+ All Categories
Home > Documents > Response to Fukushima - NCSL

Response to Fukushima - NCSL

Date post: 12-Sep-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
22
Response to Fukushima Ed Halpin, President and CEO National Conference of State Legislatures 2011 Energy Policy Summit San Antonio, Texas August 8, 2011
Transcript
Page 1: Response to Fukushima - NCSL

Response to FukushimaEd Halpin, President and CEO

National Conference of State Legislatures2011 Energy Policy Summit

San Antonio, Texas

August 8, 2011

Page 2: Response to Fukushima - NCSL

STP Overview

2

• Three Owners – Units 1 & 2

- NRG Energy 44%

- CPS Energy 40%

- Austin Energy 16%

STP Nuclear Operating Company was formed in 1997

Page 3: Response to Fukushima - NCSL

Performance Summary

3

• For seven consecutive years, STP has produced more electricity than all other two-unit facilities in the nation (2004-2010)

• Last October, named as one of 12 companies to the EHS Today 2010 list of America’s Safest Companies

- First nuclear facility to receive this award

• Last October, STP filed an application with the NRC to extend the operating license of Units 1 and 2

• Safely completed 30th refueling outage (Unit 1) in May. Preparing for Unit 2 refueling outage this fall

• In 2011, will invest $90 million in plant maintenance, improvements and refueling

Page 4: Response to Fukushima - NCSL

Tsunami Impact

Fukushima Daiichi

Nuclear Power Station

4

Page 5: Response to Fukushima - NCSL

TEPCO Impact

5

• 54 operating nuclear power

plants (NPPs) in Japan - 49

gigawatts

• Tokyo Electric Power Company

(TEPCO) operates 17 NPPs

- 6 at Fukushima Daiichi

- 4 at Fukushima Daini

- 7 at Kashiwazaki-Kariwa

• TEPCO produces 27% of

Japan’s electricity

• One new TEPCO NPP was also

under construction (Higashidori)

Page 6: Response to Fukushima - NCSL

Fukushima Daiichi Station

6

At time of the earthquake…• Reactors 1, 2 and 3 were operating; shut down automatically (seismic trip)• Reactors 4, 5 and 6 were in cold shutdown for annual outage

Unit 1

Unit 2

Unit 3

Unit 4

Units 5, 6

Page 7: Response to Fukushima - NCSL

Event Initiation

• Tohoku Pacific earthquake - Friday, March 11, 2011, at 2:26 pm

• Operating reactors tripped at both Fukushima sites (Daiichi, Daini)

• Offsite power lost - emergency diesel generators started

• Tsunami ≥ 10 m impacted sites

• Fukushima Daiichi station designed for 5.7 m tsunami

• Tsunami was beyond design basis

• Emergency diesels and some battery power lost due to flooding

7

Page 8: Response to Fukushima - NCSL

Event Sequence

Without AC power – they lost…

• Make-up water capability to the Reactor and Spent Fuel Pool (SFP)

• “Heat Sink” for decay heat removal

Loss of make-up and cooling -

• Allowed water to boil off

• Fuel became exposed / damaged

• Hydrogen formed; explosions damaged Unit 1, 3 and 4 secondary containments

• Unit 2 containment suppression chamber was damaged

8

Page 9: Response to Fukushima - NCSL

Fukushima Daiichi Accident

9

• Equivalent to our General Emergency was declared

• Public (~ 200,000 people) evacuated within 20 km (13 miles) of the plant

Page 10: Response to Fukushima - NCSL

• Cautiously stable

• Start recovery by 2012

• Future of nuclear in Japan?

• Root cause?

Fukushima Today

10

Page 11: Response to Fukushima - NCSL

Activity

11

Page 12: Response to Fukushima - NCSL

12

Page 13: Response to Fukushima - NCSL

Designed to withstand substantial earthquake even though we are

not in a significant earthquake zone

Reactor Containment Buildings

13

• Seismically hardened

• Four-foot thick concrete

• Reinforced with large steel rebar

• Steel liner plate

• Post tensioned

• Watertight

Page 14: Response to Fukushima - NCSL

14

Emergency Core Cooling Systems

Designed to withstand earthquakes, high winds, and flooding

• Seismically hardened

structures

• Site @ + 29’ MSL

• Watertight doors @ + 41’

MSL

• 3 safety “trains”

• Other U.S. plants have 2

• System trains are

independent

Page 15: Response to Fukushima - NCSL

Designed to withstand earthquakes, high winds, and flooding

Spent Fuel Pools

• In seismically hardened

buildings

• Substantial concrete

construction

• Lined with stainless steel

• Watertight doors

• Diesel generator backed

15

Page 16: Response to Fukushima - NCSL

16

Page 17: Response to Fukushima - NCSL

U.S. Industry Initiatives toEnsure Safety

• Formed the Fukushima Steering Committee

• Developed the “Way Forward” document that identifies focus areas

(Building Blocks), strategic goals and guiding principles the U.S.

industry will accomplish.

• Developed a response plan to drive implementation of established

goals with specific actions – near term and long term.

17

Page 18: Response to Fukushima - NCSL

U.S. Industry Initiatives toEnsure Safety

They include:

• Short Term (December 2011)

– Verified that all critical components, procedures and staffing are in place and

functional for mitigating flooding, seismic events, large area fires and

explosions.

– Implement interim compensatory measures as necessary to ensure spent fuel

pool cooling is protected at all times. Additional guidance was also issued to

evaluate defense in depth on cooling power sources, instrumentation and

procedural guidance.

– Assess the continued effectiveness of operator fundamentals and training

programs.

– Assess each facility’s ability to cope without power for 24 hours and not incur

fuel damage. Actions will be taken to maximize coping capability within the

existing design and licensing basis. 18

Page 19: Response to Fukushima - NCSL

U.S. Industry Initiatives toEnsure Safety

They include:

• Short Term (December 2011) continued

– Established an integrated network of information flow from nuclear

facilities worldwide to understand actions being taken and to

incorporate lessons learned.

– Evaluating near-term guideline changes to accident management and

emergency response programs based on lessons learned from

Fukushima.

– Maintain open, transparent communications with all key stakeholders

in regard to industry actions and lessons learned.

– Complete a cause analysis of the Fukushima event so that facts and

appropriate long-term actions can be understood and implemented.19

Page 20: Response to Fukushima - NCSL

U.S. Industry Initiatives toEnsure Safety

• Long Term:

– Re-evaluate credible, site-specific hazards that could lead to a

prolonged loss of power. Identify and implement corrective actions to

ensure the strategic goal of no fuel damage is achieved.

– Develop an industry protocol for the timely deployment of critical

materials to assist each facility in an emergency.

– Evaluate emergency preparedness strategies and amend as

necessary to incorporate lessons learned from the Fukushima

accident.

– Implement action plans to ensure spent fuel pool cooling as well as

containment integrity are maintained in accordance with the strategic

goals.20

Page 21: Response to Fukushima - NCSL

• Independent study commissioned, 90 day report issued

- Clarify the Regulatory Framework

- Re-evaluate, as necessary, the design basis for seismic and flood

protection

- Evaluate enhancements to seismically induced floods and fires

- Station Blackout

• Process to disposition recommendations under discussion

NRC 90 Day Task Force Report

21

Page 22: Response to Fukushima - NCSL

Conclusions

• STP has one of the safest designs in the world/experienced,

well-trained workforce

• The safety of our friends and neighbors in the local communities

is our primary responsibility

• The U.S. nuclear industry response to Fukushima is a significant

challenge

• The root cause of the accident, both technically and

organizationally, must be understood

• U.S. energy demand continues to grow-What is our

state’s/nation’s long-term energy strategy?

22


Recommended