    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page1, Total33

    RTN600 Installation Quality StandardVersion 1.0

  • 8/3/2019 RTN600 Installation Quality Standards

    2/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page2, Total33

    ContentsIndoor Installation..................................................................................................4Rack Installation....................................................................................................4Equipment Installation...........................................................................................4RTN600 Installation ..............................................................................................4Power cable routing ..............................................................................................4Power cable from APM .........................................................................................5Power cable routing to cabinet from APM.............................................................5DCDB termination .................................................................................................6Power cable routing from DCDB to equipment .....................................................7

    Indoor Grounding..................................................................................................8Rack Grounding....................................................................................................8RTN600 equipment grounding..............................................................................9Grounding connectors...........................................................................................9IF Cable connection and routing ...........................................................................9Cable connector issues.........................................................................................9Routing through the rack.....................................................................................10Routing on the ladder..........................................................................................10E1 cable routing ..................................................................................................10E1 trunk cable fixing and routing.........................................................................10Optical cable routing ...........................................................................................11

    Indoor Labeling...................................................................................................11DCDB Label........................................................................................................11RTN 600 IDU Label.............................................................................................12DDF panel Label .................................................................................................12Power cable Label ..............................................................................................12IF Cable Label ....................................................................................................13Signal Cable Label..............................................................................................13Optical Cable Label.............................................................................................14Outdoor Standards..............................................................................................14Antenna Installation ............................................................................................14Installation of antenna without offset issues........................................................15Pole installation...................................................................................................17Side bar installation.............................................................................................18Brackets..............................................................................................................20ODU installation..................................................................................................20Direct Mount 1+0,1+1 .........................................................................................20Remote mount ....................................................................................................20IF cable connection and routing..........................................................................21IF cable connection near antenna.......................................................................21Water proof curve ...............................................................................................21Loop near to antenna..........................................................................................22Out door Grounding ............................................................................................22

  • 8/3/2019 RTN600 Installation Quality Standards

    3/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page3, Total33

    ODU Grounding ..................................................................................................22IF cable Grounding .............................................................................................23Waterproof at the groundings .............................................................................24Outdoor Labels ...................................................................................................25IF Cable Label ....................................................................................................25Bundling and fixing the cables using Cable Ties.................................................25Common issues in fixing Cable ties ....................................................................26Appendix.............................................................................................................27Installing the Grounding Clip...............................................................................28IF connector Making procedure ..........................................................................29Installing the ODU on the Antenna......................................................................30

  • 8/3/2019 RTN600 Installation Quality Standards

    4/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page4, Total33

    CodeNo

    Descriptions1 Indoor Installation

    1.1 Rack InstallationRack Should be fixed vertically and fixed to the floor tightly. According tothe floor type, you should use the proper bolts, anger bolts, nuts, springwashers, flat washers etc.Correct way: No all bolts fixed

    Remark: Before start to install the equipment, We have to confirm whetherthe rack is installed properly or not.

    1.2 Equipment InstallationEquipment should be fixed accordance with the rack layout in TSSR and itshould be horizontal. All the four bolts available in the installationaccessories should be used.

    1.2.1 RTN600 InstallationHave to consider the location marked in TSSR rack layout and checkwhether that location is available or not. Then install the equipmenthorizontally using all bolts as shown below

    1.3 Power cable routingPower source for the equipment, for the reference here is taken asAPM200. According to the TSSR Power should be tapped from the powersource.

  • 8/3/2019 RTN600 Installation Quality Standards

    5/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page5, Total33

    1.3.1 Power cable from APMPower cable Should be taken from the APM from the primary (within 1-3terminals) and within(10-11 terminals)Correct way of termination inAPM power.

    One is from the Primary(1-3)and other one is from thetertiary(10-11)

    Wrong Termination in APM

    Power Tapped from 10th and 11th(fromcommon terminal

    1.3.2 Power cable routing to cabinet from APMPower from the APM should be routed to the cabinet using GI pipe. Andthis GI pipe should be laid out properly and neatly according to thestandards.Good way of GI pipe routing Wrong way of GI pipe

    Routing

    Remark:Have to consider the following issues, when you route the power cable throughGI pipe

    GI pipe should be fixed with the wall or floor very tightly

  • 8/3/2019 RTN600 Installation Quality Standards

    6/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page6, Total33

    Open area to get the power cable should be closed with rain proof

    GI pipe size should be according to the requirement. It should not be verybig or very small and also not longer or shorter

    Layout of GI pipe should be very neat and accordance to the standards.

    At the outlet all the cables should be taken out using flexible PVC.

    Grounding the GI pipeWhen you route the GI Pipe have to consider the Grounding of GI Pipe.

    Method 1:The Grounding Horse clip should be tighten with the GI Pipe and It should beconnected to nearest grounding barMethod 2:Drill the GI pipe and fix the grounding bolt and fix the other end to the Grounding

    Bar.

    Remark:If the Black horse (GI coated PVC pipe- Black Color) is used, the inner metalshield will be grounded using the same horse clip.

    1.3.3 DCDB termination

    DCDB should be fixed as the two common working ground bus bars (0Vcommon bus bar) are at bottom as shown in the below photo.When You terminate the Power source and outlet for equipments, have to

    consider the following issues.1. Each power Source cable should be separately terminated andbreakers should be separated for 1+1.2. Power source cable should share the power to the other breakers usingcommon bus bar.3. And the cables for equipments should be taken from the other side.

    Example of correctly installed and terminated DCDB

    Remark:1. Make sure -48V cables(Blue) are routed through the breakers

  • 8/3/2019 RTN600 Installation Quality Standards

    7/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page7, Total33

    2. Make sure that, there is no main breaker that is isolated from the otherbreaker.3. Make sure only one equipment is terminated in one breaker4. Make sure the effective 1+1 distribution.

    1.3.4 Power cable routing from DCDB to equipmentPay attention the following:1. DCDB termination should use the code end terminals of the powercables2. If it is 1+1, both cables should be routed inside the rack (Should use theleft side of the rack) from the DCDB and bound up neatly and tightly as

    shown below.

    3. Dont cross the power cables with signal cables as well dont twist the

  • 8/3/2019 RTN600 Installation Quality Standards

    8/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page8, Total33

    cables when you route inside the rack1.4 Indoor Grounding

    All the equipments, rack should be grounded to the main grounding bardirectly or by another grounding bar using proper grounding cables.Rack Grounding: 16 mm2 yellow green cableEquipments grounding: 5.3 mm2 yellow green cableAll the grounding cables should be grounded using appropriate OTconnectors and fixed properly using proper tools.

    1.4.1 Rack GroundingNEC 19 inch rack1. Have to fix the grounding mesh in the left side2. Grounding mesh should be grounded to the main grounding bar using16 mm2 green yellow grounding cables

    Ericson rackIf it is the 19 inch rack without the grounding mesh (-Ericson rack) then,Rack should be grounded at the TOP point where all equipmentgroundings can be tapped

    Remark: Appropriate OT connectors should be used to connect thegrounding and fixed using relevant Crimping tools.

  • 8/3/2019 RTN600 Installation Quality Standards

    9/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page9, Total33

    1.4.2 RTN600 equipment groundingNEC 19 inch rack with meshThe dual-hole OT terminal of the protection grounding cable must be fixedon the left of the IDU as below. The other side of the grounding cable, wehave to ground to the nearest ground mesh point by fixing the appropriateOT connector.

    Ericson 19 inch rack without the meshAll the grounding cables should be tapped to the main grounding point

    where the rack is grounded to the grounding bar.

    1.4.3 Grounding connectors1. Grounding cables of RTN600 is available with the accessories. One end

    will be available as fixed with dual-hole OT terminal.2. Make sure the cable length for routing to the nearest grounding point.3. 6 mm2 OT connectors should be used for the other end termination.

    1.5 IF Cable connection and routing1. IF cable for RTN 600 have IF Jumper and inch IF cable.2. IF Jumper connected to the 5th or 7th IF board should use the left sideouter routing of the rack.3. IF Jumper connected to the 6th or 8th IF board should use the right sideouter routing of the rack.

    1.5.1 Cable connector issuesIn the IF cable connector making have to consider the following steps

  • 8/3/2019 RTN600 Installation Quality Standards

    10/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page10, Total33

    Clamp1 Clamp2

    1. Check the connection is very tight.2. Check the copper inner wire is long enough as mentioned.3. Ensure the braided shield is fold back to cover clamp 1 tightly.4. Redundant part of the shielding layer should be cut and removed off.

    1.5.2 Routing through the rackIF cable jumper should be routed like below using the outer of the rack. If

    the other sideIf the Board is in slot 5th and 7th

    1.5.3 Routing on the ladderIf the Jumper cable is more, the extra cable should be put in a loop andfixed properly on the ladder.Ensure that the Jumper and the IF cable connection is reliable and fix nearto connector in accessible way.

    1.6 E1 cable routingE1 Cable should be routed through inside the right side rack. Fix the cable

    ties properly.1.6.1 E1 trunk cable fixing and routing

  • 8/3/2019 RTN600 Installation Quality Standards

    11/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page11, Total33

    1.7 Optical cable routing1. Up to the rack and inside the rack Optical cable should be routed usingPVC flexible conduit.

    2. Use the flexible shrink to route the optical fiber to the SL1 or SD1 card.

    1.8 Indoor Labeling1.8.1 DCDB Label

    In DCDB, each breaker should be labeled using permanent markers in anordered way. (Left to Right).

    Breaker Number Label

  • 8/3/2019 RTN600 Installation Quality Standards

    12/33

  • 8/3/2019 RTN600 Installation Quality Standards

    13/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page13, Total33

    1.8.5 IF Cable LabelIF Jumper cable should labeled using the Sticker label as below.

    1.8.6 Signal Cable LabelIf it is the 75 Ohm each and every E1 should be separately labeled.The Label at the DDF side

    To: Information1. Connected link far end Site ID(GAM003)2. Equipment ID (Here RTN1)3. Slot Number (Here Number 4)4. Board Name ( Here PH1)5. E1 port at PH1 port (Here Number 1)6. Whether TX or RX ( Here TX)

    From Information:

    1. Rack Information (Here DDF1)2. DDF Location Number (Here 3rd one)3. E1 port number at I/O board (Here 4th E1)4. Whether RX/TX( Here TX)

    Label at the I/O board near to RTN600 will be as

  • 8/3/2019 RTN600 Installation Quality Standards

    14/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page14, Total33

    For 120 Ohm We have to Label on the Trunk Cable as belowNear to RTN 600

    1.8.7 Optical Cable LabelOptical Fiber to MUX should be Labeled likeTo : Equipment name-Slot Number- Card Name- port number-TX/RXFrom: Equipment name-Slot Number- Card Name- port number-TX/RXE.g.:

    To : OSN2-17SPLT1-1-TXFrom : RTN1-5SD1-1-RXNear to MUXTo : RTN1-5SD1-1-RXFrom : OSN2-17SPLT1-1-TX

    2.0 Outdoor Standards2.1 Antenna Installation

    Antenna locationRefer the TSSR and find out the proper location of antenna.E.g. you can get the information of Antenna height, link azimuth, antennadiameter, hop length etc from this diagram.Note: Confirm the exact location before start the installation.

    Check all the u bolts, brackets support collar, azimuth adjustment collar,elevation adjustment assembly are all installed properly according to the

  • 8/3/2019 RTN600 Installation Quality Standards

    15/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page15, Total33

    standard.Remark: Pls refer separate installation guide for very detail informationabout specific product antenna installation.

    Elevation adjustment assembly should be fixed like below

    2.1.1 Installation of antenna without offset issuesWhen you install the antenna, have to consider the following issues for theeasy maintenance purposes:

    1. Antenna is easy accessible2. ODUs and IF cables are accessible

  • 8/3/2019 RTN600 Installation Quality Standards

    16/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page16, Total33

    Access to the ODU formaintenance is very difficult

    Accessing the ODU formaintenance is easy.

    Remark:When you fix the antenna, You have to ensure whether the right offset orleft offset of the antenna provides easy access to the antenna system.

    Offset Right Offset left

    Remark: In both Cases, the azimuth alignment bolt is at bottom.E.g. ) 3 Meter RFS antenna offset arrangement is as belowOffset left (Standard)- Insert drain plug in hole on the topOffset right

    - Rotate antenna 180 degrees of the reflector.- Rotate radome 180 degrees- Insert drain plug in hole on the top of the reflector.Offset Right Offset Left

  • 8/3/2019 RTN600 Installation Quality Standards

    17/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page17, Total33

    When you change these positions from left to right or right to left plsconsider the followings1. Alignment bolt is at the back side.2. Antenna hanging U cut is upwards.Remark: Each and every type of antenna and changing of brackets andoffsets are different. You have to refer the detail information of relevantantenna installation standards and accordance to that the standardprocedures should be followed.

    2.1.2 Pole installationInstallation of brackets for poleWhen you install the poles, make sure the followings.

    Brackets are suitable accordant to tower legs(L type or Star Type)

    The pole should be vertical and without any tilt Install the breakers according to the standards as shown below.

    Insert all thread bars, washers and ensure they are tight well.

    The following figure show some wrong installation

  • 8/3/2019 RTN600 Installation Quality Standards

    18/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page18, Total33

    If the thread bar is not long enough or the brackets are not suitable for theparticular tower leg please confirm with relevant person.

    Pole should be vertical without any tilt

    Remark: Ensure the fixing holes, to make sure the pole is vertical.

    2.1.3 Side bar installation

    Side Bar should be fixed vertically and horizontally perpendicular to theantenna pad.Generally allowed deviation as follow.

    Limits of strut position for attachment to tower member:

  • 8/3/2019 RTN600 Installation Quality Standards

    19/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page19, Total33

    Correct examples:

    Wrong examples:

    Remark1: if you couldnt find any location to fix the side bar accordancewith the side bar. Pls confirm the solution with relevant acceptance bodyand start to install.Remark2: Each and every types of antenna require different types ofsidebar installations and the tolerance of tilting angles are different to eachother. It is highly expected you have to follow the relevant antennas sidebar installation guide and have to follow the procedures according to that.

  • 8/3/2019 RTN600 Installation Quality Standards

    20/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page20, Total33

    2.1.4 BracketsEnsure all the brackets are appropriate one for the specific requirement.When you install Ensure all bolts, nuts and washers are used to fix thebrackets.

    Side Bar brackets

    2.2 ODU installation2.2.1 Direct Mount 1+0,1+1 Check the side of

    the brackets.Check whether allthe check nuts arethere.Check alignmentbolts are back sideand easy to access.

    2.2.3 Remote mount

    Check No damage bending in the soft waveguideEnter points are waterproofed according to the standardCheck whether the remotely mounted ODUs are fixed in the easy way ofaccessible.

  • 8/3/2019 RTN600 Installation Quality Standards

    21/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page21, Total33

    2.3 IF cable connection and routingPls ensure the following in IF cable routing1. The IF cable should be routed from top downwards and should bebound at the time of routing.2. The specifications and cross-sectional area of the cable, and the routeand position for the cabling should be decided beforehand.3. The cable should be arranged neatly without any overlapping orcrossover.4. The IF cable should be curved for waterproof consideration under theODU and before entering the IDU room.5. The bending radius of the IF cable should be larger than 30 cm.6. The IF cable should be bound by using the cable ties for outdoor useevery one meter.7. The cable ties for outdoor use should face the same direction. Thereshould be a slack of 3 mm to 5 mm before cutting the cable ties.

    If Cable Routing

    2.3.1 IF cable connection near antennaIF connector should be fixed to the ODU firmly and water proofedaccording to the standard(Refer the appendix)

    2.3.2 Water proof curveHave to ensure there should be water proof curve at the entrance to thecabinet and near to the ODU.

  • 8/3/2019 RTN600 Installation Quality Standards

    22/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page22, Total33

    2.3.3 Loop near to antenna1. 3-5 m Loop of IF cable should be neatly fixed near to the ODU and afterthe 1st grounding of the IF cable, to make sure the availability of IF cablefor future alterations and alignment.2. Ensure the loop bending diameter should not be less than 0.6 m

    2.4 Out door GroundingOut door grounding include ODU grounding and IF cable grounding. Whenyou are grounding any cables, ensure one end of the cable is effectivelyconnected the main grounding bar directly or other routes.Remark: All grounding cables should be down wards.

    2.4.1 ODU Grounding

    Remark:1. Grounding cable should be fixed tightly at the ODU and it should berouted downwards.2. Other end should be connected to nearest possible grounding point.3. If Grounding point is not there nearly, first remove the anticorrosionpaint and the oxidizing layer on where you want to fix the grounding.5. The grounding cable should not be spiral.6. After the connection, rustproof and waterproof the grounding points.If you are grounding to the Tower Ensure the paint at the grounding pointise removed and after fixation again repainted

  • 8/3/2019 RTN600 Installation Quality Standards

    23/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page23, Total33

    The grounding cable should be neatly routed and tied and fixed to theshortest possible place as below.

    Practical scenarios of rounding issues:

    2.4.2 IF cable GroundingIF cable should be grounded through out its routing.If the IF cable Length is greater than 60 m IF cable should be grounded in4 points1. Nearest possible from ODU: Before the loop: marked as 12. Before the bending : marked as 23. Mid place in the tower marked as 34. At the entry point : marked as 4

  • 8/3/2019 RTN600 Installation Quality Standards

    24/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page24, Total33

    If the IF cable is less than 60m, then 3 grounding points are enough.1. Near to the ODU2. Before the Bending3. Before the entry point

    Remark:When you ground the IF cable pls consider the following issues1. All grounding cables should be downwards.2. Grounding clip is fully tightened with the outer mesh.3. Water proof is made according to the standard way. Refer 3.1 for howto water proof.

    2.4.3 Waterproof at the groundingsIF cable connector at the ODU needs properly made waterproof.

  • 8/3/2019 RTN600 Installation Quality Standards

    25/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page25, Total33

    For the standard procedure of water proof, Refer the appendix.Check whether IF cable is water proofed properly according to thestandard(Refer the procedure in appendix)

    Check whether Cable ties at top and bottom of water proof

    2.5 Outdoor Labels

    2.5.1 IF Cable Label

    The labels for IF cables should be bound with the IF cables by using thecable ties for outdoor use.

    3.0 Bundling and fixing the cables using Cable TiesCables must be tightly bundled. The bundled cables should be neatlyarranged.For this We have to use three types of cable ties1. Big ,thick and long Black color cable ties: for out door use

    a. IF cable fixing through out the tower.b. To protect the both ends of the water proof

  • 8/3/2019 RTN600 Installation Quality Standards

    26/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page26, Total33

    2. White small cable ties: Indoora. To fix the cables (Power cables, Grounding cables) with the rack

    holes.3. Black long thin cable ties: Indoor

    a. Tight the cables on the ladder

    Cable ties for indoor and outdoor:

    3.1 Common issues in fixing Cable tiesBundlingThe bundling requirements are as follows:1. Do not bind the power cable with other types of cables.

    2. The cables should be bundled neatly.3. Use cable ties of different specifications according to actualcircumstances.4. Do not connect two or more cable ties and use them as one to bundlecables in case the tightness is reduced.5. After the cable ties are fixed, the extra part of the cable ties should betrimmed such that no burrs exist.6. The spacing between the cable ties should be even and should be threeor four times the diameter of the bundle.7 When making turns for bundled cables, ensure that the bending radius isas large as possible so that the cable cores do not break.

  • 8/3/2019 RTN600 Installation Quality Standards

    27/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page27, Total33

    IF routingBlack UV protect tie-wrap should be used, and fixing IF cable by cross

    tightens.For the vertical and horizontal cable run, fixing less than 1m intervals bythe tie-wrap. The IF cable must fix not loosened but not strong tightenedand not any deformation to IF cable.

    4.0 Appendix

    4.1 Waterproofing Outdoor ConnectorsRequired material:

  • 8/3/2019 RTN600 Installation Quality Standards

    28/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page28, Total33

    Step 1: Clean the connector or the grounding clip.Step 2: Uncoil the waterproof insulation tape.Step 3: Stick one end of the tape to the IF cable 2 to 5 cm away from theconnector or the grounding clip. The sticky side should face inwards.

    Step 4: Stretch the tape until it is 3/41/2 as wide as its original size.Stretch the tape in this manner when performing the following steps.Step 5: Wrap the cable spirally towards the connector or the groundingclip at a point that is 2 to 5 cm away from the connector or the groundingclip. Make sure that the overlapping area of the adjacent tape layers is 1/2of the stretched width.Step 6: When the tape reaches a point that is 2 to 5 cm away from theconnector or the grounding clip on the other side, reverse the wrappingdirection so that the tape reaches the starting point.Step 7: When the tape reaches the starting point, reverse the wrappingdirection so that the tape reaches the other ending point. That is, there are

    three layers of waterproof insulation tape.Step 8: After wrapping, squeeze the tape until it sticks to the cable. Thisensures that there is no air between the layers of tape.Step 9: Similarly, wrap three layers of PVC tape over the waterproofinsulation tape. During the wrapping, maintain the stretched length suchthat the width of the PVC tape is to 1/2 of the original size.Step 10: After waterproof processing, use the outdoor bundling strap tobind the PVC tape tightly at the positions 1 cm away from the wrappingedges at both ends, to prevent aging and falling off of the PVC tape.Appearance of waterproofed outdoor connector

    4.2 Installing the Grounding Clip

  • 8/3/2019 RTN600 Installation Quality Standards

    29/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page29, Total33

    Step1: Use an electric knife to strip the cable sheath with the opennessbeing the clip size at the installation location of the grounding clip andexpose the external conductor.

    Step 2: Clip the cable by using the grounding clip and press the cliptightly.The angle between the grounding wire of the clip and the IF cable should

    not be larger than 15 degrees. When the IF cable is vertically routed, thegrounding wire of the clip should be led downwards.

    Step 3: Refer to the above section Waterproofing OutdoorConnectors to waterproof the grounding clips.

    4.3 IF connector Making procedure

    Step 1: Use an electric knife to strip back the 16 mm cable sheath.Stripping back the cable sheath and the insulating layer

    Step2: Fit the lock nut and clamp 1 on the cable.Fitting the lock nut and clamp 1

    Step 3: Fit clamp 2.1. Fold back the braided shield to cover clamp 1.2. Tidy the braided shield and use clamp 2 to bind the braided shield.3. Cut the redundant part of the shielding layer.

  • 8/3/2019 RTN600 Installation Quality Standards

    30/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page30, Total33

    Step 4: Use the electric knife to strip back the dielectric insulating layer infront of clamp 2.During the operation, the exposed cable wire should be 6mm long.Stripping back the insulating layer

    Step 5: Use a file to taper the edge of the core wire about 0.5 mm to makethe top in an arc shape, and clean out the metal filings.Step 6: Fit the connector.

    Step 7: Connect the connector and the lock nut. Use a wrench to tightenthe connection. Use wrench 1 to rotate the lock nut and wrench 2 toposition the body of the connector. The recommended torque is 152 Nm.

    Fastening the connector

    4.4 Installing the ODU on the AntennaStep1: Remove the protective caps from the feed boom of the antennaand from the ODU antenna port. Apply the appropriate quantity of lubricanton the gasket of the feed boom and the surface of the waveguide near thegasket.

  • 8/3/2019 RTN600 Installation Quality Standards

    31/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page31, Total33

    Step 2: Ensure that the V mark on the OTU points in the polarization

    direction of the antenna. If the antenna is vertically polarized, ensure thatthe V mark points upwards or downwards. If the antenna is horizontallypolarized, ensure that the V mark points left or right. Place the ODUantenna port against the feed boom. Slowly fit the feed boom in such thatthe four ODU latches engage with the four antenna hooks.

    Remark: When you install the ODU, the IF port of the ODU should facedownwards.

    4.4.1 Installing the Hybrid Coupler on the AntennaStep 1: Check the polarization direction of the antenna.Step2: If the antenna is vertically polarized, no need to change anythingand go to step 3 or if the antenna is horizontally polarized do the followingto change the polarizationInstall a horizontal polarizer.1. Remove the protective cap from the antenna port on the coupler.2. Remove the polarization component on the antenna port of the coupler.3. Replace the polarization converter on the polarization component byusing a horizontal polarizer.4. Install the polarization component back onto the antenna port on the

  • 8/3/2019 RTN600 Installation Quality Standards

    32/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page32, Total33

    coupler.When you install the polarization component, ensure that the arrow on the

    polarization component points to the H mark on the hybrid coupler.

    Step 3: Remove the protective cap from the feed boom. Apply theappropriate quantity of lubricant on the gasket and the surface of thewaveguide near the gasket.

    Step 4: Apply appropriate anti-seize grease to the four captive screws ofthe coupler.Step 5: Align the antenna port of the coupler over the feed boom. Slowlylet the feed boom fit in such that the four latches engage with the antennahooks.When installing the hybrid coupler on the antenna, the ODU port identifiers

    marked on the hybrid coupler such as "MAIN" and "STD BY" should faceupwards.

  • 8/3/2019 RTN600 Installation Quality Standards

    33/33

    RTN600 Installation Quality StandardVersion 1.0

    Security Level: Internaluse only

    2009-03-03 HUAWEI Confidential Page33, Total33

    Step 6: Close the four latches cornerwise.Step 7: Rotate the four captive screws of the coupler about 70% andtighten them cornerwise.