Republic of the Philippines Department of Agriculture PROPOSED BREAKWATER PROJECT
Transcript
Page 1: Republic  of the Philippines

Republic of the PhilippinesDepartment of Agriculture

PROPOSED BREAKWATER PROJECT

Page 2: Republic  of the Philippines

ILOILO FISH PORT COMPLEX

ILOILO RIVER

ILOILO STRAIT

Page 3: Republic  of the Philippines

QUAYSIDE

BREAKWATER, 470 m

Page 4: Republic  of the Philippines

DAMAGED REVETMENT

WAVE DIRECTION BROUGHT BY SOUTHWEST MONSOON & INCLEMENT WEATHER

EXISTING BREAKWATER

Page 5: Republic  of the Philippines

386 m

250

m

WAVE DIRECTION BROUGHT BY SOUTHWEST MONSOON & INCLEMENT WEATHER

130 m

PROPOSED CONSTRUCTION OF NEW BREAKWATER

Page 6: Republic  of the Philippines

65 m.

86 m.

250 m.

350 m.

130 m.

ILOILO

FISHPO

RT C

OM

PLEX

PROPOSED BREAKWATER

(PHASE I)SITE DEVELOPMENT PLAN

EXISTING BREAKWATER

PROPOSED CONTRUCTION OF IFPC BREAKWATER (PHASE I)

100

m.

99 m.

Page 7: Republic  of the Philippines

PROJECT : CONSTRUCTION OF BREAKWATER AT ILOILO FISH PORT COMPLEX (PHASE 1 )

LOCATION: BRGY TANZA, ILOILO CITY

TYPE : CONCRETE BLOCKSSCOPE OF WORKS ESTIMATED COST

1. CONSTRUCTION OF BREAKWATER 35,456,310.68

ESTIMATED DIRECT COST PHP 37,044,939.71

PLUS :

MARK-UP ................................... 17% 6,297,639.75

VAT ........................................... 12% 5,201,109.54

TOTAL CONSTRUCTION COST PHP 48,543,689.00

PLUS :

ADMINISTRATIVE/ENG’G SERVICES..... 1% 485,436.89

BUDGET CONTINGENCY...................... 2% 970,873.78

TOTAL PROJECT COST PHP 50,000,000.00

TOTAL LENGHT IN METER 98.73

COST PER LINEAR METER PHP 506,428.98

Page 8: Republic  of the Philippines

PRE-CONSTRUCTION IMPLEMENTATION SCHEDULE

PROJECT BUDGETARY COST CONTRACT DURATION1. Construction of IFPC Breakwater (Phase I) PHP 50.00 M. 300 Calendar Days

ACTIVITY PERIOD1. Pre-Procurement Conference May 2, 2012

2. Publication/Posting of Invitation to Bid/Letter of Intent May 14 – 18 , 2012

3. Issuance of Bid Documents May 14 – 25 , 2012

4. Pre-bid Conference May 29, 2012

5. Submission/Bid Opening June 11, 2012

6. Evaluation of Bids June 13 – 20 , 2012

7. Post -qualification June 21 - 29 , 2012

8. Recommend Award to the PFDA Board of Directors 1st week of July 2012

9. Approval of Resolution/ Issuance of Notice of Award July

10. Contract Preparation and Signing July

11. Issuance of Notice to Proceed July

12. Construction Period August 2012 to May 2013

Page 9: Republic  of the Philippines

IFPC HARBOR BASIN TAKEN SEPT. 28, 2011

EXISTING BREAKWATER


Recommended