+ All Categories
Home > Documents > REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT...

REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT...

Date post: 01-Jun-2020
Category:
Upload: others
View: 6 times
Download: 0 times
Share this document with a friend
65
AFRICAN DEVELOPMENT BANK GROUP OPERATIONS EVALUATION DEPARTMENT (OPEV) REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD) PROJECT PERFORMANCE EVALUATION REPORT (PPER) PROJECT AND PROGRAM EVALUATION DIVISION (OPEV.1) MAY 2012
Transcript
Page 1: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

AFRICAN DEVELOPMENT BANK GROUP

OPERATIONS EVALUATION DEPARTMENT (OPEV)

REPUBLIC OF SENEGAL

DAKAR CITY SANITATION PROJECT (PAVD)

PROJECT PERFORMANCE EVALUATION

REPORT (PPER)

PROJECT AND PROGRAM EVALUATION DIVISION (OPEV.1)

MAY 2012

Page 2: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

TABLE OF CONTENTS

Currency Equivalents and Abbreviations i-ii

Acknowledgements iii

Basic Project Data iv-vi

Executive Summary vii-xi

I. THE PROJECT 1

1.1 Context 1

1.2 Project Formulation 2

1.3 Project Objectives 2

1.4 Project Description 3

II. POST EVALUATION 3

2.1 Evaluation Approach and Methodology 3

2.3 2.2 Availability and Use of Baseline Data and Key Performance Indicators 3

III. IMPLEMENTATION PERFORMANCE 4

3.1 Adherence to Implementation Schedule and Costs 4

3.2 Project Management, Reporting, Monitoring and Evaluation 4

3.2 Overall Implementation Performance 5

IV. KEY EVALUATION FINDINGS AND PERFORMANCE RATINGS 5

4.1 Key Evaluation Findings 5

(a) Relevance and Quality at Entry Assessment 5

(b) Achievement of Objectives and Outcomes (Efficacy) 7

(c) Efficiency 13

(d) Institutional Development Impact 13

(e) Other Development Impacts 14

(f) Sustainability 14

4.2 Performance Ratings 16

(a) Overall Project Performance and Outcomes 16

(b) Borrower Performance 16

(c) Bank Performance 17

4.3 Factors Affecting Implementation Performance and Outcomes 17

V. CONCLUSION, LESSONS AND RECOMMENDATIONS 17

5.1 Conclusion 17

5.2 Main Lessons 18

5.3 Main Recommendations 18

Page 3: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

TECHNICAL ANNEX TABLES Paragr.

Table 1 : Changes in the Design Parameters of the Cambérène Wastewater

Treatment Plant (WWTP)

1

Table 2 : Project Components 2

Table 3 : Rehabilitation and the Second Extension of STEREAU 5

Table 4 : Trends in Pumped Volumes from 2007 to 2010 7

Table 5 : Characterization of the Effluents of Treatment Systems 1 and 2 8

Table 6 : Characterization of the Effluents Discharged into the Sea after Pre-

treatment (35% of daily flow)

8

Table 7 : Current Sludge Output in the Cambérène Wastewater Treatment Plant 10

Table 8 : Percentage of VSS/SM of Sludge Produced by the Cambérène

Wastewater Treatment Plant

10

Table 9 : Trends in Some Cases of Diseases caused by Poor Hygiene and

Sanitation in the Project Area and in Pikine Between 2007 and 2009

12

Table 10 : Level of Cost Reduction of the Cambérène Wastewater Treatment Plant

Extension Component

13

ANNEXES Number of

pages

1. Map of Dakar and PAVD Intervention Areas 1

2. Logic Model of the Project 1

3. Socioeconomic and Macroeconomic Data 2

4. Project Technical Aspects 8

5. Rating Tables and Evaluation Criteria 8

6. Borrower Performance 2

7. Bank Performance 2

8. ONAS’ Financial Situation 2

9. Bibliography 3

Page 4: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

i

CURRENCY EQUIVALENTS AND ABBREVIATIONS

CURRENCY EQUIVALENTS

Currency Unit Appraisal

(January 2001)

Implementation

(July 2004 – Dec. 2008)

Completion

(2009)

Post Evaluation

(August 2011)

UA 1 CFAF 916.06

2005 : 793.75

2007 : 706.65

2008 : 766.91

CFAF 703.06 CFAF 735.54

UA 1 EUR 1.40

2005 : 1.18

2007 : 1.12

2008 : 1.08

EUR 1.14 EUR 1.12

UA 1 USD 1.30

2005 : 1.48

2007 : 1.53

2008 : 1.59

USD 1.51 USD 1.60

WEIGHTS AND MEASURES Metric System

LIST OF ACRONYMS AND ABBREVIATIONS

ADF : African Development Fund

AFD : French Development Agency

ANSD : National Agency for Statistics and Demography

BD : Bidding Documents

BOD : Biological Oxygen Demand

COD : Chemical Oxygen Demand

CSP : Country Strategy Paper

DAC : Development Assistance Committee

DET : Directorate of Studies and Works

DEX : Directorate of Operations

ECD : European Commission Delegation

EIRR : Economic Internal Rate of Return

ESIA : Environmental and Social Impact Assessment

ESMP : Environmental and Social Management Plan

FAO : Food and Agriculture Organization of the United Nations

FIRR : Financial Internal Rate of Return

GVT : Government

ICEA : Associated Consulting Engineers and Economists

IDA : International Development Association

IEC : Information, Education and Communication

IsDB : Islamic Development Bank

LWSP : Long-term Water Sector Programme

MDGs : Millennium Development Goals

LVDP : Low-Voltage Distribution Panel

OM : Oxidizable Material

ONAS : National Sanitation Authority of Senegal

PAVD : Dakar City Sanitation Project

EPIC : Industrial and Commercial Public Establishment

PPER : Project Performance Evaluation Report

PS : Pumping Station

Page 5: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

ii

SARAR : Self-Esteem-Associative Strength - Resourcefulness - Action Planning - Responsibility

SDE : Senegal Water Company

SM : Suspended Matter

SONEES : Senegal National Water Exploitation Corporation

SONES : Senegal National Water Corporation

SS : Senegalese Standards

WWTP : Wastewater Treatment Plant

UA : Unit of Account

WSP : Water Sector Project

Page 6: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

iii

ACKNOWLEDGEMENTS

This post evaluation report was prepared by a

team of the Operations Evaluation

Department (OPEV) of the African

Development Bank (AfDB) Group led by

Joseph Mouanda, Evaluation Officer (Project

Manager) and Tonssour Clément Bansé,

Research Assistant, under the supervision of

Mohamed Hédi Manaï, Division Manager,

Project and Program Evaluation.

The report is based on technical papers

written by Pierre BELLO, International

Consultant – Water and Sanitation Specialist,

and Ousseynou Guene, Local Consultant –

Sanitation Engineer and Environmentalist, as

well as the findings of the mission to Senegal

from 22 August to 2 September 2011.

The evaluation’s peer reviewers were

Penelope Jackson, Principal Evaluation

Officer, and administrative support was

provided by Myrtha Diop, Ruby Adzobu-

Agyare and Imen Trabelsi.

The evaluation team is grateful to Mahecor

Ndiaye, Senior Water and Sanitation

Engineer (OWAS); Xavier Boulanger, Chief

Irrigation Engineer (SNFO); and to the

colleagues of the Senegal Field

Office (SNFO) for their support and

comments. The team greatly appreciates the

close involvement and significant

contributions of Ousmane DIONE, ONAS’

Director of Studies and Works (former

Project Coordinator), Pèdre SY, Dakar II

(ONAS) Division Manager, who is

responsible for the operation of the serviced

plots (Parcelles Assainies) wastewater

collection network and the Cambérène

Wastewater Treatment Plant. The evaluation

team is also grateful to the populations of the

serviced plots for the time taken by them to

share their everyday experiences.

The evaluation team also expresses its sincere

appreciation to the Senegalese authorities,

particularly the mayors and heads of the

districts and sectors covered by the sub-

programme for their availability and

collaboration, as well as to the development

partners based in Dakar, including JICA, the

French Development Agency, the European

Commission Delegation and the Islamic

Development Bank for sharing their

experiences.

This work would not have been successful

without the enlightened leadership of OPEV

Management.

OPEV Management

Rakesh Nangia, Director, OPEV

Franck Marie Perrault, Acting Director (at the time of evaluation)

Mohamed Hedi Mohamed, Division Manager, Project and Programme Evaluation, OPEV.1

Odile Keller, Division Manager, High Level Evaluations, OPEV.2

Page 7: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

iv

BASIC PROJECT DATA

A- Preliminary Data 1. Country : Republic of Senegal

2. Project Name : Dakar City Sanitation Project (PAVD)

3. Project Code : P-SN-E00-002

4. Sector : Water and Sanitation

5. Loan Number : 2100150000855

6. Borrower : Republic of Senegal

7. Project Executing Agency : National Sanitation Authority of Senegal (ONAS)

8. Environmental Category : II

B- Loan Data

Estimated Actual

Loan amount (UA million) : 11.93 11.87

Service charge : 0.75%

Commitment fee : 0.50%

Grace period : 10 years

Appraisal date : February 2001

Loan approval date : 12 July 2001

Loan signature date : 12 October 2001 26 October 2001

Effectiveness date : 12 January 2002 22 August 2002

Date of fulfilment of conditions precedent

to first disbursement

:

January 2002 28 January 2004

Date of first disbursement : 21 September 2004

Date of last disbursement : 31 December 2006 28 August 2009

Closing date : 31 December 2006 30 June 2009

C- Project Data

Financing Plan (in UA million)

Source

Estimates at Appraisal Actual

Foreign

Exchange

Local

Currency Total %

Foreign

Exchange

Local

Currency Total %

ADF loan 9.54 2.39 11.93 89 9.48 2.39 11.87 89

Government 0.00 1.52 1.52 11 0.00 1.52 1.52 11

Total 9.54 3.91 13.45 100 9.48 3.91 13.39 100

Estimated and Final Project Cost (in CFAF billion)

No. Component Estimated Cost Final Cost

ADF Gvt Total ADF Gvt Total

1. Extension of the Cambérène Wastewater Treatment Plant

6.952 0.687 7.639 5.685 0.24 5.925

2. Restructuring of Pumping in SP 2.326 0.375 2.701 1.868 0.678 2.546

3. IEC Programme 0.137 0.046 0.183 0.115 0.031 0.146

4. Studies, Supervision and Control 1.120 0.064 1.184 0.551 0 0.551

5. Institutional Support 0.238 0.009 0.247 0.104 0 0.104

6. Project Management 0.155 0.211 0.366 0.174 0.139 0.313

TOTAL (CFAF billion) 10.928 1.392 12.320 8.497 1.088 9.585

UA/CFAF Parity 916.057 in 2001 716 in 2008

Average Brent Price in USD/barrel 24.44 in 2001 54.41 in 2005 - 96.99 in 2008

Total (in UA million) 11.930 1.520 13.450 11.868 1.520 13.388

Page 8: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

v

D- Implementation Performance Indicators

Cost Overrun /Underrun (depreciation UA / CFAF) UA – 61.915 (- 0.5%)

(CFAF – 2.73 billion: – 22%)

Time underrun/overrun

- Slippage on loan effectiveness 7 months

- Slippage on fulfilment of conditions precedent to first disbursement 2 years

- Slippage on last disbursement 32 months

- Slippage on completion date at appraisal 20 months

Number of extensions of last disbursement deadline 1

Project implementation status Completed

Rate of Return

Appraisal Completion Post-Evaluation

Economic rate of return

Financial rate of return

E- Performance Rating

Evaluation Criteria PCR PCR Review PPER

1.

Relevance and quality at entry assessment Highly satisfactory Satisfactory Unsatisfactory

Relevance Highly satisfactory Highly satisfactory Satisfactory

Quality at entry assessment Satisfactory Unsatisfactory Unsatisfactory

2. Efficacy (achievement of objectives) Satisfactory Unsatisfactory Unsatisfactory

3. Efficiency Satisfactory Unsatisfactory Unsatisfactory

4. Sustainability Unsatisfactory Unsatisfactory

5. Institutional impact Unsatisfactory

Aggregate Performance Rating Satisfactory Unsatisfactory Unsatisfactory

6. Borrower Performance Satisfactory Unsatisfactory Unsatisfactory

7. Bank Performance Satisfactory Satisfactory Unsatisfactory

F- Missions

No. Type of Mission Date Number of

Persons Composition

1. Preliminary

Appraisal February 2001 3

1 sanitation engineer, 1 financial

analyst, 1 environmentalist

2. Launching 30 October to 6 November 2001 2 1 financial analyst, 1 engineer

3. Supervision 9 to 17 November 2003 2 1 financial analyst, 1 engineer

4. Supervision 8 to 16 November 2004 2 1 division manager, 1 engineer

5. Supervision 1 to 8 July 2005 1 1 engineer

6. Supervision 19 to 25 December 2005 3 1 engineer, ...

7. Supervision 4 to 8 December 2006 3 2 engineers, 1 operations assistant

8. Supervision 19 June to 5 July 2007 2 2 engineers

9. Supervision 13 to 27 November 2007 4 3 engineers, 1 portfolio data analyst

10. Supervision 11 to 26 June 2008 3 2 engineers, 1 portfolio data analyst

11. Supervision 24 November to 9 December 2008 3 2 engineers, 1 portfolio data analyst

12. PCR 6 December to 14 December 2009 6 1 rural engineer, 2 water and

sanitation engineers, 1 financial

manager, 1 socio-economist

13. PPER 22 August to 2 September 2011 4

1 evaluation officer, 1 evaluation

assistant, 1 water and sanitation

specialist, 1 sanitation engineer and

environmentalist

Page 9: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

vi

G - Other Water and Sanitation Sector Projects Financed by the Bank Group in Senegal

No. Project Approval

Date

Approved

Amount

(UA thousand)

Net Amount

(UA

thousand)

Disbursement

Rate (%) Status

1. Water Supply Project- Dakar and

Environs.- 16/12/1975 9 565.00 5 960.50 100.0 Completed

2. Run-off Water Storage Studies 24/4/1980 940.45 938.36 100.0 Completed

3. Dakar City Sanitation Project

(Phase II) 16/12/1982 12 000.00 11 985.56 100.0 Completed

4. Rural DWSS Programme 21/09/2005 29 000.00 24 921.59 100.0 Completed

5. Ziguinchor Sanitation Master Plan 22/12/2006 866.35 712.61 81.14 Ongoing

6. Implementation of the Senegal

PAGIRE 31/8/2007 1 580.00 1 364.01 100.0 Ongoing

7. Second Rural DWSS Sub-

programme 18/2/2009 33 415.00 30 000.00 25.47 Ongoing

TOTAL 87 366.80 56 572.56

Page 10: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

vii

EXECUTIVE SUMMARY

1. The Project

1.1 This Project Performance Evaluation Report (PPER) presents the findings of the post

evaluation of the Dakar City Sanitation Project (PAVD). The project was financed by an

African Development Fund (ADF) UA 11.93 million loan. The loan, which was approved on

12 July 2001 by the Board of Directors of the African Development Bank Group, aimed at

supporting the efforts made by the Government of the Republic of Senegal to address the

renewed outbreak of diseases caused by unsanitary conditions. The project’s goal is to improve

the social, health and environmental conditions of the population in the urban and peri-urban

areas of the city of Dakar targeted by the project.

1.2 In terms of outcomes, the project was expected to: (i) increase the domestic wastewater

treatment capacity of the Cambérène Treatment Plant; (ii) increase the domestic wastewater

pumping capacity in the serviced plots (Parcelles Assainies) neighbourhood; (ii) promote the

adoption of good hygiene and sanitation practices; (iv) build ONAS’ organizational capacity;

(v) enhance wastewater treatment by-products (wastewater, sludge and methane gas); (vi)

improve the quality of water discharged into the sea; (vii) reduce the incidence of diseases

caused by poor hygiene and sanitation; and (viii) build ONAS’ operational capacity.

1.3 The project comprised six components, the two main ones of which were: (i) the

extension of the Cambérène Wastewater Treatment Plant and (ii) the restructuring of the

domestic wastewater pumping system in the serviced plots neighbourhood. The total project

cost fell slightly from UA 13.45 million at project appraisal (2001) to UA 13.39 million at

project completion (2008). In addition, due to the depreciation of the UA against the

EUR/CFAF, the initial total project cost denominated in CFAF dropped sharply by nearly 22%,

resulting in a significant reduction in the project’s scope and reach.

2. Methodological Approach

The evaluation process comprised four phases, namely (i) analysis of project documents and

other works and publications; (ii) data collection in Senegal, including interviews and group

discussions with key stakeholders; (iii) field visits to the project area, including the direct

observation of the application of good practices; and (iv) analysis and drafting of the evaluation

report. The analytical method combined the comparison of the situation in the project area

before and after project implementation on the one hand, and the situation with (serviced plots)

and without (Pikine) the project, on the other hand.

3. Key Findings

3.1 The project is considered to be relevant insofar as its objectives and components are

fully in line with Government’s priorities in the drinking water supply and sanitation sector; it

is a continuation of the Long-term Water Sector Programme (which is the cornerstone of the

sector’s long-term strategy. The project addresses a real need of the inhabitants of Dakar and

its environs who are faced with serious sanitation problems. It is also consistent with the Bank’s

strategy for Senegal (1999-2001) which seeks to strengthen social facilities in urban and peri-

urban areas under the “infrastructure” pillar. The city of Dakar has huge constantly changing

sanitation needs.

3.2 On the contrary, quality at entry assessment is deemed to be unsatisfactory owing to:

(i) inadequate consideration of constraints related to the treatment process retained (activated

Page 11: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

viii

sludge) in the Dakar context.; (ii) validation by the Bank of a partial and sub-optimal solution

to address financial constraints; and (iii) the failure to consider past lessons on the inclusion of

stormwater and other solid waste.

3.3 In addition, the design eclipsed the problem posed by the existing sewage outfall1 with

substandard hydraulic characteristics and unguaranteed durability. It was also limited to the

restructuring of the existing sanitation network without any extension to facilitate household

connection. Lastly, the ex ante evaluation underestimated the project cost and no genuine

environmental and social impact assessment was carried out.

3.4 Concerning physical outputs, out of the two new units with a wastewater treatment

capacity of 10 000 m3/d each (that is 20 000 m3/d in total), the project was able to build only an

incomplete unit (without a sludge system) with a capacity of 11 300 m3/d. Overall, the project

has helped to increase the secondary treatment capacity of the Cambérène Wastewater

Treatment Plant from 5 700 m3/d to only 17 000 m3/d due to a drastic reduction in the volume

of work initially planned for this component. However, the project has significantly improved

the wastewater pumping system of the serviced plots neighbourhood (comprising 26 units) by

restructuring the network and building the capacity of the pumping system (rehabilitation of

five plants and construction of four others), thus increasing the volume of wastewater

discharged through the Cambérène Wastewater Treatment Plant.

3.5 Concerning functionality, the engineering structures and facilities built in the

Cambérène Wastewater Treatment Plant under the project are functioning normally. In contrast,

some of the pre-treatment facilities built in 20042 are out of order and are said to be3 under

rehabilitation. At the time of the mission, the plant was temporarily shut down closed due to

heavy rain in Dakar which flooded the plant, particularly the power station which is the heart

of the system.

3.6 All the hydraulic and electromechanical equipment of the wastewater pumping system

in the serviced plots is operational, albeit with a few recurrent breakdowns. The metallic

equipment (composed mainly of generators and surge tanks) has been damaged owing to

exposure to ocean currents. Overall, frequent power cuts impede the smooth functioning of all

project engineering structures, although their negative impact is mitigated by the use of

generators installed in each plant.

3.7 Due to the inadequate treatment capacity of the plant in relation to the volume of

wastewater entering it, part of the pre-treated effluent (by-pass) is rerouted. The excess sludge

and purified effluent, which cannot be treated, is eliminated. This is a result of failure to

construct a third treatment system which seriously undermines the plant’s efficiency. . Given

the mixture of treated water with by-passed water, the level of raw wastewater discharged

directly into the sea and the lack of enhancement of wastewater treatment by-products, the

project falls within a system whose existing discharge does meet environmental quality

standards. The situation is exacerbated by failure to resolve the problem of the sea outfall as the

existing discharge is much too close to the shore to protect the coastline from pollution. Given

the technical and energy requirements of activated sludge systems and their extreme sensitivity

to variations in the flow rate and load as well as the low level of investment in relation to the

scope of needs, this poor performance was more or less predictable.

1 Not mentioned in the evaluation report. 2 Through International Development Association (IDA) financing. 3 According to the DET of ONAS.

Page 12: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

ix

3.8 Beneficiaries’ behaviour and attitude towards infrastructure, which have not changed

significantly despite the implementation of various IEC activities which are still ephemeral,

also hamper project efficacy. Consequently, the project’s contribution to the improvement of

the social, sanitary and environmental conditions of the target population remains limited. On

the whole, the achievement of project objectives and outcomes (efficacy) is deemed to be

unsatisfactory.

3.9 As regards efficiency, the project’s economic benefits have been limited by: (i) the

reduction in the anticipated physical outputs; (ii) the poor performance of the biological

treatment of the Cambérène Wastewater Treatment Plant 4; and (iii) inadequate enhancement of

treatment by-products. The sub-sector’s incapacity to generate sufficient resources to refinance

its activities has adversely affected the project’s financial viability. Indeed, the fees collected

through users’ water bills and government subsidies are not enough to cover ONAS’ operating

expenses which increase in tandem with investments made. Like the plant, the project is

considered to be inefficient.

3.10 The project has helped to initiate the building of organizational, technical and financial

capacity and strengthening of internal communication. However, the government has not

fulfilled the condition of the loan agreement regarding the increase of the sanitation levy, as

ONAS continues to depend mainly on operating subsidies to maintain a fragile balance of

annual income statements. At sector level, the project had no major impact on planning,

implementation and monitoring capacity. On the whole, the project’s impact on institutional

development is deemed to be unsatisfactory.

3.11 The sustainability of project outcomes cannot be guaranteed for several reasons,

namely: (i) ONAS’ weak financial and material capacity given that the government has not met

its commitments contained in the performance contract concluded with ONAS; (ii)

unpredictable power cuts which oblige ONAS to use emergency power generators which are

costly but essential; (iii) difficulties in supplying fuel due to ONAS’ financial problems; and

(iv) the project’s negative environmental impact. For the moment, the Government does not

seem to show a genuine commitment to improve ONAS’ worrisome situation, although

discussions are ongoing to find lasting solutions. The political agenda (2012 presidential

election) was likely to prolong the situation.

3.12 The overall project performance is deemed to be unsatisfactory.

4. Main Lessons

The emergence of a public-private partnership in the sanitation sector requires

an institutional framework that promotes: (i) the financial equilibrium of the

entity responsible for the technical, commercial and financial management of

sanitation services; (ii) the existence of a State-owned company that helps to

mobilize the funds needed to develop the sector and manage investment

contracts.

The adoption of a strategy for the development and efficient reuse of sanitation

by-products (treated wastewater, sludge and biogas) which is effectively

implemented is necessary for ensuring the efficiency of a treatment plant.

4 ONAS, EUROPEAID, 2009, “Details on the Capacity, Flow Rate and Level of Treatment of the Cambérène Treatment Plant”: Interim

Report of 30 November 2009.

Page 13: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

x

The adoption of a holistic approach through the inclusion of stormwater and

solid waste in a wastewater treatment project will provide more comprehensive

solutions to problems of liquid sanitation and insalubrity.

The systematic mainstreaming of Environmental and Social Impact Assessments

(ESIAs) in sanitation projects, particularly those concerning wastewater

treatment plants is more useful than an inefficient environmental categorization

strategy.

The uncontrolled profound modification of a project’s scope may result in the

use of sub-optimal solutions that adversely affect its efficiency.

5. Main Recommendations

To the Senegalese Government:

Adopt a programme approach: the Government should, on the basis of the new

Dakar Master Plan which is being finalized, go beyond an ad hoc management

of sanitation projects by adopting a coordinated multi-donor programme

approach in order to find solutions to Dakar’s chronic solid and liquid waste

management problems.

Build ONAS’ financial capacity: the Government should build ONAS’ financial

capacity by: (i) increasing the sanitation levy based on a new tariff schedule that

is effectively applied; (ii) ensuring the rigorous management of unpaid bills,

particularly those of government services; and (iii) looking for other sustainable

sources of funding to improve ONAS’ self-financing capacity.

Strengthen the sanitation sector in Senegal: the Government should envisage the

institutional restructuring of ONAS into: (i) a State-owned company responsible

for the direct mobilization of funds needed to develop the sub-sector and manage

investment contracts; and (ii) an operating company responsible solely for

technical, commercial and financial management of sanitation services.

Revise regulations: the Government should ensure compliance with the

regulations applicable to the operation of wastewater treatment plants (quality of

treated wastewater) for discharge on land and river environments and amend the

regulations on the discharge of treated wastewater into the sea by setting a

quality target for the natural environment that would guide the choice of

technical treatment arrangements.

To ONAS:

Formulate a strategy for the development and reuse of by-products: ONAS

should define a genuine strategy for the development and efficient reuse of

wastewater treatment by-products.

Page 14: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

xi

Improve the efficiency of the Cambérène wastewater treatment plant: ONAS

should: (i) upgrade the sludge system to limit the discharge of sludge with treated

effluent; (ii) protect the plant against the risk of flooding5; (iii) restore existing

pre-treatment equipment; (iv) carry on construction work to install the new sea

outfall as the existing one is too close to the beaches; and (iv) secure funding to

install the third treatment system within the framework of a comprehensive

Dakar City Sanitation Programme.

Ensure environmental protection: ONAS should systematically conduct, in

parallel with technical studies, ESIAs and ensure the holding of public

consultations to present projects as well as their environmental impacts and

mitigation measures (environmental management plans).

To the Bank:

Ensure quality at entry assessment: during project preparation, the Bank should

ensure the availability of key design studies and the technological options

retained for better cost estimation and reduction of implementation time frames

that undermine the outcomes of infrastructure projects. Exhaustive and quality

feasibility studies could necessitate funding by trust funds and should include

monitoring and evaluation, gender and environmental aspects as well as the

participation of beneficiaries. Furthermore, past lessons should be effectively

considered.

Modify the project: where financing is inadequate, the Bank should allow major

project modification only after assessing the impact of such modification with

respect to initial project objectives; otherwise, the Bank should ensure the

availability of additional financing to fill the gap.

Adopt the programme approach: the Bank should orient any new action related

to the sanitation of Dakar City within the framework of a comprehensive

programme that includes wastewater, stormwater and solid waste, in conjunction

with other financial partners.

Mainstream the conduct of environmental and social impact assessments in

sanitation projects: given the intrinsic nature of sanitation projects, particularly

those concerning wastewater treatment plants, the Bank should systematically

demand the conduct of environmental and social impact assessments with

environmental management plans including the resources needed for their

implementation.

5 Using the resources provided by the State.

Page 15: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

I. THE PROJECT

1.1 Context

1.1.1 Senegal is situated in the far-west of Africa. It covers a surface area of 196 722 square

kilometres. It is widely open to the Atlantic Ocean and has a 500-kilometre coastline which is

generally flat and sandy, with great tourism potential. Administratively, the country is divided

into 14 regions and 45 Departments sub-divided into districts, municipalities, villages and rural

communities. The village or neighbourhood is the basic administrative unit. Senegal’s

population increased significantly from 5.1 million in 19756 to 12.5 million in 2009, with an

average annual growth rate of 2.5%. It could reach 14.5 million in 2015. The urban population

was estimated at 5.1 million in 2009, representing an urbanization rate of about 42%.

1.1.2 From the macroeconomic perspective, since the devaluation of the CFA franc in 1994,

Senegal’s economy has been relatively dynamic with annual average growth rates of about 5%

(until 2001). In real terms, growth remained strong until 2005 (5.3%) before beginning to slow

down from 2006 when it stood at 2.3% due mainly to external shocks (rise in oil prices) and a

decline in agricultural production. After two years marked by the effects of the global financial

crisis, the Senegalese economy regained its dynamism, posting real GDP growth rates of 4.2%

and 4.1% in 2010 and 2011 respectively. Energy sector problems remain one of the main

obstacles to economic recovery7. However, the sound macro-economic performance recorded

during the 1997-2001 period was not enough to significantly reduce poverty. In fact, the

proportion of the population living below the poverty line dropped from 57.9% in 1994/1995

to 53.9% in 2000/2001, a decrease of 4 percentage points. During the 2005-2009 period, the

incidence of poverty stood at around 51%. Furthermore, Senegal, whose gross national income

per capita was estimated at USD 770 in 2010 (compared to USD 509 in 2001), is ranked among

the least developed countries and 144th out of 169 countries according to the 2010 Human

Development Report.

1.1.3 The Dakar region, which is located in the Cape Verde Peninsula, covers a surface area

of 550 square kilometres. Its population, which was estimated at 2.4 million in 20078, represents

nearly a quarter (22%) of the country’s total population. Another distinctive feature of the

region is its level of urbanization, with about half of the country’s urban population (53%) and

most of its population (97%) living in towns. The city of Dakar is a conurbation occupying

almost the whole available area. Its geographical expansion is now limited by the sea, with the

Atlantic Ocean to the north, south and west and Hann Bay to the east. It has a high population

density (822 400 inhabitants on 82 square kilometres) with an annual population growth rate of

between 4.5% and 5%. The high population density of Dakar exerts considerable pressure on

urban water and sanitation sector strategies and performance. In addition, the city is also an

industrial and commercial centre and most of the wastewater collected by the existing sanitation

network is discharged directly into the sea without any prior treatment9. In some areas, the

capacity of existing sewer facilities is low or they are poorly connected to drainage systems,

thus causing the spillage and stagnation of wastewater in open sumps, deterioration of the

quality of surface and ground water as well as coastal water resources, which degrades the

quality of the urban and marine environment.

6 1996 General Population Census (GPC). 7 AfDB-OECD-UNDP-ECA, Senegal 2010, Economic Outlook. 8 ANSDA “Economic and Social Situation of the Dakar Region in 2007 (Final Report)”, August 2008. 9 A survey carried out in 2004 by the Department of Sanitation shows that only 13% of households have access to the sanitation network

and only 14% of wastewater is treated in a wastewater treatment plant, while the remaining 86% is discharged into the sea without treatment (UN-HABITAT, Senegal – Dakar Urban Profile, 2004).

Page 16: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

2

1.1.4 This situation had led to the implementation of a water and sanitation sector reform as

well as sector projects10 in Senegal in the 1990s with the support of donors, including the

African Development Bank. However, concerning water and sanitation sector equilibrium,

successive Senegalese Governments have not adequately taken the sanitation issue into

account. Consequently, although Senegal is one of the few countries that are capable of

achieving the MDG target on access to safe drinking water, sanitation remains a major issue.

In fact, despite the significant mobilization of resources in the DWSS sector (CFAF 412 billion

between 2005 and 2008), the sanitation access rate remains relatively low and below forecasts.

The urban sanitation access rate rose from 57% in 2004 to 63% in 2008 and that of wastewater

treatment from 19% to 37% over the same period. In both cases, the prospects are not bright

and will very soon lead to a reversed trend if the mobilization of funds needed to continue to

subsidize access to sanitation and to build the capacity of wastewater treatment plants is not

guaranteed11.

1.2 Project Formulation

1.2.1 Project identification fell within the framework of Senegal’s Ninth Economic and

Social Development Plan (1996-2001) whose strategic thrusts include the improvement of the

quality of central government interventions in the provision of services and basic infrastructure.

The Water Sector Project (WSP) implemented by the Government with the support of its key

sector development partners (World Bank, AFD, CIDA and KfW) combines institutional

reforms and major investments for the construction of urban drinking water supply and

sanitation infrastructure.

1.2.2 Despite the strong performance of the WSP, significant needs remained to be met in

the sector, and new strategic approaches had to be envisaged in the medium and long term. This

assessment led to the implementation, in 1999, of a Long-term Water Sector Programme

(LWP), which includes “Drinking Water” and “Sanitation” components and is the cornerstone

of the Long-term Sector Strategy. The PAVD is part of this framework and reflects the Bank’s

commitment to carry on its sector operations by financing the extension of the Cambérène

wastewater treatment plant whose construction it had financed in 1982. The World Bank

provided support for its rehabilitation under the LWP. Bank missions were fielded to Senegal

in December 2000 and February 2001 to prepare and appraise the project.

1.3 Project Objectives

The project goal is to improve the socio-sanitary and environmental conditions of the urban and

peri-urban areas of the city of Dakar. Regarding impacts, the project was expected to: (i)

increase the domestic wastewater treatment capacity of the Cambérène Treatment Plant; (ii)

increase domestic wastewater pumping capacity in the serviced plots neighbourhood; (ii)

promote the adoption of good hygiene and sanitation practices; (iv) build ONAS’ organizational

capacity; (v) enhance treatment by-products (wastewater, sludge and methane gas); (vi)

improve the quality of water discharged into the sea; (vii) reduce the incidence of diseases

caused by poor hygiene and sanitation; and (viii) build ONAS’ operational capacity (see logic

model in Annex 2).

10 WSP (1995-2004), LWP (2001-2007) and PEPAM (2005-2015). 11 PEPAM, Joint Annual Review 2009.

Page 17: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

3

1.4 Project Description

1.4.1 The situation of wastewater treatment facilities in the project target area was mainly

characterized by: (i) sewer systems some of which had inadequate discharge capacity; (ii)

pumping stations situated in the serviced plots and their environs; (iii) a gravity collecting sewer

channelling wastewater to the treatment plant; and (iv) a domestic wastewater treatment plant

(WWTP). The main aim of the project was to address the weaknesses of the existing

infrastructure, particularly in the Cambérène Wastewater Treatment Plant and the wastewater

pumping system in the serviced plots area (see §1 of Annex 4).

1.4.2 The project comprises six components, namely: (i) extension of the Cambérène

Wastewater Treatment Plant; (ii) restructuring of the domestic wastewater pumping system of

the serviced plots neighbourhood; (iii) the Information, Education and Communication (IEC)

Programme; (iv) works studies, supervision and control; (v) institutional support; and (vi)

project management (see §2 of Annex 4).

II. POST- EVALUATION

2.1 Evaluation Approach and Methodology

2.1.1 The aim of this evaluation is to contribute to improving the Bank’s on-going or future

operations, policies and strategies by building knowledge and formulating relevant

recommendations to enhance the Bank’s efficiency. The outcomes of this evaluation will also

be used within the framework of a more comprehensive study on the Bank’s efficiency in the

water and sanitation sector. The study is based on the criteria adopted by DAC12 to evaluate

development assistance activities, namely relevance, efficiency, efficacy, impact and

sustainability. To these main criteria should be added Borrower performance and Bank

performance. It is also based on Good Practice Standards for the Evaluation of Public Sector

Operations developed by the Evaluation Cooperation Group13.

2.1.2 The evaluation was carried out in four phases, namely (i) the analysis of project

documents and other works and publications; (ii) data collection in Senegal, including

interviews and group discussions with key stakeholders; (iii) field visits to the project area,

including the direct observation of the application of good practices; and (iv) the analysis and

drafting of the evaluation report. The analytical method combined a comparison of the situation

in the project area before and after project implementation, on the one hand, and the situation

with (serviced plots) and without (Pikine) the project, on the other hand.

2.2 Availability and Use of Baseline Data and Key Performance Indicators

2.2.1 Available baseline data and key outcome indicators relate to the physical outputs,

water and pollution balances presented in ONAS’ annual and monthly operating reports, in

accordance with the provisions of the performance contract concluded in August 2008 between

the government and ONAS. Other studies on the Cambérène Wastewater Treatment Plant

helped to complement the data on biological treatment performance, the level of discharge into

the sea as well as sludge production and sale.

2.2.2 The key indicators of outcomes relating to the improvement of health status and level

of education present the health (MSP-SNIS) and school (Departmental Inspectorate of

Education) statistics of the project area. These quantitative data were supplemented by

12 Development Assistance Committee. 13 Good Practices Standards for Evaluation of Public Sector Operations, 2001 Revised Edition, Third Draft of 22 May 2011.

Page 18: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

4

qualitative data obtained before or during the OPEV evaluation mission carried out in August

2011. On the other hand, data on the environmental monitoring of the receiving environment

were not available.

III. IMPLEMENTATION PERFORMANCE

3.1 Adherence to Implementation Schedule and Costs

3.1.1 The project was implemented with a 24-month delay due, in particular, to problems

faced by the Borrower in fulfilling the conditions precedent to first disbursement (17 months

after the effectiveness date). Furthermore, it was only in early May 2004 (nearly two and a half

years after the signature of the loan) that a coordination unit was established at the ONAS

Directorate of Studies and Works, marking the effective start-up of the project, particularly the

updating of existing bidding documents, the conduct of studies to determine technical

specifications for a turnkey solution to the extension of the Cambérène Wastewater Treatment

Plant.

3.1.2 As regards adherence to costs, there was a huge funding gap at project implementation

(see §3 of Annex 4). The basic data on estimated and final costs show that, although the total

project cost (-0.5%) was maintained in UA, it dropped from CFAF 12.32 billion to CFAF 9.58

billion, that is a decrease of about CFAF 2.74 billion (representing nearly 22% of the total cost).

Several factors account for the cost overrun of the “Cambérène Wastewater Treatment Plant

Extension” component, namely: (i) initial cost underestimation; (ii) foreign exchange losses

incurred between project approval (2001) and the effective start-up of works (2007) due to the

depreciation of the UA against the EUR and the CFAF; and (iii) the increase in the prices of

raw materials owing to an escalation of oil prices, the crude oil price having increased on

average from USD 24 per barrel in 2001 to USD 72 in 2007.

3.1.3 To close this gap, the Bank recommended that the Senegalese Government seek

additional funds from the European Union from its financial envelope to support the sanitation

sector in Senegal (CFAF 7.87 billion). The failure of this initiative resulted in profound changes

including: (i) the moderation of initial objectives relating to the extension of the Cambérène

Wastewater Treatment Plant which was the main financial item of the project (62% of the initial

cost), thus modifying the nature of the project; (ii) the financing of the Djily Mbaye Pumping

Station by the Government due to the urgent need to upgrade it; and (iii) the financing of ONAS’

organizational study by the European Union.

3.2 Project Management, Reporting, Monitoring and Evaluation

3.2.1 Overall, the performance of the Project Implementation Unit (PIU) is considered to be

satisfactory while that of the executing agency (ONAS) is unsatisfactory due mainly to delays

in operationalizing the PIU and lifting of conditions precedent, resulting in the consequences

mentioned above. The executing agency submitted the required works status and audit reports

on a regular basis despite the lack of coordination14 between ONAS and the Bank regretted at

project start-up. The audit reports were sometimes submitted behind schedule15 and the quality

of the 2008 report was deemed to be unsatisfactory16.

14 AfDB, “Senegal: Portfolio Review Report 2003, ADB/BD/WP/2004/109 – ADF/BD/WP/2004/133. 15 June 2009 for that of 2007, contrary to the Bank’s guidelines (maximum period of six months, with effect from the closing date of the

financial year). 16 ORPF (Reference: ORPF.2/RPT/2010/029/ANE of 4 June 2010).

Page 19: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

5

3.2.2 Strictly speaking, the project had no monitoring and evaluation system to help ensure

the systematic collection of relevant data with clear responsibilities and a well-defined

frequency of data collection. The few monitoring actions carried out focused only on physical

outputs, eclipsing project outcomes and impacts. However, improvements have been made

following the signing of a performance contract between the Senegalese Government and

ONAS in 2008 defining a series of performance indicators, among other things. These

indicators are presented in the reports on the operation of facilities and annual progress reports

prepared by ONAS’ Management.

3.3 Overall Implementation Performance

3.3.1 In short, there were significant project implementation delays. In addition, though the

total project cost was still denominated in UA, the depreciation of the Unit of Account coupled

with rising oil prices and the underestimation of some costs necessitated the moderation of

physical output targets which significantly modified the project with respect to its initial

objectives. The engineering structures built meet required quality standards. The few anomalies

identified in pumping stations would be the result of design errors, particularly the calculation

of backflows, since piping is not commensurate with the capacity of these pumping stations.

On the whole, the overall implementation performance is considered to be unsatisfactory.

IV. KEY EVALUATION FINDINGS AND PERFORMANCE RATINGS

4.1 Key Evaluation Findings

(a) Relevance and Quality at Entry Assessment

Relevance

4.1.1 The rationale underpinning the Dakar City Sanitation Project (PAVD) is a concern to

support the Government’s efforts to address the renewed outbreak of diseases caused by

unsanitary conditions. By limiting itself to restructuring the existing network and failing to

extend it, the project did not adequately address the needs of a large number of households that

are not covered by the urban sanitation network because their connection was difficult and

costly.

4.1.2 The project is in keeping with the Government’s strategy outlined in Senegal’s Ninth

Economic and Social Development Plan (1996-2001). The plan’s major thrusts include: (i)

improving central government interventions in the provision of basic services and

infrastructure, and (ii) ensuring sound water resource management. The project objectives are

a continuation of those of the Long-term Water Sector Programme (LWSP) considered as the

cornerstone of the long-term sector strategy.

4.1.3 The PAVD is also consistent with the Bank’s strategy for Senegal ( 1999-2001 CSP)

which seeks primarily to promote robust and sustained economic growth within the framework

of sector investment programmes in order to reduce poverty. In the water and sanitation sector,

the strategy takes into account the Bank’s Integrated Water Resource Management Policy and

seeks to support actions aimed at improving the living environment of the population,

particularly through the development of social infrastructure in urban and peri-urban areas. The

project is also in line with the Bank’s general priority actions to reduce and achieve MDG

targets related to water and sanitation. The project objectives remain relevant insofar as the

constantly changing city of Dakar always has huge sanitation needs.

Page 20: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

6

Quality at Entry

4.1.4 Basic Technical Designs and Choice of Wastewater Treatment Processes: the PAVD

opted to extend the Cambérène Wastewater Treatment Plant whose basic technological options

were adopted during its initial construction17. The activated sludge process, which is based on

aerobic biological treatment, is the technical solution adopted for domestic wastewater

treatment. This process is widely used in West and Central Africa and Europe18. Although the

treatment performance and reliability of activated sludge systems are well-tested, particularly

in France, their operation has little flexibility and they are not easily adaptable to the context of

African countries (especially in terms of energy consumption) as they do not tolerate significant

flow changes. They are also too costly in terms of investment, operation and management and

are dependent on spare parts which are sometimes unavailable on the local market19. Although

the specific situation of Dakar (land constraints) limited the choice of alternative solutions20,

the PAVD did not adequately taken into account the technical and energy requirements of the

process retained and local (environmental, financial, economic and socio-political) and climatic

factors.

4.1.5 The initial project to build the plant and its different rehabilitation and extension

phases did not take the flood-prone nature of the site into account. This sometimes causes long

periods of malfunction21 because not all the interventions ensured the protection of electrical

equipment. This situation is currently exacerbated by the construction of the Rufisque highway,

especially as no drainage culvert to the south of the site to drain run-off water now trapped in a

basin. In fact, when selecting the site for the construction of the Cambérène Treatment Plant22,

land morphology (dunal landform with many basins) and the consequences of rainwater runoff

from the northern landforms were not adequately assessed.

4.1.6 The financial gap noted during bid evaluation suggests that the cost was

underestimated during project appraisal, although this is not the only cause. Lastly, the project

was not the subject of an in-depth environmental and social impact assessment23 leading to the

formulation of an environmental and social management plan (ESMP) and environmental

monitoring, which itself is a problem with this type of operations as they generally produce

major positive or negative environmental impacts.

4.1.7 Optimality of the Final Solution Approved by the Borrower and Validated by the Bank:

in reviewing the services to be provided by the successful bidder due to a financial gap that

could not be closed, the Borrower and the Bank retained a sub-optimal alternative solution

characterized by drastic reductions in the water and sludge systems that make up the core of the

project in favour of studies, general services and common works. The primary thickener, whose

installation could have contributed to ensuring the smooth operation of the existing facility and

prevent the direct discharge of sludge from the new biological treatment system was abandoned.

17 Financed by an African Development Bank loan approved on 30 April 1975. 18 Seventy-five per cent of the 155 wastewater treatment plants identified in 1993 (see op. cit). 19 Doulaye Koné, “Wastewater Treatment through Macrophyte Lagooning or Macrophytes (Pistia Stratiotes) in West and Central Africa:

Review, Treatment Performance and Design Criteria” Thesis No. 2653 (2000), Federal Institute of Technology, Lausanne. 20 With respect to other extensive processes which are natural (or artificial wetlands) wastewater treatment systems the best known of

which is macrophyte lagooning. Natural lagooning is the system most widely used in Morocco (99% of treatment plants) but only for small towns (<30 000 inhabitants)

21 The heavy rain of 19 and 20 August 2011 (50 mm of water in 24 hours), for example, damaged the retaining wall designed to protect the site which unfortunately gave way, resulting in the severe flooding of the entire treatment plant and many buildings (including the laboratory and electrical centre) and the shutdown of the plant for a prolonged period.

22 Retained following the recommendations of the first Sanitation Master Plan (SMP) prepared by NEDECO in 1973. 23 In light of those conducted by the European Union within the framework of its operations on the Cambérène Wastewater Treatment

Plant.

Page 21: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

7

In addition, the project did not adequately take into account the limitations of the existing land

and marine outfall 24 (see §4 of Annex 4) with substandard hydraulic characteristics,

unguaranteed robustness25 and zero utility in terms of the protection of the natural environment

(the maritime domain used purely for recreational purposes – swimming area), which is a source

of conflicts with the local population.

4.1.8 Consideration of Past Lessons: the project design did not take into account one of the

lessons learned from the evaluation of a previous Bank-funded project for wastewater treatment

in Dakar and its environs, namely the need to adopt a more integrated approach which includes

the management of stormwater and solid waste in sanitation projects. Although this lesson was

underscored in the ex ante evaluation report, stormwater and solid waste drainage systems were

not taken into account during PAVD design. In fact, during the rainy season26, part of the urban

run-off water enters the sanitation network due to lack of a genuine stormwater drainage system

in the connected urban areas (including the serviced plots). However, the network of serviced

plots, which has a separate wastewater treatment system, is not designed to handle the rainwater

channelled into it by the population, although this is prohibited27. This rainwater intake dilutes

the suspended matter load, disrupting the management base of the Cambérène Wastewater

Treatment Plant and the smooth operation of pumping stations. Overall, the project is

considered relevant, although its quality at entry is considered to be unsatisfactory.

(b) Achievement of Objectives and Outcomes (Efficacy)

Level of Achievement and Quality of Outputs

4.1.9 Wastewater Treatment Infrastructure (61% of total project cost at completion): out of

the two new wastewater treatment units each with a capacity of 10 000 m3/day, the project has

built only one incomplete unit (biological system) with a capacity of 11 300 m3/day (see §5 of

Annex 4) comprising an aeration tank and a final sedimentation tank. It has also helped to

upgrade the primary sedimentation tank of the old system 1 to an anoxic basin and provide the

treatment plant with electromechanical equipment (one low-voltage distribution panel, one

900-kVA power generator and three transformers). The project has not equipped the plant with

treatment and sludge recycling facilities28, as no thickener or mechanical sludge dehydration

mechanism has been installed under the project. The existing structures (digesters) do not have

the capacity to absorb sludge from the new system. Consequently, the sludge produced in the

new biological system is not treated and is discharged into the environment together with the

treated effluent.

4.1.10 Qualitatively, the structures built and the equipment supplied by the project are highly

satisfactory. However, the installation of the low voltage distribution panel (LVDP) re-

equipped by the project in an area that is frequently flooded due to the rising water table and

resumption of rainfall cycles, among other things, causing the shutdown of the entire plant for

safety reasons 29 , is regrettable. Plant operating reports show that, in recent years, the

operationality of structures has been affected by increased flow, resulting in the overflow of 24 This has been taken into account in an EU-funded project which is expected to raise its peak flow to about 52 000 m3/day and extend

the discharge from 200 metres to 1 700 metres at sea. Part of this outfall is mounted offshore pending its connection to the onshore part as this connection cannot be made without the consent of the local population.

25 Scientific Note on the Cambérène Outfall Project, ONAS, November 2010. 26 Which may represent up to 10 times the volume of wastewater discharged during rainfall of 20 millimetres per day. 27 The serviced plots only have an embryonic network that drains part of the rainwater from urban roads and some low sections and a

pumping station which discharges treated wastewater into the Niayes and other offshore gravity outfalls. 28 The temporary solution recommended (left to the initiative of the Implementation Unit and STEREAU), which consists in evacuating

biological sludge from wastewater treatment ponds to the digestion station, did not function properly as it caused thermal imbalance due to the abundant hydric flux used.

29 It is said that the State allocated resources for its relocation to the non-flooded parts of the treatment plant (ONAS / DET).

Page 22: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

8

wastewater entering the station, excessive silting of grit chambers, instability of pre-treatment

due to very advanced wear and tear and the flooding of the digester. In addition, the prolonged

shutdown of the 800-kVA generator and frequent power cuts, coupled with the problem of

sludge evaluation, do not allow for proper wastewater treatment.

4.1.11 Wastewater Pumping Infrastructure (28% of total project cost at completion): to

address the before-project situation, the Bank’s operation consisted mainly in: (i) optimizing

the system by enabling pumping stations to operate independently of each other; (ii) building

the capacity of the pumping system by rehabilitating30 and building new stations31 with new

equipment; (iii) securing the pumping system by installing new power generators in each

station; and (iv) rehabilitating backflow and defective gravity discharge networks that

frequently breakdown.

4.1.12 In terms of operationality, the data provided by the pumping station section of the

Cambérène Treatment Plant shows the recurrent breakdown of the hydraulic32 and electronic33

equipment procured. According to one of ONAS’ technicians, such breakdowns stem primarily

from design errors, particularly backflow calculations due to a mismatch between piping and

pump capacity 34 . Unpredictable power cuts on the entire SENELEC network require the

continuous use of power generators resulting in a significant increase in the use of fuel oil,

engine oil and spare parts for preventive maintenance.

4.1.13 Improving Knowledge of Good Health Practices and Sanitation Issues: through its IEC

component which targets the population of the serviced plots (about 250 00035 inhabitants in

20 units), the project has helped to implement a programme on health education and information

on the restructuring of the sanitation system in order to convince the population to accept the

inconveniences caused by such restructuring works. In addition, IEC campaigns have helped to

sensitize the population concerned on the mode of operation of community sanitation and to

encourage them to adopt facility-friendly behaviour. To this end, the project notably: (i)

organized an information meeting with 75 community leaders; (ii) trained 60 workers or

outreach officers on the use of the SARAR36 method and tools; (iii) established 25 health

committees; (iv) organized 103 neighbourhood meetings; and (v) informed and sensitized 1 542

households. In total, 15 549 people participated in an information/education session. A social

worker supervised the outreach officers and health committees at least once a week37.

4.1.14 Consequently, measures and initiatives were adopted, in accordance with SARAR tool

guidelines, to institute the systematic washing of hands with soap before meals, regular cleaning

of the surroundings of homes and the protection of food and drinking water. The conditioning

of solid waste which is a major concern for households in the project area was also instituted

and, with the influence of neighbourhood committees, measures were taken to prevent the

transformation of the wastewater network into a rubbish dump. Similarly, it was recommended

that syphon and sifter devices be installed at the outlets of pipes connected to the sanitation

network to separate solid waste from liquid waste.

30 SP7, SP23 and SP17 31 SP2, SP9, SP13, SP15, SP22 and the rehabilitation of the Djili Mbaye Station which was financed by national counterpart contributions. 32 These include the loss of sludge from ball check valves (SP15 and SP23); failure to replace the screen belt (SP23); leaks from surge

control valves (SP13, SP17, SP07 and SP22) and the failure to replace inverter cards and contactors (SP23, SP22 and SP07). 33 Electronic inverters often breakdown due to the unreliability of the electricity network (voltage variation). 34 Viewpoint that differs from that of DET, revealing some tension with DEX. 35 According to the municipal authorities, this population is currently estimated at 400 000. 36 This is a method based on the assumption that a population whose confidence is built is capable of using its own resources to improve

their living conditions, particularly sanitary conditions. 37 Moussa Seck and Francoise TOURE-KNOBEL, PAV - Mission Report 3: IEC Programme Evaluation, December 2008.

Page 23: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

9

4.1.15 ONAS’ Organizational Study and Information and Archiving System: to support

ONAS, which urgently needs to improve its operation and productivity, the recommended

review of positions under the institutional support component within the framework of the

project was replaced by a broader organizational study financed by the European Union and

conducted by the ICEA consulting firm. The main recommendations of the study resulted in

the implementation of a project with European Union assistance. This project, which is being

implemented, seeks to train ONAS staff in, and provide it with equipment for the remote

management of pumping stations, remote monitoring and a geographic information system

(GIS).

4.1.16 The PAVD was therefore limited to supporting ONAS’ Documentation Centre by

putting a relational information and archiving system and a functional database at its disposal.

The document scanning and electronic archiving system (in addition to a paper format

document archiving system) is now operational. In particular, it allowed the evaluation mission

to easily access project documents.

Achievement of Direct Outcomes

4.1.17 Improvement of Domestic Wastewater Treatment Capacity: the project, as planned and

appraised in 2001, intended to triple the capacity of the treatment plant to 30 000 m3/day (or

about 300 000 users). However, due to the drastic reduction in the volume of works included

initially in this component, the project was able to build only one biological treatment system

with a treatment capacity of 11 300 m3/day, or about 38% of the initial target. In addition, the

capacity of the first (before-project) system was reduced to 5 700 m3/day to adapt it to tertiary

treatment purposes carried out on-site. The Cambérène Wastewater Treatment Plant, therefore,

can currently handle only 17 000 m3/day for biological treatment38, whereas it receives an

annual average of 26 500 m3/day and much more during the rainy season.

4.1.18 In terms of performance, the Cambérène Wastewater Treatment Plant has the worst

water balance assessment39 of all treatment plants in Senegal. In fact, data on treatment and

operation monitoring shows that, in 2010, existing biological systems treated only 64% of the

total flow that entered the plant (9 653 955 m3)40. In other words, 36% of raw effluents were

bypassed41 and discharged as such into the natural environment, representing about 9 500 m3

of raw water per day. During the rainy season, the quantity of bypass increases and can attain

13 000 m3/day. Part of this quantity flows into the plant because the two biological systems can

handle at most 17 000 m3/day. The treated wastewater balance therefore has an influx of 30 000

m3/day of which 5 700 m3/day are fully treated (19%), but end up being mixed with

insufficiently treated wastewater and discharged into the sea (see §6 of Annex 4).

4.1.19 Increase in Domestic Wastewater Pumping Capacity: the restructuring of the pumping

station has helped to increase the quantity of residual effluents collected in the networks and

channelled to the Cambérène Wastewater Treatment Plant. Concerning the pumping capacity,

the volume of wastewater pumped by the pumping stations (excluding the Djili Mbaye station)

rose from 3 628 279 m3 in 2007 to 4 255 378 m3 in 2009, that is a 17% increase (see §7 of

38 Discharge standards relate to the quality of biologically (or secondary) treated wastewater discharge. 39 ONAS/EAWAG, “Faecal Sludge Management: Optimizing the System”, Proceedings of the International Symposium on Faecal Sludge

Management, Dakar, Senegal, 30 June - 1 July 2009. 40 The exact quantity of inflows is unknown as the available flow meters are out of order. Consequently, flows are measured depending on

pump operating times and lifting screws whose calibration is very old. It is also difficult to determine the flow distribution between biological systems 1 and 2 as the flow meters at the outlet of the sedimentation tank are out of order.

41 The share of bypass wastewater is crude because the wastewater reading is simply taken and then sent back to the onshore and offshore outfall. No pre-treatment is carried out as the wastewater screens and grit removers are not operating due to very advanced wear and tear (according to the 2010 operating report).

Page 24: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

10

Annex 4). This increase in the effluent collection capacity of pumping stations was expected to

help prevent the runoff and dispersal of effluents on public thoroughfares. However, despite the

quality of construction and finishings of pumping stations, the mission noted that this

requirement is often undermined by operating problems, because frequent power cuts and fuel

shortages result in the shutdown of stations, causing serious inconvenience to beneficiaries.

4.1.20 According to operating reports, many fairly serious breakdowns and shutdowns occur

after less than three years of operation of facilities. Similarly, the mission noted signs of rust on

the metallic parts of some equipment (valves, pressure tank balloons and standby generator

covers), suggesting that a coating adapted to the ambient hot and humid marine climate was not

applied on equipment. Overall, the restructuring of the pumping system is considered to be

efficient. However, operational weaknesses (preventive and corrective maintenance and the

operation of standby power generators) as well as the habits of the population (particularly

regarding the disposal of household refuse), contribute to the rapid degradation of facilities.

4.1.21 Application of Good Health and Hygiene Practices: the different IEC activities carried

out have helped to improve the behaviour of the beneficiary population in some areas. In fact,

direct observation in homes and the surroundings of sites visited confirm the results of group

interviews and discussions regarding progress in terms of: (i) cleaning homes and their

immediate surroundings; (ii) the actual existence of a wastewater treatment system; (iii) the

presence of refuse bins; and (iv) the absence of wastewater discharged onto the street.

4.1.22 Conversely, claims by women interviewed individually or in groups that wastewater

is screened before it is discharged into the network are contradicted by direct observations in

pumping stations. In fact, in all the stations visited, there are sizeable quantities of waste from

the screenings. This finding corroborates the view of some stakeholders42 that the population is

reluctant to change its behaviour and habits towards infrastructure to the point of asking project

promoters to adapt technologies to their behaviour. The initiatives and measures taken

following the implementation of IEC actions are transient and too limited in time to produce

the expected changes.

4.1.23 Building ONAS’ Organizational Capacity: the conduct of ONAS’ organizational study

helped to: (i) develop an action plan; (ii) design a three-year training plan; (iii) establish cost

accounting; (iv) develop an information system master plan; (v) propose agreements with local

governments for stormwater management; (vi) propose performance-based service contracts

with subcontractors; (vii) implement a priority training plan; (viii) carry out an inventory of

ONAS’ fixed assets; and (ix) update the urban sanitation financial model. The functioning of

the document management system and implementation of the findings and recommendations

of ONAS’ organizational study have not been sufficiently developed to significantly strengthen

ONAS’ organizational capacity.

42 Notables, local elected officials and municipal engineers in serviced plots met during a group discussion held at the municipality’s

headquarters.

Page 25: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

11

Achievement of Intermediate Outcomes

4.1.24 Improvement of the Quality of Wastewater Discharged into the Sea: since 2009, the

performance of the biological treatment system of the Cambérène Wastewater Treatment Plant

is poor. Wastewater from the two treatment systems is no longer compliant with Senegalese

environmental standards. Furthermore, the discharge of wastewater into the sea is no longer in

conformity with standards (SS, BOD5 and COD) given that treated wastewater mixes with

bypasses. In addition, given the absence of an adequate sludge treatment mechanism, the excess

sludge from the new system cannot be sent for digestion and is released into the natural

environment together with treated wastewater and bypasses, further deteriorating the quality of

discharges43 (see §8 Annex 4).

4.1.25 ONAS’ sea discharge objective for 2009 was 85%, which it failed to achieve. In fact,

specific average treatment output (sea discharge) for the last year of operation with data

(2009)44 is about 75% with a minimum of 56% and a maximum of 81%. To scale down their

output objectives, in May 2009, treatment plant operators introduced the concept of degraded

mode output. Set at 50%, this output enables operators to attain this arbitrarily set threshold45.

In addition, the installation of a new outfall which enables the discharge of treated wastewater

further out into sea (1 700 metres) to facilitate its dispersion in the ocean has met with resistance

from the local population (see §11 of Annex 4). In short, environmentally, the project does not

protect the natural environment it is expected to preserve.

4.1.26 Enhancement of Wastewater Treatment By-products: the project has helped to increase

the quantity of reusable water. However, due to lack of funding of tertiary treatment, it had no

effect on the safe reuse of treated water (irrigation agriculture, etc.) – (see §9 of Annex 4). The

old system 1 still has a potential for the reuse of 5 700 m3/day which cannot be absorbed by

potential customers such as the golf course and building and public works (BPW) companies.

The volume of purified water sold dropped from 3 000 m3/month in 2010 to 574 m3/month in

2011 due to the suspension of distribution to the Dakar-Technopole Golf Club in 2010, the only

remaining consumers being market gardeners46.

4.1.27 The Cambérène Wastewater Treatment Plant is currently facing a serious problem of

sludge management exacerbated by the PAVD due to the suppression of the sludge treatment

mechanism initially provided for (38 additional drying beds and a sludge dehydration unit),

clogging the existing sludge system. The Cambérène Wastewater Treatment Plant produces

about 20.2 tons of sludge per day (see §10 of Annex 4) and the project contributes about 42%

to the amount of sludge produced by the plant. In addition, the sludge produced has a very high

amount of organic matter with respect to design standards, suggesting poor performance. In

terms of sales, about 2 900 m3 of dehydrated sludge was sold in 2010 (barely 250 m3/month on

average).

43 The summary balance sheet in terms of discharge into the sea is as follows: Total pollution discharged = Residual pollution on system

1 and 2 + Pollution of bypass treated wastewater + Pollution of sludge in the biological system 2. 44 Since July 2011, the purification rate is no longer determined due to lack of a flow meter. 45 “Details on the Capacity, Flow Rate and Level of Treatment of the Cambérène Wastewater Treatment Plant”: Interim Report of 30

November 2009 – Directorate of Sanitation and Public Hygiene, ONAS (European Union Financing). 46 It should, however, be noted that, due to the importance of the issue of wastewater usage in market gardening, ONAS has established

partnerships with the Spanish Cooperation Agency through the FAO to promote market gardeners’ access to quality water in peri-urban areas (Greater Niayes). In addition, other research programmes on the safe reuse of wastewater for agriculture are ongoing (WHO/FAO/CREDI Project).

Page 26: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

12

4.1.28 Biogas production enabled ONAS to reduce its operating expenses, especially

electricity bills, by about 30% to 35% in the treatment plant47. Only two-thirds out of a total of

3 000 m3 of biogas (65% of methane) produced every day is used by a methane power generator.

The remaining one third, which cannot be used due to lack of means of generating electricity,

is flared. Worse still, after the shutdown of the gas power generator and suspension of flaring

since July 2010, methane gas production is continuing with part of the gas produced being

discharged into the atmosphere.

4.1.29 Reducing the Incidence of Disease caused by Poor Hygiene and Sanitation: the

population surveyed in six of the nine areas equipped with pumping stations has mixed views

about the project’s contribution to improving beneficiaries’ health.. The analysis of the health

statistics of the serviced plots area (North Dakar area, according to the division of the Dakar

Health District) seems to show a reduction in the prevalence and number of cases of diseases

caused by insalubrity (malaria, diarrhoea and dysentery) of about 75% (50% for diarrhoea). The

reduction of the incidence of uncomplicated malaria in absolute terms is more visible and

sensitive. A comparison with another Dakar district, that is Pikine which is situated less than 5

kilometres from the project area but has not been serviced to date, is enlightening: the incidence

of diarrhoea, amoebic dysentery and helminthiasis was higher in 2009 compared to 2007, unlike

in the project area. Conversely, the reduction in the incidence rate of uncomplicated malaria in

the project area is not better than in Pikine (reduction of 78% against 80% for Pikine) - (see §12

of Annex 4).

4.1.30 Level of Improvement of ONAS’ Operational Capacity: since ONAS is undergoing

wide-ranging reforms, the project is yet to have a major impact on the improvement of its

operational capacity. Great challenges remain: (i) the efficacy of the decision-making process,

particularly in the processing of requests by the technicians of the Cambérène Wastewater

Treatment Plant, internal communication and the capitalization of experiences acquired in

project management and (ii) the level of expertise of management, technical services and

service providers48.

The Project’s Contribution to the Improvement of the Social, Health and

Environmental Conditions of Households in the Project Area

4.1.31 Opinion of Beneficiaries on the Improvement of their Living Environment through the

Implementation of the Project: people living around pumping stations (accept those around Unit

15) unanimously acknowledge the improvement of their living environment with the

construction of the facilities. According to them, such improvements are reflected in: (i) the

ease of movement in the immediate vicinity, whereas before people would not go to these areas

for more than a week due to stagnant wastewater; (ii) time saved in the daily maintenance of

the front of houses; (iii) the reduction of bad odours in homes resulting in the reduction of

expenses related to the purchase of perfumes, generally by women in order to reduce such

odours; (iv) the reduction of disease vectors (flies, mosquitoes and vermin) in the dry season;

and (v) the possibility of using areas freed of stagnant wastewater for social and/or recreational

activities throughout the dry season.

4.1.32 However, for the residents of Units 13 and 15 of the serviced plots, the project leaves

a feeling of unfinished business as its positive outcomes are offset by the backflow of treated

wastewater into residential areas and places of worship in the rainy season or during extended

47 The electricity bill of the treatment plant in 2009 totalled CFAF six hundred and thirty million (630 000 000). 48 However, ONAS has some technical competencies as it has acquired more than 20 years experience in the management of wastewater

collection, transportation and treatment facilities, enabling its technicians to occasionally devise ingenious solutions to operational problems, despite limited resources.

Page 27: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

13

power outages. During such periods, the population are faced with serious environmental

problems likely to cause major health risks. The same applies to local residents in the area of

the Djily Mbaye pumping station (which had not yet been equipped with a standby generator)

as well as the beach users met who said that wastewater discharged from the pumping station

pollutes the beach, thus disrupting their activities (swimming, jogging, walking, etc.).

4.1.33 Impact on the Reduction of Health Expenditure: women mention some savings on the

expenditure they usually make in the dry season to deodorize their homes with incense or sprays

and combat bad odours from ambient air pollution caused by stagnant wastewater. Moreover,

a qualitative assessment could be made of the increases in incomes derived from small-scale

economic activities such as petty trading which can now be carried out during the dry season in

previous flood areas. The reduction in the prevalence of diseases caused by poor hygiene and

sanitation in the project area implies a reduction in health expenditure. However, in the environs

of the Djily Mbaye residential area pumping station, the two lessors of resting huts met on the

shore said that they have difficulty finding customers near the flow bed of the station’s tank

overflows.

4.1.34 Improvement in School Attendance due to the Implementation of the Project: the

analysis of the statistical data collected from the Departmental Inspectorate of Education in

charge of the serviced plots area does not indicate any project contribution to increased school

enrolment (the enrolment of girls and boys in Units 7, 22, 13, 15 and 9 has been declining since

2007/2008). On the contrary, study conditions in schools in the immediate vicinity of pumping

stations have improved significantly and there is less wastewater to pollute the atmosphere and

impede access.

4.1.35 On the whole, project efficacy (achievement of outcomes) is considered to be

unsatisfactory.

(c) Efficiency

4.1.36 Economic and Financial Analysis: during the ex ante evaluation, the project’s

economic internal rate of return (EIRR) was estimated at 23.26% (on the assumption of a 10%

increase in investment cost), at 25% (on the assumption of a 10% decrease in revenue) and at

21.22% (by combining both scenarios). This rate was not computed in the completion report.

Considering that the project does not generate own resources and mainly depends on the

sanitation tax levied on water consumption (whether or not the consumer is connected to the

sanitation network), the computing of the financial rate of return is not very expedient.

However, due to its heavy dependence on subsidies and the levy, ONAS has huge subsidy and

balancing tariff requirements to close its financing gap (see Annex 8)

4.1.37 Cost-effectiveness Analysis: the comparative detailed review of cost and service

reductions related to the extension of the Cambérène Wastewater Treatment Plant (see §13 of

Annex 4) shows that cost effectiveness is unsatisfactory. The project could have performed

better using the same resources, particularly by achieving the minimum sludge treatment

envisaged (primary thickener). On the whole, project efficiency is deemed to be unsatisfactory.

(d) Institutional Development Impact

4.1.38 The project has helped to start building ONAS’ organizational, technical and financial

capacity. Organizational and technical capacity was built by developing technical tools which

are vital for the fulfilment of its mission (electronic archiving, GIS, outline maps, remote

monitoring, etc.) together with training and monitoring programmes. Concerning human and

material resources, ONAS is still under-staffed and under-equipped and must call on huge

Page 28: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

14

external resources and services the lack of which impedes the implementation of its activities

and, therefore, its financial outcomes. Nevertheless, through the training of the operators of the

treatment plant and pumping stations, the project has strengthened their technical skills.

However, this institutional impact remains limited, especially as ONAS has no genuine

infrastructure maintenance and development plan.

4.1.39 The project has helped to strengthen internal communication by establishing a

coordination unit including a representative from each of the two technical directorates, namely

DET and DEX. Although this mechanism has had positive impacts on the project, it is not

sufficient to resolve personal disputes or anticipate operation-related problems; the design and

construction of treatment plants is impeded by disagreements between the two directorates,

particularly regarding technical options.

4.1.40 ONAS’ financial capacity has partly been built through the performance contract

concluded between the government and ONAS in August 2008 which includes, among other

things, the design, by the operator, of a short- and medium-term forward-looking investment

programme and the obligation to carry out a time-bound sanitation pricing study. . The limited

pricing study carried out by ICEA meets this requirement. However, the prices fixed in 2003,

except for those applied to government services, were not reviewed in 2008. Consequently, the

Borrower has not fulfilled one of the conditions of the loan agreement concerning the increase

of the sanitation levy. At sector level, the project had no major impact on the planning,

implementation and monitoring capacity. Overall, the project’s institutional development

impact is considered to be unsatisfactory.

(e) Other Development Impacts (gender)

4.1.41 The project’s IEC component is the one that most successfully mainstreamed the

gender dimension given the key role played by women in running their families in Senegal. In

addition, their hygiene habits are critical in reducing diseases caused by poor sanitation.

Accordingly, IEC actions particularly targeted this group of beneficiaries. However, because

women lack financial resources, they generally depend heavily on their husbands for money to

buy the tools (sieves, refuse bins, etc.) needed to carry out appropriate sanitation actions. As a

result, the IEC component of the project has not sufficiently taken men into account, despite

the fact that they can limit access to and the application of the knowledge acquired to promote

the adoption of good health and hygiene practices.

(f) Sustainability

4.1.42 Technical Sustainability: the project’s technical sustainability is negatively affected

by: (i) the technical options adopted due to the poor quality of designs; (ii) ONAS’ weak

financial, material and human capacity due particularly to the State’s failure to honour its

commitments specified in the performance contract concluded with ONAS; (iii) frequent power

outages and fuel shortages which impede network and equipment maintenance operations; and

(iv) very difficult operating conditions, particularly regarding the management of floating

materials in degreasing lines and in the primary sedimentation tank (thick and compact layers

of fats which are very difficult to remove). The intensive activated sludge treatment system

adopted is costly.

4.1.43 Sustained Borrower Commitment (including the legal/regulatory frameworks): this

commitment is mainly reflected in the sector reform introduced in 1995 with the splitting of the

former Senegal National Water Exploitation Corporation (SONEES) into three separate

entities, namely: (i) the Senegal National Water Corporation (SONES) which is a State-owned

and investment company; (ii) the Senegal Water Company (SDE) which is a private company

Page 29: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

15

linked to the State by an affermage contract; and (iii) the Senegal National Sanitation Authority

(ONAS) which enjoys some autonomy over the implementation of sanitation activities in the

country. The reform has helped to raise the sanitation sub-sector to a higher priority level. The

Borrower’s commitment was also reflected in the establishment of a policy, legal and

administrative framework through the adoption of several legal documents 49 . Lastly,

modification of the institutional and contractual architecture of the urban water sector which

includes the wastewater and, where appropriate, the stormwater treatment sub-sectors – in a

concession contract, is being examined50.

4.1.44 Socio-political Support: the Government does not seem to be determined to improve

ONAS’ very worrisome situation, although discussions are ongoing to find lasting solutions. In

fact, according to technical partners51, “the State has not honoured its commitment to guarantee

ONAS’ financial equilibrium as specified in the performance contract concluded with ONAS.

Consequently, the Government’s debt owed to ONAS as at 31 March 2011 stood at CFAF 5.14

billion, obliging ONAS to frequently resort to bank overdrafts to meet its working capital

needs.” This situation has been exacerbated for several years now by the drinking water price

freeze for individuals and the low rate of sanitation tax applied to drinking water bills. For their

part, users’ attitude towards sanitation facilities reflects the lack of a sanitation culture. This

situation is said to be due, among other things, to the inadequate involvement of the population

in the construction of treatment stations – only limited sociological studies are carried out and

the technological option retained is not the subject of consultation with beneficiaries.

4.1.45 Economic Viability: the economic benefits of the project are limited by: (i) the drastic

scaling down of its physical output objectives; (ii) the low technical performance of the

Cambérène Wastewater Treatment Plant; and (iii) the lack of enhancement of by-products

capable of boosting the development of urban and peri-urban agriculture, especially in a context

of food crisis.

4.1.46 Financial Viability: the project’s financial viability is negatively affected by the sub-

sector’s incapacity to generate sufficient resources for its own refinancing. The levy collected

through users’ water bills and government subsidies cannot cover ONAS’ operating costs which

are increasing owing to the investments initiated. ONAS still depends heavily on operating

subsidies to ensure a fragile annual income statement balance.

4.1.47 Institutional, Organizational and Management Efficiency: although ONAS’

institutional autonomy is real, it is incomplete. As an industrial and commercial public

establishment, it is not shielded from political pressures which may affect the management of

human resources, decision-making procedures and technical options. Furthermore, it cannot

prepare its own budget and freely mobilize funds commensurate with its real needs. The new

organizational chart prepared in 2011, which particularly provides for the position of Secretary-

General, is expected to improve ONAS’ organizational efficiency.

4.1.48 Environmental Sustainability: due to the unsatisfactory performance of biological

treatment, non-compliance with marine discharge standards and failure to take stormwater into

account in the serviced plots area, the project has a significant negative impact on the

49 Including: (i) an urban and rural water and sanitation sector policy paper, June 2005; (ii) a law governing public drinking water supply

and sanitation – Law No. 2008-59 of 24/9/2008; (iii) 8 July 2009 Sanitation Code; (iv) a performance contract concluded between the State and ONAS in August 2008.

50 Paper on the Urban Sanitation Situation presented by TFPs, European Union, 19 July 2011. 51 AFD, EIB, WB, EU Delegation.

Page 30: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

16

environment. Its categorization deprived it of an environmental impact assessment and an

environmental management plan which are essential for this type of project.

4.1.49 Resistance to Exogenous Factors: variations in the prices of raw materials, particularly

oil, and exchange rate fluctuations negatively impact project outcomes owing to the wastewater

treatment process used in the Cambérène Wastewater Treatment Plant52. The inappropriate

behaviour of users – the change of which takes a long time – also affects project performance.

Lastly, the sector’s heavy dependence on external financing, in a context of severe economic

crisis in developed countries, will likely affect project outcomes.

4.1.50 On the whole, the sustainability of project impacts is unsatisfactory.

4.2 Performance Ratings

(a) Overall Project Performance and Outcomes

4.2.1 Though the project is relevant, its quality at entry assessment is unsatisfactory. This is

due to the technical options adopted, the non-consideration of lessons learned from the inclusion

of stormwater and other solid waste, the outfall problem and its limitation to the restructuring

of the existing network, excluding extension. The achievement of objectives and outcomes is

also considered to be unsatisfactory. In fact, the physical situation of outputs worsened,

particularly the Cambérène Wastewater Treatment Plant extension component which is not

efficient and is part of a system (the entire plant) that is not at all compliant with environmental

standards of quality wastewater discharge.

4.2.2 ONAS’ weak financial, material and human capacity negatively affects the

sustainability of project impacts. This is due mainly to Government’s non-compliance with the

commitments contained in the performance contract concluded with ONAS, frequent power

outages and fuel shortages, which impede network and equipment maintenance operations. The

Government does not appear to display any real commitment to improving ONAS’ very

worrisome situation, although discussions are ongoing to find lasting solutions. The project’s

impact on institutional development is also considered to be unsatisfactory. On the whole, the

overall project performance is deemed to be unsatisfactory.

(b) Borrower Performance

4.2.3 Poor quality at entry assessment led to unsatisfactory Borrower performance at the

design stage owing to the insufficient assessment of the quality of designs (which are sometimes

not updated). In addition, the choice of the scaled down alternative of the “Cambérène

Treatment Plant extension” component constitutes, on account of its composition, capacity and

final cost, poor performance by ONAS which was unable to anticipate the poor performance of

the operation. Project implementation was characterized by: (i) the late appointment and

installation of the project coordinator; (ii) delay in project start-up, resulting in a rise in costs

and the scaling down of the initial objectives of the Cambérène Treatment Plant extension

component; (iii) failure to follow up the monitoring indicators contained in the appraisal report

until the end of the project and the signature of the performance contract between the

government and ONAS for a series of relevant performance indicators to be defined and

implemented; and (iii) non-compliance with the condition on the review of the price schedule.

52 Which affects energy expenditure and the importation of spare parts and, due to frequent power outages, requires the use of diesel-fired

generators.

Page 31: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

17

4.2.4 Although the PIU’s implementation performance is deemed to be satisfactory, that of

ONAS, the project executing agency, is considered unsatisfactory due particularly to its weak

technical, financial and human capacity, resulting in maintenance problems as it seemed that

the government of Senegal had miscalculated the challenges to be addressed and failed to

mobilize enough resources for sanitation, focusing instead on the drinking water component of

the DWSS sector programmes. Overall, Borrower performance is considered to be

unsatisfactory.

(c) Bank Performance

4.2.5 Regarding project design, the Bank validated technical options that were not the best

adapted to the Senegalese context. The Bank further validated the scaled down solution

presented by the Contractor without making any specific remarks on its cost (reduction of

services provided with respect to the new budget), its capacity (11 300 m3/day) and/or its

composition (simple biological system whereas the Contractor had drawn the project owner’s

attention to the need to strengthen the sludge system with at least one primary sludge thickener).

Consequently, it failed to anticipate the actual impacts of this reduction (in case of lack of

additional funding) on project performance.

4.2.6 The possible risks, particularly ONAS’ weak (especially financial) capacity and

inadequate IEC Programme scope, likely to impact project performance – in terms of outcomes

and sustainability – also became much more prominent than envisaged during project design

and preparation phases. The Bank fielded one launching mission in November 2001 and nine

supervision missions between November 2003 and November 2008. The composition of these

missions was satisfactory. However, the Bank did not at any moment realize the consequences

of the errors of the technical options retained and the lack of additional funding. On the whole,

Bank performance is deemed unsatisfactory.

4.3 Factors Affecting Implementation Performance and Outcomes

4.3.1 Factors under the Borrower’s Control: the direct consequence of the housing typology

is the dumping of household refuse in sanitation networks and various types of waste in drains

and private connections, clogging pipes and causing the backflow of wastewater into some

plots. Also, ONAS’ poor financial and human resources situation is one of the key factors that

negatively affect implementation performance and outcomes. Furthermore, sand and

stormwater infiltration causes unnecessary and excessive costs (removal and treatment costs).

Frequent power cuts trigger standby generators, provided they have fuel, which is not always

the case. Consequently, the suspension of pumping in some systems has often had serious

consequences such as wastewater overflow and flooding. Finally, the attitude of households

towards infrastructure negatively affects outcomes.

4.3.2 Factors Beyond the Borrower’s Control: rising oil prices and exchange rate

fluctuations negatively impact implementation performance and outcomes.

V. CONCLUSION, LESSONS AND RECOMMENDATIONS

5.1 Conclusion

5.1.1 In order to address the renewed outbreak of diseases caused by poor sanitation and

hygiene in the city of Dakar and its environs, the PAVD, particularly through the extension of

the Cambérène Wastewater Treatment Plant and the restructuring of the sanitation network of

the serviced plots area, took timely action to strengthen the outcomes of the Long-term Water

and Sanitation Programme, which is the cornerstone of Senegal’s long-term sector strategy.

Page 32: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

18

5.1.2 The project failed to adequately address the chronic liquid and solid sanitation

problems faced by the targeted areas. This is due mainly to poor quality at entry, the profound

transformation of the city of Dakar and ONAS’ persistent lack of financial resources as a result

of a lack of sanitation service taxation mechanisms as well as the non-implementation of the

provisions of the performance contract concluded between the government and ONAS in terms

of operating subsidies to cover ONAS’ cash deficit.

5.2 Main Lessons

The emergence of a public-private partnership in the sanitation sector requires

an institutional framework that promotes: (i) the financial equilibrium of the

entity responsible for the technical, commercial and financial management of

sanitation services; (ii) the existence of a State-owned company that helps to

mobilize the funds needed to develop the sector and manage investment

contracts.

The adoption of a strategy for the development and efficient reuse of sanitation

by-products (treated wastewater, sludge and biogas) which is effectively

implemented is necessary for ensuring the efficiency of a treatment plant.

The adoption of a holistic approach through the inclusion of stormwater and

solid waste in a wastewater treatment project will provide more comprehensive

solutions to problems of liquid sanitation and insalubrity.

The systematic mainstreaming of Environmental and Social Impact Assessments

(ESIAs) in sanitation projects, particularly those concerning wastewater

treatment plants is more useful than an inefficient environmental categorization

strategy.

The uncontrolled profound modification of a project’s scope may result in the

use of sub-optimal solutions that adversely affect its efficiency.

5.3 Main Recommendations

To the Senegalese Government:

Adopt a programme approach: the Government should, on the basis of the new

Dakar Master Plan which is being finalized, go beyond an ad hoc management

of sanitation projects by adopting a multi-donor coordinated programme

approach in order to find solutions to Dakar’s chronic solid and liquid waste

management problems.

Build ONAS’ financial capacity: the Government should build ONAS’ financial

capacity by: (i) increasing the sanitation levy based on a new tariff schedule that

is effectively applied; (ii) ensuring the rigorous management of unpaid bills,

particularly those of government services; and (iii) looking for other sustainable

sources of funding to improve ONAS’ self-financing capacity.

Strengthen the sanitation sector in Senegal: the Government should envisage the

institutional restructuring of ONAS into: (i) a State-owned company responsible

for the direct mobilization of funds needed to develop the sub-sector and manage

investment contracts; and (ii) into an operating company responsible solely for

technical, commercial and financial management of sanitation services.

Page 33: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

19

Revise regulations: the Government should ensure compliance with the

regulations applicable to the operation of wastewater treatment plants (quality of

treated wastewater) for discharge on land and river environments and amend the

regulation on the discharge of treated wastewater into the sea by setting a quality

target for the natural environment that would guide the choice of technical

treatment arrangements.

To ONAS:

Formulate a strategy for the development and reuse of by-products: ONAS

should define a genuine strategy for the development and efficient reuse of

wastewater treatment by-products.

Improve the efficiency of the Cambérène Wastewater Treatment Plant: ONAS

should: (i) upgrade the sludge system to limit the discharge of sludge and treated

effluent; (ii) protect the plant against the risk of flooding53; (iii) restore existing

pre-treatment facilities; (iv) carry on construction work to install the new sea

outfall as the existing one is too close to the beaches; and (iv) secure funding to

install the third treatment system within the framework of a comprehensive

Dakar City Sanitation Programme.

Ensure environmental protection: ONAS should systematically conduct, in

parallel with technical studies, ESIAs and ensure the holding of public

consultations to present projects as well as their environmental impacts and

mitigation measures (environmental management plans).

To the Bank:

Ensure quality at entry assessment: during project preparation, the Bank should

ensure the availability of key design studies and the technological options

retained for better cost estimation and reduction of implementation time frames

that undermine the outcomes of infrastructure projects. Exhaustive and quality

feasibility studies could necessitate funding by trust funds and should include

monitoring and evaluation, gender and environmental aspects as well as the

participation of beneficiaries. Furthermore, past lessons should be effectively

considered.

Modify the project: where financing is inadequate, the Bank should allow major

project modification only after assessing the impact of such modification with

respect to initial project objectives; otherwise, the Bank should ensure the

availability of additional financing to fill the gap.

Adopt the programme approach: the Bank should orient any new action related

to the sanitation of the Dakar City within the framework of a comprehensive

programme that includes wastewater, stormwater and solid waste, in conjunction

with other financial partners.

Mainstream the conduct of environmental and social impact assessments in

sanitation projects: given the intrinsic nature of sanitation projects, particularly

those concerning wastewater treatment plants, the Bank should systematically

demand the conduct of environmental and social impact assessments with

53 Using the resources provided by the government.

Page 34: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

20

environmental management plans including the resources needed for their

implementation.

Page 35: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

21

ANNEXES

Page 36: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 1

Map of Dakar and P roject Area

Source: PAVD Senegal Project Appraisal Report (ADF/BD/WP/2001/72)

Page 37: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

ANNEX 2 – LOGIC MODEL OF THE PROJECT

Development of Treatment By-

products.

Improved social, health

and environmental

conditions in the project

area

Do the people feel that the quality of their living environment has improved?

Improved health status

Increased disposable income

Improved school attendance (among girls in particular)

Activities

Extension of the treatment

plant through the

construction and

equipping of treatment

units

Outputs Short-term Outcomes Intermediate Outcomes

Impacts

IEC campaigns on

sanitation and health

Treatment infrastructure

improved and functional

Knowledge of health

practices and sanitation

problems improved

Wastewater pumping

infrastructure improved and

functional

Domestic wastewater

treatment capacity has

increased

ONAS Institutional

Support:

- Organizational study - Study on and

implementation of a relational database and an information and archiving system

Good health and hygiene

practices are applied

ONAS’ organizational study

adopted and Information and

archiving system functional. ONAS’ organizational

capacity has increased

Quantity of reusable water

produced has increased

Restructuring of the

wastewater pumping

system through the

construction and

rehabilitation of

pumping stations

Wastewater pumping

capacity has increased

Reduced incidence of

diseases caused by poor

hygiene and sanitation

Quantity of sludge reused

as fertilizer has increased

Improved quality of water

discharged into the sea

improved

ONAS’ additional

resources

Methane gas production has

increased

ONAS’ operational

capacity has

improved

Page 38: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 3

1/2

Indicators Unit 2000 2008 2009 2010 2011 2012 2013 (e)

National Accounts

GNI at Current Prices Million US $ 5 038 12 023 12 954 13 428 13 661 ... ...

GNI per Capita US$ 530 1 020 1 070 1 080 1 070 ... ...

GDP at Current Prices Million US $ 4 693 13 414 12 807 12 901 14 355 12 613 13 425

GDP at 2000 Constant prices Million US $ 4 693 6 571 6 728 7 018 7 165 7 431 7 748

Real GDP Growth Rate % 3,2 3,7 2,4 4,3 2,1 3,7 4,3

Real per Capita GDP Growth Rate % 0,6 1,0 -0,3 1,6 -0,5 1,1 1,6

Gross Domestic Investment % GDP 20,4 31,3 22,1 22,6 25,3 25,8 27,0

Public Investment % GDP 4,5 6,2 6,3 6,4 6,6 7,6 8,8

Private Investment % GDP 15,9 25,1 15,7 16,2 18,7 18,2 18,2

Gross National Savings % GDP 14,6 19,7 22,6 25,3 22,3 22,5 22,9

Prices and Money

Inflation (CPI) % 0,7 5,7 -2,2 1,2 3,4 2,5 1,6

Exchange Rate (Annual Average) local currency/US$ 712,0 447,8 472,2 495,3 471,9 510,5 ...

Monetary Growth (M2) % 10,7 1,8 11,4 13,7 6,8 ... ...

Money and Quasi Money as % of GDP % 23,6 33,4 36,9 39,8 40,0 ... ...

Government Finance

Total Revenue and Grants % GDP 18,7 21,5 21,6 21,9 22,5 23,1 23,0

Total Expenditure and Net Lending % GDP 18,2 26,3 26,8 27,3 29,1 30,1 30,9

Overall Deficit (-) / Surplus (+) % GDP 0,5 -4,8 -5,2 -5,4 -6,6 -7,0 -7,9

External Sector

Exports Volume Growth (Goods) % -12,1 -8,3 26,3 0,8 2,7 -8,6 3,7

Imports Volume Growth (Goods) % -4,5 27,5 -7,8 -5,6 8,3 -4,7 0,1

Terms of Trade Growth % -1,4 35,9 -5,7 -2,4 1,5 1,2 -4,8

Current Account Balance Million US $ -328 -1 888 -856 -584 -1 103 -1 086 -1 251

Current Account Balance % GDP -7,0 -14,1 -6,7 -4,5 -7,7 -8,6 -9,3

External Reserves months of imports 2,7 2,7 4,8 4,7 3,9 3,5 ...

Debt and Financial Flows

Debt Service % exports 15,4 4,2 5,5 5,8 13,7 7,9 7,9

External Debt % GDP 81,0 43,7 51,9 53,2 48,5 59,7 60,2

Net Total Financial Flows Million US $ 482 1 361 1 396 924 1 255 ... ...

Net Official Development Assistance Million US $ 431 1 069 1 016 928 1 052 ... ...

Net Foreign Direct Investment Million US $ 63 398 320 266 286 ... ...

Source : AfDB Statistics Department; IMF: World Economic Outlook, October 2012 and International Financial Statistics, October 2012;

AfDB Statistics Department: Development Data Portal Database, March 2013. United Nations: OECD, Reporting System Division.

Notes: … Data Not Available ( e ) Estimations Last Update: May 2013

SenegalSelected Macroeconomic Indicators

0,0

1,0

2,0

3,0

4,0

5,0

6,0

7,0

8,0

200

0

200

1

200

2

200

3

200

4

200

5

200

6

200

7

200

8

200

9

201

0

201

1

201

2

201

3

%

Real GDP Growth Rate, 2000-2013

-3

-2

-1

0

1

2

3

4

5

6

7

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

Inflation (CPI),

2000-2013

-16,0

-14,0

-12,0

-10,0

-8,0

-6,0

-4,0

-2,0

0,0

2 000

2 001

2 002

2 003

2 004

2 005

2 006

2 007

2 008

2 009

2 010

2 011

2 012

2 013

Current Account Balance as % of GDP,

2000-2013

Page 39: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 3

2/2

Year Senegal Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2011 197 30 323 98 458 35 811Total Population (millions) 2012 13,7 1 070,1 0,0 0,0Urban Population (% of Total) 2012 42,8 40,8 47,1 78,0Population Density (per Km²) 2012 64,9 34,5 69,8 23,5GNI per Capita (US $) 2012 1 040 1 604 3 795 37 653Labor Force Participation - Total (%) 2012 40,5 37,8 68,7 72,0Labor Force Participation - Female (%) 2012 43,9 42,5 38,9 44,5Gender -Related Dev elopment Index Value 2007-2011 0,457 0,525 0,694 0,911Human Dev elop. Index (Rank among 187 countries)2008-2012 154 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2009-2011 29,6 40,0 20,6 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2012 2,9 2,3 1,3 0,3Population Grow th Rate - Urban (%) 2012 3,6 3,4 2,6 0,7Population < 15 y ears (%) 2012 43,5 40,0 28,5 16,4Population >= 65 y ears (%) 2012 3,0 3,6 6,0 16,6Dependency Ratio (%) 2012 84,3 77,3 52,6 49,2Sex Ratio (per 100 female) 2012 96,1 100,0 103,3 94,3Female Population 15-49 y ears (% of total population) 2012 24,4 49,8 53,3 45,6Life Ex pectancy at Birth - Total (y ears) 2012 63,3 58,1 68,2 77,7Life Ex pectancy at Birth - Female (y ears) 2012 64,7 59,1 70,1 81,1Crude Birth Rate (per 1,000) 2012 38,1 33,3 21,4 11,3Crude Death Rate (per 1,000) 2012 7,7 10,9 7,6 10,3Infant Mortality Rate (per 1,000) 2012 49,6 71,4 40,9 5,6Child Mortality Rate (per 1,000) 2012 74,3 111,3 57,7 6,7Total Fertility Rate (per w oman) 2012 5,0 4,2 2,6 1,7Maternal Mortality Rate (per 100,000) 2006-2010 370,0 415,3 240,0 16,0Women Using Contraception (%) 2012 13,9 34,5 62,4 71,4

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2010 5,9 49,2 103,7 291,9Nurses (per 100,000 people)* 2004-2009 42,0 133,0 168,7 734,3Births attended by Trained Health Personnel (%) 2006-2010 65,1 53,7 64,3 ...Access to Safe Water (% of Population) 2011 73,4 67,8 86,5 99,1Access to Health Serv ices (% of Population) 2000 90,0 65,2 80,0 100,0Access to Sanitation (% of Population) 2011 51,4 40,2 56,8 96,1Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 0,7 4,6 0,9 0,5Incidence of Tuberculosis (per 100,000) 2011 136,0 234,6 146,0 23,0Child Immunization Against Tuberculosis (%) 2011 95,0 81,6 83,9 95,4Child Immunization Against Measles (%) 2011 82,0 76,5 83,7 93,5Underw eight Children (% of children under 5 y ears) 2006-2011 19,2 19,8 17,0 1,4Daily Calorie Supply per Capita 2009 2 479 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2010-2011 3,5 5,9 2,9 7,4

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2009-2012 86,2 107,0 107,8 102,7 Primary School - Female 2009-2012 89,0 103,1 106,2 102,3 Secondary School - Total 2009-2012 42,1 46,3 66,4 100,4 Secondary School - Female 2009-2012 40,3 41,9 65,1 100,0Primary School Female Teaching Staff (% of Total) 2009-2012 30,6 39,2 58,6 81,3Adult literacy Rate - Total (%) 2009 49,7 71,5 80,2 …Adult literacy Rate - Male (%) 2009 61,8 78,4 85,9 …Adult literacy Rate - Female (%) 2009 38,7 64,9 74,8 …Percentage of GDP Spent on Education 2008-2010 5,6 5,3 4,5 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2011 20,0 7,6 10,7 10,8Annual Rate of Deforestation (%) 2000-2009 0,7 0,6 0,4 -0,2Forest (As % of Land Area) 2011 43,8 23,0 28,7 40,4Per Capita CO2 Emissions (metric tons) 2009 0,4 1,2 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Senegal

october 2013

0102030405060708090

2004

2005

2006

2007

2008

2009

2010

2011

2012

Infant Mortality Rate( Per 1000 )

Senegal Africa

0

200

400

600

800

1000

1200

1400

1600

1800

2003

2004

2005

2006

2007

2008

2009

2010

2011

GNI Per Capita US $

Senegal Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

2004

2005

2006

2007

2008

2009

2010

2011

2012

Population Growth Rate (%)

Senegal Africa

111213141516171

2004

2005

2006

2007

2008

2009

2010

2011

2012

Life Expectancy at Birth (years)

Senegal Africa

Page 40: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 4

Page 1/8

PROJECT TECHNICAL ASPECTS

1. Shortcomings of the Cambérène Wastewater Treatment Plant (TP) and the Wastewater

Pumping System (Preliminary Design)

Cambérène Wastewater Treatment Plant (TP): the Cambérène Wastewater Treatment Plant,

commissioned in 1989 to serve 100 000 people, was designed to operate on the activated sludge

treatment system, with an excess sludge treatment unit, among others (digester and drying beds).

Treated water was pumped into a 600 mm diameter and 900 m-long pipe before gravitationally passing

through a 600 mm diameter and 1800 m-long pipe, these two pipes being the land section of the outfall.

Once on the seashore, water passed through a 400 mm pipe and was discharged about 200 m offshore;

it is the marine section of the outfall destroyed by storms shortly after construction at the end of the

1980s which thus caused the discharge of water onto the beach for a long period. To address this

situation, a temporary flexible 400 mm diameter and about 200 m long pipe was laid in 2001. As a result,

discharge was too close to the bank to protect the coastline from pollution. In addition, the bursting of

the pipe in Cambérène village in 2002 caused the flooding of many houses by the plant effluents.

With the extension of Dakar’s sewer system, coverage increased almost four-fold in ten years, leading

to high demand on the Cambérène Wastewater Treatment Plant. Its rehabilitation and extension in 2004

notwithstanding, the overworked plant could no longer meet the ever-increasing treatment demands.

Table 1 below presents the trends in the design parameters of the Cambérène Wastewater Plant.

Table 1: Changes in the Design Parameters of the Cambérène Wastewater Treatment Plant

DEGREMONT

1988-1989

1st Reinforcement

Biwater (2002-2003)

Parameters Units Quantity Quantity

Population Eq.Inhab. 100 000 200 000

Average flow rate m3/d 9600 19200

m3/d 400 800

Peak flow factor 1.75 1.75

Peak flow rate per second m3/h 700 1400

BOD5 Kg/d 6 000 14 976

mg/l 625 780

Suspended matter (SM) kg/d 9000 18 000

mg/l 937 938

Maximum temperature of effluents °C 30 30

Quality of Treated Water*

BOD5 at 20°C at full load for 2hrs mg/l ≤ 30 ≤ 30

BOD5 at 20°C at full load for 24hrs mg/l ≤ 20 ≤ 20

SM at average load for 24hrs mg/l ≤ 30 ≤ 30

COD at full load for 2hrs mg/l ≤ 120 ≤ 120

COD at full load for 24hrs mg/l ≤ 90 ≤ 90

Putrescibility test Negative Negative

* Senegalese standards are 50mg/l for SM, 40 mg/l for BOD5 and 100 mg/l for COD.

Page 41: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 4

Page 2/8

Domestic Wastewater Pumping System in the serviced plots area (Parcelles Assainies): The serviced

plots area is a densely populated residential neighbourhood in the northern suburbs of Dakar. It

developed in an area originally made up of niayes, backwater, dunes and wasteland characterized by a

very marked micro-relief in a mostly flat environment. It is Dakar’s most densely populated sub-district

(arrondissement). It comprises 26 units, each made up of about 500 concessions, and has the lowest

community sanitation coverage rate (17% against 34% in Pikine, 40% in Greater Dakar, 58% in

Colobane).

The existing pumping system was made up of 9 (nine) pumping stations (including that of DjilyMbaye)

in which wastewater generated in a given sub-zone could be pumped several times before being

discharged into the collector. This system caused overloading in many pumping stations, leading to

energy wastage. It also led to the appearance of effluent overflow and spreading areas on roads owing

to the relay functioning of the pumping stations, the outdated facilities as well as the under-sizing of

equipment. This situation posed hazards to the health of the neighbouring population and public

sanitation. As a result, it became necessary to restructure the existing pumping system for greater

efficiency. Moreover, the serviced plots area had virtually no stormwater collection and drainage

infrastructure.

2. Project Components

Table 2 : Project Components

No. Component Description

Amount in UA

Million

(percentage)

1 Extension of the

Cambérène

Wastewater Treatment

Plant

Construct two treatment units, each designed to treat 10 000 cubic metres

of domestic wastewater per day (that is about 100 000 inhabitants-

equivalent) and 9 000 kilogrammes of sludge per day from wastewater

treatment. The two new units would treat a daily average flow of 20 000

m3/d, thereby increasing the total capacity of the Cambérène Treatment

Plant from 10 000 m3/d to 30 000 m3/d

8.34 (62%)

2 Restructuring of the

Domestic Wastewater

Pumping System of

the serviced plots area

Restructure the sanitation system and upgrade the 9 pumping stations

which pump wastewater from the various areas (units) of the serviced plots

area neighbourhood to the Cambérène Treatment Plant.

Works to upgrade the pumping capacity comprise the rehabilitation of 3

out of the 9 existing pumping stations (units 7, 9 and 23) and the

construction of 6 new stations (for units 2, 13, 15, 22, DjilyMbaye and

Nord Stade) whose proposed design flow rates vary from 21 to 170 l/s.

2.95 (22%)

3 IEC Programme Carry out awareness-raising actions on sanitation and health education

issues among the beneficiary populations in the project area, especially to

ensure the success of project implementation.

0.20 (1%)

4 Studies, Works

Supervision and

Control

This component is expected to help to: (i) update studies and technical

specifications of supplies and works and readjust the existing bidding

documents (BDs), (ii) participate in the preparation, publication,

examination and analysis of tenders, and (iii) supervise and control works

executed by contractors.

0.40 (3%)

5 Institutional Support Set up a unit within ONAS’ Directorate of Studies and Works to

coordinate project implementation and, especially : (i) issue invitations to

bid; (ii) supervise the provision of services by consulting firms; (iii) ensure

coordination between the various project stakeholders, especially with

ADF; (iv) ensure project administrative and financial monitoring and

inform ADF accordingly in periodic reports; and (v) prepare and submit

to ADF the Borrower’s project completion report within the six months

following project completion.

0.27 (2%)

6 Project Management

This component was intended to help to conduct for ONAS: (i) an

organizational study with a view to proposing an organizational chart

that is more closely adapted to its mission; and (ii) the study for

establishing a relational database as well as a computerized archiving

system.

1.29 (10%)

Page 42: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 4

Page 3/8

3. Financial Bids for the Extension of the Cambérène Wastewater Treatment Plant: owing to

the increase in market prices, the financial bids received were too high in relation to the estimated budget.

The lowest bidder (STEREAU) made a CFAF 9.62 billion54 proposal for the firm tranche and CFAF

11.84 billion for all the extension works, including the optional tranche, as initially provided for at

project appraisal. However, the budget set aside for this component in the ADF financing was 6.8

billion55, showing a CFAF 3.04 billion financing gap in relation to the firm tranche and a CFAF 5.26

billion gap for the complete tranche. The search for additional financing from the European Union’s

financing line for support to Senegal’s sanitation sector (CFAF 7.87 billion) to cover the shortfall was

recommended to the Government by the Bank, but the procedure finally did not go through.

4. Existing Land and Marine Outfall: located in a basin, the Cambérène Wastewater Treatment

Plant has a pumping system which pumps water from the basin (from the TP, treated water and from the

By-pass) to a high point from where it flows gravitationally towards the ocean through a land, then

marine, outfall whose capacity is an important and limiting factor, but not sufficiently taken into account

by the project. In fact, the pumping capacity is insufficient during the rainy season when, not

hydraulically accepted for treatment (partial – primary – or complete) wastewater from the plant

overflows the networks and spreads out around the plant, while waiting to be drained.

5. Extension of the Cambérène Plant: as part of the extension of the wastewater treatment plant,

and based on the guidelines contained in the BD, TEREAU (lowest bidder) proposed a consistent plant

for both water and sludge systems by tripling the treatment capacity of the Cambérène TP. This objective

was supposed to be achieved in two phases. The first phase basically had to do with: (i) improving the

biological treatment of the existing “activated sludge” through biological denitrification, and (ii)

implementing a second activated sludge biological treatment process. The second phase to be carried

out later was expected to complete the treatment facility by: (i) implementing a third “activated sludge”

biological treatment process and, at the same time, (ii) increasing the treatment capacity (daily volume

of the treated effluents). In order to address the above-mentioned financial constraint, the Bank requested

ONAS to see what could be done technically with the ADF financing available for the treatment plant

extension works. This recommendation thus paved the way for a sub-optimal solution, with a CFAF

5.68 billion contract for the firm tranche, excluding its sludge treatment component. Table 3 below

summarizes the implemented project.

Table 3: Rehabilitation and Second Extension by STEREAU

STEREAU’s Proposal 56 Project Implementation (after scale down)

1. For the firm tranche (partially implemented)

carry out pre-treatment (screening and grit and grease removal)

for a 40 000 m3/d flow rate Not implemented

carry out primary treatment for a flow rate of 30 000 m3/d Not implemented

carry out secondary (biological) treatment for a 20 000 m3/d

flow rate

Secondary treatment with a 11300 m3/d flow

rate (System 2)

Transformation of System 1 primary

sedimentation tank into an anoxic tank

equip the Treatment Plant with a sludge dewatering unit Not implemented

2. For the conditional tranche (not implemented)

Upgrade the plant for secondary treatment with a 30 000 m3/d

flow rate Not implemented

54At the UA exchange rate of December 2005. 55Idem 13. 56Successful bidder.

Page 43: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 4

Page 4/8

6. Schematic Representation of the Water Balance of the Cambérène TP

Source : Post-evaluation Team, August 2011

Page 44: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 4

Page 5/8

7. Trends in the Volume of Wastewater Pumped by Station from 2007 to 20100 (in m3/year)

8. Improvement of the Quality of Water Discharged into the Sea: the quality of water

discharged is assessed by ONAS, in accordance with

Senegalese environmental standards, following the SM,

COD and BOD concentration and faecal coliforms57.

The analysis of these parameters of the level of pollution

of the Cambérène plant effluents shows that, since 2009,

the biological treatment output of the Cambérène TP is

low and that the effluents from the two treatment

systems no longer comply with the Senegalese standards

(SS) for these indicators. Data for 2009 show that treated

water complies with SS for SM with an average 29 mg/l

(for SS of SM, the concentration must be below 50

mg/l), but the situation deteriorated from 2010 (see

Table 5, Annex 13). Conversely, for BOD5 and COD,

the standards were never complied with before and after

project implementation.

Regarding sea discharge output, standards (SM, BOD5

and COD) are not also complied with, given the mixture

of treated water and by-passed water (see Table 6). In

addition, owing to lack of an appropriate treatment

mechanism, excess sludge from the new treatment system

cannot be sent for digestion and is discharged directly,

together with treated and by-passed water, thereby further

deteriorating the quality of discharges into the sea58. ONAS’ sea discharge objective for 2009 was 85%,

which it failed to achieve. In fact, specific average treatment output results (sea discharge) for the last

year of operation with data (2009)59 is about 75%, with the lowest being 56% and the highest 81%. To

scale down their output objectives, the TP operators in May 2009 introduced the concept of degraded

mode output. Set at 50%, this output enables the operators to attain this arbitrarily set threshold60. In

short, the project does not protect the natural environment it is expected to preserve.

57 Data on faecal coliforms are not available. 58 The sea discharge balance sheet is summarized as follows: Total pollution discharged = Residual pollution on systems 1 and 2 + By-

pass treated water pollution + Sludge pollution of biological system 2. 59 Since July 2011, treatment outputs are no longer determined owing to lack of flow meters. 60 «Details on the Capacity, Flow Rate and Level of Treatment of the Cambérène Treatment Plant », Interim Report of 30 November 2009

– Directorate of Sanitation and Public Hygiene, ONAS (European Union Funding)

Table 4: Trends in Pumped Volume from 2007 to 2010

(m3/year)

STATIONS 2007 2009 2010

PS 02 779 592 1 212 112 1 341 363

PS 07 464 843 495 170 554 480

PS 09 63 300 155 150 204 448

PS 13 1 405 544 535 294 600 144

PS 15 657 219 1 031 880 981 175

PS 17 10 715 34 174 26 784

PS 22 139 438 140 877 166 562

PS 23 107 628 650 721 785 575

TOTAL 3 628 279 4 255 378 4 660 531

Variation + 17.28% +9.52%

Source : Operations Reports, ONAS

Table 5: Characterization of the Effluents of Treatment

Systems 1 and 2

Parameter System 2008 2009 2010 2011* Standard

SM (mg/l) 1 25 29 68 70 50

2 53 55

BOD5

(mg/l) 1 45 59 99 78

40

2 102 52

COD (mg/l) 1 109 157 193 218 100

2 161 213

Source : DEX ONAS Annual Reports 2008, 2009, 2010 and

June 2011.- * June 2011

Table 6: Characterization of Effluents Discharged

into the Sea after Pre-treatment (35% of daily flow)

Parameter 2008 2009 2010 2011*

By-pass volume (m3/d) 9400 8500

SM (mg/l) 424 613 691 691

BOD5 (mg/l) 728 1 026 937 937

COD (mg/l) 1 286 1 910 1708 1708

Source : DEX ONAS Annual Reports 2008, 2009, 2010 and

June 2011.- * June 2011

Page 45: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 4

Page 6/8

9. Reuse of Water Treated by the Cambérène Treatment Plant: in terms of reuse of treated water,

the effluents of treatment system 2 financed under this project had a potential of 6 347 600 m3 in 2009

(12 800 m3/d against 2 659 000 m3 in 2008). In other words, the quantity of potentially reusable water61

was multiplied by 2.4 between 2008 and 2009. However, this potential is still untapped. Furthermore,

the project has not had any impact on the healthy reuse of treated water (agricultural irrigation, etc.)

owing to lack of financing for tertiary treatment. The old system 1 still has its 5 700 m3/d reuse potential

which is yet to be absorbed by potential clients made up of the golf course and public works and civil

engineering (BTP) companies. Thus, the average volume of filtered water was only 12 000 m3/month in

2010 and 4 700 m3/month during the first half of 2011. The volume of treated wastewater sold dropped

from 3 000 m3/month in 2010 to 574 m3/month in 2011, as a result of the suspension of distribution to

Dakar-Technopol Golf Club in 2010, the only remaining consumers being market gardeners.

10. Sludge Production in the Cambérène Wastewater Treatment Plant:

Table 7: Current Sludge Production in the Cambérène Treatment Plant

Sludge Quantity

(tons/day)

Sludge Volume

(m3/day)

20g/l

primary

sludge

20 g/l fresh sludge 10.2 510

20 g/l excess sludge from system 1 2.0 100

Excess sludge from system 2 8.0 1 000

TOTAL 20.2 1 610 Source: Upgrading of the sludge and energy production system in the Cambérène treatment plant – Final Design, ONAS – European Union,

June 2010.

The above table shows high sludge production. However, in the absence of a sludge thickener, such high

sludge production is characterized by: (i) the sending of high water content sludge into the digesters; (ii)

short duration of sludge in the digesters; (iii) low biogas production by the digesters; and (iv) the sending

of considerable volumes of thin sludge to the drying beds62. This clogging also reduces the natural

dehydration of sludge. In addition, the under-sizing of the overflow evacuation pipe in relation to the

volumes of sludge received by the digester cause permanent flooding around the digesters.

Excess secondary sludge produced by the second treatment system built by the project is drained during

the off-peak period (night) through the Cambérène outfall. In contrast, primary sludge from the primary

sedimentation tank effectively contributes to supplying the sludge treatment system of treatment system

1. However, 42% of the effluents of the primary sedimentation tank is made up of wastewater from the

pumping stations of the serviced plots area (12 800 m3/d of

which 13% is discharged around the plant, while 87 %

undergoes primary treatment – screening, grit removal and

primary sedimentation). Consequently, the project

accounts for about 42% of the quantity of sludge generated

by the plant. Between 2008 and 2009, secondary sludge

generated increased from 19 930 mg VSS/l to 29 650 mg

VSS/l from treatment system 1, with the project

contributing from 8 370 mg VSS/l to 11 190 mg VSS/l.

The increase thus generated between 2008 and 2009 stood at 34%.

61 Water resulting from the secondary system installed by the project can be reused with less risk only for bee keeping, watering of fruit

trees, recharging water tables (under certain conditions) and supplying water for some public works. 62 Upgrading of the sludge and energy production system in the Cambérène Treatment Plant – Final Design, ONAS – European Union,

June 2010.

Table 8 : Percentage of VSS/SM of

Sludge Produced by the Cambérène

Treatment Plant

Type of Sludge VSS/SM (%)

Fresh primary sludge 70

Primary digested

sludge 64

Secondary digested

sludge 60

Source : Operations Progress Report Dakar 2, DEX ONAS, 2010

Page 46: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 4

Page 7/8

Regarding the quantity of sludge produced, Table 8 (see Annex 13) shows the VSS/SM percentages,

indicating the proportion of organic matter in the sludge. It shows that after digestion, the percentage is

too high in relation to the design standards (0.65 for fresh sludge), suggesting a low output. Concerning

the sale of sludge, about 2 900 m3 of dehydrated sludge were sold in 2010 (that is 250 m3/month on

average).

11. New Cambérène Sea Outfall: the project for the construction of a new Cambérène sea outfall is

financed by the European Union to the tune of about CFAF 12.8 billion. It comprises two phases, namely a

land phase and a maritime phase. The land phase covers 2400 metres, from the seashore treatment plant

to Cambérène. The maritime phase consists in building an off-shore outfall whose normal outlet will be

located 1700 metres from the bank and 40 metres below water. In addition to this, its pumping capacity

will be increased (its peak flow rate will be increased to about 52 000 m3/day) through the extension of

the tank of the discharge station and the installation of a fourth pump. The implementation of this project

is expected to relatively deactivate the existing 200 m sea outfall. By enabling the discharge of treated

water far out in the sea (1 700 metres), thereby encouraging its dispersal in the ocean, the new outfall is

supposed to allay the concerns of the Cambérène population about the risks of polluting their beach. For

various reasons, however, the construction of this new outfall has been opposed by the neighbouring

population. In the absence of support from the main beneficiaries, the European Union was therefore

planning to suspend the project.

12. Trends in some Cases of Diseases caused by Poor Hygiene and Sanitation

13. Reduction of the Cost of the Cambérène Treatment Plant Extension Component

Table 10: Level of Reduction of the Cost of the Cambérène Treatment Plant Extension Component

No. Item

INITIAL

PROJECT

ACTUAL COST REDUCTION

(in CFAF) (in CFAF) (in CFAF) (%)

1 Overheads 952 059 715 832 831 587 119 228 128 13%

2 Studies 1 636 160 696 1 353 940 353 282 220 343 17%

3 Water treatment

system 2 538 904 333 1 156 171 503 1 382 732 830 54%

4 Sludge treatment

system 1 633 877 998 135 738 522 1 498 139 476 92%

Table 9: Trends in Some Cases of Diseases caused by Poor Hygiene and Sanitation in the Project Area

and in Pikine Between 2007 and 2009 (in %)

2007 2009

ParcellesAssainies Pikine Parcelles Assainies Pikine

Uncomplicated malaria 20.0% 8.4% 4.3% 1.7%

Diarrhoea 2.6% 2.0% 1.2% 2.7%

Amoebic dysentery 0.8% 0.4% 0.2% 0.5%

Helminthiasis 1.7% 2.7% 0.4% 3.8%

Population 360 847 582 654 376 397 656 362

Source: MSP-SNIS/Health Statistics 2007 Volume II 841 pages and Health Statistics 2009. 255 pages

Page 47: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 4

Page 8/8

No. Item

INITIAL

PROJECT

ACTUAL COST REDUCTION

(in CFAF) (in CFAF) (in CFAF) (%)

5 Common works 2 252 873 778 1 924 918 176 327 955 602 15%

6 Miscellaneous 535 667 100 294 418 000 241 249 100 45%

TOTAL (ET) 9 549 543 620 5 698 018 141 3 851 525 479 40%

Water + sludge treatment system 4 172 782 331 1 291 910 025 2 880 872 306

69%

Others 970 653 173 18%

% Water + sludge treatment system 44% 23%

Page 48: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 4

Page 9/8

In other words, with the same amount, the project could have done better, especially regarding the

implementation of the minimum envisaged for sludge treatment (primary thickener). In fact, the project

was adapted to the available budget to the detriment of the water and sludge treatment system which are

the substance of the project, and to the advantage of the other more general items. In fact, whereas the

two treatment systems which accounted for 44% of the total project cost experienced a cost reduction of

about 69%, the other items (overheads, studies, common works and miscellaneous), which initially

accounted for 56%, were reduced by only 18% while the final project adopted was reduced to a mere

biological line (aeration tank, final sedimentation tank and recirculation, since pre-treatments, primary

sedimentation tanks and the 2nd treatment system and sludge treatment/dewatering were abandoned).

Moreover, the weight of overheads (site facilities mostly) and studies are 2 or 3 times higher than the

standards.

Page 49: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 5

1/8

Rating Tables – Evaluation Criteria

DAKAR CITY SANITATION PROJECT (PAVD)

No. COMPONENT

INDICATORS

Score

(1 to 4) REMARKS

1 Relevance and Quality at

Entry Assessment

2 Unsatisfactory

1.1 Relevance 3 Satisfactory

1.1.1 Consistency with the needs of

the population

3 The project provides support to efforts made by the

Government to address the renewed outbreak of diseases

due to the unsanitary conditions under which the

populations of the city of Dakar and its environs live.

1.1.2 Consistency with overall

country development strategy

3 The project is aligned with Senegal’s Ninth Economic and

Social Development Plan (1996-2001), in particular, with

one of its key strategic thrusts, namely: the improvement

of government involvement in the provision of services

and basic infrastructure and ensuring sound water

resource management. The project’s objectives are also an

extension of those of the Long-term Water Sector

Programme (LWSP) considered as the cornerstone of the

long-term sector strategy.

Consistency with Bank

assistance strategy

3 The project is also in line with the Bank’s strategy for

Senegal (1999-2001) which, under the “infrastructure”

pillar, seeks to strengthen social facilities in urban and

peri-urban areas. Moreover, it is consistent with the

Bank’s general priorities which are poverty reduction and

the achievement of the Millennium Development Goals

(MDGs) in the area of water supply and sanitation.

1.2

1.2

Quality at Entry

Assessment

2 Unsatisfactory

1.2.1 Baseline technical studies and

choice of treatment

technologies

2 The project opted for an extension of the Cambérène

Wastewater Treatment Plant whose core technological

options (activated sludge treatment process) were adopted

at the time of its initial construction. The pre-feasibility

studies show weaknesses in the determination of the costs

of treatment and ensuring proper project integration.

Moreover, classified under Environmental Category II,

the project was not subject to an in-depth environmental

and social impact assessment, which did not allow for

measures to be taken to reduce the significant negative

environmental impacts. Owing to a shortcoming resulting

from the flood-prone nature of the plant site, long-lasting

malfunctions have been noticed.

Page 50: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 5

2/8

DAKAR CITY SANITATION PROJECT (PAVD)

No. COMPONENT

INDICATORS

Score

(1 to 4) REMARKS

1.2.2 Optimality of the final

solution approved by the

Bank and the Borrower

2 In downscaling the volume of works because of the

financing gap, the Borrower and the Bank adopted a non

optimal alternative solution. The project did not also

sufficiently take into account the limits of the existing land

and marine outfall whose low capacity is an important and

limiting factor during the rainy season. In addition, this

outfall, which is an important protection for the natural

environment, has poor hydraulic characteristics and

coupled with an uncertain sustainability, its usefulness is

reduced.

1.2.3 Reflection of Bank Group

experience and lessons

learned in sub-programme

design

2 The design did not take into consideration one of the

lessons learned from an observation made on a previous

wastewater treatment project in the city of Dakar and its

environs: namely the need to include stormwater.

Moreover, the project was limited to restructuring the

existing network without extending it further, which

makes it more difficult and more costly to connect

households located far from the system, thus maintaining

the level of household connection to the community

system low.

2 Achievement of Objectives

and Outputs (“Efficacy”)

2 Unsatisfactory

2.1 Achievement and quality of

physical outputs

2 Unsatisfactory

2.1.1 Improved and operational

treatment facilities

2 Out of the two new treatment units with a 10 000 m3/d

treatment capacity each, the project constructed one

incomplete unit (biological system) with an 11 300 m3

capacity, excluding residual sludge treatment/conversion.

The infrastructure adopted was professionally

constructed.. However, the location of the Low-Voltage

Distribution Panel (LVDP) at a regularly flooded area is

unfortunate as it causes the deactivation of the entire plant

for safety reasons. Moreover, the facilities have, for some

years now, been affected by the increased flow rate,

excessive silting of the grit chambers and pre-treatment

instability owing to very advanced wear and tear and

flooding of the digester.

2.1.2 Improved and operational

wastewater pumping

facilities

3 The PAVD mainly consisted in optimizing the system by

enabling the pumping stations to operate independently of

each other. As planned, it helped to rehabilitate 3 stations

and create 6 new ones in addition to that of Djily Mbaye

financed with Government funds. Concerning the state of

the facilities, data supplied by the pumping stations section

show that the hydraulic and electronic equipment procured

breaks down from time to time.

Page 51: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 5

3/8

DAKAR CITY SANITATION PROJECT (PAVD)

No. COMPONENT

INDICATORS

Score

(1 to 4) REMARKS

2.1.3 Improvement of

knowledge of good health

practices and sanitation

problems

3 In all, 15 549 people participated in information/education

sessions. Hygiene outreach workers and committees were

supervised through social work at least once a week.

Measures and initiatives were thus adopted to encourage

behaviour change.

2.1.4 ONAS’ organizational

studies adopted and

information and archiving

system operational

3 PAVD was limited to supporting the documentation

centre because of the conduct of a more comprehensive

organizational study financed by the European Union.

The major recommendations of this study were used to

prepare a project being implemented.

2.2 Short-term (Direct)

Impacts 2 Unsatisfactory

2.2.1 Improvement of domestic

wastewater treatment

capacity

2 The project was able to construct only one biological unit

with an 11 300 m3/d treatment capacity, that is about 38%

of the initial target. The capacity of the first treatment

system (existing system before the project) had to be

scaled down to meet the goal of tertiary treatment

implemented on the site and reduced to 5 700 m3/d. It is

therefore only a total of 17 000 m3/d that the Cambérène

Treatment Plant can currently biologically treat, whereas

it treats an annual average of 26 500 m3/d and much more

in the rainy season. The treated wastewater balance is

summarized in a 30 000 m3/d intake of which 5 700 m3/d

are completely treated (that is 19%) but are later mixed with

insufficiently treated water and discharged into the sea.

2.2.2 Increasing domestic

wastewater pumping

capacity

3 The restructuring of the pumping system helped to lift the

residual effluents collected in the systems towards the

Cambérène Treatment Plant. The volume of wastewater

pumped by the pumping stations (excluding Djili Mbaye

station) increased from 3 628 279 m3 in 2007 to 4 255 378

m3 in 2009, representing a 17% increase. This increase in

the wastewater lifting capacity was expected to prevent any

overflow or direct discharge into the sea. However, as a

result of operational problems, frequent power cuts and fuel

shortages leading to the shutdown of the pumping stations,

wastewater overflow and spreading areas reappear on

roads.

2.2.3. Level of application of

good health and hygiene

practices

2 Despite the positive change in mentality following the

various IEC actions, there is still some resistance to

behaviour and habit change with respect to infrastructure.

For example, considerable quantities of screening waste can

be seen in the pumping stations, which points to failure to

screen wastewater before its discharge into the system.

Page 52: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 5

4/8

DAKAR CITY SANITATION PROJECT (PAVD)

No. COMPONENT

INDICATORS

Score

(1 to 4) REMARKS

2.2.4. Improvement of ONAS’

organizational capacity

2 The functioning of the document management system and

the implementation of the outcomes of ONAS’

organizational study have not yet reached the level where

they can significantly improve ONAS’ organizational

capacity.

2.3 Intermediate Outcomes 2 Unsatisfactory

2.3.1 Improvement of the quality

of wastewater discharged

into the sea

1 Since 2009, the biological treatment outputs of the

Cambérène Treatment Plant are low and wastewater from

the two treatment systems no longer complies with

Senegal’s environmental standards. Moreover, sea

discharge outputs no longer comply with environmental

standards given the mixture of treated water and by-

passed water. Owing to the lack of appropriate treatment

mechanisms, excess sludge from the new treatment

system which cannot be sent for digestion is discharged

into the natural environment just like treated and by-

passed water, thereby further deteriorating the quality of

sea discharges.

2.3.2 Development of treatment

by-products

1 Highly unsatisfactory

- Wastewater reuse 1 Despite a 2.4 times increase in the quantity of potentially

usable water to about 6 347 600 m3in 2009 (12 800 m3/d),

it is still not used. In addition, the project has not had any

impact on the safe reuse of treated water (agricultural

irrigation, etc.) due to the lack of financing for tertiary

treatment. The old system 1 still has a 5 700 m3/d reuse

potential which cannot be absorbed by potential

customers made up of the golf course and building and

public works companies. The volume of treated

wastewater sold dropped from 3 000 m3/month in 2010 to

574 m3/month in 2011 as a result of the suspension of

distribution to Dakar-Technopole Golf Club in 2010, the

only remaining consumers being market gardeners.

- Sludge treatment and

conversion

1 The high sludge production – estimated at 20.2 tons/d –

coupled with the lack of a thickener, has led to the

clogging of the existing sludge treatment system. Such

clogging reduces the natural dewatering of sludge whose

quality shows the presence of a high proportion of organic

matter in sludge (VSS/SM percentages) in relation to the

design standards. Concerning sludge sale, about 2 900

m3of dewatered sludge were sold in 2010 (that is 250

m3/month on average).

Page 53: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 5

5/8

DAKAR CITY SANITATION PROJECT (PAVD)

No. COMPONENT

INDICATORS

Score

(1 to 4) REMARKS

- Methane gas production 1 Methane gas production enabled ONAS to reduce its

energy consumption costs by about 30% to 35% at the

treatment plant. Only two-thirds of the 3 000 m3 of the

65% methane content biogas produced daily is used by a

methane gas generator. The remaining one third, which

cannot be used for lack of means of electric power

generation, was flared. However, following the shutdown

of the gas generator and the suspension of flaring since

July 2010, methane gas production has continued with

part of the gas produced (which cannot even be flared)

being discharged into the atmosphere. The project has not

had any impact on biogas production.

2.3.3 Reduction of the incidence

of diseases caused by poor

hygiene and sanitation

3 Despite the low level of beneficiaries’ appreciation of the

project’s contribution to improving their health, the

analysis of health statistics in the serviced plots area

shows a reduction in the cases of diseases caused by

insalubrity (malaria, diarrhoea and dysentery) by about

75% (50% for diarrhoea and uncomplicated malaria)

following the elimination of bodies of stagnant

wastewater during the dry season (more than 9 months

out of 12). Comparison with Pikine, located less than 5

km away from the project, but still unserviced to date,

seems to confirm this fact.

2.3.4 Level of improvement of

ONAS’ operational

capacity

2 Given that ONAS is undergoing reform at several levels,

the project has not yet had any significant impact on the

improvement of its operational capacity. There are still

serious challenges, namely: (i) the efficacy of the

decision-making process, particularly in the processing of

requests from technicians working in the Cambérène TP,

internal communication and capitalization on the

experiences acquired in project management; (ii) human

resource management; and (iii) the quality of expertise of

Project Management and technical services, and service

provision by private players.

Page 54: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 5

6/8

DAKAR CITY SANITATION PROJECT (PAVD)

No. COMPONENT

INDICATORS

Score

(1 to 4) REMARKS

2.4 Project’s contribution to

improving domestic

living conditions

2 Unsatisfactory

2.4.1 Beneficiaries’ appreciation

of the

project’s improvement of

their quality of life

2 The beneficiaries appreciate the improvements brought

about by the project and reflected, among other things, in:

(i) the ease of movement in the immediate vicinity,

whereas before, people would not go to these areas for

more than a week due to stagnant wastewater; (ii) the

reduction of bad odours in homes; and (iii) the reduction

of disease vectors (flies, mosquitoes and vermin) in the

dry season. However, they also think that the project

leaves one with a sense of uncompleted work in that the

positive outcomes are offset by the backflow of the

system right into residential areas during the rainy season

or during prolonged power outages.

2.4.2

2.3.2

Impact on the reduction of

heath expenditure

2 Women mention some savings on expenditure they

usually make during the dry season to deodorize their

homes with incense or sprays or eliminate bad odours

resulting from air pollution by stagnant wastewater.

Moreover, a qualitative assessment could be made of the

increase in incomes derived from the development of

economic activities, such as petty trading, now possible

on a permanent basis in the dry season in these former

flood areas. The project’s contribution to reducing health

expenditure is however minimal.

2.4.3 Assessment of the level of

improvement in education

by the project

2 The analysis of statistical data collected from the

Departmental Inspectorate of Education in charge of the

serviced plots area does not indicate any project

contribution to increased school enrolment. On the

contrary, study conditions in schools in the immediate

vicinity of the pumping stations have improved

significantly, and there is less stagnant wastewater to

pollute the atmosphere and impede access.

3 Efficiency 2 Unsatisfactory

3.1 EIRR

Appraisal: 21.22% - 25%

Completion:

PPER:

3.2 FIRR

Appraisal:

Completion:

PPER:

3.3 Cost-effectiveness 2 Unsatisfactory

Page 55: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 5

7/8

DAKAR CITY SANITATION PROJECT (PAVD)

No. COMPONENT INDICATORS Score

(1 to 4) REMARKS

4 Institutional Development 2 Unsatisfactory

4.1 Sector 2 The project did not have any significant impact on the

sector’s planning, implementation and monitoring capacity.

4.2 Executing Agency 2 The project helped to start building ONAS’ organizational,

technical and financial capacity. However, the institutional

impact is still limited, especially as ONAS does not have a

genuine infrastructure maintenance and development plan

and real financial autonomy.

5

5

Sustainability 2 Unsatisfactory

5.1 Technical sustainability 2 The project’s technical sustainability is negatively affected by

maintenance difficulties resulting from: (i) the technical

choices made due to the poor quality of design studies; (ii)

ONAS’ low financial material and human capacity; (iii)

recurrent power outages and fuel shortages; and (iv)

extremely difficult operating conditions.

5.2 Sustained commitment by the

Borrower (including

legal/regulatory frameworks)

3 It is mainly reflected in the sector reform introduced in 1995

with the splitting of the former Senegal National Water

Exploitation Corporation (SONEES) into three separate

entities, namely: (i) a State-owned company; (ii) SDE, a

private company linked to the State by an affermage contract;

and (iii) ONAS. The reform thus helped to raise the sanitation

sub-sector to a higher priority level.

5.3 Socio-political support

(including participation by

beneficiaries, vulnerable group

protection and political

stability)

1 The Government has so far not shown any real commitment

to improving ONAS’ very worrisome situation, although

discussions are ongoing to find lasting solutions. Users’

attitude towards sanitation facilities reflects the lack of a

sanitation culture.

5.4 Economic viability 2 The project’s economic benefits are limited by : (i) the drastic

scaling down of its physical output objectives; (ii) the low

technical performance of the Cambérène Treatment Plant;

and (iii) lack of enhancement of by-products capable of

boosting the development of urban and peri-urban

agriculture, especially in a context of food crisis.

5.5 Financial viability 2 The project’s financial viability is negatively affected by the

sub-sector’s inability to generate sufficient resources for its

own refinancing. The levy collected through users’ water

bills and government subsidies cannot cover ONAS’

operating costs which are increasing owing to the investments

initiated.

Page 56: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 5

8/8

DAKAR CITY SANITATION PROJECT (PAVD)

No. COMPONENT INDICATORS Score

(1 to 4) REMARKS

5.6 Institutional arrangements

(Institutional, organizational

and management efficacy)

2 ONAS’ institutional autonomy is not yet complete. As an

industrial and commercial public establishment, it is not

shielded from political pressure and it cannot prepare its

own budget and freely mobilize funds commensurate with

its actual needs.

5.7 Environmental sustainability 1 Due to the unsatisfactory performance of biological

treatment, non-compliance with marine discharge

standards and failure to take rainwater into account in the

serviced plots area, the project has a negative impact on

the environment.

Resistance to external factors 1 Variations in the prices of raw materials, especially oil,

and exchange rate fluctuations have a negative impact on

the project owing to the Cambérène Wastewater

Treatment Plant’s technical options, which have a great

impact on spending on energy and the import of spare

parts, and owing to unpredictable power cuts leading to

use of the diesel-fired generators,. The improper

behaviour of users, which requires a long-term change

process, is likely to affect project performance. Lastly, the

sector’s heavy dependence on external financing, within a

context of severe economic crisis in countries of the

North, will probably have spinoff on the project.

6 Overall Performance

Indicator

2 Unsatisfactory

Page 57: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 6

1/2

Borrower Performance

DAKAR CITY SANITATION PROJECT (PAVD)

Component Indicators Score

(1 to 4) Remarks

1. Quality at Preparation Stage 2 Unsatisfactory

- Control and participation by beneficiaries 2 Poor quality at entry assessment led to unsatisfactory

Borrower performance at the design stage, owing to

the insufficient assessment of the quality of designs.

In addition, the population’s involvement in the

building of the treatment plants was low – only

limited sociological studies were conducted and the

population was not consulted in the selection of

technologies.

- Government’s commitment 2 The Government of Senegal appears to have

underestimated the challenges to be met and was

unable to mobilize sufficient financing for

sanitation. It prioritized drinking water in DWSS

sector programmes.

- Macroeconomic and sector policies 1 At sector level, sanitation is considered as the poor

relation of Senegal’s DWSS policies.

- Institutional arrangements 3 There is an arrangement comprising the Project

Implementation Unit established within ONAS to

serve as interface between the various parties

involved in project implementation. Placed under

the supervision of the Director of Studies and

Works, this unit is supposed to work in close

collaboration with the World Bank-established

Coordination Unit which has a good administrative

organization and competent staff and is placed under

the responsibility of the Director of Water Resources

and Sanitation to monitor and implement all the

components of the Long-term Water Sector

Programme (LWSP). This Unit was supposed to

benefit from the technical assistance services of a

consulting engineer.

2. Quality at Implementation Stage 2 Unsatisfactory

- Posting of key staff 1 The establishment of the Project Coordination Unit

within ONAS’ Directorate of Studies and Works

was only effective in early May 2004 (that is almost

two and a half years after loan signature).

Page 58: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 6

2/2

DAKAR CITY SANITATION PROJECT (PAVD)

Component Indicators Score

(1 to 4) Remarks

- Executing Agency’s management

performance 2 The performance of the Project Implementation

Unit (PIU) is deemed satisfactory, and that of the

Executing Agency (ONAS) unsatisfactory, because

PIU’s operationalization was delayed and because

conditions precedent were not fully fulfilled

resulting in the above-mentioned consequences

- Mid-term adjustments 2 The Borrower and ONAS did not anticipate the

operation’s poor outcomes.

- Adherence to time schedule and costs 2 The project was implemented 24 months behind

schedule mainly because the Borrower had

difficulties in fulfilling the conditions precedent to

first disbursement. Moreover, the total project cost

(-0.5%), expressed in units of account, fell

significantly in CFAF, from CFAF 12.32 billion to

CFAF 9.58 billion, that is a decrease of CFAF 2.74

billion (nearly 22% of the total cost).

3. Compliance with covenants 2 Non-compliance with the condition related to the

review of the tariff schedule.

4. Adequacy of monitoring and

evaluation, and reporting

2 The project did not have an efficient monitoring and

evaluation system. The few monitoring actions

undertaken focused only on physical outputs and

disregarded project outcomes and impacts.

Furthermore, because the monitoring indicators

contained in the appraisal report were not

monitored, it was necessary to wait for the end of

the project and the signature of the performance

contract between the Government and ONAS to

define and implement a series of relevant

performance indicators.

5. Satisfactory operations (where

applicable)

2 The current situation of the Cambérène Wastewater

Treatment Plant, in particular, its hydraulic

performances and the quality of water discharged into

the sea, shows that the operation is not satisfactory.

Overall Borrower Performance 2 Unsatisfactory

Page 59: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 7

1/2

Bank Performance

DAKAR CITY SANITATION PROJECT (PAVD)

Component Indicators Score

(1 to 4) Remarks

At identification stage 2 Unsatisfactory

- Project compliance with

Government’s development

strategy

3 The project is in line with the Government’s development

strategy outlined in Senegal’s Ninth Economic and Social

Development Plan (1996-2001).

- Project consistency with the

Bank’s country strategy

3 The project is also in line with the Bank’s strategy for Senegal

(1999-2001).

- Participation by

Government/beneficiaries

2 While the Government was able to mobilize the national

financial contribution, the beneficiaries’ level of participation

was not satisfactory.

- Project’s innovative nature 1 The Bank validated a common technological option which was

not adapted to some of Senegal’s specificities.

At project preparation stage 3 Satisfactory

- Rationale for Bank’s support 3 The rationale for the Dakar City Sanitation Project (PAVD)

stems from the fact that it is a backup to the Government’s

efforts to address the renewed outbreak of diseases due to

unsanitary conditions. - Bank’s timely support 3

- Quality of technical, economic,

financial, institutional and

environmental analyses

2 The Bank validated technical options which were not the most

appropriate for Senegal. The Bank also validated the scaled

down solution presented by the Contractor without making any

special remarks on its cost and/or composition (simple

biological system whereas the Contractor had drawn the

project owner’s attention to the need to strengthen the sludge

treatment system with at least a primary sludge thickener),

without anticipating the actual impacts of such down scaling

on project performance.

- Relevance of conditions and

covenants 3 The conditions and covenants were relevant.

- Adequacy of lending instrument 3 The loan was the most appropriate instrument for this

operation on account of its cost.

- Quality of coordination with

other donors/partners 3 Among other things, the Bank held meetings with the

European Union as part of the search for financing for the

extension and rehabilitation of the Cambérène TP.

- Implementation and supervision

plans (including performance

indicators, criteria)

1 No indicator monitoring plan was available.

- M&E 2 The Bank limited itself to monitoring physical and financial

implementation.

Page 60: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 7

2/2

DAKAR CITY SANITATION PROJECT (PAVD)

Component Indicators Score

(1 to 4) Remarks

At the appraisal stage 2 Unsatisfactory

At the supervision stage 2 Unsatisfactory

- Adequacy of Bank staff (skills,

time & continuity)

3 The Bank fielded a launching mission in November

2001 and 9 field supervision missions between

November 2003 and November 2008, with an

appropriate mission composition.

- Problem solving 1 The problems of additional financing were not solved.

No plans were made for the adaptation of the project’s

environmental category despite the scaling down of the

physical objectives of the Cambérène TP, which

modified the substance of the project.

- Adequacy

recommendation/decision

monitoring

2 Aide-mémoires did not provide updates on the

implementation of the recommendations of previous

missions.

- Realistic ratings at CPPR/APPR 3 The unsatisfactory rating by the Country Portfolio

Review Report 2003 is realistic since it takes into

account the bottlenecks recorded in project

implementation.

- Attention to probable impact on

social development

2 At no time did the Bank realize the errors of the

technical options and/or the lack of additional

financing. The Bank’s experts focused on the outputs

of the new biological treatment system while

disregarding all the existing facilities.

- Attention to sustainability

problems

3 Like all the development partners, the Bank drew the

Government’s attention to the sub-sector’s situation,

particularly the difficulties faced by ONAS.

Overall evaluation of Bank

performance

2 Unsatisfactory

Page 61: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 8

Page 1/2

ONAS’ FINANCIAL SITUATION63

Sanitation rates have not changed since 2003. The average sanitation rate stood at CFAF 41.5/m3 in

2007, and has remained relatively constant since 2003. Financially, ONAS posted a net loss in the 2005

and 2006 fiscal years: proceeds from the operation of ONAS covered only 87% of its operating costs,

excluding depreciation expenditure. ONAS depends largely on operating subsidies to ensure a fragile

annual income statement balance. The performance contract between the Government and ONAS was

expected to improve the situation. However, as underscored by development partners, the Government

has not honoured its commitment to ensure ONAS’ financial equilibrium for the past financial years; as

a result, ONAS is compelled to resort to standing bank overdrafts to meet its working capital needs.

Based on a so-called “high” scenario, the investment programme to achieve the sector’s objectives by

2015 stands at CFAF 279 billion including 244 billion for wastewater treatment. The amount of the

2008-2012 programme is CFAF 236 billion. It will help, among other things, to make 51 600

connections, build 91 000 individual facilities, increase the treatment capacity by 72 300 m3/d and lay

500 km of wastewater pipes and 65 km of stormwater pipes. The coverage rate resulting from these

investments stood at 83% in 2012, that is 10% above the MDG, and the treatment rate at 55%, that is

6% above the MDGs. Seven new centres will be covered by the community sanitation system.

Operating costs will be CFAF 74.3 billion for the period (see Table 1 below) 91% of which concerns

sanitation operating costs. The service will cost CFAF 118 /m3 in constant terms (CFAF 128 /m3 in

current terms, including a 2% annual inflation rate).

Table 1: Operating Costs and Depreciation Expenditure

2006 2007 2008 2009 2010 2011 2012

Total

2008-

2012

Operating Costs 7 726 8 090 9 910 11 208 13 477 16 601 19 354 70 549

of which

sanitation 7 698 7 751 9 485 10 686 12 896 15 969 18 701 67 737

rainwater management 28 339 425 522 581 632 652 2 813

Depreciation expenditure (asset< 15 years) 272 503 588 498 619 883 1 131 3 720

Total Costs (CFAF M) (A) 7 998 8 593 10 498 11 706 14 096 17 484 20 485 74 269

The three sanitation sector financing options studied, namely sanitation levy, Government subsidies and

a combination of these two sources of financial resources, indicate that:

Ruling out any increase in levy for the period, official assistance to ONAS for the operation of

infrastructure was expected to stand at CFAF 2.7 billion in 2008 (of which CFAF 1.2 billion

already pledged), and up to CFAF 6.9 billion in 2012, that is 22.6 billion accumulated for the

period. Added to these subsidies is contribution for rainwater management, that is a total of

CFAF 25.4 billion (see Table 2 below).

Table 2: Government Subsidy Needs Without Levy Increase

63Excerpt from the Limited Tariff Study Conducted as Part of Negotiations for the Performance Contract to be Signed Between the State of Senegal and ONAS.

Page 62: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 8

Page 2/2

2006 2007 2008 2009 2010 2011 2012

Total

2008-12

Total Costs (CFAF M) (A) 7 998 8 593 10 498 11 706 14 096 17 484 20 485 74 269

Sanitation Levy (CFAF/m3) 41 41 41 41 41 41 41 Total Proceeds (CFAF M) (B) 6 655 7 563 8 562 8 138 9 321 11 139 12 889 50 049

Financing Gap (CFAF M) (A B) 1 344 1 052 1 936 3 568 4 775 6 345 7 596 24 220

Government Contributions (CFAF M) 0 1 000 3 136 3 568 4 775 6 345 7 596 25 420

of which

operating subsidy (CFAF M) 0 1 000 2 711* 3 046 4 194 5 713 6 944 22 608

contribution for stormwater management (CFA M)

0 0 425 522 581 632 652 2 813

* Of which CFAF 1.2 billion as operating subsidies already committed.

Assuming total collection of operating costs through sanitation levy, such a levy should increase

from CFAF 41 /m3 in 2007 to constant CFAF 105 /m3 in 2012, that is CFAF 113 /m3 taking into

account a possible 2% annual inflation rate.

2006 2007 2008 2009 2010 2011 2012

Total

2008-

12

Total Costs (CFAF M) (A) 7 998 8 593 10 498 11 706 14 096 17 484 20 485 74 269

Sanitation Levy (CFAF/m3) 41 41 60 78 90 106 113 Total Proceeds (CFAF M) (B) 6 655 7 563 10 073 11 184 13 515 16 852 19 833 71 457

Financing Gap (CFAF M) (A B) 1 344 1 052 425 522 581 632 652 2 813

Government Contributions (CFAF M) 0 1 000 1 625 522 581 632 652 4 013

of which

operating subsidy (CFAF M) 0 1 000 1 200* 0 0 0 0 1 200

contribution for stormwater management (CFAF

M) 0 0 425 522 581 632 652 2 813

* : operating subsidy already committed

In the event of a partial levy increase, Table 3 below shows the results of three different scenarii:

25%/50%/75% financing of the service through the sanitation levy and 75%/50%/25% financing

through Government subsidies. The sanitation levy in 2012 would therefore stand at CFAF

67/m3 (in current terms, including a 2% inflation rate) in the first case, CFAF 82 /m3 in the le

second case and CFAF 98/m3 in the last case.

Table 3: Financing Gap Coverage Scenario

Total for the Period 2008 - 2012 25% Levy –

75% Government

Subsidies

50% Levy –

50% Government

Subsidies

75% Levy –

25% Government

Subsidies

Total Costs (CFAF M) (A)

Sanitation Levy 2012 (CFAF/m3)

Total Proceeds (CFAF M) (B)

Financing Gap (CFAF M) (A - B)

Government Contributions (CFAF M)

of which

operating subsidy (CFAF M)* contribution for rainwater management (CFAF M)

74 269

67

55 790

18 479

19 679

16 866

2 813

74 269

82

60 616

13 653

14 853

12 040

2 813

74 269

98

65 998

8 271

9 471

6 658

2 813

* Including operating subsidies for 2008 to the tune of CFAF 1.2 billion already committed .

Page 63: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 9

Page 1/3

BIBLIOGRAPHY

Project Documents and Strategies

1. AfDB, 2001, Senegal, Dakar City Sanitation Project (PAVD), Appraisal Report.

2. AfDB, 2010, Senegal, Dakar City Sanitation Project (PAVD), Completion Report.

3. AfDB, 2004, Loan Agreement Concluded between the Republic of Senegal and the African Development

Fund (Dakar Sanitation Project).

4. AfDB, Dakar City Sanitation Project – Summary Ledger.

5. AfDB, 2000, Senegal: Country Strategy Paper 1999-2001.

6. AfDB, 2003, Senegal: Country Strategy Paper 2002-2004.

7. AfDB, 2005, Senegal: Country Strategy Paper 2005-2009.

8. AfDB, 2008, Senegal: Mid-term Review of the Country Strategy Paper 2005-2009.

9. AfDB, 2004, Senegal: Portfolio Review Report 2003.

10 ONAS-DEC, 2010, “Upgrading the Sludge Treatment Method and Energy Production in the Cambérène

Treatment Plant”, Detailed Preliminary Design (final version).

11 ONAS-ICEA, 2008, “Limited Tariff Study Conducted as Part of Negotiations for the Performance

Contract to be Signed between the State of Senegal and ONAS”, Final Report, June 2008.

12 ONAS-SNC LAVALIN International, 2004, “New Cambérène Sea Outfall Project”, Interim Report –

Review of Existing Conditions, August 2004.

13 ONAS-SNC LAVALIN International, 2006, “New Cambérène Sea Outfall Project”, Final Version, Final

Design, March 2006.

14 ONAS-ICEA, 2006; “Organizational Study of the National Sanitation Authority of Senegal”, Report 3 –

Final Action Plan, Volume 1.

15 ONAS, 2010, “Report on the Audit of the Accounts of the Dakar City Sanitation Project” as at 31/12/2008,

Final Version, May 2010.

16 AfDB, 2009, “Inter-Office Memorandum on the Report on the Audit of the Accounts of the Dakar City

Sanitation Project” for the 2007 Financial Year.

17 ONAS, 2010, “Scientific Synthesis Note on the Cambérène Sea Outfall Construction Project”.

18 Senegal, 2005, Policy Statement on the Urban and Rural Water Supply and Sanitation Sector Policy

Statement.

19 Senegal, 2008, Law to Organize Public Water and Domestic Wastewater Treatment Services.

20 Senegal, 2010, Millennium Drinking Water and Sanitation Programme (PEPAM 2015), Annual Review.

2010 – Presentation Report by Mouhamed Fadel NDAW.

21 Senegal, 2010, Millennium Drinking Water and Sanitation Programme (PEPAM 2015), Annual Review

2009.

22 Senegal, 2006, Millennium Drinking Water and Sanitation Programme (PEPAM 2015), Support for the

Establishment of an Evaluation and Monitoring System for the Millennium Drinking Water and

Sanitation Programme.

Report No.1: PEPAM Evaluation and Monitoring System Design and Inventory of Usable Databases.

Report No. 2: Definition of PEPAM Monitoring Indicators.

23 Senegal, 2002, Poverty Reduction Strategy Paper (PRSP-I).

24 Senegal, 2006, Growth and Poverty Reduction Strategy Paper 2006-2010, October 2006 (DSRP-II).

25 Senegal, 2002, Urban and Rural Water Supply and Sanitation Sector Policy Statement.

26 Senegal, 2005, MDG Monitoring Report – Mid-term Evaluation.

27 Senegal, 2010, Dakar City Sanitation Project (PAVD), Borrower Completion Report.

28 Senegal, 2010, Post-disaster Needs Assessment Report – Urban Floods in Dakar 2009. Final Report (with

the support of the World Bank, the United Nations System and the European Commission).

29 World Bank, 2009, Senegal Long-Term Water Sector Programme, Implementation Completion Report.

30 SeydouNiang, 2009, Domestic Wastewater Treatment, prepared for the Workshop « Cities Feeding

People: Lessons Learned from Projects in African Cities », Nairobi, June 1998.

Page 64: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 9

Page 2/3

31 Senegal -JICA, 1994, “The Study on Sanitation in Dakar and its Surrounding Areas”, Main Report –

Pacific Consultants International, TOKYO in association with Tokyo Engineering Consultants CO. LTD.,

TOKYO.

Aide-mémoires and Back-to-Office Reports

1. Aide-mémoire of the Dakar City Sanitation Project (PAVD), Dakar Completion Report Preparation

Mission from 7-14 December 2009.

2. Aide-mémoire of the Dakar City Sanitation Project (PAVD), Dakar Supervision Mission from 24

November to 9 December 2008.

3. Aide-mémoire of the Dakar City Sanitation Project (PAVD), Dakar Supervision Mission from 11 to 26

June 2008.

4. Aide-mémoire of the Dakar City Sanitation Project (PAVD), Dakar Supervision Mission from 13 to 27

November 2007.

5. Aide-mémoire of the Dakar City Sanitation Project (PAVD), Dakar Supervision Mission from 19 June to

5 July 2007.

6. Aide-mémoire of the Dakar City Sanitation Project (PAVD), Dakar Supervision Mission from 19 June to

5 July 2007.

7. Back-to-Office Report, Senegal – Dakar City Sanitation Project (PAVD) and the First Rural DWSS

Initiative Sub-programme Supervision Mission, from 13 to 28 November 2007.

8. Back-to-Office Report, Senegal – Dakar City Sanitation Project (PAVD) and the First Rural DWSS

Initiative Sub-programme, Dakar Supervision Mission, from 11 to 25 June 2008.

9. Back-to-Office Report, Senegal – Dakar City Sanitation Project (PAVD) and the First Rural DWSS

Initiative Sub-programme, Dakar Supervision Mission, from 24 November to 9 December 2008.

Appraisal Reports

1. AfDB, 2010, Urban and Rural Water Supply and Sanitation Synthesis Note of Evaluation Results –

Operations Evaluation Department.

2. ADB, 2010, Evaluative Findings in Water Supply and Sanitation Projects. Asian Development Bank.

3. AfDB, 1999, Review of the Bank’s Experience in Rural Water Project Financing – Operations Evaluation

Department (OPEV).

4. AfDB, 2000, Review of the Bank’s Experience in Rural Water Project Financing. Presentation Note –

Operations Evaluation Department (OPEV).

5. AfDB, 2000, Study on the Bank’s Experience in Urban Water Supply and Sanitation Project Financing –

Operations Evaluation Department (OPEV).

6. AfDB, 2004, Assessment of the Bank’s Capacity Building Support to Urban Water Supply and Sanitation

Services of Regional Member Countries – Operations Evaluation Department (OPEV).

7. AfDB, 2000, Sector Indicators and Project Performance Indicators in the Water Supply and Sanitation

Sub-sector – Operations Evaluation Department (OPEV).

8. AfDB, 2001, Summary Report on the Bank’s Experience in Urban and Rural Water Supply and Sanitation

Projects – Operations Evaluation Department (OPEV).

9. ECG, 2011, Evaluation Findings on URBAN AND Rural Water Supply and Sanitation, ECG Paper 4.

10. EIB, 2009,”Evaluation of EIB Financing of Water and Sanitation Projects Outside the European Union.

11. European Union, 2010, Final External Project Evaluation of the “Improving Drinking Water and

Sanitation Access Conditions for the Vulnerable Populations of the Bardo Neighbourhood –San Pedro -

Côte d’Ivoire ” Project.

12. UNDP-World Bank, 1997, “Ensuring the Sustainability of Rural Water Supply – Recommendations of a

Global Study”.

13. World Bank, “Improving Access to Water and Sanitation Services by Poor Urban People – Collection of

Good Practices in Sub-Saharan Africa”.

14. World Bank, 2008, What Works in Water Supply and Sanitation? Lessons from Impact Evaluations – A

Summary of Findings”, Independent Evaluation Group.

Page 65: REPUBLIC OF SENEGAL DAKAR CITY SANITATION PROJECT (PAVD)idev.afdb.org/sites/default/files/documents/files... · evaluation of the Dakar City Sanitation Project (PAVD). The project

Annex 9

Page 3/3

15. World Health Organization, 2000, Operation and Maintenance of Water Supply and Sanitation Systems

– A Training Package for Managers and Planners.

Other Documents

1. AfDB-OECD-UNDP-ECA, Senegal 2010, Economic Outlook.

2. World Bank, 2008, “Senegal – Country Environmental Analysis», Final Report of 12 November 2008”.

3. Running Water, 2010, “For a Better Dissemination of Sahelian Rural Sanitation Facilities – 80 Concrete

Proposals”.

4. World Bank, 2005, “Operational Guidelines for World Bank Group Teams: Drinking Water and

Sanitation – Programme-based Approach and Budget Support”.

5. World Bank –Water and Sanitation Programme – Africa (PEA-AF), 2002, “The Men and Women of

Benin Evaluate their Drinking Water and Sanitation Project”.

6. World Bank, The Handwashing Handbook – Guide for Preparing a Handwashing with Soap Promotion

Programme.

7. Doulaye KONE, 2002, ‘Waste Water Treatment by Microphyte and Macrophyte (PistiaStratiotes)

Lagooning in West and Central Africa: States, treatment performances and design criteria’’ - Dissertation

No. 2653 (2002) submitted in fulfilment of the requirements for obtaining the degree of Doctor of

Technical Science in the Science and Environmental Engineering Field.

8. ECG, 2011, “Good Practices for the Evaluation of Public Sectors Operations”, 2011 Revised Edition,

First Draft of March 3, 2011.

9. WHO/FAO/CREDI, Study for the Integration of the Implementation of WHO Guidelines for the Use of

Wastewater and Excreta in Agriculture.

10. ONAS, EUROAID, 2009, “Precisions on the Capacity, Flow Rate and Treatment Level of the Cambérène

Treatment Plant ”, Nterim Report, 30 November 2009.

11. ONAS/EAWAG, “ Faecal Sludge Management – Optimizing the Process”, Proceedings of the

International Symposium on Faecal Sludge Management, Dakar, Senegal, 30 June – 1 July 2009 ».

12. ONAS, 2008, “Evaluation of the Information, Education and Communication Programme (IEC)” Cabinet

EDE & Phenix.

13. pS-Eau &F3E, 2011, “Designing and Implementing Water and Sanitation Project Monitoring and

Evaluation – Methodology Guide 1st Edition”.

14. pS-Eau,X, “Reflecting Gender in Rural and Semi-urban Drinking Water Supply Projects – Methodology

Guide”.

15. PARIS21, 2008, Officials Statistics and Monitoring and Evaluation Systems in Developing Countries:

Friends or Foes?”

16. Senegal, 2006, Drinking Water and Sanitation Programme for the Millennium (PEPAM 2015)

Implementation Procedures and Tools (provisional version).

17. Senegal, 2010, «2009 », Ministry of Health and Prevention, National Health Information Service (SNIS).

18. Senegal, 2008, 2007 Statistical Yearbook – Volume 2», Ministry of Health and Prevention, National

Health Information Service (SNIS).

19. Senegal, 2010, “Information and Sharing Workshop on Sanitation in Dakar”, Non-State Players’ Platform

for Monitoring the Cotonou Agreement in Senegal, June 2010.

20. Senegal, “Socio-economic Situation of the Dakar Region (2005, 2006, 2007 and 2008)”; Ministry of the

Economy and Finance – National Statistics and Demography Agency – Regional Statistics and

Demography Service – Dakar.

21. Senegal, “National Gender Equality and Equity Strategy (SNEEG) 2015”, Ministry of Women’s

Empowerment, Family and Social Development (MFFDS).

22. WSP, 2010, “Gender in Water and Sanitation”, Water and Sanitation Program Working Paper.

Radoux Michel et al., «Treatment and Reuse of Urban Domestic Wastewater in Developing Regions:

Examples in Senegal (Dakar Cambérène) and in Morocco (Tétouan-M’Diq).


Recommended