REPUBLIC OF INDONESIA
LIST OF PLANNED PRIORITY
EXTERNAL LOANS
2020
Ministry of National Development Planning/
National Development Planning Agency
i
Foreword
Carrying out the mandate of Government Regulation Number 10/2011 concerning Procedure
for the Procurement of External Loans and Grants, which is further regulated through
Regulation of the Minister for National Development Planning/Head of the National
Development Planning Agency Number 4/2011 concerning Procedure for Planning,
Proposing, Assessing, Monitoring, and Evaluation of Projects Financed by External Loans and
Grants, Ministry for National Development Planning/National Development Planning Agency
has compiled, and issued The List of Planned Priority External Loans or Daftar Rencana Prioritas
Pinjaman Luar Negeri (DRPPLN) 2020 through Decree of the Minister for National
Development Planning/Head of the National Development Planning Agency Number
KEP.65/M.PPN/HK/06/2020. This document embarks the first year of the mid-term external
loan planning process of 2020-2024, in line with the new development period of the National
Medium-Term Development Plan (Rencana Pembangunan Jangka Menengah Nasional/RPJMN)
2020-2024 which also constitutes the last stage of the Long-Term National Development Plan
(Rencana Pembangunan Jangka Panjang Nasional/RPJPN) 2005-2025.
As the regulation mandates, in this transition period whilst the new List of Medium-Term
Planned External-Loans (Daftar Rencana Pinjaman Luar Negeri Jangka Menengah/DRPLN-JM)
2020-2024 has yet been enacted, DRPPLN 2020 still refers to the previous DRPLN-JM 2015-
2019. The DRPPLN 2020, therefore, contains list of external-loan project proposals from
ministries/agencies, local governments, and State-Owned Enterprises (SOEs)in the DRPLN-JM
2015-2019-inclusive of all its revisions-, which have fulfilled most of the readiness criteria
required by applicable rules, and has been further proceed with development partners for its
funding indication. DRPPLN 2020 contains 31 infrastructure and non-infrastructure projects
of 12 ministries/agencies/SOEs with a total loan value of USD 5,05 billion funded by 11
development partners, as well as USD 0,55 billion of local funding.
DRPPLN 2020 is expected to be used as a reference by ministries/agencies/SOEs, particularly
those acting as executive agencies to formulate their respective work plans in order to enhance
readiness of their projects listed, as well as to carry out follow-up steps in order for the projects
can be immediately implemented. As for development partners, this document can be used as
a reference in determining steps and substances of their cooperation plan with the Government
of Indonesia
Minister for National Development Planning/
Head of the National Development Planning Agency
Suharso Monoarfa
ii
iii
List of Contents 1. Introduction i
2. Recapitulation and List of Projects in the DRPPLN 2019 ii
Kementerian Pekerjaan Umum dan Perumahan Rakyat/Ministry of Public Works
and Housing .............................................................................................................................. 9
Direktorat Jenderal Bina Marga/Directorate General of Highways ............................... 11
3. Development of Serang - Panimbang Toll Road (Cileles - Panimbang Section) 13
4. Development of Semarang-Demak Toll Road Integrated with Sea Dike 15
Direktorat Jenderal Cipta Karya/Directorate General of Human Settlements ............. 19
5. The Development of Regional Water Supply System in Wosusokas 21
6. Regency Settlement Infrastructure Development (RSID) 23
Direktorat Jenderal Sumber Daya Air/Directorate General of Water Resources .......... 26
7. Jenelata Dam Construction Project 28
8. Riam Kiwa Multipurpose Dam Construction Project 30
9. Lambakan Dam Project 32
10. Pelosika Multipurpose Dam Construction Project 34
11. Karian Dam-Serpong Water Conveyance System 36
Kementerian Perhubungan/Ministry of Transportation ................................................... 40
12. Patimban Port Development Project (Phase I-2) 42
13. Development and Improvement of Indonesian Aids to Navigation 44
Kementerian Kesehatan/Ministry of Health ....................................................................... 48
14. Strengthening of National Referral Hospitals and Vertical Technical Units 50
Kementerian Pendidikan dan Kebudayaan/ Ministry of Education and Culture ......... 54
15. The Quality Improvement Academic Hospital of Brawijaya University 56
16. Higher Education for Technology and Innovation (HETI) 59
Kementerian Pertahanan / Ministry of Defense ................................................................. 65
17. Upgrading Medical Equipment and Supporting Facilities for Army Hospital
Pelamonia 67
18. Upgrading Medical Equipments and Supporting Facilities for Army Hospital
Soedjono Magelang 69
iv
19. Upgrading Medical Equipments and Supporting Facilities for Army Hospital
Dustira Bandung 71
20. Upgrading Medical Equipments and Supporting Facilities for Army Hospital
Udayana 73
21. Upgrading Medical Equipments and Supporting Facilities for Naval Hospital
dr. Ramelan Surabaya 75
22. Upgrading Medical Equipments and Supporting Facilities for Naval Hospital
dr. R. Oetojo Sorong 77
23. Upgrading Medical Equipments and Supporting Facilities for Air Force Hospital
Suhardi Hardjolukito Yogyakarta 79
24. Upgrading Medical Equipments and Supporting Facilities for Air Force Hospital
Muhammad Sutomo Pontianak 81
Kementerian Ketenagakerjaan/ Ministry of Manpower .................................................. 84
25. Maritime Vocational Training Center in Serang 86
26. Maritime Vocational Training Center in Makassar 88
Kementerian Komunikasi dan Informatika/Ministry of Communication and
Information Technology ....................................................................................................... 92
27. Strengthening of e-Government Infrastructure 94
Kementerian Kelautan dan Perikanan/ Ministry of Marine Affairs and Fisheries ....... 98
28. Outer Ring Fishing Ports Development (Eco Fishing Port) 100
Lembaga Ilmu Pengetahuan Indonesia/ Indonesian Institute of Sciences ................... 103
29. Procurement of Multi Purposes Research Vessels 105
Badan Meteorologi Klimatologi dan Geofisika/ The Agency for Meteorology,
Climatology, and Geophysics .............................................................................................. 109
30. Strengthening Flight Information Region and Development of Aviation
Meteorology Services in Eastern Indonesia 111
Badan Informasi Geospasial/ The Geospatial Information Agency ............................. 114
31. Program to Accelerate the Provision of Large-Scale Base Maps (1:5000) for
Sustainable National Development 116
PT. PLN/ State Electricity Company ................................................................................... 120
32. Hululais Geothermal Power Plant 1 & 2 (2x55 MW) 122
33. Additional Loan for Peusangan 1 & 2 Hydroelectric Power (87 MW) 124
v
1
Chapter 1
1. Introduction
As the last stage of the Long-Term National Development Plan 2005-2025, the
Medium-Term National Development Plan (Rencana Pembangunan Jangka
Menengah Nasional/RPJMN) 2020 – 2024 is expected to accomplish various
development programs that have yet been completed in the previous
development stages during the long-term period. Therefore, in order to
achieve the goal, also particularly noting to the substantial gap existence
between investment need and government capacity of funding occurred
during the 2015-2019 period, considerable amount of development fund is
needed. External-loan is one of potential sources of financing that has long
been utilized to meet the funding needs, and to narrow the funding gap at the
same time. It is particularly due to its advantages when compared to other
sources of development funding, such as its low interests, long payment
terms, as well as its possibility to be used as a multi-year funding scheme.
Such advantages have led the source to be applicable for funding strategic
projects, which usually require large funds and take a long time to complete.
However, external-loan shall be utilized according to principles set out by the
laws. Some of the principles are that the loan shall be used transparently,
accountably, prudently, and productively. In order to meet those principles,
Ministry of National Development Planning/National Development Planning
Agency (BAPPENAS) is assigned to coordinate the planning process for
external-loans projects under the Government Regulation Number 10/2011 on
the Procedure for Procurement of External Loans and Grants, where the
annual planning process is stipulated under the The List of Planned Priority
External-Loans or Daftar Rencana Prioritas Pinjaman Luar Negeri (DRPPLN).
For the year of 2020, the DRPPLN is issued on 30th of June, 2020 through
Decree of the Minister for National Development Planning/ Head of the
National Development Planning Agency Number
KEP.65/M.PPN/HK/06/2020. It contains the short-listed project proposals of
those stated in the Medium-Term Planned External-Loans (Daftar Rencana
Pinjaman Luar Negeri Jangka Menengah/DRPLN-JM) 2015-2019, merely those
meeting most of the required readiness criteria under Regulation of the
Minister for National Development Planning/Head of the National
Development Planning Agency Number 4/2011 concerning Procedure for
Planning, Proposing, Assessing, Monitoring, and Evaluation of Projects
2
Financed by External Loans and Grants, as well as having an indicative
funding source thus ready to be negotiated within the yearly effective period.
DRPPLN 2020 is presented in two chapters. Chapter 1 consists of the
recapitulation of the projects classified by executing agencies, indicative
sources of financing, and by sector allocations. Whilst Chapter 2 consists of
summary of each project information (project digests) containing such
information as project locations, scope of works, outputs, outcomes, as well as
implementing agencies and respective stakeholders involved.
2. Recapitulation and List of Projects in the DRPPLN 2019
DRPPLN 2020 consists of 31 infrastructure and non-infrastructure projects of
12 ministries/agencies/SOEs with a total loan value of USD 5,05 billion funded
by 11 development partners, as well as USD 0,55 billion of local funding. The
recapitulation of the proposed projects in DRPPLN 2020 on the basis of
executing agencies is shown in Table 1, the proportion of infrastructure and
non-infrastructure sector allocation is presented in Table 2, while
recapitulation of projects on the basis of sources of financing is presented in
Table 3.
Table 1. The DRPPLN 2020 by Executing Agencies
No Executing Agency Number
of Projects
Amount
(USD thousands)
Loans Counterpart
Funds
Ministries/Agencies 29 4,714,872 494,582
1 Ministry of Public
Works and Housing 9 2,518,725 338,244
2 Ministry of
Transportation 2 742,203 4,464
3 Ministry of Health 1 261,718 30,594
3
No Executing Agency Number
of Projects
Amount
(USD thousands)
Loans Counterpart
Funds
4 Ministry of Education
and Culture 2 118,919 17,282
5 Ministry of Defense 8 99,999 -
6 Ministry of Manpower 2 31,300 -
7
Ministry of
Communication and
Information Technology
1 350,300 40,000
8 Ministry of Marine
Affairs and Fisheries 1 105,350 4,619
9 Indonesian Institute of
Sciences (LIPI) 1 107,851 2,942
10
The Agency for
Meteorology,
Climatology, and
Geophysics
1 26,617 -
11 Geospatial Information
Agency 1 351,890 56,437
State-Owned Enterprises 2 335,045 50,987
12
State Electricity
Company (PT.
Perusahaan Listrik
Negara)
2 335,045 50,987
Total 31 5,049,917 545,569
4
Table 2. Recapitulation of the DRPPLN 2020 by Sector
No Sector Number of
Projects
Amount (USD thousands)
Loans Local Funds
1 Infrastructure 15 3,946,273 434,695
2 Non-Infrastructure 16 1,103,644 111,874
Total 31 5,049,917 545,569
Table 3. Recapitulation of the DRPPLN 2020 by Source of Financing
No Source of Financing Loan Amount
(USD thousands)
Multilateral Agencies 341,193
1 IsDB 261,718
2 ADB 79,475
Bilateral Partners 4,708,724
3 China 2,076,050
4 JICA 1,099,993
5 Korea 484,439
6 France 403,501
7 FKE 351,890
8 KfW 134,935
9 Austria 96,299
10 Hungary 35,000
11 Finland 26,617
Total 5,049,917
5
Based on development partner, the 2020 Green Book projects consist of 11
development partners from multilateral or bilateral partner. The composition for
each development partner can be seen on chart 1. Besides, the 2020 Green Book
projects divided into infrastructure and non-infrastructure sectors which is
showed on Chart 2.
Austria2%
China (CEXIM)
41%
Finland0%
FKE7%
Hungary1%
JICA22%
KfW3%
Korea10%
France8%
ADB1%
IsDB5%
Infrastructure78%
Non-Infrastructure
22%
Chart 2. Loan Distribution
accordance to its Sector
Chart 1. Loan Distribution
accordance to its Lender
6
The 2020 Green Book projects will be executed by 11 Ministries/Agencies and 1
State Own Enterprise. The allocation for each executing agency can be seen on
chart 3.
Ministry of Public Works and Housing
50%
Ministry of Transportation
15%
Geospatial Information Agency
7%
Ministry of Communication adn
Information Technology
7%
State Electricity Company
7%
MInistry of Health5%
MInistry of Education and Culture
2%
Others7%
Chart 3. Loan Allocation accordance to its Executing Agency
7
Chapter 2
PROJECT DIGESTS
This chapter presents project digest of DRPPLN/Green Book 2020. The project
digest is a summary of information regarding the project which covers executing
agency, implementation agency, location, duration, amount of loan, counterpart
funding and disbursement plan.
8
9
Kementerian Pekerjaan Umum dan
Perumahan Rakyat/Ministry of Public
Works and Housing
10
11
Direktorat Jenderal Bina Marga/Directorate
General of Highways
12
GB-20-01-1
13
1. Project Title : Development of Serang - Panimbang Toll
Road (Cileles - Panimbang Section)
2. Program Title : Toll Road Development Program
3. Executing Agency : Ministry of Public Works and Housing
4. Implementing Agency : Directorate General of Highways, Ministry of
Public Works and Housing
5. Duration : 24 months
6. Location : Banten Province
7. Objectives
To increase economy and connectivity in Tanjung Lesung.
8. Scope of Project
Construction road and bridge of Serang-Panimbang Toll Road, Cileles-
Panimbang Section.
9. Activities
Activities Implementation
Locations Project Implementation Units
a. Preparation Stage
(Preparation of
Readiness Criteria
Document)
Banten
Province
a. Local Government of
Banten Province
b. Local Government of
Serang City
c. Local Government of
Serang Regency
d. Local Government of
Lebak Regency
e. Local Government of
Pandeglang Regency
f. Directorate General of
Highways, Ministry of
Public Works and
Housing
g. Regional Office of Road
Implementation VI
Jakarta, Ministry of Public
Works and Housing
b. Planning Stage
(Project design)
c. Construction
Stage (Civil
works)
d. Post-Construction
Stage (Operation
and maintenance
stage)
GB-20-01-1
14
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Directorate General of
Highways, Ministry of
Public Works and
Housing
221,000 0 38,000 259,000 China
Total 221,000 0 38,000 259,000
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd
38,000 130,000 91,000 259,000
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
Civil works 259,000
Total 259,000
13. Program Reference
BB-ID: BB-1519-R1-01
GB-20-02-0
15
1. Project Title : Development of Semarang-Demak Toll Road
Integrated with Sea Dike
2. Program Title : Toll Road Development Program
3. Executing Agency : Ministry of Public Works and Housing
4. Implementing Agency : Directorate General of Highways, Ministry of
Public Works and Housing
5. Duration : 36 months
6. Location : Central Java Province
7. Objectives
To improve accessibility & mobility of the Metropolitan Kedungsepur
(Kendal, Demak, Ungaran, Salatiga Semarang, and Purwodadi) and
provide protection from tidal flooding with sea dike.
8. Scope of Project
a. Road construction of Semarang - Demak Toll Road, Semarang-
Sayung Section along the sea dike.
b. The toll sea dike construction on the coast between the Banjir Kanal
Timur to the Kali Sayung which consists of two subsistem drainage:
(i) Tenggang - Sringin subsystem, between the Kanal Banjir Timur to
the Kali Babon; and (ii) Sriwulan Subsystem, between Kali Babon to
Kali Sayung.
GB-20-02-0
16
9. Activities
Activities Implementation
Locations Project Implementation Units
Road and Sea
wall/sea dike
construction
(Civil Works)
Central Java
Province
a. Local Government of
Semarang City
b. Local Government of
Demak Regency
c. Directorate General of
Highways, Ministry of
Public Works and Housing
d. Directorate General of Water
Resources, Ministry of
Public Works and Housing
e. Regional Office of Road
Implementation VII
Semarang, Ministry of Public
Works and HousingLocal
Government of Lebak
Regency
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Directorate General of
Highways, Ministry
of Public Works and
Housing
555,050 0 97,950 653,000 China
Total 555,050 0 97,950 653,000
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th
97,950 222,020 222,020 111,010 653,000
GB-20-02-0
17
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
Civil works 653,000
Total 653,000
13. Program Reference
BB-ID: BB-1519-R1-01
18
19
Direktorat Jenderal Cipta Karya/Directorate
General of Human Settlements
20
GB-20-03-1
21
1. Project Title : The Development of Regional Water Supply
System in Wosusokas
2. Program Title : Drinking Water Development Program
3. Executing Agency : Ministry of Public Works and Housing
4. Implementing Agency : Directorate General of Human Settlements,
Ministry of Public Works and Housing
5. Duration : 36 Months
6. Location : Central Java Province
7. Objectives
To enhance the quality of life in the region of Wosusokas (Wonogiri
Regency, Sukoharjo Regency, Surakarta City, and Karanganyar Regency),
which consist water processing installation with water outtake capacity
750 l/sec, main distribution network and house connection 60,000 unit or
240,000 people connected which can produce services that comply the 4K
Principle (quality, quantity, continuity, affordability).
8. Scope of Project
a. Construction of an electric mechanical system raw water unit with a
capacity of 1,450 l/sec
b. Construction of a complete IPA production unit with a capacity of 750
l/sec
c. Construction of a 73,800 m main distribution unit
d. Consulting services
9. Activities
Activities Implementation
Locations
Project
Implementation Units
a. Investment in
drinking water
supply infrastructure
Central Java
Province, (Wonogori
Regency, Sukoharjo
Regency, Surakarta
City and
Karanganyar
Regency)
Directorate General of
Human Settlements b. Technical assistance
and capacity
building
GB-20-03-1
22
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local*) Total
Directorate General of
Human Settlements,
Ministry of Public Works
and Housing
95,491 1,000 37,286 133,777 KfW
Total 95,491 1,000 37,286 133,777
11. Disbursement Plan*
Disbursement Plan (US $ 000) Total
1st 2nd 3rd
15,858 46,503 33,130 95,491
*) Not included local fund and grant
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Investment in
drinking
water supply
infrastructure
4,348 66,286 24,857
b. Technical
assistance
and capacity
building
1,000
c. Land
acquisition
and local
distribution
37,286
Total 4,348 66,286 1,000 62,143
Currency: 1 $ US = IDR 13.800
13. Program Reference
BB-ID: BB-1519-R0-04
GB-20-04-2
23
1. Project Title : Regency Settlement Infrastructure
Development (RSID)
2. Program Title : Slum Alleviation Program
3. Executing Agency : Ministry of Public Works and Housing
4. Implementing Agency : Directorate General of Human Settlements,
Ministry of Public Works and Housing
5. Duration : 60 Months
6. Location : Various Big Cities in Indonesia
7. Objectives
To improve sustainable peri-urban development that complies with
spatial through building capacity of local governments and providing
settlement infrastructure in peri-urban in piloting cities.
8. Scope of Project
a. Capacity building for central and local governments
(i) Planning, implementing and controlling of peri-urban area
development that complies with spatial plan
(ii) Policy development and policy coordination
(iii) Managing capital investment in developing peri-urban area
b. Assisting local government to formulate masterplan of peri-urban
area
c. Constructing green infrastructure development in peri-urban area in
order to m, such as water supply, wastewater, solid waste, road,
drainage, and green belt.
d. Providing project management
9. Activities
Activities Implementation
Locations
Project
Implementation
Units
a. Capacity Building
Various Location in
Indonesia Regency
Directorate General
of Human
Settlements,
Ministry of Public
Works and Housing
b. Masterplan
c. Infrastructure
d. Project Management
GB-20-04-2
24
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local*) Total
Directorate General of
Human Settlements,
Ministry of Public
Works and Housing
90,000 0 15,000 105,000 JICA
Total 90,000 0 15,000 105,000
*) Local funding for taxes and administration costs
11. Disbursement Plan*
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th 5th
1,393 17,776 25,552 33,308 11,971 90,000
*) Not included local fund
12. Funding Allocation*
Activities
Category (US $ 000)
Services Constructions Goods Training
s Other
a. Capacity
Building 1,000
b. Masterplan 4,278
c. Infrastructure 82,141
d. Project
Management 2,581
Total 6,859 82,141 1,000
*) Not included local fund
13. Program Reference
BB-ID: BB-1519-R0-07
25
26
Direktorat Jenderal Sumber Daya
Air/Directorate General of Water Resources
27
GB-20-05-2
28
1. Project Title : Jenelata Dam Construction Project
2. Program Title : Dam Development Program
3. Executing Agency : Ministry of Public Works and Housing
4. Implementing Agency : Directorate General of Water Resources
5. Duration : 48 Months
6. Location : South Sulawesi Province
7. Objectives
a. To irrigate an area of 24.000 Ha
b. Reducing flood discharge at 475 m³ / sec
c. Provide raw water supply of 3,12 m³ / sec
d. And to generate electricity of 10,9 MW
8. Scope of Project
a. Civil works including access road; river diversion, main dam;
spillway and water diversion; hydro-mechanical works, electrical
works, and building facilities.
b. Consulting services.
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Civil work South Sulawesi
Province
Directorate General of
Water Resources,
Ministry of Public Works
and Housing b. Consulting services
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Directorate General of
Water Resources 300,000 0 0 300,000 China
Total 300,000 0 0 300,000
GB-20-05-2
29
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th
30,000 75,000 120,000 75,000 300,000
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Civil Works 300,000
b. Consulting
services
c. Other
Total 300,000
13. Program Reference
BB-ID: BB-1519-R1-10
GB-20-06-2
30
1. Project Title : Riam Kiwa Multipurpose Dam
Construction Project
2. Program Title : Dam Development Program
3. Executing Agency : Ministry of Public Works and Housing
4. Implementing Agency : Directorate General of Water Resources,
Ministry of Public Works and Housing
5. Duration : 48 Months
6. Location : South Kalimantan Province
7. Objectives
a. To irrigate an area of 1.800 Ha
b. Reducing flood discharge at 797 M³ / sec
c. Provide raw water supply of 1,56 m³ / sec
d. And to generate electricity of 0,92 MW
8. Scope of Project
a. Civil works including access road; base-camp, pool heavy vehicle;
diversion channel; cofferdam; spillway; main dam; intake; and
electrical mechanical.
b. Consulting services.
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Civil work South
Kalimantan
Province
Directorate General of
Water Resources, Ministry
of Public Works and
Housing
b. Consulting services
GB-20-06-2
31
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Directorate General of
Water Resources,
Ministry of Public
Works and Housing
250,000 0 0 250,000 China
Total 250,000 0 0 250,000
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th
25,000 62,500 100,000 62,500 250,000
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Civil Works 250,000
b. Consulting
services
c. Other
Total 250,000
13. Program Reference
BB-ID: BB-1519-R1-10
GB-20-07-0
32
1. Project Title : Lambakan Dam Project
2. Program Title : Dam Development Program
3. Executing Agency : Ministry of Public Works and Housing
4. Implementing Agency : Directorate General of Water Resources
5. Duration : 60 Months
6. Location : East Kalimantan Province
7. Objectives
a. To irrigate an area of 23.000 Ha
b. Reducing flood discharge by 30%
c. Provide raw water supply of 5 m³ / sec
d. And to generate electricity of 19,44 MW
8. Scope of Project
a. Civil works including roads and bridge; diversion channel; spillway;
main dam; intake; hydro mechanical; and building facilities.
b. Consulting services.
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Civil Works East Kalimantan
Province, Paser
District
Directorate General of
Water Resources,
Ministry of Public
Works and Housing b. Consulting Services
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Directorate General of
Water Resources,
Ministry of Public
Works and Housing
450,000 0 97,058 547,058 China
Total 450,000 0 97,058 547,058
GB-20-07-0
33
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th 5th
27,353 82,059 164,117 164,117 109,412 547,058
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Civil works 450,000
b. Consulting
services 45,000
c. Other 52,058
Total 45,000 450,000 52,058
13. Program Reference
BB-ID: BB-1519-R1-10
GB-20-08-1
34
1. Project Title : Pelosika Multipurpose Dam Construction
Project
2. Program Title : Dam Development Program
3. Executing Agency : Ministry of Public Works and Housing
4. Implementing Agency : Directorate General of Water Resources
5. Duration : 60 Months
6. Location : South East Sulawesi Province
7. Objectives
a. To irrigate an area of 22.764 Ha
b. Reducing flood discharge at 647 m³ / sec
c. Provide raw water supply of 0.808 m³ / sec
d. And to generate electricity of 20 MW
8. Scope of Project
a. Civil works including access road; diversion channel; spillway; main
dam; intake; hydro mechanical; and building facilities.
b. Consulting services.
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Civil Works South East
Sulawesi
Province
Directorate General of
Water Resources,
Ministry of Public
Works and Housing b. Consulting Services
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Directorate General of
Water Resources,
Ministry of Public
Works and Housing
300,000 52,950 352,950 China
Total 300,000 52,950 352,950
GB-20-08-1
35
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th 5th
17,648 52,942 105,885 105,885 70,590 352,950
12. Funding Allocation*
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Civil works 229,501
b. Consulting
services 25,500
c. Other 44,999
Total 25,500 229,501 44,999
*) Not included local fund
13. Program Reference
BB-ID: BB-1519-R1-10
GB-20-09-2
36
1. Project Title : Karian Dam-Serpong Water Conveyance
System
2. Program Title : Provision and Management of Bulk Water
Supply Program
3. Executing Agency : Ministry of Public Works and Housing
4. Implementing Agency : Directorate General of Water Resources
5. Duration : 60 Months
6. Location : DKI Jakarta & Banten Province
7. Objectives
a. To supply raw water to Tangerang area (9,1 m3/sec, 786.240 m3/day)
and supply irrigation water (5,5 m3/sec, 475.200 m3/day) additionally
to Serang, Cilegon and Ciujung areas. Supply-able water capacity by
Karian Dam is 12,4 m3/sec (1.071.360 m3/day). Depending on water
demand in Tangerang Area, 6,2 m3/sec (535.680 m3/day) of it has been
distributed to Tangerang Area;
b. To increase the piped water service coverage to 40% for Banten Province
from the current level stands at piped 21 %, in which the 18% are
supplied by PDAMs and around 3% are supplied by private sectors;
c. To increase the service coverage pf Palyja (Western Jakarta) from 64%
to 80%;
d. To secure stable operation of water supply facilities through operation
improvement of 8 PDAMs & PAM Jaya. The target beneficiaries are to
serve around 4 million inhabitants or around 800.000 new connection;
e. To improve sanitation environment and living standards in Banten
Province and Special Region Jakarta.
8. Scope of Project
a. Main water conveyance pipeline.
b. Booster pumping and booster pumping station.
c. Branch conveyance pipeline
d. Electric receiving power
e. Instrumentation and control work.
GB-20-09-2
37
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Construction works Banten and DKI
Jakarta Province
Directorate General of
Water Resources, Ministry
of Public Works and
Housing
b. Construction
services
10. Funding Source
Implementing
Agency
Funding (US $ 000) Source
Loan Grant Local Total
Directorate General
of Water Resources,
Ministry of Public
Works and Housing
257,184 0 0 257,184 Korea
Total 257,184 0 0 257,184
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th 5th
12,859 38,578 77,155 77,155 51,437 257,184
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Civil Works 217,346
b. Consulting
services 15,033
c. Management 7,516
d. General
e. Other 17,289
Total 15,033 217,346 24,805
13. Program Reference
BB-ID: BB-1519-R0-09
39
40
Kementerian Perhubungan/Ministry
of Transportation
41
GB-20-10-1
42
1. Project Title : Patimban Port Development Project
(Phase I-2)
2. Program Title : Sea Transportation Development Program
3. Executing Agency : Ministry of Transportation
4. Implementing Agency : Directorate General of Sea Transportation
5. Duration : 48 Months
6. Location : Subang, West Java Province
7. Objectives
To sstrengthen the port logistics capacity of Jakarta Metropolitan Area and
improve the total economics activities in the region
8. Scope of Project
a. Civil works
b. Consulting services
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Civil works
Subang, West
Java Province
Directorate General of
Sea Transportation,
Ministry of
Transportation b. Construction services
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Directorate General of
Sea Transportation,
Ministry of
Transportation
674,948 0 0 674,948 JICA
Total 674,948 0 0 674,948
GB-20-10-1
43
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th
247,476 179,987 213,736 33,749 674,948
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Package 5
(Terminal for
Phase I-2)
487,423
b. Package 6
(Dredging 1) 90,213
c. Package 7
(Dredging 2) 97,312
Total 674,948
13. Program Reference
BB-ID: BB-1519-R2-37
GB-20-11-1
44
1. Project Title : Development and Improvement of
Indonesian Aids to Navigation
2. Program Title : Sea Transportation Development Program
3. Executing Agency : Ministry of Transportation
4. Implementing Agency : Directorate of Navigation
5. Duration : 40 Months
6. Location : North Sulawesi, South Sulawesi, South
Kalimantan, West Kalimantan, East
Kalimantan, North Kalimantan, North
Sumatra, West Sumatra, South Sumatra, Riau
Islands, Central Java, East Java, DKI Jakarta,
Bali, East Nusa Tenggara, Maluku, Papua, and
West Papua Province
7. Objectives
a. The enhancement of reliability level on the 8 lighthouses and 95 light
beacons in 20 Districts of Navigation
b. The enhancement of the AtoN Technology on the 8 lighthouses and
95 light beaconw in 20 Districts of Navigation
c. The enhancement of the availability on the AtoN spare parts on 20
District of Navigation
8. Scope of Project
a. Lighthouse
b. Light Buoy
GB-20-11-1
45
9. Activities
Activities Implementation
Locations
Project
Implementation
Units
a. Project management
services
North Sulawesi,
South Sulawesi,
South Kalimantan,
West Kalimantan,
East Kalimantan,
North Kalimantan,
North Sumatra, West
Sumatra, South
Sumatra, Riau
Islands, Central Java,
East Java, DKI
Jakarta, Bali, East
Nusa Tenggara,
Maluku, Papua, and
West Papua Province
Directorate of
Navigation,
Ministry of
Transportation
b. Consulting services
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Directorate of
Navigation 67,255 0 4,464 71,719 Korea
Total 67,255 0 4,464 71,719
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th
2,732 16,910 29,314 22,763 71,719
GB-20-11-1
46
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Construction 51,869
b. Consulting
services 7,214
c. Project
Management 886
d. Contingencies 8,105
e. Services
Charge 67
f. Others 3,578
Total 8,167 51,869 11,683
13. Program Reference
BB-ID: BB-1519-R2-37
47
48
Kementerian Kesehatan/Ministry of
Health
49
GB-20-12-1
50
1. Project Title : Strengthening of National Referral Hospitals
and Vertical Technical Units
2. Program Title : Health Services Referral Program
3. Executing Agency : Ministry of Health
4. Implementing Agency : Ministry of Health
5. Duration : 60 Months
6. Location : West Java, DKI Jakarta, South Sulawesi, DI
Yogyakarta, and Bali Province
7. Objectives
a. To improve access and quality of mother and child health services,
oncology, respiratory, and stem cells
b. To improve infrastructures, facilities, medical and nonmedical
equipment.
c. To improve capacity of human resources
d. To strengthen collaboration between hospitals, referral systems and
its networks
8. Scope of Project
a. Construction work
b. Procurement of health infrastructures and equipment
c. Improvement of human resource capacity
d. Strengthening institutional capacity
e. Improvement of emergency preparedness
GB-20-12-1
51
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Building
West Java, DKI
Jakarta, South
Sulawesi, DI
Yogyakarta, and
Bali Province
a. RSUP Dr. Hasan
Sadikin Bandung
b. RSUP Persahabatan
Jakarta
c. RS Kanker
Dharmais Jakarta
d. RSUP Dr. Wahidin
Sudirohusodo
Makassar
e. RSUP Dr. Sardjito
Yogyakarta
f. RSUP Sanglah
Denpasar
b. Medical equipment
c. Non-medical
Equipment
d. Interior and
furniture
e. Human resources
development
(including research,
fellowship, and
trainings)
f. Hospital Institutions
g. Emergency
Preparedness
h. Project management
i. Financial auditing
10. Funding Source
Implementing
Agency
Funding (US $ 000) Source
Loan Grant Local Total
Directorate General
of Health Service,
Ministry of Health
261,718 0 30,594 292,312 IsDB
Total 261,718 0 30,594 292,312
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th 5th
5,340 66,012 100,854 97,346 22,760 292,312
GB-20-12-1
52
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Building 154,238
b. Medical
Equipment 95,326
c. Non-medical
Equipment 8,283
d. Interior and
Furniture 4,433
e. Human
Resources
Development
11,176
f. Hospital
Institutions 2,555
g. Emergency
Preparedness 3,245
h. Project
Management 12,891
i. Financial
auditing 165
Total 12,891 154,238 108,042 14,421 2,720
13. Program Reference
BB-ID:BB-1519-R2-23
53
54
Kementerian Pendidikan dan
Kebudayaan/ Ministry of Education
and Culture
55
GB-20-13-1
56
1. Project Title : The Quality Improvement Academic Hospital
of Brawijaya University
2. Program Title : Improving Access, Quality, Relevance, and
Competitiveness of Higher Education Program
3. Executing Agency : Ministry of Education and Culture
4. Implementing Agency : a) Directorate General of Higher Education
b) University of Brawijaya
5. Duration : 36 Months
6. Location : Malang City, East Java Province
7. Objectives
a. To enhance University of Brawijaya capacity in delivering medical
education, research, and health services through the completion of
academic hospital construction and provision of required medical and
research equipment as well as staff capacity development.
b. To develop University of Brawijaya’s specific excellences through the
development of Pain Centre, Cardiovascular Centre, Kidney Centre,
Emergency Centre, Infertility Centre, and Research Centre within the
academic hospital.
8. Scope of Project
a. Construction of three towers of University of Brawijaya Hospital
(RSUB) and one building of Dental & Mouth Hospital (RSGM).
b. Procurement of RSUB and RSGM medical and research equipment.
c. Human resource development through non-degree training.
d. Project management.
GB-20-13-1
57
9. Activities
Activities Implementation
Location
Project Implementation
Unit
a. Construction of RSUB
and RSGM
Malang City,
East Java
Province
University of
Brawijaya
b. Procurement of RSUB
and RSGM medical and
research equipment
c. Human resource
development through
non-degree training
d. Project Management
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
University of Brawijaya 39,444 0 4,167 43,611 KfW
Total 39,444 0 4,167 43,611
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3th
9,702 27,097 6,812 43,611
GB-20-13-1
58
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Construction of
University of
Brawijaya
Hospital
6,190 26,014
b. Construction of
Dental & Mouth
Hospital
3,584 5,564
c. Human Resource
Development 153
d. Consultant 573
e. Project
Management 321
f. Contingency 1,212
Total 894 9,774 31,578 153 1,212
13. Program Reference
BB-ID: BB-1519-R1-17
GB-20-14-1
59
1. Project Title : Higher Education for Technology and Innovation
(HETI)
2. Program Title : Improving Access, Quality, Relevance, and
Competitiveness of Higher Education Program
3. Executing Agency : Ministry of Education and Culture
4. Implementing
Agency
: a) Directorate General of Higher Education
b) Institute of Technology Sepuluh Nopember (ITS)
c) University of Lampung (Unila)
5. Duration : 60 Months
6. Location : East Java Province and Lampung Province
7. Objectives
The general objectives are to improve the quality of graduates and to
enhance market-based research in two public Higher Education
Institutions (HEIs) which lead to economic development within the HEIs
area. For each HEI, the objectives are:
a. Institute of Technology Sepuluh Nopember (ITS)
1) To improve ITS teaching and research quality towards a World
Class University;
2) To strengthen ITS science and techno park (STP) as a hub for
innovation creation in triple-helix collaboration scheme through
the improvement of Centre for Maritime, Centre for Automotive,
Centre for Creative Industry facilities, and Advanced ICT and
Robotic Centre;
3) To provide distinct academic facility, namely ITS Tower for
several study programs;
4) To equip ITS graduates with language skills and cultural
knowledge required by the global labour market; and
5) To develop ITS human resource capacity in managing research
and innovation commercialization.
GB-20-14-1
60
b. University of Lampung (Unila)
1) To strengthen Unila medical education and research capacity
through the development of Type C Teaching Hospital that
provide services especially in tropical disease, endocrine and
metabolism, geriatrics and medical rehabilitation cases;
2) To enhance Unila research and entrepreneurship capability
through the development of research centres in tropical medicine,
biomolecular, genetic and degenerative diseases, pathology and
toxicology, clinical trial and diagnostic trial laboratory, and
nutrition;
3) To increase the knowledge and competence of staff regarding
effective and efficient management of teaching hospital;
4) To expand the network and partnerships between Unila and
neighbouring hospitals, polytechnics, local government, and
industry.
8. Scope of Project
a. ITS
1) Construction of: four centres of technologies (Centre for Maritime,
Centre for Automotive, Centre for Creative Industry, and
Advanced ICT and Robotic Centre), one academic building ITS
Tower, and one Cultural and Language Centre;
2) Procurement of laboratory equipment, software, and furniture;
3) Staff capacity development;
4) Research and innovation grant, entrepreneurial grant, technical
expert, research and innovation bridging for STP-ITS;
5) Technical expert;
6) Infrastructure development; and
7) Project management.
b. Unila
1) Construction of: (1) two buildings of teaching hospital, (2) one
building of Integrated Research Centre (IRC), consists of five main
laboratories;
GB-20-14-1
61
2) Procurement of laboratory and teaching hospital equipment,
software, and furniture;
3) Staff capacity development;
4) Project management.
c. Project Management Unit (at Ministry of Education and Culture)
9. Activities
Activities Implementation
Location
Project Implementation
Unit
a. Building Constructions
of ITS
East Java
Province
Institute of Technology
Sepuluh November (ITS
Surabaya)
b. Infrastructure of ITS
c. Procurement of
Laboratory Equipment
of ITS
d. Human resource
development of ITS
e. Research and Innovation
Grant & Technical
Expert of ITS
f. Project management of
ITS
g. Building Constructions
of UNILA
Lampung
Province
Lampung University
(UNILA)
h. Infrastructure of UNILA
i. Procurement of Hospital
& Laboratory
Equipment of UNILA
j. Human Resource
development of UNILA
k. Project management of
UNILA
GB-20-14-1
62
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
a. Institute of
Technology Sepuluh
Nopember (ITS
Surabaya)
39,325 0 6,451 45,776 ADB
b. University of
Lampung (UNILA) 38,150 0 6,114 44,264 ADB
c. PMU 2,000 0 550 2,550 ADB
Total 79,475 0 13,115 92,590
11. Disbursement Plan
Implementing
Agency
Disbursement Plan (US $ 000) Total
1st 2nd 3th 4th 5th
ITS 4,704 18,130 12,922 4,199 5,820 45,775
UNILA 3,605 7,831 11,394 14,553 6,882 44,265
PMU 552 552 533 456 456 2,550
GB-20-14-1
63
12. Funding Allocation
IA Activities Category (US $ 000)
Services Constructions Goods Training Other
ITS
a. Buildings
Construction &
Infrastructure
13,953
b. Procurement of
Equipment,
Software,
Furniture, and
IT
14,484
c. Human
Resources
Development
6,499
d. Consultancy
Services 1,556
e. Operational
Cost 1,900
f. Tax & Duties 4,132
UNILA
a. Buildings
Construction &
Infrastructure
3,251
b. Procurement of
Equipment 14,178
c. Human
Resources
Development
12,091
d. Consultancy
Services 7,516
e. Operational
Cost 2,259 1,802
f. Tax & Duties 3,785
g. Contingency 2,634
PMU a. Operational
Cost 2,550
Total 3,815 28,131 26,575 14,015 20,054
13. Program Reference
BB-ID: BB-1519-R1-17
64
65
Kementerian Pertahanan / Ministry
of Defense
66
GB-20-15-3
67
1. Project Title : Upgrading Medical Equipment and
Supporting Facilities for Army Hospital
Pelamonia
2. Program Title : Military Hospitals Development Program
3. Executing Agency : Ministry of Defense
4. Implementing Agency : Indonesian Army
5. Duration : 12 Months
6. Location : Makassar, South Sulawesi Province
7. Objectives
To increase medical service quality to the Army, Indonesia Army
employee and family, and general society.
8. Scope of Project
a. Procurement of medical equipment
b. Installation and equipment try out
c. Training and equipment maintenance
9. Activities
Activities Implementation
Location
Project Implementation
Unit
a. Procurement of medical
equipment
Makassar City,
South Sulawesi
Province
a. Ministry of Defense
b. Indonesian Army
b. Pre-installation and
installation
c. Training
d. Logistics management
and maintenance
10.Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Indonesian Army 10,000 10,000 Hungary
Total 10,000 10,000
GB-20-15-3
68
11.Disbursement Plan
Disbursement Plan (US $ 000) Total
1st
10,000 10,000
12.Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Procurement
of medical
equipment
9,000
b. Installation
and testing the
equipment
800
c. Training and
maintenance of
equipment
200
Total 800 9,000 200
13.Program Reference
BB-ID: BB-1519-R1-3
GB-20-16-1
69
1. Project Title : Upgrading Medical Equipments and
Supporting Facilities for Army Hospital
Soedjono Magelang
2. Program Title : Military Hospital Development Program
3. Executing Agency : Ministry of Defense
4. Implementing Agency : 1. Ministry of Defense
2. Health Center Indonesian Army
5. Duration : 24 Months
6. Location : Magelang City, Central Java Province
7. Objectives
To increase medical service quality to the Army, Indonesia Army
employee and family, and general society.
8. Scope of Project
a. Procurement and instalment of medical equipment in Soedjono
Magelang Hospital. 7 surgery room facilities (nervous, orthopaedic,
otorhinolaryngology, digestive, urology, general surgeon, obstetrics
and gynaecology), preparation and recovery center tools, sterilization
kit, radiology/ imaging, other polyclinic tools (ophthalmology,
obstetrics and cardiovascular, dentistry, medical check-up, medical
rehabilitation), and emergency room tools.
b. Training for health workers to operate medical equipment.
c. Training for maintenance of medical equipment.
9.Activities
Activities Implementation
Location
Project Implementation
Unit
a. Design and planning
Magelang City,
Central Java
Province
a. Ministry of Defense
b. Health Center
Indonesian Army
b. Procurement
c. Transport and delivery
d. Installation
e. Testing and
commissioning
f. User training
g. Handling over
GB-20-16-1
70
10.Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
a. Ministry of Defense
15,000 0 0 15,000 Hungary b. Health Center
Indonesian Army
Total 15,000 0 0 15,000
11.Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd
13,875 1,125 15,000
12.Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Procurement
of medical
equipment
72 13,181 247
b. Installation
and testing
the
equipment
1,200
c. Training and
maintenance
of
equipment
300
Total 72 14,381 300 247
13.Program Reference
BB-ID: BB-1519-R1-33
GB-20-17-1
71
1. Project Title : Upgrading Medical Equipments and
Supporting Facilities for Army Hospital
Dustira Bandung
2. Program Title : Military Hospital Development Program
3. Executing Agency : Ministry of Defense
4. Implementing Agency : 1. Ministry of Defense
2. Health Center Indonesian Army
5. Duration : 24 Months
6. Location : Cimahi City, West Java Province
7. Objectives
To increase medical service quality to the Army, Indonesia Army
employee and family, and general society.
8. Scope of Project
a. Procurement and instalment of medical equipment in Hospital
Dustira Bandung (8 surgery rooms of Nervous, Cardiovascular,
Orthopaedic, Obstetrics and Gynaecology, Urology, Ophthalmology,
Otorhinolaryngology, General Surgeon, Obsygn IGD, ICU).
b. Training and recruitment of health workers for operating medical
equipment.
c. Training for maintenance of medical equipment and hospital system
development.
9. Activities
Activities Implementation
Location
Project Implementation
Unit
a. Procurement of medical
equipment
Cimahi City,
West Java
Province
a. Ministry of
Defense
b. Health Center
Indonesian Army
b. Installation and testing
the equipment
c. Training and
maintenance of
equipment
GB-20-17-1
72
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
a. Ministry of Defense
10,000 0 0 10,000 Hungary b. Health Center
Indonesian Army
Total 10,000 0 0 10,000
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd
9,250 750 10,000
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Procurement
of medical
equipment
48 8,787 165
b. Installation
and testing
the
equipment
800
c. Training and
maintenance
of
equipment
200
Total 48 9,587 200 165
13. Program Reference
BB-ID: BB-1519-R1-33
GB-20-18-3
73
1. Project Title : Upgrading Medical Equipments and
Supporting Facilities for Army Hospital
Udayana
2. Program Title : Military Hospitals Development Program
3. Executing Agency : Ministry of Defense
4. Implementing Agency : Indonesian Army
5. Duration : 12 Months
6. Location : Denpasar, Bali Province
7. Objectives
To increase medical service quality to the Army, Indonesia Army
employee and family, and general society.
8. Scope of Project
a. Procurement of medical equipment
b. Installation and equipment try out
c. Training and equipment maintenance
9. Activities
Activities Implementation
Location
Project Implementation
Unit
a. Procurement of medical
equipment
Denpasar, Bali
a. Ministry of
Defense
b. Indonesian Army
b. Pre-installation and
installation
c. Training
d. Logistics management
and maintenance
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Indonesian Army 10,000 10,000 Austria
Total 10,000 10,000
GB-20-18-3
74
11.Disbursement Plan
Disbursement Plan (US $ 000) Total
1st
10,000 10,000
12.Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Procurement
of medical
equipment
9,000
b. Installation
and testing
the
equipment
800
c. Training and
maintenance
of equipment
200
Total 800 9,000 200
13.Program Reference
BB-ID: BB-1519-R1-33
GB-20-19-1
75
1. Project Title : Upgrading Medical Equipments and
Supporting Facilities for Naval Hospital dr.
Ramelan Surabaya
2. Program Title : Military Hospital Development Program
3. Executing Agency : Ministry of Defense
4. Implementing Agency : 1. Ministry of Defense
2. Indonesian Army
5. Duration : 18 Months
6. Location : Surabaya City, East Java Province
7. Objectives
To increase the quality of medical services for navy personnel, retired
families, and public.
8. Scope of Project
a. Procurement and instalment of medical equipment in Naval Hospital
dr. Ramelan Surabaya.
b. Training and recruitment of health workers for operating medical
equipment.
c. Training for maintenance of medical equipment and hospital system
development.
9. Activities
Activities Implementation
Location
Project Implementation
Unit
a. Procurement of medical
equipment Surabaya City,
East Java
Province
a. Ministry of Defense
b. Indonesian Army b. Pre-installation and
installation
c. Training
GB-20-19-1
76
10.Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
a. Ministry of Defense 15,000 0 0 15,000 Austria
b. Indonesian Army
Total 15,000 0 0 15,000
11.Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd
14,119 881 15,000
12.Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Procurement
of medical
equipment
13,719
b. Installation
and testing
the
equipment
873
c. Training and
maintenance
of
equipment
408
Total 14,592 408
13.Program Reference
BB-ID: BB-1519-R1-33
GB-20-20-1
77
1. Project Title : Upgrading Medical Equipments and
Supporting Facilities for Naval Hospital dr.
R. Oetojo Sorong
2. Program Title : Military Hospital Development Program
3. Executing Agency : Ministry of Defense
4. Implementing Agency : 1. Ministry of Defense
2. Indonesian Army
5. Duration : 18 Months
6. Location : Sorong City, West Papua Province
7. Objectives
To increase the quality of medical services for navy personnel, families,
and public.
8. Scope of Project
a. Procurement and instalment of medical equipment in dr. R. Oetojo
Sorong Hospital. 11 type of equipment (Operating room, Recovery
room, Sterilization, Radiology, Nutrition service, Clinical Pathology,
Emergency installation, Midwifery, Intensive Space, Forensic and
Specialist Polyclinic).
b. Training to operate medical and maintenance of medical equipment.
9. Activities
Activities Implementation
Location
Project Implementation
Unit
a. Procurement,
transportation and
delivery and insurance Sorong City,
West Papua
Province
a. Ministry of Defense
b. Indonesian Army b. Installation
c. Testing and
commissioning
d. User training
GB-20-20-1
78
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
a. Ministry of Defense 15,000 0 0 15,000 Austria
b. Indonesian Army
Total 15,000 0 0 15,000
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd
14,119 881 15,000
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Procurement of
medical
equipment,
transport and
delivery and
insurance
12,750
b. Installation and
testing the
equipment
1,925
c. Training and
maintenance of
equipment
325
Total 14,675 325
13. Program Reference
BB-ID: BB-1519-R1-33
GB-20-21-1
79
1. Project Title : Upgrading Medical Equipments and
Supporting Facilities for Air Force Hospital
Suhardi Hardjolukito Yogyakarta
2. Program Title : Military Hospital Development Program
3. Executing Agency : Ministry of Defense
4. Implementing Agency : Indonesian Army
5. Duration : 24 Months
6. Location : Bantul City, Special Region Yogyakarta
Province
7. Objectives
To increase the quality of medical services for air force personnel, families,
and public.
8. Scope of Project
a. Procurement and instalment of medical equipment in Air Force
Hospital Suhardi Hardjolukito Yogyakarta
b. Training and recruitment of health workers for operating medical
equipment.
c. Training for maintenance of medical equipment and hospital system
development.
9. Activities
Activities Implementation
Location
Project Implementation
Unit
a. Procurement Bantul City,
Special Region
Yogyakarta
Province
Indonesian Army
b. Installation
c. Testing and
commissioning
d. User training
GB-20-21-1
80
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Indonesian Army 11,561 0 0 11,561 Austria
Total 11,561 0 0 11,561
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd
10,810 751 11,561
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Procurement of
equipment 10,752
b. Installation and
testing 231
c. Preparation of
planning and
supervision
578
Total 578 10,983
13. Program Reference
BB-ID: BB-1519-R1-33
GB-20-22-1
81
1. Project Title : Upgrading Medical Equipments and
Supporting Facilities for Air Force Hospital
Muhammad Sutomo Pontianak
2. Program Title : Military Hospital Development Program
3. Executing Agency : Ministry of Defense
4. Implementing Agency : Indonesian Army
5. Duration : 24 Months
6. Location : Kubu Raya Regency, West Kalimantan
Province
7. Objectives
To increase the quality of medical services for navy personnel, families,
and public.
8. Scope of Project
a. Procurement and instalments of medical equipment in Muhammad
Sutomo Pontianak Hospital.
b. Training and recruitment of health workers for operating medical
equipment.
c. Training for maintenance of medical equipment and hospital system
development.
9. Activities
Activities Implementation
Location
Project Implementation
Unit
a. Procurement of medical
equipment Kubu Raya
City, West
Kalimantan
Province
Indonesian Army b. Training and testing the
equipment
c. Maintenance of
equipment
GB-20-22-1
82
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Indonesian Army 13,438 0 0 13,438 Austria
Total 13,438 0 0 13,438
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd
12,498 940 13,438
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Procurement of
medical
equipment
12,498
b. Training and
testing the
equipment
268
c. Maintenance of
equipment 672
Total 12,766 672
13. Program Reference
BB-ID: BB-1519-R1-33
83
84
Kementerian Ketenagakerjaan/
Ministry of Manpower
85
GB-20-23-2
86
1. Project Title : Maritime Vocational Training Center in
Serang
2. Program Title : Improving Labor Competitiveness Program
3. Executing Agency : Ministry of Manpower
4. Implementing Agency : a. Directorate General of Training and
Productivity, Ministry of Manpower
b. Maritime Training Center
5. Duration : 36 months
6. Location : Serang, Banten Province
7. Objectives
To preparation of skilled and competent labor in the maritime field.
8. Scope of Project
a. Preparation of program and training on electrical and welding.
b. Preparation of the infrastructure building workshop and vocational
welding and electrical classrooms.
c. Procurement of welding and electrical training equipment at BBPLK
Serang.
d. Training of trainers (ToT).
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Equipment
procurement
Serang, Banten
Province
a. Directorate General of
Training and
Productivity, Ministry
of Manpower
b. Maritime Training
Center
b. Construction of
building
c. Instructor training
d. Program
development,
module and training
management
GB-20-23-2
87
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total*
a. Directorate General of
Training and
Productivity, Ministry
of Manpower 17,700 0 0 17,700 Austria
b. Maritime Training
Center
Total 17,700 0 0 17,700
*) Equivalent EUR 14,888
11. Disbursement Plan
Disbursement Plan (US $ 000) Total*
1st 2nd 3rd
13,532 2,990 1,178 17,700
*) Equivalent EUR 14,888
12. Funding Allocation*
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Equipment
procurement 10,877
b. Construction
of building 3,386
c. Infrastructure
training 929
d. Program
development,
module and
training
management
2,508
Total 10,877 3,386 3,437
*) Equivalent EUR 14,888
13. Program Reference
BB-ID: BB-1519-R0-26
GB-20-24-2
88
1. Project Title : Maritime Vocational Training Center in
Makassar
2. Program Title : Improving Labor Competitiveness Program
3. Executing Agency : Ministry of Manpower
4. Implementing Agency : a. Directorate General of Training and
Productivity, Ministry of Manpower
b. Maritime Training Center
5. Duration : 36 months
6. Location : Makassar, South Sulawesi Province
7. Objectives
To preparation of skilled and competent labour in the maritime field.
8. Scope of Project
a. Preparation of program and training on automotive/maritime engines,
electrical, metal, wood, maritime wood-glasfiber and welding.
b. Preparation of the construction of metal, maritime wood-glasfiber,
and welding workshops building.
c. Procurement of automotive/maritime engines, electrical, metal,
maritime wood-glasfiber and welding training equipment.
d. Training of trainers (ToT).
e. Program and training development.
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Equipment
procurement
Makassar,
Province of
South Sulawesi
a. Directorate General of
Training and
Productivity, Ministry
of Manpower
b. Maritime Training
Center
b. Construction of
building
c. Infrastructure
training
d. Program
development,
module and training
management
GB-20-24-2
89
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total*
a. Directorate
General of
Training and
Productivity,
Ministry of
Manpower
13,600 0 0 13,600 Austria
b. Maritime Training
Center
Total 13,600 0 0 13,600
*) Equivalent EUR 12,599.5
11. Disbursement Plan
Disbursement Plan (US $ 000) Total*
1st 2nd 3rd
10,880 2,034 686 13,600
*) Equivalent EUR 12,599.5
GB-20-24-2
90
12. Funding Allocation*
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Equipment
procurement 5,723
b. Construction
of building 4,577
c. Infrastructure
training 201
d. Program
development,
module and
training
management
3,099
Total 5,723 4,577 3,300
*) Equivalent EUR 12,599.5
13. Program Reference
BB-ID: BB-1519-R0-26
91
92
Kementerian Komunikasi dan
Informatika/Ministry of
Communication and Information
Technology
93
GB-20-25-1
94
1. Project Title : Strengthening of e-Government
Infrastructure
2. Program Title : Information Communication and Technology
(ICT) and Broadcasting Infrastructure
Development Program
3. Executing Agency : Ministry of Communication and Information
Technology
4. Implementing Agency : a) Ministry of Communication and
Information Technology
b) State Cyber and Cryptography Agency
5. Duration : 60 months
6. Location : 2 Provinces (to be selected)
7. Objectives
a. Avoiding silos and creating new synergies in G2G.
b. Enhancing security at all levels.
c. Creating a coherent technical framework to deploy new services.
d. Reducing costs of maintenance and operations.
e. Identifying a dedicated budget shared by different ministries and
agencies.
f. Enhancing competencies in digital applications inside the
government.
g. Launching new services: G2G, G2B, G2C, G2E & E2E.
h. Providing the ideal support to develop e-government support.
8. Scope of Project
a. Construction and implementation of 4 National data Centers (NDC)
capable of Government Cloud Computing (hosting government
application on virtualized machines), capable of the provision of
infrastructure as a Service, Platform as a Service, or Software as a
Service, Security as a Service and Big data Analytic.
b. Implementation of a high-availability Government Secured Network
(GSN), designed to interconnect 35 national agencies or sites of the
Central Government and the NDCs using encryption technology.
c. A Network Operation Centre (NOC), including a Security Operation
Center (SOC), located at each NDC, in charge of the monitoring of the
GB-20-25-1
95
infrastructure and its security and of the enforcement of the IT
security policy.
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Development and
operational of
National Data
Center (NDC)
2 Provinces
(to be selected)
a. Directorate General of
Informatics Application,
Ministry of
Communication and
Information Technology
b. Directorate of
Government Informatics
Application Service (e-
Government), Ministry
of Communication and
Information Technology
c. State Cyber and
Cryptography Agency
d. Local governments
b. Development and
operational of
Indonesia’s
Disaster Recovery
Center (DRC
c. Development and
operational of
Indonesia’s
National Network
Operation Center
(NNOC)
d. Development and
operational of
Govt-CA
Indonesia
10. Funding Source
Implementing
Agency
Funding (US $ 000) Source
Loan Grant Local Total
Ministry of
Communication
and Information
Technology
190,300
10,000 40,000 400,300
France
160,000 Korea
Total 350,300 10,000 40,000 400,300
GB-20-25-1
96
11. Disbursement Plan*
France Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th 5th
35,184 72,279 82,837 0 0 190,300
Korea Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th 5th
24,804 64,294 70,900 0 0 160,000
*) not included grant portion and local fund
12. Funding Allocation*
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Construction of
Data Centers 273,777
b. Monitoring and
Security of the
Infrastructure
19,840
c. Construction of
Government
Secured
Network
10,187
d. Common
Services 40,350 6,146
Total 40,350 303,804 6,146
*) not included grant portion and local fund
13. Program Reference
BB-ID: BB-1519-R0-15
97
98
Kementerian Kelautan dan
Perikanan/ Ministry of Marine
Affairs and Fisheries
99
GB-20-26-0
100
1. Project Title : Outer Ring Fishing Ports Development (Eco
Fishing Port)
2. Program Title : Improvement of Fisheries Facilities Program
3. Executing Agency : Ministry of Marine Affairs and Fisheries
4. Implementing Agency : Ministry of Marine Affairs and Fisheries
5. Duration : 60 months
6. Location : South Sumatra, North Sulawesi, Southeast
Sulawesi, and Bangka Belitung Province
7. Objectives
To develop an environmentally-friendly fishing ports (eco fishing ports)
to serve fishermen and other stakeholders in the fishing port and to
comply with international standards to increase Indonesia’s fisheries
export.
8. Scope of Project
a. Civil port work in Bitung, Kendari, Sungailiat, and Belawan
b. Transversal component, which includes: Electronic Reporting System
dan Port Management System
c. Capacity building
d. Consultancy services, which includes Consultant to Support (CTS) the
Ministry of Marine Affairs and Fisheries, ISO 14001, and Energy Study
for Support of Fishing Port Operation
e. Unforeseen expenses
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Civil works South Sumatra, North
Sulawesi, Southeast
Sulawesi, and Bangka
Belitung Province
Ministry of Marine
Affairs and Fisherie
b. Transversal
component
c. Consultancy
d. Unforeseen
GB-20-26-0
101
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Ministry of Marine
Affairs and Fisheries 105,350 2,155 4,619 112,124 AFD
Total 105,350 2,155 4,619 112,124
11.Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th 5th
245 1,037 43,251 34,862 32,729 112,124
12.Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Construction
works 80,111
b. Transversal
component 16,283
c. Consultancy 9,037
d. Unforeseen 6,693
Total 9,037 80,111 16,283 6,693
13.Program Reference
BB-ID: BB-1519-R0-27
102
103
Lembaga Ilmu Pengetahuan
Indonesia/ Indonesian Institute of
Sciences
104
GB-20-27-2
105
1. Project Title : Procurement of Multi Purposes Research
Vessels
2. Program Title : Marine Research Development Program
3. Executing Agency : Indonesian Institute of Sciences
4. Implementing Agency : Deputy Chairman of Earth Science
5. Duration : 60 months
6. Location : Domestic and overseas
7. Objectives
a. To provide a marine research facility in the form of Research Vessels
comprises one new Research Vessel and one retrofit Research Vessel,
KR Baruna Jaya VIII;
b. To support marine research within all the Exclusive Economic Zone
(ZEE) of Indonesia area and also outside the Indonesia’s jurisdiction
water area;
c. To improve marine resources exploration and exploitation capacity
whether biological or non-biological, marine tourism, and fisheries in
sustainable way; and
d. To develop a Fleet Management Unit (FMU) and build the capacity
through training, technical assistance, and further education to ensure
the infestation will deliver sustainable benefits.
8. Scope of Project
a. Preparation and development of technical design
b. The construction of one new vessel and installment of scientific
instrument
c. Retrofit of KR. Baruna Jaya VIII
d. Supervision of vessel construction
e. Capacity building (training and dissemination, joint expedition)
f. Testing, commissioning and handover including general maintenance
GB-20-27-2
106
9. Activities
Activities Implementation
Locations
Project
Implementation Units
a. Preparation and
development of
technical design
DKI Jakarta
Province*
Deputy Chairman of
Earth Science
b. The construction of
vessel and installment
of scientific instrument
Overseas
shipyard
c. Retrofit of KR. Baruna
Jaya VIII
Domestic
shipyard
d. Supervision of vessel
construction Indonesia
e. Capacity building Donor country
f. Testing, commissioning
and handover Indonesia
10. Funding Source
Implementing
Agency
Funding (US $ 000) Source
Loan Grant Local Total
Deputy Chairman
of Earth Science 107,851 0 2,942 110,793 AFD
Total 107,851 0 2,942 110,793
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th 5th
48,627 33,776 18,801 6,790 2,799 110,793
GB-20-27-2
107
12. Funding Allocation
Activities
Category (US $ 000)
Services Constructions Goods Trainings Other
a. Construction of
Retrofit KR.
Baruna Jaya
VIII
15,876
b. Construction of
a new vessel 79,970
c. Capacity
Building 14,947
Total 95,846 14,947
13. Program Reference
BB-ID: BB-1519-R1-35
108
109
Badan Meteorologi Klimatologi dan
Geofisika/ The Agency for Meteorology,
Climatology, and Geophysics
110
GB-20-28-0
111
1. Project Title : Strengthening Flight Information Region
and Development of Aviation Meteorology
Services in Eastern Indonesia
2. Program Title : Program for Development and Guidance of
Meteorology, Climatology and Geophysics
3. Executing Agency : Meteorology, Climatology, and Geophysics
Agency (BMKG)
4. Implementing Agency : Meteorology, Climatology, and Geophysics
Agency (BMKG)
5. Duration : 36 months
6. Location : Nationwide
7. Objectives
To strengthen Flight Information Region (FIR) and to develop aviation
meteorological services especially in Eastern Indonesia, for the sake of
safety and security in aviation operations, as well as modernization of the
ability to observe and forecast volcanic ash in order to prevent accidents
and to reduce the impact of volcanic eruptions towards the national
economy.
8. Scope of Project
a. Automated Weather Observing System (AWOS) for 6 airports in
Indonesia
b. X-Band Windshear Weather Radar as TDWR for 7 airports in
Indonesia
c. Windshear Wind LIDAR for 7 airports in Indonesia
d. LIDAR Volcanic Ash 3D for 5 airports in Indonesia
e. National Integration System
f. National Volcanic Ash Advisory System
g. Capacity building
GB-20-28-0
112
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Manufacturing
Western (FIR) and
Eastern Indonesia
Meteorology,
Climatology, and
Geophysics Agency
b. Configuration and
testing
c. Shipping
d. Installation
e. Capacity building
10. Funding Source
Implementing
Agency
Funding (US $ 000) Source
Loan Grant Local Total
Meteorology,
Climatology, and
Geophysics Agency
26,617 0 0 26,617 Finland
Total 26,617 0 0 26,617
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd
560 16,844 9,213 26,617
GB-20-28-0
113
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Others
Automated
Weather
Observing System
(AWOS)
3,354
X-Band Windshear
Weather Radar as
TDWR for 7
airports location
10,028
Windshear Wind
LIDAR for 7
airports in
Indonesia
6,946
LIDAR Volcanic
Ash 3D
4,962
National
Integration System:
National Volcanic
Ash Advisory
System
489
National Volcanic
Ash Advisory
System
332
Capacity building 506
Total 26,617
13. Program Reference
BB-ID:BB-1519-R1-28
114
Badan Informasi Geospasial/ The
Geospatial Information Agency
115
GB-20-29-0
116
1. Project Title : Program to Accelerate the Provision of Large-
Scale Base Maps (1:5000) for Sustainable
National Development
2. Program Title : Implementation of Geospatial Information
Program
3. Executing Agency : Geospatial Information Agency (BIG)
4. Implementing Agency : Geospatial Information Agency (BIG)
5. Duration : 48 months
6. Location : Nationwide
7. Objectives
a. To accelerate the provision of the large-scale basemaps (1:5.000) for
supporting sustainable national development in Indonesia. The large-
scale basemaps will be used for the thematic map reference by various
sectors for decision-making tools based on geospatial information.
b. Specific objectives, which includes:
1) the availability of the additional capacity for the mapping
production
2) the availability of the geospatial data to produce the countrywide
three dimensional (3D) geospatial information
3) the availability of the countrywide 3D geospatial information
8. Scope of Project
a. Preparation of a detailed plan, consists of several sub-components, as
follows:
1) Terms of Reference (TOR) of Program to Accelerate the Provision
of Large-Scale Basemaps;
2) Detailed Design of Geospatial Data Production Centre Building
Renovation;
3) Detailed Design of Basemaps Production System;
b. Establishment of Integrated Geospatial Data Production System,
consists of several sub-components, as follows:
1) Preparation (Rent) of Geospatial Data Production Centre
Building;
GB-20-29-0
117
2) Development of Integrated Geospatial Data Production System
Infrastructure;
c. Acquisition and Production of Large-Scale Geospatial Data (1:5,000)
of the entire country of Indonesia, consists of several sub-components,
as follows:
1) Acquisition of Geospatial Data of 1:5,000 Scale;
2) Production of Geospatial Information of 1:5,000 Scale;
3) Production of Geospatial Information of 1:25,000 Scale and
1:250,000 Scale;
d. Capacity Building and transfer of knowledge should cover technical
and management aspects for BIG’s personnel, trainers, and new
recruited personnel for project implementation.
e. Project Management and Work Supervision
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Goods Procurement
Nationwide Geospatial Information
Agency
b. Consulting Services
c. Construction Services
d. Other Services
10. Funding Source
Implementing Agency Funding (US $ 000)
Source Loan Grant Local Total
Geospatial Information
Agency 351,890 0 56,437 408,327 FKE
Total 351,890 0 56,437 408,327
11. Disbursement Plan*
Disbursement Plan (US $ 000) Total
1st 2nd 3rd 4th
79,706 146,191 90,744 35,249 351,890
*) Not included local fund
GB-20-29-0
118
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Establishment
of Integrated
Geospatial
Data
Production
System
20,669
b. Data
Acquisition
and
Production
of Large-
Scale
Geospatial
Data (1:5,000)
for the entire
country of
Indonesia
76,043 212,655
c. Capacity
Building 39,055
d. Project
Management
and Work
Supervision
3,468
Total 76,043 233,324 39,055 3,468
13. Program Reference
BB-ID: BB-1519-R1-34
119
120
PT. PLN/ State Electricity Company
121
GB-20-30-2
122
1. Project Title : Hululais Geothermal Power Plant 1 & 2 (2x55
MW)
2. Program Title : Electricity Infrastructure Development
Program
3. Executing Agency : State Electricity Company (PT. PLN)
4. Implementing Agency : State Electricity Company (PT. PLN)
5. Duration : 36 months
6. Location : Bengkulu Province
7. Objectives
a. To meet growing electricity demand in Sumatera by increasing power
generation installed capacity.
b. To increase the portion of renewable energy in national energy mix.
c. To decrease electricity production cost.
8. Scope of Project
a. Construction of 2x55 MW power plant
b. Construction of 150 kV transmission line
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Construction of 2x55 MW
power plant Bengkulu
Province
State Electricity
Company (PT. PLN) b. Construction of 150 kV
transmission line
c. Consulting Services
10. Funding Source
Implementing
Agency
Funding (US $ 000) Source
Loan Grant Local Total
State Electricity
Company (PT. PLN) 204,000 0 42,000 246,000 JICA
Total 204,000 0 42,000 246,000
GB-20-30-2
123
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd
49,200 98,400 98,400 246,000
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Construction
of 2x55 MW
power plant
238,000
b. Construction
of 150 kV
transmission
line
c. Consultant
Services 8,000
Total 8,000 238,000
13. Program Reference
BB-ID: BB-1519-R1-16
GB-20-31-2
124
1. Project Title : Additional Loan for Peusangan 1 & 2
Hydroelectric Power (87 MW)
2. Program Title : Electricity Infrastructure Development Program
3. Executing Agency : State Electricity Company (PT. PLN)
4. Implementing
Agency
: State Electricity Company (PT. PLN)
5. Duration : 26 months
6. Location : Aceh Province
7. Objectives
a. To meet growing electricity demand in Sumatra by increasing power
generation installed capacity.
b. To increase the portion of renewable energy in national energy mix
and reduce CO2 emissions.
8. Scope of Project
a. Civil works.
b. Metal works.
c. Electromechanical.
d. Construction of 150 kV transmission line substations.
e. Consulting services.
9. Activities
Activities Implementation
Locations
Project Implementation
Units
a. Civil works
Aceh Province State Electricity
Company (PT. PLN)
b. Metal works
c. Electromechanical
d. Construction of 150 kV
transmission line and
substation
e. Consulting service
GB-20-31-2
125
10. Funding Source
Implementing
Agency
Funding (US $ 000) Source
Loan Grant Local Total
State Electricity
Company (PT.
PLN)
131,045 0 8,987 140,032 JICA
Total 131,045 0 8,987 140,032
11. Disbursement Plan
Disbursement Plan (US $ 000) Total
1st 2nd 3rd
79,542 39,786 20,794 140,032
12. Funding Allocation
Activities Category (US $ 000)
Services Constructions Goods Trainings Other
a. Civil works
and
equipment
work
112,602
b. Consulting
service 21,958
c. Others 5,472
Total 140,032
13. Program Reference
BB-ID: BB-1519-R1-16
126
127