St. Louis River/Interlake/Duluth Tar Site (SLRIDT) Remedy Construction Activities c-s3-16v
Transcript
Page 1: Remedy Construction Activities Presentation

St. Louis River/Interlake/Duluth Tar Site

(SLRIDT)

Remedy Construction Activities

c-s3-16v

Page 2: Remedy Construction Activities Presentation
Page 3: Remedy Construction Activities Presentation
Page 4: Remedy Construction Activities Presentation

Extent of Contaminated Sediment

Page 5: Remedy Construction Activities Presentation

Stryker Bay Oil Blooms

Page 6: Remedy Construction Activities Presentation

Stakeholder Process • MPCA & RPs sought input from a

broad group of stakeholders • Meetings to discuss new

information and the remedy implications –A wide range of issues were

discussed

Page 7: Remedy Construction Activities Presentation
Page 8: Remedy Construction Activities Presentation
Page 9: Remedy Construction Activities Presentation

Participants that Helped Shape the Remedy • Minnesota Department of Natural Resources • Minnesota Department of Health • US Fish and Wildlife Service • US Environmental Protection Agency • US Environmental Protection Agency Great Lakes Natl. Program Office • US Army Corp of Engineers • Fond du Lac Band of Lake Superior Chippewa • 1854 Authority • National Oceanic and Atmospheric Administration • City of Duluth • Responsible Parties and their consultants • SLRIDT Community Work Group • Metropolitan Interstate Committee • Harbor Technical Advisory Committee • St. Louis River Citizens Action Committee • Spirit Valley Economic Development Association • Community Associations • Hallett Dock Company • Stryker Bay Residents • Landowners and Neighbors • Neighboring Communities • Nationally-recognized dredging, capping and sediment remediation experts

Page 10: Remedy Construction Activities Presentation

Best approach is a combination of

cleanup methods

Page 11: Remedy Construction Activities Presentation

Construction of the Dredge/Cap Hybrid

Remedy

Page 12: Remedy Construction Activities Presentation

CAD

Stryker Bay Sheet Pile Wall & Surcharged Cap CAD End Dike Construction Stryker Bay, Nav. Channel, Wis. & Wetland Dredging Slip 7/Keene Creek Bay & 48” Outfall Capping Stryker Bay Sheet Pile & Surcharge Removal Final Confined Aquatic Disposal Cell Capping

Elements of the Selected Remedy

Page 13: Remedy Construction Activities Presentation

2006 Stryker Bay

Cap & Surcharge Construction

Page 14: Remedy Construction Activities Presentation

Sheet Pile Wall

Sheet Pile Wall Installation

Page 15: Remedy Construction Activities Presentation

Sheet Pile Wall Constructed

Page 16: Remedy Construction Activities Presentation

Surcharge Cap

Capping with Spreader Barge

Page 17: Remedy Construction Activities Presentation

Spreader Barge Movement Trace

Page 18: Remedy Construction Activities Presentation

First Lift of Cap Sand

Page 19: Remedy Construction Activities Presentation
Page 20: Remedy Construction Activities Presentation

Carbon Mat Placement

Activated Carbon Mat deployed with Roller Barge

Page 21: Remedy Construction Activities Presentation
Page 22: Remedy Construction Activities Presentation

Activated Carbon Mat Deployment Pattern

Page 23: Remedy Construction Activities Presentation
Page 24: Remedy Construction Activities Presentation

Land Based Cap Placement

Page 25: Remedy Construction Activities Presentation

Cap Above Water Placement

1

Placing Cap & Surcharge Material

Page 26: Remedy Construction Activities Presentation

Installing Sheet Pile Wall Tie-backs

Page 27: Remedy Construction Activities Presentation

Cap Above Water Placement

2

Adding Surcharge Material

Page 28: Remedy Construction Activities Presentation

Full Cap & Surcharge

Page 29: Remedy Construction Activities Presentation

Cap and Surcharge

Area

Page 30: Remedy Construction Activities Presentation

CAD

CAD End Dike Construction

Page 31: Remedy Construction Activities Presentation

CAD End Dike

Page 32: Remedy Construction Activities Presentation

Clay Mat & Ballast Installation

Page 33: Remedy Construction Activities Presentation

Completed Slip 6 End Dike

Page 34: Remedy Construction Activities Presentation

CAD End Dike Finnished

Page 35: Remedy Construction Activities Presentation

CAD

2007

Stryker Bay Dredging

Page 36: Remedy Construction Activities Presentation

Best Technology Water Treatment Plant

Page 37: Remedy Construction Activities Presentation

Water Filled Dam and Weir Wall Isolating Stryker Bay

Page 38: Remedy Construction Activities Presentation

Aquatic Vegetation Harvesting

Page 39: Remedy Construction Activities Presentation

Herding Fish out of

Work Areas

Page 40: Remedy Construction Activities Presentation

Debris Removal from Stryker Bay

Page 41: Remedy Construction Activities Presentation

Mechanical/Hydraulic Hybrid Dredge

Page 42: Remedy Construction Activities Presentation
Page 43: Remedy Construction Activities Presentation
Page 44: Remedy Construction Activities Presentation
Page 45: Remedy Construction Activities Presentation
Page 46: Remedy Construction Activities Presentation

Mechanical Dredging with Hydraulic Transport

Page 47: Remedy Construction Activities Presentation

Dredge Material Placement In CAD With Tremi Barge

Page 48: Remedy Construction Activities Presentation
Page 49: Remedy Construction Activities Presentation

24 Hour Dredge Operations

Page 50: Remedy Construction Activities Presentation

Post Dredge Cover Application

Page 51: Remedy Construction Activities Presentation

CAD

North & South Wetland Excavations

Page 52: Remedy Construction Activities Presentation

North Wetland Excavation

Page 53: Remedy Construction Activities Presentation

South Wetland Area

Page 54: Remedy Construction Activities Presentation

CAD

2008 Dredge

Wisconsin & Nav. Channel

Page 55: Remedy Construction Activities Presentation
Page 56: Remedy Construction Activities Presentation
Page 57: Remedy Construction Activities Presentation

Deep Water Dredging With

Hydraulic Transport

Page 58: Remedy Construction Activities Presentation
Page 59: Remedy Construction Activities Presentation

Land Based &

Water Based Capping

Page 60: Remedy Construction Activities Presentation

Capping with Spreader Barge

Page 61: Remedy Construction Activities Presentation

Land Based Capping Installing Root Barrier

Page 62: Remedy Construction Activities Presentation
Page 63: Remedy Construction Activities Presentation
Page 64: Remedy Construction Activities Presentation

Installing Root Barrier in Cap

Page 65: Remedy Construction Activities Presentation

Capping Slip 7 Flats

Page 66: Remedy Construction Activities Presentation

Armor Material Placement

Page 67: Remedy Construction Activities Presentation

Staging Armor Materials

Page 68: Remedy Construction Activities Presentation
Page 69: Remedy Construction Activities Presentation

Placing Cap Armor Layer

Page 70: Remedy Construction Activities Presentation

CAD

2009

Remove Sheet Pile & Surcharge

Page 71: Remedy Construction Activities Presentation

Sheet Pile & Surcharge to be Removed

Page 72: Remedy Construction Activities Presentation
Page 73: Remedy Construction Activities Presentation
Page 74: Remedy Construction Activities Presentation
Page 75: Remedy Construction Activities Presentation

Cutting Sheet Pile Sections

Page 76: Remedy Construction Activities Presentation

Removing Sheet Pile sections

Page 77: Remedy Construction Activities Presentation

Capping Over Sheet Pile Cut

Page 78: Remedy Construction Activities Presentation

Removing Surcharge to leave Final Cap

Page 79: Remedy Construction Activities Presentation

Surveying final Cap Elevation

Page 80: Remedy Construction Activities Presentation

Capped Area After Surcharge Removal

Page 81: Remedy Construction Activities Presentation

Complete Cap Construction

and Armoring

Page 82: Remedy Construction Activities Presentation

Placing Cap Armor Material

Page 83: Remedy Construction Activities Presentation

Cap Armor Along Shoreline

Page 84: Remedy Construction Activities Presentation

Slip 7 flats with Final Cap

Page 85: Remedy Construction Activities Presentation

CAD

Construct First Layer of CAD Cap

Page 86: Remedy Construction Activities Presentation

Slip 6 CAD Capping Spreader Barge

Page 87: Remedy Construction Activities Presentation

Slip 6 Land Based Capping

Page 88: Remedy Construction Activities Presentation

Wetland dredging & Capping

Page 89: Remedy Construction Activities Presentation

Horizontal Auger Dredge in South Wetland

Page 90: Remedy Construction Activities Presentation

South Wetland Excavation

Page 91: Remedy Construction Activities Presentation

South Wetland

Page 92: Remedy Construction Activities Presentation

CAD

Complete Final CAD Cap

2010

Page 93: Remedy Construction Activities Presentation

Placing Activated Carbon Mat in CAD Cap

Page 94: Remedy Construction Activities Presentation

Placing Activated Carbon Mat from Roller Barge

Page 95: Remedy Construction Activities Presentation

Carbon Mat Layout Pattern

Page 96: Remedy Construction Activities Presentation

Final CAD Capping

Page 97: Remedy Construction Activities Presentation

Cad End Dike Removal

Page 98: Remedy Construction Activities Presentation
Page 99: Remedy Construction Activities Presentation

CAD End Dike Removal

Page 100: Remedy Construction Activities Presentation

CAD

Environmental Media Placement

Page 101: Remedy Construction Activities Presentation

Environmental Media Pumped from Tallas Island Project to Stryker Bay

Page 102: Remedy Construction Activities Presentation
Page 103: Remedy Construction Activities Presentation

Environmental Media Placement Plot

Page 104: Remedy Construction Activities Presentation

Shoreline Buffer Zones &

Conservation Easement Areas

Page 105: Remedy Construction Activities Presentation

Shoreline Debris & Industrial Fill Prior to Removal

Page 106: Remedy Construction Activities Presentation
Page 107: Remedy Construction Activities Presentation

Shoreline Improvements

Page 108: Remedy Construction Activities Presentation

Shoreline Re-grading & Planting

Page 109: Remedy Construction Activities Presentation

Shoreline Buffer Zones &

Conservation Easement Areas

Page 110: Remedy Construction Activities Presentation

Exposed Flue Dust & Slag Cliff

Page 111: Remedy Construction Activities Presentation
Page 112: Remedy Construction Activities Presentation

Bluff Face Erosion

Page 113: Remedy Construction Activities Presentation

Grading & Softening Slopes

Page 114: Remedy Construction Activities Presentation

Final Grading & Topsoil Placement

Page 115: Remedy Construction Activities Presentation

Seeding, Planting & Mulching

Page 116: Remedy Construction Activities Presentation

Slope Contouring & Topsoil Placement

Page 117: Remedy Construction Activities Presentation

Topsoil Enhancements

Page 118: Remedy Construction Activities Presentation

Tree & Shrub Planting

Page 119: Remedy Construction Activities Presentation

3375 Trees and Shrubs Planted

Page 120: Remedy Construction Activities Presentation

Shoreline Improvements

Page 121: Remedy Construction Activities Presentation
Page 122: Remedy Construction Activities Presentation
Page 123: Remedy Construction Activities Presentation

St. Louis River/Interlake/Duluth Tar Site

(SLRIDT)

Thank You It’s a Wrap!