+ All Categories
Home > Documents > Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4...

Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4...

Date post: 24-Jun-2020
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
36
Richard Rickett, General Manager Engineering and Procurement - March 2015 Case Study
Transcript
Page 1: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

Richard Rickett, General Manager Engineering and Procurement - March 2015

Case Study

Page 2: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

Case Study :Diverless Fast Track

Repair of Mooring System

Page 3: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

3DOF Subsea

Introduction

• ~ 300 floating production units in use around the world

• Design = maximise uptime = minimise disconnection/reconnection=> need to withstand fairly extreme weather conditions

• Analysis based on historical environmental data• However - weather is inherently unpredictable and expected limits can be exceeded

• Potential early deterioration of mooring system components or at worst, failure of single or multiple mooring lines.

• Very few have facilities to detect early warning signs of deterioration or impending failure

• Regular inspection campaigns carried out to confirm integrity of mooring system

• Not uncommon for the early signs of failure to be detected during routine inspection

Page 4: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

4DOF Subsea

Mooring System Early Failures

• Many single line failures• Several examples of multiple line failures (wire, chain and/or connections)• Major component failures (yoke, wire, chain, connections)• Vessel drift-off• Subsea hardware and risers damaged or broken, catastrophic failure

RegularInspection

Repair prior to failure

Failure

Inspect damage

Repair

Planned $$ Emergency $$$$$

3-6 months

on station / off-station

Page 5: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Located 80km off the coast of South Taranaki, New Zealand, at the entry to the Cook Strait

• Largest crude oil field in New Zealand• Contributes significantly to the economy and

development of the Taranaki region.

DOF Subsea 5

Case Study - Maari Oil Field

Page 6: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

DOF Subsea 6

Maari field consists of :

• Subsea wells, flowlines & control umbilicals• Maari wellhead platform• FPSO Raroa, 8 leg mooring system

Water depth approx. 100m

Page 7: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

DOF Subsea 7

Each mooring leg comprises :

• Driven anchor pile• Lower 118mm chain section 50m• Lower 110mm wire section 200m / 400m / 500m• Upper 118mm chain section 400m• Upper 110mm wire section 200m

Chain : 118mm studless linksWire : 110mm spiral strand uncoated wire rope

Page 8: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• In February 2013, a 5-year ABS inspection programme was carried out by DOF Subsea Diving Support Vessel Skandi Singapore

• Survey included an ROV survey of the 8 mooring legs• Bird-caging of spiral strand wire mooring rope was observed on mooring legs 1, 2, 3 & 4• Considered likely to effect the capacity of the mooring legs• Subsequent to the inspection, the Upper Wire Section on mooring leg No. 2 parted• Temporary mooring leg installed in Aug 2013 by others

Mooring wire anomalies

Timeline Feb Mar Apr May June July Aug Sep Oct Nov Dec

Page 9: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

Anomalies identified in this area

DOF Subsea 9

Cut & add chain

Cut & reterminate

Page 10: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

10

• Letter of Intent for engineering signed end July 2013• Procedure and tooling review held early August• Method statement developed, design loads calculated – 65-150 tonnes• Design based on 3m significant wave height limit• Concept developed based on an existing (lower capacity) tool previously accepted by the

classification society :

Existing tool (10t pull capacity) New concept (150t pull capacity)

• Orders for long lead hydraulic parts placed immediately

Engineering of Solution

Feb Mar Apr May June July Aug Sep Oct Nov DecTimeline

Page 11: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

DOF Subsea 11

Engineering of Solution

Page 12: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Fabrication of tool awarded to a New Zealand company (New Plymouth)

• Close to port of mobilisation• Fabrication commenced end Aug 2013• Tool completed in 4 weeks• Load and function testing completed 7 weeks after

contract award)

Fabrication

Feb Mar Apr May June July Aug Sep Oct Nov DecTimeline

Page 13: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

DOF Subsea 13

• Built : 2010• Length : 108 m• Beam : 24 m• DP : Class 2• Bollard Pull : 350 t• Chain locker capacity : 1150 m3• Triple drum main winch : 500 t• Heave compensated crane : 140 t• 2 off safe Deck rail cranes : 5t• A-frame : 250 t• Clear Deck Area : 1,070 m2• Accommodation : 90 personnel• ROVs: inbuilt 3,000 m work class ROV + overside

work class ROV (Schilling UHD)

Execution - Skandi Hercules

Page 14: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

DOF Subsea 14

• Depth rating : 3,000 m• Power : 150 HP• Payload capacity : 400 kg• Through frame lift : 3,500 kg• Manipulators :

• 7-function Titan T4• 5-function Rigmaster

Execution – Schilling UHD ROVs

Page 15: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

Feb Mar Apr May June July Aug Sep Oct Nov Dec

Mobilisation - Skandi Hercules

• Vessel contract signed mid August 2013• Hercules mobilised in Singapore 3 weeks later• Constructability Review held early September• Vessel arrived in New Plymouth NZ end September• Final risk assessment held early October

Timeline

Page 16: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Identify location for Upper Chain Section cut subsea• Lift chain section into cutting stand• Cut chain with ROV carbide blade cutter

DOF Subsea 16

Repair Methodology

cut location

Page 17: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Recover FPSO end upper chain section and upper wire section

• Store chain section in vessel chain lockers

DOF Subsea 17

Repair Methodology

Page 18: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Fit recovery clamp to wire• Recover wire to deck & secure• Cut & remove damaged wire• Clean wire end• Re-terminate with new wire socket

DOF Subsea 18

Repair Methodology

Page 19: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Reconnect chain to repaired Upper Wire Section• Deploy chain until end is reached• Fit end of chain through ACCD stroking tool skid and secure in place

DOF Subsea 19

Repair Methodology

Page 20: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Deploy chain and ACCD tool to seabed

DOF Subsea 20

Repair Methodology

Page 21: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Recover other end of mooring line to deck• Attach new length of chain section• Lay end of chain into ANC ACCD tool• Fit H-link to end of chain

DOF Subsea 21

Repair Methodology

Page 22: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Deploy chain and ANC ACCD tool to seabed• Connect 20m tether lines between HYD and ANC

DOF Subsea 22

Repair Methodology

Page 23: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Connect hydraulic downline• Connect crane to chain end• Stroke tool (varied 5- 30m) & recover chain

DOF Subsea 23

Repair Methodology

Page 24: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Once sufficient slack is pulled through, lower chain end link into H-link• Insert H-link pin• Attach locknut.

DOF Subsea 24

Repair Methodology

Page 25: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Release load from ANC tool, remove tethers• Slide ACCD tool off carriages• Recover ACCD tool to deck, recover carriages to deck

DOF Subsea 25

Repair Methodology

Page 26: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

• Remove pins to release ACCD ANC tool• Lift chain off tool• Recover ACCD ANC tool to deck

DOF Subsea 26

Repair Methodology

Page 27: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

All tooling is recovered, leaving only H-links and anchor shackles in the chain leg

DOF Subsea 27

Repair Methodology

Page 28: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

Challenges - Range of Weather

DOF Subsea 28

Leg 2 : 7.5d ops + 6.5d WOW, FPSO in place.Leg 3 : 4d ops + 1d WOWLeg 1 : ~4d ops + 1d WOWLeg 4 : 2.5d ops, no weather downtime.

Page 29: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

Challenges – Visibility at the Seabed

DOF Subsea 29

Page 30: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

Challenges - first leg repaired with FPSO in place

DOF Subsea 30

Page 31: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

Jul Aug Sep Oct Nov

2013 Final risk assessment

Constructability Review

Skandi Hercules mobilised in Singapore

Vessel contract signed

Tooling review

Engineering awarded

Engineering

Tool fabrication

Tool testing

Mobilisation in Taranaki, New Zealand

Offshore works 1 month

Performance - Timeline

Complete14/11/2013

Award31/07/2013

DOF Subsea 31

Learning curve‐‐‐‐‐‐‐‐

Page 32: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

Performance - Safety

DOF Subsea 32

• 1 non-work related injury (rolled ankle climbing out of bunk while vessel in harbour)• 1 first aid case – small cut to finger while cleaning under shelving• Significant amount of deck work• All work performed without divers

Page 33: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

DOF Subsea 33

Key Success Factors

• Proper detailed Engineering assessment

• Competent and experienced team, onshore and offshore

• Preparation – testing, trial fits, site integration tests

• Right assets

Page 34: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

Conclusion

DOF Subsea 34

Fast track repair of FPSO mooring legs can be carried out safely and effectively, without the use of divers, and with the FPSO in place.

Page 35: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

DOF Subsea wish to recognise and thank OMV New Zealand Limited for permitting the use of the material contained within this presentation.

DOF Subsea 35

Acknowledgements

Page 36: Richard Rickett, General Manager Engineering and Procurement … · 2017-12-22 · DOF Subsea 4 Mooring System Early Failures • Many single line failures • Several examples of

DOF Subsea 36

Questions ?

Thank you


Recommended