    The 4thBridge Project

    LA 143 US 165 Connector andOuachita River Bridge

    Ouachita Parish

    State Project No. H.004782.2Federal Aid Project No. H.004782

    Imagine the result

    Scott Hoffeld, [email protected]

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    2/42

    2012 ARCADIS27 February 20132

    Safety Moment

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    3/42

    2012 ARCADIS27 February 20133

    Parking Lot Safety

    Watch where you park

    Panic buttons, keys, sprays,and your elbow

    Suspicious vehicles / people

    Look behind/front, side, and incar before entering

    Get in; Drive off

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    4/42

    2012 ARCADIS27 February 20134

    Project TeamAcknowledgement

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    5/42

    2012 ARCADIS27 February 20135

    Architectural ResourcesTerrestrial and Marine ArchaeologySection 106 Consulting PartiesCoordination

    Topographic SurveyProperty ResearchElected Official and StakeholderCoordination

    Project Consultant Team

    Level 1 Toll StudyBridge Constructability andConstruction Sequencing

    Project ManagementNEPA Analysis and DocumentationPublic and Agency Outreach

    Bridge Concept , Line & Grade

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    6/42

    2012 ARCADIS27 February 20136

    Agency Coordination and Public Scoping

    Notice of Intent

    Draft EIS

    Public and Agency Review and Comments

    Alternatives Development /Screening

    Final EIS

    Final Comments

    Record of Decision

    Funding, Design, Right-of-Way,Construction

    Federal Register June 28, 2012

    SOV June 27, 2012

    Interagency Meeting July 31, 2012Stakeholder and Public Meetings August 14, 2012

    Research, Field Data, Level 1 Toll Study, AlternativesDevelopment and Screening.

    Summer 2013

    Summer / Fall 2013

    Winter 2014

    Winter / Spring 2014

    Spring / Summer 2014

    Delivery Schedule

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    7/42

    2012 ARCADIS27 February 20137

    Description andLocation

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    8/42

    2012 ARCADIS27 February 20138

    Description

    LA 143 to US 165 Connector

    Ouachita River Bridge(4th Bridge)

    4-Lane Facility with

    Construction Phasing Level 1 Toll Study

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    9/42

    2012 ARCADIS27 February 20139

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    10/42

    2012 ARCADIS27 February 201310

    Project History

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    11/42

    2012 ARCADIS27 February 201311

    4thBridges Long History

    1968 1st reference

    1971 Monroe Metropolitan Area Stage 1Priority

    1981 Twin Cities Expressway CorridorStudy

    1996 Ouachita Loop MIS

    2007 Legislation establishing OuachitaExpressway Authority

    2008 Stage 0 Feasibility Study

    2012 EIS / Line & Grade / Level 1 TollStudy Contract

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    12/42

    2012 ARCADIS27 February 201312

    Proposed project is a Section of Independent Utilitywithin the long-range plan (unfunded) project known as the

    Ouachita Loop

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    13/42

    2012 ARCADIS27 February 201313

    Current Study Area

    What is the Project?

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    14/42

    2012 ARCADIS27 February 201314

    Project Need

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    15/42

    2012 ARCADIS27 February 201315

    Need

    Maintain east-west mobility for

    local and long-distance travel Create rural transportation

    system linkages across

    Ouachita River north ofcongested urbanized areas ofMonroe and West Monroe

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    16/42

    2012 ARCADIS27 February 201316

    20

    165

    20

    2015 Traffic Congestion Projection

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    17/42

    2012 ARCADIS27 February 201317

    20

    165

    20

    4th Bridge

    2035 Traffic Congestion Projection

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    18/42

    2012 ARCADIS27 February 20131818

    With Loop48% of all trips are

    Rural to Rural

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    19/42

    2012 ARCADIS27 February 20131919

    Note: This map shows the roads that contribute traffic to/get traffic from the Fourth Bridge. Also shown are the trip origin zones and the corresponding traffic volumes. These

    volumes were extracted from CDM Smiths year 2035 travel demand models for the toll scenario with the outer loop.

    With Loop4th Bridge Trip Sources with Loop

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    20/42

    2012 ARCADIS27 February 20132020

    Note: This map shows the roads that contribute traffic to/get traffic from the Fourth Bridge. Also shown are the trip origin zones and the corresponding traffic volumes. These

    volumes were extracted from CDM Smiths year 2035 travel demand models for the toll scenario without the outer loop.

    Without Loop4th Bridge Trip Sources without Loop

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    21/42

    2012 ARCADIS27 February 201321

    Level 1 Toll Study

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    22/42

    2012 ARCADIS27 February 201322

    22

    165

    165

    143

    143

    Stage 0 Concepts (2008)

    1

    2

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    23/42

    2012 ARCADIS27 February 201323

    Level 1 Toll Study Results

    Finks Hideaway Connection

    most important on east LA 143 terminus has more

    utility the further south

    Two lanes are adequatethrough a portion of theplanning period

    Tolling will likely pay for only a

    portion of costs

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    24/42

    2012 ARCADIS27 February 201324

    Funding

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    25/42

    2012 ARCADIS27 February 201325

    Costs and Funding

    Costs: $300-400M (2007$ Est.)

    SAFETEA-LU

    Ouachita Expressway Authorityhas bonding authority, among

    other powers

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    26/42

    2012 ARCADIS27 February 201326

    AlternativesDevelopment

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    27/42

    2012 ARCADIS27 February 201327

    27

    165

    165

    143

    143

    Stage 0 Concepts (2008)

    1

    2

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    28/42

    Elevation Wetlands

    Floodplain Land Cover

    Resource Data

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    29/42

    2012 ARCADIS27 February 201329

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    30/42

    2012 ARCADIS27 February 201330

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    31/42

    2012 ARCADIS27 February 201331

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    32/42

    2012 ARCADIS27 February 201332

    Stage 0 Alts + All New Segments

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    33/42

    2012 ARCADIS27 February 201333

    All Segments without Stage 0 Concepts

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    34/42

    2012 ARCADIS27 February 201334

    Screening

    Termini Comparisons

    Wetland MinimizationCenterlines

    Trade-Off Optimization

    Retained: Best WetlandMinimization and Trade-OffOptimization Centerlines

    Corridor centerlines thendeveloped into alternativecorridors

    R i i S t

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    35/42

    2012 ARCADIS27 February 201335 35

    Remaining Segments

    E l f O ti i ti

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    36/42

    2012 ARCADIS27 February 201336

    Optimization Line: Structuresand Wetlands

    Example of Optimization

    P li i C id

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    37/42

    2012 ARCADIS27 February 201337 37

    Preliminary Corridors

    Preliminary. Subject to Change.

    P li i Alt ti

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    38/42

    2012 ARCADIS27 February 201338 38

    Preliminary Alternatives

    1

    3

    2

    NW

    SW

    NE

    SE

    Preliminary. Subject to Change.

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    39/42

    2012 ARCADIS27 February 201339

    What are the NextSteps?

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    40/42

    2012 ARCADIS27 February 201340

    Tasks to be Completed

    Alternatives Impact Analysis

    Draft EIS

    Final EIS and ROD

  • 7/29/2019 S65_Ouachita River Bridge LA143 to US165_LTC2013

    41/42

    2012 ARCADIS27 February 201341

    Questions?

    Scott Hoffeld, [email protected]