Date post: | 14-Dec-2015 |
Category: |
Documents |
Upload: | reginald-boise |
View: | 221 times |
Download: | 3 times |
RWE NUKEM
The Design, Construction and Operation of NORM Descaling Plants
E Taylor and L Fellingham
RWE NUKEM 2
Structure of the Presentation
Background to the Problem of NORM Contamination
Potential Solutions
De-scaling Techniques
Design of Plants
Examples of Operational Plant
Safety Assessment
Waste Management
Concepts for Next Generation Plant
Conclusions
RWE NUKEM 3
Nature of the Problem
Around the world there are significant arisings of NORM-contaminated plant being generated by the oil & gas industry
Much of this is stored in open yards
There is a potential contamination threat to workers and a long-term environmental liability
RWE NUKEM 4
NORM-contaminated Equipment
RWE NUKEM 5
Required Solution
Manage NORM wastes in accordance with best international practice
Reduce the volume of NORM-contaminated waste arisings
Concentrate the radioactivity into the minimum practical volume
Store the concentrated activity safely
Reuse or recycle as much of the contaminated equipment, etc, as possible.
RWE NUKEM 6
RWE NUKEM’s Experience of providing Solutions
Design, construction and initial operation of the Al-Furat Petroleum Company (AFPC) facility in Syria
Design, construction and operation of the NORM facility at the Dounreay site serving the North Sea oilfields (now closed)
Design, construction and operation of a modular facility at the Winfrith site to meet the requirements of the Wytch Farm oilfield operated by BP
RWE NUKEM 7
The Facilities
RWE NUKEM 8
Techniques evaluated for removing Scale and Sludge from contaminated Equipment Proprietary and developmental stage, chemical descaling
methods
Various forms of particle blasting using sand, ballotini, metal shot, solid CO2, etc;
Abrasion techniques using wire and other forms of brushes; and
High pressure jetting techniques, using water and other process fluids.
RWE NUKEM 9
High Pressure Water Jetting – The Optimum Choice for Descaling It is very efficient at scale removal, irrespective of the chemical and mineral
form of the scale;
The water is capable of penetrating into narrow crevices, cracks, corrosion pits, etc, and removing scale and other adhering deposits. Hence residual contamination levels are very low and high decontamination factors are achieved;
The speed of processing is higher than with any alternatives, so reducing the necessary size of any plant;
It does minimal damage to the metal surface of the components, etc, being descaled;
The process makes use of the very low solubility of the scale and particularly the radium salts. The scale and radioactive contaminants are not solubilised. Hence the process water treatment is very simple involving only filtration and no chemical treatment;
RWE NUKEM 10
High Pressure Water Jetting – The Optimum Choice for Descaling (2)
The process water is recycled after filtration, so enabling the minimum volume of water to be used and generating no or a minimal volume of liquid effluent;
The scale can be encapsulated or re-injected with the minimum of treatment.
It is compatible with hydraulic cements, making it ideal for encapsulation directly or after maceration.
It can be disposed of after maceration and slurrying by reinjection into appropriate geological formations, including those exhausted of oil and gas.
Left in the chemical form in which it was originally deposited, the very low solubility of the scale in aqueous environments makes it an ideal waste form for long-term storage and disposal in both near surface and geological formations.
RWE NUKEM 11
Deployment of High Pressure Water Jetting
RWE NUKEM 12
Safety Assessment of NORM Descaling Facilities
Calculation of radiological doses due to routine decontamination operations for operators of the plant and an assessment for the general public.
Determination of the radiological risk to both operators and the public from potential accidents arising from fault conditions.
A bounding credible accident scenario, which would demonstrate that “worst case” scenarios result in negligible dose uptake by members of the workforce and general public in the surrounding areas.
A review of industrial hazards
RWE NUKEM 13
Main Hazards assessed in Safety Assessment
Radiological Hazards Non-Radiological Hazards
(i) Loss of sludge settling tank containment.
(i)
Fire.
(ii) The dropping of a bundle of received "dirty" tubulars within NDF and Waste Store
(ii)
Handling of heavy components.
(iii) Failures of the ventilation system. (iii)
Noise.
(iv) Loss of containment (iv) Burns
(v) High Pressure Jets
(vi) Legionella
(vii) Slips, trips and falls
(viii) Fume emission from oxy-propane cutting
(ix) Loss of breathing air
(x) External events
RWE NUKEM 14
Typical Results of Radiological Safety Assessments
Fault Dose to Operator
(Sv)
Dose to Public (Sv)
Minor Tank Failure 13.5 Negligible
Major Tank Failure Negligible Negligible
Dropping of a Bundle of Tubulars
Negligible Negligible
Ventilation System Fan Failure
7.5 Negligible
Ventilation System HEPA Filter Failure
- Negligible
Dropped Drum 0.34 Negligible
Aircraft Crash - 1.36
RWE NUKEM 15
Design Concept for Plants
A high proportion of the equipment to be descaled is in the form of tubulars with a much smaller proportion in the form of valves, Christmas trees, heaters, treaters, separators, pumps, meters, dehydrators, salt water tanks, etc.
The tubulars are uniform geometry items, differing only in length and diameter.
The other equipment comes in a very diverse range of shapes and sizes, making process automation much more difficult without complex equipment.
Treat these as two distinct streams. In order to achieve high throughputs and to process the much higher quantities, use a semi-automated approach for tubular de-scaling where possible.
Use manual descaling with dismantlement and potentially cutting to expose internal surfaces for other equipment.
RWE NUKEM 16
Examples of Plant Design
NORM facility at Dounreay
Al-Furat Petroleum Company (AFPC) NORM facility in Syria
The modular NORM Decontamination Facility at Winfrith operated for BP
RWE NUKEM 17
The NORM Descaling Plant at Dounreay
RWE NUKEM 18
Tubular Monitoring in the NORM Descaling Plant at Dounreay
RWE NUKEM 19
Equipment Descaling in the NORM Descaling Plant at Dounreay
RWE NUKEM 20
A View of the Front of the Al-Furat Petroleum Company (AFPC) facility in Syria
RWE NUKEM 21
The Burning Bay/Stripdown Area
RWE NUKEM 22
Tubular Descaling Unit in the NDF Plant
RWE NUKEM 23
The Liquid Effluent Settling Tanks in the NDF
RWE NUKEM 24
The Winfrith NORM Decontamination Facility
RWE NUKEM 25
The Winfrith NORM Descaling PlantTubular Receipt Area
RWE NUKEM 26
The Winfrith NORM Descaling PlantTubular Descaling Area
RWE NUKEM 27
The Winfrith NORM Descaling PlantSkid Mounted Pump and Extract System
RWE NUKEM 28
The Management of the Residual Radioactive Waste
Options
– Storage on-site
– Use of National Repository Facilities
– Dedicated long term safe storage
– Re-injection
RWE NUKEM 29
View of the Interior of a Dedicated Waste Store
RWE NUKEM
NORM Descaling Plants – The Next Generation
RWE NUKEM 31
Modular Descaling Facility using ModuCon Units – Fixed Unit (1)
Gridded Area for Descaling Operations within ModuCon(double skin with flat roof on lined bund & sump). Active area under Depression
UHPWJ Re-circulation& waste handling Unitwith lined bund anddivided into active/cleanareas
‘Clean’ Receipt/Despatch Area, via insulated double doors, leadingto active dismantling area, serviced with lifting equipment
ModuCon Entry/BarrierUnit with decon,wash/shower pluschange/monitor facilities
Flow OUT via HEPAExtract Plant withSafe Change filters
Flow IN via AirConditioning units
Clean Service Unit(air/electric generators).
4 ISOs lined/barrieredwith ModuCon forinsulation and eas ofdecontamination
All ISO doors Open Normally
(Closed in Storm)
ModuCon Barrier/Tunnel
RWE NUKEM 32
Modular Descaling Facility using ModuCon Units – Fixed Unit (2)
ModuCon Entry/BarrierUnit with wash & shower+ change/monitor facilities
UHPWJ Re-circulation & wastehandling Unit(s)housed in linedISO(s)
Assembly installed on lined hardstand (bund & sump)
ModuCon Receipt/Despatch Area via insulated double doors serviced with lifting ‘I’ Beam on ‘A’frame. Double skin for insulation and flat transparent roof for natural lighting
Gridded Area behind for Descaling Operations - Active area under Depression
RWE NUKEM 33
Modular Descaling Facility using ModuCon Units – Field Transportable Unit (1)
Active Vessel under Depression
UHPWJ Re-circulation& waste handling Unitwith lined bund anddivided into active/cleanareas
ModuCon Entry/BarrierUnit with decon,wash/shower pluschange/monitor facilities
Flow IN via AirConditioning units
Clean Service Unit(air/electric generators).
4 ISOs lined/barrieredwith ModuCon forinsulation and eas ofdecontamination
All ISO doors Open Normally
(Closed in Storm)
Chiller SkidModuCon Barrier/Tunnel
RWE NUKEM 34
Modular Descaling Facility using ModuCon Units – Field Transportable Unit (2)
ModuCon Entry/BarrierUnit with wash & shower+ change/monitor facilities
UHPWJ Re-circulation & wastehandling Unit(s)housed in linedISO(s)
Active vessel under Depression
ModuCon Barrier/Tunnel
Ventilation Extractto VentilationModule
RWE NUKEM 35
Conclusions
There is now considerable design and operational experience of NORM de-scaling plants
Techniques for de-scaling have also been extensively developed
Waste management is an ongoing issue
New designs of plant using modular approaches could be more cost effective.