ROI AND TCO: TWO WINNING FACTORS FOR ANY DEAL
Randeep SinghAshwani Kumar SinglaHCL Commet
2012 EMC Proven Professional Knowledge Sharing 2
Table of Contents Abstract ........................................................................................................................... 3
Introduction ..................................................................................................................... 5
Return on Investment (ROI) ......................................................................................... 5
Total Cost of Ownership (TCO) .................................................................................... 6
ROI and TCO Common Factors ................................................................................... 6
Compute/Server Technology (Rack, Blade, and Cisco UCS) .......................................... 7
Network ......................................................................................................................... 13
Storage and Backup ...................................................................................................... 18
Virtualization ................................................................................................................. 24
Data Center Facilities and Hosting ................................................................................ 38
Cloud ............................................................................................................................ 45
Conclusion .................................................................................................................... 55
Appendix: Bibliography .................................................................................................. 56
Disclaimer: The views, processes, or methodologies published in this article are those of the authors. They do not necessarily reflect EMC Corporation’s views, processes, or methodologies.
2012 EMC Proven Professional Knowledge Sharing 3
Abstract Technology, the lifeblood of today’s business, is undergoing rapid and constant change
with a plethora of technologies being launched every day. As a result of this rapid
evolution, today’s IT environment has grown much more complex while business
objectives and expectations have remained the same. Economies associated with
today’s information demand that IT managers enhance the business value of existing
and planned IT investments while simultaneously reducing the costs of IT operations.
However, the challenge remains the same; how to reduce business cost and business
pressure driving the technology for IT.
IT is facing immense pressure to reduce costs without impacting critical services
delivery. IT has taken some recent initiatives by introducing activities that will reduce
cost that will result in operating expense savings very specific to the infrastructure
(compute, network, storage etc.). Thus, it becomes a need of hour to reduce the
inefficiencies that result from the growth of distributed infrastructure, thereby resulting in
more and more demand for high cost resources. We need to address this distributed IT
infrastructure management issue to reduce the overall operating expenses of IT.
Lowering IT costs does not equate to purchasing low cost solutions to reduce OPEX or
improve TCO. Purchasing cheaper solutions to reduce short-term CAPEX can produce a
negative long-term impact on OPEX. It’s important to understand that price never
equates to cost. Solutions that are centralized and managed in a consistent and well-
structured manner are less expensive. Even when compared against widely distributed
solutions, management of such solutions is cheaper.
Solutions—whether they are enterprise, modular, or small—will continue to experience
price erosion, but OPEX-sensitive architects and managers are looking with interest at
total solutions that can reduce ownership costs, while enabling the deployment of new
solutions and strategies to support business requirements. A holistic approach toward
different technology and cost components is important and there is significant potential
to impact the bottom line by controlling these technology levers.
In this Knowledge Sharing article, we present a comprehensive methodology that will
help IT organizations reduce Total Cost of Ownership (TCO) and ensure higher Return
on Investment (ROI) by implementing any of the technologies and solutions mentioned
2012 EMC Proven Professional Knowledge Sharing 4
below. This will help us to quantify the cost drivers of IT infrastructure and analyze how
much savings remain hidden in the IT infrastructure. We hope this article will help IT
professionals reduce TCO of their IT solutions using techniques that will be described in
detail in the following categories.
• Compute
• Network
• Storage and Backup
• Virtualization
• Data Center and Hosting Costs
• Cloud
The fact is that most of the IT budget is spent on infrastructure costs and most of this
spending goes into daily operations, migrations, upgrades, and so forth. On average,
less than 20% of budget goes toward innovation. Thus, it is very critical to utilize this
remaining average (<20%) as best we can and optimize the infrastructure utilization by
consolidating assets, improving utilization, and making the business more resilient and
agile. That will ultimately achieve results; ROI reduction and achieving better TCO for
the IT environment.
This article will focus on concepts and experiences rather than products, so that when
applying the fundamentals or principles mentioned on any technology, business can
drive benefits.
Figures associated with TCO and ROI are derived from a sample of business cases the
authors have worked on in the past. The numbers represented are sometimes case-
specific and are derived from these business cases with specific factors taken into
consideration. There can be more factors that might vary the cost depending on the
priority and scale of each environment; however, efforts have been made to cover
maximum factors per author’s experience and study that are essential for delivering a
good combination of TCO and ROI.
2012 EMC Proven Professional Knowledge Sharing 5
Introduction What is the difference between TCO and ROI? They appear quite similar. However,
these two terms fundamentally differ based on decisions one is actually going to make.
Let’s first understand the ROI and TCO definitions and their comparison before going
further into details.
Return on Investment (ROI) First, ROI becomes an efficient process whenever existing technology or processes or
activities are going to be replaced by new or next generation technology/ process/
activities. CEOs have always paid close attention to ROI, asking how much ROI they are
going to get against the investment they are going to make. No matter how much cash is
in a CEO’s pocket, CEOs typically claim a limited cash amount for investment.
Additionally, even with that limited cash, the CEO wants every benefit for the
organization, making it even more difficult to convince a CEO to make the investment.
However, if you can show the return on investment that your solution can provide, the
CEO becomes ready to invest to enhance the IT environment. Hence, it becomes
necessary to define each of the investment options to the respective return on
investment.
New IT infrastructure requests must be considered in light of its ROI. No matter the
multiple technical solutions to the same problem (such as different topologies or
protocols), each option will exhibit different return on investment. Basic ROI analysis
always has to answer the following three questions:
1. How much investment?
2. When will I get payback?
3. Total or net savings against investment?
It becomes very necessary to demonstrate to the business management team of any IT
organization that even with the ability of existing infrastructure to meet existing needs
(Case of Existing Customer), changing existing architecture to new architecture can
provide positive ROI because of the reduction in OPEX in many cost-sensitive areas.
Consequently, ROI demonstration is becoming crucial for existing or new customers. If
one must reduce OPEX costs associated with components, ROI analysis becomes the
justification point.
2012 EMC Proven Professional Knowledge Sharing 6
Total Cost of Ownership (TCO) Total cost of ownership (TCO) is reactive, the opposite of ROI (proactive). To calculate
projected costs of competitive solutions that need to be compared, TCO is the obvious
choice. TCO is a financial estimate whose purpose is to help consumers and enterprise
managers determine direct and indirect costs of a product or system. When determining
TCO, several costs associated with an infrastructure solution must be considered that
will cater over coming years. A few are highlighted below:
• IT components and services such as hardware, software, installation, migration, and so
forth that need to be purchased from the vendor.
• Installation and training costs associated with new solutions.
• Write-off costs if the systems being replaced are not fully depreciated or are not at the
end of the lease term.
• Data Center Hosting costs such as power, cooling or air conditioning, and floor space.
• Maintenance costs associated with expired warranty hardware and software.
• Ongoing management, labor costs, and vendor fees not otherwise covered.
TCO becomes more effective in scenarios/cases where we are doing a like-to-like
comparison of two or more solutions which are compared in terms of vendor, topology,
or technical architecture. Looking at best practices mentioned in various TCO analyses,
95-98% indicate that TCO requirements are included in all competitive bid situations,
while deciding parameters for TCO cost analysis will be chosen by the customer.
One-time cost or CAPEX has never been a deciding factor in a way that one can say
that I assume low TCO since the purchase price is lower. One-time cost can never
define TCO. Not only must lowest price be considered, competitive solutions always
need to be considered as well when doing TCO analysis since this will allow
management to choose a solution with confidence since, based on the same parameters
set for different competitors, it is known which solution is going to lower TCO.
ROI and TCO Common Factors While doing ROI and TCO calculations, we come across many calculation parameters
common across both terms. This article will outline the areas or parameters where we
2012 EMC Proven Professional Knowledge Sharing 7
need to apply the costs while performing TCO/ROI calculations/analysis. Once the areas
or parameters are identified, defined, and described, they can be used to compare
different-different solutions/topologies/vendors and select the best one.
In today’s IT environment, IT managers are under great pressure to evaluate all areas of
IT solutions to gain improvements, increase efficiency, and reduce cost. Investment in
people/labor/capital/ processes is always required to achieve benefits such as reduced
costs; however, these costs can be identified, prioritized first, and recovered against the
investment made. Technology specific- and operationally efficient-specific investments
have always been smaller than against ROI they deliver. At the same time, it enables IT
with new IT infrastructure solutions that offer technical benefits.
Compute/Server Technology (Rack, Blade, and Cisco UCS)
For the typical enterprise, growth in customer base, staff, and revenues strains existing
IT infrastructure. Companies expanding their infrastructure to meet the needs of
customers and employees alike look for solutions that solve their immediate needs and
prepare them for long-term expansion. Organizations need affordable solutions that are
easy to manage and easy to grow, yet allow control of IT costs for years to come.
Most mid-sized businesses are aware of blade server technology and know that blade
servers have been widely adopted by enterprises to save space in the data center. What
they don't realize is that the same blade technology that's helping large companies
increase density and save space may be just the solution they've been looking for to
address their own IT expansion needs.
In this article, we'll explain what blade servers are. We'll discuss the unique benefits they
can deliver to medium-sized companies, and help them determine whether or not they're
the right solution for their specific business.
The term "blade server" is often misused and frequently misunderstood. A blade server
is a compact, high-density server that has its own CPU and memory, but that shares
networking cables, switches, power, and storage with other blade servers in an
enclosure designed specifically to house and manage them. The servers, the enclosure,
and all the components of the integrated rack work together to provide seamless, unit-
increasing efficiency and reduce costs by eliminating many of the overlapping resources
often required to run stacks of individual rack servers. So, although the term "blade
2012 EMC Proven Professional Knowledge Sharing 8
server" is often used when talking about blade technology, the reality is that the servers
themselves are just one part of a larger system, sold as a unit and designed to provide
businesses with greater density, simplified management, and easy, affordable
expansion. Benefits of blade servers are:
Figure 1: Blade Server Benefits
While large enterprises initially adopted blade servers as they fulfilled high performance
computing (HPC) requirements, medium-sized businesses often considered blade
technology as either more complex or more expensive depending on their needs.
However, this thinking is exactly opposite. Enterprises have benefited from blade servers
because their high density enables efficient use of data center space, and can be easily
clustered as well. The primary benefits of blade servers to the enterprise are a
combination of simplicity, flexibility, and affordability, making them the best components
to consider in any IT infrastructure solution for business. Many businesses have relied
on rack-mount servers as well—and have for years—to meet their IT infrastructure
needs However, when taking needs/circumstances into consideration, blade servers
offer a better solution. Business enterprises with the following constraints find that blade
servers fulfill their needs in a way that no way rack-mounted server can achieve.
This is because the underlying function remains the same for blade servers as for rack
servers.
Additional advantages are much greater for growing businesses if they opt for blade
servers: Some of the benefits are:
Physical Space LimitationsIT Resource RestrictionsCommercial Constraints
2012 EMC Proven Professional Knowledge Sharing 9
Physical Advantages Shared resources—for example, power, cooling, and cabling—are examples of physical
advantages offered by blade servers.
Power: Power consumption per unit is significantly reduced. Chassis offer reduced
power consumption and higher availability; reduction in power cables required for server
and network architecture.
Cable complexity: Network connectivity within the shared enclosure has reduced the
cabling requirement significantly, roughly around 85% less cabling compared to rack
servers, and per 10/100/1000 network port, saving around $120-$330. At the same time,
storage port cabling and switching costs are also reduced as are future modification
costs. Graphical user interface is another benefit offered by blade servers eliminating
keyboard, mouse, and video (KVM) requirements. All told, reduction in cables and
switches saves roughly $30000 (USD) per rack server.
Size and Density: Compact and small, blade servers require less floor space compared
to rack servers; integrated design offers higher density, making blade servers easy to
deploy and service.
Operational cost savings Easier to manage. Reducing the number of physical resources with which to physically
interact requires fewer staff—and less staff time.
Combining networking components, servers, and shared storage, blade servers can
reduce the need to physically interact with the growing number of individual devices in
your environment, enabling existing staff to do more in less time.
Less Floor SpaceLess Power
Lesser Operating CostEasier ManagementIntegrated Approach
Easy to Deploy and ChangeAffordable
ScalableIdeal for Limited Resources Business Units
2012 EMC Proven Professional Knowledge Sharing 10
A few of the specific ways blade servers streamline system management include:
Setup: Expanding blade servers is easier and saves time; typical time is around 20-30
minutes compared to 8-12 hours for rack server.
Ongoing Operations: Advanced management tools, single screen, quickly create and
deploy resources to automate, and simplifying administrative tasks based on business
requirements make blade servers an obvious choice.
Remote Operations: Remote office administrative tasks, i.e. management; adding
blade servers can be handled from a centralized location, eliminating need for a
dedicated person at each remote site.
Availability Redundant power subsystems, VLAN switches, backplane data paths, storage
interconnects, cooling fans, and hot swap power are examples of improved availability
compared to rack servers. Upgrading components in blade servers (RAM, CPU, even
physically replacing a server) does not require recabling as they can be individually
removed from the enclosure, upgraded, repaired, and replaced, reducing downtime.
Acquisition cost Blade servers offer an integrated system for components such as management
software, OS, SAN components, mouse, keyboard, monitor, and other redundant
features, resulting in lesser acquisition costs as compared to rack servers.
Figure 2 and Figure 3 provide an example business case we had designed for a SMB
customer. The figures show a comparison of the total cost of using rack mount versus
blade servers over a period of five years. Please note that we have not specified the
technology implemented in this case as this article is more oriented across principles
rather than technology:
2012 EMC Proven Professional Knowledge Sharing 11
Figure 2: Blade Server TCO Figure 3: Blade Server Cost Savings
As scale increases, so do savings. Cost effectiveness will be greater if the IT
environment is bigger itself, thereby yielding maximum benefits. There is no doubt that
blade servers play a cost effective role in today’s environment deriving the maximum
benefit one can get out of its IT environment.
To further enhance cost effectiveness, Cisco’s Unified Computing Platform (UCS)
reduces TCO by providing a unified environment; a combination of compute, network,
storage, and virtualization. Business agility also increases with the Cisco UCS solution.
A high-level example of traditional server and networking architecture comparison
against Cisco UCS—which came out while creating a business case for another
customer—is shown in Figure 4.
Figure 4: Cisco UCS Benefits
Component Servers CablesTraditional Server And Networking Architecture 6 Rack Servers 30
Cisco UCS Architecture 24 Blade Servers 32Aditional 8 blade servers will only require 4 additional cables
2012 EMC Proven Professional Knowledge Sharing 12
Benefits Associated with Cisco UCS
Benefits DescriptionIT Adminstrative and Hardware Costs Reduction Time and effort reduced to manage the data center
Network port and Switch Cost
Reduction of IP and FC ports is one of the major savings that are required to connect into the data center using UCS. Its simplified structure reduces time and effort, at same time reducing capital expenditure. This category focus is
on measuring the capital expenditure reductionRefresh Cost Indicate the hardware refreshes cost that was avoided
Power and Cooling Costs Reduction Indicate the comparison in power and cooling costs between the UCS architecture and traditional server-network architecture
Reduction in Electrical circuits deployed Indicate reduction in power outlets necessary for the new UCS hardware versus the outlets required to support the original environment and growth.
Data center Space Cost Savings Indicate the reduction in data center space after implementing UCS.
End user Productivity Savings Indicate an improvement in end user productivity when organizations reduced the number of planned and unplanned downtimes
UCS hardware, License, and Annual Maintenance Costs Indicate the investment in UCS hardware license fee and the annual maintenance cost
UCS Port and Switch Costs Indicate the investment in switches and ports required to run UCS.
Implementation Costs Indicate the IT staff time allocated to discovery, testing, and deployment of Cisco UCS.
Training Costs Indicate the investment made to attend third-party training course for UCS.
Professional Services Investment Indicate the investment for a member of the Cisco professional services team to be on-site during initial implementation of UCS
2012 EMC Proven Professional Knowledge Sharing 13
Network In today’s business environment, underlying complexity managed by one, right network
can be a powerful base for growth and competitive differentiation compared to traditional
network. The right network will keep expanding across the users, devices, applications
and locations even beyond anything.
In the past, IP was considered the technology to bring together multiple distributed
networks. Consolidation of multiple networks onto a single IP-based network has
enabled organizations to streamline their business along with IT operations. While
significant benefits and savings were notable, the changes required significant effort as
well.
In today’s IT environment, network evolution is becoming necessary to intelligently and
efficiently support new business objectives and user requirements. To flexibly adapt to
new technology trends, efficient operations must be introduced via next-generation
network architecture, similar to what the IP network did when it came into existence. A
good TCO model should include costs associated with hardware and software,
installation, licensing, and support and maintenance, as well as financing options. It must
also include operational expenditure (OPEX) costs—for example, deployment, power,
training, testing, training costs, and upgrade costs. Additionally, the impact of service
growth and the network expansion over the coming years required to support the growth
must be covered by a TCO model.
Traditional data center networks may require up to eight discrete ports and cables for
each physical server in a VMware-type deployment. Meanwhile, the blade chassis has
evolved over quite some time as well. However, when comparing blade servers with
traditional architecture, they are still the same in that they require multiple separate
Ethernet-FC connectors and cables from the chassis. Such is not the case with Cisco’s
unified architecture approach.
Cisco enables converged networking using its Unified Fabric offering, which allows traffic
for all server requirements (also FC, FCoE, iSCSI, NAS, and HPC) using a single cable
that provides a low latency, no-loss Ethernet connection. TCO is lowered by a reduction
in cabling complexity, installation, maintenance, configuration costs, and ports required,
resulting in a lesser number of switches required.
2012 EMC Proven Professional Knowledge Sharing 14
Unlike traditional blade server architectures, Cisco UCS blades eliminate the
requirement of buying extra switches along with the chassis. This results in significantly
reducing cost and complexity associated with management. Unified Fabric interconnects
make the entire management domain look like a single system to upstream Ethernet and
FC switches, simplifying Layer 2 management and FC network configuration. This virtual
blade chassis concept is a compelling architectural differentiator for Cisco UCS. This
architecture also delivers predictable and dependable network latency between all
servers (rack and blade) throughout the “virtual chassis’” versus current competitive
designs which have variable latency between blades depending on where they reside in
the various multiple chassis. Converged networking results in increased network
performance through the elimination of protocol conversions between FC and Ethernet
devices in addition to predictable latency that is vitally important for critical application
performance.
Consider this example: Compare 3-year costs associated with a 500 server data center.
Costs for an unconsolidated environment approximate $4.5M; whereas a consolidated
network based on a Nexus 5000 would cost an estimated $3.0M, resulting in a total of
$1.5M savings over 3 years (Figure 5). These calculations take into account network
hardware, cable installation, and power costs.
Figure 5: TCO Comparison
Various organizations have used the concept of ROI and TCO fundamentals to calculate
the costs associated with infrastructure components (network/other), and at the same
time show business the associated benefits and cost savings against the investment
business is going to make. There has always been pressure from the business side in
any IT environment. This pressure is primarily to reduce costs associated with
2012 EMC Proven Professional Knowledge Sharing 15
infrastructure, with more than 50% of the total cost of ownership going toward
management and labor costs. A good point of Cisco’s approach is that it does not
evaluate its TCO itself; instead it uses a third-party to develop a TCO model for them
that will help them measure benefits that a business will derive from a Cisco network
solution.
The results were categorized into four areas, summarized in Figure 6.
Figure 6: Total cost of Ownership Considerations
If we look at results, they clearly indicate that purchase price is always higher for the
Cisco solution. However if we look at associated labor costs, there are significant labor
savings that offset these costs. Architectural benefits associated with Cisco TCO have
been significant as well.
CapEx and Network TCO Network TCO comprises the initial purchase price of a standardized, basic network
design, plus the lifetime costs of labor, maintenance services, and energy costs. The
baseline network TCO considered the lowest-cost solutions to meet network
requirements from Cisco and other vendors. In this baseline, the research revealed that
despite a Cisco price premium, the TCO difference over the lifetime of the network was
at most 7%. These comparisons assume equal and undifferentiated functionality—a
network that is “good enough.” But Cisco networks deliver far more capability: capability
that is only captured in an architectural TCO.
2012 EMC Proven Professional Knowledge Sharing 16
Architectural TCO Architectural TCO takes into consideration the measurable advantages that a next-
generation network can deliver. Analyzing customer data in the TCO model revealed
that Cisco delivers up to 13% lower TCO than competing networks. TCO savings in this
model included IT savings related to labor and operations, as well as non-labor savings
such as reduced energy costs and longer deployment lifespans.
Some IT decision makers interviewed indicated that not all TCO savings could be
credited to their organization. For example, some IT departments indicated they
operated on fixed asset depreciation schedules or product refresh cycles. Cisco TCO
was 1% lower than other solutions when extended lifecycle investment protection was
taken into consideration. Some customers also indicated that energy savings could not
be considered because IT doesn’t assume responsibility for energy costs. Energy
savings from network-integrated power management provided 3% savings for endpoints,
and up to 9% additional savings when including building integration. These variations in
business practices resulted in a network architecture TCO model where Cisco TCO
varied from 4% more expensive to 13% less expensive.
One key highlight of the research was investment protection. Many customers indicated
that their Cisco investment was expected to last 6 to 7 years. In contrast, non-Cisco
customers indicated a 4- to 5-year lifecycle for comparable competing products. A “good
enough” network is often sufficient for today’s needs, but does not provide the flexibility
or investment protection to carry the business beyond years 4 or 5. Roadmap inspection
(studying product end of sale/end of life announcements) shows that Cisco products
have significantly longer life spans than similar competing products.
Architectural Benefits Architectural TCO captures the business benefits a customer can realize from Cisco
innovations embedded in the network infrastructure. Key highlights of the customer
research included:
1. While Cisco CapEx costs are higher, overall TCO is at worst 4% to 7% higher.
When extended lifecycles and labor savings are taken into account, Cisco TCO
is up to 13% lower than other vendors.
2. Cisco offers significant labor savings versus the competition—on average,
customers reported 5% to 10% labor savings when compared to similar
2012 EMC Proven Professional Knowledge Sharing 17
solutions, attributed to the benefits of unified wired and wireless platforms and
integrated security.
3. The cost of sourcing and/or training network engineering talent on non-Cisco
networks outweighs the CapEx savings of a “good enough” network.
Labor savings derived from an architectural approach offer compounded annual savings
when compared to onetime CapEx savings.
Many of the benefits noted are derived from innovations introduced in the Cisco
Borderless Networks portfolio in 2010 and 2011. Cisco customers highlighted the
increased value realized from architecture-wide network services and management
platforms. These innovations streamline the mobile user experience and facilitate “bring-
your own-device” business policies, enable delivery and management of real-time
multimedia traffic, and reduce IT overhead when performing user access troubleshooting
and wired-wireless integration. Professional services from Cisco and its partners help
customers accelerate their ROI and manage TCO by predictably managing the health
and stability of their networks, reduce costs related to outages and operations, mitigate
security and business risks, and drive innovation.
Beyond TCO In addition to offering architectural TCO benefits, a Cisco network provides many
additional business benefits that help drive down TCO and increase ROI. These benefits
are often measured in terms of higher business growth rates, increased customer reach,
or new business processes that streamline operations and increase employee
productivity.
Some examples of these benefits include:
● Improved network update (broader global support structure, network resiliency
innovations)
● Higher user productivity (IT and end-user productivity)
● Lower threat of security breach (Cisco SIO and SenderBase)
● Comprehensive professional and technical services offers that free IT resources for
strategic projects, help improve network health and stability, reduce cost, and mitigate
risk
2012 EMC Proven Professional Knowledge Sharing 18
Storage and Backup It is rare to find IT organizations that willingly increase their budgets, even considering
the significant storage volume growth in today’s IT environment. IT organizations began
streamlining their strategies by adopting storage consolidation solutions. Based on their
previous experiences, these organizations have come to realize that a flexible and
consolidated infrastructure will be the best environment to help them manage the
increased data availability demands and application requirements, and at the same time,
keep the budget within limits or minimal. The traditional practice being followed by IT
organizations of today’s environment is to allocate budget for overall IT infrastructure, a
part or percentage of which is associated with storage hardware, services, and software.
Of course, everyone wants the budget to remain the same year after year. It’s necessary
to control or utilize this budget efficiently because, if not controlled, costs will invariably
increase to match business requirement complexity.
Many IT managers who are responsible for storage decisions have misinterpreted that
that a low price disk solution or lesser per Gig price solution is sufficient to meet their
objective to lower the TCO associated with storage. They must recognize that TCO
results can only improve if we look at long term and short term plans. Purchasing
cheap/inexpensive solutions always lead to higher TCO if we look long term over a 3 to
5 year period. While low per Gig price for disks is helpful in short-term plans where
CAPEX turns out to be lower, if we factor in OPEX costs, it turns out be quite a bit higher
over longer duration/term. OPEX costs associated with storage and considering the cost
deciding parameter is becoming crucially important to achieve better results or savings
in IT infrastructure solutions.
Technologies come and go, with new ones still coming; however, pressure on CAPEX
and OPEX will always remain the same. It’s necessary to have a vision beyond the
acquisition costs associated with technologies and search for ways to provide additional
savings. IT organizations have started creating business cases to win management’s
support for making planned calculated investments that will result in reducing not only
CAPEX, but also OPEX costs.
Return on Investment (ROI), Return on Assets (ROA), TCO analysis and measurement
along with cash flow analysis should always be considered while doing strategic
planning to meet technical and operational objectives. Why? Because adding basic cash
2012 EMC Proven Professional Knowledge Sharing 19
flow analysis helps to measure ROI, ROA, and TCO. This analysis can then be used by
IT managers to undertake initiatives, helping them to create a well-planned strategy. A
crucial activity required from IT is to first identify the parameters on which analysis is
going to be performed. Only then do payback and savings analysis showing cost
reduction initiatives to be undertaken become visible.
There are well-planned calculated, certified solutions available for storage (from
individual technology areas to organization level changes, management, storage
provision, and so on) that help reduce costs associated with storage infrastructure. Many
SMB IT companies have achieved benefits and costs savings such as reduction in
power, space, cooling, floor space, low per Gig price, and maintenance costs reduction
per Gig. These objectives have been achieved by deploying storage solutions that are
more aligned to services, while at the same time doing well-planned utilization of existing
infrastructure capacity. A very basic step is to first define and measure current costs. We
can only improve if we know existing costs, so it is necessary to measure current costs,
thereby providing a base of the current estate on which improvement needs to be done
and measured against.
Price of disk is falling year by year, roughly 20-30% per year, making it easy for anyone
to believe that they have lower cost of acquisition and are achieving a lower TCO.
However, the fact is that cost of acquisition has never been a deciding factor in TCO.
Looking at past few years, this cost has reduced from an average 55-60% of TCO to
about 20-25 % today. The remaining 75-80% percent of storage TCO apart from
acquisition is what needs to be handled or controlled in a well-structured/planned
manner during tough periods. Operational expenses—the costs of storage
infrastructure—are recurring costs that need to be identified by IT managers and action
needs to be taken to control these costs.
The importance of establishing a TCO baseline for storage infrastructure measurement
is being recognized by today’s CEO’s and IT managers involved in budget decisions.
Cost per GB per year is becoming a base method to identify all of the costs to own GB
storage. Confusion can occur when it is realized that, while the price of disk decreases
every year, TCO is not following the same pace, does not change at all, or in some
situations, is increasing. The reason for this is because other components associated
with TCO—labor, maintenance, power, floor space, migrations—are increasing year by
2012 EMC Proven Professional Knowledge Sharing 20
year. It is crucial to look at total costs rather than focusing on one-time costs to increase
the business efficiencies.
Figure 7 highlights the storage and backup cost categories/components and helps to
identify where the majority of the cost is associated with storage infrastructure. These
categories include:
Figure 7: Cost Categories and Description
There are a number of superior storage and backup architecture options available now—
EMC VMAX®, EMC VNX®, Data Domain®, Hitachi VSP, Hitachi 3PAR, and Netapp
FAS6100 series—that can be brought into the environment incrementally or during data
center migration and technology refresh periods. Initially, these storage and backup
architectures might not appear to be the least expensive option but owning these
architectures is always cheaper. The environment they are suited for varies depending
on the current need of the IT manager. For example, some want to control high-growth
environments, others want to reduce compliance/legal support costs, and others want to
reduce power and space costs. There are many more like them. Some of the key
Category DescriptionHardware Depreciation Yearly costs for hardware depreciation or monthly leases
Software Purchase or Depreciation Monthly or yearly costs for the purchase of the software. Some software can be capitalized with the original hardware acquisition
Hardware Maintenance Recurring maintenance or warranty costs for all storage hardware after the base warranty periodSoftware Maintenance Recurring maintenance or warranty costs for all storage software
Storage Management Labor Management labor costs associated with the various tasks of storage management, such as provisioning, tuning, load balancing, troubleshooting and upgrades
Backup and DR Labor Aside from storage management, additional labor related to backups and restores, as well as disaster recovery planning and testing
Migration, Re-mastering Various costs associated with data migration at the storage system's end of life. In large environments, there is continuous labor effort associated with data migrations
Data mobility Time and effort required to move data to different tiers or archive solutions. Different from re-mastering, data mobility follows the data lifecycle, not the system lifecycle.
Power Consumption and Cooling kVA, BTU costs (converted to kW) of data center power. Power costs should include industrial grade conditioning and battery or diesel backup
Monitoring SNMP, NOC and operations consoles for the storage, SAN and backup infrastructures
DC Floor space Cost per square meter of data center floor space. This often includes uninterruptible power supply (UPS) and raised floor costs
Provisioning Time Business impact for the time waiting from when the request is made until capacity is presented to the host
Cost of waste Two types: usable and not allocated, and allocated and not used
Cost of copies Database management systems and other applications often require copies to be made. In-tier or out-
of-tier copies are possible. Test, development, quality assurance (QA), data mart, data loaders and similar applications all require multiple copies of structured and unstructured data
Cost of Duplicate Data Overhead associated with several copies of the same data. This is very common in unstructured file systems
Cost of Growth Fundamentally, every storage architecture has a cost of growth. In high-growth environments with the wrong architecture, the cost of growth can be acute
Cost of Scheduled Outage Microcode changes, capacity upgrades
Cost of Unscheduled Outage (machine related)
In both the storage system and the connections or data path
Cost of unscheduled outage (people and process related)
Often due to capacity problems, operational control and physical thresholds
Cost of Disaster Risk, Business Resumption Business impact with slow or fast recovery after a catastrophic event (declared disaster)
RTO and RPO Costs Business impact costs resulting from the time it takes to return to a recovery time (or point) after a system failure or backup recovery
Data Loss Business and enterprise costs for lost, corrupted or unrecoverable data
Litigation, Discovery Risk Legal risk and e-discovery time costs associated with lawsuits. This also covers general data location and recovery effort time
Reduction of Hazardous Waste EU cost due to regulations such as RoHS Noncompliant hardware may incur an additional tariff for disposal of the asset
Cost of Performance Impact to the business (good or bad) relative to total storage performance (IOPS, latency, MB/sec)
Backup Infrastructure Fixed cost infrastructure for backup. This includes backup servers, media servers, tape libraries, drives, etc.
Cost of Risk with Backup Windows Business impact of shortened or limited backup windows
CIFS-, NFS-related infrastructure Filers, gateways and the necessary software to provide file servers and shared services in the enterprise
Local and Remote Data Circuits Dark fibre used for SAN extensions, remote replication and the associated software
SAN Dedicated Fibre Channel, iSCSI or NAS connection infrastructures. This includes routers, gateways, host bus adapter switches and directors
Noncompliance risk (archive, data retention) Several legal and legislative requirements (HIPAA, Basel II, Sarbanes-Oxley, carbon emissions), noncompliance with which can incur fines, negative publicity and criminal prosecution
Security, Encryption Costs associated with protecting, securing and encrypting data and the storage infrastructure
2012 EMC Proven Professional Knowledge Sharing 21
elements for storage and backup architectures which are economical too are shown in
Figure 8:
Figure 8: Key Elements of Economical Storage and Backup Architectures
Virtualization storage technology, a key component of storage solutions, has proven its
impact on TCO over the years/decades now. Virtualization lays the foundation that
enables other key elements such as Dynamic Tiered Storage and Thin Provisioning. A
25-30% reduction in storage TCO has been because of the following three elements:
1. Storage Virtualization
2. Automated, policy-driven tiered storage
3. Thin Provisioning
Each has technical as well as cost benefits on its own. However, when we unify all three
in a storage architecture, the impact created by this combination is significantly greater
than what they offer individually. Benefits offered by these three constituents when
unified together in one storage architecture include:
• Storage Reclamation: Combination of one-time reclamation and a significant
reduction in cost with growth over time
• Return on assets (ROA): Better utilization of assets; can be utilized even after
asset has passed its depreciation life
• Minimal Storage Estate: Quality of service delivered remains the same
• Migration: Minimal or no disruption to business with heterogeneous storage
migration
2012 EMC Proven Professional Knowledge Sharing 22
• Backup and Recovery: Disk-based backup devices, VTL’s, and deduplication
have significantly reduced backup and recovery times. Multitier functionality in
storage has reduced the cost of copies. Sharing backup services, performing
replication of backups, and snapshot management has become easier with
centrally managed virtual pools.
• License Costs: Contradictory to an increase in storage capacity has been
associated license cost per GB, which has been reduced.
• Downtime: Reduction in scheduled activities such as provisioning time,
maintenance, and upgrades.
• Management Costs: Reduced labor, time, and effort required for provisioning,
configuration changes and management tasks to manage heterogeneous
storage devices.
• Hosting Environment: If we have to measure per TB, there is significant
reduction in the hosting environment, such as reduction in power requirement,
floor space, and cooling/air conditioning.
Compared to traditional or silo storage architectures, the new generation of storage
architectures provide a real world cost savings. Figure 9 provides an example, showing
significant reduction in TCO with the new generation storage architecture.
2012 EMC Proven Professional Knowledge Sharing 23
Figure 9: Cost Savings of Advanced Storage Architectures
Baseline storage capacity considered for the analysis above is 130 TB (analysis is
TCO/TB/Year). It is clear from the above analysis that decreased TCO is significantly
due to reduction in the costs associated with the following elements:
• Migration Costs • Cost of Waste • Cost of Copies • Storage Management Labor Costs
To summarize, if an IT manager is looking to control costs associated with storage, the
first step would be to identify and measure which types of cost have major impact in the
current environment and are most relevant to control. Keeping these elements in mind,
choice is not left to selecting products only. Storage design plays a vital role in meeting
an IT organization’s objective to reduce costs. As discussed earlier, combining Storage
Virtualization, Dynamic Tiered Storage, and Thin Provisioning in a storage architecture
results in significant savings. Technologies will continue to change. However, the good
news is that the underlying principles are not dependent on time. Following these
BaselineNew Generation Architecture
with 3 key Constituents
2012 EMC Proven Professional Knowledge Sharing 24
principles will always help an IT organization meet their objectives by implementing best
practices associated with them.
Virtualization Virtualization delivers multiple benefits—higher processor utilization, less power
consumption, better management through centralized control, higher availability of
applications, reduced execution timelines by eliminating need for hardware procurement,
improvised disaster recovery capability, and improved outsourcing services.
Virtualization has rapidly become a reality. The technologies that are used for servers,
clients, storage, and networks are being virtualized to create flexible and cost-effective
IT infrastructures. Given today’s concerns on TCO and ROI, server virtualization is
positively impacting data center systems. The reduction in power consumption as a
result of virtualization is a factor in TCO and ROI and helps data centers with the
“greening of IT”.
VMware is a leader in virtualization but Microsoft’s recent focus and product
announcements are giving VMware tough competition. As time passes, the virtualization
leader will need to deliver solutions on all aspects of virtualization (networks, servers,
storage, desktops, and so on) while maintaining TCO and ROI for its customers.
Licensing is already a discussion with respect to TCO and ROI and vendors are
responding. Management of virtualization environments will need “ease of use” and an
inventory management component that dynamically tracks virtualization ensuring that
data center managers will always know the state of their virtual environments.
Virtualization is seen as a benefit for a swift and less painful business continuity process
but only if the total data center environment remains manageable.
Today, virtualization is the primary focus for many companies. Virtualization provides a
number of benefits which impact many aspects of information technology operations. A
few of these benefits are:
• reduced power requirements
• improved CPU utilization
• fewer physical servers needed to support swift failover when a virtual server fails
• more flexible allocation of storage
2012 EMC Proven Professional Knowledge Sharing 25
• faster and easier disaster recovery at the disaster recovery site
• enhanced centralized delivery of work station services
Considering these and other benefits of virtualization, it is no wonder that companies are
actively pursuing and embracing this technology.
Though virtualization provides many benefits, there are new challenges. It is important to
keep in mind that because it is faster to create virtual servers than to specify and install
hardware, there is a tendency to create virtual environments “ad hoc”. Consequently,
virtual environments could quickly sprawl and become uncontrollable. In addition, having
more virtual server instances increases the workload for patching, maintaining, and
security.
The following sections will focus on the eight components associated with virtualization:
1. Data Center Server Hardware
2. Data Center Server Storage
3. Data Center Server Networking
4. Data Center Server Power and Cooling
5. Data Center Server Space
6. Data Center Server Provisioning
7. Data Center Server Administrative Costs
8. Reduced Business Risks around Data Center Server Disaster Recovery and
Data Center Server Unplanned Downtime
Data Center Server Hardware With virtualization, data center server workloads can be consolidated, typically in the
range of 10:1 to 20:1. The resulting benefit is significant in that the consolidated servers
can be reallocated to other applications, and future server sprawl avoided.
To calculate the level of consolidation, virtualization best practice involves workload
assessments—in essence, looking at the number of CPUs in use today, and how many
CPUs can be consolidated. The key variable is the amount of workloads that can be
consolidated onto a single CPU. Based on examining VMware deployments in customer
environments, on average four to five virtual machines are typically consolidated per
CPU.
2012 EMC Proven Professional Knowledge Sharing 26
The following inputs (Figure 10) will be useful for data center server hardware TCO
calculations:
Figure 10: Data Center Server Hardware TCO Inputs
TCO Calculation for Data Center Hardware Data Center Hardware Savings = (Total Servers * Amortized Cost per Server) As-Is
State - (Total Servers * Amortized Cost per Server) To-Be State
Data Center Server Storage Storage virtualization can help companies implement an enterprise virtualization strategy
to reduce IT costs / improve IT productivity even further. A key cost factor while
implementing a storage attached network (SAN) architecture is that almost all servers
need to be connected to the SAN network, resulting in an investment of network
connections, deploying and managing HBAs that will connect the server to the SAN
network, and SAN switches to connect the servers to the “SAN Fabric”.
VMware infrastructure server consolidation projects have dramatically reduced SAN
deployment costs by reducing the number of SAN switches and HBAs needed post-
virtualization. In many deployments where there is no SAN in place today, storage
virtualization is often part of the server consolidation project. In such cases, many
customers will invest in SAN connectivity and SAN storage incrementally as part of the
virtualization project.
The following inputs (Figure 11) will be needed for data center server storage TCO
calculations:
2012 EMC Proven Professional Knowledge Sharing 27
Figure 11: Data Center Server Storage TCO Inputs
TCO Calculation of Data Center Server Storage
Savings on HBAs = [(Number of HBAs * Price per HBA) / Useful Life of Servers] As Is
- [(Number of HBAs * Price per HBA) / Useful Life of Servers] To Be
Savings on SAN Switches = [(Number of SAN Switches * Price per SAN Switch) / Useful
Life of Servers] As Is
- [(Number of SAN Switches * Price per SAN Switch) / Useful Life of Servers] To Be
Storage Savings = [Percentage of Storage DAS * Total Storage Capacity * Cost per GB
DAS] As Is
- [Percentage of Storage DAS * Total Storage Capacity * Cost per GB DAS] To Be
+ [Percentage of Storage SAN * Total Storage Capacity * Cost per GB SAN] As Is
- [Percentage of Storage SAN * Total Storage Capacity * Cost per GB SAN] To Be
Data Center Server Networking Similar to storage, virtual infrastructure has dramatically reduced the number of physical
network components. Fewer Level 1 and Level 2 switches, NICs, and cables are
required to provide server connectivity to the corporate network with fewer physical
servers attached to the network.
Typically, I/O requirements in a virtualized scenario result in an increased number of
NICs per server (3 per server), although the total number of NICs across all servers is
2012 EMC Proven Professional Knowledge Sharing 28
substantially reduced. For the TCO calculation, the reduced NIC requirements are
accounted for in the price of the server hardware, since they often accompany server
purchase.
Inputs needed for data center server network TCO calculations are shown in Figure 12.
Figure 12: Data Center Server Network TCO Inputs
TCO Calculation for Network Annual Network Savings = ROUND UP [(Number of Servers * Number of NICs per
Server * Number of Ports per NIC) / Number of Ports per Network Switch)] As Is
- ROUND UP [(Number of Servers * Number of NICs per Server * Number of Ports per
NIC) / Number of Ports per Network Switch)] To Be
Data Center Server Power and Cooling Data center power consumption can be categorized into three main categories:
• Operating Power for the computing infrastructure (IT loads): Server hardware,
network switches, SAN components, and so forth.
• Network Critical Physical Infrastructure (non-IT loads): Facility infrastructure/
transformers, uninterruptible power supplies (UPS), power wiring, fans, and
lighting.
• Cooling Power for air conditioners, pumps, and humidifiers.
Virtualization lessens the need for physical servers and related networking, storage, and
data center infrastructure, resulting in less power consumption for operations and
cooling. This typically drives substantial reductions in annual power service costs, as
well as important “green” savings in carbon consumption. A complete model would
account for each asset consuming power as listed above, but for simplicity, the
methodology focuses only on the power saved from reduction in server hardware with
2012 EMC Proven Professional Knowledge Sharing 29
regard to direct operating and cooling power omitting potential power and cooling
savings for networking, storage, and other data center infrastructure. As with other TCO
saving calculations, the savings in power is calculated by estimating the differences in
operating power consumption and cooling power of server hardware before (as is) and
after (to be) virtualization.
The operating power consumed by server hardware can be calculated by adding up the
power ratings of each server in the data center. Because this number represents the
maximum power used, it should be de-rated (30-40% of rated power) to achieve steady-
state power consumption. As well as operating power, servers produce heat and require
substantial cooling to keep them running at prescribed temperatures by OEM’s. Data
center design plays an important role in determining the thermal efficiency and the cost
of cooling. Many data centers still employ a front-to-back layout, which positions servers
in the same direction. This means the heat emission from the back of one server feeds
directly into the air intake of the front of another server. A better approach is the hot-
aisle/cold-aisle layout (Figure 13) which mitigates the unacceptable temperature
gradients associated with front-to-back layouts.
Figure 13: Aisle/Cold-Aisle Layout
Data centers often use a seven-tile aisle pitch. This measurement allows two 2 x 2 foot
(0.61 x 0.61 m) floor tiles in the cold aisle, 3 feet (0.9 m) in the hot aisle, and a 42-inch
(1-m) allowance for the depth of the cabinet or rack
In the event of a Computer Room Air Conditioning unit failure, airflow redundancy will
continue to satisfy cooling requirements. Furthermore, many data centers have hot
spots, where heat density is greater than other areas. Focused redundancy satisfies
localized data center cooling requirements.
2012 EMC Proven Professional Knowledge Sharing 30
The analysis below (Figure 14) gives a snapshot of the HVAC scaling with regard to
different cooling techniques applied in the data center.
Figure 14: HVAC Scaling
IT equipment energy costs need to reflect cooling costs that can be as much as twice
those of the actual IT equipment, depending on the PUE (power usage effectiveness) of
the data center.
Beyond annual operating and cooling power fees, many organizations are becoming
more conscious as to the environmental impact of data center power consumption.
Figure 15 provides a holistic view on the green datacenter approach.
2012 EMC Proven Professional Knowledge Sharing 31
Figure 15: Holistic View of Green Data Center
Figure 16 shows inputs needed for data center server power TCO calculations.
Figure 16: Data Center Server Power and Space TCO Inputs
TCO Calculation For each server type, the following equations are used to determine annual operating
power:
Server Operating Power per Server per Year As Is = Server Nameplate Operating Power
* Nameplate to steady state power conversion * Data Center Operating Hours *
Electricity Price per Hour
2012 EMC Proven Professional Knowledge Sharing 32
Server Operating Power per Server per Year To Be = Server Nameplate Operating
Power * VMware Utilization Uplift * Nameplate to steady state power conversion * Data
Center Operating Hours * Electricity Price per Hour
To calculate the total operating power consumption, the above equations are used and
summed for each server type taking the product for Quantity of Servers and the Server
Operating Power per Server per Year.
To calculate the TCO savings, the difference between operating power costs are
compared.
For server cooling power consumption, the following equations are used:
Annual Server Cooling Power per Server per Year = Operating Power per Server per
Year * Cooling Load Factor * Airflow Redundancy / Airflow De-rating
To calculate the total operating power consumption, the above equations are used and
summed for each server type taking the product for Quantity of Servers and the Server
Operating Power per Server per Year.
To calculate the TCO savings, the difference between operating power costs are
compared.
Annual Power and Cooling Savings = Power and Cooling Costs As Is - Power and
Cooling Costs To Be
Data Center Server Space Decreasing the quantity of physical servers can lead to retrieval of current data center
space, reducing the need to consume more space due to server proliferation to handle
growth, and avoiding future data center facilities build-out or colocation requirements
Virtualization technologies such as VMware can reduce a company’s physical server
count, impacting data center footprint today, and preventing future requirement of data
center space (new facility or third party colocation). The TCO calculation accounts for
the total annual data center carrying costs, monthly real-estate rental charges, plus
amortizing the cost of data center facilities, including power and cooling infrastructure.
The annual space cost is calculated as follows:
2012 EMC Proven Professional Knowledge Sharing 33
Annual Data Center Cost per Square Foot = (Cost to Build Data Center Facilities + Cost
for Data Center Power and Cooling Infrastructure) / Years to Amortize Build-out Costs +
Annual Space Lease or Allocated
Annual Real Estate Cost per Square Foot
Inputs needed for data center space TCO calculations are shown in Figure 17.
Figure 17: Data Center Server Space TCO Inputs
Data Center Server Provisioning A VMware infrastructure enables administrators to provision workloads from their
systems without having to acquire, set up, and deploy new hardware to meet increasing
workload demands.
Labor hours are saved by not having to manually provision servers. The savings are
calculated by multiplying the hours saved by an administrator hourly wage.
Provisioning a server in a non-virtualized environment takes approximately 20 hours per
server on average including overhead tasks for server procurement and vendor and
contract management, and server administration time for server unpack, set up,
installation, test, and deployment.
The savings are most commonly realized as a productivity improvement since fewer
administrators are required to accomplish big roll outs and redeployment of
administrators from routine provisioning tasks to more strategic value added activities.
However, the opportunity savings for this are calculated using labor hour and cost
savings.
2012 EMC Proven Professional Knowledge Sharing 34
Inputs needed for data center server provisioning TCO calculations are shown in Figure
18.
Figure 18: Data Center Server Provisioning TCO Inputs
Data Center Server Administrative Costs Virtualization of workloads and reducing the number of physical assets to manage helps
decrease the number of server administrators needed for physical moves and changes,
asset inventory, physical security, disaster recovery and planning, compliance
management/reporting, vendor and contracts management, chargeback, and
financial/budget management.
In a typical virtualized environment, an administrator can manage 30-40% more
workloads as compared to physical infrastructure.
The following inputs are beneficial for calculating TCO of administrative costs:
• Average Servers per IT Administration FTE
• Average Hourly Burdened Labor Rate for IT System Administration and Support
Staff
• Annual increase in server administration costs
Disaster recovery and Business risks When it comes to disaster recovery and business resilience, virtual infrastructure offers
significant savings, including:
• Recovery from a massive failure: Unsuccessful or lengthy recoveries are
commonplace, and VMware infrastructure can speed recovery and enable long-
term survival;
2012 EMC Proven Professional Knowledge Sharing 35
• General Downtime – VMware can dramatically reduce planned downtime
associated with scheduled software upgrades, application maintenance,
hardware reconfiguration, and so forth. In addition, it reduces unplanned
downtime such as unscheduled outages due to hardware failure, application
(software) failure, and so on;
• Reduced cost for DR planning: Covered in server administration savings.
In the event of a massive failure (disaster), VMware infrastructure can dramatically
decrease recovery time by
1. Consolidating servers which reduces the number of physical servers which need
to be restored in case of disaster.
2. Hardware-independent virtual servers which require only single step file
recovery, reducing time to recover and resume.
VMware infrastructure can help reduce both planned and unplanned downtime. During
planned hardware maintenance, a server may have to be powered down which can
result in a temporary disruption of business. VMware’s vMotion technology drastically
reduces this downtime by allowing IT administrators to move running virtual machines
between servers without end user impact.
Unplanned downtime is also reduced using VMware Infrastructure. vMotion enables
administrators to dynamically move virtual machines away from overloaded hosts or
failed servers. This minimizes disruption to normal business activity and can ultimately
lead to preservation of revenue which might have been lost due to downtime.
Because planned downtime usually has minimal impact on a company (performed
during non-business hours), only unplanned downtime impact is considered.
Based on the parameters discussed above, Figure 19 shows TCO savings with current
and to-be state for around 300 servers:
2012 EMC Proven Professional Knowledge Sharing 36
Figure 19: VMware Infrastructure TCO Calculation
Figure 20: VMware Infrastructure Benefits
Figure 21: VMware Infrastructure 3 year Benefits
Cumulative 3 Year TCO ComparisonCurrent (As
Is)With VI
(Projected)Difference ($ and %
savings)VMware Infrastructure BenefitsData Center Server Hardware $3,839,931 $482,538 $3,357,393; 87.4%Data Center Server Storage $231,733 $495,056 $-263,323; -113.6%Data Center Server Networking $220,612 $30,886 $189,726; 86.0%Data Center Server Power and Cooling Consumption $1,068,742 $97,847 $970,895; 90.8%Data Center Server Space $1,005,578 $95,427 $910,151; 90.5%Data Center Server Provisioning $424,527 $31,841 $392,686; 92.5%Data Center Server Administration $2,367,810 $1,815,321 $552,489; 23.3%Disaster Recovery Site Investment $2,796,480 $502,833 $2,293,647; 82.0%Data Center Server Disaster Recovery (Indirect) $864,000 $86,400 $777,600; 90.0%Data Center Server Downtime (Indirect) $2,314,305 $578,577 $1,735,728; 75.0%
Investment RequiredVI Software Licensing and SnS $0 $392,439 $-392,439; 0%Additional Software Licensing Costs (if any) $0 $0 $; 0%VI Design, Plan and Deployment Services $0 $239,013 $-239,013; 0%VI Training $0 $12,930 $-12,930; 0%
TCO - Direct $11,955,413 $4,196,131 $7,759,282; 64.9%TCO - Indirect $3,178,305 $664,977 $2,513,328; 79.1%Total TCO (3 year) $15,133,718 $4,861,108 $10,272,610; 67.9%
Expected Benefits from VI Year 1 Year 2 Year 3 Total
Data Center Server Hardware $1,014,318 $1,115,750 $1,227,325 $3,357,393Data Center Server Storage ($79,554) ($87,509) ($96,260) ($263,323)Data Center Server Networking $57,319 $63,051 $69,356 $189,726Data Center Server Power and Cooling Consumption $293,322 $322,654 $354,919 $970,895Data Center Server Space $274,970 $302,467 $332,714 $910,151Data Center Server Provisioning $113,732 $130,109 $148,845 $392,686Data Center Server Administration $160,015 $183,057 $209,417 $552,489Disaster Recovery Site Investment $764,549 $764,549 $764,549 $2,293,647Data Center Server Disaster Recovery (Indirect) $259,200 $259,200 $259,200 $777,600Data Center Server Downtime (Indirect) $578,576 $578,576 $578,576 $1,735,728Total Benefits $3,436,447 $3,631,904 $3,848,641 $10,916,992
2012 EMC Proven Professional Knowledge Sharing 37
Figure 22: 3 year TCO Comparison for VMware Infrastructure
Numbers used above can vary based on enhancement of features in products. Figure 23
lists the assumptions taken to arrive at the above TCO savings and numbers:
Figure 23: VMware Infrastructure TCO Calculation Assumptions
To summarize, for most IT organizations, infrastructure costs consume too much of the
IT budget. In fact, the average company spends 61% of their budget on day-to-day
Current Data Center Server Hardware ProfileNumber of Data Center Servers AS-IS cost
2 CPU 100 $5,0004 CPU 200 $9,500How many gigabytes (GB) of storage do you have in your current environment (in total)? 30000What is the percentage of current servers attached to SAN? 10%Current (As Is) Data Center Storage ProfileOn average, by what percentage does your server storage increase each year? 10.0%When server is attached to a SAN, what is the number of HBAs per host? 2.0How many ports are there per typical SAN switch? 24What is the cost of each HBA? $1,250What is the cost for SAN switches? $6,000What is the cost for DAS storage (per GB)? $3.00What is the cost for SAN storage (per GB)? $10.00Current (As Is) Data Center Server Networking ProfileWhat are the current number of network interface cards (NICs) per server? 2What are the current number of ports per NIC? 2What are the current number of ports per network switch? 24What is the total cost for a network switch? $4,000On average, by what percentage does your server networking costs increase each year? 10.0%What percentage of the annual server networking savings can be realized? 100.0%Current (As Is) Data Center Server Power and CoolingWhat is the current price of electricity (cost per kWatt hour) for the data center facilities? $0.1000What is the operating power (in Watts) per server?2 CPU 5504 CPU 950Current (As Is) Data Center Server ProvisioningHow many servers are provisioned per year (growth / replacements)? 130
On average, by what percentage does your server provisioning task workload increase each year?10.0%
What percentage of the annual provisioning labor savings can be realized? 100.0%Current (As Is) Data Center Server IT Operations and AdministrationWhat is the average server:administrator ratio? 40.0What percentage of the annual IT operations and administration overhead labor savings can be realized? 50.0%Current (As Is) Data Center Server DowntimeWhich most closely describes the application(s) supported by these server operations?On average, how many downtime hours occur per year for these server operations? 150.0On average, what is the per hour business cost in lost productivity or transactions from these downtime events?
$51,429
Current (As Is) Data Center Server Disaster Recovery Risks and CostsWhat is the likelihood of a disaster occurring in any given year which will require recovery? 16.0%What is the estimated hourly cost of recovery including downtime and labor costs? $450,000What is the expected time (in hours) for full recovery for all servers / data? 40Current Disaster Recovery (DR) Site InvestmentWhat is the current number of servers installed (As Is) for disaster recovery (DR)? 150.00 How many person hours are needed to setup and deploy each replication server? 20.0 What is the total storage infrastructure cost for the DR site? $35,005What is the total network infrastructure cost for the DR site? $33,325What is the total data center space cost for the DR site? $151,900VMware Infrastructure Proposed Configuration and Benefit Assumptions4 CPU $15,200What is the estimated provisioning task time reduction factor with VMware? 13.48What is the estimated number of workloads/vms per IT operations and administration staff FTE with VMware?
75
What is the estimated disaster recovery time reduction factor with VMware? 90.0%What is the estimated downtime reduction factor with VMware? 75.0%
For the VMware solution, the GB to add per workload/vm unit? 20.0 After VMware, what percentage of storage will be SAN? 100.0%What is the number of Network Interface Card (NIC) per server with the VMware solution? 3What is the number of ports per NIC with the VMware solution? 2
2012 EMC Proven Professional Knowledge Sharing 38
operations, and 25% on progressive migrations and upgrades, leaving little of the
budget—less than 14%—for innovation. One way to reduce “keeping the lights on” costs
is through enterprise virtualization—providing a flexible pool of server, QA lab, storage,
and desktop resources which can be allocated based on business demands.
Infrastructure optimization using enterprise virtualization can help to consolidate assets,
improve utilization, and make the business more resilient and agile.
Data Center Facilities and Hosting Even through challenging economic times, the need for physical data center capacity
continues to grow. For some businesses, the driver is expansion into new markets or
geographies. For others, it’s the need to deal with growing amounts of data generated by
applications with high-capacity demands, evolving end-user abilities, or regulatory
bodies that demand ever-increasing quantities of meticulous documentation. If a
customer’s data center is running out of space—or power, an increasingly important
constraint—there are two options. Customers can either build and operate a new facility,
or lease the capacity required from a colocation provider who can solve the problem
immediately.
Colocation, often referred to as “COLO,” differs from traditional hosting, where the
hosting company provides the hardware and some or all of the software required to run
your applications. In a colocation arrangement, customers own all the hardware, and
typically provide the technicians to support it as well. Customers don’t have to worry
about floor space, cooling, power (and its distribution), cabling, fire suppression, and
physical security. This is all managed by the COLO provider.
Predicting and measuring TCO for the physical infrastructure for network rooms and
data centers is required for ROI analysis and other business decision processes.
The “build-or-buy” decision between construction and colocation should be weighed
carefully, as the choice will affect your company and your bottom line quite literally for
decades. This article will review six key factors that affect that choice, some of which
extend beyond basic TCO analysis.
Let’s consider some facts on buy vs. build and then shed some light on ways to reduce
TCO for customers who have already made investments.
2012 EMC Proven Professional Knowledge Sharing 39
Key Benefits of Buying vs. Building a Data Center
Leasing a data center Building a data center
A predictable and operational expenditure
model with costs that are easy to predict
and that increase at a consistent rate over
the life of the data center.
Complete control over operating
environment, from who can access the
facility to the temperature that it runs.
Additional capacity can be brought on
quickly and only as-needed, shielding you
from having to build out extra capacity that
might not be used for many years.
Very low risk of losing your lease and
being forced to leave the facility.
Data center is run by professionals with
more experience and expertise in the
practice of running an efficient and highly
available data center facility.
Ability to leverage and share existing
space, giving IT staff the ability to work in
close proximity to the data center floor for
a low cost.
An ecosystem of partners in the same
facility that can be leveraged with
extremely low latency via a cross-connect.
Figure 24 gives a snapshot of TCO components for a typical rack in a highly available
2N data center.
Figure 24: TCO components for typical rack
1% 5%
18%
6%
18% 20%
15%
2% 15%
System Monitoring
Project Management
Power Equipment
Cooling Equipment
Engineering & Installation
Electricity
2012 EMC Proven Professional Knowledge Sharing 40
According to a Forrester study, most companies find leasing is more cost effective than
building a data center. In this study, it was found that the total cost of building versus
leasing a data center over a time period of 15 years were not significantly different. The
original estimates indicated following the net present value of the cash flows.
Leasing a Data Center – $(29.60)
New Data Center build – $(28.70)
However when risk was factored into the model, the new “Most likely NPV Model”
jumped to $47 million while leasing remained under $35 million.
The major risk identified with building a data center facility was over- or under-
provisioning of the data center facility which may have huge costs in the longer run with
high probability of impacting business case.
Clearly substantiating the above risks, Figure 25 shows the results of the installed
versus utilized power of a study conducted by APC on data center facilities that are built
by customers.
Figure 25: Power Utilization Percentage
0%
20%
40%
60%
80%
100%
120%
0 5 10
Util
izat
ion
Perc
enta
tge
Years from Commissioning
Installed Power capacity
Expected power Requirement
Actual Power requirment
2012 EMC Proven Professional Knowledge Sharing 41
Opportunities to control TCO for COLO providers and customers having their own data centers A variety of strategies to control lifetime TCO are apparent. These include efficiency
improvement, improved planning, rightsizing the system, negotiating costs, self-service,
and so forth. Per rack TCO savings for a typical 2N data center or network room
resulting from a variety of scenarios are summarized below.
Scenario TCO $ saved per rack
% of TCO saved
Purchasing power equipment with 2% higher electrical efficiency
$1,472.00 1.1%
Reducing the electric rate by 1 cent per KW-Hr $3,100.00 2.4%
Eliminating the raised floor $4,200.00 3.3%
Increasing the cooling performance coefficient by 100%
$5,500.00 4.3%
Obtaining space at no cost $12,000.00 9.4%
Obtaining all capital equipment at 50% discount from standard
$15,700.00 12.3%
Rightsizing the system to the actual requirement over time
$76,400.00 60.1%
There are many contributors to the total cost of a data center that are difficult to scale
with time and are typically incurred up-front, such as facility space improvements, facility
switch gear, and engineering costs. When the modular, scalable technology is used to
the extent which is currently practical, saving up to 30-40% have been recorded in some
cases.
2012 EMC Proven Professional Knowledge Sharing 42
The oversizing of infrastructure is a major contributor to this cost, and on average 30%
cost savings can be obtained by implementing practical design techniques using
modular scalable data center infrastructure.
Figure 26 shows a matrix of the opportunities vs. their impact on TCO.
Figure 26: Opportunities vs. their impact on TCO
Some of the initiatives on a facility level with savings estimated in different customer
scenarios are shown below:
Initiative Savings Approach Limitations
Rack
Optimization
10-15% Use of proper tool to allocate space
and power in each rack
Need re-
allocation of
systems
amounting to
some
downtime
Power
Management
Up to
50% of
server
power
usage
By turning off servers when idle and
successfully powering-up when
needed again
Complementary to virtualization
initiative
2012 EMC Proven Professional Knowledge Sharing 43
Efficient air
conditioning
architecture
7-15% Row-oriented cooling is efficient for
higher density
Shorter air paths require less fan
power
For new
designs
only
Benefits are
limited to high
density
designs
Economizer
modes of air
conditioners
4-15% This can offer substantial energy
savings, depending on geographic
location
Some data centers have air
conditioners with economizer modes,
but economizer operation is
disabled
For new
designs
only
Difficult to
retrofit
Server
Virtualization
10-40% Involves consolidation of applications
onto fewer servers, typically blade
servers
Also frees up space for power and
cooling capacity for expansion
Requires
major IT
process
changes
To achieve
savings in
an existing
facility,
some power
and
cooling
devices may
need to be
turned off
2012 EMC Proven Professional Knowledge Sharing 44
Efficient Floor
Layout
5-12% Floor layout has a large effect on the
efficiency of the air conditioning
system
Involves hot-aisle / cold-aisle
arrangement with suitable air
conditioner locations
For new
designs and
expansions
Difficult to
retrofit
Efficient Power
Equipment
4-10% New best-in-class UPS systems have
70% less losses than legacy UPS at
typical loads
For new
designs or
retrofits only
Coordinate air
conditioners
0-10% Many data centers have multiple air
conditioners that actually conflict,
resulting in gross waste
May require a professional
assessment to diagnose
For data
center
with multiple
air
conditioners
Correct
Placement of
Vented Floor
Tiles
1-6% Reduces hot spots
A professional assessment can
ensure an optimal result
Only for data
centers
using raised
floor
Requires
expert
guidance to
achieve best
result
2012 EMC Proven Professional Knowledge Sharing 45
Energy Efficient
Lighting
1-3% Turn off some or all lights based on
time of day or motion
Use more efficient lighting software
technology
Benefit is
greater on low
density or
partly filled
data centers
Install Blanking
Panels
1-2% Decrease server inlet temperature
Saves energy by increasing the
CRAC return air temperature
Cheap and easy with new snap-in
blanking panels, such as those by
APC
Cloud It is now common knowledge that, while traditional, customized solutions can meet
business requirements, they result in higher license costs, inefficient utilization, and
increased TCO. It’s becoming clear that increasing business requirements will push IT
organizations toward data center transformation. This includes finding ways to reduce
existing IT infrastructure costs such as through virtualization and consolidation that
decrease the number of physical servers needed and reducing energy consumption. IT
organizations can quickly address and respond to business needs by introducing a self-
management layer that enable services to be provisioned automatically, allowing
everyone to use service by themselves.
Nearly all IT organizations (almost 90%) are looking for a way to move toward business
agility as they face the daily challenges arising from costly and rigid IT infrastructure.
There are many reasons for this. Almost 70% of an IT organization’s budget is
consumed by existing environment maintenance itself; 30% is for new projects.
Management, power, and cooling costs associated with operations of systems
distributed across geographies are increasing and will continue to increase. Utilization
rates of these distributed servers are very low, averaging around 7-8%, putting
maximum capacity in waste only. Provisioning time for new servers takes a very long
2012 EMC Proven Professional Knowledge Sharing 46
time, sometimes months. This creates an opportunity to address these business issues
and provide new solutions with an innovative approach. As a result, many companies
have taken the initiative to move out of their data center and move to public cloud
providers such as Azure or Amazon with an aim to lower costs, increase response time,
and other benefits. Seeing this move, there is a need for a dynamic IT infrastructure that
gives reason or justification why a customer should stay with a data center.
In this article, we will analyze the TCO for a dynamic IT infrastructure built around private
cloud services, while at the same time comparing it with public cloud alternatives and
traditional distributed server models as well.
Virtualization and Server Consolidation—Starting Point for Cloud Virtualizing an existing environment enables IT organizations to move toward an on-
demand platform where IT resources can be easily available from a centralized virtual
pool. Close analysis of a 4500 distributed server environment show that operational
costs associated with each server amounts to more than $35,000, with almost 91% due
to software maintenance and systems administration. Virtualization reduces the number
of physical servers leading to more capable virtual machines which ultimately will greatly
reduce maintenance costs. A number of significant benefits have been identified by this
approach; consolidation of workloads, meeting SLA’s, scalability, lowest per VM image
cost being a few examples.
One way to answer all the questions and calculate TCO of a private cloud-based IT
environment, while at the same time comparing it with other options, is to:
1. Calculate the estimated consolidation ratio based on environment type (Windows,
Linux, etc).
2. Calculate the cost associated with the operation of the virtualized server environment
over a period of 3 or 5 years.
3. Perform a comparison between traditional and public cloud services solutions.
Service Management The cost savings associated with service management are easily recognized after
implementing a private cloud solution. Fewer servers to manage, reduced software
2012 EMC Proven Professional Knowledge Sharing 47
requirements, less management required, and lower cost are key benefits. Apart from
basic monitoring costs, the following solution components are required for improving
service management efficiency:
• Centralized monitoring of applications, where different components run on
different servers
• Unified view of the business-level services state that has dependency on shared
infrastructure spread out across multiple physical machines
• A database that will store and track changes made to hardware, software, and
networking configurations in a better controlled way
• A service desk that will allow the administrators to handle and resolve service
requests using the automated processes
Provisioning of Requests While the first three points discussed—virtualization, consolidation, and service
management—form the basic startup of an IT infrastructure, there is still a need for a
service portal that enables users to be self-dependent and request IT services as and
when required on demand in minimal time, even in minutes. A central repository, used
for defining and creating services, can be accessed by any user to search for the
required service. Indexes make it easier to perform the search function. Once approved
based on the rules set up initially, the underlying infrastructure fulfills the user request.
As soon as the user stops using the service, the allocated underlying resources become
free for any other user request. Management process must be automated using some
software to enable users to use the services.
By leveraging cloud computing’s multi-tenancy and elasticity, EMC IT has begun to offer
IT solutions on demand, scalable services that provide high availability, self-service
provisioning, metered usage, and chargeback. Via implementation of these
technologies, EMC IT is focusing on cloud-based architecture which will provide
customers with reduced TCO using consolidation, and at the same time offer good ROI,
effectiveness, better service, and last but not least, agility.
Similar to other companies, EMC is faced with increasing application complexity, which
increases the time and cost to provision infrastructure, platforms, and applications. In an
effort to reduce complexity and optimize IT infrastructure wherever possible, EMC has
2012 EMC Proven Professional Knowledge Sharing 48
focused on cloud computing to address current IT challenges and business
transformation, thereby driving maximum benefits. IT-as-a-Service (ITaaS) has been an
encouraging factor for cost savings, energy consumption reduction via shared
resourcing, and enabling rapid and agile deployment of customer environments or
applications. Other benefits of ITaaS are:
• Agility – Enables business users to browse and select required services and IT
personnel to easily provision, configure, and monitor virtual applications,
databases, and platforms in minimal time. This results in around 45-50%
reduction in software platform provisioning time.
• Architect for Future – Seamlessly provision for the future with infrastructure,
platforms, and applications that scale up and out to meet fluctuating demands.
• Cost Savings – Reduce real estate, energy, and maintenance costs.
IT-as-a-Service is a business-focused approach that focuses on results, operational
efficiency, competitiveness, and rapid response. The result is improved services
utilization aligned with business needs.
EMC provide three types of ITaaS services to business units:
Infrastructure-as-a-Service (IaaS): Offers compute, storage, backup and recovery, and
networks, individually or as an integrated service.
Platforms-as-a-Service (PaaS): Provides databases and application platforms such as
development tools, runtime environments, application frameworks, ILM, and enterprise
content management (ECM) as services.
Software-as-a-Service (SaaS): Widely used applications being offered to business units
including BI, ERP, CRM, and master data management. Consolidation and
standardization of infrastructure, streamlining of services to internal departments,
providing a more efficient working model, and decreased provisioning time has been an
observation of EMC IT delivery that delivers enterprise applications to business units
with higher agility.
2012 EMC Proven Professional Knowledge Sharing 49
Figure 27: Cloud Services Framework
Figure 27 shows the concept of IT-as-a-Service. There are the stakeholders, the
providers of the Cloud service. These services can be represented as public, private, or
hybrid Cloud services. There are the brokers, typically the IT department. There are the
consumers, typically company lines of business.
A collection of Cloud services are offered to consumers in a service catalog. These
services have agreed-upon characteristics and benefits to the stakeholders. The source
of the services is transparent to the consumers. Figure 27 shows a VDC within a private
Cloud that supports service offerings within a service catalog. These VDC’s are pooled
and tiered providing different levels and features of service offerings.
Platform-as-a-Service (PaaS) – Two categories have been identified under PaaS: 1. Database platforms including Oracle Database as a Service, SQL Server as a
Service, and Greenplum® as a Service.
2. Application Platforms including application development as a service, enterprise
content management as a service, ILM as a service, security platform as a
service, and integration as a service.
2012 EMC Proven Professional Knowledge Sharing 50
PaaS is a rapidly evolving type of Cloud service. It offers quick time to market,
transparent database connectivity, and new types of Web 2.0 developer environments.
These services are now offering virtual application portability across private and public
Clouds, or integration with SaaS applications.
Figure 28: PaaS Characteristics
In Database as a Service, business units are offered reduced TCO, improved service
levels, more efficient management, easier administration, and much stronger
compliance.
Figure 29: Design Principles for Database as a Service
Figure 29 shows the four design principles taken by EMC IT in setting up Database as a
Service. The table below provides a description of each.
2012 EMC Proven Professional Knowledge Sharing 51
Design Principles Description
Database Consolidation
Disparate databases consolidated into tiered clusters based on business criticality, required availability, and I/O profile
Information Optimization
Reduction of duplicate data to optimize the databases using effective information monitoring tools
Standardization Consistency, easier management, lower costs, and better performance via standard hardware and database footprints
Compliance Common management, administration, and compliance-related policies and procedures
For providing Database as a Service, EMC IT has adopted both a grid-based and a
virtualization approach toward database virtualization and consolidation. EMC has two
principal DB platforms, including Oracle and SQL Database, along with the Greenplum
DB platform. Database as a Service has also significantly reduced internal project
lifecycles, offering businesses the advantage of a faster turnaround. High availability and
same time reduction of data discrepancies support and run costs have made Database
as a Service a best option.
Applications Platform as a Service Tools are a major requirement to design and build applications for a cloud-based
operating environment. EMC IT has effectively provided tools for its cloud-based
solution, using EMC and partner technologies to provide a platform for developing
secure next generation applications. Applications built out of this platform are optimized
for virtual, self-managed operating environments. EMC IT’s objectives were to leverage
the power of this next generation cloud platform for application development, reduce
footprint of physical machines, simplify system architectures needed to run and manage
business critical applications, and reduce application development time and time to
market by enabling development teams to use rapid and flexible development
methodologies.
2012 EMC Proven Professional Knowledge Sharing 52
Guiding principles for building this platform are shown in the table below.
Guiding Principles Description
Lightweight Framework
Interfaces and frameworks that have lightweight, reusable, agile, and aspect-oriented programming.
Agile Development Optimized with testing and production platforms that scale up or down and shifts loads physically and geographically.
Service Based Self-managed and on demand provided applications.
Efficiency Efficient programming methodologies to increase efficiencies of system management.
Many other platforms are provided to users for application development, ECM, ILM,
information security, and IT integration. Figure 30 provides a brief description for each.
Service Type Description
Application Development
Application developers leverage application development platforms to easily build and deploy applications into the cloud.
Enterprise Content
Consolidated, scalable platform for hosting unstructured content using tiered storage and centralized management, supports more efficient provisioning and reduces management costs, in future chargeback based on usage and governance frameworks are expected to be incorporated.
Information Lifecycle
Enables end to end information optimization throughout the lifecycle of the data thereby ensuring right level of performance for applications at the lowest cost, efficient and cost effective data storage platform by reducing infrastructure, resources and maintenance costs.
Security Platform
Helps administrators securely administer and monitor public networks while keeping them separate from corporate networks; a Governance, Risk, Compliance (GRC) framework to drive policy adherence, govern network infrastructure, manage information security policies and ensure compliance with legal and regulatory requirements. Comprehensive platforms are being build to allow for common identity management and audit transactions that occur in private cloud environment.
2012 EMC Proven Professional Knowledge Sharing 53
Integration
Integrating multiple sources across business units to leverage this data seamlessly for business purposes. Service oriented architectures/web services, enterprise messaging, and extract, transform and load (ETL) provide integration services.
Figure 30: Service Types
Figure 31 highlights the benefits of application Platform as a Service.
Application Platforms as a Service Benefits
Benefit Type Description
Efficiency Improvement
High quality application infrastructure on demand with minimum time and effort.
Agility Quickly and efficiently adapt to new technologies and best practices.
Simplicity Reduce complexity and redundancy of systems.
Availability Enable high performance and zero application downtime.
Scalability High degree of scalability and effective dynamic application capacity management.
Figure 31: Benefits of Application Platforms as a Service
Software-as-a-Service (SaaS) Services such as BI, ERP, CRM, and master data management are being provided by
EMC IT resulting in the following benefits:
• Unify business definitions and provide a consistent online experience to
geographically dispersed users
• Implement consistent application security policies
• Consolidate process and integration logic outside of individual applications and
interfaces
It helps to streamline IT services to various internal departments and provide more
efficient services. It also helps to deliver enterprise applications to business units with a
high degree of agility, while reducing provisioning time and costs. EMC IT offers BI,
2012 EMC Proven Professional Knowledge Sharing 54
ERP, and CRM applications services under SaaS. Figure 32 provides a brief description
of each.
SaaS Service Type Description and Benefits
Business Intelligence
Reduction of TCO of business intelligence, reduction in number of source feeds and removal of data and hardware redundancies, eliminates risk of data discrepancies from multiple code bases. Significant performance gains including improvement in batch job performance, and a reduction in storage footprint. Going forward, EMC's Greenplum which is known as highly scalable analytical database is a key design point in offering BI as a service.
ERP and CRM
ERP as a Service will reduce the overall investment and time required to provision ERP modules, and increase ROI for investments on ERP made by customers. This will lay down a path for smooth and problem free integration of organizations and will help in working more effectively with suppliers, vendors, and partners.
Figure 32: SaaS Service benefits
Anything As a Service (XaaS) Recently, we have heard the term “Anything as a Service” (XaaS). With new technology,
market demands, and experience enterprises are embracing a new infrastructure model
to deliver IT-as–a-Service through hybrid Cloud computing. The rigid boundaries among
types of services or private and public Clouds are becoming transparent with distributed,
integrated, and portable Cloud applications. Figure 33 shows the XaaS services.
Figure 33: Anything as a Service (XaaS)
2012 EMC Proven Professional Knowledge Sharing 55
In summary, a cloud-based solution will provide customers with on-demand, scalable
service applications as a service, higher efficiency, high availability, better service, self-
service provisioning, chargeback, and metered usage. Automation, policy, and
governance add more to the cloud option. If customers opt for a cloud solution, it will
offer the best balance of these benefits:
• Lower TCO
• Higher ROI
• Enhanced Efficiency
• Better Service
• Increased Enterprise Agility
Conclusion Technologies will come. Technologies may vanish. The enduring questions from
business will remain, “How much investment, how much payback, how much ROI, how
much TCO” is your solution going to provide? Getting money out of the CEO’s pocket is
becoming increasingly difficult until and unless you have something new to bring a smile
to the CEO’s face. There is a need for new initiatives, innovations, and strategies to
reduce IT operating cost.
Over the past many years, there have been issues with underutilization and
oversubscribed capacity and IT organizations recognize these problems now. Now, with
a limited budget to invest, many IT organizations are rising to the challenge to do more
with less investment and to take decisions for this little investment in hand. Demands are
more, investment is less. Hence, it becomes crucial to identify the underlying basic
principles associated with any solution that will help reduce TCO and achieve higher
ROI.
2012 EMC Proven Professional Knowledge Sharing 56
Appendix: Bibliography
1. Reference Source: Wikipedia http://en.wikipedia.org/wiki/Total_cost_of_ownership
2. http://www.hp.com/sbso/productivity/howto/it_bladesystem/index.html
3. http://www.cisco.com/en/US/solutions/collateral/ns1015/white_paper_c11-687149.pdf, Cisco Economics of Networking, P.No. 3-5
4. David R. Merrill, Storage Economics, Four Principles for Reducing Total Cost of Ownership, May2009, P.No. 8, 9 and 12
5. http://www.conectividad.org/archivo/estudios/tco/vmware.pdf, VMware TCO/ROI Methodology, P.No. 8, 9, 11, 14, 16.
6. Build or Buy? The Economics of datacenter facilities – Rachel A. Dines, July 29 2011 Determining TCO for Datacenter and Network room Infrastructure – APC, Revision 3, White Paper#6
7. http://www.emc.com/collateral/software/white-papers/h8134-it-journey-applications-cloud-wp.pdf, EMC IT’s Journey to the Private Cloud, December 2010, 5-8.
8. EMC Virtual Data Center and Cloud Infrastructure, Cloud Services, 2010, 2011, P.No. 10, 13 and 18.
EMC believes the information in this publication is accurate as of its publication date. The information is subject to change without notice.
THE INFORMATION IN THIS PUBLICATION IS PROVIDED “AS IS.” EMC CORPORATION MAKES NO RESPRESENTATIONS OR WARRANTIES OF ANY KIND WITH RESPECT TO THE INFORMATION IN THIS PUBLICATION, AND SPECIFICALLY DISCLAIMS IMPLIED WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE.
Use, copying, and distribution of any EMC software described in this publication requires
an applicable software license.