+ All Categories
Home > Documents > Risk Analysis for Projects with CCS - World...

Risk Analysis for Projects with CCS - World...

Date post: 15-Apr-2020
Category:
Upload: others
View: 7 times
Download: 0 times
Share this document with a friend
54
Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants CCS Alliance for Risk-based Policy in collaboration with Hunton & Williams www.ccsalliance.net Co-Author Maria Dubravka Pineda, Ph.D. CCS Alliance Washington, DC 202-460-8269 [email protected] Presented by: Andrew Paterson CCS Alliance Washington, DC 619-807-3267 [email protected] World Bank Balkans Workshop Dubrovnik 3-5 May 2011 1
Transcript
Page 1: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Risk Analysis for Projects with CCSFactors Affecting Financing for Early Plants

CCS Alliance for Risk-based Policyin collaboration with Hunton & Williams

www.ccsalliance.net

Co-Author

Maria Dubravka Pineda, Ph.D.

CCS Alliance

Washington, DC

202-460-8269

[email protected]

Presented by:

Andrew Paterson

CCS Alliance

Washington, DC

619-807-3267

[email protected]

World Bank Balkans Workshop

Dubrovnik

3-5 May 2011

1

Page 2: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Background: CCS Alliancewww.ccsalliance.net

Focus of the CCS Alliance (started in 2007):

A coalition of entities sharing a common interest in removing impediments to the investment in

and development of projects with CCS. (Rural coops, utilities, insurance, resource companies)

Particularly focused on regulatory requirements regarding financial assurance, site closure

certification, post-closure monitoring, and long-term liability.

Addresses issues regarding the applicability of other federal environmental statutes, project and

pipeline siting authority, subsurface property rights, and other issues.

Promote the development of policy at state and federal levels to address CCS risk and liability

issues appropriately. Work with regional partnerships on state level issues.

Not limited to the power sector; industrial projects are important also for near-term progress.

Efforts and Accomplishments:

Conducted a comprehensive study of risk and legal liability issues, focusing on barriers posed by

existing law and regulatory regimes to the commercial-scale deployment of CCS.

Submitted comments on proposed CCS-related regulatory regimes, including EPA’s proposed

rule for underground injection wells (a new Class VI) under the SDWA.

Communicated key issues to policy-makers regarding the treatment of liability and regulatory

issues under proposed climate change and energy legislation.

Examining the design and impact of a variety of incentives and regulatory approaches that

stimulate investment and commercial deployment. Actively commenting on EPA rule makings.

2

Page 3: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

What if ? (dealing with politics in N.America)

3

Page 4: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

World Bank Workshop on Projects with CCS – Dubrovnik (May 2011)

4

Page 5: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

World Coal Reserves

End of Cheap Coal, Nature 18 Nov 2010

USA and Russia wield the greatest

reserves, followed by China. Those

three countries account for nearly

60% of total reserves, but China is

the leading producer and consumer,

by far now with > 3 billion tons a year.

Australia is the leading exporter,

primarily to Asia.

South America has minimal reserves.

Unlike oil and gas, no new

reserves of coal are expected

to be discovered… but we

know where the coal is.

5

Current annual consumption

= 7 billion tonnes

Why Coal?: Reliable supply, we know where it is, high energy density, not explosive.

Page 6: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

World Coal Production (without China), 2000 – 2010

Source:

EIA

Global coal production is only rising in Asia, and other countries feeding the appetite in Asia: Australia, Indonesia,

and then India for its own consumption. Production is declining in Europe, particularly as gas becomes more available.

China is projected to consume more than 3 billion tons of coal in 2011, rising at 2%-5% a year.

6

EU consumption declining in favor of gas

Higher

production

feeding

growth in

Asia.

Page 7: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Population Growth a Key Factor in Policy Differences

7

Population growth in the NAFTA region is robustly rising, while EU-15, Japan, and Russia are not growing.

Technology Investment:

Growing populations mean

that EE and RE are not

enough. More fossil and

nuclear are needed to

modernize the fleet and

supply plug-in hybrids. NAFTA

EU-27

USA

Russia

EU-15

Japan

Mexico

Canada

Page 8: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Fossil Signal: Tories (blue) Roll to Majority (May 2011)

8

• Tory PM Harper got his

majority, 167 seats total,

a gain of 21 (308 total),

seen as “pro-fossil fuels”.

• The NDP (102) are now

the official opposition.

• The bloc Quebecois were

reduced to 4 seats (from

48) and no longer have

official party status.

• The Liberals lost a vast

number of seats (-43,

down to 34), except in

some Atlantic areas.

• The Green party kept 1

seat (Elizabeth May won

in her riding in Victoria)

http://www.theglobeandmail.com/news/politics/election-results/

Harper, the PM from Calgary SW, remains committed to fossil fuels for N.America.

Page 9: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Initial “Larger Context” Observations

• China, primarily, and then USA and India determine global usage of

coal from here (60% of total), for power and industrial projects. CCS

(or coal use) in the Balkans will not impact climate measurably.

• Just ten countries account for 80% of coal use worldwide.

• Still, CCS (“synthesis) can deliver higher value uses of coal (fuels,

chemicals, steam) versus only burning it for power.

• Think “Carbon Management” -- look at best purposes + biomass

• Burning coal simply for electricity produces little direct export value.

• Industrial and power projects with CCS will be funded with debt,

therefore credit risk evaluation (repayment) drives financing.

• Once used, a nation’s coal resources cannot be recreated, therefore,

garnering more value from coal enhances the nation’s economy.

• CCS is costly AND entails more risks. Liabilities must be addressed.

• The credit crisis remains, placing greater importance on revenues,

management, credit quality, collateral, and efficiencies, not just cost.

• Hence, projects with CCS will require public – private partnerships.

9

Page 10: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

EIA International Energy Outlook 2010 (base case)

The world remains dependent on Fossil Fuels through 2050 (liquids, coal, gas)

Coal remains an expanding portion of energy supply through 2030 (Asia, OECD).

Coal

(Asian growth)

We cannot conserve our way to lower GHG emissions. Energy use is rising, demanding investment.

Rising renewables, but

just to feed new demand,

rather than replace fossil.

Nuclear will hold current

share (with new plants).

10

Page 11: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Also Benefaction: Improve Values of Coal (>50%)

11

K-Fuel®upgrading technology processes low

quality sub-bituminous coal resulting in:

• Higher energy value –Demonstrated to

increase the efficiency and heating value of

sub-bituminous, lignite and brown coals by

30% on average, accomplished by decreasing

equilibrium moisture content by 50%

• Higher economic value –Allows product to

compete with bituminous coals and makes low

rank coal marketable

• Physically and chemically stable product –

Handled/transported as the feed coal

• Reduced transport costs –Reduced moisture

content can lead to lower transportation costs

• More environmentally friendly product –

More efficient burning could lead to lower

carbon emissions, and in particular reduced

Hg, SO2and NOx

The consequence is that a significantly large

number of low quality, high moisture coal deposits

worldwide become economically viable and more

environmentally friendly K-Fuel® is a patented coal technology which upgrades low value sub-bituminous,

lignite and brown coals to high ranking thermal coal quality, for example from

3,500kcal/kg (~6,300BTU/lb) to 5,650kcal/kg (~10,200BTU/lb)

Page 12: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Coal-based Electricity for Europe

12

Page 13: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Lignite and Coal Production

13

Page 14: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Lignite and Coal Production, SE Europe

14

Page 15: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Balkan Overview: Vital Statistics

15

(comparison) Total Estimated Estimated

Greece Balkan Albania Bosnia Croatia Macedonia Serbia Montenegro Kosovo

Population 2010 11.00 23.82 3.00 4.60 4.50 2.00 7.30 0.62 1.80

GDP 2010 (PPP) $306 $243 $23.30 $30.40 $77.70 $19.50 $82.70 $4.10 $5.30

GDP per capita $27,850 $10,202 $7,400 $6,600 $17,330 $9,400 $11,360 $6,600 $2,940

GDP per capita (to Greece) 100% 37% 27% 24% 62% 34% 41% 24% 11%

Sovereign credit rating BB ?? B B B CCC ?? ??

Energy use (000 bbls/day) 414 292 36 26 106 18 90 4 12

Electricity Consumed

(billion KWh)58.3 84.7 6.6 10.8 18.0 8.2 34.1 3.0 4.0

Electricity use per capita 5,300 3,556 2,200 2,348 4,000 4,100 4,671 4,839 2,222

Coal usage (electricity) 50% 45% 3% 60% 5% 70% 65% 30% 50%

Coal power (billion KWh) 29.2 38.4 0.2 6.5 0.9 5.7 22.2 0.9 2.0

% Total of Coal Power 100% 1% 17% 2% 15% 58% 2% 5%

Credit quality is intensifying as issue driving finance going forward.

Page 16: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Key Industrial Sites and Hot Spots

16

http://maps.grida.no/index.cfm?ev

ent=searchFree&q=Macedonia

Page 17: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

WorldBank Balkans Workshop -- notes

• EU offering funding subsidy from New Entrants Reserve (NER 300)

• 22 projects applied (18 in power mode; 4 industrial)

• Damir Pušet: “Capital likes growing markets” (emerging vs. developed)

― In Balkans, 60% of space heating, cooking, is electric (vs gas)

― Old age of plants and networks, many losses

― “Concerns for energy supply are highly expressed.”

― Prices too low – still need to recognize socialization of energy

― Significant potential for wind, biomass, energy efficiency

― Electricity gap causes need for imports, upgrades

― Significant crude refining base already [useful for C-T-L]

― Pipeline connectivity is needed to realize potential for export

― Energy sector itself cannot resolve political / policy challenges

17

Page 18: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

CSLF Structure

POLICY GROUP

Chair: United States

Vice Chair: United Kingdom

Vice Chair: South Africa

TECHNICAL GROUP

Chair: Norway

Vice Chair: Australia

Vice Chair: South Africa

CSLF

SecretariatTask ForcesTask Forces

CSLF Technical Group Reviews Progress of Collaborative Projects

and Identifies Promising Directions for Research• Projects Interaction and Review Team (Australia chair)

• Risk Assessment Task Force (United States chair)

• CCS in Academic Community Task Force (Brazil chair)

18

CCS Alliance has been supporting the CSLF Finance Task Force

Page 19: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Opening Observations for CSLF Finance Roundtable

1. Energy use cannot be curbed as much as GHG emissions by 2030; so,

carbon management (CCS) enables more efficient use of fossil fuels.

2. Commercial plants and projects with CCS are not being built (except with

EOR) for several reasons: not just elevated costs, but higher risks also.

3. Subsidies are NOT enough to get plants built; market uncertainties and

emissions regulations and subsurface rules must be addressed as well.

4. The inherent size of projects with CCS requires debt financing, not venture

capital; therefore, predictable cash flow (debt service) is the top issue.

5. Dealing with just some elevated costs and higher risks of first plants

will not promote commercial deployment. Financing industrial plants

is like a rocket launch: all risks must be addressed.

6. Stove-piping of power, energy and chemicals hinder best use of a broader

industrial base with varying access to capital to deploy CCS.

7. A more resilient 21stC industrial base can be built, by drawing on broader

industrial experience and engineering know-how. Bridging the commercial

gap entails more industrial cross-uses and joint ventures.

(Drilling technology in oil sector to power plant CCS; gasification from chemicals to power)

19

Page 20: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

CSLF Financing Roundtable

6 April 2010, Washington, DC

Photo, B.Frois, Chairman

Page 21: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Landscape for Investment in Energy Projects

Difficult Challenges

Tight credit globally, with stiff

competition for investment

Cheap fossil fuels (natural gas), with

E&P subsidies still intact

High uncertainty about GHG policy

Severe fiscal deficits (local, federal)

Unclear regulatory permitting in some

areas and sectors

Lack of technology operating

performance for many innovations

Cheap, old coal plants still running

(competition for new supply)

Major Opportunities

• Historically low interest rates

• Reduced volatility in market prices with

by reducing imports of feedstock

• Tech pathways exist to fix large GHG

sources by adopting alternatives

• Modernization of industrial base toward a

lower fossil use profile (engineering)

• International cooperation (public and

private) needed to accelerate progress

• Local economic development

• Alternative fuel diversification with

broader domestic utilization provides

better energy security

21

Page 22: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Perspective from Shell (CSLF Financing Roundtable)

Dr. Graeme Sweeney of Shell,

summarized a majority

viewpoint in the roundtable :

1) Fossil fuels will remain

dominant until at least 2050;

so CCS is vital.

2) There are physical limits to

the rate at which new energy

technologies can be deployed.

Structured government

intervention is needed to drive

technology change. Energy

infrastructure takes decades

to turnover: e.g., power plants,

energy-intensive industry,

transmission, buildings,

vehicles, transportation

patterns, city planning.

3) We need policies and

incentives targeted specifically

at CCS to accelerate

deployment, and these policies

and mechanisms need to

adapt as deployment unfolds.

22

Page 23: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Capital Investment is Daunting Requires Debt

Lenders and bondholders will provide the bulk of energy financing to 2030, NOT venture capital,

so a credit risk framework will prevail, focused on predictable, steady cash flows.

$13.6 T $6.3 T $5.5 T

$30 Trillion by 2030

75% of power sector

investment ($13.6 T)

targeted in China,

OECD Europe,

and N.America

23

Page 24: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Societe Generale: Financing Challenges

24

Page 25: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

25

Approach to Business Case Framework

Energy

Project

Development

Timeline

Risk Analysis

of Project

Development

Stages

Rating and

Ranking of

Risks by

Stages

Evaluation,

Application

of Risk

Mitigation

Mechanisms

Fossil projects with CCS cannot

complete financing without a

comprehensive commercial risk

analysis by creditors with debt

financing.

Deployment = debt financing.

[credit risk framework]

$

$

Design & Development

Engineering &Construction

Operations &Maintenance

CloseFinancing

Permitting

and profit

possible

downtime

Regulatory and policy risks

Technical and operating risks

Market risks

$

$

Design & Development

Engineering &Construction

Operations &Maintenance

CloseFinancing

Permitting

and profit

possible

downtime

$

$

Design & Development

Engineering &Construction

Operations &Maintenance

CloseFinancing

Permitting

Revenues and profit

possible

downtime

Regulatory and policy risksRegulatory and policy risks

Technical and operating risksTechnology and operating risks

Market risksMarket and Financial risks

Debt Financing Drives the Framework, not Equity or Venture Capital

Page 26: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Risks Mitigation Approaches Actions Needed

Risk Type Key Risks1) Tech-CCS Capital cost with CCS too high

2) Reg-CCS State rules on CCS not clear

3) …

4) …

Analysis based on Interviews of key actors:

(results of Risk Study)

C) Government

Actions needed

for Mitigation

(Match actions with

mechanisms)

Near-term / Long-term

• Appropriations

• Legislation

• Tax bill

• Regulation

• Agency action

• Executive order

• Reserves (e.g., SPRO)

• Others

B) Mitigation

Mechanisms

Government

• Loan guarantees

• Grants (by DOE, etc.)

• Tax subsidies

• Injection regulations

• Permitting approaches

• Carbon emission rules

• Federal “Energy Bank”

• LT purchase contracts

Industry / Investors

• Insurance / bonding

• Engineering backups

• Long-term contracts

• Site review, feasibility

• Collateral, backup supply

CCS Alliance Scope:

I) Risk Study for CCS Deployment (coal power plants or energy projects with CCS)

II) Legal research on critical issues, risks and formulation of mitigation options

30 Respondents 25 point scale

Category (Q#) Specific Risk

Rated

Severity Relative Value

ALL (34 Qs) Overall Average 10.2 Average

Tech - CCS 7. Capital costs for carbon capture equipment (>50% capture) impair

financing of a new plant. 17.1 High

Policy 18. National policies lack sufficient incentives (loans, tax measures) for first-

of-a-kind plants.16.2 High

Policy - CCS 13. Uncertainty about EPA carbon emission regulations and CCS hampers

permitting on new plant.15.9 High

Policy - CCS 19. National policies (e.g., tax credits) lack sufficient incentives for

sequestration of carbon.15.6 High

Policy - CCS 17. Regional, state policies fail to provide sufficient clarity about CCS

requirements and liability.15.2 High

Policy - CCS 15. Value of (eventual) carbon emission allowances does not adequately

cover costs of CCS.13.9 Above Avg.

Market-CCS 31. EPA regulations on underground injection of CO2 and liability fail to

offer clarity for financing.13.4 Above Avg.

Market-CCS 34. Prospect of liability for long-term leakage of CO2 from CCS threatens

new plant financing.13.3 Above Avg.

Market 28. Financing of new plant proves difficult (e.g., debt tenors too short, more

equity required).13.3 Above Avg.

Market-CCS 33. Revenues from the sale of CO2 (e.g., for EOR) are not adequate to

cover costs of CCS.12.9 Above Avg.

Policy - CCS 16. Regional, state policies fail to provide sufficient incentives to support

plant economics with CCS.12.9 Above Avg.

Market-CCS 27. Market rates or state PUC approved rates do not offer sufficient

recovery of CCS costs.12.8 Above Avg.

Market 23. Current conventional coal plants are allowed to run longer, curbing

demand for new plants.9.7 Average

Tech - CCS 9. The site for CCS could suffer a significant technical failure and more

than minor leakage occurs.7.3 Below Avg

Tech - CCS 11. Transportation of CO2 for CCS proves difficult logistically (e.g., transit

path too long)7.0 Below Avg

Market-CCS 32. Transport costs of CO2 become more costly after new plant is

operating, threatening run time.6.1 Low

Market 24. Natural gas prices drift and stay lower (<$4/MBtu), making the plant

with CCS uncompetitive.5.3 Low

A) Commercial

Risk Analysis

26

Page 27: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Rating Respondents: Sophisticated on CCS Issues

Gasification Technologies Council

Conoco Phillips

GE

Siemens

Air Liquide

Chevron

Excelsior Energy (IPP)

Worley Parsons

CH2M Hill

Burns & McDonnell

Potomac-Hudson Engineering

Oglethorpe Energy

Eastman Chemical

e3Gasification

ZeroGen (Australia)

Arkansas Electric Coop Corp.

National Rural Electric Coop Assoc.

Minnkota Power Coop

Pace Energy Consultants

IEA GHG R&D Programme (London)

Hensley Energy

EPRI

World Coal Institute (WCI)

ICO2N (Canada)

Natural Resources Defense Council

World Resources Institute

Imperial College of London

MIT

U.S. Dept. of Energy (Fossil Energy)

New Energy Finance

27

Page 28: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

0.0 5.0 10.0 15.0 20.0 25.0

High capital cost (w/o CCS)

High labor/operating cost

Excessive downtime, repairs

High cost of basic materials

Constrained EPC capacity

Accident damages plant

Capital costs on CCS high

CCS equipment downtime

CCS site technical failure

"Thin" EPC system warranty

Transport of CO2 difficult

Rating of Risks (probability x impact)

Risk Ratings: TECHNICAL

Deploying CCS creates a large drain on plant production, so capital costs run much higher.

Capital costs spiraled higher

since 2005, but costs are up

for all energy projects.

Respondents expect that

CCS equipment will work,

and do not see CO2

transport as a major issue,

nor do they see a storage

site failure as likely with

sound site characterization.

CAPITAL COST is the major

issue (including parasitic

load for CCS compression),

not operating costs.

average

30 respondents

CCS related

Interesting

“lows”

Spring 2008

28

Page 29: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

0.0 5.0 10.0 15.0 20.0 25.0

State air permitting delays

Uncertain EPA carbon regs

Future carbon limits tighter

CO2 allowances don't fund CCS

Regional support lags on plants

State regs on CCS not clear

Nat'l subsidies lag on plants

Nat'l incentives for CCS lacking

Water use regs tightened

Rating of Risks (probability x impact)

Risk Ratings: REGULATORY / POLICY

Regulatory uncertainties (federal + state) about CCS costs and liability threaten financing.

averageOvercoming higher costs is

essential but not enough.

Subsidies are needed.

Regulatory uncertainties

pose “show stopper risks”:

- Carbon legislation and EPA

performance standards are

not defined.

- State regs are not clear

enough yet to resolve CCS

cost and liability issues.

- Incentives are not in place

to offset CCS costs.

A tightening of water regs

needs to be monitored.

30 respondents

CCS related

Interesting

“lows”

Spring 2008

29

Page 30: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

0.0 5.0 10.0 15.0 20.0 25.0

Long-term demand falls short

Coal transport erosion, hitches

Old, cheap coal units run longer

NGas prices decline (<$4/Mbtu)

Coal prices rise markedly

Interest rates rise (to 2012)

Market/PUC rates low for CCS

Finance difficult (equity, terms)

Transmission congestion

Customers breach off-take

EPA regs unclear on CCS

Transport of CO2 expensive

EOR revenue inadequate for CCS

CCS liability threatens financing

Rating of Risks (probability x impact)

Risk Ratings: MARKET & FINANCE

Lack of subsidies and uncertainty about liability for CCS make financing very difficult.

Low natural gas prices in some regions also make energy with CCS less competitive.

“First mover” risks on early

plants are prohibitive for

owner utilities, bond

holders, or PUCs; and

engineering firms cannot

economically offer enough

warranty (or “wrap”) to

cover risks feasibly.

EOR / EGR is not readily

available in all regions, or

volumes are not adequate

to offset costs of carbon

capture and storage.

Clarity is needed on CCS

liability to close financing.

average

30 respondents

CCS related

Interesting

“lows”

Spring 2008

30

Page 31: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Overview of Business Case Critical Risks

# Risk Type Business Case Risk Description EU N.Am Asia

1 Tech Capital costs (+ parasitic load) with CCS run too high relative to competing baseload High High High

2 Policy Electricity rate regulation fails to offer dispatch preference or incentives for CCS High High High

3 Mkt / Fin Credit financing constraints result in difficult terms (more equity, short debt tenor) High High Med

4 Policy Uncertain regulation on CO2 emissions results in low economic value for CCS Low High High

5 Mkt / Fin Natural gas prices remain lower making coal with CCS uneconomic Med High Med

6 Policy Incentives for CCS operations (allowances, tax credits) are inadequate for costs Med Med High

7 Mkt / Fin Volatility of (or lack of) carbon allowance prices hinders financing Med High Low

8 Policy Water use regulations threaten coal plant operations with CCS (shutdowns) Med Med Med

9 Policy Lack of clarity about liability for long-term stewardship of CCS hinders financing Low High Low

10 Mkt / Fin Long-term demand growth fails to justify investment in baseload units High Low Low

11 Tech Technical performance problems lead to excessive repairs and downtime Med Med Low

12 Policy Older coal units are allowed to run longer posing competitive challenges Low Med Low

13 Mkt / Fin Imported coal prices rise or see more volatility raising costs Med Low Low

14 Tech Transport of CO2 proves too costly or logistically difficult Med Low Low

15 Policy Lack of public recognition or acceptance of value of CCS hinders permitting Med Low Low

16 Tech Injection and storage encounters operating problems triggering higher costs Med Low Low

17 Mkt / Fin Interest rates rise threatening financing terms and costs Low Low Low

Some of the risks vary based on the market and policy differences by region; other risks are common across regions.

31

Page 32: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Example: U.S. Risk Ratings on CCS

Concerns about capital costs remain high, primarily because of parasitic load.

Low NGas prices (<$6/MBtu) since late 2008 pose larger competitive problems.

Subsidies are needed to overcome higher costs, but that is not enough.

(e.g., “Boucher bill” proposes to pay for subsidies with a wires charge on coal, fossil fuels)

Regulatory uncertainties pose “show stopper” risks for deployment of CCS:

U.S. EPA regulatory rules (UIC) on CCS are not defined, but are in process.

The outlook for GHG/carbon emission legislation is more uncertain despite passage of the

House bill… in other words; more questions about rule-makings were raised !

But, without a cap of some form, utility commissioners face little prudence to consider CCS.

State regulations are not clear enough yet to fully resolve CCS cost and liability issues.

Incentives (tax credits, loans, allowances) are not enough to offset higher CCS costs.

A tightening of water regulations does not appear to pose much of a risk, but monitor this.

“First mover” risks are prohibitive for owner utilities, bondholders, or PUCs; and

engineering firms cannot economically offer enough warranty (or “wrap”) to cover

risks. Few owners want to finance early CCS demos and plants.

Respondents expect that CCS equipment will work, and do not see CO2 transport as

a showstopper issue, nor do they see a CCS site failure as likely.

Clarity is needed on CCS liability to close financing – perhaps a “showstopper”.

Increases in coal prices or transport costs were not rated high risks.

32

Page 33: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Current Landscape: Challenges to Financing

The credit crisis deeply damaged project finance (no balance sheet), but at

least interest rates are low… for now.

Imported energy aggravates trade deficits and currency instability.

The fossil price roller coaster in 2008 increases revenue uncertainties, and a

reversal in oil and gas investment could trigger more volatility.

Volatile revenues (market prices) make debt financing extremely difficult.(and carbon trading increases volatility of energy pricing, compared to more stable tax policies).

Many alternative technologies have not achieved scale yet.

Intermittent nature of some renewable energy options poses physical limits

Conventional fossil-based sources wield a vast, already depreciated capital

investment advantage – but face expansion problems.

Regional differences on energy are severe, further fragmenting markets

State budgets are in deficit and will not rebound soon, hampering options.

The depth of the federal deficit demands that some subsidies be repaid.

Financing domestic-based energy resources is one of the best hedges a

country can make.

33

Page 34: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Commercial Scale Projects with CCS: Key Elements

Risk Analysis rooted in Project Structure

34

Public Sector

Policies

Page 35: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Mitigation Mechanisms vs. Critical Commercial Risks

35

Governments wield a variety of tools or mechanisms for mitigating critical risks. Subsidies cost the treasury more,

whereas, permitting preferences or liability coverage may address other risks more directly. In North America some

mechanisms are carried out at the state level (e.g., rate boosts or permitting) more than at the federal level.

Page 36: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Public Private Partnerships (PPP) Evolve

PPP 1.0: Subsidies

Grants and tax credits or

feed-in tarriffs – basic

subsidies (“throw money at

it”) with bids by private

projects, demonstration

phase mostly; minimal

attention to regulatory issues

or risk analysis.

PPP 2.0: Subsidies +

Regulatory Reform

Grants and subsidies coupled

with regulatory reform (e.g.,

emissions rules, site

characterization, CO2 injection

regulations, long-term liability

rules, etc.).

Debt investors, in particular,

demand regulatory clarity.

PPP 3.0: Risk-based Subsidies

+ Regulatory Reform, Negotiated

Subsidies + Regulatory measures +

Risk analysis with credit support

(loan guarantees; government

preferred equity possibly; insurance

or transferrable trust funds).

Requires more in-depth negotiation

between public agencies and private

projects and investors on specific

risk-oriented instruments.

System performance guarantees

remain a crucial mechanism, which

may require public sector support for

early projects.

Enough support to enable financing.

Built around tax policy

or feed-in tariffs.

Engages parliaments

and regulatory agencies

Engages parliaments and

requires training with

energy and regulatory

agencies (federal, local)

36

Page 37: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Public Private Partnerships are not easy…

Page 38: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Public-Private Funding Models: Key Elements

Government• GHG policy

• Siting regulations

• Performance Standards

• R&D / Tech cooperation

• Demonstration & FEED

• Monetary incentives- Tax measures, FITs

- Allowances

- Green bonds

• Energy/Elec. rates

Industry & Investors• Property investment

• Feedstock & infrastructure

• Monetizing cost / benefit

• Engineering & Innovation

• System integration

• Training, education

• Debt / Equity financing

• Insurance; trust funds

• Market presence

“Trigger points”

for mobilizing capital

FUNDING MODELS

- Public utility

- Private project

- Hybrids… others

Finance Roundtable Dialog

“Reliable energy from

secure supply with

environmental

stewardship”

CSLF(IEA, G20,

other forums)

38

Page 39: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Policy Response Uncertainties (in supply and demand)

Renewables will not offset new demand, let alone replace old capacity.

End-use energy efficiency will be difficult because consumers don’t tolerate price

increases well and change behavior slowly (in NAFTA).

Transmission costs and resistance will hinder renewables (wind, solar) somewhat.

Biomass power and fuels face local and regional supply challenges.

Off-shore wind is proving more expensive and riskier (more maintenance, etc.).

Not all the nuclear reactors needed for carbon savings can be built physically.

“Electricity competition” (or liberalization) is proving difficult.

Access to shale gas bounty faces some regulatory hurdles.

Will Russia make investments needed to deliver gas to EU (or to Asia) ?

Rotating the vehicle fleet takes 30+ years; consumer acceptance is difficult to gauge.

Retooling takes decades and auto makers face substantial credit constraints to

manufacture plug-in hybrids.

Urban planning and new traffic infrastructure will take two generations.

State and federal financing capacities are under severe strain.

39

Page 40: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Balkans: Need for Development >> GHG Savings

• Balkan countries are more than 50% below EU-15 in energy use

• Holding them to a 1990 baseline of energy use stifles development

IDEA: Give Balkan and other transition economies a 1990 baseline of

EU-15 per capita energy and electric consumption

• Allows more flexibility in modernizing energy and electric sectors

• Enables use of more efficient, better performing technologies

• More modern infrastructure is ultimately more efficient for EU-35…

• Also allows investments to be more competitive in longer term

• Could bolster regional “resilience” to energy supply disruptions

• Improves value of EU-wide connectivity (electric, pipelines, supply)

• Provides superior employment and development options

40

Page 41: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Discussion

41

Page 42: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Strategic Option: Co-Production (Fuels + Power) with CCS

Investment Analysis:

• Co-production plants provide BOTH fuels

and power, offering better economics … if

oil is >€60 or $80.

• Provides a higher value export than

electricity with development dividends.

• Offers strategic national value by

expanding domestic supply.

• Carbon capture is performed to make the

fuels. Power is generated from heat

recapture to steam turbines.

• Burning syngas (H2 + CO) is an economic

reversal – why burn valuable inventory ?

• Some risks are higher: such as capital

cost recovery, and complexity of

operations, CCS liability.

• But, some risks are lower, e.g., ability to

stockpile production, access to broader

market than a dedicated power plant.

42

Joint study led by U.S. DOE with DOD, EPRI, U.S. EPA, 2006-7

http://www.climatevision.gov/pdfs/Co-Production_Report.pdf

Page 43: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Concerns about Future Oil Supply Remain

43

?

Expanding need for liquid fuel supply (LDC growth), plus EOR…

Page 44: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Strategic Option: Co-Production (Fuels + Power) with CCS

44

Joint study led by U.S. DOE with DOD, EPRI, U.S. EPA, 2006-7

For a 32,500 bbls per day plant ($3.7B with financing costs and CC&C). Using 18,000 tons per day of bituminous coal

(or 33.600 tons of lignite). Carbon capture would be operating 90% of the time at an effective level of 80%. Electricity

co-production was sold at $58/MWh with a 19% IRR allowed to fund a 70/30 debt / equity structure.

The model entails use of 8 gasifier trains for lignite (6 gasifiers for bituminous coal), rotating O&M to optimize run time.

Incentives modeled include grants, tax subsidies for capital and for operations, plus government loan guarantees.

A most effective combination: an early stage grant ($200M), plus a loan and excise tax based on carbon capture, with

EOR (of $12/ton). Off-take agreements or rate-basing of the electricity also improve the credit profile of the project.

Page 45: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Strategic Option: Co-Production (Fuels + Power) with CCS

45

Joint study led by U.S. DOE with DOD, EPRI, U.S. EPA, 2006-7

Page 46: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Value of Gasification (CTL)

46

Gasification is more costly, but provides more strategic / economic values.

Page 47: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

SASOL: Healthy Business Model on CTL

47

SASOL remains one of the leading enterprises for coal conversion, and is doing well financially.

Revenues have run up to $16B annually, and the enterprise value has risen to $30B.

Page 48: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

… or you can just burn the Coal

48

Mere combustion is easiest, but fails to provide many strategic options.

Countries can pursue combustion and gasification in parallel.

Page 49: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Balkan Coal Profiles

49

Page 50: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

World Bank Workshop on Projects with CCS – Dubrovnik (May 2011)

50

Page 51: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Serbia

51

Page 52: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Bosnia

52

Page 53: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Greece

53

Page 54: Risk Analysis for Projects with CCS - World Banksiteresources.worldbank.org/EXTENERGY2/Resources/...Risk Analysis for Projects with CCS Factors Affecting Financing for Early Plants

Business Case: Key Financing Factors

Essential “Business Case” Term Sheet elements to address financing include:

1) Strong customer profile for revenues, say, in the form of stable wholesale energy markets,

or of creditworthy industrial off-takers, possibly even with rate guarantees (power projects).

2) Long-term agreements for feedstock or vital supplies, preferably with multiple sources, or

other sources of stability of supply commensurate with the state of the host energy market

3) Technology systems with demonstration and performance data at larger scale

4) An experienced EPC / engineering contractor identified, ideally engaged with incentives

5) Well-detailed construction and project baseline schedule and budget to contain overruns

6) Site control for both the commercial plant and the CCS operations

7) Competitive economics and good debt coverage for given debt with additional subsidies

(feed-in tariffs, tax credits, repayment options, etc.) and regional development impact

8) Equity backing already engaged, supplemented with public sector investment subsidies

9) Advantageous site features with evidence of community support and government backing

10) Project permitting initiated (air, water, land use, storage etc.) with a clear track for

approvals, and pollutant savings with a clear methodology accepted by regulators

11) Insurance for critical events and force majeure incidents and first losses on CCS activities

12) Capable management team with a track record in sector at scale for such projects.

Balkans

??

54


Recommended