+ All Categories
Home > Documents > Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an...

Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an...

Date post: 01-Mar-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
14
Research Article Model and Topological Characteristics of Power Distribution System Security Region Jun Xiao, Guo-qiang Zu, Xiao-xu Gong, and Cheng-shan Wang Key Laboratory of Smart Grid of Ministry of Education, Tianjin University, Nankai District, Tianjin 300072, China Correspondence should be addressed to Jun Xiao; [email protected] and Guo-qiang Zu; zuguoqiang [email protected] Received 16 January 2014; Accepted 28 June 2014; Published 24 July 2014 Academic Editor: H. D. Chiang Copyright © 2014 Jun Xiao et al. is is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. As an important tool of transmission system dispatching, the region-based method has just been introduced into distribution area with the ongoing smart distribution grid initiatives. First, a more accurate distribution system security region (DSSR) model is proposed. e proposed model is based on detailed feeder-interconnected topology, and both substation transformer and feeder N-1 contingencies are considered. Second, generic characteristics of DSSR are discussed and mathematically proved. at is, DSSR is a dense set of which boundary has no suspension and can be expressed by several union subsurfaces. Finally, the results from both a test case and a practical case demonstrate the effectiveness of the proposed modeling approach; the shape of DSSR is also illustrated by means of 2- and 3-dimensional visualization. Moreover, the DSSR-based assessment and control are preliminary illustrated to show the application of DSSR. e researches in this paper are fundamental work to develop new security region theory for future distribution systems. 1. Introduction is paper presents a model of power distribution system security region (DSSR) which takes both substation trans- former and feeder N-1 contingencies into account. Mean- while, main topological characteristics of DSSR are also discussed and mathematically proved. DSSR is a newly proposed concept originated from N- 1 security guideline [1, 2]. DSSR is defined as the set of all operating points that make the distribution system N-1 secure, taking into account the capacities of substation trans- formers, network topology, network capacity, and operational constraints. Traditional method of security assessment and control focused on service restoration in which load transfer scheme is made on case by case N-1 test [3, 4]. However, the “point-wise” simulation method only provides the binary information of security and insecurity, which causes global information and description of the security boundary to fail to be obtained [5]. Moreover, with the number of intercon- nected feeders growing in distribution systems, especially in urban areas, the simulation time of “point-wise” method that has to be calculated online is highly prohibitive. In contrast, the “region” method has advantages in dealing with the problems above. In transmission system, the research on security region has made substantial achievements. Author of [68] described the topological characteristics for security region and defined the practical model for engineering application. However, the “region” method has scarcely been applied in distribution area. Because early systems were little more than an extension of SCADA beyond the substation fence, most operations of 10 or 20 kV feeders required a high degree of human intervention [9]. Plus, without high speed peer- to-peer communication system, a wealth of key operation information cannot be timely received by dispatchers, which limited the actual contribution of “region” method. Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution systems to fully information-based systems [10, 11]. at is a motivation for researchers to perform the research on “region” method aiming at distribution system. References [12, 13] proposed the concept of loadability. It is defined as the maximum loading level that can be supplied. Loadability is similar to the proposed “region” Hindawi Publishing Corporation Journal of Applied Mathematics Volume 2014, Article ID 327078, 13 pages http://dx.doi.org/10.1155/2014/327078
Transcript
Page 1: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

Research ArticleModel and Topological Characteristics of Power DistributionSystem Security Region

Jun Xiao Guo-qiang Zu Xiao-xu Gong and Cheng-shan Wang

Key Laboratory of Smart Grid of Ministry of Education Tianjin University Nankai District Tianjin 300072 China

Correspondence should be addressed to Jun Xiao xiaojuntjueducn and Guo-qiang Zu zuguoqiang tju163com

Received 16 January 2014 Accepted 28 June 2014 Published 24 July 2014

Academic Editor H D Chiang

Copyright copy 2014 Jun Xiao et alThis is an open access article distributed under the Creative Commons Attribution License whichpermits unrestricted use distribution and reproduction in any medium provided the original work is properly cited

As an important tool of transmission system dispatching the region-based method has just been introduced into distribution areawith the ongoing smart distribution grid initiatives First a more accurate distribution system security region (DSSR) model isproposed The proposed model is based on detailed feeder-interconnected topology and both substation transformer and feederN-1 contingencies are considered Second generic characteristics ofDSSR are discussed andmathematically provedThat is DSSR isa dense set of which boundary has no suspension and can be expressed by several union subsurfaces Finally the results from both atest case and a practical case demonstrate the effectiveness of the proposedmodeling approach the shape of DSSR is also illustratedby means of 2- and 3-dimensional visualization Moreover the DSSR-based assessment and control are preliminary illustrated toshow the application of DSSRThe researches in this paper are fundamental work to develop new security region theory for futuredistribution systems

1 Introduction

This paper presents a model of power distribution systemsecurity region (DSSR) which takes both substation trans-former and feeder N-1 contingencies into account Mean-while main topological characteristics of DSSR are alsodiscussed and mathematically proved

DSSR is a newly proposed concept originated from N-1 security guideline [1 2] DSSR is defined as the set ofall operating points that make the distribution system N-1secure taking into account the capacities of substation trans-formers network topology network capacity and operationalconstraints Traditional method of security assessment andcontrol focused on service restoration in which load transferscheme is made on case by case N-1 test [3 4] Howeverthe ldquopoint-wiserdquo simulation method only provides the binaryinformation of security and insecurity which causes globalinformation and description of the security boundary to failto be obtained [5] Moreover with the number of intercon-nected feeders growing in distribution systems especiallyin urban areas the simulation time of ldquopoint-wiserdquo methodthat has to be calculated online is highly prohibitive In

contrast the ldquoregionrdquo method has advantages in dealing withthe problems above

In transmission system the research on security regionhas made substantial achievements Author of [6ndash8]described the topological characteristics for security regionand defined the practical model for engineering applicationHowever the ldquoregionrdquo method has scarcely been applied indistribution area Because early systems were little more thanan extension of SCADA beyond the substation fence mostoperations of 10 or 20 kV feeders required a high degreeof human intervention [9] Plus without high speed peer-to-peer communication system a wealth of key operationinformation cannot be timely received by dispatcherswhich limited the actual contribution of ldquoregionrdquo methodDistribution automation (DA) is an important conceptincluded in smart distribution grid and will upgrade thedistribution systems to fully information-based systems[10 11] That is a motivation for researchers to perform theresearch on ldquoregionrdquo method aiming at distribution system

References [12 13] proposed the concept of loadabilityIt is defined as the maximum loading level that can besupplied Loadability is similar to the proposed ldquoregionrdquo

Hindawi Publishing CorporationJournal of Applied MathematicsVolume 2014 Article ID 327078 13 pageshttpdxdoiorg1011552014327078

2 Journal of Applied Mathematics

Substation 1

Traditional load

transfermode

Future load transfer mode

with FA

Substation 2

Load Bus tie

FaultTie switchFeeder

switchSectionalswitch

Load

Bus tie

T1

T2

T3

T4

2 times 40MVA 2 times 40MVA

Figure 1 Load transfer mode

concept However because of not considering N-1 cases theconcept is not suitable for urban system where N-1 security isa high concern

Total supply capability (TSC) is a newly proposed conceptwhich is defined as the capability that a system can supplythe load when the N-1 security for distribution systems isconsidered [14 15] At the TSC point the facilities in thesystem are usually fully utilized Although some TSC resultscan be used as the points of DSSR boundary [15] TSC failsto describe the integrated boundary Moreover TSC cannotobtain the relative location of an operating point in securityregion which is very useful for dispatchers tomake decisionsIn a word TSC ismore suitable to be applied in planning thanoperating process

Author of [1] made attempt to present a simplified modeland approach of security assessment with the concept ofDSSR But the papers exposed 2 main defects (1) only theload of substation transformers and their rated capacities areformulated which provide relatively limited information onthe system status (2) feeder contingency and maintenanceare ignored although feeder contingency occurs much morefrequently than transformer contingency

The DSSR theory has potential applications Howeversome wrong conclusions will be reached if the topologicalcharacteristics of DSSR are not studied Paper [16] designedan N-1 approximating approach to study the characteristicsof DSSR But those characteristics have not been provedby rigorous mathematical method and some of them areinaccurately described

This paper proposes a more accurate DSSR model Themathematical proof for the characteristics of DSSR is alsoperformed Finally a test case and a practical case are bothselected to testify the proposed model

2 Basic Concept and Method

21 N-1 Security for Distribution System The DSSR conceptis based on contingency scenarios Feeder contingency andsubstation transformer contingency are two main scenarios

considered in security analysis Here if a distribution systemis feeder N-1 secure it means that when a fault occursat outlet of any main feeder the corresponding load canbe transferred to other feeders with a series of tie-switchoperations Meanwhile all components in the system operatenormally without overload or overvoltage Similarly if adistribution is substation transformer N-1 secure it meansthat when a fault occurs at any substation transformer thecorresponding load can be transferred to other transformerswith all the components satisfying the operation constraintsThe load of a transformer can be transferred in two waysone way is to be transferred to the adjacent transformers inthe same substation with bus-tie switches the other way is tobe transferred to other substations by tie-switch operationsamong feeders

22 Load Transfer and Concept of DSSR Feeders in tra-ditional medium-voltage network are not completely auto-mated When a fault occurs at a substation transformerload will be only transferred to adjacent transformers inthe same substation even though feeders form connectionbetween substationsManual performing for complex circuit-restoration switching takes time and is not performed inpractical operation Thus it causes a lower load ratio ofsubstation transformers which also means a conservativeutilization of assets

However development of smart distribution grid hasgreatly promoted the level of feeder automation especially insome core urban areaDistributed intelligence and automatedswitching accomplish the task that is to transfer load amongdifferent substations quickly accurately and flexibly In otherwords switches that the planner formerly could not tie cannow be tied resulting in higher load ratio within securityconstraints This draws the attention to a more accuratecalculation of security boundary Figure 1 shows the loadtransfer mode after feeder automation (FA)

As is shown in Figure 1 when a fault occurs at T1 intraditional way all of the load of T1 will be only transferredto T2 because the time of load transfer through feeders is

Journal of Applied Mathematics 3

Feeder 1

Normally closed switchNormally open switchBack-feed (transfer) path

FaultS1 S2 S3

S4Feeder 2

Feeder 3

S1f

S1FS2f

S3f

S4f

Figure 2 Feeder and transfer unit load

too long In contrast with feeder automation the load of T2can be transferred not only to T1 but also to T3 in anothersubstation

The DSSR model in this paper takes both substationtransformer N-1 and feeder N-1 contingency into accountThe DSSR is defined as the set of operating points whichassure the N-1 security of distribution system An operatingpoint in transmission system is the current power injectionsof nodes while in distribution system it represents a set oftransfer unit load Consider

W = (1198781

119891 1198782

119891 119878

119899

119891)119879

(1)

whereW is the operating point which is an n-dimensionvector 119878119894

119891is transfer unit load ldquoTransfer unitrdquo is defined as

the set of feeder sections of which load has the same back-feed (transfer) path If two feeders form single loop networktransfer unit load is equivalent to feeder load If a feederis connected to two other feeders which is called two-tieconnection the feeder load can be divided into two parts ofload each of which is a transfer unit load In this paper feederload i is denoted by 119878119894

119865and transfer unitload 119894 is denoted by

119878119894119891 Take the brief case in Figure 2 as an exampleIn Figure 2 feeder 1 forms two-tie connection and feeder

2 and feeder 3 form single loop network respectively withfeeder 1 In normal state 1198781

119891and 1198782119891are both supplied by feeder

1 that is 1198781119865= 1198781119891+ 1198782119891 When a fault occurs at outlet of

feeder 1 S1 and S2 disconnect and S4 closes and then 1198781119891

changes to be supplied by feeder 3 while 1198782119891is supplied by

feeder 2 via closing S3 Transfer scheme is usually not uniqueAnother scheme is that transferring both 1198781

119891and 1198782119891to feeder

2 by disconnecting S1 and closing S3 However multischememakes the DSSR model overcomplicated Thus scheme isfixed in this paper which stipulates that each of the backupfeeders restores only one section of the whole faulted feederas the first scheme above More important this fixed schemecan usually balance the branch load in the postfault networkwhich is an important index concerned by dispatchers

The DSSR model in this paper is accurate to the safetymonitoring of transfer unit load We can certainly get feederload by summing up the transfer unit load and further get

transformer load by summing up the feeder load This is abasis for DSSR model considering both transformer N-1 andfeeder N-1 security

3 Mathematical Model for DSSR

After the load transfer incurred by tie switches against N-1 contingency all the transformers and feeders cannot beoverloading Since the tie-line is designed after the radialnetwork planning the capacity is considered as enough totransfer loadTherefore the transformer load and feeder loadshould be under a series of constraints The DSSR model canbe mathematically formulated as

ΩDSSR = W | ℎ (119909) le 0 119892 (119909) = 0 (2)

where W = (1198781119891 1198782119891 119878119899

119891)119879 is the operating point cor-

responding to 1198781119891 1198782

119891 119878

119899

119891 The inequality and equality

constraints are such that

119878119898

119865= sum119899=1

119878119898119899

119891119905119903 (3)

119878119898119899

119891119905119903+ 119878119899

119865le 119878119899

119865max (forall119898 119899) (4)

119878119894119895

119879119905119903= sum

119898isinΦ(119894)119899isinΦ(119895)

119878119898119899

119891119905119903 (5)

119878119894

119879= sum

119898isinΦ(119894)

119878119898

119865(forall119894) (6)

119878119894119895

119879119905119903+ 119878119895

119879le 119878119895

119879max (7)

where 119878119898119865

= all the load supplied by feeder m 119878119898119899119891119905119903

=the load transferred from feeder m to feeder n when anN-1 fault occurs at outlet of feeder m 119878119899

119865max = maximalthermal capacity of feeder 119899 119878119894119895

119879119905119903= the load transferred from

transformer 119894 to transformer 119895 when an N-1 fault occursat transformer 119894 Φ(119894) = the set of feeders that derive fromtransformer 119894 119878119895

119879= all of the load supplied by transformer 119894

119898 isin Φ(119894)means that feeder119898 derives from the correspondingbus of transformer 119894 119878119894

119879max = the rated capacity of transformer119894

It is notable that the correspondence relation of ldquo119878119891119905119903

rdquoand ldquo119878

119891rdquo depends on the load transfer scheme For example

in Figure 2 in the former scheme 11987812119891119905119903

= 1198782119891 in the latter

scheme 11987812119891119905119903= 1198781119891+ 1198782119891

Equation (3) shows that the sum of each load to betransferred away from feeder m should be equal to thetotal load supplied by feeder m in normal state inequalityconstraint (4) means that feeders cannot be overloading inthe postfault network (5) shows that path of load transferredfrom transformer 119894 to 119895 is the tie-lines between transformers 119894and 119895 Equation (6) means that load of transformer is equal tothe sum of corresponding feeder loads inequality constraint(7) describes that the load of transformer 119895 cannot exceed itsrated capacity after a substation transformerN-1 contingency

It should be pointed out that power flow and voltage dropare not taken into consideration in this DSSR model which

4 Journal of Applied Mathematics

determines that the DSSR model is completely linear Sinceoverloading under contingencies is the most critical prob-lem in urban power the simple linear model is acceptablefrom the standpoint of security-based operation [1] Moreimportantly research of [16] has demonstrated that the DSSRmodel is approximately linear even when considering factorsof power flow and voltage drop which further proves that thelinear model is highly approximate to the real DSSR model

4 Formulation for DSSR Boundary

Research on the boundary of security region has vital signif-icance because the characteristics determine the applicationway of DSSR theory [7] The proposed DSSR model whichis formulated as (2)ndash(7) cannot distinctly express the DSSRboundary Therefore derivation should be performed totransform the originalmodel to a new expression form Select119878119906V119891119905119903

as research object 119906 isin Φ(119894) and V isin Φ(119895) First formula(4) can be transformed to

119878119906V119891119905119903le 119878

V119865max minus 119878

V119865 (8)

Second substitute formulas (5) and (6) into (7) and thenperform identical deformation We obtain

0 le 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)

119878119898119899

119891119905119903 (9)

Third add 119878119906V119891119905119903

on both sides of formula (9) and then

119878119906V119891119905119903le 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)119898 =119906119899 =V

119878119898119899

119891119905119903 (10)

Finally according to (8) and (10) the expression of DSSRboundary in direction of 119878119906V

119891119905119903can be neatly formulated as

119878119906V119891119905119903

le min

119878V119865max minus 119878

V119865 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)

119898 =119906119899 =V

119878119898119899

119891119905119903

(11)

There are 119899 boundaries if the system consists of 119899load transfer units To express the dimension of boundaryclearly we denote all ldquo119878119906V

119891119905119903rdquo by 1198781

119891119905119903 1198782119891119905119903 119878119899

119891119905119903 Because

the transfer scheme in this paper is fixed as is illustrated inSection 22 an important equivalence holds as follows

119878119894

119891119905119903= 119878119894

119891(119894 = 1 2 119899) (12)

Through (12) 119878119891119905119903

and 119878119891have one-to-one corresponding

relation Above all the complete and succinct boundaryformulation for DSSR is expressed as

ΩDSSR

=

1198611

1198612

119861119894

119861119899

=

1198781119891le min

1198781198871119865max minus 119878

1198871

119865 1198781198871119879max minus sum

119895isinΦ(1198871)

119878119895

119865minus sum

119896 =1119896isinΘ(1)

119878119896119891

1198782

119891le min

1198781198872

119865max minus 1198781198872

119865 1198781198872

119879max minus sum

119895isinΦ(1198872)

119878119895

119865minus sum

119896 =2119896isinΘ(2)

119878119896

119891

119878119894

119891le min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

119878119899119891le min

119878119887119899119865max minus 119878

119887119899

119865 119878119887119899119879max minus sum

119895isinΦ(119887119899)

119878119895

119865minus sum

119896 =119899119896isinΘ(119899)

119878119896119891

(13)

With the form transformation ofDSSRmodel correspondingsymbols and their meaning should be adjusted too Thus 119887119894and Θ(119894) are used for new expression 119887119894 = the number ofback-feed feeders of 119878119894

119891 119878119887119894119865= all of the load supplied by the

back-feed feeder 119887119894 Θ(119894) = the set of transfer unit loads ofwhich both normal-feed and back-feed transformer are thesame as those of 119878119894

119891 It should be pointed out that feeder 1198871

feeder 119887119899 are not 119899 different actual feeders Take the case inFigure 2 as an example again when fault occurs the back-feed feeders of 1198783

119891and 1198784

119891are both feeder 1 which means

feeder b3 = feeder b4 = feeder 1 When any equality in (13)holds the operating point is just upon the DSSR boundaryWe denote the n boundaries by 119861

1 119861

119899

The DSSR boundary formulation can also reflect bothsubstation transformer and feeder N-1 secure constraintsTake 119894 subformula of (13) to concretely explain 119878119894

119891le

119878119887119894119865max minus 119878

119887119894

119865shows that transfer of 119878119894

119891cannot cause the feeder

overloading which ensures that the feeder N-1 is secure 119878119894119891le

119878119887119894119879max minus sum119895isinΦ(119887119894) 119878

119895

119865minus sum119896 =1119896isinΘ

(119894) 119878119896

119891shows that transfer of 119878119894

119891

cannot lead to the substation transformer overloading whichensures that the transformer N-1 is secure

5 Topological Characteristics of DSSR andMathematical Proof

The research on differential topological characteristics of theDSSR focuses on several aspects as follows

Journal of Applied Mathematics 5

(1) Are there any holes inside the DSSR that is thedenseness in terms of the topology

(2) Does the boundary of the DSSR have suspension(3) Could the boundary of the DSSR be expressed with

the union of several subsurfaces

The identical deformation from formulas (2)ndash(7) to (13) isa breakthrough for the research on topological characteristicsof the DSSR However to research on these characteristicsformula (13) should be further simplified to obtain themathematical essence Take 119894 subformula of (13) as researchobject the equivalent form is

119878119894

119891+ 119878119887119894

119865le 119878119887119894

119865max

119878119894

119891+ sum

119895isinΦ(119887119894)

119878119895

119865+ sum

119896 =1119896isinΘ(119894)

119878119896

119891le 119878119887119894

119879max(14)

According to formulas (3) and (12) 119878119887119894119865

and 119878119895119865

can beexpressed as linear combination of a series of differentelement ldquo119878

119891rdquo Then formula (14) will be simplified as

119899

sum119898=1

120572119898119878119898

119891le 119878119887119894

119865max

119899

sum119898=1

120573119898119878119898

119891le 119878119887119894

119879max

(15)

where 119878119887119894119865max and 119878119887119894

119879max are positive constants Throughformula (14) coefficients 120572 and 120573 have the following features

120572119898= 1 120573

119898= 1 (119898 = 119894)

120572119898= 0 or 1 120573

119898= 0 or 1 (119898 = 119894)

(16)

LetΩDSSR be a set which consists of operating pointW DSSRboundary formulation can be abstracted as

AW le C (17)

whereW is a vector defined as formula (1)Through formulas(15)-(16) matrices A and C should satisfy

A = [119886119894119895]2119899times119899

119894 ge 1 119895 ge 1

119886119894119895= 1 (119894 = 2119895 minus 1 or 119894 = 2119895)

119886119894119895= 0 or 1 (119894 = 2119895 minus 1 119894 = 2119895)

C = [1198881 1198882 1198882119899]119879

C isin R+

(18)

Because one integrated subformula is divided into equivalenttwo parts as is shown in formula (15) the dimension ofA is 2119899 times 119899 instead of 119899 times 119899 Here ΩDSSR is both linearspace and Euclidean space which has been proved in [17]Besides this important premise we should review somepreparation definitions and theorems about topology andEuclidean space including cluster point closure dense setand hyperplane

Definition 1 (cluster point) Let x be a point in Euclideanspace 119865 sub 119877 If there is a point sequence in set 119865 convergingto x then x is the cluster point of set 119865 [17]

Definition 2 (closure) 119860 is a subset of topological space 119860represents all the points inside 119860 and cluster points of 119860 andthen 119860 is called closure of 119860 [18]

Theorem 3 If the 119861 is a subset of 119860 119861 = 119860 then 119861 is dense in119860 [18]

Theorem 4 Let 119871 be a subspace of linear space 119877 x0 is a fixedvector which does not belong to 119871 generally Considering set119867which consists of the vector x x is obtained by

x = x0 + y (19)

where vector y varies in the whole subspace 119871 Thus119867 is calledhyperplane The dimension of119867 equals that of subspace 119871 [17]

The topological characteristics of DSSR are mathemati-cally proved in the following section

Characteristic 1 TheΩDSSR is dense inside

Proof First a new setΩ1015840DSSR is defined as the set of all pointsofΩDSSR except those on boundariesΩ1015840DSSR meets

AW lt C (20)

Select randomly a vector W = (1198781119891 1198782119891 119878119899

119891)119879 from Ω1015840DSSR

and then construct a sequenceY = Y1Y2 Ym as the

following formula

Y =

Y1= (1198781119891minus1198781119891

1 1198782119891minus1198782119891

1 119878119899

119891minus119878119899119891

1)

119879

= (0 0 0)119879

Y2= (1198781

119891minus1198781119891

2 1198782

119891minus1198782119891

2 119878

119899

119891minus119878119899119891

2)

119879

Y119898= (1198781119891minus1198781119891

119898 1198782119891minus1198782119891

119898 119878119899

119891minus119878119899119891

119898)

119879

= (1 minus1

119898)W

(21)

According to (20)-(21) we obtain

AYm = A(1 minus 1119898)W lt AW lt C (22)

Therefore sequence Y = Y1Y2 Ym is inside Ω1015840

DSSRLet 120588(WYm) be the distance betweenWandYm in Euclideanspace and then

lim119898rarrinfin

120588 (WYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(23)

6 Journal of Applied Mathematics

0

Snf (MVA)

Smf (MVA)

c3

c2c1 gt c2 + c3

DSSR

max(c2 c3) lt c1 lt c2 + c3

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

min(c2 c3) lt c1 lt max(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

0 lt c1 lt min(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

Figure 3 Shapes of 2-dimension cross-section of DSSR

Thismeans that for any vectorW inΩ1015840DSSR sequenceY existsand converges toW andY is also insideΩ1015840DSSRTherefore anypoint insideΩ1015840DSSR is cluster point of Ω

1015840

DSSRSimilarly select vector Z = (1198781

119891 1198782119891 119878119899

119891)119879 which is just

upon boundary ofΩ119863119878119878119877

AZ = C (24)

Construct a sequence U = U1U2 Um

Um = (1 minus1

119898)Z (25)

Then we obtain

AUm = A(1 minus 1119898)Z lt AZ = C (26)

According to formula (26) sequence U is also inside Ω1015840DSSRThrough the following

lim119898rarrinfin

120588 (ZYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(27)

We obtain that any point just upon the ΩDSSR boundary isalso cluster point ofΩ1015840DSSR Above all cluster points ofΩ

1015840

DSSR

include not only all the points inside Ω1015840DSSR but also all thepoints just upon the boundaries ofΩDSSRThus the followingformula holds

Ω1015840DSSR = ΩDSSR (28)

Through Theorem 3 Ω1015840DSSR is dense in ΩDSSR This proof iscompleted

Characteristic 2 The boundary ofΩDSSR has no suspension

Proof This characteristic can be approximately simplified toprove that any 2-dimension cross-section of ΩDSSR is convexpolygon For W = (1198781

119891 1198782119891 119878119899

119891)119879 select a 2-dimension

cross-section by taking 119878119898119891

and 119878119899119891as variables and 119878

119891in

another dimension as constants According to formula (16)the coefficient of 119878

119891(including variable 119878

119891and constant ones)

can be only 1 or 0 thus in process of dimension reduction 119878119898119891

and 119878119899119891are simply constrained by

119878119898

119891+ 119878119899

119891le 1198881

0 le 119878119898

119891le 1198882

0 le 119878119899

119891le 1198883

forall1198881 1198882 1198883isin 119877+

(29)

Journal of Applied Mathematics 7

Table 1 Profile of test case

Substation Transformer Voltages (kVkV) Transformer capacity (MVA) Number of feeders Total feeder capacity (MVA)

S1 T1 3510 400 9 8028T2 3510 400 9 8028

S2 T3 3510 400 9 8028T4 3510 400 8 7136

S3 T5 11010 630 10 892T6 11010 630 10 892

S4 T7 11010 630 10 892T8 11010 630 10 892

The shape of 2-dimension cross-section varies with the valuesof 1198881 1198882 and 119888

3 as is shown in Figure 3 The dashed oblique

line represents 119878119898119891+ 119878119899119891le 1198881

As is shown in Figure 3 the shapes of 2-dimension sectionare confined to rectangle triangle ladder and convex pen-tagon This means that any 2-dimension section of DSSR isconvex polygon which proves that the boundary ofΩDSSR hasno suspension in an indirect wayThe proof is completed

Characteristic 3 The ΩDSSR boundary can be expressed withseveral subsurfaces

Proof 119867 is a set of vector W = (1198781119891 1198782119891 119878119899

119891)119879 each of

which satisfies nonhomogeneous linear equation set

AW = C (30)

where matrices A and C meet formula (18) and W is theoperating point just upon the boundary of ΩDSSR Let W0 =

(120579(0)

1 120579(0)

2 120579(0)

119899)119879 be a fixed solution of equation set (31)

Meanwhile 119871 is a subspace of 119877 which consists of y =

(1205821 1205822 120582

119899)119879 that is y varies in the whole subspace 119871

The coordinates of ymeet the following homogeneous linearequation set

Ay = 0 (31)

If y = (1205821 1205822 120582

119899)119879 is a solution of (31) W = W0

+y = (120579(0)

1+ 1205821 120579(0)

2+ 1205822 120579(0)

119899+ 120582119899)119879 is obviously

a solution of equation set (30) that is W is included inset 119867 Meanwhile x0 is not in 119871 Through Theorem 3 119867is hyperplane The boundary of ΩDSSR can be expressedwith hyperplane that is several subsurfaces Because thedimension of 119871 is 119899 the dimension of hyperplane is also 119899This proof is completed

In transmission area topological characteristics of secu-rity region (SR) have been deeply studied [7] It has shownthat the boundary of SR has no suspension and is compactand approximately linear there is no hole inside the SR Theproof above demonstrates that characteristics of DSSR aresimilar but it has its own features

(a) DSSR is a convex set of denseness in terms ofthe topology This means that DSSR has no holesinside and its boundary has no suspension Basedon this feature dispatchers can analyze the securityof operating point by judging whether the point isinside theDSSRboundarywithout being afraid of anyinsecure point inside or losing security points

(b) DSSR boundary can be described by hyperplane (sev-eral Euclidean subsurfaces) meanwhile the bound-ary ismore linear than that of SR In practical applica-tion calculation of high dimensional security regionwill incur great computation burdens and consumelarge amount of time Therefore this characteristicwill improve the computational efficiency

6 Case Study

In order to verify the effectiveness of the proposedmodel twocases are illustrated in this section The first one is a test caseand the second is a practical case

61 Test Case

611 Overview of Test Case As is shown in Figure 4 the gridis comprised of 4 substations 8 substation transformers and75 feeders 68 feeders form 34 single loop networks and 7form two-tie connections resulting in 82 load transfer unitsThe total capacity of substations is 412MVA To illustrate themodeling process clearly each load transfer unit is numberedCase profile is shown in Table 1

The conductor type of all feeders is LGJ-185 (892MVA)This type is selected based on the national electrical code inChina

612 Boundary Formulation The test case grid has 75 feed-ers 14 feeders form 7 two-tie connections Each load of these7 feeders can be divided into 2 parts to transfer in differentback-feed path So the number of load transfer units is 82which means that the dimension of operation point W is82 and the number of subformulas of DSSR boundary is82 Based on the topology of the test case we substitutethe rated capacity of substation transformers and feedersinto 1198781

119865max 119878119899

119865max and 1198781119879max 119878

119899

119879max of formula (13)

8 Journal of Applied Mathematics

Then the boundary formulation for DSSR of test case can beexpressed as

ΩDSSR =

1198781

119891le min 892 minus (11987876

119891+ 11987836119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198782119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198782119891le min 892 minus (11987837

119891+ 11987877119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198783119891le min 892 minus (11987838

119891+ 11987878119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198784119891+ 1198785119891)

1198784119891le min 892 minus 11987839

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198785119891)

1198785119891le min 892 minus 11987840

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198784119891)

11987882119891le min 892 minus 11987851

119891 63 minus (11987846

119891+ 11987847119891+ 11987848119891+ 11987849119891+ 11987850119891+ 11987851119891+ 11987852119891+ 11987853119891+ 11987854119891+ 11987855119891) minus 11987881119891

(32)

Considering the similarity of calculation approach ofeach boundary and thesis length we present 5 subformulasof 1198781119891 1198785

119891here Complete formulation is given in the

appendix (in the Supplementary Material available online athttpdxdoiorg1011552014327078) Take the first subfor-mula in (32) as an example to explain the modeling processFigure 5 shows the local topology related with 1198781

119891 including

all relative transfer units in the first subformulaFirst analyze the topology and determine the parameters

of formula (13)We know that back-feed feeder of 1198781119891is feeder

36 and the back-feed substation transformer of 1198781119891is T5 In

normal state 11987836119891 11987845

119891and 11987876

119891 11987878

119891are all load of T5

which means sum119895isinΦ(1198871) 119878119895

119865= sum45

119895=36119878119895

119891+ sum78

119895=76119878119895

119891 11987836119891

and 11987876119891

are load of feeder 36 which means 1198781198871119865= 11987836119891+ 11987876119891 1198782119891 1198785

119891

are the load transferred fromT1 to T5when fault occurs at T1whichmeanssum

119896 =1119896isinΘ(1) 119878119896

119891= sum5

119896=2119878119896119891Therefore the formula

of B1 is preliminary expressed as

1198781

119891le min 11987836

119865max minus (11987876

119891+ 11987836

119891)

1198785

119879max minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(33)

Second according to case profile substitute 11987836119865max =

892MVA and 1198785119879max = 63MVA into formula (33) and then

we obtain

1198781

119891le min 892 minus (11987876

119891+ 11987836

119891)

63 minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(34)

613 Visualization and Topological Characteristics To visu-alize the shape of DSSR the dimension is reduced to 2 and 3which means that the coordinates of W should be constantsother than those to be visualized Thus an operating pointhas to be predetermined to provide the constants TSC is aspecial operating point just upon the security boundary [1]on which the facilities are usually fully utilizedThe operationof distribution system is closing to the boundaries and loadlevel is reaching TSCThus in this test case we select the TSCpoint as the predetermined operating point WTSC which isshown in Table 2The calculation approach for TSC has beenpresented in [15]

Choose randomly transfer unit loads 11987815119891

and 11987852119891

toobserve Substitute the rated capacity of transformers T1simT6capacity of all feeders and all transfer unit loads other than11987815119891

and 11987852119891 into formula (32) Then the 2D DSSR shown in

Figure 6 is obtainedAlthough the dimension is 2 the number of subformulas

which constrain the figure shape is not just 2 In fact eachof the subformulas which contains 11987815

119891or 11987852119891

should beconsidered But the subformulas withmore severe constraintswill cover the others and finally form theDSSR boundaryThefinal formulation of 2D figure is

0 le 11987815

119891le 52

0 le 11987852

119891le 3

(35)

Journal of Applied Mathematics 9

T1S1

T2

T3

T4

S 2

S4

T8

T6S3

T5

17-1

8

20-19

12ndash1

415

-16

21ndash23

41-4

3

36ndash3

8

39-4

044

-45

47-4

650

-51

52-5

3

54-5

548

-49

10-1

1

9-8

1 ndash3

4-5

6-7

76ndash7

8

79-80

58-5960-61

57-5665-62

66ndash6970-71

72ndash7524-25

29-28

26-27

30-31

32ndash35

81-8

2

Tie switch

T7

Distribution transformer

(i + 1) j are the same in the topologyin terms of calculation for DSSR

Note means that transfer units iindashj

Figure 4 Test case with eight substation transformers

Feeder 1

T1

T5

Feeder 2Feeder 36Feeder 37

S1f

S2f

S3f

S76f

S77f

S78f

S36f

S36f

S37f

S45f

S4f

S5f

middot middot middot

middot middot middot middot middot middot

Figure 5 Local topology related with f1

Similarly we choose randomly transfer unit loads 11987819119891 11987824119891

and 11987832119891

to observe and then the 3D DSSR is obtained as isshown in Figure 7

In Figure 6 it can be seen that the 2D DSSR is a denserectangle of which boundaries are linear without suspension

DSSR

0

1

2

3

1 2 3 4 52 S52f (MVA)

S15f (MVA)

Figure 6 Shape of 2D DSSR

In Figure 7 the 3D DSSR is surrounded by several subplanesforming a convex pentagon that is a special 3-dimensionhyperplane

10 Journal of Applied Mathematics

Table 2 Transfer unit load ofWTSC in test case

Transfer unit Load (MVA)1 2882 2883 2884 2885 2886 1647 1648 1649 16410 28811 28812 31713 31714 31715 31716 31717 30018 30019 31720 31721 34722 34723 31124 31125 31126 34727 34728 34729 34730 28031 28032 16133 16134 16135 16136 28037 28038 28039 28040 25241 32942 25243 32944 25245 32946 28847 28848 39549 395

Table 2 Continued

Transfer unit Load (MVA)50 39551 44652 44653 44654 44655 56456 56457 56958 56959 59260 59261 53362 53363 35964 35965 51366 51367 49468 49469 44670 44671 44672 44673 44674 44675 44676 44677 28078 28079 28080 28081 28082 280mdash mdashmdash mdash

01 2 3 4 5

2

3

1

12

34

56

DSSR

S32f

(MVA

)

S24f (MVA)

S19

f(M

VA)

Figure 7 Shape of 3D DSSR

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 2: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

2 Journal of Applied Mathematics

Substation 1

Traditional load

transfermode

Future load transfer mode

with FA

Substation 2

Load Bus tie

FaultTie switchFeeder

switchSectionalswitch

Load

Bus tie

T1

T2

T3

T4

2 times 40MVA 2 times 40MVA

Figure 1 Load transfer mode

concept However because of not considering N-1 cases theconcept is not suitable for urban system where N-1 security isa high concern

Total supply capability (TSC) is a newly proposed conceptwhich is defined as the capability that a system can supplythe load when the N-1 security for distribution systems isconsidered [14 15] At the TSC point the facilities in thesystem are usually fully utilized Although some TSC resultscan be used as the points of DSSR boundary [15] TSC failsto describe the integrated boundary Moreover TSC cannotobtain the relative location of an operating point in securityregion which is very useful for dispatchers tomake decisionsIn a word TSC ismore suitable to be applied in planning thanoperating process

Author of [1] made attempt to present a simplified modeland approach of security assessment with the concept ofDSSR But the papers exposed 2 main defects (1) only theload of substation transformers and their rated capacities areformulated which provide relatively limited information onthe system status (2) feeder contingency and maintenanceare ignored although feeder contingency occurs much morefrequently than transformer contingency

The DSSR theory has potential applications Howeversome wrong conclusions will be reached if the topologicalcharacteristics of DSSR are not studied Paper [16] designedan N-1 approximating approach to study the characteristicsof DSSR But those characteristics have not been provedby rigorous mathematical method and some of them areinaccurately described

This paper proposes a more accurate DSSR model Themathematical proof for the characteristics of DSSR is alsoperformed Finally a test case and a practical case are bothselected to testify the proposed model

2 Basic Concept and Method

21 N-1 Security for Distribution System The DSSR conceptis based on contingency scenarios Feeder contingency andsubstation transformer contingency are two main scenarios

considered in security analysis Here if a distribution systemis feeder N-1 secure it means that when a fault occursat outlet of any main feeder the corresponding load canbe transferred to other feeders with a series of tie-switchoperations Meanwhile all components in the system operatenormally without overload or overvoltage Similarly if adistribution is substation transformer N-1 secure it meansthat when a fault occurs at any substation transformer thecorresponding load can be transferred to other transformerswith all the components satisfying the operation constraintsThe load of a transformer can be transferred in two waysone way is to be transferred to the adjacent transformers inthe same substation with bus-tie switches the other way is tobe transferred to other substations by tie-switch operationsamong feeders

22 Load Transfer and Concept of DSSR Feeders in tra-ditional medium-voltage network are not completely auto-mated When a fault occurs at a substation transformerload will be only transferred to adjacent transformers inthe same substation even though feeders form connectionbetween substationsManual performing for complex circuit-restoration switching takes time and is not performed inpractical operation Thus it causes a lower load ratio ofsubstation transformers which also means a conservativeutilization of assets

However development of smart distribution grid hasgreatly promoted the level of feeder automation especially insome core urban areaDistributed intelligence and automatedswitching accomplish the task that is to transfer load amongdifferent substations quickly accurately and flexibly In otherwords switches that the planner formerly could not tie cannow be tied resulting in higher load ratio within securityconstraints This draws the attention to a more accuratecalculation of security boundary Figure 1 shows the loadtransfer mode after feeder automation (FA)

As is shown in Figure 1 when a fault occurs at T1 intraditional way all of the load of T1 will be only transferredto T2 because the time of load transfer through feeders is

Journal of Applied Mathematics 3

Feeder 1

Normally closed switchNormally open switchBack-feed (transfer) path

FaultS1 S2 S3

S4Feeder 2

Feeder 3

S1f

S1FS2f

S3f

S4f

Figure 2 Feeder and transfer unit load

too long In contrast with feeder automation the load of T2can be transferred not only to T1 but also to T3 in anothersubstation

The DSSR model in this paper takes both substationtransformer N-1 and feeder N-1 contingency into accountThe DSSR is defined as the set of operating points whichassure the N-1 security of distribution system An operatingpoint in transmission system is the current power injectionsof nodes while in distribution system it represents a set oftransfer unit load Consider

W = (1198781

119891 1198782

119891 119878

119899

119891)119879

(1)

whereW is the operating point which is an n-dimensionvector 119878119894

119891is transfer unit load ldquoTransfer unitrdquo is defined as

the set of feeder sections of which load has the same back-feed (transfer) path If two feeders form single loop networktransfer unit load is equivalent to feeder load If a feederis connected to two other feeders which is called two-tieconnection the feeder load can be divided into two parts ofload each of which is a transfer unit load In this paper feederload i is denoted by 119878119894

119865and transfer unitload 119894 is denoted by

119878119894119891 Take the brief case in Figure 2 as an exampleIn Figure 2 feeder 1 forms two-tie connection and feeder

2 and feeder 3 form single loop network respectively withfeeder 1 In normal state 1198781

119891and 1198782119891are both supplied by feeder

1 that is 1198781119865= 1198781119891+ 1198782119891 When a fault occurs at outlet of

feeder 1 S1 and S2 disconnect and S4 closes and then 1198781119891

changes to be supplied by feeder 3 while 1198782119891is supplied by

feeder 2 via closing S3 Transfer scheme is usually not uniqueAnother scheme is that transferring both 1198781

119891and 1198782119891to feeder

2 by disconnecting S1 and closing S3 However multischememakes the DSSR model overcomplicated Thus scheme isfixed in this paper which stipulates that each of the backupfeeders restores only one section of the whole faulted feederas the first scheme above More important this fixed schemecan usually balance the branch load in the postfault networkwhich is an important index concerned by dispatchers

The DSSR model in this paper is accurate to the safetymonitoring of transfer unit load We can certainly get feederload by summing up the transfer unit load and further get

transformer load by summing up the feeder load This is abasis for DSSR model considering both transformer N-1 andfeeder N-1 security

3 Mathematical Model for DSSR

After the load transfer incurred by tie switches against N-1 contingency all the transformers and feeders cannot beoverloading Since the tie-line is designed after the radialnetwork planning the capacity is considered as enough totransfer loadTherefore the transformer load and feeder loadshould be under a series of constraints The DSSR model canbe mathematically formulated as

ΩDSSR = W | ℎ (119909) le 0 119892 (119909) = 0 (2)

where W = (1198781119891 1198782119891 119878119899

119891)119879 is the operating point cor-

responding to 1198781119891 1198782

119891 119878

119899

119891 The inequality and equality

constraints are such that

119878119898

119865= sum119899=1

119878119898119899

119891119905119903 (3)

119878119898119899

119891119905119903+ 119878119899

119865le 119878119899

119865max (forall119898 119899) (4)

119878119894119895

119879119905119903= sum

119898isinΦ(119894)119899isinΦ(119895)

119878119898119899

119891119905119903 (5)

119878119894

119879= sum

119898isinΦ(119894)

119878119898

119865(forall119894) (6)

119878119894119895

119879119905119903+ 119878119895

119879le 119878119895

119879max (7)

where 119878119898119865

= all the load supplied by feeder m 119878119898119899119891119905119903

=the load transferred from feeder m to feeder n when anN-1 fault occurs at outlet of feeder m 119878119899

119865max = maximalthermal capacity of feeder 119899 119878119894119895

119879119905119903= the load transferred from

transformer 119894 to transformer 119895 when an N-1 fault occursat transformer 119894 Φ(119894) = the set of feeders that derive fromtransformer 119894 119878119895

119879= all of the load supplied by transformer 119894

119898 isin Φ(119894)means that feeder119898 derives from the correspondingbus of transformer 119894 119878119894

119879max = the rated capacity of transformer119894

It is notable that the correspondence relation of ldquo119878119891119905119903

rdquoand ldquo119878

119891rdquo depends on the load transfer scheme For example

in Figure 2 in the former scheme 11987812119891119905119903

= 1198782119891 in the latter

scheme 11987812119891119905119903= 1198781119891+ 1198782119891

Equation (3) shows that the sum of each load to betransferred away from feeder m should be equal to thetotal load supplied by feeder m in normal state inequalityconstraint (4) means that feeders cannot be overloading inthe postfault network (5) shows that path of load transferredfrom transformer 119894 to 119895 is the tie-lines between transformers 119894and 119895 Equation (6) means that load of transformer is equal tothe sum of corresponding feeder loads inequality constraint(7) describes that the load of transformer 119895 cannot exceed itsrated capacity after a substation transformerN-1 contingency

It should be pointed out that power flow and voltage dropare not taken into consideration in this DSSR model which

4 Journal of Applied Mathematics

determines that the DSSR model is completely linear Sinceoverloading under contingencies is the most critical prob-lem in urban power the simple linear model is acceptablefrom the standpoint of security-based operation [1] Moreimportantly research of [16] has demonstrated that the DSSRmodel is approximately linear even when considering factorsof power flow and voltage drop which further proves that thelinear model is highly approximate to the real DSSR model

4 Formulation for DSSR Boundary

Research on the boundary of security region has vital signif-icance because the characteristics determine the applicationway of DSSR theory [7] The proposed DSSR model whichis formulated as (2)ndash(7) cannot distinctly express the DSSRboundary Therefore derivation should be performed totransform the originalmodel to a new expression form Select119878119906V119891119905119903

as research object 119906 isin Φ(119894) and V isin Φ(119895) First formula(4) can be transformed to

119878119906V119891119905119903le 119878

V119865max minus 119878

V119865 (8)

Second substitute formulas (5) and (6) into (7) and thenperform identical deformation We obtain

0 le 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)

119878119898119899

119891119905119903 (9)

Third add 119878119906V119891119905119903

on both sides of formula (9) and then

119878119906V119891119905119903le 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)119898 =119906119899 =V

119878119898119899

119891119905119903 (10)

Finally according to (8) and (10) the expression of DSSRboundary in direction of 119878119906V

119891119905119903can be neatly formulated as

119878119906V119891119905119903

le min

119878V119865max minus 119878

V119865 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)

119898 =119906119899 =V

119878119898119899

119891119905119903

(11)

There are 119899 boundaries if the system consists of 119899load transfer units To express the dimension of boundaryclearly we denote all ldquo119878119906V

119891119905119903rdquo by 1198781

119891119905119903 1198782119891119905119903 119878119899

119891119905119903 Because

the transfer scheme in this paper is fixed as is illustrated inSection 22 an important equivalence holds as follows

119878119894

119891119905119903= 119878119894

119891(119894 = 1 2 119899) (12)

Through (12) 119878119891119905119903

and 119878119891have one-to-one corresponding

relation Above all the complete and succinct boundaryformulation for DSSR is expressed as

ΩDSSR

=

1198611

1198612

119861119894

119861119899

=

1198781119891le min

1198781198871119865max minus 119878

1198871

119865 1198781198871119879max minus sum

119895isinΦ(1198871)

119878119895

119865minus sum

119896 =1119896isinΘ(1)

119878119896119891

1198782

119891le min

1198781198872

119865max minus 1198781198872

119865 1198781198872

119879max minus sum

119895isinΦ(1198872)

119878119895

119865minus sum

119896 =2119896isinΘ(2)

119878119896

119891

119878119894

119891le min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

119878119899119891le min

119878119887119899119865max minus 119878

119887119899

119865 119878119887119899119879max minus sum

119895isinΦ(119887119899)

119878119895

119865minus sum

119896 =119899119896isinΘ(119899)

119878119896119891

(13)

With the form transformation ofDSSRmodel correspondingsymbols and their meaning should be adjusted too Thus 119887119894and Θ(119894) are used for new expression 119887119894 = the number ofback-feed feeders of 119878119894

119891 119878119887119894119865= all of the load supplied by the

back-feed feeder 119887119894 Θ(119894) = the set of transfer unit loads ofwhich both normal-feed and back-feed transformer are thesame as those of 119878119894

119891 It should be pointed out that feeder 1198871

feeder 119887119899 are not 119899 different actual feeders Take the case inFigure 2 as an example again when fault occurs the back-feed feeders of 1198783

119891and 1198784

119891are both feeder 1 which means

feeder b3 = feeder b4 = feeder 1 When any equality in (13)holds the operating point is just upon the DSSR boundaryWe denote the n boundaries by 119861

1 119861

119899

The DSSR boundary formulation can also reflect bothsubstation transformer and feeder N-1 secure constraintsTake 119894 subformula of (13) to concretely explain 119878119894

119891le

119878119887119894119865max minus 119878

119887119894

119865shows that transfer of 119878119894

119891cannot cause the feeder

overloading which ensures that the feeder N-1 is secure 119878119894119891le

119878119887119894119879max minus sum119895isinΦ(119887119894) 119878

119895

119865minus sum119896 =1119896isinΘ

(119894) 119878119896

119891shows that transfer of 119878119894

119891

cannot lead to the substation transformer overloading whichensures that the transformer N-1 is secure

5 Topological Characteristics of DSSR andMathematical Proof

The research on differential topological characteristics of theDSSR focuses on several aspects as follows

Journal of Applied Mathematics 5

(1) Are there any holes inside the DSSR that is thedenseness in terms of the topology

(2) Does the boundary of the DSSR have suspension(3) Could the boundary of the DSSR be expressed with

the union of several subsurfaces

The identical deformation from formulas (2)ndash(7) to (13) isa breakthrough for the research on topological characteristicsof the DSSR However to research on these characteristicsformula (13) should be further simplified to obtain themathematical essence Take 119894 subformula of (13) as researchobject the equivalent form is

119878119894

119891+ 119878119887119894

119865le 119878119887119894

119865max

119878119894

119891+ sum

119895isinΦ(119887119894)

119878119895

119865+ sum

119896 =1119896isinΘ(119894)

119878119896

119891le 119878119887119894

119879max(14)

According to formulas (3) and (12) 119878119887119894119865

and 119878119895119865

can beexpressed as linear combination of a series of differentelement ldquo119878

119891rdquo Then formula (14) will be simplified as

119899

sum119898=1

120572119898119878119898

119891le 119878119887119894

119865max

119899

sum119898=1

120573119898119878119898

119891le 119878119887119894

119879max

(15)

where 119878119887119894119865max and 119878119887119894

119879max are positive constants Throughformula (14) coefficients 120572 and 120573 have the following features

120572119898= 1 120573

119898= 1 (119898 = 119894)

120572119898= 0 or 1 120573

119898= 0 or 1 (119898 = 119894)

(16)

LetΩDSSR be a set which consists of operating pointW DSSRboundary formulation can be abstracted as

AW le C (17)

whereW is a vector defined as formula (1)Through formulas(15)-(16) matrices A and C should satisfy

A = [119886119894119895]2119899times119899

119894 ge 1 119895 ge 1

119886119894119895= 1 (119894 = 2119895 minus 1 or 119894 = 2119895)

119886119894119895= 0 or 1 (119894 = 2119895 minus 1 119894 = 2119895)

C = [1198881 1198882 1198882119899]119879

C isin R+

(18)

Because one integrated subformula is divided into equivalenttwo parts as is shown in formula (15) the dimension ofA is 2119899 times 119899 instead of 119899 times 119899 Here ΩDSSR is both linearspace and Euclidean space which has been proved in [17]Besides this important premise we should review somepreparation definitions and theorems about topology andEuclidean space including cluster point closure dense setand hyperplane

Definition 1 (cluster point) Let x be a point in Euclideanspace 119865 sub 119877 If there is a point sequence in set 119865 convergingto x then x is the cluster point of set 119865 [17]

Definition 2 (closure) 119860 is a subset of topological space 119860represents all the points inside 119860 and cluster points of 119860 andthen 119860 is called closure of 119860 [18]

Theorem 3 If the 119861 is a subset of 119860 119861 = 119860 then 119861 is dense in119860 [18]

Theorem 4 Let 119871 be a subspace of linear space 119877 x0 is a fixedvector which does not belong to 119871 generally Considering set119867which consists of the vector x x is obtained by

x = x0 + y (19)

where vector y varies in the whole subspace 119871 Thus119867 is calledhyperplane The dimension of119867 equals that of subspace 119871 [17]

The topological characteristics of DSSR are mathemati-cally proved in the following section

Characteristic 1 TheΩDSSR is dense inside

Proof First a new setΩ1015840DSSR is defined as the set of all pointsofΩDSSR except those on boundariesΩ1015840DSSR meets

AW lt C (20)

Select randomly a vector W = (1198781119891 1198782119891 119878119899

119891)119879 from Ω1015840DSSR

and then construct a sequenceY = Y1Y2 Ym as the

following formula

Y =

Y1= (1198781119891minus1198781119891

1 1198782119891minus1198782119891

1 119878119899

119891minus119878119899119891

1)

119879

= (0 0 0)119879

Y2= (1198781

119891minus1198781119891

2 1198782

119891minus1198782119891

2 119878

119899

119891minus119878119899119891

2)

119879

Y119898= (1198781119891minus1198781119891

119898 1198782119891minus1198782119891

119898 119878119899

119891minus119878119899119891

119898)

119879

= (1 minus1

119898)W

(21)

According to (20)-(21) we obtain

AYm = A(1 minus 1119898)W lt AW lt C (22)

Therefore sequence Y = Y1Y2 Ym is inside Ω1015840

DSSRLet 120588(WYm) be the distance betweenWandYm in Euclideanspace and then

lim119898rarrinfin

120588 (WYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(23)

6 Journal of Applied Mathematics

0

Snf (MVA)

Smf (MVA)

c3

c2c1 gt c2 + c3

DSSR

max(c2 c3) lt c1 lt c2 + c3

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

min(c2 c3) lt c1 lt max(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

0 lt c1 lt min(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

Figure 3 Shapes of 2-dimension cross-section of DSSR

Thismeans that for any vectorW inΩ1015840DSSR sequenceY existsand converges toW andY is also insideΩ1015840DSSRTherefore anypoint insideΩ1015840DSSR is cluster point of Ω

1015840

DSSRSimilarly select vector Z = (1198781

119891 1198782119891 119878119899

119891)119879 which is just

upon boundary ofΩ119863119878119878119877

AZ = C (24)

Construct a sequence U = U1U2 Um

Um = (1 minus1

119898)Z (25)

Then we obtain

AUm = A(1 minus 1119898)Z lt AZ = C (26)

According to formula (26) sequence U is also inside Ω1015840DSSRThrough the following

lim119898rarrinfin

120588 (ZYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(27)

We obtain that any point just upon the ΩDSSR boundary isalso cluster point ofΩ1015840DSSR Above all cluster points ofΩ

1015840

DSSR

include not only all the points inside Ω1015840DSSR but also all thepoints just upon the boundaries ofΩDSSRThus the followingformula holds

Ω1015840DSSR = ΩDSSR (28)

Through Theorem 3 Ω1015840DSSR is dense in ΩDSSR This proof iscompleted

Characteristic 2 The boundary ofΩDSSR has no suspension

Proof This characteristic can be approximately simplified toprove that any 2-dimension cross-section of ΩDSSR is convexpolygon For W = (1198781

119891 1198782119891 119878119899

119891)119879 select a 2-dimension

cross-section by taking 119878119898119891

and 119878119899119891as variables and 119878

119891in

another dimension as constants According to formula (16)the coefficient of 119878

119891(including variable 119878

119891and constant ones)

can be only 1 or 0 thus in process of dimension reduction 119878119898119891

and 119878119899119891are simply constrained by

119878119898

119891+ 119878119899

119891le 1198881

0 le 119878119898

119891le 1198882

0 le 119878119899

119891le 1198883

forall1198881 1198882 1198883isin 119877+

(29)

Journal of Applied Mathematics 7

Table 1 Profile of test case

Substation Transformer Voltages (kVkV) Transformer capacity (MVA) Number of feeders Total feeder capacity (MVA)

S1 T1 3510 400 9 8028T2 3510 400 9 8028

S2 T3 3510 400 9 8028T4 3510 400 8 7136

S3 T5 11010 630 10 892T6 11010 630 10 892

S4 T7 11010 630 10 892T8 11010 630 10 892

The shape of 2-dimension cross-section varies with the valuesof 1198881 1198882 and 119888

3 as is shown in Figure 3 The dashed oblique

line represents 119878119898119891+ 119878119899119891le 1198881

As is shown in Figure 3 the shapes of 2-dimension sectionare confined to rectangle triangle ladder and convex pen-tagon This means that any 2-dimension section of DSSR isconvex polygon which proves that the boundary ofΩDSSR hasno suspension in an indirect wayThe proof is completed

Characteristic 3 The ΩDSSR boundary can be expressed withseveral subsurfaces

Proof 119867 is a set of vector W = (1198781119891 1198782119891 119878119899

119891)119879 each of

which satisfies nonhomogeneous linear equation set

AW = C (30)

where matrices A and C meet formula (18) and W is theoperating point just upon the boundary of ΩDSSR Let W0 =

(120579(0)

1 120579(0)

2 120579(0)

119899)119879 be a fixed solution of equation set (31)

Meanwhile 119871 is a subspace of 119877 which consists of y =

(1205821 1205822 120582

119899)119879 that is y varies in the whole subspace 119871

The coordinates of ymeet the following homogeneous linearequation set

Ay = 0 (31)

If y = (1205821 1205822 120582

119899)119879 is a solution of (31) W = W0

+y = (120579(0)

1+ 1205821 120579(0)

2+ 1205822 120579(0)

119899+ 120582119899)119879 is obviously

a solution of equation set (30) that is W is included inset 119867 Meanwhile x0 is not in 119871 Through Theorem 3 119867is hyperplane The boundary of ΩDSSR can be expressedwith hyperplane that is several subsurfaces Because thedimension of 119871 is 119899 the dimension of hyperplane is also 119899This proof is completed

In transmission area topological characteristics of secu-rity region (SR) have been deeply studied [7] It has shownthat the boundary of SR has no suspension and is compactand approximately linear there is no hole inside the SR Theproof above demonstrates that characteristics of DSSR aresimilar but it has its own features

(a) DSSR is a convex set of denseness in terms ofthe topology This means that DSSR has no holesinside and its boundary has no suspension Basedon this feature dispatchers can analyze the securityof operating point by judging whether the point isinside theDSSRboundarywithout being afraid of anyinsecure point inside or losing security points

(b) DSSR boundary can be described by hyperplane (sev-eral Euclidean subsurfaces) meanwhile the bound-ary ismore linear than that of SR In practical applica-tion calculation of high dimensional security regionwill incur great computation burdens and consumelarge amount of time Therefore this characteristicwill improve the computational efficiency

6 Case Study

In order to verify the effectiveness of the proposedmodel twocases are illustrated in this section The first one is a test caseand the second is a practical case

61 Test Case

611 Overview of Test Case As is shown in Figure 4 the gridis comprised of 4 substations 8 substation transformers and75 feeders 68 feeders form 34 single loop networks and 7form two-tie connections resulting in 82 load transfer unitsThe total capacity of substations is 412MVA To illustrate themodeling process clearly each load transfer unit is numberedCase profile is shown in Table 1

The conductor type of all feeders is LGJ-185 (892MVA)This type is selected based on the national electrical code inChina

612 Boundary Formulation The test case grid has 75 feed-ers 14 feeders form 7 two-tie connections Each load of these7 feeders can be divided into 2 parts to transfer in differentback-feed path So the number of load transfer units is 82which means that the dimension of operation point W is82 and the number of subformulas of DSSR boundary is82 Based on the topology of the test case we substitutethe rated capacity of substation transformers and feedersinto 1198781

119865max 119878119899

119865max and 1198781119879max 119878

119899

119879max of formula (13)

8 Journal of Applied Mathematics

Then the boundary formulation for DSSR of test case can beexpressed as

ΩDSSR =

1198781

119891le min 892 minus (11987876

119891+ 11987836119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198782119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198782119891le min 892 minus (11987837

119891+ 11987877119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198783119891le min 892 minus (11987838

119891+ 11987878119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198784119891+ 1198785119891)

1198784119891le min 892 minus 11987839

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198785119891)

1198785119891le min 892 minus 11987840

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198784119891)

11987882119891le min 892 minus 11987851

119891 63 minus (11987846

119891+ 11987847119891+ 11987848119891+ 11987849119891+ 11987850119891+ 11987851119891+ 11987852119891+ 11987853119891+ 11987854119891+ 11987855119891) minus 11987881119891

(32)

Considering the similarity of calculation approach ofeach boundary and thesis length we present 5 subformulasof 1198781119891 1198785

119891here Complete formulation is given in the

appendix (in the Supplementary Material available online athttpdxdoiorg1011552014327078) Take the first subfor-mula in (32) as an example to explain the modeling processFigure 5 shows the local topology related with 1198781

119891 including

all relative transfer units in the first subformulaFirst analyze the topology and determine the parameters

of formula (13)We know that back-feed feeder of 1198781119891is feeder

36 and the back-feed substation transformer of 1198781119891is T5 In

normal state 11987836119891 11987845

119891and 11987876

119891 11987878

119891are all load of T5

which means sum119895isinΦ(1198871) 119878119895

119865= sum45

119895=36119878119895

119891+ sum78

119895=76119878119895

119891 11987836119891

and 11987876119891

are load of feeder 36 which means 1198781198871119865= 11987836119891+ 11987876119891 1198782119891 1198785

119891

are the load transferred fromT1 to T5when fault occurs at T1whichmeanssum

119896 =1119896isinΘ(1) 119878119896

119891= sum5

119896=2119878119896119891Therefore the formula

of B1 is preliminary expressed as

1198781

119891le min 11987836

119865max minus (11987876

119891+ 11987836

119891)

1198785

119879max minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(33)

Second according to case profile substitute 11987836119865max =

892MVA and 1198785119879max = 63MVA into formula (33) and then

we obtain

1198781

119891le min 892 minus (11987876

119891+ 11987836

119891)

63 minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(34)

613 Visualization and Topological Characteristics To visu-alize the shape of DSSR the dimension is reduced to 2 and 3which means that the coordinates of W should be constantsother than those to be visualized Thus an operating pointhas to be predetermined to provide the constants TSC is aspecial operating point just upon the security boundary [1]on which the facilities are usually fully utilizedThe operationof distribution system is closing to the boundaries and loadlevel is reaching TSCThus in this test case we select the TSCpoint as the predetermined operating point WTSC which isshown in Table 2The calculation approach for TSC has beenpresented in [15]

Choose randomly transfer unit loads 11987815119891

and 11987852119891

toobserve Substitute the rated capacity of transformers T1simT6capacity of all feeders and all transfer unit loads other than11987815119891

and 11987852119891 into formula (32) Then the 2D DSSR shown in

Figure 6 is obtainedAlthough the dimension is 2 the number of subformulas

which constrain the figure shape is not just 2 In fact eachof the subformulas which contains 11987815

119891or 11987852119891

should beconsidered But the subformulas withmore severe constraintswill cover the others and finally form theDSSR boundaryThefinal formulation of 2D figure is

0 le 11987815

119891le 52

0 le 11987852

119891le 3

(35)

Journal of Applied Mathematics 9

T1S1

T2

T3

T4

S 2

S4

T8

T6S3

T5

17-1

8

20-19

12ndash1

415

-16

21ndash23

41-4

3

36ndash3

8

39-4

044

-45

47-4

650

-51

52-5

3

54-5

548

-49

10-1

1

9-8

1 ndash3

4-5

6-7

76ndash7

8

79-80

58-5960-61

57-5665-62

66ndash6970-71

72ndash7524-25

29-28

26-27

30-31

32ndash35

81-8

2

Tie switch

T7

Distribution transformer

(i + 1) j are the same in the topologyin terms of calculation for DSSR

Note means that transfer units iindashj

Figure 4 Test case with eight substation transformers

Feeder 1

T1

T5

Feeder 2Feeder 36Feeder 37

S1f

S2f

S3f

S76f

S77f

S78f

S36f

S36f

S37f

S45f

S4f

S5f

middot middot middot

middot middot middot middot middot middot

Figure 5 Local topology related with f1

Similarly we choose randomly transfer unit loads 11987819119891 11987824119891

and 11987832119891

to observe and then the 3D DSSR is obtained as isshown in Figure 7

In Figure 6 it can be seen that the 2D DSSR is a denserectangle of which boundaries are linear without suspension

DSSR

0

1

2

3

1 2 3 4 52 S52f (MVA)

S15f (MVA)

Figure 6 Shape of 2D DSSR

In Figure 7 the 3D DSSR is surrounded by several subplanesforming a convex pentagon that is a special 3-dimensionhyperplane

10 Journal of Applied Mathematics

Table 2 Transfer unit load ofWTSC in test case

Transfer unit Load (MVA)1 2882 2883 2884 2885 2886 1647 1648 1649 16410 28811 28812 31713 31714 31715 31716 31717 30018 30019 31720 31721 34722 34723 31124 31125 31126 34727 34728 34729 34730 28031 28032 16133 16134 16135 16136 28037 28038 28039 28040 25241 32942 25243 32944 25245 32946 28847 28848 39549 395

Table 2 Continued

Transfer unit Load (MVA)50 39551 44652 44653 44654 44655 56456 56457 56958 56959 59260 59261 53362 53363 35964 35965 51366 51367 49468 49469 44670 44671 44672 44673 44674 44675 44676 44677 28078 28079 28080 28081 28082 280mdash mdashmdash mdash

01 2 3 4 5

2

3

1

12

34

56

DSSR

S32f

(MVA

)

S24f (MVA)

S19

f(M

VA)

Figure 7 Shape of 3D DSSR

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 3: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

Journal of Applied Mathematics 3

Feeder 1

Normally closed switchNormally open switchBack-feed (transfer) path

FaultS1 S2 S3

S4Feeder 2

Feeder 3

S1f

S1FS2f

S3f

S4f

Figure 2 Feeder and transfer unit load

too long In contrast with feeder automation the load of T2can be transferred not only to T1 but also to T3 in anothersubstation

The DSSR model in this paper takes both substationtransformer N-1 and feeder N-1 contingency into accountThe DSSR is defined as the set of operating points whichassure the N-1 security of distribution system An operatingpoint in transmission system is the current power injectionsof nodes while in distribution system it represents a set oftransfer unit load Consider

W = (1198781

119891 1198782

119891 119878

119899

119891)119879

(1)

whereW is the operating point which is an n-dimensionvector 119878119894

119891is transfer unit load ldquoTransfer unitrdquo is defined as

the set of feeder sections of which load has the same back-feed (transfer) path If two feeders form single loop networktransfer unit load is equivalent to feeder load If a feederis connected to two other feeders which is called two-tieconnection the feeder load can be divided into two parts ofload each of which is a transfer unit load In this paper feederload i is denoted by 119878119894

119865and transfer unitload 119894 is denoted by

119878119894119891 Take the brief case in Figure 2 as an exampleIn Figure 2 feeder 1 forms two-tie connection and feeder

2 and feeder 3 form single loop network respectively withfeeder 1 In normal state 1198781

119891and 1198782119891are both supplied by feeder

1 that is 1198781119865= 1198781119891+ 1198782119891 When a fault occurs at outlet of

feeder 1 S1 and S2 disconnect and S4 closes and then 1198781119891

changes to be supplied by feeder 3 while 1198782119891is supplied by

feeder 2 via closing S3 Transfer scheme is usually not uniqueAnother scheme is that transferring both 1198781

119891and 1198782119891to feeder

2 by disconnecting S1 and closing S3 However multischememakes the DSSR model overcomplicated Thus scheme isfixed in this paper which stipulates that each of the backupfeeders restores only one section of the whole faulted feederas the first scheme above More important this fixed schemecan usually balance the branch load in the postfault networkwhich is an important index concerned by dispatchers

The DSSR model in this paper is accurate to the safetymonitoring of transfer unit load We can certainly get feederload by summing up the transfer unit load and further get

transformer load by summing up the feeder load This is abasis for DSSR model considering both transformer N-1 andfeeder N-1 security

3 Mathematical Model for DSSR

After the load transfer incurred by tie switches against N-1 contingency all the transformers and feeders cannot beoverloading Since the tie-line is designed after the radialnetwork planning the capacity is considered as enough totransfer loadTherefore the transformer load and feeder loadshould be under a series of constraints The DSSR model canbe mathematically formulated as

ΩDSSR = W | ℎ (119909) le 0 119892 (119909) = 0 (2)

where W = (1198781119891 1198782119891 119878119899

119891)119879 is the operating point cor-

responding to 1198781119891 1198782

119891 119878

119899

119891 The inequality and equality

constraints are such that

119878119898

119865= sum119899=1

119878119898119899

119891119905119903 (3)

119878119898119899

119891119905119903+ 119878119899

119865le 119878119899

119865max (forall119898 119899) (4)

119878119894119895

119879119905119903= sum

119898isinΦ(119894)119899isinΦ(119895)

119878119898119899

119891119905119903 (5)

119878119894

119879= sum

119898isinΦ(119894)

119878119898

119865(forall119894) (6)

119878119894119895

119879119905119903+ 119878119895

119879le 119878119895

119879max (7)

where 119878119898119865

= all the load supplied by feeder m 119878119898119899119891119905119903

=the load transferred from feeder m to feeder n when anN-1 fault occurs at outlet of feeder m 119878119899

119865max = maximalthermal capacity of feeder 119899 119878119894119895

119879119905119903= the load transferred from

transformer 119894 to transformer 119895 when an N-1 fault occursat transformer 119894 Φ(119894) = the set of feeders that derive fromtransformer 119894 119878119895

119879= all of the load supplied by transformer 119894

119898 isin Φ(119894)means that feeder119898 derives from the correspondingbus of transformer 119894 119878119894

119879max = the rated capacity of transformer119894

It is notable that the correspondence relation of ldquo119878119891119905119903

rdquoand ldquo119878

119891rdquo depends on the load transfer scheme For example

in Figure 2 in the former scheme 11987812119891119905119903

= 1198782119891 in the latter

scheme 11987812119891119905119903= 1198781119891+ 1198782119891

Equation (3) shows that the sum of each load to betransferred away from feeder m should be equal to thetotal load supplied by feeder m in normal state inequalityconstraint (4) means that feeders cannot be overloading inthe postfault network (5) shows that path of load transferredfrom transformer 119894 to 119895 is the tie-lines between transformers 119894and 119895 Equation (6) means that load of transformer is equal tothe sum of corresponding feeder loads inequality constraint(7) describes that the load of transformer 119895 cannot exceed itsrated capacity after a substation transformerN-1 contingency

It should be pointed out that power flow and voltage dropare not taken into consideration in this DSSR model which

4 Journal of Applied Mathematics

determines that the DSSR model is completely linear Sinceoverloading under contingencies is the most critical prob-lem in urban power the simple linear model is acceptablefrom the standpoint of security-based operation [1] Moreimportantly research of [16] has demonstrated that the DSSRmodel is approximately linear even when considering factorsof power flow and voltage drop which further proves that thelinear model is highly approximate to the real DSSR model

4 Formulation for DSSR Boundary

Research on the boundary of security region has vital signif-icance because the characteristics determine the applicationway of DSSR theory [7] The proposed DSSR model whichis formulated as (2)ndash(7) cannot distinctly express the DSSRboundary Therefore derivation should be performed totransform the originalmodel to a new expression form Select119878119906V119891119905119903

as research object 119906 isin Φ(119894) and V isin Φ(119895) First formula(4) can be transformed to

119878119906V119891119905119903le 119878

V119865max minus 119878

V119865 (8)

Second substitute formulas (5) and (6) into (7) and thenperform identical deformation We obtain

0 le 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)

119878119898119899

119891119905119903 (9)

Third add 119878119906V119891119905119903

on both sides of formula (9) and then

119878119906V119891119905119903le 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)119898 =119906119899 =V

119878119898119899

119891119905119903 (10)

Finally according to (8) and (10) the expression of DSSRboundary in direction of 119878119906V

119891119905119903can be neatly formulated as

119878119906V119891119905119903

le min

119878V119865max minus 119878

V119865 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)

119898 =119906119899 =V

119878119898119899

119891119905119903

(11)

There are 119899 boundaries if the system consists of 119899load transfer units To express the dimension of boundaryclearly we denote all ldquo119878119906V

119891119905119903rdquo by 1198781

119891119905119903 1198782119891119905119903 119878119899

119891119905119903 Because

the transfer scheme in this paper is fixed as is illustrated inSection 22 an important equivalence holds as follows

119878119894

119891119905119903= 119878119894

119891(119894 = 1 2 119899) (12)

Through (12) 119878119891119905119903

and 119878119891have one-to-one corresponding

relation Above all the complete and succinct boundaryformulation for DSSR is expressed as

ΩDSSR

=

1198611

1198612

119861119894

119861119899

=

1198781119891le min

1198781198871119865max minus 119878

1198871

119865 1198781198871119879max minus sum

119895isinΦ(1198871)

119878119895

119865minus sum

119896 =1119896isinΘ(1)

119878119896119891

1198782

119891le min

1198781198872

119865max minus 1198781198872

119865 1198781198872

119879max minus sum

119895isinΦ(1198872)

119878119895

119865minus sum

119896 =2119896isinΘ(2)

119878119896

119891

119878119894

119891le min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

119878119899119891le min

119878119887119899119865max minus 119878

119887119899

119865 119878119887119899119879max minus sum

119895isinΦ(119887119899)

119878119895

119865minus sum

119896 =119899119896isinΘ(119899)

119878119896119891

(13)

With the form transformation ofDSSRmodel correspondingsymbols and their meaning should be adjusted too Thus 119887119894and Θ(119894) are used for new expression 119887119894 = the number ofback-feed feeders of 119878119894

119891 119878119887119894119865= all of the load supplied by the

back-feed feeder 119887119894 Θ(119894) = the set of transfer unit loads ofwhich both normal-feed and back-feed transformer are thesame as those of 119878119894

119891 It should be pointed out that feeder 1198871

feeder 119887119899 are not 119899 different actual feeders Take the case inFigure 2 as an example again when fault occurs the back-feed feeders of 1198783

119891and 1198784

119891are both feeder 1 which means

feeder b3 = feeder b4 = feeder 1 When any equality in (13)holds the operating point is just upon the DSSR boundaryWe denote the n boundaries by 119861

1 119861

119899

The DSSR boundary formulation can also reflect bothsubstation transformer and feeder N-1 secure constraintsTake 119894 subformula of (13) to concretely explain 119878119894

119891le

119878119887119894119865max minus 119878

119887119894

119865shows that transfer of 119878119894

119891cannot cause the feeder

overloading which ensures that the feeder N-1 is secure 119878119894119891le

119878119887119894119879max minus sum119895isinΦ(119887119894) 119878

119895

119865minus sum119896 =1119896isinΘ

(119894) 119878119896

119891shows that transfer of 119878119894

119891

cannot lead to the substation transformer overloading whichensures that the transformer N-1 is secure

5 Topological Characteristics of DSSR andMathematical Proof

The research on differential topological characteristics of theDSSR focuses on several aspects as follows

Journal of Applied Mathematics 5

(1) Are there any holes inside the DSSR that is thedenseness in terms of the topology

(2) Does the boundary of the DSSR have suspension(3) Could the boundary of the DSSR be expressed with

the union of several subsurfaces

The identical deformation from formulas (2)ndash(7) to (13) isa breakthrough for the research on topological characteristicsof the DSSR However to research on these characteristicsformula (13) should be further simplified to obtain themathematical essence Take 119894 subformula of (13) as researchobject the equivalent form is

119878119894

119891+ 119878119887119894

119865le 119878119887119894

119865max

119878119894

119891+ sum

119895isinΦ(119887119894)

119878119895

119865+ sum

119896 =1119896isinΘ(119894)

119878119896

119891le 119878119887119894

119879max(14)

According to formulas (3) and (12) 119878119887119894119865

and 119878119895119865

can beexpressed as linear combination of a series of differentelement ldquo119878

119891rdquo Then formula (14) will be simplified as

119899

sum119898=1

120572119898119878119898

119891le 119878119887119894

119865max

119899

sum119898=1

120573119898119878119898

119891le 119878119887119894

119879max

(15)

where 119878119887119894119865max and 119878119887119894

119879max are positive constants Throughformula (14) coefficients 120572 and 120573 have the following features

120572119898= 1 120573

119898= 1 (119898 = 119894)

120572119898= 0 or 1 120573

119898= 0 or 1 (119898 = 119894)

(16)

LetΩDSSR be a set which consists of operating pointW DSSRboundary formulation can be abstracted as

AW le C (17)

whereW is a vector defined as formula (1)Through formulas(15)-(16) matrices A and C should satisfy

A = [119886119894119895]2119899times119899

119894 ge 1 119895 ge 1

119886119894119895= 1 (119894 = 2119895 minus 1 or 119894 = 2119895)

119886119894119895= 0 or 1 (119894 = 2119895 minus 1 119894 = 2119895)

C = [1198881 1198882 1198882119899]119879

C isin R+

(18)

Because one integrated subformula is divided into equivalenttwo parts as is shown in formula (15) the dimension ofA is 2119899 times 119899 instead of 119899 times 119899 Here ΩDSSR is both linearspace and Euclidean space which has been proved in [17]Besides this important premise we should review somepreparation definitions and theorems about topology andEuclidean space including cluster point closure dense setand hyperplane

Definition 1 (cluster point) Let x be a point in Euclideanspace 119865 sub 119877 If there is a point sequence in set 119865 convergingto x then x is the cluster point of set 119865 [17]

Definition 2 (closure) 119860 is a subset of topological space 119860represents all the points inside 119860 and cluster points of 119860 andthen 119860 is called closure of 119860 [18]

Theorem 3 If the 119861 is a subset of 119860 119861 = 119860 then 119861 is dense in119860 [18]

Theorem 4 Let 119871 be a subspace of linear space 119877 x0 is a fixedvector which does not belong to 119871 generally Considering set119867which consists of the vector x x is obtained by

x = x0 + y (19)

where vector y varies in the whole subspace 119871 Thus119867 is calledhyperplane The dimension of119867 equals that of subspace 119871 [17]

The topological characteristics of DSSR are mathemati-cally proved in the following section

Characteristic 1 TheΩDSSR is dense inside

Proof First a new setΩ1015840DSSR is defined as the set of all pointsofΩDSSR except those on boundariesΩ1015840DSSR meets

AW lt C (20)

Select randomly a vector W = (1198781119891 1198782119891 119878119899

119891)119879 from Ω1015840DSSR

and then construct a sequenceY = Y1Y2 Ym as the

following formula

Y =

Y1= (1198781119891minus1198781119891

1 1198782119891minus1198782119891

1 119878119899

119891minus119878119899119891

1)

119879

= (0 0 0)119879

Y2= (1198781

119891minus1198781119891

2 1198782

119891minus1198782119891

2 119878

119899

119891minus119878119899119891

2)

119879

Y119898= (1198781119891minus1198781119891

119898 1198782119891minus1198782119891

119898 119878119899

119891minus119878119899119891

119898)

119879

= (1 minus1

119898)W

(21)

According to (20)-(21) we obtain

AYm = A(1 minus 1119898)W lt AW lt C (22)

Therefore sequence Y = Y1Y2 Ym is inside Ω1015840

DSSRLet 120588(WYm) be the distance betweenWandYm in Euclideanspace and then

lim119898rarrinfin

120588 (WYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(23)

6 Journal of Applied Mathematics

0

Snf (MVA)

Smf (MVA)

c3

c2c1 gt c2 + c3

DSSR

max(c2 c3) lt c1 lt c2 + c3

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

min(c2 c3) lt c1 lt max(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

0 lt c1 lt min(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

Figure 3 Shapes of 2-dimension cross-section of DSSR

Thismeans that for any vectorW inΩ1015840DSSR sequenceY existsand converges toW andY is also insideΩ1015840DSSRTherefore anypoint insideΩ1015840DSSR is cluster point of Ω

1015840

DSSRSimilarly select vector Z = (1198781

119891 1198782119891 119878119899

119891)119879 which is just

upon boundary ofΩ119863119878119878119877

AZ = C (24)

Construct a sequence U = U1U2 Um

Um = (1 minus1

119898)Z (25)

Then we obtain

AUm = A(1 minus 1119898)Z lt AZ = C (26)

According to formula (26) sequence U is also inside Ω1015840DSSRThrough the following

lim119898rarrinfin

120588 (ZYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(27)

We obtain that any point just upon the ΩDSSR boundary isalso cluster point ofΩ1015840DSSR Above all cluster points ofΩ

1015840

DSSR

include not only all the points inside Ω1015840DSSR but also all thepoints just upon the boundaries ofΩDSSRThus the followingformula holds

Ω1015840DSSR = ΩDSSR (28)

Through Theorem 3 Ω1015840DSSR is dense in ΩDSSR This proof iscompleted

Characteristic 2 The boundary ofΩDSSR has no suspension

Proof This characteristic can be approximately simplified toprove that any 2-dimension cross-section of ΩDSSR is convexpolygon For W = (1198781

119891 1198782119891 119878119899

119891)119879 select a 2-dimension

cross-section by taking 119878119898119891

and 119878119899119891as variables and 119878

119891in

another dimension as constants According to formula (16)the coefficient of 119878

119891(including variable 119878

119891and constant ones)

can be only 1 or 0 thus in process of dimension reduction 119878119898119891

and 119878119899119891are simply constrained by

119878119898

119891+ 119878119899

119891le 1198881

0 le 119878119898

119891le 1198882

0 le 119878119899

119891le 1198883

forall1198881 1198882 1198883isin 119877+

(29)

Journal of Applied Mathematics 7

Table 1 Profile of test case

Substation Transformer Voltages (kVkV) Transformer capacity (MVA) Number of feeders Total feeder capacity (MVA)

S1 T1 3510 400 9 8028T2 3510 400 9 8028

S2 T3 3510 400 9 8028T4 3510 400 8 7136

S3 T5 11010 630 10 892T6 11010 630 10 892

S4 T7 11010 630 10 892T8 11010 630 10 892

The shape of 2-dimension cross-section varies with the valuesof 1198881 1198882 and 119888

3 as is shown in Figure 3 The dashed oblique

line represents 119878119898119891+ 119878119899119891le 1198881

As is shown in Figure 3 the shapes of 2-dimension sectionare confined to rectangle triangle ladder and convex pen-tagon This means that any 2-dimension section of DSSR isconvex polygon which proves that the boundary ofΩDSSR hasno suspension in an indirect wayThe proof is completed

Characteristic 3 The ΩDSSR boundary can be expressed withseveral subsurfaces

Proof 119867 is a set of vector W = (1198781119891 1198782119891 119878119899

119891)119879 each of

which satisfies nonhomogeneous linear equation set

AW = C (30)

where matrices A and C meet formula (18) and W is theoperating point just upon the boundary of ΩDSSR Let W0 =

(120579(0)

1 120579(0)

2 120579(0)

119899)119879 be a fixed solution of equation set (31)

Meanwhile 119871 is a subspace of 119877 which consists of y =

(1205821 1205822 120582

119899)119879 that is y varies in the whole subspace 119871

The coordinates of ymeet the following homogeneous linearequation set

Ay = 0 (31)

If y = (1205821 1205822 120582

119899)119879 is a solution of (31) W = W0

+y = (120579(0)

1+ 1205821 120579(0)

2+ 1205822 120579(0)

119899+ 120582119899)119879 is obviously

a solution of equation set (30) that is W is included inset 119867 Meanwhile x0 is not in 119871 Through Theorem 3 119867is hyperplane The boundary of ΩDSSR can be expressedwith hyperplane that is several subsurfaces Because thedimension of 119871 is 119899 the dimension of hyperplane is also 119899This proof is completed

In transmission area topological characteristics of secu-rity region (SR) have been deeply studied [7] It has shownthat the boundary of SR has no suspension and is compactand approximately linear there is no hole inside the SR Theproof above demonstrates that characteristics of DSSR aresimilar but it has its own features

(a) DSSR is a convex set of denseness in terms ofthe topology This means that DSSR has no holesinside and its boundary has no suspension Basedon this feature dispatchers can analyze the securityof operating point by judging whether the point isinside theDSSRboundarywithout being afraid of anyinsecure point inside or losing security points

(b) DSSR boundary can be described by hyperplane (sev-eral Euclidean subsurfaces) meanwhile the bound-ary ismore linear than that of SR In practical applica-tion calculation of high dimensional security regionwill incur great computation burdens and consumelarge amount of time Therefore this characteristicwill improve the computational efficiency

6 Case Study

In order to verify the effectiveness of the proposedmodel twocases are illustrated in this section The first one is a test caseand the second is a practical case

61 Test Case

611 Overview of Test Case As is shown in Figure 4 the gridis comprised of 4 substations 8 substation transformers and75 feeders 68 feeders form 34 single loop networks and 7form two-tie connections resulting in 82 load transfer unitsThe total capacity of substations is 412MVA To illustrate themodeling process clearly each load transfer unit is numberedCase profile is shown in Table 1

The conductor type of all feeders is LGJ-185 (892MVA)This type is selected based on the national electrical code inChina

612 Boundary Formulation The test case grid has 75 feed-ers 14 feeders form 7 two-tie connections Each load of these7 feeders can be divided into 2 parts to transfer in differentback-feed path So the number of load transfer units is 82which means that the dimension of operation point W is82 and the number of subformulas of DSSR boundary is82 Based on the topology of the test case we substitutethe rated capacity of substation transformers and feedersinto 1198781

119865max 119878119899

119865max and 1198781119879max 119878

119899

119879max of formula (13)

8 Journal of Applied Mathematics

Then the boundary formulation for DSSR of test case can beexpressed as

ΩDSSR =

1198781

119891le min 892 minus (11987876

119891+ 11987836119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198782119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198782119891le min 892 minus (11987837

119891+ 11987877119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198783119891le min 892 minus (11987838

119891+ 11987878119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198784119891+ 1198785119891)

1198784119891le min 892 minus 11987839

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198785119891)

1198785119891le min 892 minus 11987840

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198784119891)

11987882119891le min 892 minus 11987851

119891 63 minus (11987846

119891+ 11987847119891+ 11987848119891+ 11987849119891+ 11987850119891+ 11987851119891+ 11987852119891+ 11987853119891+ 11987854119891+ 11987855119891) minus 11987881119891

(32)

Considering the similarity of calculation approach ofeach boundary and thesis length we present 5 subformulasof 1198781119891 1198785

119891here Complete formulation is given in the

appendix (in the Supplementary Material available online athttpdxdoiorg1011552014327078) Take the first subfor-mula in (32) as an example to explain the modeling processFigure 5 shows the local topology related with 1198781

119891 including

all relative transfer units in the first subformulaFirst analyze the topology and determine the parameters

of formula (13)We know that back-feed feeder of 1198781119891is feeder

36 and the back-feed substation transformer of 1198781119891is T5 In

normal state 11987836119891 11987845

119891and 11987876

119891 11987878

119891are all load of T5

which means sum119895isinΦ(1198871) 119878119895

119865= sum45

119895=36119878119895

119891+ sum78

119895=76119878119895

119891 11987836119891

and 11987876119891

are load of feeder 36 which means 1198781198871119865= 11987836119891+ 11987876119891 1198782119891 1198785

119891

are the load transferred fromT1 to T5when fault occurs at T1whichmeanssum

119896 =1119896isinΘ(1) 119878119896

119891= sum5

119896=2119878119896119891Therefore the formula

of B1 is preliminary expressed as

1198781

119891le min 11987836

119865max minus (11987876

119891+ 11987836

119891)

1198785

119879max minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(33)

Second according to case profile substitute 11987836119865max =

892MVA and 1198785119879max = 63MVA into formula (33) and then

we obtain

1198781

119891le min 892 minus (11987876

119891+ 11987836

119891)

63 minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(34)

613 Visualization and Topological Characteristics To visu-alize the shape of DSSR the dimension is reduced to 2 and 3which means that the coordinates of W should be constantsother than those to be visualized Thus an operating pointhas to be predetermined to provide the constants TSC is aspecial operating point just upon the security boundary [1]on which the facilities are usually fully utilizedThe operationof distribution system is closing to the boundaries and loadlevel is reaching TSCThus in this test case we select the TSCpoint as the predetermined operating point WTSC which isshown in Table 2The calculation approach for TSC has beenpresented in [15]

Choose randomly transfer unit loads 11987815119891

and 11987852119891

toobserve Substitute the rated capacity of transformers T1simT6capacity of all feeders and all transfer unit loads other than11987815119891

and 11987852119891 into formula (32) Then the 2D DSSR shown in

Figure 6 is obtainedAlthough the dimension is 2 the number of subformulas

which constrain the figure shape is not just 2 In fact eachof the subformulas which contains 11987815

119891or 11987852119891

should beconsidered But the subformulas withmore severe constraintswill cover the others and finally form theDSSR boundaryThefinal formulation of 2D figure is

0 le 11987815

119891le 52

0 le 11987852

119891le 3

(35)

Journal of Applied Mathematics 9

T1S1

T2

T3

T4

S 2

S4

T8

T6S3

T5

17-1

8

20-19

12ndash1

415

-16

21ndash23

41-4

3

36ndash3

8

39-4

044

-45

47-4

650

-51

52-5

3

54-5

548

-49

10-1

1

9-8

1 ndash3

4-5

6-7

76ndash7

8

79-80

58-5960-61

57-5665-62

66ndash6970-71

72ndash7524-25

29-28

26-27

30-31

32ndash35

81-8

2

Tie switch

T7

Distribution transformer

(i + 1) j are the same in the topologyin terms of calculation for DSSR

Note means that transfer units iindashj

Figure 4 Test case with eight substation transformers

Feeder 1

T1

T5

Feeder 2Feeder 36Feeder 37

S1f

S2f

S3f

S76f

S77f

S78f

S36f

S36f

S37f

S45f

S4f

S5f

middot middot middot

middot middot middot middot middot middot

Figure 5 Local topology related with f1

Similarly we choose randomly transfer unit loads 11987819119891 11987824119891

and 11987832119891

to observe and then the 3D DSSR is obtained as isshown in Figure 7

In Figure 6 it can be seen that the 2D DSSR is a denserectangle of which boundaries are linear without suspension

DSSR

0

1

2

3

1 2 3 4 52 S52f (MVA)

S15f (MVA)

Figure 6 Shape of 2D DSSR

In Figure 7 the 3D DSSR is surrounded by several subplanesforming a convex pentagon that is a special 3-dimensionhyperplane

10 Journal of Applied Mathematics

Table 2 Transfer unit load ofWTSC in test case

Transfer unit Load (MVA)1 2882 2883 2884 2885 2886 1647 1648 1649 16410 28811 28812 31713 31714 31715 31716 31717 30018 30019 31720 31721 34722 34723 31124 31125 31126 34727 34728 34729 34730 28031 28032 16133 16134 16135 16136 28037 28038 28039 28040 25241 32942 25243 32944 25245 32946 28847 28848 39549 395

Table 2 Continued

Transfer unit Load (MVA)50 39551 44652 44653 44654 44655 56456 56457 56958 56959 59260 59261 53362 53363 35964 35965 51366 51367 49468 49469 44670 44671 44672 44673 44674 44675 44676 44677 28078 28079 28080 28081 28082 280mdash mdashmdash mdash

01 2 3 4 5

2

3

1

12

34

56

DSSR

S32f

(MVA

)

S24f (MVA)

S19

f(M

VA)

Figure 7 Shape of 3D DSSR

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 4: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

4 Journal of Applied Mathematics

determines that the DSSR model is completely linear Sinceoverloading under contingencies is the most critical prob-lem in urban power the simple linear model is acceptablefrom the standpoint of security-based operation [1] Moreimportantly research of [16] has demonstrated that the DSSRmodel is approximately linear even when considering factorsof power flow and voltage drop which further proves that thelinear model is highly approximate to the real DSSR model

4 Formulation for DSSR Boundary

Research on the boundary of security region has vital signif-icance because the characteristics determine the applicationway of DSSR theory [7] The proposed DSSR model whichis formulated as (2)ndash(7) cannot distinctly express the DSSRboundary Therefore derivation should be performed totransform the originalmodel to a new expression form Select119878119906V119891119905119903

as research object 119906 isin Φ(119894) and V isin Φ(119895) First formula(4) can be transformed to

119878119906V119891119905119903le 119878

V119865max minus 119878

V119865 (8)

Second substitute formulas (5) and (6) into (7) and thenperform identical deformation We obtain

0 le 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)

119878119898119899

119891119905119903 (9)

Third add 119878119906V119891119905119903

on both sides of formula (9) and then

119878119906V119891119905119903le 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)119898 =119906119899 =V

119878119898119899

119891119905119903 (10)

Finally according to (8) and (10) the expression of DSSRboundary in direction of 119878119906V

119891119905119903can be neatly formulated as

119878119906V119891119905119903

le min

119878V119865max minus 119878

V119865 119878119895

119879max minus sum

119905isinΦ(119895)

119878119905

119865minus sum

119898isinΦ(119894)119899isinΦ(119895)

119898 =119906119899 =V

119878119898119899

119891119905119903

(11)

There are 119899 boundaries if the system consists of 119899load transfer units To express the dimension of boundaryclearly we denote all ldquo119878119906V

119891119905119903rdquo by 1198781

119891119905119903 1198782119891119905119903 119878119899

119891119905119903 Because

the transfer scheme in this paper is fixed as is illustrated inSection 22 an important equivalence holds as follows

119878119894

119891119905119903= 119878119894

119891(119894 = 1 2 119899) (12)

Through (12) 119878119891119905119903

and 119878119891have one-to-one corresponding

relation Above all the complete and succinct boundaryformulation for DSSR is expressed as

ΩDSSR

=

1198611

1198612

119861119894

119861119899

=

1198781119891le min

1198781198871119865max minus 119878

1198871

119865 1198781198871119879max minus sum

119895isinΦ(1198871)

119878119895

119865minus sum

119896 =1119896isinΘ(1)

119878119896119891

1198782

119891le min

1198781198872

119865max minus 1198781198872

119865 1198781198872

119879max minus sum

119895isinΦ(1198872)

119878119895

119865minus sum

119896 =2119896isinΘ(2)

119878119896

119891

119878119894

119891le min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

119878119899119891le min

119878119887119899119865max minus 119878

119887119899

119865 119878119887119899119879max minus sum

119895isinΦ(119887119899)

119878119895

119865minus sum

119896 =119899119896isinΘ(119899)

119878119896119891

(13)

With the form transformation ofDSSRmodel correspondingsymbols and their meaning should be adjusted too Thus 119887119894and Θ(119894) are used for new expression 119887119894 = the number ofback-feed feeders of 119878119894

119891 119878119887119894119865= all of the load supplied by the

back-feed feeder 119887119894 Θ(119894) = the set of transfer unit loads ofwhich both normal-feed and back-feed transformer are thesame as those of 119878119894

119891 It should be pointed out that feeder 1198871

feeder 119887119899 are not 119899 different actual feeders Take the case inFigure 2 as an example again when fault occurs the back-feed feeders of 1198783

119891and 1198784

119891are both feeder 1 which means

feeder b3 = feeder b4 = feeder 1 When any equality in (13)holds the operating point is just upon the DSSR boundaryWe denote the n boundaries by 119861

1 119861

119899

The DSSR boundary formulation can also reflect bothsubstation transformer and feeder N-1 secure constraintsTake 119894 subformula of (13) to concretely explain 119878119894

119891le

119878119887119894119865max minus 119878

119887119894

119865shows that transfer of 119878119894

119891cannot cause the feeder

overloading which ensures that the feeder N-1 is secure 119878119894119891le

119878119887119894119879max minus sum119895isinΦ(119887119894) 119878

119895

119865minus sum119896 =1119896isinΘ

(119894) 119878119896

119891shows that transfer of 119878119894

119891

cannot lead to the substation transformer overloading whichensures that the transformer N-1 is secure

5 Topological Characteristics of DSSR andMathematical Proof

The research on differential topological characteristics of theDSSR focuses on several aspects as follows

Journal of Applied Mathematics 5

(1) Are there any holes inside the DSSR that is thedenseness in terms of the topology

(2) Does the boundary of the DSSR have suspension(3) Could the boundary of the DSSR be expressed with

the union of several subsurfaces

The identical deformation from formulas (2)ndash(7) to (13) isa breakthrough for the research on topological characteristicsof the DSSR However to research on these characteristicsformula (13) should be further simplified to obtain themathematical essence Take 119894 subformula of (13) as researchobject the equivalent form is

119878119894

119891+ 119878119887119894

119865le 119878119887119894

119865max

119878119894

119891+ sum

119895isinΦ(119887119894)

119878119895

119865+ sum

119896 =1119896isinΘ(119894)

119878119896

119891le 119878119887119894

119879max(14)

According to formulas (3) and (12) 119878119887119894119865

and 119878119895119865

can beexpressed as linear combination of a series of differentelement ldquo119878

119891rdquo Then formula (14) will be simplified as

119899

sum119898=1

120572119898119878119898

119891le 119878119887119894

119865max

119899

sum119898=1

120573119898119878119898

119891le 119878119887119894

119879max

(15)

where 119878119887119894119865max and 119878119887119894

119879max are positive constants Throughformula (14) coefficients 120572 and 120573 have the following features

120572119898= 1 120573

119898= 1 (119898 = 119894)

120572119898= 0 or 1 120573

119898= 0 or 1 (119898 = 119894)

(16)

LetΩDSSR be a set which consists of operating pointW DSSRboundary formulation can be abstracted as

AW le C (17)

whereW is a vector defined as formula (1)Through formulas(15)-(16) matrices A and C should satisfy

A = [119886119894119895]2119899times119899

119894 ge 1 119895 ge 1

119886119894119895= 1 (119894 = 2119895 minus 1 or 119894 = 2119895)

119886119894119895= 0 or 1 (119894 = 2119895 minus 1 119894 = 2119895)

C = [1198881 1198882 1198882119899]119879

C isin R+

(18)

Because one integrated subformula is divided into equivalenttwo parts as is shown in formula (15) the dimension ofA is 2119899 times 119899 instead of 119899 times 119899 Here ΩDSSR is both linearspace and Euclidean space which has been proved in [17]Besides this important premise we should review somepreparation definitions and theorems about topology andEuclidean space including cluster point closure dense setand hyperplane

Definition 1 (cluster point) Let x be a point in Euclideanspace 119865 sub 119877 If there is a point sequence in set 119865 convergingto x then x is the cluster point of set 119865 [17]

Definition 2 (closure) 119860 is a subset of topological space 119860represents all the points inside 119860 and cluster points of 119860 andthen 119860 is called closure of 119860 [18]

Theorem 3 If the 119861 is a subset of 119860 119861 = 119860 then 119861 is dense in119860 [18]

Theorem 4 Let 119871 be a subspace of linear space 119877 x0 is a fixedvector which does not belong to 119871 generally Considering set119867which consists of the vector x x is obtained by

x = x0 + y (19)

where vector y varies in the whole subspace 119871 Thus119867 is calledhyperplane The dimension of119867 equals that of subspace 119871 [17]

The topological characteristics of DSSR are mathemati-cally proved in the following section

Characteristic 1 TheΩDSSR is dense inside

Proof First a new setΩ1015840DSSR is defined as the set of all pointsofΩDSSR except those on boundariesΩ1015840DSSR meets

AW lt C (20)

Select randomly a vector W = (1198781119891 1198782119891 119878119899

119891)119879 from Ω1015840DSSR

and then construct a sequenceY = Y1Y2 Ym as the

following formula

Y =

Y1= (1198781119891minus1198781119891

1 1198782119891minus1198782119891

1 119878119899

119891minus119878119899119891

1)

119879

= (0 0 0)119879

Y2= (1198781

119891minus1198781119891

2 1198782

119891minus1198782119891

2 119878

119899

119891minus119878119899119891

2)

119879

Y119898= (1198781119891minus1198781119891

119898 1198782119891minus1198782119891

119898 119878119899

119891minus119878119899119891

119898)

119879

= (1 minus1

119898)W

(21)

According to (20)-(21) we obtain

AYm = A(1 minus 1119898)W lt AW lt C (22)

Therefore sequence Y = Y1Y2 Ym is inside Ω1015840

DSSRLet 120588(WYm) be the distance betweenWandYm in Euclideanspace and then

lim119898rarrinfin

120588 (WYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(23)

6 Journal of Applied Mathematics

0

Snf (MVA)

Smf (MVA)

c3

c2c1 gt c2 + c3

DSSR

max(c2 c3) lt c1 lt c2 + c3

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

min(c2 c3) lt c1 lt max(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

0 lt c1 lt min(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

Figure 3 Shapes of 2-dimension cross-section of DSSR

Thismeans that for any vectorW inΩ1015840DSSR sequenceY existsand converges toW andY is also insideΩ1015840DSSRTherefore anypoint insideΩ1015840DSSR is cluster point of Ω

1015840

DSSRSimilarly select vector Z = (1198781

119891 1198782119891 119878119899

119891)119879 which is just

upon boundary ofΩ119863119878119878119877

AZ = C (24)

Construct a sequence U = U1U2 Um

Um = (1 minus1

119898)Z (25)

Then we obtain

AUm = A(1 minus 1119898)Z lt AZ = C (26)

According to formula (26) sequence U is also inside Ω1015840DSSRThrough the following

lim119898rarrinfin

120588 (ZYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(27)

We obtain that any point just upon the ΩDSSR boundary isalso cluster point ofΩ1015840DSSR Above all cluster points ofΩ

1015840

DSSR

include not only all the points inside Ω1015840DSSR but also all thepoints just upon the boundaries ofΩDSSRThus the followingformula holds

Ω1015840DSSR = ΩDSSR (28)

Through Theorem 3 Ω1015840DSSR is dense in ΩDSSR This proof iscompleted

Characteristic 2 The boundary ofΩDSSR has no suspension

Proof This characteristic can be approximately simplified toprove that any 2-dimension cross-section of ΩDSSR is convexpolygon For W = (1198781

119891 1198782119891 119878119899

119891)119879 select a 2-dimension

cross-section by taking 119878119898119891

and 119878119899119891as variables and 119878

119891in

another dimension as constants According to formula (16)the coefficient of 119878

119891(including variable 119878

119891and constant ones)

can be only 1 or 0 thus in process of dimension reduction 119878119898119891

and 119878119899119891are simply constrained by

119878119898

119891+ 119878119899

119891le 1198881

0 le 119878119898

119891le 1198882

0 le 119878119899

119891le 1198883

forall1198881 1198882 1198883isin 119877+

(29)

Journal of Applied Mathematics 7

Table 1 Profile of test case

Substation Transformer Voltages (kVkV) Transformer capacity (MVA) Number of feeders Total feeder capacity (MVA)

S1 T1 3510 400 9 8028T2 3510 400 9 8028

S2 T3 3510 400 9 8028T4 3510 400 8 7136

S3 T5 11010 630 10 892T6 11010 630 10 892

S4 T7 11010 630 10 892T8 11010 630 10 892

The shape of 2-dimension cross-section varies with the valuesof 1198881 1198882 and 119888

3 as is shown in Figure 3 The dashed oblique

line represents 119878119898119891+ 119878119899119891le 1198881

As is shown in Figure 3 the shapes of 2-dimension sectionare confined to rectangle triangle ladder and convex pen-tagon This means that any 2-dimension section of DSSR isconvex polygon which proves that the boundary ofΩDSSR hasno suspension in an indirect wayThe proof is completed

Characteristic 3 The ΩDSSR boundary can be expressed withseveral subsurfaces

Proof 119867 is a set of vector W = (1198781119891 1198782119891 119878119899

119891)119879 each of

which satisfies nonhomogeneous linear equation set

AW = C (30)

where matrices A and C meet formula (18) and W is theoperating point just upon the boundary of ΩDSSR Let W0 =

(120579(0)

1 120579(0)

2 120579(0)

119899)119879 be a fixed solution of equation set (31)

Meanwhile 119871 is a subspace of 119877 which consists of y =

(1205821 1205822 120582

119899)119879 that is y varies in the whole subspace 119871

The coordinates of ymeet the following homogeneous linearequation set

Ay = 0 (31)

If y = (1205821 1205822 120582

119899)119879 is a solution of (31) W = W0

+y = (120579(0)

1+ 1205821 120579(0)

2+ 1205822 120579(0)

119899+ 120582119899)119879 is obviously

a solution of equation set (30) that is W is included inset 119867 Meanwhile x0 is not in 119871 Through Theorem 3 119867is hyperplane The boundary of ΩDSSR can be expressedwith hyperplane that is several subsurfaces Because thedimension of 119871 is 119899 the dimension of hyperplane is also 119899This proof is completed

In transmission area topological characteristics of secu-rity region (SR) have been deeply studied [7] It has shownthat the boundary of SR has no suspension and is compactand approximately linear there is no hole inside the SR Theproof above demonstrates that characteristics of DSSR aresimilar but it has its own features

(a) DSSR is a convex set of denseness in terms ofthe topology This means that DSSR has no holesinside and its boundary has no suspension Basedon this feature dispatchers can analyze the securityof operating point by judging whether the point isinside theDSSRboundarywithout being afraid of anyinsecure point inside or losing security points

(b) DSSR boundary can be described by hyperplane (sev-eral Euclidean subsurfaces) meanwhile the bound-ary ismore linear than that of SR In practical applica-tion calculation of high dimensional security regionwill incur great computation burdens and consumelarge amount of time Therefore this characteristicwill improve the computational efficiency

6 Case Study

In order to verify the effectiveness of the proposedmodel twocases are illustrated in this section The first one is a test caseand the second is a practical case

61 Test Case

611 Overview of Test Case As is shown in Figure 4 the gridis comprised of 4 substations 8 substation transformers and75 feeders 68 feeders form 34 single loop networks and 7form two-tie connections resulting in 82 load transfer unitsThe total capacity of substations is 412MVA To illustrate themodeling process clearly each load transfer unit is numberedCase profile is shown in Table 1

The conductor type of all feeders is LGJ-185 (892MVA)This type is selected based on the national electrical code inChina

612 Boundary Formulation The test case grid has 75 feed-ers 14 feeders form 7 two-tie connections Each load of these7 feeders can be divided into 2 parts to transfer in differentback-feed path So the number of load transfer units is 82which means that the dimension of operation point W is82 and the number of subformulas of DSSR boundary is82 Based on the topology of the test case we substitutethe rated capacity of substation transformers and feedersinto 1198781

119865max 119878119899

119865max and 1198781119879max 119878

119899

119879max of formula (13)

8 Journal of Applied Mathematics

Then the boundary formulation for DSSR of test case can beexpressed as

ΩDSSR =

1198781

119891le min 892 minus (11987876

119891+ 11987836119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198782119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198782119891le min 892 minus (11987837

119891+ 11987877119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198783119891le min 892 minus (11987838

119891+ 11987878119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198784119891+ 1198785119891)

1198784119891le min 892 minus 11987839

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198785119891)

1198785119891le min 892 minus 11987840

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198784119891)

11987882119891le min 892 minus 11987851

119891 63 minus (11987846

119891+ 11987847119891+ 11987848119891+ 11987849119891+ 11987850119891+ 11987851119891+ 11987852119891+ 11987853119891+ 11987854119891+ 11987855119891) minus 11987881119891

(32)

Considering the similarity of calculation approach ofeach boundary and thesis length we present 5 subformulasof 1198781119891 1198785

119891here Complete formulation is given in the

appendix (in the Supplementary Material available online athttpdxdoiorg1011552014327078) Take the first subfor-mula in (32) as an example to explain the modeling processFigure 5 shows the local topology related with 1198781

119891 including

all relative transfer units in the first subformulaFirst analyze the topology and determine the parameters

of formula (13)We know that back-feed feeder of 1198781119891is feeder

36 and the back-feed substation transformer of 1198781119891is T5 In

normal state 11987836119891 11987845

119891and 11987876

119891 11987878

119891are all load of T5

which means sum119895isinΦ(1198871) 119878119895

119865= sum45

119895=36119878119895

119891+ sum78

119895=76119878119895

119891 11987836119891

and 11987876119891

are load of feeder 36 which means 1198781198871119865= 11987836119891+ 11987876119891 1198782119891 1198785

119891

are the load transferred fromT1 to T5when fault occurs at T1whichmeanssum

119896 =1119896isinΘ(1) 119878119896

119891= sum5

119896=2119878119896119891Therefore the formula

of B1 is preliminary expressed as

1198781

119891le min 11987836

119865max minus (11987876

119891+ 11987836

119891)

1198785

119879max minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(33)

Second according to case profile substitute 11987836119865max =

892MVA and 1198785119879max = 63MVA into formula (33) and then

we obtain

1198781

119891le min 892 minus (11987876

119891+ 11987836

119891)

63 minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(34)

613 Visualization and Topological Characteristics To visu-alize the shape of DSSR the dimension is reduced to 2 and 3which means that the coordinates of W should be constantsother than those to be visualized Thus an operating pointhas to be predetermined to provide the constants TSC is aspecial operating point just upon the security boundary [1]on which the facilities are usually fully utilizedThe operationof distribution system is closing to the boundaries and loadlevel is reaching TSCThus in this test case we select the TSCpoint as the predetermined operating point WTSC which isshown in Table 2The calculation approach for TSC has beenpresented in [15]

Choose randomly transfer unit loads 11987815119891

and 11987852119891

toobserve Substitute the rated capacity of transformers T1simT6capacity of all feeders and all transfer unit loads other than11987815119891

and 11987852119891 into formula (32) Then the 2D DSSR shown in

Figure 6 is obtainedAlthough the dimension is 2 the number of subformulas

which constrain the figure shape is not just 2 In fact eachof the subformulas which contains 11987815

119891or 11987852119891

should beconsidered But the subformulas withmore severe constraintswill cover the others and finally form theDSSR boundaryThefinal formulation of 2D figure is

0 le 11987815

119891le 52

0 le 11987852

119891le 3

(35)

Journal of Applied Mathematics 9

T1S1

T2

T3

T4

S 2

S4

T8

T6S3

T5

17-1

8

20-19

12ndash1

415

-16

21ndash23

41-4

3

36ndash3

8

39-4

044

-45

47-4

650

-51

52-5

3

54-5

548

-49

10-1

1

9-8

1 ndash3

4-5

6-7

76ndash7

8

79-80

58-5960-61

57-5665-62

66ndash6970-71

72ndash7524-25

29-28

26-27

30-31

32ndash35

81-8

2

Tie switch

T7

Distribution transformer

(i + 1) j are the same in the topologyin terms of calculation for DSSR

Note means that transfer units iindashj

Figure 4 Test case with eight substation transformers

Feeder 1

T1

T5

Feeder 2Feeder 36Feeder 37

S1f

S2f

S3f

S76f

S77f

S78f

S36f

S36f

S37f

S45f

S4f

S5f

middot middot middot

middot middot middot middot middot middot

Figure 5 Local topology related with f1

Similarly we choose randomly transfer unit loads 11987819119891 11987824119891

and 11987832119891

to observe and then the 3D DSSR is obtained as isshown in Figure 7

In Figure 6 it can be seen that the 2D DSSR is a denserectangle of which boundaries are linear without suspension

DSSR

0

1

2

3

1 2 3 4 52 S52f (MVA)

S15f (MVA)

Figure 6 Shape of 2D DSSR

In Figure 7 the 3D DSSR is surrounded by several subplanesforming a convex pentagon that is a special 3-dimensionhyperplane

10 Journal of Applied Mathematics

Table 2 Transfer unit load ofWTSC in test case

Transfer unit Load (MVA)1 2882 2883 2884 2885 2886 1647 1648 1649 16410 28811 28812 31713 31714 31715 31716 31717 30018 30019 31720 31721 34722 34723 31124 31125 31126 34727 34728 34729 34730 28031 28032 16133 16134 16135 16136 28037 28038 28039 28040 25241 32942 25243 32944 25245 32946 28847 28848 39549 395

Table 2 Continued

Transfer unit Load (MVA)50 39551 44652 44653 44654 44655 56456 56457 56958 56959 59260 59261 53362 53363 35964 35965 51366 51367 49468 49469 44670 44671 44672 44673 44674 44675 44676 44677 28078 28079 28080 28081 28082 280mdash mdashmdash mdash

01 2 3 4 5

2

3

1

12

34

56

DSSR

S32f

(MVA

)

S24f (MVA)

S19

f(M

VA)

Figure 7 Shape of 3D DSSR

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 5: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

Journal of Applied Mathematics 5

(1) Are there any holes inside the DSSR that is thedenseness in terms of the topology

(2) Does the boundary of the DSSR have suspension(3) Could the boundary of the DSSR be expressed with

the union of several subsurfaces

The identical deformation from formulas (2)ndash(7) to (13) isa breakthrough for the research on topological characteristicsof the DSSR However to research on these characteristicsformula (13) should be further simplified to obtain themathematical essence Take 119894 subformula of (13) as researchobject the equivalent form is

119878119894

119891+ 119878119887119894

119865le 119878119887119894

119865max

119878119894

119891+ sum

119895isinΦ(119887119894)

119878119895

119865+ sum

119896 =1119896isinΘ(119894)

119878119896

119891le 119878119887119894

119879max(14)

According to formulas (3) and (12) 119878119887119894119865

and 119878119895119865

can beexpressed as linear combination of a series of differentelement ldquo119878

119891rdquo Then formula (14) will be simplified as

119899

sum119898=1

120572119898119878119898

119891le 119878119887119894

119865max

119899

sum119898=1

120573119898119878119898

119891le 119878119887119894

119879max

(15)

where 119878119887119894119865max and 119878119887119894

119879max are positive constants Throughformula (14) coefficients 120572 and 120573 have the following features

120572119898= 1 120573

119898= 1 (119898 = 119894)

120572119898= 0 or 1 120573

119898= 0 or 1 (119898 = 119894)

(16)

LetΩDSSR be a set which consists of operating pointW DSSRboundary formulation can be abstracted as

AW le C (17)

whereW is a vector defined as formula (1)Through formulas(15)-(16) matrices A and C should satisfy

A = [119886119894119895]2119899times119899

119894 ge 1 119895 ge 1

119886119894119895= 1 (119894 = 2119895 minus 1 or 119894 = 2119895)

119886119894119895= 0 or 1 (119894 = 2119895 minus 1 119894 = 2119895)

C = [1198881 1198882 1198882119899]119879

C isin R+

(18)

Because one integrated subformula is divided into equivalenttwo parts as is shown in formula (15) the dimension ofA is 2119899 times 119899 instead of 119899 times 119899 Here ΩDSSR is both linearspace and Euclidean space which has been proved in [17]Besides this important premise we should review somepreparation definitions and theorems about topology andEuclidean space including cluster point closure dense setand hyperplane

Definition 1 (cluster point) Let x be a point in Euclideanspace 119865 sub 119877 If there is a point sequence in set 119865 convergingto x then x is the cluster point of set 119865 [17]

Definition 2 (closure) 119860 is a subset of topological space 119860represents all the points inside 119860 and cluster points of 119860 andthen 119860 is called closure of 119860 [18]

Theorem 3 If the 119861 is a subset of 119860 119861 = 119860 then 119861 is dense in119860 [18]

Theorem 4 Let 119871 be a subspace of linear space 119877 x0 is a fixedvector which does not belong to 119871 generally Considering set119867which consists of the vector x x is obtained by

x = x0 + y (19)

where vector y varies in the whole subspace 119871 Thus119867 is calledhyperplane The dimension of119867 equals that of subspace 119871 [17]

The topological characteristics of DSSR are mathemati-cally proved in the following section

Characteristic 1 TheΩDSSR is dense inside

Proof First a new setΩ1015840DSSR is defined as the set of all pointsofΩDSSR except those on boundariesΩ1015840DSSR meets

AW lt C (20)

Select randomly a vector W = (1198781119891 1198782119891 119878119899

119891)119879 from Ω1015840DSSR

and then construct a sequenceY = Y1Y2 Ym as the

following formula

Y =

Y1= (1198781119891minus1198781119891

1 1198782119891minus1198782119891

1 119878119899

119891minus119878119899119891

1)

119879

= (0 0 0)119879

Y2= (1198781

119891minus1198781119891

2 1198782

119891minus1198782119891

2 119878

119899

119891minus119878119899119891

2)

119879

Y119898= (1198781119891minus1198781119891

119898 1198782119891minus1198782119891

119898 119878119899

119891minus119878119899119891

119898)

119879

= (1 minus1

119898)W

(21)

According to (20)-(21) we obtain

AYm = A(1 minus 1119898)W lt AW lt C (22)

Therefore sequence Y = Y1Y2 Ym is inside Ω1015840

DSSRLet 120588(WYm) be the distance betweenWandYm in Euclideanspace and then

lim119898rarrinfin

120588 (WYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(23)

6 Journal of Applied Mathematics

0

Snf (MVA)

Smf (MVA)

c3

c2c1 gt c2 + c3

DSSR

max(c2 c3) lt c1 lt c2 + c3

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

min(c2 c3) lt c1 lt max(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

0 lt c1 lt min(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

Figure 3 Shapes of 2-dimension cross-section of DSSR

Thismeans that for any vectorW inΩ1015840DSSR sequenceY existsand converges toW andY is also insideΩ1015840DSSRTherefore anypoint insideΩ1015840DSSR is cluster point of Ω

1015840

DSSRSimilarly select vector Z = (1198781

119891 1198782119891 119878119899

119891)119879 which is just

upon boundary ofΩ119863119878119878119877

AZ = C (24)

Construct a sequence U = U1U2 Um

Um = (1 minus1

119898)Z (25)

Then we obtain

AUm = A(1 minus 1119898)Z lt AZ = C (26)

According to formula (26) sequence U is also inside Ω1015840DSSRThrough the following

lim119898rarrinfin

120588 (ZYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(27)

We obtain that any point just upon the ΩDSSR boundary isalso cluster point ofΩ1015840DSSR Above all cluster points ofΩ

1015840

DSSR

include not only all the points inside Ω1015840DSSR but also all thepoints just upon the boundaries ofΩDSSRThus the followingformula holds

Ω1015840DSSR = ΩDSSR (28)

Through Theorem 3 Ω1015840DSSR is dense in ΩDSSR This proof iscompleted

Characteristic 2 The boundary ofΩDSSR has no suspension

Proof This characteristic can be approximately simplified toprove that any 2-dimension cross-section of ΩDSSR is convexpolygon For W = (1198781

119891 1198782119891 119878119899

119891)119879 select a 2-dimension

cross-section by taking 119878119898119891

and 119878119899119891as variables and 119878

119891in

another dimension as constants According to formula (16)the coefficient of 119878

119891(including variable 119878

119891and constant ones)

can be only 1 or 0 thus in process of dimension reduction 119878119898119891

and 119878119899119891are simply constrained by

119878119898

119891+ 119878119899

119891le 1198881

0 le 119878119898

119891le 1198882

0 le 119878119899

119891le 1198883

forall1198881 1198882 1198883isin 119877+

(29)

Journal of Applied Mathematics 7

Table 1 Profile of test case

Substation Transformer Voltages (kVkV) Transformer capacity (MVA) Number of feeders Total feeder capacity (MVA)

S1 T1 3510 400 9 8028T2 3510 400 9 8028

S2 T3 3510 400 9 8028T4 3510 400 8 7136

S3 T5 11010 630 10 892T6 11010 630 10 892

S4 T7 11010 630 10 892T8 11010 630 10 892

The shape of 2-dimension cross-section varies with the valuesof 1198881 1198882 and 119888

3 as is shown in Figure 3 The dashed oblique

line represents 119878119898119891+ 119878119899119891le 1198881

As is shown in Figure 3 the shapes of 2-dimension sectionare confined to rectangle triangle ladder and convex pen-tagon This means that any 2-dimension section of DSSR isconvex polygon which proves that the boundary ofΩDSSR hasno suspension in an indirect wayThe proof is completed

Characteristic 3 The ΩDSSR boundary can be expressed withseveral subsurfaces

Proof 119867 is a set of vector W = (1198781119891 1198782119891 119878119899

119891)119879 each of

which satisfies nonhomogeneous linear equation set

AW = C (30)

where matrices A and C meet formula (18) and W is theoperating point just upon the boundary of ΩDSSR Let W0 =

(120579(0)

1 120579(0)

2 120579(0)

119899)119879 be a fixed solution of equation set (31)

Meanwhile 119871 is a subspace of 119877 which consists of y =

(1205821 1205822 120582

119899)119879 that is y varies in the whole subspace 119871

The coordinates of ymeet the following homogeneous linearequation set

Ay = 0 (31)

If y = (1205821 1205822 120582

119899)119879 is a solution of (31) W = W0

+y = (120579(0)

1+ 1205821 120579(0)

2+ 1205822 120579(0)

119899+ 120582119899)119879 is obviously

a solution of equation set (30) that is W is included inset 119867 Meanwhile x0 is not in 119871 Through Theorem 3 119867is hyperplane The boundary of ΩDSSR can be expressedwith hyperplane that is several subsurfaces Because thedimension of 119871 is 119899 the dimension of hyperplane is also 119899This proof is completed

In transmission area topological characteristics of secu-rity region (SR) have been deeply studied [7] It has shownthat the boundary of SR has no suspension and is compactand approximately linear there is no hole inside the SR Theproof above demonstrates that characteristics of DSSR aresimilar but it has its own features

(a) DSSR is a convex set of denseness in terms ofthe topology This means that DSSR has no holesinside and its boundary has no suspension Basedon this feature dispatchers can analyze the securityof operating point by judging whether the point isinside theDSSRboundarywithout being afraid of anyinsecure point inside or losing security points

(b) DSSR boundary can be described by hyperplane (sev-eral Euclidean subsurfaces) meanwhile the bound-ary ismore linear than that of SR In practical applica-tion calculation of high dimensional security regionwill incur great computation burdens and consumelarge amount of time Therefore this characteristicwill improve the computational efficiency

6 Case Study

In order to verify the effectiveness of the proposedmodel twocases are illustrated in this section The first one is a test caseand the second is a practical case

61 Test Case

611 Overview of Test Case As is shown in Figure 4 the gridis comprised of 4 substations 8 substation transformers and75 feeders 68 feeders form 34 single loop networks and 7form two-tie connections resulting in 82 load transfer unitsThe total capacity of substations is 412MVA To illustrate themodeling process clearly each load transfer unit is numberedCase profile is shown in Table 1

The conductor type of all feeders is LGJ-185 (892MVA)This type is selected based on the national electrical code inChina

612 Boundary Formulation The test case grid has 75 feed-ers 14 feeders form 7 two-tie connections Each load of these7 feeders can be divided into 2 parts to transfer in differentback-feed path So the number of load transfer units is 82which means that the dimension of operation point W is82 and the number of subformulas of DSSR boundary is82 Based on the topology of the test case we substitutethe rated capacity of substation transformers and feedersinto 1198781

119865max 119878119899

119865max and 1198781119879max 119878

119899

119879max of formula (13)

8 Journal of Applied Mathematics

Then the boundary formulation for DSSR of test case can beexpressed as

ΩDSSR =

1198781

119891le min 892 minus (11987876

119891+ 11987836119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198782119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198782119891le min 892 minus (11987837

119891+ 11987877119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198783119891le min 892 minus (11987838

119891+ 11987878119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198784119891+ 1198785119891)

1198784119891le min 892 minus 11987839

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198785119891)

1198785119891le min 892 minus 11987840

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198784119891)

11987882119891le min 892 minus 11987851

119891 63 minus (11987846

119891+ 11987847119891+ 11987848119891+ 11987849119891+ 11987850119891+ 11987851119891+ 11987852119891+ 11987853119891+ 11987854119891+ 11987855119891) minus 11987881119891

(32)

Considering the similarity of calculation approach ofeach boundary and thesis length we present 5 subformulasof 1198781119891 1198785

119891here Complete formulation is given in the

appendix (in the Supplementary Material available online athttpdxdoiorg1011552014327078) Take the first subfor-mula in (32) as an example to explain the modeling processFigure 5 shows the local topology related with 1198781

119891 including

all relative transfer units in the first subformulaFirst analyze the topology and determine the parameters

of formula (13)We know that back-feed feeder of 1198781119891is feeder

36 and the back-feed substation transformer of 1198781119891is T5 In

normal state 11987836119891 11987845

119891and 11987876

119891 11987878

119891are all load of T5

which means sum119895isinΦ(1198871) 119878119895

119865= sum45

119895=36119878119895

119891+ sum78

119895=76119878119895

119891 11987836119891

and 11987876119891

are load of feeder 36 which means 1198781198871119865= 11987836119891+ 11987876119891 1198782119891 1198785

119891

are the load transferred fromT1 to T5when fault occurs at T1whichmeanssum

119896 =1119896isinΘ(1) 119878119896

119891= sum5

119896=2119878119896119891Therefore the formula

of B1 is preliminary expressed as

1198781

119891le min 11987836

119865max minus (11987876

119891+ 11987836

119891)

1198785

119879max minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(33)

Second according to case profile substitute 11987836119865max =

892MVA and 1198785119879max = 63MVA into formula (33) and then

we obtain

1198781

119891le min 892 minus (11987876

119891+ 11987836

119891)

63 minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(34)

613 Visualization and Topological Characteristics To visu-alize the shape of DSSR the dimension is reduced to 2 and 3which means that the coordinates of W should be constantsother than those to be visualized Thus an operating pointhas to be predetermined to provide the constants TSC is aspecial operating point just upon the security boundary [1]on which the facilities are usually fully utilizedThe operationof distribution system is closing to the boundaries and loadlevel is reaching TSCThus in this test case we select the TSCpoint as the predetermined operating point WTSC which isshown in Table 2The calculation approach for TSC has beenpresented in [15]

Choose randomly transfer unit loads 11987815119891

and 11987852119891

toobserve Substitute the rated capacity of transformers T1simT6capacity of all feeders and all transfer unit loads other than11987815119891

and 11987852119891 into formula (32) Then the 2D DSSR shown in

Figure 6 is obtainedAlthough the dimension is 2 the number of subformulas

which constrain the figure shape is not just 2 In fact eachof the subformulas which contains 11987815

119891or 11987852119891

should beconsidered But the subformulas withmore severe constraintswill cover the others and finally form theDSSR boundaryThefinal formulation of 2D figure is

0 le 11987815

119891le 52

0 le 11987852

119891le 3

(35)

Journal of Applied Mathematics 9

T1S1

T2

T3

T4

S 2

S4

T8

T6S3

T5

17-1

8

20-19

12ndash1

415

-16

21ndash23

41-4

3

36ndash3

8

39-4

044

-45

47-4

650

-51

52-5

3

54-5

548

-49

10-1

1

9-8

1 ndash3

4-5

6-7

76ndash7

8

79-80

58-5960-61

57-5665-62

66ndash6970-71

72ndash7524-25

29-28

26-27

30-31

32ndash35

81-8

2

Tie switch

T7

Distribution transformer

(i + 1) j are the same in the topologyin terms of calculation for DSSR

Note means that transfer units iindashj

Figure 4 Test case with eight substation transformers

Feeder 1

T1

T5

Feeder 2Feeder 36Feeder 37

S1f

S2f

S3f

S76f

S77f

S78f

S36f

S36f

S37f

S45f

S4f

S5f

middot middot middot

middot middot middot middot middot middot

Figure 5 Local topology related with f1

Similarly we choose randomly transfer unit loads 11987819119891 11987824119891

and 11987832119891

to observe and then the 3D DSSR is obtained as isshown in Figure 7

In Figure 6 it can be seen that the 2D DSSR is a denserectangle of which boundaries are linear without suspension

DSSR

0

1

2

3

1 2 3 4 52 S52f (MVA)

S15f (MVA)

Figure 6 Shape of 2D DSSR

In Figure 7 the 3D DSSR is surrounded by several subplanesforming a convex pentagon that is a special 3-dimensionhyperplane

10 Journal of Applied Mathematics

Table 2 Transfer unit load ofWTSC in test case

Transfer unit Load (MVA)1 2882 2883 2884 2885 2886 1647 1648 1649 16410 28811 28812 31713 31714 31715 31716 31717 30018 30019 31720 31721 34722 34723 31124 31125 31126 34727 34728 34729 34730 28031 28032 16133 16134 16135 16136 28037 28038 28039 28040 25241 32942 25243 32944 25245 32946 28847 28848 39549 395

Table 2 Continued

Transfer unit Load (MVA)50 39551 44652 44653 44654 44655 56456 56457 56958 56959 59260 59261 53362 53363 35964 35965 51366 51367 49468 49469 44670 44671 44672 44673 44674 44675 44676 44677 28078 28079 28080 28081 28082 280mdash mdashmdash mdash

01 2 3 4 5

2

3

1

12

34

56

DSSR

S32f

(MVA

)

S24f (MVA)

S19

f(M

VA)

Figure 7 Shape of 3D DSSR

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 6: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

6 Journal of Applied Mathematics

0

Snf (MVA)

Smf (MVA)

c3

c2c1 gt c2 + c3

DSSR

max(c2 c3) lt c1 lt c2 + c3

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

min(c2 c3) lt c1 lt max(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

0 lt c1 lt min(c2 c3)

0

Snf (MVA)

Smf (MVA)

c3

c2

DSSR

Figure 3 Shapes of 2-dimension cross-section of DSSR

Thismeans that for any vectorW inΩ1015840DSSR sequenceY existsand converges toW andY is also insideΩ1015840DSSRTherefore anypoint insideΩ1015840DSSR is cluster point of Ω

1015840

DSSRSimilarly select vector Z = (1198781

119891 1198782119891 119878119899

119891)119879 which is just

upon boundary ofΩ119863119878119878119877

AZ = C (24)

Construct a sequence U = U1U2 Um

Um = (1 minus1

119898)Z (25)

Then we obtain

AUm = A(1 minus 1119898)Z lt AZ = C (26)

According to formula (26) sequence U is also inside Ω1015840DSSRThrough the following

lim119898rarrinfin

120588 (ZYm) = lim119898rarrinfin

radic119899

sum119894=1

[119878119894119891minus (119878119894119891minus119878119894119891

119898)]

2

= 0

(27)

We obtain that any point just upon the ΩDSSR boundary isalso cluster point ofΩ1015840DSSR Above all cluster points ofΩ

1015840

DSSR

include not only all the points inside Ω1015840DSSR but also all thepoints just upon the boundaries ofΩDSSRThus the followingformula holds

Ω1015840DSSR = ΩDSSR (28)

Through Theorem 3 Ω1015840DSSR is dense in ΩDSSR This proof iscompleted

Characteristic 2 The boundary ofΩDSSR has no suspension

Proof This characteristic can be approximately simplified toprove that any 2-dimension cross-section of ΩDSSR is convexpolygon For W = (1198781

119891 1198782119891 119878119899

119891)119879 select a 2-dimension

cross-section by taking 119878119898119891

and 119878119899119891as variables and 119878

119891in

another dimension as constants According to formula (16)the coefficient of 119878

119891(including variable 119878

119891and constant ones)

can be only 1 or 0 thus in process of dimension reduction 119878119898119891

and 119878119899119891are simply constrained by

119878119898

119891+ 119878119899

119891le 1198881

0 le 119878119898

119891le 1198882

0 le 119878119899

119891le 1198883

forall1198881 1198882 1198883isin 119877+

(29)

Journal of Applied Mathematics 7

Table 1 Profile of test case

Substation Transformer Voltages (kVkV) Transformer capacity (MVA) Number of feeders Total feeder capacity (MVA)

S1 T1 3510 400 9 8028T2 3510 400 9 8028

S2 T3 3510 400 9 8028T4 3510 400 8 7136

S3 T5 11010 630 10 892T6 11010 630 10 892

S4 T7 11010 630 10 892T8 11010 630 10 892

The shape of 2-dimension cross-section varies with the valuesof 1198881 1198882 and 119888

3 as is shown in Figure 3 The dashed oblique

line represents 119878119898119891+ 119878119899119891le 1198881

As is shown in Figure 3 the shapes of 2-dimension sectionare confined to rectangle triangle ladder and convex pen-tagon This means that any 2-dimension section of DSSR isconvex polygon which proves that the boundary ofΩDSSR hasno suspension in an indirect wayThe proof is completed

Characteristic 3 The ΩDSSR boundary can be expressed withseveral subsurfaces

Proof 119867 is a set of vector W = (1198781119891 1198782119891 119878119899

119891)119879 each of

which satisfies nonhomogeneous linear equation set

AW = C (30)

where matrices A and C meet formula (18) and W is theoperating point just upon the boundary of ΩDSSR Let W0 =

(120579(0)

1 120579(0)

2 120579(0)

119899)119879 be a fixed solution of equation set (31)

Meanwhile 119871 is a subspace of 119877 which consists of y =

(1205821 1205822 120582

119899)119879 that is y varies in the whole subspace 119871

The coordinates of ymeet the following homogeneous linearequation set

Ay = 0 (31)

If y = (1205821 1205822 120582

119899)119879 is a solution of (31) W = W0

+y = (120579(0)

1+ 1205821 120579(0)

2+ 1205822 120579(0)

119899+ 120582119899)119879 is obviously

a solution of equation set (30) that is W is included inset 119867 Meanwhile x0 is not in 119871 Through Theorem 3 119867is hyperplane The boundary of ΩDSSR can be expressedwith hyperplane that is several subsurfaces Because thedimension of 119871 is 119899 the dimension of hyperplane is also 119899This proof is completed

In transmission area topological characteristics of secu-rity region (SR) have been deeply studied [7] It has shownthat the boundary of SR has no suspension and is compactand approximately linear there is no hole inside the SR Theproof above demonstrates that characteristics of DSSR aresimilar but it has its own features

(a) DSSR is a convex set of denseness in terms ofthe topology This means that DSSR has no holesinside and its boundary has no suspension Basedon this feature dispatchers can analyze the securityof operating point by judging whether the point isinside theDSSRboundarywithout being afraid of anyinsecure point inside or losing security points

(b) DSSR boundary can be described by hyperplane (sev-eral Euclidean subsurfaces) meanwhile the bound-ary ismore linear than that of SR In practical applica-tion calculation of high dimensional security regionwill incur great computation burdens and consumelarge amount of time Therefore this characteristicwill improve the computational efficiency

6 Case Study

In order to verify the effectiveness of the proposedmodel twocases are illustrated in this section The first one is a test caseand the second is a practical case

61 Test Case

611 Overview of Test Case As is shown in Figure 4 the gridis comprised of 4 substations 8 substation transformers and75 feeders 68 feeders form 34 single loop networks and 7form two-tie connections resulting in 82 load transfer unitsThe total capacity of substations is 412MVA To illustrate themodeling process clearly each load transfer unit is numberedCase profile is shown in Table 1

The conductor type of all feeders is LGJ-185 (892MVA)This type is selected based on the national electrical code inChina

612 Boundary Formulation The test case grid has 75 feed-ers 14 feeders form 7 two-tie connections Each load of these7 feeders can be divided into 2 parts to transfer in differentback-feed path So the number of load transfer units is 82which means that the dimension of operation point W is82 and the number of subformulas of DSSR boundary is82 Based on the topology of the test case we substitutethe rated capacity of substation transformers and feedersinto 1198781

119865max 119878119899

119865max and 1198781119879max 119878

119899

119879max of formula (13)

8 Journal of Applied Mathematics

Then the boundary formulation for DSSR of test case can beexpressed as

ΩDSSR =

1198781

119891le min 892 minus (11987876

119891+ 11987836119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198782119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198782119891le min 892 minus (11987837

119891+ 11987877119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198783119891le min 892 minus (11987838

119891+ 11987878119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198784119891+ 1198785119891)

1198784119891le min 892 minus 11987839

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198785119891)

1198785119891le min 892 minus 11987840

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198784119891)

11987882119891le min 892 minus 11987851

119891 63 minus (11987846

119891+ 11987847119891+ 11987848119891+ 11987849119891+ 11987850119891+ 11987851119891+ 11987852119891+ 11987853119891+ 11987854119891+ 11987855119891) minus 11987881119891

(32)

Considering the similarity of calculation approach ofeach boundary and thesis length we present 5 subformulasof 1198781119891 1198785

119891here Complete formulation is given in the

appendix (in the Supplementary Material available online athttpdxdoiorg1011552014327078) Take the first subfor-mula in (32) as an example to explain the modeling processFigure 5 shows the local topology related with 1198781

119891 including

all relative transfer units in the first subformulaFirst analyze the topology and determine the parameters

of formula (13)We know that back-feed feeder of 1198781119891is feeder

36 and the back-feed substation transformer of 1198781119891is T5 In

normal state 11987836119891 11987845

119891and 11987876

119891 11987878

119891are all load of T5

which means sum119895isinΦ(1198871) 119878119895

119865= sum45

119895=36119878119895

119891+ sum78

119895=76119878119895

119891 11987836119891

and 11987876119891

are load of feeder 36 which means 1198781198871119865= 11987836119891+ 11987876119891 1198782119891 1198785

119891

are the load transferred fromT1 to T5when fault occurs at T1whichmeanssum

119896 =1119896isinΘ(1) 119878119896

119891= sum5

119896=2119878119896119891Therefore the formula

of B1 is preliminary expressed as

1198781

119891le min 11987836

119865max minus (11987876

119891+ 11987836

119891)

1198785

119879max minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(33)

Second according to case profile substitute 11987836119865max =

892MVA and 1198785119879max = 63MVA into formula (33) and then

we obtain

1198781

119891le min 892 minus (11987876

119891+ 11987836

119891)

63 minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(34)

613 Visualization and Topological Characteristics To visu-alize the shape of DSSR the dimension is reduced to 2 and 3which means that the coordinates of W should be constantsother than those to be visualized Thus an operating pointhas to be predetermined to provide the constants TSC is aspecial operating point just upon the security boundary [1]on which the facilities are usually fully utilizedThe operationof distribution system is closing to the boundaries and loadlevel is reaching TSCThus in this test case we select the TSCpoint as the predetermined operating point WTSC which isshown in Table 2The calculation approach for TSC has beenpresented in [15]

Choose randomly transfer unit loads 11987815119891

and 11987852119891

toobserve Substitute the rated capacity of transformers T1simT6capacity of all feeders and all transfer unit loads other than11987815119891

and 11987852119891 into formula (32) Then the 2D DSSR shown in

Figure 6 is obtainedAlthough the dimension is 2 the number of subformulas

which constrain the figure shape is not just 2 In fact eachof the subformulas which contains 11987815

119891or 11987852119891

should beconsidered But the subformulas withmore severe constraintswill cover the others and finally form theDSSR boundaryThefinal formulation of 2D figure is

0 le 11987815

119891le 52

0 le 11987852

119891le 3

(35)

Journal of Applied Mathematics 9

T1S1

T2

T3

T4

S 2

S4

T8

T6S3

T5

17-1

8

20-19

12ndash1

415

-16

21ndash23

41-4

3

36ndash3

8

39-4

044

-45

47-4

650

-51

52-5

3

54-5

548

-49

10-1

1

9-8

1 ndash3

4-5

6-7

76ndash7

8

79-80

58-5960-61

57-5665-62

66ndash6970-71

72ndash7524-25

29-28

26-27

30-31

32ndash35

81-8

2

Tie switch

T7

Distribution transformer

(i + 1) j are the same in the topologyin terms of calculation for DSSR

Note means that transfer units iindashj

Figure 4 Test case with eight substation transformers

Feeder 1

T1

T5

Feeder 2Feeder 36Feeder 37

S1f

S2f

S3f

S76f

S77f

S78f

S36f

S36f

S37f

S45f

S4f

S5f

middot middot middot

middot middot middot middot middot middot

Figure 5 Local topology related with f1

Similarly we choose randomly transfer unit loads 11987819119891 11987824119891

and 11987832119891

to observe and then the 3D DSSR is obtained as isshown in Figure 7

In Figure 6 it can be seen that the 2D DSSR is a denserectangle of which boundaries are linear without suspension

DSSR

0

1

2

3

1 2 3 4 52 S52f (MVA)

S15f (MVA)

Figure 6 Shape of 2D DSSR

In Figure 7 the 3D DSSR is surrounded by several subplanesforming a convex pentagon that is a special 3-dimensionhyperplane

10 Journal of Applied Mathematics

Table 2 Transfer unit load ofWTSC in test case

Transfer unit Load (MVA)1 2882 2883 2884 2885 2886 1647 1648 1649 16410 28811 28812 31713 31714 31715 31716 31717 30018 30019 31720 31721 34722 34723 31124 31125 31126 34727 34728 34729 34730 28031 28032 16133 16134 16135 16136 28037 28038 28039 28040 25241 32942 25243 32944 25245 32946 28847 28848 39549 395

Table 2 Continued

Transfer unit Load (MVA)50 39551 44652 44653 44654 44655 56456 56457 56958 56959 59260 59261 53362 53363 35964 35965 51366 51367 49468 49469 44670 44671 44672 44673 44674 44675 44676 44677 28078 28079 28080 28081 28082 280mdash mdashmdash mdash

01 2 3 4 5

2

3

1

12

34

56

DSSR

S32f

(MVA

)

S24f (MVA)

S19

f(M

VA)

Figure 7 Shape of 3D DSSR

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 7: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

Journal of Applied Mathematics 7

Table 1 Profile of test case

Substation Transformer Voltages (kVkV) Transformer capacity (MVA) Number of feeders Total feeder capacity (MVA)

S1 T1 3510 400 9 8028T2 3510 400 9 8028

S2 T3 3510 400 9 8028T4 3510 400 8 7136

S3 T5 11010 630 10 892T6 11010 630 10 892

S4 T7 11010 630 10 892T8 11010 630 10 892

The shape of 2-dimension cross-section varies with the valuesof 1198881 1198882 and 119888

3 as is shown in Figure 3 The dashed oblique

line represents 119878119898119891+ 119878119899119891le 1198881

As is shown in Figure 3 the shapes of 2-dimension sectionare confined to rectangle triangle ladder and convex pen-tagon This means that any 2-dimension section of DSSR isconvex polygon which proves that the boundary ofΩDSSR hasno suspension in an indirect wayThe proof is completed

Characteristic 3 The ΩDSSR boundary can be expressed withseveral subsurfaces

Proof 119867 is a set of vector W = (1198781119891 1198782119891 119878119899

119891)119879 each of

which satisfies nonhomogeneous linear equation set

AW = C (30)

where matrices A and C meet formula (18) and W is theoperating point just upon the boundary of ΩDSSR Let W0 =

(120579(0)

1 120579(0)

2 120579(0)

119899)119879 be a fixed solution of equation set (31)

Meanwhile 119871 is a subspace of 119877 which consists of y =

(1205821 1205822 120582

119899)119879 that is y varies in the whole subspace 119871

The coordinates of ymeet the following homogeneous linearequation set

Ay = 0 (31)

If y = (1205821 1205822 120582

119899)119879 is a solution of (31) W = W0

+y = (120579(0)

1+ 1205821 120579(0)

2+ 1205822 120579(0)

119899+ 120582119899)119879 is obviously

a solution of equation set (30) that is W is included inset 119867 Meanwhile x0 is not in 119871 Through Theorem 3 119867is hyperplane The boundary of ΩDSSR can be expressedwith hyperplane that is several subsurfaces Because thedimension of 119871 is 119899 the dimension of hyperplane is also 119899This proof is completed

In transmission area topological characteristics of secu-rity region (SR) have been deeply studied [7] It has shownthat the boundary of SR has no suspension and is compactand approximately linear there is no hole inside the SR Theproof above demonstrates that characteristics of DSSR aresimilar but it has its own features

(a) DSSR is a convex set of denseness in terms ofthe topology This means that DSSR has no holesinside and its boundary has no suspension Basedon this feature dispatchers can analyze the securityof operating point by judging whether the point isinside theDSSRboundarywithout being afraid of anyinsecure point inside or losing security points

(b) DSSR boundary can be described by hyperplane (sev-eral Euclidean subsurfaces) meanwhile the bound-ary ismore linear than that of SR In practical applica-tion calculation of high dimensional security regionwill incur great computation burdens and consumelarge amount of time Therefore this characteristicwill improve the computational efficiency

6 Case Study

In order to verify the effectiveness of the proposedmodel twocases are illustrated in this section The first one is a test caseand the second is a practical case

61 Test Case

611 Overview of Test Case As is shown in Figure 4 the gridis comprised of 4 substations 8 substation transformers and75 feeders 68 feeders form 34 single loop networks and 7form two-tie connections resulting in 82 load transfer unitsThe total capacity of substations is 412MVA To illustrate themodeling process clearly each load transfer unit is numberedCase profile is shown in Table 1

The conductor type of all feeders is LGJ-185 (892MVA)This type is selected based on the national electrical code inChina

612 Boundary Formulation The test case grid has 75 feed-ers 14 feeders form 7 two-tie connections Each load of these7 feeders can be divided into 2 parts to transfer in differentback-feed path So the number of load transfer units is 82which means that the dimension of operation point W is82 and the number of subformulas of DSSR boundary is82 Based on the topology of the test case we substitutethe rated capacity of substation transformers and feedersinto 1198781

119865max 119878119899

119865max and 1198781119879max 119878

119899

119879max of formula (13)

8 Journal of Applied Mathematics

Then the boundary formulation for DSSR of test case can beexpressed as

ΩDSSR =

1198781

119891le min 892 minus (11987876

119891+ 11987836119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198782119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198782119891le min 892 minus (11987837

119891+ 11987877119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198783119891le min 892 minus (11987838

119891+ 11987878119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198784119891+ 1198785119891)

1198784119891le min 892 minus 11987839

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198785119891)

1198785119891le min 892 minus 11987840

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198784119891)

11987882119891le min 892 minus 11987851

119891 63 minus (11987846

119891+ 11987847119891+ 11987848119891+ 11987849119891+ 11987850119891+ 11987851119891+ 11987852119891+ 11987853119891+ 11987854119891+ 11987855119891) minus 11987881119891

(32)

Considering the similarity of calculation approach ofeach boundary and thesis length we present 5 subformulasof 1198781119891 1198785

119891here Complete formulation is given in the

appendix (in the Supplementary Material available online athttpdxdoiorg1011552014327078) Take the first subfor-mula in (32) as an example to explain the modeling processFigure 5 shows the local topology related with 1198781

119891 including

all relative transfer units in the first subformulaFirst analyze the topology and determine the parameters

of formula (13)We know that back-feed feeder of 1198781119891is feeder

36 and the back-feed substation transformer of 1198781119891is T5 In

normal state 11987836119891 11987845

119891and 11987876

119891 11987878

119891are all load of T5

which means sum119895isinΦ(1198871) 119878119895

119865= sum45

119895=36119878119895

119891+ sum78

119895=76119878119895

119891 11987836119891

and 11987876119891

are load of feeder 36 which means 1198781198871119865= 11987836119891+ 11987876119891 1198782119891 1198785

119891

are the load transferred fromT1 to T5when fault occurs at T1whichmeanssum

119896 =1119896isinΘ(1) 119878119896

119891= sum5

119896=2119878119896119891Therefore the formula

of B1 is preliminary expressed as

1198781

119891le min 11987836

119865max minus (11987876

119891+ 11987836

119891)

1198785

119879max minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(33)

Second according to case profile substitute 11987836119865max =

892MVA and 1198785119879max = 63MVA into formula (33) and then

we obtain

1198781

119891le min 892 minus (11987876

119891+ 11987836

119891)

63 minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(34)

613 Visualization and Topological Characteristics To visu-alize the shape of DSSR the dimension is reduced to 2 and 3which means that the coordinates of W should be constantsother than those to be visualized Thus an operating pointhas to be predetermined to provide the constants TSC is aspecial operating point just upon the security boundary [1]on which the facilities are usually fully utilizedThe operationof distribution system is closing to the boundaries and loadlevel is reaching TSCThus in this test case we select the TSCpoint as the predetermined operating point WTSC which isshown in Table 2The calculation approach for TSC has beenpresented in [15]

Choose randomly transfer unit loads 11987815119891

and 11987852119891

toobserve Substitute the rated capacity of transformers T1simT6capacity of all feeders and all transfer unit loads other than11987815119891

and 11987852119891 into formula (32) Then the 2D DSSR shown in

Figure 6 is obtainedAlthough the dimension is 2 the number of subformulas

which constrain the figure shape is not just 2 In fact eachof the subformulas which contains 11987815

119891or 11987852119891

should beconsidered But the subformulas withmore severe constraintswill cover the others and finally form theDSSR boundaryThefinal formulation of 2D figure is

0 le 11987815

119891le 52

0 le 11987852

119891le 3

(35)

Journal of Applied Mathematics 9

T1S1

T2

T3

T4

S 2

S4

T8

T6S3

T5

17-1

8

20-19

12ndash1

415

-16

21ndash23

41-4

3

36ndash3

8

39-4

044

-45

47-4

650

-51

52-5

3

54-5

548

-49

10-1

1

9-8

1 ndash3

4-5

6-7

76ndash7

8

79-80

58-5960-61

57-5665-62

66ndash6970-71

72ndash7524-25

29-28

26-27

30-31

32ndash35

81-8

2

Tie switch

T7

Distribution transformer

(i + 1) j are the same in the topologyin terms of calculation for DSSR

Note means that transfer units iindashj

Figure 4 Test case with eight substation transformers

Feeder 1

T1

T5

Feeder 2Feeder 36Feeder 37

S1f

S2f

S3f

S76f

S77f

S78f

S36f

S36f

S37f

S45f

S4f

S5f

middot middot middot

middot middot middot middot middot middot

Figure 5 Local topology related with f1

Similarly we choose randomly transfer unit loads 11987819119891 11987824119891

and 11987832119891

to observe and then the 3D DSSR is obtained as isshown in Figure 7

In Figure 6 it can be seen that the 2D DSSR is a denserectangle of which boundaries are linear without suspension

DSSR

0

1

2

3

1 2 3 4 52 S52f (MVA)

S15f (MVA)

Figure 6 Shape of 2D DSSR

In Figure 7 the 3D DSSR is surrounded by several subplanesforming a convex pentagon that is a special 3-dimensionhyperplane

10 Journal of Applied Mathematics

Table 2 Transfer unit load ofWTSC in test case

Transfer unit Load (MVA)1 2882 2883 2884 2885 2886 1647 1648 1649 16410 28811 28812 31713 31714 31715 31716 31717 30018 30019 31720 31721 34722 34723 31124 31125 31126 34727 34728 34729 34730 28031 28032 16133 16134 16135 16136 28037 28038 28039 28040 25241 32942 25243 32944 25245 32946 28847 28848 39549 395

Table 2 Continued

Transfer unit Load (MVA)50 39551 44652 44653 44654 44655 56456 56457 56958 56959 59260 59261 53362 53363 35964 35965 51366 51367 49468 49469 44670 44671 44672 44673 44674 44675 44676 44677 28078 28079 28080 28081 28082 280mdash mdashmdash mdash

01 2 3 4 5

2

3

1

12

34

56

DSSR

S32f

(MVA

)

S24f (MVA)

S19

f(M

VA)

Figure 7 Shape of 3D DSSR

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 8: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

8 Journal of Applied Mathematics

Then the boundary formulation for DSSR of test case can beexpressed as

ΩDSSR =

1198781

119891le min 892 minus (11987876

119891+ 11987836119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198782119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198782119891le min 892 minus (11987837

119891+ 11987877119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198783119891+ 1198784119891+ 1198785119891)

1198783119891le min 892 minus (11987838

119891+ 11987878119891) 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198784119891+ 1198785119891)

1198784119891le min 892 minus 11987839

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198785119891)

1198785119891le min 892 minus 11987840

119891 63 minus (11987836

119891+ 11987837119891+ 11987838119891+ 11987839119891+ 11987840119891+ 11987841119891+ 11987842119891+ 11987843119891+ 11987844119891+ 11987845119891+ 11987876119891+ 11987877119891+ 11987878119891)

minus (1198781119891+ 1198782119891+ 1198783119891+ 1198784119891)

11987882119891le min 892 minus 11987851

119891 63 minus (11987846

119891+ 11987847119891+ 11987848119891+ 11987849119891+ 11987850119891+ 11987851119891+ 11987852119891+ 11987853119891+ 11987854119891+ 11987855119891) minus 11987881119891

(32)

Considering the similarity of calculation approach ofeach boundary and thesis length we present 5 subformulasof 1198781119891 1198785

119891here Complete formulation is given in the

appendix (in the Supplementary Material available online athttpdxdoiorg1011552014327078) Take the first subfor-mula in (32) as an example to explain the modeling processFigure 5 shows the local topology related with 1198781

119891 including

all relative transfer units in the first subformulaFirst analyze the topology and determine the parameters

of formula (13)We know that back-feed feeder of 1198781119891is feeder

36 and the back-feed substation transformer of 1198781119891is T5 In

normal state 11987836119891 11987845

119891and 11987876

119891 11987878

119891are all load of T5

which means sum119895isinΦ(1198871) 119878119895

119865= sum45

119895=36119878119895

119891+ sum78

119895=76119878119895

119891 11987836119891

and 11987876119891

are load of feeder 36 which means 1198781198871119865= 11987836119891+ 11987876119891 1198782119891 1198785

119891

are the load transferred fromT1 to T5when fault occurs at T1whichmeanssum

119896 =1119896isinΘ(1) 119878119896

119891= sum5

119896=2119878119896119891Therefore the formula

of B1 is preliminary expressed as

1198781

119891le min 11987836

119865max minus (11987876

119891+ 11987836

119891)

1198785

119879max minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(33)

Second according to case profile substitute 11987836119865max =

892MVA and 1198785119879max = 63MVA into formula (33) and then

we obtain

1198781

119891le min 892 minus (11987876

119891+ 11987836

119891)

63 minus (11987836

119891+ 11987837

119891+ 11987838

119891+ 11987839

119891+ 11987840

119891+ 11987841

11989111987842

119891

+11987843

119891+ 11987844

119891+ 11987845

119891+ 11987876

119891+ 11987877

119891+ 11987878

119891)

minus (1198782

119891+ 1198783

119891+ 1198784

119891+ 1198785

119891)

(34)

613 Visualization and Topological Characteristics To visu-alize the shape of DSSR the dimension is reduced to 2 and 3which means that the coordinates of W should be constantsother than those to be visualized Thus an operating pointhas to be predetermined to provide the constants TSC is aspecial operating point just upon the security boundary [1]on which the facilities are usually fully utilizedThe operationof distribution system is closing to the boundaries and loadlevel is reaching TSCThus in this test case we select the TSCpoint as the predetermined operating point WTSC which isshown in Table 2The calculation approach for TSC has beenpresented in [15]

Choose randomly transfer unit loads 11987815119891

and 11987852119891

toobserve Substitute the rated capacity of transformers T1simT6capacity of all feeders and all transfer unit loads other than11987815119891

and 11987852119891 into formula (32) Then the 2D DSSR shown in

Figure 6 is obtainedAlthough the dimension is 2 the number of subformulas

which constrain the figure shape is not just 2 In fact eachof the subformulas which contains 11987815

119891or 11987852119891

should beconsidered But the subformulas withmore severe constraintswill cover the others and finally form theDSSR boundaryThefinal formulation of 2D figure is

0 le 11987815

119891le 52

0 le 11987852

119891le 3

(35)

Journal of Applied Mathematics 9

T1S1

T2

T3

T4

S 2

S4

T8

T6S3

T5

17-1

8

20-19

12ndash1

415

-16

21ndash23

41-4

3

36ndash3

8

39-4

044

-45

47-4

650

-51

52-5

3

54-5

548

-49

10-1

1

9-8

1 ndash3

4-5

6-7

76ndash7

8

79-80

58-5960-61

57-5665-62

66ndash6970-71

72ndash7524-25

29-28

26-27

30-31

32ndash35

81-8

2

Tie switch

T7

Distribution transformer

(i + 1) j are the same in the topologyin terms of calculation for DSSR

Note means that transfer units iindashj

Figure 4 Test case with eight substation transformers

Feeder 1

T1

T5

Feeder 2Feeder 36Feeder 37

S1f

S2f

S3f

S76f

S77f

S78f

S36f

S36f

S37f

S45f

S4f

S5f

middot middot middot

middot middot middot middot middot middot

Figure 5 Local topology related with f1

Similarly we choose randomly transfer unit loads 11987819119891 11987824119891

and 11987832119891

to observe and then the 3D DSSR is obtained as isshown in Figure 7

In Figure 6 it can be seen that the 2D DSSR is a denserectangle of which boundaries are linear without suspension

DSSR

0

1

2

3

1 2 3 4 52 S52f (MVA)

S15f (MVA)

Figure 6 Shape of 2D DSSR

In Figure 7 the 3D DSSR is surrounded by several subplanesforming a convex pentagon that is a special 3-dimensionhyperplane

10 Journal of Applied Mathematics

Table 2 Transfer unit load ofWTSC in test case

Transfer unit Load (MVA)1 2882 2883 2884 2885 2886 1647 1648 1649 16410 28811 28812 31713 31714 31715 31716 31717 30018 30019 31720 31721 34722 34723 31124 31125 31126 34727 34728 34729 34730 28031 28032 16133 16134 16135 16136 28037 28038 28039 28040 25241 32942 25243 32944 25245 32946 28847 28848 39549 395

Table 2 Continued

Transfer unit Load (MVA)50 39551 44652 44653 44654 44655 56456 56457 56958 56959 59260 59261 53362 53363 35964 35965 51366 51367 49468 49469 44670 44671 44672 44673 44674 44675 44676 44677 28078 28079 28080 28081 28082 280mdash mdashmdash mdash

01 2 3 4 5

2

3

1

12

34

56

DSSR

S32f

(MVA

)

S24f (MVA)

S19

f(M

VA)

Figure 7 Shape of 3D DSSR

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 9: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

Journal of Applied Mathematics 9

T1S1

T2

T3

T4

S 2

S4

T8

T6S3

T5

17-1

8

20-19

12ndash1

415

-16

21ndash23

41-4

3

36ndash3

8

39-4

044

-45

47-4

650

-51

52-5

3

54-5

548

-49

10-1

1

9-8

1 ndash3

4-5

6-7

76ndash7

8

79-80

58-5960-61

57-5665-62

66ndash6970-71

72ndash7524-25

29-28

26-27

30-31

32ndash35

81-8

2

Tie switch

T7

Distribution transformer

(i + 1) j are the same in the topologyin terms of calculation for DSSR

Note means that transfer units iindashj

Figure 4 Test case with eight substation transformers

Feeder 1

T1

T5

Feeder 2Feeder 36Feeder 37

S1f

S2f

S3f

S76f

S77f

S78f

S36f

S36f

S37f

S45f

S4f

S5f

middot middot middot

middot middot middot middot middot middot

Figure 5 Local topology related with f1

Similarly we choose randomly transfer unit loads 11987819119891 11987824119891

and 11987832119891

to observe and then the 3D DSSR is obtained as isshown in Figure 7

In Figure 6 it can be seen that the 2D DSSR is a denserectangle of which boundaries are linear without suspension

DSSR

0

1

2

3

1 2 3 4 52 S52f (MVA)

S15f (MVA)

Figure 6 Shape of 2D DSSR

In Figure 7 the 3D DSSR is surrounded by several subplanesforming a convex pentagon that is a special 3-dimensionhyperplane

10 Journal of Applied Mathematics

Table 2 Transfer unit load ofWTSC in test case

Transfer unit Load (MVA)1 2882 2883 2884 2885 2886 1647 1648 1649 16410 28811 28812 31713 31714 31715 31716 31717 30018 30019 31720 31721 34722 34723 31124 31125 31126 34727 34728 34729 34730 28031 28032 16133 16134 16135 16136 28037 28038 28039 28040 25241 32942 25243 32944 25245 32946 28847 28848 39549 395

Table 2 Continued

Transfer unit Load (MVA)50 39551 44652 44653 44654 44655 56456 56457 56958 56959 59260 59261 53362 53363 35964 35965 51366 51367 49468 49469 44670 44671 44672 44673 44674 44675 44676 44677 28078 28079 28080 28081 28082 280mdash mdashmdash mdash

01 2 3 4 5

2

3

1

12

34

56

DSSR

S32f

(MVA

)

S24f (MVA)

S19

f(M

VA)

Figure 7 Shape of 3D DSSR

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 10: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

10 Journal of Applied Mathematics

Table 2 Transfer unit load ofWTSC in test case

Transfer unit Load (MVA)1 2882 2883 2884 2885 2886 1647 1648 1649 16410 28811 28812 31713 31714 31715 31716 31717 30018 30019 31720 31721 34722 34723 31124 31125 31126 34727 34728 34729 34730 28031 28032 16133 16134 16135 16136 28037 28038 28039 28040 25241 32942 25243 32944 25245 32946 28847 28848 39549 395

Table 2 Continued

Transfer unit Load (MVA)50 39551 44652 44653 44654 44655 56456 56457 56958 56959 59260 59261 53362 53363 35964 35965 51366 51367 49468 49469 44670 44671 44672 44673 44674 44675 44676 44677 28078 28079 28080 28081 28082 280mdash mdashmdash mdash

01 2 3 4 5

2

3

1

12

34

56

DSSR

S32f

(MVA

)

S24f (MVA)

S19

f(M

VA)

Figure 7 Shape of 3D DSSR

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 11: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

Journal of Applied Mathematics 11

T2 T1

T4 T3

T5 T6

T8 T7

T11 T9

T13 T12

T15 T14

T20 T19

T22 T21

T24 T23

T26 T25

T17 T16T18

T10

S4

S2

S3S5

S6

S7

S9

S8

S10S11

S12

6ndash10 1ndash5

11ndash15

16ndash20

21ndash25 26ndash31

37ndash40 32ndash36

41ndash4549ndash52

46ndash48

53ndash5657ndash61

62ndash6566ndash69

70ndash7374ndash77

78ndash80

81ndash8485ndash89

90ndash9394ndash9697ndash100101ndash105

106ndash110111ndash114

S12 times 40MVA 2 times 40MVA

2 times 40MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 50MVA

2 times 40MVA

3 times 40MVA

2 times 40MVA

2times40

MVA

3times315

MVA

Figure 8 The medium-voltage urban power grid of one city of southern China

62 Practical Case In this section the assessment andcontrol method based on DSSR is demonstrated on a realmedium-voltage distribution network of one city in south-ern China which consists of 12 substations 26 substationtransformers and 114 main feeders as is shown in Figure 8Total capacity of substation transformers is 10945MVA It isnotable that each two of all main feeders form a single loopnetwork in this case which leads to the fact that the numberof main feeders is equal to that of load transfer units

Paper [1] has presented concept and calculation methodof relative location of operating point in DSSR based onsubstation transformer contingency Similarly in this paperrelative location 119871

119894describes the distance from the operating

pointW to the boundary 119861119894(119894 = 1 2 119899)

119871119894= min

119878119887119894

119865max minus 119878119887119894

119865 119878119887119894

119879max minus sum

119895isinΦ(119887119894)

119878119895

119865minus sum

119896 =119894119896isinΘ(119894)

119878119896

119891

minus 119878119894

119891

(36)

119871119894is an index which is applied in security assessment

Here is an example Let W1 be an insecure operating pointEach transfer unit load of W1 is 08 times of TSC load inthe practical case except 1198781

119891and 11987810119891 while 1198781

119891= 8MVA and

11987810119891= 7MVA Total load of W1 is 5087MVA while TSC is

6289MVAAverage load rate is 046Thatmeans that current

Table 3 Distance to boundaries of 1198611and 119861

10atW1

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

operating point can be controlled back to security regionThrough formula (36) the location of a given operating pointin DSSR can be calculated We present the 119861

119894of which 119871

119894are

negative in Table 3Table 3 shows that the system should lose 3222MVA if

fault occurs at feeder 1 or feeder 10 so the system is locallyoverloading The location of W1 can be easily observed inFigure 9 To meet operational constraints under N-1 contin-gency 1198781

119891and 11987810

119891should be adjusted For example W1 is

adjusted toW1015840

1 through the dashed arrow shown in Figure 9The location ofW

1015840

1 is shown in Table 4

7 Conclusion and Further Work

This paper proposes a mathematical model for distributionsystem security region (DSSR) generic topological character-istics of DSSR are discussed and proved

First the operating point for a distribution system isdefined as the set of transfer unit loads which is a vector in the

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 12: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

12 Journal of Applied Mathematics

DSSR

0

2

4

6

2 4 6 8 10 11778

8

10

11778

S1f (MVA)

S10f (MVA)

W1(8 7)

W9984001 (7 4)

Figure 9 2D DSSR cross-section and preventive control

Table 4 Distance to boundaries of 1198611and 119861

10atW10158401

119861119894

1198611

11986110

119871119894(MVA) 0778 0778

Euclidean space Then the DSSR model for both substationtransformer and feeder contingency is proposed which is theset of all operating points each ensures that the system N-1 issecure

Second to perform research on the characteristic ofDSSR the boundary formulation for DSSR is derived fromthe DSSR model Then three generic characteristics areproposed and proved by rigor mathematical approach whichare as follows (1) DSSR is dense inside (2) DSSR boundaryhas no suspension (3)DSSR boundary can be expressed withthe union of several subsurfaces

Finally the results from a test case and a practical casedemonstrate the effectiveness of the proposed model Thevisualization for DSSR boundary is also discussed to verifythe topological characteristics of DSSR Security assessmentmethod based on DSSR is preliminary exhibited to show theapplicability of DSSR for future smart distribution system

This paper improves the accuracy and understanding ofDSSR which is fundamental theoretic work for future smartdistribution system Further works to improve the accuracyof DSSR model include fully considering power flow voltageconstraints and integration of DGs

Conflict of Interests

The authors declare that there is no conflict of inter-ests regarding the publication of this paper None ofthe authors have a commercial interest financial interestandor other relationship with manufacturers of pharma-ceuticalslaboratory supplies andor medical devices or withcommercialproviders of medically related services

Acknowledgments

This work was supported by the National Natural ScienceFoundation of China (no 51277129) and National HighTechnology Research and Development Program of China(863 Program) (no 2011AA05A117)

References

[1] J Xiao W Gu C Wang and F Li ldquoDistribution systemsecurity region definition model and security assessmentrdquo IETGeneration TransmissionampDistribution vol 6 no 10 pp 1029ndash1035 2012

[2] State Grid Corporation of China Guidelines of Urban PowerNetwork Planning State Grid Corporation of China BeijingChina 2006 (Chinese)

[3] E Lakervi and E J Holmes Electricity Distribution NetworkDesign IET Peregrinus UK 1995

[4] K N Miu and H D Chiang ldquoService restoration for unbal-anced radial distribution systems with varying loads solutionalgorithmrdquo in Proceedings of the IEEE Power Engineering SocietySummer Meeting vol 1 pp 254ndash258 1999

[5] Y X Yu ldquoSecurity region of bulk power systemrdquo in Proceedingsof the International Conference on Power System Technology(PowerCon rsquo02) vol 1 pp 13ndash17 Kunming China October2002

[6] F Wu and S Kumagai ldquoSteady-state security regions of powersystemsrdquo IEEE Transactions on Circuits and Systems vol 29 no11 pp 703ndash711 1982

[7] Y Yu Y Zeng and F Feng ldquoDifferential topological character-istics of the DSR on injection space of electrical power systemrdquoScience in China E Technological Sciences vol 45 no 6 pp 576ndash584 2002

[8] S J Chen Q X Chen Q Xia and C Q Kang ldquoSteady-state security assessment method based on distance to securityregion boundariesrdquo IET Generation Transmission amp Distribu-tion vol 7 no 3 pp 288ndash297 2013

[9] D M Staszesky D Craig and C Befus ldquoAdvanced feederautomation is hererdquo IEEE Power and Energy Magazine vol 3no 5 pp 56ndash63 2005

[10] C L Smallwood and J Wennermark ldquoBenefits of distributionautomationrdquo IEEE Industry Applications Magazine vol 16 no1 pp 65ndash73 2010

[11] X Mamo S Mallet T Coste and S Grenard ldquoDistributionautomation the cornerstone for smart grid development strat-egyrdquo in Proceedings of the IEEE Power amp Energy Society GeneralMeeting (PES rsquo09) pp 1ndash6 July 2009

[12] P W Sauer B C Lesieutre and M A Pai ldquoMaximumloadability and voltage stability in power systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 15 no 3 pp145ndash153 1993

[13] K N Miu and H Chiang ldquoElectric distribution systemload capability problem formulation solution algorithm andnumerical resultsrdquo IEEE Transactions on Power Delivery vol 15no 1 pp 436ndash442 2000

[14] F Z Luo C S Wang J Xiao and S Ge ldquoRapid evaluationmethod for power supply capability of urban distribution sys-tem based on N-1 contingency analysis of main-transformersrdquoInternational Journal of Electrical Power andEnergy Systems vol32 no 10 pp 1063ndash1068 2010

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 13: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

Journal of Applied Mathematics 13

[15] J Xiao F X LiWZGuC SWang andP Zhang ldquoTotal supplycapability and its extended indices for distribution systemsdefinitionmodel calculation and applicationsrdquo IETGenerationTransmission and Distribution vol 5 no 8 pp 869ndash876 2011

[16] J Xiao X X Gong and C S Wang ldquoTopology properties andalgorithm of N-1 security boundary for smart gridrdquo Proceedingsof the CSEE vol 34 no 4 pp 545ndash554 2014 (Chinese)

[17] G E Shilov An Introduction to the Theory of Linear SpacesDover New York NY USA 1975

[18] J R Munkres Topology vol 2 Prentice Hall Upper SaddleRiver NJ USA 2000

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 14: Research Article Model and Topological Characteristics of ...Distribution automation (DA) is an important concept included in smart distribution grid and will upgrade the distribution

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of


Recommended