+ All Categories
Home > Documents > Rutting in Flexible Pavements – A Case Study (1)

Rutting in Flexible Pavements – A Case Study (1)

Date post: 10-Feb-2018
Category:
Upload: ala-thajil
View: 217 times
Download: 0 times
Share this document with a friend

of 15

Transcript
  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    1/15

    Paper No. 535

    RUTTING IN FLEXIBLE PAVEMENTS A CASE STUDY

    V.K. SINHA*, H.N. SINGH** & SAURAVSHEKHAR***

    ABSTRACT

    Flexible pavements are generaly adopted for construction of roads in India. Bitumen as a binder is known to be highly

    sensitive to high temperatures. Distresses in the form of ruts, cracking, ageing etc. are common on Flexible pavements.

    These are still observed on pavements constructed presently with thick layers of binder courses at high cost. Rutting one of

    the commonly observed permanent nature distress is the subject matter of this case study. The effect of high pavement

    temperature on the stability of mix in conjunction with lower softening point of bitumen has been studied in the context of

    prevail ing high temperature in top pavement layers. Study brings out the inadequacies in existing specifications and

    suggests some follow up actions to improve the existing specifications. Use of modifiers in the top binder courses like DBM

    to enhance the thermal dependent characteristics of the bituminous mixes is one of the recommendations. Adoption of

    catalogue type performance based specifications covering different climatic regions of the country are also suggested.

    1. INTRODUCTION

    Flexible pavements have been traditionally provided

    on most of the important highways of the country. Thick

    bituminous pavement layer broadly comprising of a DBM

    layer of 160 to 180 mm topped with 50 mm bituminous

    concrete are being provided presently by way of

    strengthening. The bitumen used in the design of mixes

    for SDBC, PC, DBM and BM is typically of 60/70 grade.

    However, in few cases wearing course, having

    bituminous concrete 50 mm thick is also being provided

    with modified bitumen. Modifiers in such cases are either

    CRMB or PMB. Use of modifiers, however, is not

    common. The design of mixes are being done as perMarshall method with normal 75 blows for all locations

    without considering the effects of climatic, traffic

    variations etc.

    Despite the construction of thicker pavement, such

    bituminous pavements suffer from rutting frequently in

    quite early age. Such deformations in the form of rutting

    are more pronounced at locations of intersections, curves

    and in stretches where heavy traffic operates with low

    speed and is subject to frequent stop/start condition. Such

    early rutting of the flexible pavements should concern

    all highway engineers. This is particularly so, whenconstructing long performing pavements is the moto of

    all highway agencies in view of huge investment being

    made on the construction of such highways.

    The Paper is based on a case study representing a

    typical rutted stretch of a four-lane road which has been

    * Secretary General, IRC } E-mail: [email protected]

    ** Executive Engineer (Retd.) PWD Bihar, Material Engineer, Quest Consultants Pvt. Ltd.

    *** Director, SA Infrastructure Consultants Pvt. Ltd.

    Written comments on this Paper are invited and will be received upto 31st December, 2007

    widened and strengthened recently with thick bituminous

    pavement layers. The effect of high temperature ofpavement layers on in-service behaviour of compacted

    bituminous mixes is the key objective of this case study.

    2. STUDY STRETCH

    The stretch considered is about 250 m long, suffering

    substantial rutting to a maximum depth upto 35 mm. This

    stretch is near an intersection. Heavy trucks with high

    axle loads in large number (about of 4500 trucks per

    day) are operating on this stretch, at a relatively low

    speed with frequent stop/start condition. The crust

    composition of this stretch is given in Table 1.

    S.No. Type of layer Thickness

    (mm)

    1. Bituminous Concrete (BC with CRMB 60) 5 0

    2. Dense Bitumen Macadam (DBM Layer II) 8 0

    3. Dense Bitumen Macadam (DBM Layer I) 8 0

    4. Wet Mix Macadam (WMM) 250

    5. Granular Sub-Base (GSB) 260

    The study stretch comprises both types of surfaces

    (i) Exposed DBM surface without BC and (ii) DBM

    layer covered with BC surface in adjoining length. Same

    traffic is operating on both these surfaces. Time lag

    between laying of DBM and laying of BC on the DBM

    is on average about six months plus.

    TABLE 1. CRUSTCOMPOSITION ATTHESTUDYSTRETCH

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    2/15

    178 SINHA, SINGH& SHEKHARON

    3. RUT DEPTH MEASUREMENT

    The rut depth measurements has been done in the

    field using a string line across the carriageway. The details

    of rut depth with assumed chainages are furnished in

    Table 2. Fig 1 depicts the general appearance of therutted portion.

    Cores were taken from both rutted and fair locations.

    At rutted locations, the top layer of DBM (Layer II)

    was observed to have undergone deformations, whereas

    TABLE2. DETAILSOFRUTDEPTH

    Off-set from Kerb edge (m)

    Chainage 1 2 3 4 5 6 7

    102.300 14 16 11 7 3 2 1

    102.250 22 21 18 15 14 11 2

    102.200 8 9 10 9 9 8 4

    102.150 12 12 11 11 5 4 2

    102.100 12 9 6 6 2 1 -2

    102.050 12 1 9 0 5 0 1

    102.000 21 15 15 4 5 2 2

    101.950 12 2 1 0 1 -4 -2

    101.900 23 10 18 10 6 2 2

    101.850 28 5 14 - 4 - 2 - 1 - 2

    101.800 32 Junction Crossing

    101.770 33 12 19 2 14 8

    101.750 26 4 21 -5 10 4 8

    101.720 22 8 21 6 5 6 8

    101.700 10 2 17 6 5 6 8

    101.650 12 9 15 10 18 14 8

    101.600 9 2 4 3 5 9 9

    Fig 1. Showing the Rutted Portion of the Pavement

    (Not to Scale)

    BC layer, in general, was not found significantly

    disturbed. Subsidence under the wheel paths was

    observed to be due to the deformation of top layer of

    DBM. The above observations reveal that the actual

    rutting is due to permanent deformation in the DBM

    (Layer II), immediately underneath the BC layer.

    Both the bituminous mix material as taken from the

    cores at rutted locations and at fair locations, were tested

    in the laboratory for the engineering properties. Tables 3

    and 4 give the test details for the BC portion at rutted

    and fair locations respectively. It is seen that the density

    of the mix are same for both locations. Marginally higher

    bitumen content has been noted in the rutted portion.

    Optimum Bitumen Content (OBC) under job-mix formula

    (JMF) was 5.0 per cent with permissible variation of

    0.3 per cent. Such marginal variations could be due to

    migration of bitumen during formation of the rut, due to

    movement of aggregates from rutted portion and due to

    some aggregate particles being cut partly through cutting

    of the cores. Some reduction in air voids is also noticed.

    These factors might contribute marginally to the process

    of rutting or may even have arisen due to rutting. The

    variations are, however, insignificant.

    4. INVESTIGATION DONE

    The methodology of investigation is based on the

    TABLE

    3. ENGINEERING

    PROPERTIES

    OF

    RUTTED

    PORTION

    OF

    BC

    Core Density Bitumen FI + Air

    No. (gm/cc) content EI Voids

    (%) (%) (%)

    01 R 2.511 5.475 3.09

    02 R 2.497 5.551 32.70 3.63

    03 R 2.508 5.520 3.20

    TABLE 4. ENGINEERINGPROPERTIES OFFAIRPORTION OFBC

    Core Density Bitumen FI + Air

    No. (gm/cc) content EI Voids

    (%) (%) (%)

    01 S 2.5 5.080 3.9

    02 S 2.496 5.137 29.34 3.67

    03 S 2.486 5.105 4.05

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    3/15

    HIGHLIGHTSOFTHE178THCOUNCILMEETING 179 RUTTINGINFLEXIBLEPAVEMENTS- A CASESTUDY

    process of elimination of lesser or insignificant causes

    to enable focusing on the main cause. Rutting in

    bituminous pavement can occur due to variety of causes.

    Some of the common causes for rutting could be as given

    below.

    Inappropriate mix design

    Incorrect grading

    Excessive Binder content

    Excessive fines like sand/clay

    Round aggregates with smooth texture

    Inadequate initial field compaction and density

    Effects of hot weather temperature on

    pavement

    Effects of heavy traffic loads

    Effect of slow speed (frequent stop/start or

    stationary condition)

    Effect of secondary compaction

    4.1. Inappropriate Mix Design

    Initial mix design was done by Marshall method with

    75 blows. Grading of aggregates followed in actual

    execution are broadly as prescribed under Job-Mix

    Formula (JMF). The Design Bitumen Content (OBC)

    has been arrived as per Marshall test.

    Tables 5, 6 & 7 give the details of the gradation and

    other engineering properties of BC mix with CRMB 60,

    as used in actual construction of the rutted portion. Tables

    8, 9 &10 give similar details for DBM (Layer II)

    underneath BC. From the perusal of the tables it will be

    seen that actual execution has been done in accordance

    with MOSRT&H Specifications and as per JMF. Some

    marginal variations in gradation determined by extraction

    of bitumen and from dry aggregates taken from Hot

    Bins are just natural and are not significant. Binder content

    also appears to be as per JMF and MOSRT&H

    Specifications. Natural sand has not been used. Similarly,

    rounded aggregates are also not used as is evident from

    Photo 1.

    Sieve Sizes 26.5 19.0 13.2 9.5 4.75 2.36 1.18 0.60 0.30 0.15 0.075

    (Percent Passing)

    Range as per 100 90 - 59 - 52 - 35 - 28 - 20 - 15 - 10 - 5 - 2 - 8

    MOSRT& H 100 79 72 55 44 34 27 20 13

    Specifications

    As per approved 100 94 74 63 46 35 25 19 13 9 6

    JMF

    Permissible 7 7 6 6 5 4 4 4 3 3 1.5

    Variation for JMF

    Date Sample Gradation as per samples taken at the time of laying mix at rutted locations

    No.

    18.4.05 BC/33 100 93.45 73.17 64.57 46.55 34.26 25.86 18.08 12.14 8.15 6

    BC/34 100 94.11 75.19 63.59 46.19 35.12 24.14 18.16 11.56 8.26 7

    26.4.05 BC/35 100 95.4 73.21 66.09 45.68 34.17 26.11 18.16 12.09 8.11 5

    BC/36 100 93.74 72.55 65.84 45.1 34.82 25.16 18.72 12.1 8.7 6

    TABLE5. SUMMARYOFAGGREGATEGRADATIONFORBC (CRMB 60)

    (GRADATIONAFTEREXTRACTIONOFBINDER)

    Photo 1.

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    4/15

    180 SINHA, SINGH& SHEKHARON

    TABLE 7. SUMMARY OFACTUAL BITUMENCONTENTVS DESIGNBITUMENCONTENT

    Properties Binder Bulk Air VMA VFB Stability Retained Flow Stability AIV FI & Average

    Measured content Density Voids (%) (%) (kg.) Stability (mm) / Flow (%) EI Core

    (%) (gm/cc) (%) (%) (kg/mm) (%) Density

    (gm/cc)

    Properties as per 5.00 2.480 4.28 16.05 71.0 1240 95.17 3.2 987.5 15.23 24.85

    approved JMFSpecified Limit Min Not 3 - 5 Min 14 65 - 75 Min 90 2.5 - 250 Max Max

    as per MOSRTH 5.0 specific to 16 1200 Min 4.0 - 500 30 30

    Specifications

    Date Sample As per actual samples taken at the time of laying mix at rutted locations

    No.

    18.4.05 BC/33 5.010 2.474 4.48 15.44 71.0 1358.8 96.6 2.87 473.45 16.14 26.8 99.56

    BC/34 5.002 2.473 4.52 15.46 70.76 1375.17 2.90 474.2 15.57 26.3

    26.4.05 BC/35 5.020 2.472 4.52 15.5 70.8 1418.7 96.9 2.93 484.2 15.5 27.6 99.35

    BC/36 5.011 2.472 4.52 15.5 70.8 1386.0 2.93 473.04 15.8 27.9

    Sieve Sizes (Percent 45.0 37.5 26.5 13.2 4.75 2.36 0.30 0.075

    Passing)

    Range as per MOSRT&H 100 95-100 63-93 55-75 38-54 28-42 7-21 2-8

    Specifications

    As per approved JMF 100 100 85 63 45 34 13 4

    Permissible Variation for 8 8 8 7 6 5 4 2

    JMF

    TABLE8. SUMMARYOFMEASUREDAND CALCULATED PROPERTIES OFDENSEBITUMINOUSMACADAM (DBM) (60/70)(GRADATIONAFTEREXTRACTIONOFBINDER)

    Sieve Sizes 26.5 19.0 13.2 9.5 4.75 2.36 1.18 0.60 0.30 0.15 0.075

    (Percent Passing)

    Range as per 100 90 - 59 - 52 - 35 - 28 - 20 - 15 - 10 - 5 - 2 - 8

    MOSRT&H 100 79 72 55 44 34 27 20 13

    Specifications

    As per approved 100 94 74 65 46 35 25 19 13 9 6

    JMF

    Permissible 7 7 6 6 5 4 4 4 3 3 1.5

    Variation for JMF

    Date Sample Gradation as per samples taken at the time of laying mix at rutted locations

    No.

    18.4.05 BC/33 100 93.9 73.22 63.2 44.66 33.68 24.75 17.25 10.10 7.87 6

    BC/34 100 93.2 72.55 64.33 43.99 33.61 24.81 18.56 12.93 9.79 726.4.05 BC/35 100 94.5 76.2 67.11 44.71 36.13 24.68 20.07 14.17 8.89 5

    BC/36 100 92.8 73.2 66.7 46.38 36.08 28.2 22.22 15.72 8.90 6

    TABLE6. SUMMARYOFAGGREGATEGRADATIONOFDRYAGGREGATESFORBC (CRMB 60)

    (GRADATIONDETERMIND FROMDRYAGGREGATES FROMHOTBINS)

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    5/15

    HIGHLIGHTSOFTHE178THCOUNCILMEETING 181 RUTTINGINFLEXIBLEPAVEMENTS- A CASESTUDY

    Date Sample No. Gradation as per samples taken at the time of laying mix at rutted locations

    2.8.04 DBM/272 100 100 85.08 63.65 46.21 34.24 13.68 4.48

    DBM/ 273 100 100 84.84 63.42 45.98 33.45 13.04 4.57

    3.8.04 DBM/274 100 100 84.34 62.14 44.27 34.60 12.12 4.20

    DBM/ 275 100 100 86.52 63.53 46.47 35.49 14.48 4.55

    4.2. Compaction and Density

    Details of Table 7 for BC and Table 10 for DBM

    suggest that there is no significant problem due to lack

    of compaction and inadequate density of the rutted portion

    at the time of execution. The compaction density does

    not appear to be a significant cause of rutting from the

    specifications point of view.

    4.3. Effect of High Pavement Temperature on

    Performance of BC and DBM Layer

    The key objective of the case study was to assess

    the likely effect of high temperature on the performance

    of top bituminous layers in a flexible pavement. It is a

    common knowledge that bitumen as a material is quite

    sensitive to high temperature. Stability aspects of bitumen

    TABLE 10. SUMMARYOFMEASURED AND CALCULATED PROPERTIES OFDENSEBITUMINOUSMACADAM (DBM) (60/70)

    (ASPERLABTESTSRESULTOFRUTTEDSAMPLES)

    Properties Measured Binder Bulk Air VMA VFB Stability Flow FI & AIV Average

    content Density Voids (%) (%) (kg.) (mm) EI (%) (%) Core(%) (gm/ (%) Density

    cc) (gm/cc)

    Properties as per JMF 4.580 2.43 4.20 14.90 71.74 1120 2.82 26.84 13.1 98%

    Specified Limits as per Min 4.0 Not 3 - 6 Min 66.75 Min. 990 2 - 4 < 30 < 30

    MOSRT&H specified 12 to

    Specifications 14

    Date Sample No. As per actual samples taken at the time of laying mix at rutted locations

    2.8.04 DBM/272 4.59 2.481 4.39 14.97 70.67 1321.1 2.33 26.86 16.77 98.99

    DBM/273 4.60 2.470 4.82 15.36 68.62 1152.3 2.50 27.99 17.20

    3.8.04 DBM/274 4.57 2.479 4.32 15.62 71.24 1272.2 2.40 25.85 17.44 98.95

    DBM/275 4.58 2.477 4.40 15.10 70.86 1137.6 2.40 27.36 16.97

    TABLE9. SUMMARYOFMEASUREDAND CALCULATED PROPERTIES OFDENSEBITUMINOUSMACADAM (DBM) (60/70)

    (GRADATIONDETERMINEDFROMDRYAGGREGATESTAKENFROMHOTBINS)

    Sieve Sizes (Percent 45.0 37.5 26.5 13.2 4.75 2.36 0.30 0.075

    Passing)

    Range as per MOSRT&H 100 95-100 63-93 55-75 38-54 28-42 7-21 2-8

    Specifications

    As per approved JMF 100 100 85 63 45 34 13 4

    Permissible Variation for 8 8 8 7 6 5 4 2

    JMFDate Sample No. Gradation as per samples taken at the time of laying mix at rutted locations

    2.8.04 DBM/272 100 97.50 82.65 63.09 43.9 32.93 13.61 4.48

    DBM/ 273 100 98.56 85.76 62.45 44.55 35.46 15.51 5.98

    3.8.04 DBM/274 100 100 84.34 62.14 44.27 34.60 12.12 4.20

    DBM/ 275 100 100 86.52 63.53 46.47 35.49 14.48 4.55

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    6/15

    182 SINHA, SINGH& SHEKHARON

    mix for both top BC layer and underneath DBM layer

    were accordingly investigated.

    4.3.1.Measurement of pavement temperature:

    Two different types of thermometers were used for

    recording the temperature.One was electronicallycontrolled digital thermometer and the other was ordinary

    glass mercury thermometer. These were duly calibrated

    before the measurement. The ambient air temperature

    on the day of measurement was 48 oC layer-wise

    pavement temperature was measured during the peak

    summer hour of 2.30 P.M. in the month of June 2007.

    The temperature measurement was done on the

    rutted portion of the pavement at number of locations.

    The temperature was measured at different locations

    depth-wise in increment of 20 mm. The first measurement

    was done at 20 mm below the top of BC surface and

    thereafter it was measured broadly at the interface of

    BC and underlying DBM layer. The measurement in

    DBM layer continued thereafter at interval depth of every

    20 mm. The layer-wise pavement temperature was

    measured for both locations i.e. covered with 50 mm

    BC wearing course as well as at locations where top

    surface of DBM was not covered with BC. The

    corresponding layer-wise temperatures as measured are

    furnished in Table 11. Fig 2 again shows these

    temperatures layerwise. Fig 3 shows the equipment

    used for making the temperature measurement.

    From the perusal of the Table 11, it will be seen that

    TABLE11. LAYERWISERECORDINGOFTEMPERATUREDATED7.6.07 AT2.30 PM

    DBM Layers Exposed to Sun (Partial Construction) DBM Layer Covered with BC CRMB-60 (Completed

    Cosntruction)

    Location of Temperature Temperature Location of Temperature Temperature

    recorded in Digital in Glass recorded in Digital in Glass

    temperature Thermometer Thermometer temperature Thermometer Thermometer

    in (oC) in (oC) in (oC) at particular in (oC) in (oC) in (oC)

    place near

    chowk

    Top surface 68.2 67 Top surface 60.2 59

    of DBM (at the of BC (at the

    depth of 20 mm depth of 20

    from top) mm from top)

    Below 20 mm 63.7 63 Below 50 mm 57.3 56

    (from above) BC (at the inter

    -face of BC and

    DBM layer)

    Below 40 mm 58.8 58 Below 20 mm 55 54

    (from DBM Top

    surface)

    Below 60 mm 56 54 Below 40 mm 54.2 53

    (from DBM Top

    surface)

    Below 80 mm 53.9 52 Below 60 mm 52.7 51

    (from DBM Top

    surface)

    Below 100 mm 53.9 52 Below 80 mm 51.3 50

    (from DBM Top

    surface)

    Below 100 mm 50.2 49

    from DBM Top

    surface)

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    7/15

    HIGHLIGHTSOFTHE178THCOUNCILMEETING 183 RUTTINGINFLEXIBLEPAVEMENTS- A CASESTUDY

    the pavement temperature in top BC layer was observed

    to be 60oCand at the interface of DBM and BC layer it

    was 57oC. Against this, the pavement temperature in

    the top DBM layer (where BC has not been laid) was

    68.2oC. The difference of 8 oC is due to better

    characteristic of CRMB modifier with respect to specific

    heat and other associated thermal attributes. It is furtherobserved that the temperature gradient also, is less steep

    at locations covered with CRMB 60 than the locations

    where top layer was DBM without BC. The advantage

    of modifiers like CRMB in this respect needs to be noted.

    4.3.2. Softening point of bitumen used: The

    bitumen of 60/70 grade was procured from Panipat and

    Halida refineries. As per the test results done by the oil

    companies, the softening point was 49oC (Panipat) and

    47oC (Haldia). The softening point for CRMB as per

    Panipat refinery test was 61oC. The softening point of

    60/70 grade bitumen used, when compared with thepavement temperature in DBM layer (vide Table 11) is

    much lower than the temperature of corresponding

    pavement layers.

    The summer temperature, broadly of this or still

    higher range, normally occurs in the plains of India for

    at least three months. During these months the

    bituminous mixes of the pavement layers are obviously

    in a very soft state of cohesion. The heavy traffic

    operating during these months actually subject the mix

    Fig. 3. Temperature Measured under the different Layers

    of Pavement

    Fig. 2. (a) Layer-wise Temperatures of Location having

    DBM with BC (CRMB 60) (Not to scale)

    BC (CRMB) 60 (50 mm) 60oC

    57oC

    DBM (Layer II) with 60/70 grade bitumen

    Thickness - 80 mm

    54oC

    52oC

    51oC

    DBM (Layer I) with 60/70 grade bitumen

    Thickness - 80 mm 50oC

    WMM

    Thickness 250 mm

    GSB

    Thickness 260 mm

    55oC

    Fig. 2. (b) Layer-wise Temperatures of Location having

    DBM without BC (Not to scale)

    DBM (Layer II) with 60/70 grade bitumen

    exposed to Sun 68.2oC

    63.7oC

    Thickness 80 mm 58.8oC

    56oC

    DBM (Layer I) with 60/70 grade bitumen

    53.9oC

    Thickness 80 mm

    WMM

    Thickness 250 mm

    GSB

    Thickness 260 mm

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    8/15

    184 SINHA, SINGH& SHEKHARON

    of top DBM layers into a kneading action. The

    determination of stability by applying blows as per

    Marshall, therefore deserves reconsideration. Hveem

    method is more suitable under such situations.

    Specifications should look into this aspect, because

    according to authors the temperature of the mix higherthan softening point may be a significant factor to the

    occurrence of rutting in flexible pavements in our country.

    According to Australian Asphalt Pavement Association

    (AAPA) Asphalt guide (Table 3.2 of the guide), pavement

    temperatures as reproduced in Table 12 are to be rated

    as high to medium temperature category, deserving

    special consideration for the selection of bitumen type,

    including mix design.

    Temperature Category Maximum Pavement

    Temperature

    High > 58oC

    Medium 52oC - 58oC

    Low < 52oC

    4.3.3.Stability loss study:Stability of the mix is

    one of the key design consideration in the Marshall

    method of design. IRC:SP:53-2002 prescribes

    requirements of mix prepared with modified bitumen.

    This is reproduced in Table 13. It will be observed that

    minimum Marshall stability (75 blows) at 60oC is 1200

    kg. It also prescribes the requirement of minimum

    retained stability of 90 per cent after 24 hours in water

    bath at 60oC. For high rainfall areas it is 100 per cent.

    Minimum Marshall stability for both BC and DBM with

    60/70 grade bitumen as prescribed in MOSRT&H

    Specifications (Fourth Revision 2001) is 900 kg only. No

    criteria for retained stability has been prescribed in

    MOSRT&H Specifications for BC and DBM with 60/

    70 grade bitumen. Prescribing same stability for BC and

    DBM (900 kg) and not prescribing any minimum

    percentage for retained stability in normal 60/70 gradebitumen is a gap in the specifications. It needs to be

    addressed.

    The tests for Retained Stability is done as per ASTM

    D-1075. ASTM D-1075 basically prescribe the

    procedure to evaluate the effect of hot weather

    temperature on cohesion of compacted bituminous mixes.

    For this purpose, the procedure prescribes conducting

    (Source: IRC:SP:53-2002)

    (Source: AAPA, Asphalt Guide 2002)

    TABLE 12. PAVEMENTTEMPERATURE

    TABLE13. REQUIREMENTSOFMIXPREPAREDWITHMODIFIEDBITUMEN

    Sl.No. Properties Requirement Method of Test

    Hot Climate Cold Climate High Rainfall

    1. Marshall Stability 1200 1000 1200 ASTM:D:1559-

    (75 blows)at 60oC, 1979

    kg, Minimum

    2. Marshall Flow at 2.5 -4.0 3.5-5.0 3.0-4.5 ASTM:D:1559-

    60oC, mm 1979

    3. Marshall Quotient 250-500 Stability /flow

    kg/mm

    4. Voids in 3.0-5.0

    compacted mix, %

    5. Requirement of 90 95 100 ASTM:D:1075-

    retained stability 1979

    after, 24 hours in

    water at 60oC, %

    Minimum

    6. Coating with 95 95 100 AASHTO T 182

    aggregate, %

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    9/15

    HIGHLIGHTSOFTHE178THCOUNCILMEETING 185 RUTTINGINFLEXIBLEPAVEMENTS- A CASESTUDY

    TABLE14. RETAINEDSTABILITYOFBC MIXAFTER24 HOURSATDIFFERENTTEMPERATURES

    Retained Stability = 24 hours stability * 100

    at 650C 30 minute stability

    = 1161.2 *100 = 93.40%

    1243.3

    Compaction 75 blows Date- 3/7/07 to 4/7/07

    Binder CRMB-60

    STABILITY AFTER 24 HOURS IN WATER BATH @65

    0

    CSl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen (cc)

    (A) (B) (C) (D)* E = BxCxD

    1 486.5 385 2.767 1.09 1161.2 4.4

    2. 483.5 390 2.767 1.09 1176.3 4.5

    3. 484.0 380 2.767 1.09 1146.1 4.3

    1161.2 4.40

    STABILITY AFTER 30 MINUTES IN WATER BATH @600C

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen

    (in cc)

    1 486.0 415 2.767 1.09 1251.7 2.9

    2. 480.5 400 2.767 1.14 1261.7 3.3

    3. 485.5 410 2.767 1.09 1236.6 3.2

    4. 484.0 405 2.767 1.09 1221.5 3.4

    5. 483.5 415 2.767 1.09 1251.7 3.0

    6. 487.0 410 2.767 1.09 1236.6 3.1

    1243.4 3.15

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen

    (in cc)

    1 486.5 395 2.767 1.09 1191.3 3.6

    2. 484.5 405 2.767 1.09 1221.5 3.4

    3. 485.0 395 2.767 1.09 1191.3 3.6

    1201.4 3.53

    STABILITY AFTER 24 HOURS IN WATER BATH @600C

    Retained Stability = 24 hours stability * 100

    at 600C 30 minute stability

    = 1201.4 *100 = 96.63%

    1243.3

    * D is corelated to A

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    10/15

    186 SINHA, SINGH& SHEKHARON

    STABILITY AFTER 30 MINUTES IN WATERT BATH @600C

    Retained Stability = 24 hours stability * 100at 650C 30 minute stability

    = 995.3 *100 = 82.50%

    1206.4

    Compaction 75 blows

    Binder 60/70 bitumen

    STABILITY AFTER 24 HOURS IN WATER BATH @ 600C

    TABLE15. RETAINEDSTABILITYOFBC MIXAFTER24 HOURSATDIFFERENTTEMPERATURES

    Compaction 75 blows Date- 4/7/07 to 5/7/07

    Binder 60/70 Bitumen without CRMB

    STABILITY AFTER 24 HOURS IN WATER BATH @650C

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen(cc)

    (A) (B) (C) (D)* E = BxCxD

    1 487.5 320 2.767 1.09 965.1 4.6

    2. 483.5 330 2.767 1.09 995.3 4.9

    3. 486.5 340 2.767 1.09 1025.5 4.7

    995.3 4.73

    Retained Stability = 24 hours stability * 100

    at 600C 30 minute stability

    = 1110.9 *100 = 92.08%

    1206.4

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)specimen

    (in cc)

    1 485.5 400 2.767 1.09 1206.4 2.8

    2. 481.5 395 2.767 1.14 1191.3 2.9

    3. 486.0 400 2.767 1.09 1206.4 3.1

    4. 484.5 390 2.767 1.09 1176.3 3.0

    5. 484.0 410 2.767 1.09 1236.6 3.2

    6. 487.0 405 2.767 1.09 1221.5 3.3

    1206.4 3.05 mm

    * D is corelated to A

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen

    (in cc)

    1 484.5 360 2.767 1.09 1085.8 3.8

    2. 486.0 375 2.767 1.09 1131.0 3.7

    3. 483.5 370 2.767 1.09 1115.9 3.8

    1110.9 3.77 mm

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    11/15

    HIGHLIGHTSOFTHE178THCOUNCILMEETING 187 RUTTINGINFLEXIBLEPAVEMENTS- A CASESTUDY

    TABLE16. RETAINEDSTABILITYOFDBM MIXAFTER24 HOURSATDIFFERENTTEMPERATURES

    Compaction 75 blows Date-7/7/07 to 9/7/07

    Binder 60/70 Bitumen

    STABILITY AFTER 24 HOURS IN WATER BATH @550C

    Retained Stability = 24 hours stability * 100

    at 550C 30 minute stability

    = 1095.8 *100 = 91.71%

    1194.9

    Binder 60/70 bitumen

    STABILITY AFTER 24 HOURS IN WATER BATH @600C

    STABILITY AFTER 30 MINUTES IN WATER BATH 600C

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen

    (in cc)

    1 486.5 330 2.767 1.09 995.3 3.8

    2. 484.0 345 2.767 1.09 1040.5 4

    3. 487.0 330 2.767 1.09 995.3 3.7

    1010.4 3.8

    Retained Stability = 24 hours stability * 100

    at 600C 30 minute stability

    = 1010.4 *100 = 84.56%

    1194.9

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen(cc)

    (A) (B) (C) (D)* E = BxCxD

    1 486.5 370 2.767 1.09 1115.9 3.3

    2. 488.5 365 2.767 1.09 1100.9 3.2

    3. 484.5 355 2.767 1.09 1070.7 3.0

    1095.8 3.2

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen

    (in cc)

    1 486.5 390 2.767 1.09 1176.3 2.9

    2. 487.5 395 2.767 1.09 1191.3 2.7

    3. 481.5 410 2.767 1.14 1293.3 3.1

    4. 484.5 360 2.767 1.09 1085.5 3.7

    5. 480.0 400 2.767 1.14 1261.8 34

    6. 483.5 385 2.767 1.09 1161.2 3.3

    1194.9 3.18

    * D is corelated to A

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    12/15

    188 SINHA, SINGH& SHEKHARON

    TABLE17. RETAINEDSTABILITYOFDBM MIXAFTER24 HOURSATDIFFERENTTEMPERATURES

    Compaction 75 blows Date-30/6/07 to 2/7/07

    Binder 60/70 Bitumen

    STABILITY AFTER 24 HOURS IN WATER BATH @600C

    Retained Stability = 24 hours stability * 100

    at 600C 30 minute stability

    = 990.3 *100 = 81.58%

    1213.9

    Compaction 75 blows

    Binder 60/70 bitumen

    STABILITY AFTER 24 HOURS IN WATER BATH @650C

    STABILITY AFTER 30 MINUTES IN WATER BATH @600C

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen

    (in cc)

    1 497.5 405 2.767 1.04 1165.5 3.2

    2. 486.5 395 2.767 1.09 1191.3 3.1

    3. 484.5 415 2.767 1.09 1251.7 2.9

    4. 480.0 400 2.767 1.14 1261.8 3.0

    5. 485.0 390 2.767 1.09 1176.3 2.8

    6. 487.5 410 2.767 1.09 1236.6 2.6

    1213.9 2.93

    Retained Stability = 24 hours stability * 100

    at 650C 30 minute stability

    = 774.6 *100 = 63.81%

    1213.9

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen

    (in cc)

    1 498.5 265 2.767 1.04 762.6 5.5

    2. 496.5 270 2.767 1.04 777.0 6.3

    3. 488.0 260 2.767 1.09 784.2 3.3

    774.6 5.0

    Sl. No Volume of Proving Ring Calibration factor Volume CORRECTED FLOW IN

    marshall Reading of Proving Ring Correction VALUE (Kg) (mm)

    specimen(cc)

    (A) (B) (C) (D)* E = BxCxD

    1 486.5 335 2.767 1.09 1010.4 3.6

    2. 483.5 330 2.767 1.09 995.3 3.7

    3. 487.0 320 2.767 1.09 965.1 3.3

    990.3 3.5

    * D is corelated to A

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    13/15

    HIGHLIGHTSOFTHE178THCOUNCILMEETING 189 RUTTINGINFLEXIBLEPAVEMENTS- A CASESTUDY

    the tests at a temperature of 60oC 1oC. These tests

    are done in a bath tub at 60oC by keeping the samples

    both for 30 minutes and for 24 hours. The stability after

    30 minutes and after 24 hours is compared and the ratio

    of the stability values gives the retained stability (per

    cent basis) at the temperature of 60 oC. This loss of

    stability with temperature is a measure of stable

    performance of the bituminous mixes at high temperature.

    Ten number of samples have been tested in the

    laboratory to study the effect of high temperature in terms

    of the retained stability. These samples have been taken

    for different types of bitumen mixes i.e. BC with CRMB

    60, BC with 60/70 grade, bitumen (without CRMB),

    DBM with 60/70 grade bitumen (without CRMB). The

    samples have been taken directly from batch mix plant

    producing these mixtures as per the JMF and as used in

    the construction of the rutted portion of the road project,

    comprising the study stretch for this case study.

    Details of these tests are furnished in Tables 14 to

    17. The JMF for this stretch prescribes a retained stability

    of 95 per cent for BC (CRMB 60) layer. Fig 4 shows in

    a graphical form the retained stability (per cent basis) of

    different mixes at temperatures 650C & 600C after 24

    hours as compared to stability value at 600C after 30

    minutes. Fig 5 shows, in the form of a histogram, the

    stability values of these mixes at the temperatures of

    600C and 650C. The typical values presented in the

    Tables and Figures as above, indicate the likely loss of

    stability at high temperature. This is interesting when

    compared with the lower softening points of these mixes.

    It is observed that loss of stability is substantial at a higher

    temperature, particularly in case of DBM mixes. The

    behaviour of BC mixes with modifiers like CRMB is

    much better as compared to those without a modifier.

    4.3.4. Retained stability for BC mix: Retained

    stability of BC mix with CRMB after 24 hours at 60 oC

    is 96.63 per cent which is well above 90 per cent

    prescribed in IRC:SP:53-2002. The retained stability of

    the BC mix of 60/70 bitumen without CRMB at 65oC,however is 82.50 per cent against 93.40 per cent with

    CRMB at 65oC. It is 92.08 per cent without CRMB as

    against 96.63 per cent with CRMB at 60oC. The effect

    of modifier like CRMB or PMB in preventing the stability

    loss at higher temperature is thus quite vivid.

    4.3.5. Retained stability for DBM mix: The

    retained stability for top layer of DBM at 60oC is about

    82 per cent. The retained stability at 650C for DBM is

    far low, around 63 per cent. The stability loss in case of

    DBM at higher temperatures deserves early

    consideration for up-gradation and updation of our

    specifications of top layers of flexible pavement. The

    test results obliquely suggest that perhaps we cannot

    have flexible pavements in our country lasting for 20 to

    30 years with the use of 60/70 grade bitumen without

    modifiers. Performance grade bitumen with superpave

    type specifications needs to be evolved. We should

    otherwise consider providing composite or even rigid

    pavements as an alternative considering the expected

    long-term pavement life of 20 years plus.

    Fig. 5. Histogram Showing Stability (kg) of different mix

    at 600C (30 min), 600C (24 hours) & 650C (24 hours)

    Fig. 4. Layer-wise retained stability of pavement materials

    Vs various temperatures

    ASTMD 1075-1979

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    14/15

    190 SINHA, SINGH& SHEKHARON

    4.4. Effect of Heavy Traffic Loading Moving at

    Slow Speed

    Literature suggests that permanent deformation like

    rutting gets further accentuated at high pavement

    bituminous pavements are inadequate and need early

    updation. Rutting observed in the case study obviously,

    had the compound effect of both the high pavement layer

    temperature and slow moving/stationary vehicles.

    temperature, when the heavy truck traffic operates at a

    slow speed with frequent stop/start condition as is the

    case in the study stretch. This is a typical situation on

    most of heavily trafficked corridors in India, particularly

    near intersections, roundabouts and adjoining Toll Plazas

    and other control booths like Check posts, Octroi booths

    etc. Australian Asphalt Pavement Association (AAPA)

    gives a table indicating damaging effect of slow moving

    vehicles. This is reproduced in Table 18.

    Superpave mix design recommends for additional

    requirements in the selection of bitumen grade etc. to

    account for the vehicles moving at a slow speed and for

    conditions of standing load applications. According to

    superpave recommendations for slow moving design

    loads, the binder would be selected one high temperature

    grade higher, such as a PG-64 instead of a PG-58. For

    standing design loads, the binder would be selected two

    high temperature grades higher, such as a PG-70 instead

    of PG-58. For extraordinary high numbers of heavy

    traffic loads (between 10,000,000 to 30,000,000 ESAL)

    the engineer is encouraged to consider one high

    temperature binder grade higher than the selection based

    on climate. These recommendations do suggest the

    additionality of adverse effect due to slow moving

    vehicles on the performance of flexible pavement. These

    are over and above the effects due to the hot climatic

    region. This also speak loudly that our specifications for

    TABLE 18. TRAFFIC LOADING

    Indicative Traffic Volume

    Traffic category Heavy vehicle/lane/day Structural design level (MSA) Traffic speed

    Very heavy > 1000 2 x 107 Generally > 25 Km/hr

    > 500 5 x 106 Stop/start Generally

    < 25 Km/hr

    Heavy 500 to 1000 5 x 106to 2 x 107 Generally > 25 Km/hr

    100 to 500 5 x 105to 5 x 106 Stop/start Generally

    < 25 Km/hr

    Medium 100 to 500 5 x 105

    to 5 x 106

    Generally > 25 km/h< 100 < 5 x 105 Sop/Start, climbing lanes

    or generally < 25 km/h

    Light < 100 < 5 x 105 Generally > 25 km/h

    (Source: AAPA, Asphalt Guide 2002)

    4.5. Effect of Secondary Compaction

    One of the known cause of rutting in flexible

    pavement is the secondary compaction by the plying

    vehicles over the time. Compaction of bitumen mixes at

    refusal density while maintaining a minimum air voids of

    3 per cent is being suggested in the literature. Bitumen

    mixes used in study stretch had been tested for 300 blows,

    while broadly maintaining air voids at 2.75 per cent and

    VMA and VFB as per specifications. As the study stretch

    has been opened to traffic only about a year back, effect

    of the secondary compaction was not considered in the

    case study.

    CONCLUSIONS & RECOMMENDATIONS

    The present case study is a limited study. It has

    attempted to examine the adverse effects of high

    temperature in the top layers of binder course on theoverall performance of flexible pavements. It

    demonstrates that existing pavement design method

    followed in India requires an early review and up-

    gradation to meet the different (specific) site conditions.

    The generic nature of specifications as prescribed at

    present cannot cater to the need of constructing flexible

    pavements for design life of 20 to 30 years. At least

    some catalogue type specifications covering different

    regions of the country need to be evolved on the pattern

  • 7/22/2019 Rutting in Flexible Pavements A Case Study (1)

    15/15

    HIGHLIGHTSOFTHE178THCOUNCILMEETING 191 RUTTINGINFLEXIBLEPAVEMENTS- A CASESTUDY

    of performance based specifications like Superpave of

    USA. The results of the limited case study undertaken

    are only indicative. More elaborate studies are required

    to ensure wider understanding of the problems of the

    flexible pavement. Some of the recommendations areas below:-

    Needs for instrumentation to study the behaviour of

    temperature on the performance of the bituminous

    mixes is required to be taken up to enforce

    development of mechanistic design based on

    indigenous database.

    Data bank needs to be created, maintained andanalyzed to study the variations and variability in

    material characterization.

    Specifications should be evolved considering the

    need to construct long-term performing pavements.

    Higher standards in respect of bitumen binder is

    required to be set. The present standards for

    viscosity, stability, loss of stability at higher

    temperature etc. are either inadequately provided

    or are missing in the existing specifications.

    Generic nature specifications, as followed today

    need to be discarded in favour of performance based

    specifications as highlighted above.

    Special provisions to account the adverse effect ofslow moving/stationary vehicles is to be provided

    rather presuming transient loads in our design.

    Specifications need to provide against stability loss

    at higher temperature. For top DBM layers stability

    loss at 60oC should preferably be kept around 97

    per cent.

    Use of modifiers to enhance thermal related

    characteristics of bitumen should be made

    mandatory in top DBM layer. General paving

    bitumen as being used in the DBM layers may not

    serve.

    Composite construction including Whitetopping in

    top layers should be tried on pilot basis to safeguard

    bituminous roads against deformations at high

    temperature.

    Cement is relatively much better binder compared

    to bitumen. In heavy traffic corridor with high

    temperature, cement concrete roads may be

    considered as a viable alternative on long-term

    performance considerations, based upon life cycle

    cost.

    REFERENCES

    1. Superpave Mix Design Vol. I & Vol. II, Superpave series

    No.1 & 2 (SP1 & SP2), Asphalt Institute, Lexington.

    2. Specifications for Road and Bridge Works, MOSRT&H

    (Fourth Revision 2001), IRC.

    3. IRC:SP:53-2002 (First Revision) Guidelines on Use of

    Polymer and Rubber Modified Bitumen in Road

    Construction.

    4. Asphalt Guide, Australian Asphalt Pavement Association(AAPA) AUSTROADS Sydney 2002.

    5. Highway Research Record No. 189 Design Performance

    and Surface Properties of Pavement (9 Reports) 1967.

    6. The Properties of Asphaltic Bitumen , Edited by J.PH.

    Pffiffer, Elsevier Publishing Company, Inc. New York

    Amsterdam, London Brussels.


Recommended