Daily SAIDI for 5 years (2011-2015)

0000

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

January 12 2018 77

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

200

400

600

800

1000

1200

1400

1600

1800

00 10 20 30 40 50 60 70 80 90 100

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily SAIDI

Frequency

Cumulative

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

50

100

150

200

250

300

350

400

-75

-69

-63

-57

-51

-45

-39

-33

-27

-21

-15

-09

-03

03

09

15

21

27

33

39

45

Mo

re

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily Ln SAIDI

Frequency

Cumulative

Mean = -20Median = -20Std Dev = 13

Mean = 05Median = 01Std Dev = 27

Tmed = e(mean + (25std dev))

Daily SAIDI Re-Ordered from Lowest to Highest

Tmed = 34

January 12 2018 88

0000

1000

2000

3000

4000

5000

6000

7000

U1 Year 2016 Daily SAIDI

4 MEDs in year 20161 Feb 162 Jun 163 Jul 134 Aug 28

TMED = 34

Daily SAIDI for 2016 rarr 4 MEDs

January 12 2018 99

Introducing Reliability Value-Based Planning

The pace of electricity grid modernization efforts will be determined by

decisions made by electric utilities their customers and local

communitiesstates to adopt new technologies and practices

An important motivation for these actions will be maintaining or

improving the reliability and resiliency of electric service

From an economic perspective the justification for these actions will

therefore depend at least in part on

◼ The cost of the actions under consideration

◼ The impact they are expected to have on reliability or resilience and

◼ The value these impacts have to the utility its customers and the

communitystate

Better information will enable but does not guarantee better decisions

and rememberhellip we will never have perfect information

January 12 2018 1010

Value-Based Reliability Planning is a means for taking the cost of interruptions borne by customers into utility planning decisions

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 3: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 33

Electricity reliability is measured by the annual average amount of time and frequency that the lights are out

System Average Interruption Duration Index

total duration of sustained customer

interruptions ( 5min each)

------------------------------------------------

number of customers served

SAIDI =

System Average Interruption Frequency Index

frequency of sustained customer

interruptions ( 5min each)

--------------------------------------------

number of customers served

SAIFI =

Customer Average Interruption Duration Index

SAIDI-------------------

SAIFICAIDI =

frequency of momentary customer

interruptions (lt 5min each)

--------------------------------------------

number of customers served

MAIFI =

Momentary Average Interruption Frequency Index

January 12 2018 44

IEEE Standard 1366Investor Owned

Cooperative Municipal

Number of utilities reporting 137 296 117

of US sales by type of utility 51 47 43

SAIDI with Major Events 237 302 115

SAIDI without Major Events 136 159 50

SAIFI with Major Events 14 28 09

SAIFI without Major Events 12 21 07

Information Reported to EIA for 2015

January 12 2018 55

IEEE Standard 1366

First developed in 1998 to define reliability indices amended in 2003 to

add a consistent approach for segmenting Major Event Days (amended

again in 2012 MED definition unchanged)

Uses 25beta to estimate a threshold daily SAIDI Tmed above which a

Major Event Day is identified

◼ Tmed = exp (α+25β)

◼ Beta = log-normal standard deviation

◼ Alpha = log-normal statistical mean

For a normal distribution

◼ Multiplying beta (the standard deviation) by 25 covers 99379 of the

expected observations (assuming a one-sided confidence interval)

◼ For a year of daily observations this translates to an expectation of 23 Major

Event Days per year

But utility daily SAIDI data are not ldquoperfectlyrdquo normally distributed

January 12 2018 66

Daily SAIDI for 5 years (2011-2015)

0000

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

January 12 2018 77

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

200

400

600

800

1000

1200

1400

1600

1800

00 10 20 30 40 50 60 70 80 90 100

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily SAIDI

Frequency

Cumulative

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

50

100

150

200

250

300

350

400

-75

-69

-63

-57

-51

-45

-39

-33

-27

-21

-15

-09

-03

03

09

15

21

27

33

39

45

Mo

re

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily Ln SAIDI

Frequency

Cumulative

Mean = -20Median = -20Std Dev = 13

Mean = 05Median = 01Std Dev = 27

Tmed = e(mean + (25std dev))

Daily SAIDI Re-Ordered from Lowest to Highest

Tmed = 34

January 12 2018 88

0000

1000

2000

3000

4000

5000

6000

7000

U1 Year 2016 Daily SAIDI

4 MEDs in year 20161 Feb 162 Jun 163 Jul 134 Aug 28

TMED = 34

Daily SAIDI for 2016 rarr 4 MEDs

January 12 2018 99

Introducing Reliability Value-Based Planning

The pace of electricity grid modernization efforts will be determined by

decisions made by electric utilities their customers and local

communitiesstates to adopt new technologies and practices

An important motivation for these actions will be maintaining or

improving the reliability and resiliency of electric service

From an economic perspective the justification for these actions will

therefore depend at least in part on

◼ The cost of the actions under consideration

◼ The impact they are expected to have on reliability or resilience and

◼ The value these impacts have to the utility its customers and the

communitystate

Better information will enable but does not guarantee better decisions

and rememberhellip we will never have perfect information

January 12 2018 1010

Value-Based Reliability Planning is a means for taking the cost of interruptions borne by customers into utility planning decisions

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 4: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 44

IEEE Standard 1366Investor Owned

Cooperative Municipal

Number of utilities reporting 137 296 117

of US sales by type of utility 51 47 43

SAIDI with Major Events 237 302 115

SAIDI without Major Events 136 159 50

SAIFI with Major Events 14 28 09

SAIFI without Major Events 12 21 07

Information Reported to EIA for 2015

January 12 2018 55

IEEE Standard 1366

First developed in 1998 to define reliability indices amended in 2003 to

add a consistent approach for segmenting Major Event Days (amended

again in 2012 MED definition unchanged)

Uses 25beta to estimate a threshold daily SAIDI Tmed above which a

Major Event Day is identified

◼ Tmed = exp (α+25β)

◼ Beta = log-normal standard deviation

◼ Alpha = log-normal statistical mean

For a normal distribution

◼ Multiplying beta (the standard deviation) by 25 covers 99379 of the

expected observations (assuming a one-sided confidence interval)

◼ For a year of daily observations this translates to an expectation of 23 Major

Event Days per year

But utility daily SAIDI data are not ldquoperfectlyrdquo normally distributed

January 12 2018 66

Daily SAIDI for 5 years (2011-2015)

0000

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

January 12 2018 77

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

200

400

600

800

1000

1200

1400

1600

1800

00 10 20 30 40 50 60 70 80 90 100

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily SAIDI

Frequency

Cumulative

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

50

100

150

200

250

300

350

400

-75

-69

-63

-57

-51

-45

-39

-33

-27

-21

-15

-09

-03

03

09

15

21

27

33

39

45

Mo

re

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily Ln SAIDI

Frequency

Cumulative

Mean = -20Median = -20Std Dev = 13

Mean = 05Median = 01Std Dev = 27

Tmed = e(mean + (25std dev))

Daily SAIDI Re-Ordered from Lowest to Highest

Tmed = 34

January 12 2018 88

0000

1000

2000

3000

4000

5000

6000

7000

U1 Year 2016 Daily SAIDI

4 MEDs in year 20161 Feb 162 Jun 163 Jul 134 Aug 28

TMED = 34

Daily SAIDI for 2016 rarr 4 MEDs

January 12 2018 99

Introducing Reliability Value-Based Planning

The pace of electricity grid modernization efforts will be determined by

decisions made by electric utilities their customers and local

communitiesstates to adopt new technologies and practices

An important motivation for these actions will be maintaining or

improving the reliability and resiliency of electric service

From an economic perspective the justification for these actions will

therefore depend at least in part on

◼ The cost of the actions under consideration

◼ The impact they are expected to have on reliability or resilience and

◼ The value these impacts have to the utility its customers and the

communitystate

Better information will enable but does not guarantee better decisions

and rememberhellip we will never have perfect information

January 12 2018 1010

Value-Based Reliability Planning is a means for taking the cost of interruptions borne by customers into utility planning decisions

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 5: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 55

IEEE Standard 1366

First developed in 1998 to define reliability indices amended in 2003 to

add a consistent approach for segmenting Major Event Days (amended

again in 2012 MED definition unchanged)

Uses 25beta to estimate a threshold daily SAIDI Tmed above which a

Major Event Day is identified

◼ Tmed = exp (α+25β)

◼ Beta = log-normal standard deviation

◼ Alpha = log-normal statistical mean

For a normal distribution

◼ Multiplying beta (the standard deviation) by 25 covers 99379 of the

expected observations (assuming a one-sided confidence interval)

◼ For a year of daily observations this translates to an expectation of 23 Major

Event Days per year

But utility daily SAIDI data are not ldquoperfectlyrdquo normally distributed

January 12 2018 66

Daily SAIDI for 5 years (2011-2015)

0000

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

January 12 2018 77

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

200

400

600

800

1000

1200

1400

1600

1800

00 10 20 30 40 50 60 70 80 90 100

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily SAIDI

Frequency

Cumulative

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

50

100

150

200

250

300

350

400

-75

-69

-63

-57

-51

-45

-39

-33

-27

-21

-15

-09

-03

03

09

15

21

27

33

39

45

Mo

re

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily Ln SAIDI

Frequency

Cumulative

Mean = -20Median = -20Std Dev = 13

Mean = 05Median = 01Std Dev = 27

Tmed = e(mean + (25std dev))

Daily SAIDI Re-Ordered from Lowest to Highest

Tmed = 34

January 12 2018 88

0000

1000

2000

3000

4000

5000

6000

7000

U1 Year 2016 Daily SAIDI

4 MEDs in year 20161 Feb 162 Jun 163 Jul 134 Aug 28

TMED = 34

Daily SAIDI for 2016 rarr 4 MEDs

January 12 2018 99

Introducing Reliability Value-Based Planning

The pace of electricity grid modernization efforts will be determined by

decisions made by electric utilities their customers and local

communitiesstates to adopt new technologies and practices

An important motivation for these actions will be maintaining or

improving the reliability and resiliency of electric service

From an economic perspective the justification for these actions will

therefore depend at least in part on

◼ The cost of the actions under consideration

◼ The impact they are expected to have on reliability or resilience and

◼ The value these impacts have to the utility its customers and the

communitystate

Better information will enable but does not guarantee better decisions

and rememberhellip we will never have perfect information

January 12 2018 1010

Value-Based Reliability Planning is a means for taking the cost of interruptions borne by customers into utility planning decisions

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 6: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 66

Daily SAIDI for 5 years (2011-2015)

0000

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

January 12 2018 77

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

200

400

600

800

1000

1200

1400

1600

1800

00 10 20 30 40 50 60 70 80 90 100

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily SAIDI

Frequency

Cumulative

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

50

100

150

200

250

300

350

400

-75

-69

-63

-57

-51

-45

-39

-33

-27

-21

-15

-09

-03

03

09

15

21

27

33

39

45

Mo

re

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily Ln SAIDI

Frequency

Cumulative

Mean = -20Median = -20Std Dev = 13

Mean = 05Median = 01Std Dev = 27

Tmed = e(mean + (25std dev))

Daily SAIDI Re-Ordered from Lowest to Highest

Tmed = 34

January 12 2018 88

0000

1000

2000

3000

4000

5000

6000

7000

U1 Year 2016 Daily SAIDI

4 MEDs in year 20161 Feb 162 Jun 163 Jul 134 Aug 28

TMED = 34

Daily SAIDI for 2016 rarr 4 MEDs

January 12 2018 99

Introducing Reliability Value-Based Planning

The pace of electricity grid modernization efforts will be determined by

decisions made by electric utilities their customers and local

communitiesstates to adopt new technologies and practices

An important motivation for these actions will be maintaining or

improving the reliability and resiliency of electric service

From an economic perspective the justification for these actions will

therefore depend at least in part on

◼ The cost of the actions under consideration

◼ The impact they are expected to have on reliability or resilience and

◼ The value these impacts have to the utility its customers and the

communitystate

Better information will enable but does not guarantee better decisions

and rememberhellip we will never have perfect information

January 12 2018 1010

Value-Based Reliability Planning is a means for taking the cost of interruptions borne by customers into utility planning decisions

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 7: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 77

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

200

400

600

800

1000

1200

1400

1600

1800

00 10 20 30 40 50 60 70 80 90 100

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily SAIDI

Frequency

Cumulative

000

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

50

100

150

200

250

300

350

400

-75

-69

-63

-57

-51

-45

-39

-33

-27

-21

-15

-09

-03

03

09

15

21

27

33

39

45

Mo

re

Fre

qu

en

cy

Bin

Histogram of 2011-2015 Daily Ln SAIDI

Frequency

Cumulative

Mean = -20Median = -20Std Dev = 13

Mean = 05Median = 01Std Dev = 27

Tmed = e(mean + (25std dev))

Daily SAIDI Re-Ordered from Lowest to Highest

Tmed = 34

January 12 2018 88

0000

1000

2000

3000

4000

5000

6000

7000

U1 Year 2016 Daily SAIDI

4 MEDs in year 20161 Feb 162 Jun 163 Jul 134 Aug 28

TMED = 34

Daily SAIDI for 2016 rarr 4 MEDs

January 12 2018 99

Introducing Reliability Value-Based Planning

The pace of electricity grid modernization efforts will be determined by

decisions made by electric utilities their customers and local

communitiesstates to adopt new technologies and practices

An important motivation for these actions will be maintaining or

improving the reliability and resiliency of electric service

From an economic perspective the justification for these actions will

therefore depend at least in part on

◼ The cost of the actions under consideration

◼ The impact they are expected to have on reliability or resilience and

◼ The value these impacts have to the utility its customers and the

communitystate

Better information will enable but does not guarantee better decisions

and rememberhellip we will never have perfect information

January 12 2018 1010

Value-Based Reliability Planning is a means for taking the cost of interruptions borne by customers into utility planning decisions

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 8: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 88

0000

1000

2000

3000

4000

5000

6000

7000

U1 Year 2016 Daily SAIDI

4 MEDs in year 20161 Feb 162 Jun 163 Jul 134 Aug 28

TMED = 34

Daily SAIDI for 2016 rarr 4 MEDs

January 12 2018 99

Introducing Reliability Value-Based Planning

The pace of electricity grid modernization efforts will be determined by

decisions made by electric utilities their customers and local

communitiesstates to adopt new technologies and practices

An important motivation for these actions will be maintaining or

improving the reliability and resiliency of electric service

From an economic perspective the justification for these actions will

therefore depend at least in part on

◼ The cost of the actions under consideration

◼ The impact they are expected to have on reliability or resilience and

◼ The value these impacts have to the utility its customers and the

communitystate

Better information will enable but does not guarantee better decisions

and rememberhellip we will never have perfect information

January 12 2018 1010

Value-Based Reliability Planning is a means for taking the cost of interruptions borne by customers into utility planning decisions

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 9: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 99

Introducing Reliability Value-Based Planning

The pace of electricity grid modernization efforts will be determined by

decisions made by electric utilities their customers and local

communitiesstates to adopt new technologies and practices

An important motivation for these actions will be maintaining or

improving the reliability and resiliency of electric service

From an economic perspective the justification for these actions will

therefore depend at least in part on

◼ The cost of the actions under consideration

◼ The impact they are expected to have on reliability or resilience and

◼ The value these impacts have to the utility its customers and the

communitystate

Better information will enable but does not guarantee better decisions

and rememberhellip we will never have perfect information

January 12 2018 1010

Value-Based Reliability Planning is a means for taking the cost of interruptions borne by customers into utility planning decisions

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 10: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1010

Value-Based Reliability Planning is a means for taking the cost of interruptions borne by customers into utility planning decisions

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 11: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1111

Value-Based Reliability Planning example

Distribution Automation

Utility EPB of Chattanooga

Customers Impacted 174000

customers (entire territory)

Investment 1200 automated circuit

switches and sensors on 171 circuits

Reliability Improvement

◼ SAIDI 45 (from 112 to 618

minutesyear)

◼ SAIFI 51 (from 142 to 069

interruptionsyear) (between 2010 and

2015)

$56 M

$268 MBenefits

Investment Costs

Utility Avoided customer outage costs

Annual Costs and Benefits

Avoided Cost of Severe Storm

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 12: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1212

ICE Calculator httpicecalculatorcom

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 13: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1313

Customer-weighted proportion of SAIDI and

SAIFI due to loss of supply (2008-2014 n = 73)

SAIDI w major events

SAIDI wo major events

SAIFI w major events

SAIFI wo major events

0

2

4

6

8

10

12

2008 2009 2010 2011 2012 2013 2014

Pro

po

rtio

n o

f cu

sto

mer

-wei

ghte

d in

terr

up

tio

ns

d

ue

to lo

ss o

f su

pp

ly

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 14: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1414

Still we are moving in the right directionhellip

yet there remains much work to be done

0

5

10

15

20

25

30

lt10 kVn=20

10-19 kVn=189

20-29 kVn=101

30-39 kVn=99

40-65 kVn=6

gt65 kVn=27

Pro

po

rtio

n o

f o

uta

ge d

ue

to L

OS

Maximum distribution voltage

SAIFI mean

SAIFI medianSAIDI mean

SAIDI median

SAIDI and SAIFI due to loss of supply vs maximum reported distribution voltage

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 15: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1515

LBNL finds that reliability is getting worse due to

increased severityfrequency of major events

Source Larsen P K LaCommare J Eto J Sweeney Recent Trends in Power System Reliability and Implications for Evaluating Future Investments in Resiliency Energy 117 (2016) 29-46 httpdxdoiorg101016jenergy201610063

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 16: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1616

The Costs of Power Interruptions

Interruption Cost

Interruption Duration

Momentary 30 minutes 1 hour 4 hours 8 hours

Medium and Large CampI

Morning $8133 $11035 $14488 $43954 $70190

Afternoon $11756 $15709 $20360 $59188 $93890

Evening $9276 $12844 $17162 $55278 $89145

Small CampI

Morning $346 $492 $673 $2389 $4348

Afternoon $439 $610 $818 $2696 $4768

Evening $199 $299 $431 $1881 $3734

Residential

Morning $37 $44 $52 $99 $136

Afternoon $27 $33 $39 $78 $107

Evening $24 $30 $37 $84 $119

Varies by type of customer and depends on when and for how long their lights are out

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 17: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1717

NewEngland

Mid-Atlantic

East NorthCentral

West NorthCentral

SouthAtlantic

West SouthCentral

East SouthCentral

Mountain Pacific

Residential 1 19 2 1 11 1 1 1 3

Commercial 14 23 14 86 19 7 7 4 18

Industrial 14 52 11 12 10 18 18 15 22

0

10

20

30

40

50

60

70

80

90

100

Bac

k-u

p G

ener

atio

n (

BU

G)

shar

e o

f to

tal i

nst

alle

d c

apac

ity

Installed Capacity of Back-up Generation

Source Frost and Sullivan 2015 ldquoAnalysis of the US Power Quality Equipment Marketrdquo Berkeley California Lawrence BerkeleyNational Laboratory LBNL-1003990 August Accessible at httpeetdlblgovsitesallfileslbnl-1003990pdf

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 18: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1818

Some themes to keep in mind

ldquoWhats measured improvesrdquo

― Peter F Drucker

ldquoDelegating your accountabilities is abdicationrdquo

― Michael E Gerber

ldquoNot everything that can be counted counts

and not everything that counts can be countedrdquo

― Albert Einstein

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 19: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 1919

Bibliography

LaCommare Kristina Hamachi Peter H Larsen and Joseph H Eto Evaluating Proposed Investments in Power System

Reliability and Resilience Preliminary Results from Interviews with Public Utility Commission Staff

2017httpsemplblgovsitesdefaultfileslbnl-_1006971pdf

Larsen Peter H A Method to Estimate the Costs and Benefits of Undergrounding Electricity Transmission and Distribution

lines Energy Economics 60 no November 2016 (2016) 47-61 httpsemplblgovsitesdefaultfileslbnl-1006394_pre-

publicationpdf

Larsen Peter H Kristina Hamachi LaCommare Joseph H Eto and James L Sweeney Assessing Changes in the

Reliability of the US Electric Power System 2015 httpsemplblgovsitesdefaultfileslbnl-188741pdf

Eto Joseph H Kristina Hamachi LaCommare Michael D Sohn and Heidemarie C Caswell Evaluating the Performance

of the IEEE Standard 1366 Method for Identifying Major Event Days View Document IEEE Transactions on Power

Systems 32 no 2 (2016)

Sullivan Michael J Josh A Schellenberg and Marshall Blundell Updated Value of Service Reliability Estimates for

Electric Utility Customers in the United States 2015 httpsemplblgovsitesdefaultfileslbnl-6941epdf

httpsemplblgovresearchelectricity-reliability

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 20: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 2020

Supporting Slides

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 21: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 2121

Evaluating the performance of alternatives

to the Standard 1366 method

-100

-80

-60

-40

-20

0

20

40

60

80

100

-400 -300 -200 -100 0 100 200 300 400

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Effect of changing beta multiplier from 25 to 4

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 22: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 2222

The effect of using fewer historical years to

calculate Tmed 4 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13

n=8

n=34

n=22

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 23: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 2323

The effect of using fewer historical years to

calculate Tmed 4 years 3 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17

n=8n=8

n=34n=31

n=22n=21

Ch

ange

in A

vera

ge M

EDs

year

Change in Standard Deviation of SAIDI wo Major Events

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events

Page 24: Reliability Metrics and Reliability Value-Based …...January 12, 2018 1 Reliability Metrics and Reliability Value-Based Planning Lawrence Berkeley National Laboratory Distribution

January 12 2018 2424

The effect of using fewer historical years to

calculate Tmed 4 years 3 years 2 years

-100

-80

-60

-40

-20

0

20

40

60

80

100

-100 -80 -60 -40 -20 0 20 40 60 80 100

n=13n=17n=8

n=8n=8n=12

n=34n=31n=40

n=22n=21n=17

C

han

ge in

Ave

rage

MED

sye

ar

Change in Standard Deviation of SAIDI wo Major Events


Recommended