Date post: | 23-Jan-2018 |
Category: |
Engineering |
Upload: | nikhil-jaipurkar |
View: | 7,383 times |
Download: | 25 times |
Sagana III Hydro Electric Project (2 x 5000 KW)
Detailed Project Report
Lucid Power Generation Limited
Kibagare Way, Next to the Mexican Embassy,
Loresho, P.O. Box 66244 – 00800,
Nairobi, KENYA
Ph: +254 736222065
Consultants
D 449, Sector 4, Phase II, New Shimla,
Near DAV School, Shimla 171 009,
H.P., India
Phone: +91 177 26 72 945
Fax: +91 177 26 72 945
http://www.scg-india.com March 2012
Contents
Chapter
Number Name of the Chapter Page Numbers
Executive summary Executive Summary 1
1. Introduction 1- 1 to 1 - 11
2. Justification of the Project 2 – 1 to 2 - 5
3. Infrastructure facilities 3 – 1 to 3 - 7
4. Survey & Investigation 4 – 1 to 4 - 3
5. Hydrology 5 – 1 to 5 - 17
6. Power Potential and Installed Capacity 6 – 1 to 6 - 10
7. Geology 7 – 1 to 7 - 6
8. Civil Engineering Structures 8 – 1 to 8 - 28
9. Electro Mechanical 9 – 1 to 9 - 17
10. Construction Plan & Program 10 – 1 to 10 - 7
11. Construction Materials 11 – 1 to 11 - 3
12. Project Organization 12 – 1 to 12 - 7
13. Environmental & ecological aspects 13 – 1 to 13 - 7
14. Estimates of cost 14 – 1 to 14 - 19
15. Financial Evaluation 15 – 1 to 15 - 18
16. Appendix I Photographs Appendix I - 1 to 5
17. Appendix II Drawings Appendix II - 1 to 51
ABBREVIATIONS
cum Cubic meter
Cumecs Cubic meter per second
DPR Detailed project Report
El. Elevation
FC Financial Charges
FSL Full Reservoir Level
GOK Government of Kenya
GWh Gigawatt Hour
ha Hectare
HEP Hydro Electric Project
hr Hour
IDC Interest During Construction
km Kilometer
kv Kilovolt
kVA Kilovolt Ampere
kW Kilowatt
kWh Kilowatt Hour
m Meter
MDDL Minimum Draw Down Level
MT Metric Tonne
MU Million Units
MVA Megavolt Ampere
MW Megawatt
Sec Second
SLD Single line diagram
TWL Tail Water Level
USD United States Dollars ($)
WARMA Water Resource Management Authority
List of Drawings
Sr. No. Drawing No. Name of drawing
CIVIL DRAWINGS
1 1 General Layout of Project (sheet 1/6)
2 General Layout of Project (sheet 2/6)
3 General Layout of Project (sheet 3/6)
4 General Layout of Project (sheet 4/6)
5 General Layout of Project (sheet 5/6)
6 General Layout of Project (sheet 6/6)
7 2 Plan of trench weir
8 3 Sections of trench weir
9 4 Water conductor system -Sections
10 5 Sections of tunnel (sheet 1/4)
11 Sections of tunnel (sheet 2/4)
12 Sections of tunnel (sheet 3/4)
13 Sections of tunnel (sheet 4/4)
14 6 Desilting tank – Plan & Section Details
15 7 Desilting tank – section details-1
16 7 Desilting tank – section details-2
17 8 Forebay Plan
18 9 Forebay Section
19 10 Plan & section of penstock
20 11 Plan of Power house
21 12 Section of Power house
22 13 Plan & section of TRP & TRC
HYDRO MECHANICAL DRAWINGS
23 14 Diversion weir trash rack-1
24 Diversion weir trash rack-2
25 15 Forebay trash rack-1
26 Forebay trash rack-2
27 Forebay trash rack-3
28 Forebay trash rack-4
29 16 Stop log gate panel-1
30 Stop log gate panel-2
31 17 Stop log gate embedment-1
32 Stop log gate embedment-2
33 18 Service gate panel -1
34 Service gate panel -2
Sr. No. Drawing No. Name of drawing
35 19 Service gate embedment -1
36 Service gate embedment -2
37 20 Shingle flushing gate panel – 1
38 Shingle flushing gate panel – 2
39 21 Shingle flushing gate embedment -1
40 Shingle flushing gate embedment -2
41 22 Penstock gate panel-1
42 Penstock gate panel-2
43 23 Penstock gate embedments-1
44 Penstock gate embedments-2
45 24 DT gate Panel -1
46 DT gate Panel -2
47 25 DT gate embedment - 1
48 DT gate embedment - 2
ELECTRICAL DRAWINGS
49 26 Single line diagram
50 27 Switchyard (1 of 2)
51 Switchyard (2 of 2)
Detailed Project Report Sagana-III HEP Chapter 1 – Executive Summary & Introduction
Executive Summary - 1
Executive Summary
The Ministry of Energy, Government of Kenya has invited proposals from Independent Power
Producer (IPP) companies for developing Hydro Electric Projects. To pursue the same,
promoters of Lucid Power Generation Limited have identified Sagana-III Hydro Electric Project
(2 x 5000 KW) on the Sagana River in Nyeri District (Central Province) of Kenya. Strategic
Consulting Group, a hydro power consulting firm from India has been appointed as technical and
financial advisor for the project.
The Sagana-III HEP is located approximately 180 Kms from Nairobi. The project envisages
utilizing the water of Sagana River through a diversion structure at an elevation of 1274m. The
Power house is located at an elevation of 1210 m. The main components include trench weir, de-
silting arrangement, ~4.8 Km long water conductor system (containing 2 Nos. Tunnel), Forebay
and one number main buried penstock which at later stage has been bifurcated. The scheme
proposes to utilize a gross head of 58.46m to generate 10 MW of power, with a rated discharge
of 21.26 Cumecs. The power will be evacuated through a ~7 km long 132 KV transmission line
to the 132 KV Sagana-Kutus line in Sagana Town.
The catchment area at the diversion site of Sagana-III HEP is 1460 sq. Kms. The average annual
rainfall received in the catchment area is 1200mm. Hydrology studies have been conducted
based on annual flow data from WARMA. Based on hydrology data, it is estimated that the
project will generate around 54 Million Units of electricity in a 75% dependable year.
Carbon emission reduction analysis has been done for the project. The project is likely to result
in an emission reduction of close to 38,690 tons of CO2, which will translate into around 145,120
USD of revenue for the project (assuming 75% share for the developer).
The project is likely to cost 22.97 Million USD. The major components of this cost are Civil
works (11.79 Million USD), Electromechanical works (5.76 Million USD), Indirect Charges,
Financial Charges including Interest during Construction & Construction Cost Escalation (5.42
Million USD).
Financial analysis of the project has been conducted, and results have been found to be
encouraging. The average DSCR over the loan repayment period is 1.54x, while the minimum
DSCR is 1.41x. The equity IRR in the base case is found to be 16.12%. Sensitivity results
conducted on key variables indicate that the project has cushion to absorb variations in
assumptions. The project is found to be techno-economically feasible and commercially viable,
and should be pursued further.
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 1
Chapter 1: Introduction
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 2
1.1 Introduction
The Ministry of Energy, Government of Kenya has a mandate to facilitate the provision of clean,
secure, sustainable and affordable energy services for socio-economic development while
protecting the environment. In accordance with its mandate the Ministry has invited proposals
from Independent Power Producer (IPP) companies for developing Hydro Electric Projects. The
Ministry of Energy has fostered an environment conducive to private participation in such
projects which in addition to adding to the energy generation capacity of the country will help in
creating local employment opportunities as well.
1.2 Promoters
Promoters of Lucid Power Generation Limited has more than 20 years of operating presence in
Africa, and specifically in Kenya. With a vast experience in design, engineering, execution,
renovation and commissioning of hydro projects, Lucid is comfortably placed to execute a hydro
power project from concept to commissioning. Lucid Power is keen on investing in the
opportunity provided by the Ministry of Energy, Government of Kenya.
Sagana-III Hydro Electric Project (HEP) is a (2 x 5000kW) project on the Sagana river in Nyeri
District (Central Province) of Kenya, and is being considered under the same opportunity.
Specific details in terms of project location & design are provided in this report.
1.3 Consultants for the project
Strategic Consulting Group (SCG) is an Indian hydro power development and consulting firm
located in Shimla, Himachal Pradesh, India. SCG provides concept to commissioning services
for hydro and other renewable energy projects. The promoters of Lucid Power Generation
Limited have appointed SCG as technical & financial advisors for the project.
A technical team from SCG conducted a thorough topographical survey of the project area over a
period of two months. Based on the survey, the components of the project were placed. The
discharge data was collected from Water Resource Management department (WARMA) of
Government of Kenya, and analyzed. Hydraulic design studies were conducted for the sizing of
the various civil and hydro mechanical components. A study was also conducted on the
availability and cost of the raw material and labour. With the help of all the collected primary
and secondary data, a detailed techno-economic project report has been prepared for the project.
The studies conducted and the conclusions arrived at have been described in detail in this report.
The studies conducted and the conclusions arrived at have been described in detail in this report.
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 3
1.4 Project location
The project is located in Nyeri district in the Central Province of Kenya. The project site is at a
distance of 180 Kms from the national capital Nairobi and is well connected by road.
Map of Kenya with location of the project
Sagana-III (10 MW)
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 4
1.5 Project Description
Sagana-III Hydroelectric project (HEP) is proposed as a run-of-the-river project on River Sagana
in Nyeri district (Central province) of Kenya.
The project envisages utilizing the water of the Sagana River through a diversion structure at an
elevation of 1274m. The co-ordinates of the intake structure are 0°34'49.31"S, 37° 9'1.60"E. The
Power house is located at an elevation of 1210 m. The co-ordinates of the power house are
0°36'52.64"S, 37°10'45.79"E. With a proposed rated discharge of 21.26 Cumecs, and a gross
head of 58.46 m, the project will have a capacity of 10 MW.
The diversion structure for the Sagana-III HEP at 1274m benefits from the availability of a good
bench on the right bank. This allows for easy placement of diversion structure components such
as headworks, de-silting chamber, connecting channel etc. Not much earth work is envisaged to
be required and there is availability of construction power at the intake site.
A good gradient is available for the placement of the water conductor channel/ pipe all along the
right bank. The water conductor consists of combination of an RCC rectangular channel and
tunnels of lengths of total length ~4800 m.
From the forebay a buried penstock of ~175m length is used to draw the discharge to the turbines
which at later stage will be bifurcated. After bifurcation, the branches are of length around ~15.5
m & diameter of 1.9 m each has been envisaged which feeds 5MW turbines (2 nos.).
A Surface Powerhouse has been envisaged at an elevation of 1210m on the right bank of the
Sagana River. From the powerhouse a Tail Race Channel of about 4.65 m bed width and approx.
10m length discharging tail waters of power house back to Sagana River will be designed
The scheme thus proposes to utilize a gross head of around 58.46m & a rated discharge of 21.26
Cumecs to generate 10 MW of power. To utilize the mentioned discharges, two numbers Francis
Horizontal with runner overhung on generator shaft type turbines with a rated capacity of (5000
kW) have been proposed.
The power generated shall be evacuated from the switchyard of Sagana-III HEP via a ~7km
transmission line to the substation in Sagana town for the 132 KV Sagana – Kutus line.
As per the Net Slope Level (NSL) observed all along the project area, it is seen that adequate
bench will be available for placement of appurtenant features: e.g. Diversion structure, RCC
Channel/ pipe, Forebay, penstock (buried), Surface Power house, Switchyard etc. Area required
for construction sites is also available near the site.
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 5
Photographs of project areas taken during site visit are included as Annexure 2. The location of
the project on topo-sheet (1:50,000 scale) is also shown in Annexure 2. The drawings showing
project components are included as Annexure 3.
The table below provides the salient features of the proposed scheme.
Table 1: Salient Features
Sl. No. Particulars Details
A Location:
a State Kenya
b District Nyeri
c Province Central Province
d Village Ithanji, Mutundu
e Toposheet no. 135/1
f Longitude 370 10’ 46” E
g Latitude 000 36'52” S
h Stream/Khad Sagana
i River Sagana
j Basin Tana
k Nearest town Nyeri-30 km
l Nearest Air port Nairobi -180 km
B Hydrological data
a Catchment area sq.km. 1,460.00
b Climate
c Altitude m 1210.00
d Mean Annual Rainfall mm 1200 mm
e Temperature o C 5
o to 27
o C
f Minimum Discharge cumecs
g Maximum Discharge cumecs 226.17
h Estimated Flood discharge cumecs 301.59
C Features of the project
a Project Type Run Off River
D Head works:
a Type of diversion weir Trench type
b Design Discharge cumecs 24.45
c Length of weir m 25.00
d Width of weir mm 3.80
e Depth of weir m 3.50
f Bed slope of weir 1 in 16.00
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 6
Sl. No. Particulars Details
g FSL in Trench weir m 1,274.00
h Upstream mat Boulder mat enclosed in wire
mesh
i Thickness of mat blocks mm 1500
j Length of mat mesh m 10
k Slope of Mat mesh 1 in 20
l Downstream mat Boulder mat enclosed in wire
mesh
m Thickness of mat blocks m 1500
n Length of mat mesh m 10
o Slope of Mat mesh 1 in 20
p High Flood Level at Weir site m 1,276.70
E Details Of Intake Gates
a Stop log gate
i No. of gates Nos. 1
ii Size of gate (Clear opening) m 3.80
iii Type of gate Screw type
b Service gate
i No. of gates Nos. 1
ii Size of gate (Clear opening) m 4.60
iii Type of gate Screw type
c Silt flushing gate
i No. of gates Nos. 1
ii Size of gate (Clear opening) m 1.50
iii Type of gate Valve with spindle
iv Height of stem rod 10.40
F Water Conductor System
1 Intake to D-tank
Approach Tunnel
a Design discharge cumecs 29.34
b Bed width m 4.60
c Full supply depth m 3.20
d Free board m 0.90
e Bed slope 1 in 1130
f Length of tunnel m 1260.00
g Reduced level at beginning of tunnel m 1,274.00
h Reduced level at end of tunnel m 1,272.88
2 Approach channel
a Design discharge cumecs 29.34
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 7
Sl. No. Particulars Details
b Bed width m 4.60
c Full supply depth m 3.20
d Free board m 0.90
e Bed slope 1 in 1130
f Length of channel m 90
g Reduced level at beginning of channel m 1,272.88
h Reduced level at end of channel m 1,272.80
3 De-silting chamber
a Length m 56.00
b Bed width m 10.00
c Water depth m 6.67
d Design discharge cumecs 29.34
e Diameter of Silt Flushing pipe mm 1,000.00
f Size of Silt gutter mm 1000 x 1000
g Slope of gutter 1 in 25.00
4 Desilting Tank to Forebay
Power channel-1
a Design discharge cumecs 24.45
b Type Rectangular
c Bed width m 4.20
d Full supply depth m 2.90
e Free board m 0.90
f Bed slope 1 in 1010.00
g Length of channel 745.00
h Reduced level at beginning m 1272.80
i Reduced level at end m 1272.06
5 Tunnel
a Design discharge cumecs 24.45
b Bed width m 4.20
c Full supply depth m 2.90
d Free board m 0.90
e Bed slope 1 in 1,010.00
f Length of tunnel m 2,340.00
g Reduced level at beginning of tunnel m 1,272.06
h Reduced level at end of tunnel m 1,269.74
6 Power channel-2
a Design discharge cumecs 24.45
b Type Rectangular
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 8
Sl. No. Particulars Details
c Bed width m 4.20
d Full supply depth m 2.90
e Free board m 0.90
f Bed slope 1 in 1,010.00
g Length of channel 370.00
h Reduced level at beginning m 1,269.74
i Reduced level at end m 1,269.37
G Forebay:
a Design discharge cumecs 24.45
b Storage capacity duration minutes 3
c Capacity m3 4,401.00
d Length of spillway m 40.00
e Breadth of spillway m 18.00
f Drawdown depth m 6.18
g Forebay top m 1,270.27
h Forebay bottom m 1,256.62
i F.S.L. level of Forebay m 1,269.37
j M D D L m 1,263.19
k Crest of Waste Weir m 1,269.37
H Penstock
1 Main Penstock
a No. of penstocks Nos. 1
b Diameter penstock Mm 2,700
c Design discharge cumecs 24.45
d Length of penstock M 175.00
e Center of penstock take off at forebay M 1,259.36
2 Branch Penstock
a No. of penstocks nos. 2
b Diameter penstock Mm 1,900.00
c Design discharge cumecs 12.23
d Length of each branch penstock M
e Center of penstock at power house M 1,209.91
I Power House
a Type of Power House Surface
b Dimensions M 28.25 x 16.8 x 18M
c Machine Hall Floor Level M 1,210.00
d Service/ unloading bay M 1,215.00
e Centre line of machine m 1209.91
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 9
Sl. No. Particulars Details
f Nos. of DT Gates Nos. 2
g Dimensions of DT gate m 3.0 x 2.0
h Type of gate Vertical slide Lift gate, MS Steel
i High Flood Level m 1,211.90
J Tail Race Channel
a Type & Shape RCC / Rectangular Ducts
b Length m 10.00
c Bed width m 4.65
d Full supply depth m 3.50
e Free board m 0.90
f Maximum tail Water level m 1,213.50
g Minimum tail water level m 1,210.91
K Electrical And Mechanical
Equipment
1 Design data
a Rated Unit Discharge cumecs 10.63
b Net Head at Rated Discharge m 55.76
c Gross Head m 58.46
d Site Elevation m 1,210.00
e Water Temperature 0C
f Setting to Tailwater m (1.00)
g Efficiency Priority 10.00
h Rated Head/Best Eff. Head 55.76
i System Frequency Hz 50
j Minimum Net Head m 46.99
k Plant rated discharge cumecs 21.26
l Plant max. discharge cumecs 24.45
2 Turbine
a Unit capacity KW 5,000.00
b Unit capacity with overload KW 5,750.00
c Number of units Nos. 2
d Rated Plant capacity KW 10,000.00
e Max. Plant capacity KW 11,500.00
f Runner diameter mm 1,288.00
h Turbine speed Rpm 428.00
i Runaway speed Rpm 774.00
j Inlet diameter mm 1,524.00
3 Generator
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 10
Sl. No. Particulars Details
a Type of Generator Synchronous
b Rated Capacity kW 5000
c Maximum capacity kW 5750
d No. of Generators Nos. 2 nos.
e Generation Voltage level Kv 11KV
4 Power evacuation
a Dimensions of switchyard m
b E.L. of Switchyard m 1,215.00
c Voltage KV 11 /132
d Transmission line Km 20
e Location of feeding s/s Sagana Kutus Line
f Voltage level KV 132 KV
M Land acquisition
1 Forest/Govt. land Ha 15.62
2 Private land Ha 0.00
3 Total land requirement Ha 15.62
N Cost of the project
1 Civil Works USD MM 11.79
2 E & M USD MM 5.76
O/W Transmission Work USD MM 0.29
Total cost without IDC & FC USD MM 17.55
3 Indirect Cost USD MM 0.13
(a) Total direct & indirect cost USD MM 17.68
4 Initial Working capital, capitalized
spares
USD MM 0.27
5 Interest during Construction, Financial
Charges
USD MM 1.41
6 Escalation during construction USD MM 1.18
7 Contingency USD MM 1.24
8 DSRA Cost loaded upfront USD MM 1.20
(b) Total USD MM 5.29
9 Total (a) + Total (b) USD MM 22.97
10 Capacity 10
11 Cost per MW USD MM 2.30
Detailed Project Report Sagana III HEP Chapter 1 – Introduction
Chapter 1 - 11
Sl. No. Particulars Details
12 Total project cost USD MM 22.97
O Financial results
1 IRR % 16.12
2 Payback period Years 9
3 DSCR Average 1.54
4 Average cost of generation USDc/Unit 5.08
Detailed Project Report Sagana III HEP Chapter 2 – Justification of the project
Chapter 2 - 1
Chapter 2 –Justification of the Project
Detailed Project Report Sagana III HEP Chapter 2 – Justification of the project
Chapter 2 - 2
2 Energy situation in Kenya
A fast growing power sector is crucial to sustain Kenya’s economic growth. Kenya has an
assessed hydropower potential to the tune of 9,000 MW; out of this less than 15% has been
developed so far. In the past various factors such as the dearth of adequately investigated
projects, environmental concerns, resettlement and rehabilitation issues, land acquisition
problems, regulatory issues, long clearance and approval procedures, power evacuation
problems, the dearth of good contractors, and in some cases, law and order problems have
contributed to the slow pace of hydropower development. There have been large time and cost
overruns in case of some projects due to geological surprises, resettlement and rehabilitation
issues, etc. However, considering the large potential and importance of hydropower in promoting
the country’s energy security and flexibility in system operation, the Government is keen to
accelerate hydropower development. Many of the factors that lead to delays in implementation of
power projects are being addressed through a number of legislative and policy initiatives by the
Government.
2.1 Demand & Supply situation in Kenya
The total nameplate power generation capacity of the Republic of Kenya is 1,473 MW and the
peak electricity demand (for 2009-10) was 1,107 MW. Though the name place capacity is higher
than the peak demand, this does not give a true picture of the electricity demand supply scenario
in the country. Firstly, there is lack of connectivity with only around a quarter of the population
having access to electricity. Then there are problems with the network which often result into
shutdowns. Thirdly, a significant part of the electricity generation comes from short term HFO
and HSD fired thermal plants which are expensive and are damaging for the environment.
Finally, even though the name plate capacity seems sufficient, breakdowns and inefficiencies
often result in plants operating at less than peak capacity. Also Kenya has a very low per capita
energy consumption of ~ 160 kWh/year against a world average of 2,429 kWh/year, thus leaving
an enormous room for growth. The peak electricity demand has been increasing at a CAGR of
5% for the last five years, and in 2013, the demand is expected to increase to 1,527 MW.
Detailed Project Report Sagana III HEP Chapter 2 – Justification of the project
Chapter 2 - 3
Table 2.1: Total Power: Demand vs. Installed
2007/08 2008/09 2009/10
YoY
growth
08/09 vs
07/08
YoY
growth
09/10 vs
08/09
Peak Demand (MW) 1036 1072 1107 3% 3%
Installed capacity (MW) 1310 1345 1473 3% 10%
Effective Capacity (MW) 1267 1280 1416 1% 11%
Reserve Capacity margin % 12% 9% 15% Source: Kenya Power & Lighting Company
Chart 2.1: Kenya Power Scenario: Demand Vs Installed Capacity
Source: Kenya Power & Lighting Company
2.2 Power capacity in Kenya
According to the generation data available for the year 2009, a significant amount of power in
Kenya is produced by Hydro Power Projects (42%). The bulk of this electricity is tapped from
five generating plants along the River Tana. The five stations combined - Kindaruma, Kamburu,
Gitaru, Masinga and Kiambere - have an installed capacity of more than 400 MW. There are also
several small hydro stations - Mesco, Ndula, Wanjii, Tana, Gogo Falls and Selby Falls - all built
before independence in 1963, with a combined generation output of 40 MW.
0
200
400
600
800
1000
1200
1400
1600
2007/8 2008/09 2009/10
Peak Demand (MW) Installed capacity (MW) Effective Capacity (MW)
Detailed Project Report Sagana III HEP Chapter 2 – Justification of the project
Chapter 2 - 4
Thermal power (HFO & HSD) together form almost 36% of the total energy generated.
Chart 2.2: Distribution of Power Source
Source: Energy Regulatory Commission; Kenya
Due to a severe shortage in power in the year 2000-01, for the first time HSD was used to
generate power (~660 GWh) after which it was used again 2006-07 onwards and still continues
to be used in spite of it being one of the most expensive sources of power.
Chart 2.3: Annual Energy (GWh) Actual (1998-99 to 2008-09)
Source: Energy Regulatory Commission; Kenya
Gas Turbine 4%
High Speed
Deisel, 17%
Heavy Fuel Oil,
19%
Geothermal,
17% Non Firm Hydro, 5%
Firm Hydro, 37%
0
200
400
600
800
1000
1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09
GT High Speed Deisel Heavy Fuel Oil GeothermalNon Firm Hydro Firm Hydro Uganda Electricity Board
Detailed Project Report Sagana III HEP Chapter 2 – Justification of the project
Chapter 2 - 5
2.3 Need for the project
Small Hydro Power is an important, reliable, eco-friendly and renewable source of energy. It has
a low environmental impact and minimal issues of displacement of the local population. Its
principle advantage is the ability to start and stop the plant quickly and instantaneous load
acceptance/rejection. The long life of the hydro power plants, the renewable nature of the energy
source, very low operating and maintenance costs, absence of inflationary pressures experienced
by the fossil fuels are some of the other advantages. Kenya is blessed with a vast hydro power
potential in its perennial river Basins. The speedy exploitation of hydroelectric power potential,
with minimum cost and with minimum environmental negative consequences, will definitely
improve the economic health of Kenya.
Sagana-III Hydro Electric Power project is a promising site for development. The perennial
Sagana River originating from the Aberdare forest, the ease of approach to the site areas, the
central location of the project, makes it an attractive and feasible site for development.
Detailed Project Report Sagana III HEP Chapter 3 - Infrastructure Facilities
Chapter 3 - 1
Chapter 3-Infrastructure Facilities
Detailed Project Report Sagana III HEP Chapter 3 - Infrastructure Facilities
Chapter 3 - 2
3 Infrastructure facilities
Development of adequate infrastructure is a pre-requisite for timely implementation of the
project. Establishment of proper infrastructure considering the existing facilities in the nearby
area and the requirement of different worksites for various activities goes a long way in speedy
execution of the works minimizing delays in project completion.
3.1 Location of the project
Sagana-III H.E. Project is situated on Sagana River near Ithanji, Mutundu village in Nyeri
district of Central Province. This project is contemplated as a run-of-the river scheme. It
envisages Trench type weir located downstream of the power house of the proposed Sagana II
HEP.
3.2 Transportation
The Project area is 30 kms from the Nyeri Town and approximately 180 kms from the capital
city of Nairobi.
3.3 Infrastructure Facilities
The following infrastructure facilities will be required at the project site area.
Access roads in the Project area to various work sites, camps, offices, muck disposal area,
job facility sites, etc.
Bridge works.
Residential buildings for the Project staff & offices including their electricity and provision
of water supply, sanitation & drainage works.
Non-residential buildings
Telecommunication network
Construction Power
3.4 Project Roads
The Appurtenant structures of Sagana-III HEP are well connected by road. There are motorable
mud tracks running throughout the length of the project.
3.4.1 Intake
Detailed Project Report Sagana III HEP Chapter 3 - Infrastructure Facilities
Chapter 3 - 3
The intake structure of the Sagana-III Hydro Electric project is downstream of the power
house of the proposed Sagana II Hydro Electric power project. A motorable mud track
runs parallel to the water conductor throughout its length. A ~1 km road will have to be
constructed to connect the mud track to the diversion site.
3.4.2 Power House
The power house site is connected by a motorable mud track on the right bank. However
patches totaling to a length of 700m will have to be reconstructed to make it worthy to
transport the various equipment to the power house site.
3.4.3 Other approach roads
Approach roads to Quarry sites/Borrow areas
Approach road to inlet & outlet portal of the Head Race tunnel
Haul roads to dumping areas for muck disposal
Approach roads to explosive magazine, Crusher, B&M plant, Stores, Workshops
Penstock fabrication yard, Sheds etc.
Sr. No. Description Length (m)
1 Road for intake site 1000
2 Road for Power house site 700
3 Tunnel I Inlet & Outlets 1000
4 Other approach roads 300
Total 3000
3.5 Manpower Requirement, Availability & Accommodation
3.5.1 Project Authority
The total number of permanent Operating and Maintenance staff required for the project is
estimated to be about 10 persons working in two shifts. However, during construction stage, the
staff requirement shall be more and shall be provided accordingly and housed near the flat area
available near Othaya town or Nyeri Town.
3.5.2 Contractor
Manpower for the construction of Civil, Hydro-mechanical and Electro-mechanical works will
be required to be provided by the Contractor. The total number of engineers, officers and
Detailed Project Report Sagana III HEP Chapter 3 - Infrastructure Facilities
Chapter 3 - 4
workers of various disciplines to be deployed by the contractor will be planned commensurate
with the construction program. For the contractor staff the area will be provided near project site.
3.5.3 Labour
Unskilled labour is available near the project site. Skilled labour will have to be arranged from
the nearby towns of Nyeri, Othaya & Muranga. Labour to be deployed during construction stage
will be accommodated near work sites.
3.5.4 Accommodation
Rented Accommodation is available in Othaya, Nyeri and Muranga. These will be of use to carry
out the pre-construction activities. Temporary structures will be erected to house workmen and
labour at the site.
A workshop to carry out the fabrication work during construction is proposed near the power
house. This will work as service bay for the power house post commissioning.
3.6 Construction Plant and Job Facility
The various installations that will erected by the contractor for the construction plant for
construction works will be as follows:
3.6.1 Crushing Plant
Two crushing plants of size 80 TPH and 60 TPH shall be located near the power.
3.6.2 Batching and Mixing Plant
As per requirement of concreting at various work sites, the batching and mixing plant of
80 cum/hr capacity for Intake, Water channel, Head race tunnel, Penstock, Powerhouse
and appurtenant works.
3.6.3 Penstock Fabrication Yard
Site for fabrication of Penstock ferrules will be provided on the right bank of Sagana
River downstream to the project area. This area will also be used for storing of E & M
equipment on their receipt. Electrical & Mechanical, Heavy machinery workshop, E&M
equipment storage yard and storage area for cement & steel will be provided in the
acquired area.
Detailed Project Report Sagana III HEP Chapter 3 - Infrastructure Facilities
Chapter 3 - 5
3.7 Construction power
The peak demand for power for construction activities is estimated to be about 1.2 MW taking
the capacities of electric driven equipment and lighting purpose. The initial requirement of power
for construction activities in the first year would be about 0.8 MW and this may subsequently
increase to 1.2 MW.
In addition to grid supply, it is also proposed to provide supplemental power by diesel sets as
standby in case of interruptions in grid supply.
The breakup of peak demand has been estimated as follows:
Sr. No. Description Capacity Unit Rating
(kW)
1 Capacity of Crushing Plant (at Intake) 80 TPH 240
Capacity of Crushing Plant (powerhouse) 60 TPH 180
2 Batching and Mixing Plant (near tunnel) 80 Cubic m/hour 240
3 Contractor workshops etc. 250
4
Electrification & other miscellaneous in
project areas LS - 200
Total ~1200
3.8 Construction Material
The construction material survey for availability of coarse and fine aggregates shall be carried
out during Geological mapping. Suitable sites shall be identified and a crushing plant will be
installed at suitable location near to the quarry site to crush and process the stone materials for
use as coarse and fine aggregates. Sand deposits will also be identified during Geological
mapping for use as fine aggregates.
3.9 Communication Facilities
The different work sites of the project offices, stores, laboratories, workshops and residences etc
will be connected by a telecommunication network. The telecommunication facilities will also be
provided between the project and the outside. All important sites of the works, offices and
residences of senior officers will be connected by telephone. Suitable number of mobile phones /
wireless radios (walky-talky) would also be provided.
Detailed Project Report Sagana III HEP Chapter 3 - Infrastructure Facilities
Chapter 3 - 6
3.10 Muck Disposal Areas
The construction activities will generate a significant quantity of muck which will have to be
disposed off at appropriate locations in line with the topographic conditions. The quantity of
muck expected to be generated from various work sites is tentatively assessed to be as under.
Sl. No. Structures Approximately Muck Quantity Cum
1 Diversion works 1555.55
2 Water Channel 18150.42
3 Desilting Tank 10640.45
4 Tunnel 20412.00
5 Forebay 5359.54
6 Penstock Before Bifurcation' 2698.18
7 Penstock After Bifurcation 936.00
8 Power House 4495.14
9 Switchyard 5008.64
10 Tail Pool 4216.58
11 Tail Race Channel 118.30
Total 73590.78
Muck disposal areas for the above mentioned quantities have to be identified during construction
and will be developed by providing stable slopes and adequate berms, so that muck flow in to the
river is avoided.
3.11 Explosive Magazine
In order to cater for blasting requirements of various work sites, it is estimated that around 50
MT of gelatin will be required, along with proportionate quantity of detonators. Portable site
magazines of 500 kg capacity will also be provided to cater to the day to day requirement of
explosives. Explosive van will be used for the transport of explosives from the magazine to the
work sites. All safety codes and regulations prescribed by the Government in this respect will be
followed and magazines will be suitability guarded round the clock. Necessary permits &
licenses will be taken from the concerned authorities for use of these explosives.
Detailed Project Report Sagana III HEP Chapter 3 - Infrastructure Facilities
Chapter 3 - 7
3.12 Transportation
Sagana-III HEP is well accessible by road. A motorable mud track connected to the
Kiawamururu road connecting Mukurwe-ini to the Thika road (A2 highway).
3.13 Site Safety & Insurances
Adequate arrangements for lighting, security etc. will be made in the project area. Adequate
preventive measures against accidents will be taken in accordance with the international
construction site safety norms. The project work sites will have restricted entry and visitors will
only be allowed on permits issued by the project authority. All work force and other project
personnel will be provided with identity cards and passes issued by the Project authority which
will be checked at the entry check posts located at suitable places. Adequate insurances will be
maintained by Project Company and contractor.
Detailed Project Report Sagana III HEP Chapter 4 - Survey & Investigation
Chapter 4 - 1
Chapter 4 - Survey & Investigation
Detailed Project Report Sagana III HEP Chapter 4 - Survey & Investigation
Chapter 4 - 2
4 Topographic Survey
The Senior Engineers of the consultant have done preliminary identification of layout at site in
association with representatives of M/s Lucid Power Generation Limited. The principal
components of the project were identified. Subsequently, visits were conducted for carrying out,
topographical surveys and to freeze the layout of site and establish the feasibility of the project.
Reconnaissance of the project was carried out and location of the principal components of the
project was identified. The essential topographical surveys as detailed below were carried out to
decide upon the general layout of the project and to identify the exact location of the various
components of the scheme. The toposheet no. 135/1 in the scale of 1:50000 were procured for
the project area. The detailed topographical surveys carried out for various components of the
project are as follows:-
4.1 General Layout:
The topographical surveys for general layout of the project extending from about 500 m
upstream of the proposed diversion structure and covering the area up to the proposed power
house and appurtenant works site has been carried out in the scale of 1:500 with 1m contour
interval. Different alternatives have been studied and general layout of the various components
of the project has been marked indicating the proposed location of the diversion structure, intake,
silt flushing channel/conveyance channel, desilting tank, water conductor system, forebay,
penstock and power house and appurtenant structures. Components wise detailed surveys carried
out are as follows:-
4.1.1 Diversion structure:
Detailed topographical survey for location of diversion structure, covering about 500 m
upstream and up to the proposed desilting tank, 10 m above the anticipated highest flood
covering both the banks at the proposed location has been carried out in the scale 1:500 with
contour interval of 1m.
4.1.2 Desilting tank:
Detailed topographical survey at the proposed location of desilting arrangement in the scale of
1:500 with contour interval of 1 m.
Detailed Project Report Sagana III HEP Chapter 4 - Survey & Investigation
Chapter 4 - 3
4.1.3 Water Conductor System:
Detailed topography strip survey along the proposed alignment of water conductor system
including conveyance channel, silt flushing channel, desilting tank/power channel/tunnel and
forebay tank has been carried out in the scale of 1:500 with conductor interval of 1 m covering
an area of 20 m on the hill side and 20 m on the valley side.
4.1.4 Forebay and Penstock:
Detailed topographical survey of the proposed location of forebay and surface penstock in the
scale of 1:500 with contour interval of 1 m has been done for carrying detailed engineering
studies of the structure.
4.1.5 Power house area:
Topographical surveys of the proposed power house area in the scale of 1:500 with contour
interval of 1 m covering tail race channel, switchyard and extending to the other side of the river
has been done . Water level and high flood marks have also been recorded.
4.2 Hydrological Studies
The daily flows measured at station on River Sagana (code 4AA05), River Chania (code 4AC04)
and River Gura (code 4AD01) of WARMA were procured to analyse to flow and the power
potential for Sagana III HEP. The data was made available from January 1966 to December
1986. The data points spanning over 20 years was considered sufficient to form a long term
series for all hydrological calculations. For the detailed analysis for hydrology and power
potential calculations please refer to chapter 5 & Chapter 6 respectively.
4.3 Geological investigation
Geological investigations shall be conducted at the Detailed Engineering stage. Surface geology
report for the project area will be prepared by an experienced geologist. Sub-soil explorations
will be carried out by drilling cores and testing samples in a laboratory. More details are
provided in Chapter 7.
4.4 Power evacuation
The power generated from Sagana III HEP shall be evacuated through a double/single circuit 132
kV, ~7 Km transmission line to the Sagana – Kutus line at Sagana.
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 1
Chapter 5 - Hydrology
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 2
5 General
This chapter describes the study of the hydro-meteorological characteristics of the catchment
area and the methodology used for establishing various hydro-meteorological metrics, which in
turn serves as inputs for the project planning and design. The hydrological analysis has been
carried out encompassing the following:
Assessing the availability of water for power generation by establishing a long- term
series of average 10 day daily discharge for the project site.
Establishing the design flood.
5.1 Catchment Description & Characteristics
Sagana III HEP is situated on the Sagana River which finds its origins in the dense Aberdare
Forest. The River flows in the South East direction till it meets River Gura near the town of
Ngunguru. The catchment area at the diversion site of Sagana III HEP is 1460 sq. Kms, out of
which over 50% is in dense forest area (Aberdare Forest).
5.2 Climate
Sagana III HEP (10 MW) is located in the Central Province of Kenya. The climate of Central
Province is generally cooler than that of the rest of Kenya, due to the region's higher altitude.
The temperature varies between 7ºC to 30ºC. The period from February to March is the hottest
while the one from July to August is the coldest.
5.3 Rainfall
Rainfall is fairly reliable in the Central Province. There are two rainy seasons in Kenya: one
from early March to June (the long rains) and a second during October and November (the short
rains). The average annual rainfall received in the catchment area is 1200mm (as per the Rainfall
gauges at Embu Metrological station, Sagana Technical School, Sagana State lodge, etc.). The
rainfall, being spread over two seasons and a number of months in the year, results in lower
variation in the discharge of the river over the year. The mean annual runoff at the diversion
structure is estimated to be 518.97 MCM.
5.4 Sediment Load
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 3
The Sagana River carries significant sediment load during the rainy months. The river bed is
characterized by an accumulation of boulders of different sizes along the course of the River.
The size of the boulders varies from small pebbles to big boulders.
5.5 Water Quality
The water in the Sagana River is free from any kind of pollution till the intake site of the Sagana
III HEP. However it is murky and turbid during the rains. The sediment load analysis shall be
done at the detailed engineering stage.
5.6 Flow Variation
The flow in the rivers the in Aberdare and Mount Kenya region changes seasonally and differs
from year to year, due to temporal and spatial variation in precipitation. The flow pattern in the
Sagana River is no exception to this. The variation in flow in the Sagana River can be seen in the
months of March to June (the long rains) and a second during October and November (the short
rains).
5.7 Available data
The discharge data for the Sagana River has been collected over a period of 20 years from 1966
to 1986 by Water Resource Management (WARMA) department of Govt. of Kenya. We have
summed the individual discharges for River Sagana, River Chania and River Gura before their
confluence points and adjusted for the catchment area till the intake site of Sagana III HEP. The
discharge stations for River Sagana (code 4AA05) and River Chania (code 4AC04) are located
upstream of the confluence of River Chania with River Sagana. The discharge station for River
Gura (code 4AD01) is located upstream of the confluence of River Gura with River Sagana.
We have used this data to arrive at the 50%, 75% and 90% dependable flow years for Sagana,
with appropriate adjustment for flow on a catchment area proportion basis. The years with
incomplete data have been removed from the series to give a complete 20 year series. The
catchment of the river at the discharge stations are River Gura ~230sq Kms, River Chania
~370sq Kms, River Sagana ~800sq Kms (totaling to ~1400 sq Kms). The effective catchment at
the intake point of the Sagana III HEP is 1460 sq. Kms. The discharge has been suitably
increased by multiplication with the catchment area factor (1460/1400 = 1.04).
The ten daily combined discharge data for the Sagana River at the diversion structure of Sagana
III HEP is being shown in the following pages:
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 4
Average Ten Day Daily Discharge of the Sagana River at the Diversion Structure
From Jan 1960 to Dec 1967 Catchment at Sagana III Intake 1460 sq. kms
PERIOD 1960 1963 1964 1966 1967
10 day
JAN 1 10.45 17.45 25.86 14.82 9.49
2 8.53 19.07 16.44 11.09 8.28
3 10.33 20.02 11.62 11.58 7.38
FEB 4 8.44 14.02 10.11 10.18 6.92
5 9.20 12.74 9.73 10.03 6.36
6 7.61 9.94 7.75 12.93 6.18
MAR 7 6.58 12.83 8.26 11.68 6.35
8 8.92 16.68 9.97 10.66 6.74
9 15.82 16.16 19.27 24.07 5.62
APR 10 22.56 15.21 41.87 50.20 9.13
11 34.77 35.64 67.42 58.04 16.73
12 31.26 110.93 103.62 103.09 12.44
MAY 13 43.32 118.02 56.16 80.25 55.60
14 21.35 109.62 56.44 42.39 75.01
15 17.36 66.48 41.27 27.14 44.68
JUN 16 15.20 98.34 29.60 23.82 34.37
17 12.37 50.43 24.20 22.62 25.86
18 11.23 33.72 16.87 19.61 21.33
JUL 19 10.97 16.75 14.14 15.07 17.23
20 9.31 12.80 13.57 13.13 18.87
21 8.27 10.71 15.62 12.11 21.03
AUG 22 7.95 11.08 19.15 11.38 17.67
23 8.35 14.57 18.08 10.88 18.54
24 10.47 10.08 16.26 13.61 17.60
SEP 25 9.86 8.60 14.03 13.44 18.27
26 11.39 6.47 14.82 11.02 15.14
27 11.80 7.14 14.06 12.27 15.14
OCT 28 14.25 7.40 17.01 9.75 15.46
29 13.85 11.77 21.27 9.79 26.53
30 20.24 8.54 23.70 22.29 62.75
NOV 31 33.29 15.56 20.39 44.61 51.93
32 34.14 16.32 19.93 35.32 56.50
33 20.08 25.17 21.83 25.20 85.17
DEC 34 12.19 52.76 30.60 17.09 38.17
35 11.62 34.60 24.71 14.04 24.80
36 11.68 30.25 21.29 10.66 19.87
Yearly Average 15.42 29.94 24.91 23.50 24.98
Inflow, Million Cu M 486.19 944.23 785.68 740.99 787.69
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 5
Average Ten Day Daily Discharge of the Sagana River at the Diversion Structure
From Jan 1968 to Dec 1972 Catchment at Sagana III Intake 1460 sq. kms
PERIOD 1968 1969 1970 1971 1972
10 day
JAN 1 14.91 16.86 9.23 8.53 14.53
2 12.26 14.31 13.95 11.16 13.14
3 10.78 16.47 22.27 7.48 11.83
FEB 4 9.97 13.86 13.22 6.95 22.02
5 11.69 12.66 10.30 6.98 19.61
6 36.21 15.14 10.05 4.98 14.33
MAR 7 59.14 15.82 10.21 4.37 13.18
8 44.09 16.21 11.54 4.91 10.17
9 34.63 18.50 16.82 5.39 9.09
APR 10 45.91 15.32 37.44 6.79 12.22
11 59.43 19.03 31.73 13.97 12.33
12 131.77 17.13 52.64 24.69 11.65
MAY 13 79.12 39.04 64.05 56.81 24.65
14 49.32 70.93 50.07 53.19 28.03
15 47.24 32.46 28.74 42.23 39.75
JUN 16 37.73 18.99 22.98 27.56 37.45
17 34.56 14.45 19.90 18.85 30.10
18 26.95 12.33 16.47 17.25 30.04
JUL 19 23.10 11.31 15.67 15.73 20.65
20 21.07 10.57 12.60 17.89 17.03
21 19.61 10.39 11.47 15.10 14.55
AUG 22 18.16 10.33 10.67 14.77 15.88
23 18.40 10.45 11.51 18.52 20.35
24 18.90 9.99 14.03 23.66 18.03
SEP 25 14.85 9.98 14.33 17.97 12.84
26 13.98 14.39 12.92 13.70 11.58
27 12.71 9.97 11.82 13.97 13.93
OCT 28 11.94 8.82 12.01 13.35 21.74
29 14.34 14.74 23.32 16.67 34.91
30 26.76 10.02 16.59 14.30 43.15
NOV 31 36.90 10.48 17.95 14.04 65.78
32 26.27 13.44 16.36 12.80 58.97
33 85.13 23.32 18.46 15.21 60.21
DEC 34 94.70 15.25 12.30 13.18 37.35
35 37.27 10.61 10.37 11.99 24.80
36 22.30 8.87 10.19 16.69 17.81
Yearly Average 35.06 16.46 19.28 16.71 23.99
Inflow, Million Cu M 1105.61 518.97 608.12 527.01 756.57
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 6
Average Ten Day Daily Discharge of the Sagana River at the Diversion Structure
From Jan 1973 to Dec 1978 Catchment at Sagana III Intake 1460 sq. kms
PERIOD 1973 1974 1975 1976 1978
10 day
JAN 1 17.96 9.65 10.43 12.14 13.62
2 20.54 8.61 8.22 9.18 16.38
3 14.51 7.18 7.38 7.90 11.41
FEB 4 11.17 2.85 6.83 7.51 8.71
5 18.56 3.06 5.94 7.37 8.47
6 16.68 2.35 4.98 7.66 20.24
MAR 7 11.54 8.11 5.74 7.19 20.41
8 9.63 6.66 6.07 5.72 42.18
9 8.85 8.02 5.54 6.68 39.86
APR 10 7.49 25.17 5.45 7.47 58.76
11 26.45 31.67 14.71 15.88 90.13
12 39.21 33.87 27.53 15.03 70.19
MAY 13 36.46 22.55 12.60 18.30 91.49
14 28.57 19.60 25.87 25.96 62.93
15 33.03 21.80 22.91 44.44 31.05
JUN 16 29.32 23.55 17.23 20.67 20.40
17 23.05 17.92 13.05 14.66 16.83
18 18.43 19.16 13.75 15.49 13.39
JUL 19 16.86 34.48 11.99 14.52 14.22
20 14.12 41.38 13.73 20.96 13.16
21 13.01 30.13 15.56 13.29 10.71
AUG 22 17.21 22.25 16.26 10.88 12.05
23 16.12 17.24 15.10 10.05 10.83
24 13.14 18.36 16.21 11.10 10.61
SEP 25 12.09 20.43 16.75 15.32 10.71
26 10.82 16.86 15.84 9.76 9.53
27 16.42 14.97 15.29 9.85 11.88
OCT 28 11.05 14.94 20.03 12.18 10.48
29 19.31 13.10 19.92 13.17 11.31
30 19.82 16.65 30.79 13.44 19.25
NOV 31 25.22 32.90 23.81 15.97 33.94
32 36.92 34.17 20.11 13.67 22.43
33 28.52 21.91 17.79 17.06 20.56
DEC 34 17.64 16.90 19.27 23.06 19.89
35 12.27 14.22 16.21 22.30 20.00
36 11.08 11.65 12.44 14.64 16.58
Yearly Average 18.97 18.45 14.76 14.18 25.41
Inflow, Million Cu M 598.39 581.95 465.47 447.16 801.18
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 7
Average Ten Day Daily Discharge of the Sagana River at the Diversion Structure
From Jan 1980 to Dec 1986 Catchment at Sagana III Intake 1460 sq. kms
PERIOD 1980 1981 1982 1984 1986
10 day
JAN 1 11.67 9.41 15.13 44.34 16.99
2 9.29 9.28 12.92 35.57 14.40
3 9.60 8.77 10.20 22.89 13.38
FEB 4 9.80 6.97 7.95 18.52 10.88
5 8.31 8.69 8.37 13.96 10.04
6 7.53 6.96 6.98 19.70 7.31
MAR 7 9.47 13.02 6.37 21.73 25.80
8 9.04 17.28 5.83 11.71 11.39
9 8.80 20.91 6.04 10.54 21.14
APR 10 17.05 29.87 35.57 17.80 9.16
11 27.33 58.25 21.40 32.41 18.62
12 22.23 49.68 42.07 31.56 62.77
MAY 13 29.48 41.44 68.60 25.27 63.72
14 45.36 60.01 89.25 17.73 52.73
15 33.11 53.96 108.71 13.31 66.85
JUN 16 22.58 29.84 48.58 14.81 40.64
17 16.82 19.92 27.05 12.73 30.05
18 19.61 17.97 20.60 13.28 25.55
JUL 19 15.74 15.23 16.70 11.70 16.95
20 11.86 16.36 13.67 11.49 15.12
21 10.05 14.11 13.17 12.92 12.49
AUG 22 10.33 15.43 11.86 10.30 9.96
23 9.64 15.45 10.41 8.52 10.08
24 9.58 13.14 10.72 10.66 9.17
SEP 25 8.33 12.56 9.47 12.24 8.61
26 7.55 10.89 9.97 15.86 11.04
27 6.82 13.68 10.07 17.11 9.88
OCT 28 6.16 15.19 9.64 53.00 21.87
29 10.47 14.94 26.71 43.73 23.26
30 10.02 26.54 43.11 57.05 24.70
NOV 31 19.58 18.04 56.34 59.80 25.45
32 30.42 21.24 34.03 90.70 22.02
33 28.66 18.37 34.07 70.94 14.41
DEC 34 20.22 14.56 39.73 55.64 19.23
35 17.88 22.85 29.93 39.90 16.33
36 14.76 19.57 22.95 30.97 24.77
Yearly Average 15.70 21.12 26.23 27.51 22.13
Inflow, Million Cu M 598.39 495.07 666.12 827.11 867.57
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 8
Chart 5.1: Discharge Dependability
0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
40.00
5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100%
Discharge available 50% of Time = 21.12 CuM (1981)
Discharge available 75% of Time = 16.46 CuM (1969)
Discharge available 90% of Time = 14.76 CuM (1975)
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 9
Chart 5.2: 10 Day Daily Discharge (Cumecs)
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
1960 1963 1964 1966 1967 1968 1969 1970 1971 1972
1973 1974 1975 1976 1978 1980 1981 1982 1984 1986
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 10
Chart 5.3: Flow Duration Curve (75% Dependable Year: 1969)
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 11
5.8 Dependable flow
We have used this data to arrive at the 50%, 75% and 90% dependable flow years for Sagana,
with appropriate adjustment for flow on a catchment area proportion basis. The flow data for
forty years was then arranged in descending order of annual flow, to calculate the 50%, 75% &
90% dependable years. The following result was obtained:
50% dependable year = 1981
75% dependable year = 1969
90% dependable year = 1975
5.9 Design Flood
Though there are many methods available for design flood estimation they are region specific
and Dicken’s method has been found best for design flood estimation of Hilly streams. Two
methods have been used to estimate the design flood for the project, they being:
a) Exceedance probability method
b) Gumbel's method
The calculations for the Exceedance probability method are shown below:
Sr.
No.
Year Flood
Peak
(Cumecs)
Flood Peak
Descending
(Cumecs)
Rank
(b)
Frequency
(a)= y/(b)
Chance %
=100/(a)
1 1952 71.79 226.17 1 34.00 2.9
2 1953 68.25 214.07 2 17.00 5.9
3 1954 103.81 208.28 3 11.33 8.8
4 1955 70.08 207.27 4 8.50 11.8
5 1959 60.74 201.56 5 6.80 14.7
6 1960 62.15 184.79 6 5.67 17.6
7 1961 208.28 176.58 7 4.86 20.6
8 1962 126.78 152.66 8 4.25 23.5
9 1963 207.27 149.89 9 3.78 26.5
10 1964 184.79 144.01 10 3.40 29.4
11 1965 107.43 138.92 11 3.09 32.4
12 1966 144.01 135.13 12 2.83 35.3
13 1967 152.66 131.88 13 2.62 38.2
14 1968 201.56 130.75 14 2.43 41.2
15 1969 113.76 128.71 15 2.27 44.1
16 1970 101.24 126.78 16 2.13 47.1
17 1971 85.92 113.76 17 2.00 50.0
18 1972 100.21 113.34 18 1.89 52.9
19 1973 83.81 112.84 19 1.79 55.9
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 12
Sr.
No.
Year Flood
Peak
(Cumecs)
Flood Peak
Descending
(Cumecs)
Rank
(b)
Frequency
(a)= y/(b)
Chance %
=100/(a)
20 1974 85.66 107.43 20 1.70 58.8
21 1975 68.35 103.81 21 1.62 61.8
22 1976 68.11 101.24 22 1.55 64.7
23 1977 130.75 100.21 23 1.48 67.6
24 1978 128.71 85.92 24 1.42 70.6
25 1979 113.34 85.66 25 1.36 73.5
26 1980 84.96 84.96 26 1.31 76.5
27 1981 112.84 83.81 27 1.26 79.4
28 1982 176.58 71.79 28 1.21 82.4
29 1983 214.07 70.08 29 1.17 85.3
30 1984 149.89 68.35 30 1.13 88.2
31 1985 226.17 68.25 31 1.10 91.2
32 1986 135.13 68.11 32 1.06 94.1
33 1987 131.88 62.15 33 1.03 97.1
34 1988 138.92 60.74 34 1.00 100.0
No. of floods = y = 34
The magnitude of flood having frequency of 100 years = 100/100 = 1
From graph the flood discharge = 300 Cumecs
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 13
Chart 5.4: Sagana River Flood
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
210
220
230
240
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Flo
od
Pea
k i
n C
um
ecs
Chance Percent
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 14
Chart 5.5: Sagana River Flood Peaks (Cumecs)
0
50
100
150
200
250
1950 1955 1960 1965 1970 1975 1980 1985 1990
FLO
OD
PEA
K C
UM
ECS
YEAR
SAGANA RIVER FLOOD PEAKS ( Cumecs)
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 15
The calculations for the Gumbel’s method are shown below:
Sr.
No. Year
Flood
Peak
(Cumecs)
Flood Peak
(Qp)
Descending
(Cumecs)
Rank
(b)
Frequency
(a)=
(y+1)/(b)
Chance %
=100/(a) Qp
2
1 1952 71.79 226.17 1 35.00 2.9 51152.2
2 1953 68.25 214.07 2 17.50 5.7 45827.2
3 1954 103.81 208.28 3 11.67 8.6 43380.0
4 1955 70.08 207.27 4 8.75 11.4 42961.5
5 1959 60.74 201.56 5 7.00 14.3 40626.3
6 1960 62.15 184.79 6 5.83 17.1 34146.9
7 1961 208.28 176.58 7 5.00 20.0 31178.8
8 1962 126.78 152.66 8 4.38 22.9 23305.4
9 1963 207.27 149.89 9 3.89 25.7 22467.0
10 1964 184.79 144.01 10 3.50 28.6 20739.1
11 1965 107.43 138.92 11 3.18 31.4 19300.0
12 1966 144.01 135.13 12 2.92 34.3 18260.9
13 1967 152.66 131.88 13 2.69 37.1 17391.3
14 1968 201.56 130.75 14 2.50 40.0 17096.1
15 1969 113.76 128.71 15 2.33 42.9 16566.3
16 1970 101.24 126.78 16 2.19 45.7 16072.2
17 1971 85.92 113.76 17 2.06 48.6 12940.5
18 1972 100.21 113.34 18 1.94 51.4 12846.8
19 1973 83.81 112.84 19 1.84 54.3 12733.8
20 1974 85.66 107.43 20 1.75 57.1 11540.8
21 1975 68.35 103.81 21 1.67 60.0 10775.6
22 1976 68.11 101.24 22 1.59 62.9 10249.9
23 1977 130.75 100.21 23 1.52 65.7 10043.0
24 1978 128.71 85.92 24 1.46 68.6 7381.8
25 1979 113.34 85.66 25 1.40 71.4 7337.5
26 1980 84.96 84.96 26 1.35 74.3 7217.6
27 1981 112.84 83.81 27 1.30 77.1 7024.8
28 1982 176.58 71.79 28 1.25 80.0 5154.0
29 1983 214.07 70.08 29 1.21 82.9 4911.8
30 1984 149.89 68.35 30 1.17 85.7 4672.0
31 1985 226.17 68.25 31 1.13 88.6 4658.7
32 1986 135.13 68.11 32 1.09 91.4 4638.8
33 1987 131.88 62.15 33 1.06 94.3 3863.2
34 1988 138.92 60.74 34 1.03 97.1 3689.9
Σ 4219.92 Σ 602151.80
Detailed Project Report Sagana III HEP Chapter 5 - Hydrology
Chapter 5 - 16
Mean peak discharge
Qp = 4219.920912 / 34
= 124.12
Mean of squares
Qp2 =
602151.8 / 34
= 17710.35
Standard deviation σ = [ y
[Qp2 - (Qp)
2]]
1/2
y-1
= 34 / (34 - 1 )
= 48.73
Frequency factor 'k' values for 46 years for 100 years
30 3.653 Therefore for 34 years = 3.642
35 3.598
The expected peak discharge for a flood having a = Qp + kσ
frequency of 100 years
= 124.12 + 3.642 x 48.73
= 301.59 Cumecs
Detailed Project Report Sagana III HEP Chapter 6- Power Potential and Installed Capacity
Chapter 6 - 1
Chapter 6 - Power Potential and Installed
Capacity
Detailed Project Report Sagana III HEP Chapter 6- Power Potential and Installed Capacity
Chapter 6 - 2
6 General
The assessment of amount of power that could be generated at the Sagana III Hydro – Electric
Power project and the related determination of generating capacity to be installed at this power
project have been made in accordance with the best internationally accepted technical practices,
recommendations and guidelines for small hydro power projects. This is a principal step towards
deriving the parameters of technically and economically suitable projects considering the
expected water availability at the intake site over the years, the seasonal variation in water flow,
the available head and the other related factors influencing the project dimensions.
The principal factors for this assessment are:
a) The available discharge of the Sagana River for different levels of dependability,
b) The appropriate head which can be developed based on actual topographic conditions,
c) The placement of the appurtenant structures of the project on the available topography.
6.1 Hydrological Data
A detailed analytical study of Hydrological data as prescribed for the project has been provided
in Chapter 5 – Hydrology. The calculations have been made on the basis of the discharge data for
the Sagana River collected over a period of 20 years from 1966 to 1986 by Water Resource
Management (WARMA) department of Govt. of Kenya. We have summed the individual
discharges for River Sagana, River Chania and River Gura before their confluence points and
adjusted for the catchment area till the intake site of Sagana III HEP. The discharge station for
River Sagana (code 4AA05) is located around11 Kms upstream of the Sagana III Intake site,
before the confluence of River Chania with River Sagana. The discharge station for River Chania
(code 4AC04) is located upstream of the confluence of River Chania with River Sagana. The
discharge station for River Gura (code 4AD01) is located around12 Kms upstream of the Sagana
III Intake site, before the confluence of River Gura with River Sagana. We have used this data to
arrive at the 50%, 75% and 90% dependable flow years for Sagana, with appropriate adjustment
for flow on a catchment area proportion basis. The years with incomplete data have been
removed from the series to give a complete 20 year series with appropriate adjustment for flow
on a catchment area proportion basis. The flow data for forty years was then subjected of the
weibull distribution analysis to calculate the 50%, 75% & 90% dependable years. The duration
curve of a 75% year is expected to give a fair approximation of the average flow over the
Detailed Project Report Sagana III HEP Chapter 6- Power Potential and Installed Capacity
Chapter 6 - 3
operative range of discharges. The discharge data worked out for a 75% year can thus form the
basis for optimization of installed capacity on energy generation basis.
6.2 Calculation of Net Head
The calculations for arriving at the net head are shown below:
Sr. No.
Particulars Calculations
A Design Data
a FSL at forebay = 1,269.37 m
b MDDL in forebay = 1,263.19 m
c Tail Water Level - Min = 1,210.91 m
d Tail Water Level - Max = 1,213.50 m
e Max. head variation = 100%
f Min. Head variation = 90%
g Design discharge = Qmax = 24.45 cumec
h Diameter of penstock =Dm = 2.70 m
i Length of penstock = Lmp = 180.00 m
j No. of bends = 5 Nos
k No of reduces = 2 Nos
l No. of valves = 2 Nos
m No of Y-piece = 1 Nos
n Gravity constant =g = 9.81 m/sec2
o Co-efficient for fritional loss =f = 0.012
p coefficient for bend loss =P = 0.060
q Entrance velocity =Ve = 0.750 m/sec
r Frictional velocity =Vf = 4.270 m/sec
s Velocity in bends =Vb = 4.270 m/sec
t Velocity in reducers =Vr = 4.270 m/sec
u Velocity in Valves Vv = 4.270 m/sec
v Velocity in y piece =Vy = 4.270 m/sec
B Design Calculations
(Reference- Manual on planning & design of small HEP, page-72
(i) Entrance loss = hffe = ( 0.1 * Ve2)/(2*g)
= 0.1 x 0.75^2) / (2 x 9.81)
= 0.003 m
(ii) Friction loss = hffr = (f * Lmp * Vf2)/ ( 2 * g * Dm)
= ( 0.012 x 180 x 4.27^2) / (2 x 9.81 x 2.7)
Detailed Project Report Sagana III HEP Chapter 6- Power Potential and Installed Capacity
Chapter 6 - 4
Sr. No.
Particulars Calculations
= 0.74 m
(iii) No of bends = N1 = 5
Bend losses = hfb = N1*P * Vb2/2*g
= ( 5 x 0.06 x 4.27^2) / (2 x 9.81)
= 0.279 m
(iv) No of reduces = N2 = 2
Loss in reducer pipe =hfr = N2*(0.25*Vr2/2*g) m
= ( 2 x 0.25 x 4.27^2) / (2 x 9.81)
= 0.465 m
(v) No. of valves =N3 = 2
Loss in valve = hfv = N3(0.25*V2/2*g)
= ( 2 x 0.25 x 4.27^2) / (2 x 9.81)
= 0.465 m
(vi) No of Y-piece =N4 = 1
Loss in Y-Piece = hfy = N4 *(0.8*Vm2/2*g)
= ( 1 x 0.8 x 4.27^2) / (2 x 9.81)
= 0.743 m
Total Losses (say ) =hfp = hffr+hfe+hfb+hfr+hfv+hfm
= 2.70 m
Head Calculations
(i) Max. Head = Gross head =Hmax = FSL in forebay - TWL min
= 1269.37 - 1210.91
= 58.46 m
(ii) Rated Head = Hrated = Gross head / Max. Head range
= 58.46 / 1
= 58.46 m
(iii) Min. Head = Hmin = MDDL in forebay - TWL max
= 1263.19 - 1213.5
= 49.69 m
(iv) Min. Head (based on turbine parameters)
= Rated Head x min head variation
= 58.46 x 0.9
= 52.61 m
Detailed Project Report Sagana III HEP Chapter 6- Power Potential and Installed Capacity
Chapter 6 - 5
Sr. No.
Particulars Calculations
Min. Head –lower of above two = 49.69 m
(v) Net Max. Head =Hmax(net) = Max. Head - Head loss
= 58.46 - 2.7
= 55.76 m
(vi) Net Rated Head =Hrated(net) = Rated Head - Head loss
= 58.46 - 2.7
= 55.76 m
(vii) Net Min. Head =Hmin(net) = Min. Head - Head loss
= 49.69 - 2.7
= 46.99 m
ABSTRACT
1 FSL at forebay = 1269.37 m
2 Tail Water Level - Min = 1210.91 m
3 Tail Water Level - Max = 1213.50 m
4 Max. Head = Gross head = 58.46 m
5 Min. Head = 49.69 m
6 Max. Net Head = 55.76 m
7 Rated Head = 55.76 m
8 Min. Net Head = 46.99 m
9 Total losses = 2.70 m
6.3 Energy Generation at different installed capacities
Optimization studies have been conducted to determine the optimum installed capacity of the
project. For study of power output and generation ten daily discharges as per 75% dependability
has been considered for various installed capacities form 7 MW to 14 MW on an incremental
basis of 1 MW.
Corresponding to the minimum discharge available during the lean season in the Sagana River
and the Gross head of 58.46m, the Francis turbine has been considered for study. An overall
efficiency of 86% (91% Turbine efficiency, 96% Generator efficiency and 98.5% Gear box
efficiency), has been used.
The power output from the project both in terms of MW, as well as energy generation in MU
with installed capacities ranging from 7 MW to 14 MW has been calculated. The detailed
calculations for assessment of power potential afforded by the project for various installations
are shown below:
Detailed Project Report Sagana III HEP Chapter 6- Power Potential and Installed Capacity
Chapter 6 - 6
MW 7 8 9 10 11 12 13 14
Total energy
generated in GWh 48.98 50.86 51.99 52.95 53.75 54.47 55.19 55.91
Plant Load Factor 80% 73% 66% 60.4% 56% 52% 48% 46%
Incremental energy
increase, GWh - 1.88 1.13 0.96 0.80 0.72 0.72 0.72
Generation
(GWh/MW) 7.00 6.36 5.78 5.30 4.89 4.54 4.25 3.99
% Utilization 80% 83% 85% 86% 87% 89% 90% 91%
PLF (lean season) 76% 67% 60% 54% 49% 45% 41% 38%
Rated discharge
(Cumecs) 14.90 17.02 19.15 21.28 23.41 25.53 27.66 29.79
Chart 6.1: Increase in Capacity vs. Incremental Energy:
-
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
1.80
2.00
44.00
46.00
48.00
50.00
52.00
54.00
56.00
58.00
7 8 9 10 11 12 13 14
Total energy generated in GWh Incremental energy increase, GWh
Detailed Project Report Sagana III HEP Chapter 6- Power Potential and Installed Capacity
Chapter 6 - 7
Chart 6.2 Generation vs. PLF
Based on a 75% dependable year, the scheme will generate around 52.95 Million Units (at 100%
availability and no overloading) of Energy with an installed capacity of 10 MW.
6.4 Energy Generation
Power output and energy generation, both restricted and unrestricted on a ten daily basis for 75%
dependable discharge on the Sagana River are shown in the tables below:
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
44
46
48
50
52
54
56
58
7 8 9 10 11 12 13 14
Pe
rce
nta
ge
GW
h
MW
Total energy generated in GWh Plant Load Factor
Detailed Project Report Sagana III HEP Chapter 6- Power Potential and Installed Capacity
Chapter 6 - 8
7
MONTH PERIOD 75% discharge 15% of lean Net Discharge Unrestricted Unrestricted
Restricted
Power Energy
10 day
Sagana III
HEP discharge cumecs Power, MW Power, GWh 7 MW GWh
JAN 1 16.86 1.32 15.54 7.30 1.75 7.00 1.68
2 14.31 1.32 12.98 6.10 1.46 6.10 1.46
3 16.47 1.32 15.14 7.12 1.71 7.00 1.68
FEB 4 13.86 1.32 12.53 5.89 1.41 5.89 1.41
5 12.66 1.32 11.34 5.33 1.28 5.33 1.28
6 15.14 1.32 13.82 6.49 1.56 6.49 1.56
MAR 7 15.82 1.32 14.49 6.81 1.63 6.81 1.63
8 16.21 1.32 14.88 6.99 1.68 6.99 1.68
9 18.50 1.32 17.18 8.07 1.94 7.00 1.68
APR 10 15.32 1.32 14.00 6.58 1.58 6.58 1.58
11 19.03 1.32 17.71 8.32 2.00 7.00 1.68
12 17.13 1.32 15.80 7.43 1.78 7.00 1.68
MAY 13 39.04 1.32 37.72 17.72 4.25 7.00 1.68
14 70.93 1.32 69.61 32.71 7.85 7.00 1.68
15 32.46 1.32 31.14 14.63 3.51 7.00 1.68
JUN 16 18.99 1.32 17.67 8.30 1.99 7.00 1.68
17 14.45 1.32 13.13 6.17 1.48 6.17 1.48
18 12.33 1.32 11.00 5.17 1.24 5.17 1.24
JUL 19 11.31 1.32 9.98 4.69 1.13 4.69 1.13
20 10.57 1.32 9.24 4.34 1.04 4.34 1.04
21 10.39 1.32 9.07 4.26 1.02 4.26 1.02
AUG 22 10.33 1.32 9.01 4.23 1.02 4.23 1.02
23 10.45 1.32 9.13 4.29 1.03 4.29 1.03
24 9.99 1.32 8.67 4.07 0.98 4.07 0.98
SEP 25 9.98 1.32 8.66 4.07 0.98 4.07 0.98
26 14.39 1.32 13.07 6.14 1.47 6.14 1.47
27 9.97 1.32 8.65 4.06 0.98 4.06 0.98
OCT 28 8.82 1.32 7.50 3.52 0.85 3.52 0.85
29 14.74 1.32 13.41 6.30 1.51 6.30 1.51
30 10.02 1.32 8.70 4.09 0.98 4.09 0.98
NOV 31 10.48 1.32 9.16 4.31 1.03 4.31 1.03
32 13.44 1.32 12.12 5.69 1.37 5.69 1.37
33 23.32 1.32 21.99 10.34 2.48 7.00 1.68
DEC 34 15.25 1.32 13.92 6.54 1.57 6.54 1.57
35 10.61 1.32 9.29 4.37 1.05 4.37 1.05
36 8.87 1.32 7.55 3.55 0.85 3.55 0.85
Total energy generated in GWh
61.45
48.98
Plant Load Factor
79.88%
Incremental energy increase, GWh
-
Generation (GWh/MW)
7.00
% Utilization
79.7%
PLF (lean season)
75.5%
Detailed Project Report Sagana III HEP Chapter 6- Power Potential and Installed Capacity
Chapter 6 - 9
8 9 10 11
MONTH PERIOD
10 day 8 MW GWh 9 MW GWh 10 MW GWh 11 MW GWh
JAN 1 7.30 1.75 7.30 1.75 7.30 1.75 7.30 1.75
2 6.10 1.46 6.10 1.46 6.10 1.46 6.10 1.46
3 7.12 1.71 7.12 1.71 7.12 1.71 7.12 1.71
FEB 4 5.89 1.41 5.89 1.41 5.89 1.41 5.89 1.41
5 5.33 1.28 5.33 1.28 5.33 1.28 5.33 1.28
6 6.49 1.56 6.49 1.56 6.49 1.56 6.49 1.56
MAR 7 6.81 1.63 6.81 1.63 6.81 1.63 6.81 1.63
8 6.99 1.68 6.99 1.68 6.99 1.68 6.99 1.68
9 8.00 1.92 8.07 1.94 8.07 1.94 8.07 1.94
APR 10 6.58 1.58 6.58 1.58 6.58 1.58 6.58 1.58
11 8.00 1.92 8.32 2.00 8.32 2.00 8.32 2.00
12 7.43 1.78 7.43 1.78 7.43 1.78 7.43 1.78
MAY 13 8.00 1.92 9.00 2.16 10.00 2.40 11.00 2.64
14 8.00 1.92 9.00 2.16 10.00 2.40 11.00 2.64
15 8.00 1.92 9.00 2.16 10.00 2.40 11.00 2.64
JUN 16 8.00 1.92 8.30 1.99 8.30 1.99 8.30 1.99
17 6.17 1.48 6.17 1.48 6.17 1.48 6.17 1.48
18 5.17 1.24 5.17 1.24 5.17 1.24 5.17 1.24
JUL 19 4.69 1.13 4.69 1.13 4.69 1.13 4.69 1.13
20 4.34 1.04 4.34 1.04 4.34 1.04 4.34 1.04
21 4.26 1.02 4.26 1.02 4.26 1.02 4.26 1.02
AUG 22 4.23 1.02 4.23 1.02 4.23 1.02 4.23 1.02
23 4.29 1.03 4.29 1.03 4.29 1.03 4.29 1.03
24 4.07 0.98 4.07 0.98 4.07 0.98 4.07 0.98
SEP 25 4.07 0.98 4.07 0.98 4.07 0.98 4.07 0.98
26 6.14 1.47 6.14 1.47 6.14 1.47 6.14 1.47
27 4.06 0.98 4.06 0.98 4.06 0.98 4.06 0.98
OCT 28 3.52 0.85 3.52 0.85 3.52 0.85 3.52 0.85
29 6.30 1.51 6.30 1.51 6.30 1.51 6.30 1.51
30 4.09 0.98 4.09 0.98 4.09 0.98 4.09 0.98
NOV 31 4.31 1.03 4.31 1.03 4.31 1.03 4.31 1.03
32 5.69 1.37 5.69 1.37 5.69 1.37 5.69 1.37
33 8.00 1.92 9.00 2.16 10.00 2.40 10.34 2.48
DEC 34 6.54 1.57 6.54 1.57 6.54 1.57 6.54 1.57
35 4.37 1.05 4.37 1.05 4.37 1.05 4.37 1.05
36 3.55 0.85 3.55 0.85 3.55 0.85 3.55 0.85
Total energy generated in GWh 50.86
51.99
52.95
53.75
Plant Load Factor
72.58%
65.94%
60.45%
55.78%
Incremental energy increase, GWh
1.88
1.13
0.96
0.80
Generation (GWh/MW)
6.36
5.78
5.30
4.89
% Utilization
82.8%
84.6%
86.2%
87.5%
PLF (lean season) 66.9%
59.5%
53.6%
48.7%
Detailed Project Report Sagana III HEP Chapter 6- Power Potential and Installed Capacity
Chapter 6 - 10
12
13
14
15
MONTH PERIOD
10 day 12 MW GWh 13 MW GWh 14 MW GWh 15 MW GWh
JAN 1 7.30 1.75 7.30 1.75 7.30 1.75 7.30 1.75
2 6.10 1.46 6.10 1.46 6.10 1.46 6.10 1.46
3 7.12 1.71 7.12 1.71 7.12 1.71 7.12 1.71
FEB 4 5.89 1.41 5.89 1.41 5.89 1.41 5.89 1.41
5 5.33 1.28 5.33 1.28 5.33 1.28 5.33 1.28
6 6.49 1.56 6.49 1.56 6.49 1.56 6.49 1.56
MAR 7 6.81 1.63 6.81 1.63 6.81 1.63 6.81 1.63
8 6.99 1.68 6.99 1.68 6.99 1.68 6.99 1.68
9 8.07 1.94 8.07 1.94 8.07 1.94 8.07 1.94
APR 10 6.58 1.58 6.58 1.58 6.58 1.58 6.58 1.58
11 8.32 2.00 8.32 2.00 8.32 2.00 8.32 2.00
12 7.43 1.78 7.43 1.78 7.43 1.78 7.43 1.78
MAY 13 12.00 2.88 13.00 3.12 14.00 3.36 15.00 3.60
14 12.00 2.88 13.00 3.12 14.00 3.36 15.00 3.60
15 12.00 2.88 13.00 3.12 14.00 3.36 14.63 3.51
JUN 16 8.30 1.99 8.30 1.99 8.30 1.99 8.30 1.99
17 6.17 1.48 6.17 1.48 6.17 1.48 6.17 1.48
18 5.17 1.24 5.17 1.24 5.17 1.24 5.17 1.24
JUL 19 4.69 1.13 4.69 1.13 4.69 1.13 4.69 1.13
20 4.34 1.04 4.34 1.04 4.34 1.04 4.34 1.04
21 4.26 1.02 4.26 1.02 4.26 1.02 4.26 1.02
AUG 22 4.23 1.02 4.23 1.02 4.23 1.02 4.23 1.02
23 4.29 1.03 4.29 1.03 4.29 1.03 4.29 1.03
24 4.07 0.98 4.07 0.98 4.07 0.98 4.07 0.98
SEP 25 4.07 0.98 4.07 0.98 4.07 0.98 4.07 0.98
26 6.14 1.47 6.14 1.47 6.14 1.47 6.14 1.47
27 4.06 0.98 4.06 0.98 4.06 0.98 4.06 0.98
OCT 28 3.52 0.85 3.52 0.85 3.52 0.85 3.52 0.85
29 6.30 1.51 6.30 1.51 6.30 1.51 6.30 1.51
30 4.09 0.98 4.09 0.98 4.09 0.98 4.09 0.98
NOV 31 4.31 1.03 4.31 1.03 4.31 1.03 4.31 1.03
32 5.69 1.37 5.69 1.37 5.69 1.37 5.69 1.37
33 10.34 2.48 10.34 2.48 10.34 2.48 10.34 2.48
DEC 34 6.54 1.57 6.54 1.57 6.54 1.57 6.54 1.57
35 4.37 1.05 4.37 1.05 4.37 1.05 4.37 1.05
36 3.55 0.85 3.55 0.85 3.55 0.85 3.55 0.85
Total energy generated in GWh
54.47
55.19
55.91
56.54
Plant Load Factor
51.82%
48.46%
45.59%
43.03%
Incremental energy increase, GWh
0.72
0.72
0.72
0.63
Generation (GWh/MW)
4.54
4.25
3.99
3.77
% Utilization
88.6%
89.8%
91.0%
92.0%
PLF (lean season)
44.7%
41.2%
38.3%
35.7%
Detailed Project Report Sagana III HEP Chapter 7 - Geology
Chapter 7 - 1
Chapter 7- Geology
Detailed Project Report Sagana III HEP Chapter 7 - Geology
Chapter 7 - 2
7. General
Kenya is located in the Eastern part of Africa. The Rift valley transverse through Kenya from
north to south. The East African Rift System (EARS) is a 50 to 60km wide zone of active
volcanoes and faulting that extends north-south in Eastern Africa for more than 3000 km (1864
miles) from Ethiopia in the north to Zambezi in the south. It is a rare example of an active
continental rift zone, where a continental plate is attempting to split into two plates which are
moving away from one another. This is the main source of seismicity in Kenya.
The Sagana III hydroelectric power project is in the central province of Kenya. The intake of the
project is located on the Sagana River. Historically no major earthquake has occurred in this
region.
Table 7.1 Major Earthquakes in Kenya
Region Magnitude Date Location
Lake Rudolf Region 5.3 22-Jan-12 549 km (341 miles) N of NAIROBI, Kenya
Lake Turkana 4.8 23-Oct-10 180 km (110 miles) N of Lodwar, Kenya
Lake Tanganyika region 6.8 5-Dec-05 960 km (590 miles) SW of NAIROBI, Kenya
To assess to true geological pattern of the project, geological and geophysical investigations
including drilling and drifting, field and laboratory tests on rocks, construction material
investigations and testing, collection of hydrological and meteorological data, hydraulic model
studies for all the appurtenant features of the project will have to be carried out. This will help in
activities such as foundation treatment measures and minimizing construction surprises. The
following summarizes the various tests that should be carried out to get an understanding of the
geological profile of the project:
7.1 Geological Investigation
A wide range of investigation techniques will have to be carried out to collect the required
geological and geotechnical data viz. surface geological mapping, exploratory drilling, drifting,
laboratory testing and in-situ rock mechanics testing for various component of the project. These
investigations will be utilized in fulfilling the following objectives:
To evaluate and optimize the layout of the different project components on geological
considerations.
Detailed Project Report Sagana III HEP Chapter 7 - Geology
Chapter 7 - 3
To collect sufficient qualitative and quantitative geological and geotechnical information
for techno economic design of the project components so that basic parameters for major
structures can be optimized.
To collect sufficient data to plan suitable construction methodology and a reasonable cost
estimate, etc.
7.2 Regional Geological Studies:
Available literature on geology of the central province of Kenya will have to be studied to
understand the geological setup of the area.
7.3 Geological Mapping:
Detailed geological mapping of the proposed project area should be carried out on 1:1000 scale.
During the surface geological mapping, different rock types and overburden material should be
classified. Geotechnical parameters of each outcrop were collected for rock mass
characterization. During reservoir geological mapping, traverses should be taken along the
reservoir rim to separate different type of overburden/rock and to identify potential zone of
landslides, if any, to establish overall stability of the structures.
7.4 Exploratory Drilling:
Appropriate number of exploratory drill holes should be drilled in proposed project area to
evaluate depth of overburden and quality of bed rock. Summary of the location of drill holes to
serve as a guideline for these drill holes are given in table below:
Sl. no. Location Number of drills
1 Diversion Structure left Bank 2
2 Diversion Structure Right Bank 3
3 Weir Axis River bed 2
4 Power House center 1
5 Power House Wall 1
6 Downstream Apron 1
7 Coffer Dam, River Bed 1
8 Head Race Tunnel Inlet 1
Detailed Project Report Sagana III HEP Chapter 7 - Geology
Chapter 7 - 4
Sl. no. Location Number of drills
9 Head Race Tunnel Outlet 1
10 Water Channel 2
11 TRC Outlet 1
7.5 Permeability Test:
Permeability test for overburden have to be conducted in exploratory drill holes using constant
head method. Water pressure tests in bed rock will also have to be conducted using single/double
packer. The length of each test section should be kept as 1.5 to 3.0m.
7.6 Exploratory Drift:
The intake area should be explored with two exploratory drifts of size 1.8m x 2.1m in the right
and left abutments to ascertain the soundness of abutments, limit of distressing and visualize the
abutment rock parameters like rock mass quality, and assess the rock material and mass
characteristics.
7.7 Laboratory Tests:
The laboratory tests on core samples/ rock samples should be conducted to determine the
following physical and engineering properties of the rock mass in project area:
Density;
Unconfined Compressive Strength (Dry & Saturated);
Water Absorption;
Modulus of Elasticity and Poisson’s ratio;
Tensile Strength (Dry & Saturated);
Ultra Sonic pulse wave velocity;
Point Load Strength Index;
Slake Durability;
Shear Parameter;
Detailed Project Report Sagana III HEP Chapter 7 - Geology
Chapter 7 - 5
7.8 Petrographic Studies:
Five number of rock core sample from different project component of the proposed project area
should be tested to determine the minerological content and its percentage.
7.9 In-situ Tests:
Following in-situ tests should been carried out-
Block Shear Test - Between Concrete and rock (C & Φ values).
Between Rock and Rock (C& Φ values).
Plate Load Test - Modulus of Elasticity/deformation
7.10 Construction Material Survey and tests
Construction material survey were carried out to estimate quality and quantity of coarse and fine
aggregate and impervious material for proposed diversion structure, coffer dam, HRT, water
channel and power house complex.
Various laboratory tests have been suggested, such as-
A) Test for coarse aggregates:
Gradation analysis;
Specific Gravity;
Water Absorption;
Aggregate Abrasion value;
Aggregate Crushing value;
Aggregate Impact value;
Soundness (5 Cycles);
Flakiness Index;
B) Test for fine aggregates:
Gradation analysis;
Specific Gravity;
Detailed Project Report Sagana III HEP Chapter 7 - Geology
Chapter 7 - 6
Fineness Modulus;
Water Absorption;
Silt and Clay content;
Soundness (5 Cycles);
Organic Impurities;
Petrographic examination (for fine and silt) etc.
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 1
Chapter 8-Civil Engineering Structures
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 2
8. Structure & Layout
The main objective of the Sagana-III Small Hydro Electric Project is to generate power
economically and expeditiously, utilizing the local available material and labour to the extent
possible. The design for the project components has been planned to have simple and cost
effective execution of civil works. General layout of the scheme is shown in Drawing No.
‘Sagana-III-001’. The project envisages utilizing the water of Sagana River through a
diversion structure at an elevation of 1274m. The Power house is located at an elevation of
1210 m. The main components include trench weir, de-silting arrangement, a ~4.8 km long
water conductor system, Forebay & buried Penstock, with the main Penstock being ~175m,
branch penstock of ~15 m length each. The scheme proposes to utilize a gross head of
58.46m to generate 10 MW of power, with a rated discharge of 21.26 cumecs. The power will
be evacuated through a ~7 km long 132KV line to Sagana Town for Sagana - Kutus line.
8.1 General:
The major civil engineering structures of the project are as under:-
1. Diversion Structure (Intake)
2. Intake channel
3. Desilting tank
4. Tunnel
5. Power channel
6. Penstock
7. Power House
8. Tail pool
9. Tail race channel
10. Switchyard
Detailed description of each of these structures is as follows:-
8.1.1 Diversion Structure and Intake
Diversion structure is required across the stream for diverting its discharge for power
generation which should be least expensive and as simple as possible. The diversion structure
in hilly streams can be of two types:
Solid boulder type weirs
Trench type weirs
The following aspects need to be considered while selecting the type of weir.
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 3
Diversion structures face a recurring problem due to choking of over ground intake
structures and are vulnerable to damage from heavy boulders and bed loads.
More often it is not possible to provide storage at the diversion site due to fast filling
up tendency of the storage space by stone and boulders.
Where the riverbed is non-rocky, maintenance and repairs of damages due to scour
may create problems in case of solid boulder type weirs.
This is a run of the river type scheme and storage cannot be provided because of its inherent fast
filling tendency. A trench type weir is thus considered suitable for this site. Trench type weirs
constructed in similar hilly terrains have proved to be successful over the years in various other
projects worldwide. The trench type weir shall be capable of diverting all the lean season flows
and the structure shall also be capable of passing safely the 100-year return period flood discharge.
A trench type weir is a simple trapezoidal/rectangular trough made up of reinforced cement
concrete (RCC) provided with sloping steel trash rack over the full width of weir on the top. The
criteria for determining the length of the trench weir is that it should be capable to pass the design
flood discharge. Length of the trench weir has been kept as 25 meters to pass the 46-year return
period flood discharge of 301.59 cumecs with HFL at EL. 1276.7 meters. The bed of the trench
weir has been provided with an adequate slope of 1 in 16 in the flow direction so that sufficient
velocity is generated to carry away small stones and heavy silt upto 25 mm size that may find
entry into the weir through the trash rack openings. The FSL in the trench weir has been fixed at
EL. 1274.00 meter. The trash rack proposed is proposed to be of the size 4.7 x 2.5 meter. The trash
rack has been given a slope of 1 in 10 in the flow direction so that stones and pebbles above 25
mm size do not enter into the weir but roll down into the stream with the flow. The trash rack area
of opening is adequate to draw the entire lean season flow and desired diversion discharge during
the flood season even if 50% of the effective area of the trash rack is clogged. The trash rack will
have to be cleaned periodically during and after rainy season to clear any deposited material.
The upstream and downstream of trench weir is protected RCC wall of 1.3 m x 25 m. with boulder
filled wire crates of size 0.5m x 1m x 1m is also put on bed of river and downstream of trench weir
has been protected with cast in SITU concrete blocks of 500 m with slope 1 in 20 upstream and
1:20 downstream along the flow.
The intake located at the end of the trench weir is a gated well structure to be constructed in RCC.
The intake gate control shall permit the release of desired discharge through (4.6m x ~4.5m x
.25m) approach tunnel and (4.6m x ~4.1m x .25m) RCC channel to the desilting tank. The top of
intake structure has been fixed at elevation EL. 1277.90 m. The intake structure has been provided
with one vertical lift gate for regulating the discharge into the water conductor system. One
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 4
vertical lift slide type stoplog gate of size 4.9m x 4.2m is provided for emergency and maintenance
purpose at the upstream of the service gate. Shingle flushing pipe of diameter 1500mm has been
provided to exclude debris, wooden logs and such bigger particles at the bottom of the intake
structure having elevation of EL. 1269.50 m. One number shingle flushing gate of size 1.4m x 1.5
m has been provided at the entry of the pipe.
Plan and section of trench weir and intake well are shown in drawing no Sagana-III-002 &
Sagana-III-003 respectively.
8.1.2 Approach Tunnel
A 1260 m long tunnel of height 4.5m, width 4.9m, thickness of RCC box 0.15m has been
proposed to carry the discharge from the trench weir to the desilting basin. The bed slope
provided in the channel is 1 in 1130 which will generate a velocity of 2.0 m/s at a discharge
of 29.34 cumecs (adding 20% excess flow to the plant flow of 24.45 cumecs for desilting
basin).
8.1.3 Approach Channel
A 90 m long RCC box intake channel of base width 4.6m and the full supply depth being
3.2m, thickness of RCC box 0.25m has been proposed to carry the discharge from approach
tunnel to the desilting basin. The bed slope provided in the channel is 1 in 1130 which will
generate a velocity of 2.0 m/s at a discharge of 29.34 cumecs (adding 20% excess flow to the
plant flow of 24.45 cumecs for desilting basin). After construction the intake channel would
be backfilled to the ground level.
8.1.4 Desilting Tank
The hilly streams generally carry appreciable quantities of coarse silt and sand during the
rainy season. It is, therefore, necessary to provide desilting tank to exclude coarse particles so
as to minimize the abrasion to the turbine runner or buckets especially in high head schemes
where abrasion effect becomes more pronounced.
A desilting tank proposed is of conventional Surface Central Silt Gutter type having 2
chambers of ~82 m x 10 m each to exclude coarser particles of size exceeding 0.25 mm from
water flow. The horizontal velocity of flow and the settling velocity of flow are 0.22 m/sec
and 0.0275 m/sec respectively. Slope of 1 in 4 has been provided to flush out the accumulated
silts. The accumulated silt is proposed through 1000 mm diameter MS pipe. The flushing
operation in the pipe will be regulated by means of 1000mm diameter gate valve provided in
the pipe outside the desilting basin. Two vertical lift type gates upstream and downstream
have been provided for maintenance purpose in each chamber.
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 5
8.1.5 Water Conductor System
The Water conductor system consists of the following sections:
8.1.5.1 Tunnel Ch. 01 to Ch. 1260
A 1260 m long tunnel of bed width of 4.8 m and vertical height of ~4.5 m for fair to
good rock and base width of 4.8 m for poor rocks and base width of 5.4 m for very
poor rocks have been proposed to convey the discharge. The tunnel has been provided
with bed slope of 1 in 1130. The velocity in the tunnel has been limited to 2.0 m/s.
8.1.5.2 RCC Rectangular Channel Ch.1260 to Ch.1350
A 90 m long RCC rectangular channel of base width of 4.6 m and vertical height of 4.1
m has been proposed to convey the discharge from approach tunnel to the desilting tank.
The channel has been provided with bed slope of 1 in 1130. The velocity in the channel
has been limited to 2.0 m/s
8.1.5.3 Power Channel 1 Ch.1432 to Ch. 2177
A 745 m long RCC rectangular channel of base width of 4.2 m and vertical height of 3.8
m has been proposed to convey the discharge from desilting tank. The channel has been
provided with bed slope of 1 in 1130. The velocity in the channel has been limited to 2.0
m/s.
8.1.5.4 Tunnel 2 Ch.2177 to Ch. 4517
A 2340 m long tunnel of bed width of 4.8 m and vertical height of ~4.5 m for fair to
good rock and base width of 4.8 m for poor rocks and base width of 5.4 m for very
poor rocks have been proposed to convey the discharge. The tunnel has been provided
with bed slope of 1 in 1010. The velocity in the tunnel has been limited to 2.0 m/s.
8.1.5.5 Power Channel 2 Ch. 4517 to 4887
A 370 m long RCC rectangular channel of base width of 4.2 m and vertical height of 3.8
m has been proposed to convey the discharge from tunnel 2. The channel has been
provided with bed slope of 1 in 1010. The velocity in the channel has been limited to 2.0
m/s.
8.1.6 Forebay
To cater to the sudden surges in demand or rejection of the turbine, a depressed bed type forebay ~
(40 m x 18 m x 15m) having storage of ~4400 cu. m. (equivalent to 3 Minutes of operation at peak
load) will be designed. Land in the form of a flat field has been identified for the location of the
forebay. A provision for trash rack and penstock gates has been provided before the penstock
intake.
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 6
Plan and section of forebay and other details are shown in drawing no. ‘Sagana-III- 008’ and
‘Sagana-III- 009’.
8.1.7 Penstock
Penstock alignment has been finalized after a careful study of the alternative proposals and
adopting the one, which requires minimum excavation as well as minimum number of bends.
Buried penstock has been provided suitable to the existing topography. One no. main penstock
pipe of steel 2700 mm diameter has been provided from the forebay. The length of main penstock
is ~168 meter and that of the two branches is ~15.5m. The penstock is proposed to be fabricated
from medium tensile steel plates conforming to IS: 2002-1992 grade 2 steel and properly welded.
The welded penstock shall have less hydraulic losses besides ease of transportation and erection.
The plate thicknesses of penstock will vary from 10 mm to 14 mm in various reaches. Flow
velocity of 4.3 m/sec through the penstock is proposed to reduce the losses.
The buried penstock has been anchored at both the horizontal and vertical bends to resist the
unbalanced hydrostatic forces due to change in the direction of flow and to prevent movement of
penstock on account of vibration or water hammer effect. All anchor blocks will be of RCC and
their stability has been checked as per IS Standards. The buried penstock is supported between the
anchor blocks by the saddle supports made of RCC. The main penstock shall be bifurcated into 2
unit penstocks of diameter 1.9 m and length ~15.5 m each, which will feed 2 horizontal axis
Francis turbine situated in the power house. Layout and details of penstock, bends, bellmouth, and
reducers are shown in drawing no. Sagana-III-06.
8.1.8 Power House and Tail Race Channel
A surface power house has been proposed on the right bank of Sagana River at an elevation of
1209.91 m. The proposed power house building is ~28.2 meter long and ~17 meter wide for
housing the generating unit, control panels, store cum workshop, battery room etc.. The height of
powerhouse from the floor level has been kept about ~18 meter. The sidewalls shall be made of
stone masonry and columns, beams, foundations of generating units shall be laid in RCC M-25
grade. The power house shall comprise of following components :
1) Service Bay
2) Machine Hall
3) Control Room
1) Service Bay: it has been proposed at elevation RL. 1215 m.
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 7
2) Machine Hall: The machine hall dimensions are 12.05m x 23 m. It will house 2 units of
horizontal axis Francis turbine with c/c distance of 10 m. the machine hall elevation in RL.1209.91
m. And center line of Machine shall be kept at RL.1208.18 m.
3) Control Room It has an elevation of RL.1215 m and consists of battery room, office block,
toilet block, store room. Its dimensions are 4500mm x 6425mm.
A crane beam has been provided at elevation EL. 1221.5 m on both side of power house to support
operational load of EOT crane. Two Draft Tube gates have been provided dimensions of ~3 m x
2.2 m operated by rope drum hoist
8.1.9 Tail Race Channel
A RCC rectangular channel of base width 4.65 m and length 10 m has been proposed to carry
water discharge after power generation back to Sagana River with a slope of 1 in 2150. A tail pool
of 13 m x 36m with slope of 1 in 4 is considered having max tail water level at EL1213.50m.
8.1.10 Switchyard
Surface switchgear cum transformer yard has been proposed adjacent to the power house. It will
consist of a power transformer, circuit breakers, current transformers, potential transformers,
isolators etc. The equipment will be designed for stepping up from 11 kV to 132 kV for
evacuation.
A ~7 km transmission line will be constructed to evacuate the power to the newly being
constructed Sagana town substation from where it will meet Sagana-Kutus 132 KV line
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 8
Annexure 8.1- Hydraulic Design of Components
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 9
Hydraulic Design of Project Components for Sagana-III HEP:
Trench Weir
Sl.
No. Particulars
Units Calculations
A Design Data
a Design Discharge of plant= (Qmax) cumecs = 24.45
b Width of stream = L m = 25.00
c River bed level = (RBL) m = 1,274.00
B Design calculations
1 Width of trench weir (w)
a Width of trench weir at top = (B)
=
( )
Where
B = Width of trashrack (width of trench weir
at top) in m
Q = Diverted discharge in cumecs
E1 = Ratio of Area of opening to total area
of trash rack surface over trench
50%
E2 = Ratio of opening in the trashrack likely
to be clogged
50%
Cd = Coefficient of discharge through
opening
0.46
L = Width of stream m
25.00
g = Acceleration due to gravity m/sec2
9.81
E = Specific energy at any section of stream
in the trench weir
= (
)
C = Coefficient of discharge for broad
crested weir
1.53
Diverted discharge (Q)
=
Design Discharge of plant + 20%
extra for flushing at D-tank + 25%
extra for flushing at intake
cumecs = 24.45 + (24.45 x 0.45 )
cumecs = 35.45
Specific energy at any section of stream in
the trench weir (E) = (
)
= (35.45 /1.53 x25)^(2/3)
= 0.95
Therefore,
Width of trench weir at top m B=
√
= 35.45
0.5 x0.5 x0.46 x25 (2 x 9.81 x
0.95)^(1/2)
= 35.45
12.41
= 2.86
Provide Width
2.90
b Width by considering velocity
Allowable velocity through trashrack
opening m/sec v 0.75
Width m =
= 35.45 / ( 25 x 0.75)
= 1.89
Width required for 50% clogging criteria m = 2 x 1.89
= 3.78
Provide width, being higher m = 3.80
2 Depth of trench weir (d)
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 10
Sl.
No. Particulars
Units Calculations
Area (A) = Width x depth
= 3.8 x d
Velocity head at the end of trench (H ) = (η/η+1) x (A/2w)
Where,
η= constant depending on bottom profile of
channel = 0.50
= (0.5 / 0.5 + 1) x (3.8 x d / 2 x3.8)
= 0.17000
= 0.17 d
The corresponding discharge =(Q) = ( )
35.45 = 3.8 x d x (2x 9.81 x0.17 d)^0.5
d3/2 = 5.11
d = 2.97
Provide depth at end ( From Intake criteria) m = 4.50
Therefore, Provide depth at start
m =
4.5 - ( width of stream / slope in
trench)
= 4.5 - ( 25 / 25)
= 3.50
Greater than required depth
Hence OK
Check for adequacy of waterway
Average depth = m = (3.5 + 4.5 )/2
= 4.000
Area (A) Sq. m = 3.8 x 4
= 15.20
Wetted perimeter (P) m = 3.8 +( 2 x 4 )
= 11.80
Slope provided (S) = ( 4.5 - 2.97) /25
= 0.06120
i.e. 1 in
16.00
Using Manning’s formula with value of n =
0.018
Discharge Q cumecs = (
)
=
(1/0.018) x 15.2 x (15.2 /
11.8)^(2/3) x0.0612^(1/2)
cumecs = 247.32
which is greater than design Q Hence OK
Check for adequacy of capacity with 50%
area clogged
Average depth (d) m = 4 / 2
= 2.00
Area (A) Sq. m = 3.8 x 2
= 7.60
Wetted perimeter (P) m = 3.8 +( 2 x 2 )
= 7.80
Slope provided (S) = ( 4.5 - 2.97) /25
= 0.060
Using Manning’s formula with value of n =
0.018
Discharge Q cumecs = (
)
=
(1/0.018) x 7.6 x (7.6 / 7.8)^(2/3)
x0.06^(1/2)
cumecs = 101.65
which is greater than designed Q Hence OK
3 Top RL of trench
Provide Top RL of trench m = River bed level
= 1274.00
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 11
Sl.
No. Particulars
Units Calculations
Therefore, FSL in Trench weir = Top RL of trench
m = 1274.00
4 Trash rack dimensions
slope of trash rack 1 in = 10.00
Therefore, Width of trash rack
=
((3.8/10)^2 +(3.8^2))^0.5 + 2 x
0.175
m = 3.97
ABATRACT
1 Length of trench m = 25.00
2 Width of trench m = 3.80
3 Trench depth at start m = 3.50
4 Trench depth at intake m = 4.50
5 Slope provided 1 in m = 16.00
6 FSL in Trench weir m = 1,274.00
7 Bottom RL at start of trench m = 1,270.50
8 Bottom RL at end of trench m = 1,269.50
9 Length of trash rack m = 25.00
10 Width of trash rack m = 3.97
Intake Tower
Sl.
No. Particulars Units Calculations
A Design Data
a Design discharge of plant = Qmax Cumecs = 24.45
b Pond level = FSL M = 1,274.00
c Height of opening @ entry of WCS =(h) M = 3.20
e Flushing velocity = vf m/sec = 3.50
f Provision for bellmouth = hb M = 0.30
g Silt trap depth proposed m = 0.50
h HFL at trench weir site m = 1,276.70
B Design Computations
1 Computation of bottom level of Intake
Bottom of Intake = FSL in cut & cover channel -FSD
= 1274 - 3.2
= 1,270.80
Sill level of bellmouth = Bottom of Intake -hb
= 1270.8 - 0.3
= 1,270.50
Bottom of shingle flushing pipe =
Sill level of bellmouth - Dia. of
shingle flushing pipe
= 1270.5 - 1.5
= 1,269.00
Bottom of stop log gate (Allowing water
cushion) =
Bottom of shingle flushing pipe +
Water cushion
= 1269 + 0.5
= 1,269.50
2 Computation of dia. of flushing pipe
Flushing discharge = 25 % 0f design discharge
Qf = (24.45x 0.25)
= 6.11
Therefore, Dia. of flushing pipe = d m = (Qf x 4 / 3.14 x 3.5 )^0.5
= 1.49
Say = 1.50
3 Computation of depth of trench at exit
Depth of trench at exit = D = FSLp - Sill level of stop log gate
m = (1274 -1269.5)
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 12
Sl.
No. Particulars Units Calculations
D m = 4.50
4 Height of intake chamber = HFL + free board
= 1276.7 + 1.2
m = 1,277.90
ABSTRACT
1 Sill level of intake opening (service gate) m = 1,270.80
2 Dia. Of shingle flushing pipe m = 1.50
3 Sill RL of Shingle flushing pipe m = 1,269.00
4 Sill RL of Stop log gate = 1,269.50
5 Depth of trench at exit m = 4.50
6 Top RL of intake chamber m = 1,277.90
Tunnel 1
Sl.
No. Particulars Units Calculations
From Intake to Desilting Tank
1 Design data
a Design discharge of plant =Qmax cumecs = 24.45
b FSL at the start of tunnel m = 1,274.00
c Velocity limited = V m/sec = 2.00
d Rugosity coefficient = n = 0.018
e Length of tunnel =L m = 1,260.00
2 Design calculations
Computation of bed width & FSD of tunnel
Design discharge in tunnel = (Q) cumecs = 29.34
Area required = A Sq. m = Q/V
= 29.34 / 2
Sq. m = 14.67
Provide water depth in tunnel m = 3.20
Therefore, width of tunnel m = 14.67 / 3.2
m = 4.60
Perimeter = (P) = b + 2 d
= 4.6 + (2 x3.2 )
m =
11.00
Hydraulic Radius =(R ) = A / P
= 14.67 /11
m =
1.33
Computation of slope of tunnel bed
Using Manning's Formula = v = (
)
S1/2 = (
)
S = (
)
= (2 x 0.018)/1.33^(2/3))^2
S = 0.0009
Provide slope of 1 in = 1130
Computation of FSL at end of tunnel
Reduced FSL at the beginning m = FSL at start of cut & cover tunnel
m = 1,274.00
Reduced FSL at end m = FSL1 - (Length/Slope)
= 1274- (1260 / 1130)
m = 1,272.88
Provision of free board
Free board (for 7 to 30 cumecs ) m = 0.90
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 13
Sl.
No. Particulars Units Calculations
ABSTRACT
1 Base width m = 4.60
2 FSD in tunnel m = 3.20
3 Free board of tunnel m = 0.90
4 Bed slope of tunnel - 1 in m = 1,130
5 Length of tunnel m = 1,260
6 FSL at beginning of tunnel m = 1,274.00
7 FSL at end of tunnel m = 1,272.88
Approach Channel
Sl.
No. Particulars Units Calculations
From Intake to Desilting Tank
1 Design data
a Design discharge of plant =Qmax cumecs = 24.45
b FSL at the end of power channel-2 m = 1,272.88
c Velocity limited = V m/sec = 2.00
d Rugosity coefficient = n = 0.018
e Length of power channel =L m = 90.00
2 Design calculations
Computation of bed width & FSD of channel
Design discharge in channel = (Q) cumecs = 29.34
Area required = A Sq. m = Q/V
= 29.34 / 2
Sq. m = 14.67
Provide water depth in channel m = 3.20
Therefore, width of channel m = 14.67 / 3.2
m = 4.60
Perimeter = (P) = b + 2 d
= 4.6 + (2 x3.2 )
m = 11.00
Hydraulic Radius =(R ) = A / P
= 14.67 /11
m = 1.33
Computation of slope of channel bed
Using Manning's Formula = v = (
)
S1/2 = (
)
S = (
)
= (2 x 0.018)/1.33^(2/3))^2
S = 0.0009
Provide slope of 1 in = 1130
Computation of FSL at end of channel
Reduced FSL at the beginning m = FSL at start of cut & cover channel
m = 1,272.88
Reduced FSL at end m = FSL1 - (Length/Slope)
= 1272.88- (90 / 1130)
m = 1,272.80
Provision of free board
Free board (for 7 to 30 cumecs ) m = 0.90
ABSTRACT
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 14
Sl.
No. Particulars Units Calculations
1 Base width m = 4.60
2 FSD in channel m = 3.20
3 Free board of channel m = 0.90
4 Bed slope of channel - 1 in m = 1,130
5 Length of channel m = 90
6 FSL at beginning of channel m = 1,272.88
7 FSL at end of channel m = 1,272.80
Desilting Tank
Sl.
No. Particulars Units Calculations
1 Design data
Propose two tanks
a Design discharge of plant =(Qmax) = 24.45
b Design discharge per D-tank =Q cumecs = 14.67
c Particle size to be removed => Ps mm = 0.25
d Flow through velocity =uf m/sec = 0.22
e Settling velocity =us cm/sec = 2.75
f FSL in desilting tank m 1,272.80
2 Design calculation
A Design of tank
Width proposed for tank =W m = 10.00
Depth required = D m = =Q/W*uf
= 14.67 / (10 x 0.22)
m = 6.67
Moderated settling velocity =um cm/sec = us - (0.132/(D)1/2 *us
= 2.75 - ( 0.132 /( 6.67)^0.5) x 2.75
cm/sec = 2.61
m/sec = 0.026
Settling length of tank
(Flow through velocity x
Depth)/Settling velocity
m Ls = (u1 / um) *d
= ( 0.22 / 0.026) x 6.67
m Ls 56.44
Say m 56.00
By providing minimum gutter slope 1 in
25
Depth at the end of silt gutter (56/25)+ 6.67
m 8.91
Bottom RL of gutter at start of tank = FSL -depth at start
= 1272.8 - 6.67
m 1266.13
Bottom RL of gutter at end of tank = FSL -depth at end
= 1272.8 - 8.91
m 1263.89
Top RL of tank = FSL + Free board
= 1272.8 + 0.90
m 1273.70
B For Silt Flushing Pipe
1 Design data
Silt flushing discharge ( 20% of design
discharge) = Qf cumecs = 18.33 x 0.20/2
cumecs =
1.83
Velocity of water in flushing pipe (Assumed) m/sec = 2.50
2 Design calculation
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 15
Sl.
No. Particulars Units Calculations
Diameter of silt flushing pipe = D silt = Qfp x 4 / ( 3.14 x v )
= 1.83 x 4/ (3.14 x 2.5)
m 0.966
Provide dia. of pipe mm 1,000
ABSTRACT
1 Settling tank - width m = 10.00
2 Settling tank length m = 56.00
3 FSL in De-silting tank m = 1,272.80
4 Bottom RL at start of tank m = 1,266.13
5 Bottom RL of gutter at end of tank m = 1,263.89
6 Top RL of tank m = 1,273.70
7 Dia. of slit flushing pipe mm = 1,000
Power Channel-1
Sl.
No. Particulars Units Calculations
From desilting
1 Design data
a Design discharge of plant =Qmax cumecs = 24.45
b FSL at the end of power channel-2 m = 1,272.80
c Velocity limited = V m/sec = 2.00
d Rugosity coefficient = n = 0.018
e Length of power channel =L m = 745.00
2 Design calculations
Computation of bed width & FSD of channel
Design discharge in channel = (Q) cumecs = 24.45
Area required = A Sq. m = Q/V
= 24.45 / 2
Sq. m = 12.23
Provide water depth in channel m = 2.90
Therefore, width of channel m = 12.23 / 2.9
m = 4.20
Perimeter = (P) = b + 2 d
= 4.2 + (2 x2.9 )
m = 10.00
Hydraulic Radius =(R ) = A / P
= 12.23 /10
m = 1.22
Computation of slope of channel bed
Using Manning's Formula = v = (
)
S1/2 = (
)
S = (
)
= (2 x 0.018)/1.22^(2/3))^2
S = 0.0010
Provide slope of 1 in = 1010
Computation of FSL at end of channel
Reduced FSL at the beginning m = FSL at start of cut & cover channel
m = 1,272.80
Reduced FSL at end m = FSL1 - (Length/Slope)
= 1272.8- (745 / 1010)
m = 1,272.06
Provision of free board
Free board (for 7 to 30 cumecs ) m = 0.90
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 16
Sl.
No. Particulars Units Calculations
ABSTRACT
1 Base width m = 4.20
2 FSD in channel m = 2.90
3 Free board of channel m = 0.90
4 Bed slope of channel - 1 in m = 1,010
5 Length of channel m = 745
6 FSL at beginning of channel m = 1,272.80
7 FSL at end of channel m = 1,272.06
Tunnel - 2
Sl.
No. Particulars Units Calculations
1 Design data
a Design discharge of plant =Qmax cumecs = 24.45
b FSL at the start of tunnel m = 1,272.06
c Velocity limited = V m/sec = 2.00
d Rugosity coefficient = n = 0.018
e Length of tunnel =L m = 2,340.00
2 Design calculations
Computation of bed width & FSD of channel
Design discharge in channel = (Q) cumecs = 24.45
Area required = A Sq. m = Q/V
= 24.45 / 2
Sq. m = 12.23
Provide water depth in channel m = 2.90
Therefore, width of channel m = 12.23 / 2.9
m = 4.20
Perimeter = (P) = b + 2 d
= 4.2 + (2 x2.9 )
m = 10.00
Hydraulic Radius =(R ) = A / P
= 12.23 /10
m = 1.22
Computation of slope of channel bed
Using Manning's Formula = v = (
)
S1/2 = (
)
S = (
)
= (2 x 0.018)/1.22^(2/3))^2
S = 0.0010
Provide slope of 1 in = 1010
Computation of FSL at end of channel
Reduced FSL at the beginning m = FSL at start of cut & cover channel
m = 1,272.06
Reduced FSL at end m = FSL1 - (Length/Slope)
= 1272.06- (2340 / 1010)
m = 1,269.74
Provision of free board
Free board (for 7 to 30 cumecs ) m = 0.90
ABSTRACT
1 Base width m = 4.20
2 FSD in channel m = 2.90
3 Free board of channel m = 0.90
4 Bed slope of channel - 1 in m = 1,010
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 17
Sl.
No. Particulars Units Calculations
5 Length of tunnel m = 2,340
6 FSL at beginning of channel m = 1,272.06
7 FSL at end of channel m = 1,269.74
Power Channel - 2
Sl.
No. Particulars Units Calculations
1 Design data
a Design discharge of plant =Qmax cumecs = 24.45
b FSL at the end of power channel-2 m = 1,269.74
c Velocity limited = V m/sec = 2.00
d Rugosity coefficient = n
= 0.018
e Length of power channel =L m = 370.00
2 Design calculations
Computation of bed width & FSD of channel
Design discharge in channel = (Q) cumecs = 24.45
Area required = A Sq. m = Q/V
= 24.45 / 2
Sq. m = 12.23
Provide water depth in channel m = 2.90
Therefore, width of channel m = 12.23 / 2.9
m = 4.20
Perimeter = (P)
= b + 2 d
= 4.2 + (2 x2.9 )
m = 10.00
Hydraulic Radius =(R )
= A / P
= 12.23 /10
m = 1.22
Computation of slope of channel bed
Using Manning's Formula = v
= (
)
S1/2
= (
)
S
= (
)
= (2 x 0.018)/1.22^(2/3))^2
S
= 0.0010
Provide slope of 1 in
= 1010
Computation of FSL at end of channel
Reduced FSL at the beginning m = FSL at start of cut & cover channel
m = 1,269.74
Reduced FSL at end m = FSL1 - (Length/Slope)
= 1269.74- (370 / 1010)
m = 1,269.37
Provision of free board
Free board (for 7 to 30 cumecs ) m = 0.90
ABSTRACT
1 Base width m = 4.20
2 FSD in channel m = 2.90
3 Free board of channel m = 0.90
4 Bed slope of channel - 1 in m = 1,010
5 Length of channel m = 370
6 FSL at beginning of channel m = 1,269.74
7 FSL at end of channel m = 1,269.37
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 18
Forebay
Sl.
No. Particulars
Units
Calculations
A Design data
a Design discharge =Qmax cumecs Qr 24.45
b Max level in forebay = FSL m FSL1 1,269.37
c TWL max m
1,213.50
d TWL min m
1,210.91
e Storage capacity (2-3 minutes ) Minutes T 3
B Design calculations
1
Drawdown level in forebay & MDDL
Calculation
H max = MWL - TWL min = 1269.37 - 1210.91
m = 58.46
considering, Hmax = H rated m = 58.46
Minimum head considering
Head variations below rated head
10% m = 52.61
15% m = 49.69
20% m = 46.77
25% m = 43.84
30% m = 40.92
35% m = 38.00
Considering 10% below rated head
Min. Head m = 49.69
Therefore, MDDL of forebay = TWL max + H min
= 1213.5+ 49.69
m = 1,263.19
Drawdown depth =D = FSL - MDDL
= 1269.37 - 1263.19
m = 6.18
1
Storage capacity & Dimensions of forebay
tank
Volume of storage required = Vm = Qr * T *60
cum = 4,401
Area requirement for the forebay = A Sq. m = Vm / D
= 4401 / 6.18
Sq. m = 712.14
Provide length of forebay m L 40.00
Therefore,
Breadth required m B= A / L
= 712.14/40
17.80
Say
m
18.00
3 Computation of C/L of Intake opening
Area of Penstock = Pi /4 x 2.7^2
Sq. m =
5.72
Area of bellmouth Sq. m = Area of penstock / 0.6 cos (0)
(As per IS 9761) = 5.72 / 0.6 cos (0)
Sq. m =
9.53
Therefore,
Diameter of bellmouth =h = (9.53 x 4 / pi )^0.5
= 3.48
m Say 3.48
Water cushion above bellmouth = 0.6 h
(Ref-P.S.Nigam -Intake structures P-383) m = 2.09
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 19
Sl.
No. Particulars
Units
Calculations
C/L of Intake opening
=
M.D.D.L.- (water cushion + 1/2
bellmouth height)
= 1263.19 - (2.09 + 3.48/2)
m = 1,259.36
Sill level of bellmouth
=
M.D.D.L - (water cushion +
Bellmouth opening Height)
= 1263.19 - (2.09 + 3.48)
m = 1,257.62
Bottom RL of Forebay = Sill level - 1
= 1257.62 - 1
m = 1,256.62
Top RL of Forebay = FSL I fore bay + Free Board
= 1269.37 + 0.90
m = 1,270.27
ABSTRACT
1 Length of forebay m = 40.00
2 Breadth of forebay m = 18.00
6 F.S.L. at Forebay m = 1,269.37
7 MDDL m = 1,263.19
8 C/L of penstock intake opening m = 1,259.36
9 Sill level of penstock opening m = 1,257.62
10 Bottom RL of forebay m = 1,256.62
Escape channel
Sl.
No. Particulars Units Calculations
1 Design data
a Design discharge =Qmax cumecs Qr 24.45
b Max level in forebay = FSL m FSL1 1,269.37
c
Min. level in forebay (FSL-FSD in channel
behind) m 1,263.19
d Velocity limited = V m/sec = 2.00
e Rugosity coefficient = n = 0.018
f Length of channel =L m = 125.00
2 Design calculations
Computation of bed width & FSD of
channel
Design discharge in channel = (Q) cumecs = 24.45
Area required = A Sq. m = Q/V
= 24.45 / 2
Sq. m = 12.23
Provide water depth in channel m = 2.90
Therefore, width of channel m = 12.23 / 2.9
m = 4.20
Perimeter = (P) = b + 2 d
= 4.2 + (2 x2.9 )
m = 10.00
Hydraulic Radius =(R ) = A / P
= 12.23 /10
m = 1.22
Computation of slope of channel bed
Using Manning's Formula = v = (
)
S1/2 = (
)
S = (
)
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 20
Sl.
No. Particulars Units Calculations
= (2 x 0.018)/1.22^(2/3))^2
S = 0.0010
Provide slope of 1 in = 1010
Provision of free board
Free board (for 7 to 30 cumecs ) m = 0.90
Computation of Length of surplus escape
Crest of surplus escape = FSL in forebay
m = 1,269.37
Let head over the crest of spillway = m = 0.60
therefore, top of forebay = 1269.37 + 0.9
m = 1,270.27
Discharge through surplus escape = Q =
Where,
Q = Discharge through rect. channel cumecs = 24.45
C = Constant for rectangular opening = (2/3) x 0.62 x(2 x 9.81)^0.5
(ref- R.S.khurmi -textbook of hyd. P-331) = 1.83
1.83
H = Head over crest m = 0.60
L= length of escape channel
therefore,
Length of surplus escape = L =
= 24.45 / (1.83 x 0.6^(3/2))
m = 28.75
Provide length m = 29.00
ABSTRACT
1 Base width m = 4.20
2 FSD in channel m = 2.90
3 Free board of channel m = 0.90
4 Bed slope of channel - 1 in m = 1,010
5 Length of channel m = 125
6 Length of spillway m = 29.00
7 Top level of Forebay m = 1,270.27
8 Crest level of Spillway escape m = 1,269.37
Penstock
Sl.
No. Particulars Units Calculations
A Design data
a Design discharge of plant =Qmax cumecs =
24.45
b Limiting velocity in penstock = vp m/sec = 4.30
c No. of machines Nos. = 2
d FSL at forebay m = 1269.37
e Av. Tail Water Level m = 1212.21
f Length of penstock =Lp m =
166.00
g Time constant =Ct sec =
10.00
B Design calculations
1 Diameter of main penstock (Dm)
(i) Discharge through penstock Qb =
24.45
(ii) Area of penstock required =Am = Qmax / vp
= (24.45 /4.3)
Sq. m = 5.69
Therefore,
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 21
Sl.
No. Particulars Units Calculations
(iii) Diameter of penstock = Dm m = (Area x 4 / 3.14)^0.5
= (5.69 x 4 )/ 3.14)^0.5
m = 2.69
Therefore,
Provide diameter of penstock m = 2.70
2 Diameter of Branch penstock (Db)
(i) Discharge through each penstock=Qb = 12.23
(ii) Area of penstock required =Ab = Qb / vp
Sq. m = (12.225 /4.3)
m = 2.84
Therefore,
(iii) Diameter of branch penstock =Db = (Area x 4 / 3.14)^0.5
= (2.84 x 4 )/ 3.14)^0.5
m = 1.90
Therefore,
Provide diameter of penstock m 1.90
3
Calculations for Pressure Rise due to
Water Hammer
Method I :
TNEB Power Engineering handbook page
No.1.16
Penstock Diameter m = 2.70
Area of penstock provided Sq. m = (3.14 / 4) x 2.7^2
5.73
Therefore, Velocity = Q / A provided
= ( 24.45 )/ 5.73
= 4.27
Pressure rise due to closing of guide
Vanes. = H =
Where,
Pressure rise = H
Length of penstock =L m 180
Gravitational Acceleration =g m/sec2 9.81
Gide vane closing time = T sec 4.5
Therefore, H = = (2 x 180 x 4.27)/( 9.81 x 4.5)
m = 34.82
Method II :
(Ref : Environmental Engineering Vol. II,
by Santosh Kumar Garg page No. 268)
P h max = = 14.6 V / ( 1+k d/t)0.5
Where,
k = Ew/Epipe - ( for steel pipe ) = 0.01
d = Diameter of pipe m = 2.70
t = Thickness of pipe( from 3 below) m = 0.010
V= Velocity of water in pipe m/sec = 4.27
Ph max =
14.6 x 4.27 / ( 1+ 0.01 x 2.7
/0.01)^0.5
kg/cm2 = 32.41
When actual closure time T, is less than
Critical closure time Tc
P = P h max * (Tc / T)
Where,
Tc = 2 S / Up
Where,
S = Distance of valve from reservoir m = 180
UP= (Ew/e)0.5 x 1/( 1+k d/t)0.5
Where,
(Ew/e)0.5 m/sec = 1433
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 22
Sl.
No. Particulars Units Calculations
UP = = 1433 x 1 /( 1 +0.01 x 2.7 x 0.01)^0.5
= 744.98
Therefore,
Critical closure time Tc = = 2 S / Up
= 2 x 180 / 744.98
= 0.48
Therefore,
P = = P h max * (Tc / T)
= 32.41 x (0.48 / 4.5)
kg/cm2 = 3.46
Therefore,
H = P x 10 = 3.46 x 10
m = 34.60
Therefore,
Maximum pressure rise m = 19.84
4 Steel liner thickness
A Method-I
CWC Penstock Mannual Page No.23 / IS
11639:1995(Part 2) /Page 03
Thickness = t =
Static head = H1 = FRL - Min. TWL
1269.37 - 1212.205
m = 57.17
Rise in Head due to Water hammer m = 19.84
Total Head = H = H1 + H2
m = 77.01
Internal Pressure inclu. Dynamic m = 7.700
pressure =P
Internal radius of penstock = R cm 135
Hoop Tensile stress in steel =S kg/cm2 1192
Thickness of steel liner shell = t = ( 7.7 x 135) /1192
cm = 0.872
mm = 8.72
Add corrosion allowance(Ref:IS mm = 0.00
11639:1995 Part2/p 05)
Concrete lined = t mm = 8.72
B Method-II
Thickness of pensock considering joint
efficiency
t =
Static head = H1 = FRL - Min. TWL
= 1269.37 - 1212.205
m = 57.17
Rise in head due to water hammer =H2 m = 19.84
Total Head = H m = H1 + H2
57.17 + 19.843
m 77.01
Internal Pressure incl. dynamic =P kg/cm2 = 7.700
pressure
Internal diameter of penstock =D cm = 270.00
Safe working stress in steel =f kg/cm2 = 1192
Joint efficiency =n % = 0.90
Thickness of steel liner shell =t t = ( 7.7 x 270) / (2 x1192 x 0.9)
cm 0.969
mm 9.69
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 23
Sl.
No. Particulars Units Calculations
Add corrosion allowance(Ref: IS
11639:1995 Part2/p 05) Concrete lined mm mm 9.69
C Method-II
Minimum Handling thickness ( Ref :
I.S.4880 (part VII) : 1975 / P. 6
(I) Thickness of liner = t cm = ( Dia. of penstock + 50) /400
(2.7 x 100 + 50) /400
t cm = 0.800
t mm = 8.00
Therefore,
The Maximum of above criteria,
The thickness of Penstock works mm 9.69
Therefore required Thickness mm 10.00
Thickness provided mm 10.00
ABSTRACT
1 Diameter of main penstock mm = 2,700
2 Diameter of branch penstock mm = 1,900
3 Provide steel liner thickness-start mm = 8
4 Provide steel liner thickness-end mm = 10
Tail Race Channel
Sl.
No. Particulars Units Calculations
From power house to river Sagana
1 Design data
a Design discharge of plant =Qmax cumecs = 24.45
b CBL of channel at beginning m = 1,210.00
c Velocity limited = V m/sec = 1.50
d Rugosity coefficient =n = 0.018
e Length of Rect. channel =L m = 10.00
2 Design calculations
Computation of bed width & FSD of channel
Area required =A = Q/V
= 24.45 / 1.5
Sq. m = 16.30
Provide water depth in channel =d m = 3.50
Area =A = b x d
16.30 = b x 3.5
16.30 = b x 3.5
Therefore, width ( b ) Sq. m = 4.65
Perimeter =P = b + 2d
= 4.65 + 2 x3.5
= 1.00
m = 11.65
Hydraulic Radius = R = A / P
= 16.3 / 11.65
m = 1.4
Computation of slope of channel bed
Using Manning's Formula = v = (
)
S1/2 = (
)
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 24
Sl.
No. Particulars Units Calculations
S = (
)
Channel bed slope =S = (
)
= (1.5 x 0.018)/1.4^(2/3))^2
= 0.0005
Provide slope of 1 in m = 2150
Computation of TWL Maximum
CBL of channel at start m = 1,210.00
Add FSD for designed discharge m = 3.50
Therefore,
TWL Max = 1210 + 3.5
m = 1,213.50
Computation of TWL (min)
b m = 4.65
A = Q/V
= 6.378 / 1.5
Sq. m = 4.252
A = (b x d)
4.252 = (4.65 x d )
d m = 4.252 / 4.65
d m = 0.91
TWL min = CBL + d
= 1210 + 0.91
m = 1,210.91
ABSTRACT
1 Base width of channel m = 4.65
2 FSD in channel m = 3.50
3 Bed slope of channel - 1 in m = 2,150
4 Length of channel m = 10
5 TWL Max m = 1,213.50
6 TWL min m = 1,210.91
Net Head
Sl.
No. Particulars Units Calculations
A Design Data
a FSL at forebay m = 1,269.37
b MDDL in forebay m = 1,263.19
c Tail Water Level - Min m = 1,210.91
d Tail Water Level - Max m = 1,213.50
e Max. head variation = 100%
f Min. Head variation = 90%
g Design discharge = Qmax cumecs = 24.45
h Diameter of penstock =Dm m = 2.70
i Length of penstock = Lmp m = 180.00
j No. of bends Nos. = 5
k No of reduces Nos. = 2
l No. of valves Nos. = 2
m No of Y-piece Nos. = 1
n Gravity constant =g m/sec2 = 9.81
o Co-efficient for frictional loss =f = 0.012
p coefficient for bend loss =P = 0.060
q Entrance velocity =Ve m/sec = 0.750
r Frictional velocity =Vf m/sec = 4.270
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 25
Sl.
No. Particulars Units Calculations
s Velocity in bends =Vb m/sec = 4.270
t Velocity in reducers =Vr m/sec = 4.270
u Velocity in Valves Vv m/sec = 4.270
v Velocity in y piece =Vy m/sec = 4.270
B Design Calculations
(Reference- Manual on planning & design of
small HEP, page-72
(i) Entrance loss = hfe =
= 0.1 x 0.75^2) / (2 x 9.81)
m = 0.003
(ii) Friction loss = hffr =
=
( 0.012 x 180 x 4.27^2) / (2 x 9.81 x
2.7)
m = 0.74
(iii) No of bends = N1 =
5
Bend losses = hfb =
= ( 5 x 0.06 x 4.27^2) / (2 x 9.81)
m = 0.279
(iv) No of reduces = N2 = 2
Loss in reducer pipe =hfr m =
= ( 2 x 0.25 x 4.27^2) / (2 x 9.81)
m = 0.465
(v) No. of valves =N3 = 2
Loss in valve = hfv =
= ( 2 x 0.25 x 4.27^2) / (2 x 9.81)
m = 0.465
(vi) No of Y-piece =N4 = 1
Loss in Y-Piece = hfy = (
)
= ( 1 x 0.8 x 4.27^2) / (2 x 9.81)
m = 0.743
Total Losses (say ) =hfp = hffr+hfe+hfb+hfr+hfv+hfm
m = 2.70
Head Calculations
(i) Max. Head = Gross head =Hmax = FSL in forebay - TWL min
= 1269.37 - 1210.91
m = 58.46
(ii) Rated Head = Hrated = Gross head / Max. Head range
= 58.46 / 1
m = 58.46
(iii) Min. Head = Hmin = MDDL in forebay - TWL max
= 1263.19 - 1213.5
m = 49.69
(iv) Min. Head (based on turbine parameters) = Rated Head x min head variation
= 58.46 x 0.9
m = 52.61
Min. Head -lower of above two m = 49.69
(v) Net Max. Head =Hmax(net) = Max. Head - Head loss
= 58.46 - 2.7
m = 55.76
(vi) Net Rated Head =Hrated(net) = Rated Head - Head loss
= 58.46 - 2.7
m = 55.76
(vii) Net Min. Head =Hmin(net) = Min. Head - Head loss
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 26
Sl.
No. Particulars Units Calculations
= 49.69 - 2.7
m = 46.99
ABSTRACT
1 FSL at forebay m = 1269.37
2 Tail Water Level - Min m = 1210.91
3 Tail Water Level - Max m = 1213.50
4 Max. Head = Gross head m = 58.46
5 Rated Head m = 58.46
6 Min. Head m = 49.69
7 Max. Net Head m = 55.76
8 Rated Net Head m = 55.76
9 Min. Net Head m = 46.99
10 Total losses m = 2.70
Design Discharge
Sl.
No. Particulars Units Calculations
A Design Data
a Project Capacity = P KW = 10000
b Number of units = N Nos. = 2
c Max. Head = Hmax m = 58.46
d Rated head = Hrated = 58.46
e Min Head =Hmin m = 49.69
f Max. net Head =Hmax(net) m = 55.76
g Rated net head =Hrated(net) = 55.76
h Min net Head =Hmin(net) m = 46.99
i Max. Overload = 115%
j Min. load (as specified by Manufacturer) = 60%
k Turbine efficiency =nt = 91.00%
l Generator efficiency =ng = 96.00%
m Gear box efficiency =ngb = 98.50%
B Design calculations
I) Power Plant capacity =P KW =
Where,
P = Power in kW
Q= Rated discharge
H= Rated head
η = Combined efficiency of TG unit = ηt x ηg x ηgb
= 0.91 x 0.96 x 0.985
= 86.00%
ii) Rated discharge = Qr = P / H x 9.81 x η
= (10000 / (55.76x 9.81 x 0.86)
Cumecs 21.26
iii) Maximum Discharge = Design discharge =
Rated discharge x max. overload
capacity
= 21.26 x 1.15
Cumecs = 24.45
iv) Min. discharge per unit =Qmin =
(rated discharge/machine) x min.
load
= (21.26 / 2) x 0.6
Cumecs = 6.38
ABSTRACT
1 Design discharge -plant Cumecs = 24.45
2 Rated discharge Cumecs = 21.26
3 Min. discharge per unit Cumecs = 6.38
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 27
Turbine
Sr.
No. Particulars Details
A Design data
1 Rated Discharge: 10.63 cumecs
2 Net Head at Rated Discharge: 55.76 m
3 Gross Head: 58.46 m
4 Site Elevation 1,210.00 m
5 Setting of tail water level (1.00) m
6 Efficiency Priority: 10
7 System Frequency: 50 Hz
8 Minimum Net Head: 46.99 m
9 Maximum Net Head: 55.76 m
B Turbine selection
1 Arrangement:
Horizontal with
runner overhung
on generator shaft
2 Type of turbine Francis
3 Intake Type:
spiral case with
inlet below unit
axis
4 Runner pitch Diameter: 1288 mm
5 Unit Speed: 428 rpm
6 Multiplier Efficiency Modifier 1
7 Flow Squared Efficiency Modifier 0
8
Specific Speed at Rated Net Head (
Turbine )
At 100% Turbine Output: 206.8
At peak Efficiency Condition: 206.8
C Turbine performance data
At Rated Net Head of: 55.80 m
% of Rated Discharge Output (kW) Efficiency (%) m3/s
** 115 6203 91.1 12.4
100 5403 92.9 10.6
* 100 5403 92.9 10.6
75 3869 88.7 8.0
50 2166 74.5 5.3
25 687 47.3 2.7
+ 66.6 3299 85.2 7.1
** - Overcapacity * - Best
Efficiency Condition at Rated Net
Head
+ Peak draft surging condition
D Sigma Allowable
Sigma Allowable Max. Output (kW) Efficiency (%) Discharge (m3/s)
1 At Maximum Net Head of: 55.8 m
6203 91.1 12.4
2 At Minimum Net Head of: 47 m
4839 89.7 11.7
E Summary of turbine selection
1
Maximum Runaway Speed (at
Max. Net Head): 774 rpm
2
Turbine discharge at runaway
speed 7.2 Cumecs
3
Maximum Hydraulic Thrust (at
Max. Net Head): 35961 kg
4 Approximate runner weight 1871 kg
5 Velocity at draft tube exit 2.3 m/sec
Detailed Project Report Sagana III HEP Chapter 8 - Civil Engineering Structures
Chapter 8 - 28
Sr.
No. Particulars Details
Intake type
spiral case with
inlet below unit
axis
1 Inlet Diameter: 1524 mm
2 Inlet offset 1734 mm
Draft tube Elbow
1 Centre line to invert 2576 mm
2 Shaft axis to exit length 6955 mm
3 Exit diameter 2447 mm
4 Exit to bottom floor 1295 mm
Shafting Arrangement
Horizontal with
runner on turbine
shaft
1 Generator shaft extension 801 mm
2 Turbine shaft diameter 279 mm
Miscellaneous
Horizontal with
runner on turbine
shaft
1 Wicket gate height 353 mm
2 Wicket gate Circle diameter 1506 mm
Notes
All information listed above is
typical only.
Detailed characteristics will vary
based on turbine manufacturer's
actual designs.
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 1
Chapter 9-Electro-mechanical works
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 2
9. Introduction
Sagana-III Small Hydro project is a run of the river type scheme on Sagana River in Nyeri
district (Central Province) of Kenya. It consists of 2 (two) units (2 x 5 MW), operating under a
gross head of 58.46 m and rated discharge of 21.26 cumecs. The two generating units with other
associated equipment will be accommodated in a surface powerhouse. The generation voltage is
proposed to be 11 kV. This voltage will be stepped up to 132 kV voltage level by generator step-
up transformers which are located at the upstream side of the Power House. It is proposed to use
two (2) number three-phase step-up generator transformers rated (8 MVA x 2), 11 kV/132 kV.
On the LV side, transformers will be connected to the generators by means of 11 kV isolated
phase bus duct. On the HV side, transformers will be connected to 132 kV outdoor conventional
type switchyard by 132 kV overhead transmission lines (link lines).
The power generated at Sagana-III HEP will be evacuated through 132 kV Outdoor Switch Yard
through double circuit to 132 kV transmission line to Sagana town.
9.1 Drawings
The following drawings may be referred
Sl. No. Item Description Drawing No.
1 Power House Sagana-III-011
2 Power House Sec. Sagana-III-012
3 Single Line diagram Sagana-III-026
4 Switch Yard Sgaana-III-027
9.2 Turbine
As discussed in previous chapter on Power Potential studies, the optimum output of the
generating plant has been decided as (2 x 5000 kW). This is in view of the effective utilization of
the discharges and to ensure reliability of generation and flexibility in operation.
9.3 Main Electro-Mechanical Components
9.3.1 Main Inlet Valve
Two nos. main inlet valve of 1524 mm diameter butterfly valve shall be provided for controlling
the flow while discharging the water into the turbine and also required to be closed for
maintenance of the units. The M.I.V. is provided with a closing weight and hydraulic cylinder to
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 3
act under an emergency as a reliable shut-off device, even when no other external power
dependent activating source is available. The torque for closing is derived from the weight from
the closing hydraulic moment acting on the disc and also from the appropriate eccentric pivoting
of the valve disc under an emergency situation; it shall be complete with pipes, hydraulic
systems, embedded parts etc.
9.3.2 Hydraulic Turbines
The scope of supply and specifications for the equipment under the same shall be generally in
accordance with the tender specifications, taking into account amendments and clarifications
thereof. Few changes in type of construction or materials of construction in the offered
equipment are either due to the advancement in technology over period of time or due to the fact
that type of construction varies slightly from manufacturer to manufacturer. The offered
materials of construction are of the equivalent or better grade than specified in tender. Below is a
typical site photograph of assembly of the complete Turbine-generator system and indicating
major assemblies for reference.
9.3.3 Choice of type of Turbine
As per the power potential studies carried out in previous chapter (two) number turbines each of
(5000 KW) capacity at 100% of rated discharge which is 21.26 cumecs for 10 MW with
efficiency of 92.5% has been suggested. The selection of type of turbine for a Hydro Power
Project is a function of its specific speed. Following are the design parameters for Sagana-III
Small Hydro Project.
FSL at Forebay = EL 1269.37 m
Minimum tail water level = EL 1210.91 m
Gross Head = 58.46 m
Total Losses = 2.70 m
Hence, Rated Net head = 55.76 m
The specific speed of turbine can be calculated from the following formula
Specific Speed ( )
N = Rotational speed of turbine in rpm
= 428
H = Rated net head = 55.76 m
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 4
P = Rated turbine output in metric Horse Power
= 5403 / 0.736 (Since, 1 Metric HP = 0.736 KW)
= 7341.032 HP (~7341 HP)
( )
The range of specific speeds for various types of turbines is given below:
Sl. No. Type of runner Ns
1 Fixed Blade Propeller 300-1000
2 Adjustable Blade Kaplan Turbine 300-1000
3 Reaction- Francis 65-445
Impulse Turbine
4 Pelton turbine per jet 16-20 per jet for multiple jet
5 Cross Flow 12-80
This definitely indicates a choice of Francis turbine. For the given head condition also, Francis
is recommended turbine which shall be capable of running at 115 % of rated capacity.
Turbine shall be horizontal shaft type suitable for coupling directly to horizontal shaft
synchronous generators of 5000 KW (0.85 power factor assumed) rating. The turbine shall be
capable of giving outputs higher then rated outputs to match the over load capability of
generator. Turbine shall be designed to give a rated output corresponding to 5000 KW at bus bar
at a gross head of 58.46 m. However, the final decision in this regard shall be taken after detailed
discussions with manufacturer of the machines for the given set of conditions.
9.3.4 Turbine Description
9.3.4.1 Spiral Casing with Stay Ring and Generator Side Cover
The spiral casing shall be fabricated from several spiral plate sections to suit transportation
requirements, which shall be adapted to the side plates of the stay ring and welded in place. On
the upstream side, one welded-on flange with a distance piece provides the connection between
spiral inlets to the turbine inlet butterfly valve (through telescopic type of dismantling joint). The
stay ring shall have adequate number of stay vanes of correct profile and inlet and outlet angles.
The turbine spiral casing is mounted on the turbine floor by supporting feet and foundation
plates. The spiral case shall be equipped with tapings for Winter Kennedy Method (if applicable)
and drainage of spiral case. The required anchoring material is included in our scope of supply.
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 5
The welds in the spiral casing and stay ring shall be inspected by dye-penetration test/ ultrasonic
test. Spiral casing shall be subjected to a hydrostatic pressure test as per relevant standard. For
the purpose of the pressure test, the stay ring opening shall be closed by a separate pressure test
ring. The embedding of the spiral casing in concrete shall be carried out with the casing under
suitable pressure.
9.3.4.2 Draft tube
Draft tube shall consist of:
Cone
Elbow sections
Anchoring material
Conical liner
“Draft tube cone & bend” is flanged on one side to “draft tube side head cover” and on the other
side to the draft tube liner flange.
The flange connections considerably facilitate and simplify the assembly and dismantling
operations consisting of:
9.3.4.3 Generator-side head cover
The solid plate together with the generator-side plate of the stay ring can be made either as a
single component or of bolted construction. It accommodates the guide vane drive side bearing,
labyrinth rings and the shaft sealing casing.
9.3.4.4 Draft tube side head cover
The single-part, solid plate is attached to the stay ring and accommodates the suction side guide
vane bearings and the labyrinth rings.
9.3.4.5 Stationary labyrinths
The single-stage labyrinth rings are of the non-split type, and frictionally connected to the head
cover. The chosen material guarantees a large hardness difference between the stationary and
revolving labyrinth rings.
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 6
9.3.4.5 Guide vanes
The guide vanes with its trunion are castings of 13% Cr – 4% Ni stainless steel. All wicket gate
bearings, both radially and axially, are made to be maintenance-free. An `O’ ring seal does
sealing against the water flow channel.
9.3.4.6 Levers
The guide vane levers designed as links are clamped to the guide vane stems and locked in
position during assembly. A disc bolted to the stem prevents the lever from shifting axially. The
frictional connection is a safety clutch and prevents possible damage to the guide vanes in case
foreign bodies get stuck between the gates. All guide vane levers are connected by the bolts to
the vane operating ring.
9.3.4.7 Gate operating ring
The gate operating ring is connected by bolts, carried in maintenance-free bushes thereon with
the individual wicket gate levers and also supported.
9.3.4.8 Servomotor
The wicket gate servomotor is of double-acting type, operated by oil pressure and mounted on
the generator-side head cover. The piston rod is directly connected with the gate-operating ring
and the levers control the wicket gate position. The servomotor can be supplied with an integral
feedback transmitter.
9.3.4.9 Francis Runner
The Francis runner shall be integral cast of 13% Cr and 4% Ni alloy stainless steel (ASTM A-
743 Gr. CA-6NM) and shall be designed to provide the best hydraulic profile so that it gives
maximum efficiency with minimum of cavitation. The runner cone shall be stainless steel casting
/ weld plate stainless steel fabrication. All surfaces on the runner exposed to the flow of water
shall be finished smooth by grinding or other means so as to be free from hollows, depression,
cracks and projection. The water passage on the blades, crown & skirt shall be finished to correct
profiles for the prototype based on homology with the successful turbine model. The runners
shall be balanced statically at the works before dispatch. A friction-type flange coupling
guarantees a perfect interchangeability of the runner with no need for additional machining or
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 7
adjustment. Hydraulically pre-tensioned bolts provide the necessary contact pressure. It is
understood that the special pretension-equipment will form part of the supply.
9.3.4.10 Shaft Sealing Arrangement
A labyrinth seal prevents the operating water to escape from between the shaft and the generator
side head cover. The small leakage flow cools the labyrinth. The leakage flow is radially
splashed off into the seal housing by a splash ring and flows off naturally through an adequately
dimensioned pipe. Admission of sealing water is not necessary.
9.3.4.11 Turbine Control & Governing System
The digital microprocessor based governor developed for double regulated turbines will be
installed in the Unit Control Board. The governor system will be complete with feedback
sensors, pressure oil pumping unit, piping, valves, instrumentation as well as all accessories and
equipment necessary for the operation. The governing system will consist of the following main
parts:
1. Digital microprocessor based governor (one no. for each unit) located in Unit Control
Board.
2. Speed measurement devices.
3. Feedback measurement devices.
4. Governor hydraulic oil supply unit including oil tank with level indicator, temperature
switch and breather.
5. Accumulator of adequate capacity for one closure with charging and gauging equipment.
6. One normal running AC motor driven pump
7. One standby electric AC motor driven pump
Following hydraulic control elements are also provided as required during detailed engineering:
1. Valve for wicket gates control.
2. Pressure relief valve.
3. Pressure gauges.
4. Pressure switches.
5. Pressure filter.
6. Emergency valves
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 8
7. All interconnecting piping between the governor pressure oil pumping unit and
servomotor.
9.3.5 Mechanical Auxiliaries
9.3.5.1 Cooling Water
A pumping system would be provided to supply adequate quantity of water from the tail race for
cooling of the turbine and generator bearings, generator air coolers and selected plant services.
9.3.5.2 Fire Protection System
Water for firefighting would be taken from elevated reservoir providing both reliable operation
and ample capacity to fight fire in the power house. A back up water supply to this reservoir
would also be provided.
9.3.5.3 Material Handling in the Power House
In order to expedite the completion of various construction activities of the power house, one
EOT of 25/5 tones capacity would be installed in the power house. This crane shall primarily be
used for erection, maintenance and repair of generating units.
9.3.5.4 Compressed Air System
A compressed air plant would be installed to meet the requirements of the governor oil system
and the oil pressure system spherical valves at 120 bar pressure.
9.3.6 Electrical Equipment, Control and Protection Equipment
9.3.6.1 Generator
To convert mechanical energy achieved through turbine to electrical energy, generators shall be
provided. Generator should be able to supply 3 phase, 50 Hertz A.C. at 11 KV level. Generator
shall be synchronous, brushless type having 0.85 power factor (lag). The rated output of
generator shall be (5000kW) and it shall be horizontally and directly coupled to the turbines.
For this reason, speed of generator has been matched with the speed of the turbine. The above
capacity of generator ensures 115% load output at 0.85 p.f.
The generator manufacturer shall coordinate with the turbine manufacturer to match the speed,
Runway speed, moment of inertia, overloads capacity and coupling arrangements etc.
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 9
9.3.6.2 Synchronous Versus Induction Generator
For small capacity projects, line excited induction generators can be preferred over synchronous
generators because of their low initial cost, ease of operation and maintenance simplicity. The
induction generator uses excitation power supplied from an external source, which is normally
the grid. However, in case of grid failure, black start of machines will be difficult. Since
Sagana-III Small Hydro project is of 10 MW, dependability on grid could result in loss of
power due to standstill generator. Hence, synchronous generators are proposed with the
following protections:
Stator - phase to earth faults
Stator - phase to phase faults
Over load
Single phasing
High/low voltage
Loss of load and over speeding
Reverse power flow
Poor power factor
Stator overheating
Rotor overheating
Bearing overheating
The electromechanical equipment manufacturer has to co-ordinate with the control panel
manufacturer to provide necessary protections.
9.3.6.3 Stator Frame
The stator frame is made of Welded Steel Construction and has adequate thickness to prevent
distortion under operation. The frame is robust and rugged, designed to withstand bending
stresses and deflections due to its self-weight and weight of the complete core to be supported
by it. The design takes care of safe transmission load of all types and minimizes vibration and
noise level, Stator bore is circular to ensure uniform air gap between the stator and rotor,
thereby minimizing the unbalance magnetic pull. The Frame is rugged and strong to withstand
stresses during normal operation and extreme stresses due to short circuits.
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 10
9.3.6.4 Stator Core
The stator core is built-up of thin, high quality, low loss non oriented grains, cold rolled Silicon
steel Laminations. Each punching is carefully deburred and laminations are insulated on both
sides with high quality insulating varnish to minimize eddy current losses. Ventilation ducts are
provided at intervals along the stator core, being formed by means of steel spacing bars securely
welded to adjacent punching. The laminations are securely held in place by clamping flanges at
each end. The clamping flanges are made up of mild steel.
9.3.6.5 Stator Winding
The stator winding has class “F” insulation system. The stator winding is of multi-turn type,
insulated throughout with epoxy resin, mica paper tape and glass tape insulation system. Each
coil is made up of number of strands of glass braided copper of electrolytic quality, and of
rectangular cross section, to minimize eddy current loses. The coils are provided with class “F”
epoxy resin, mica paper tape and glass tape insulation. The coils are treated to eliminate void to
ensure high factor of safety against breakdown. An anti-corona shield consisting of a butt layer
of asbestos tape and a semi conducting graphite tape / paint is applied to the straight portion of
each bar. The overhang portions of the winding is braced together with packing blocks and
securely laced to support rings made of molded synthetic resins bonded fabric carried on
brackets adjacent to the stator core end plate. Sufficient gap is provided in the top and bottom
coils for good ventilation and to avoid hot spots. The coils are held in place in open type slots by
wedges of non-shrinking material of class F Epoxy glass laminates.
The whole stator is Vacuum Pressure Impregnated (VPI). After the impregnation and curing
process, the whole unit forms a rigidly supported fully consolidated, void free winding. The resin
fills all the voids in the stator winding and results in better heat transfer from conductor to stator
core.
9.3.6.6 Terminal Arrangement
The three main leads and three neutral leads of the generator windings are brought out of the
stator frame, in two separate Terminal Boxes. The Phase and Neutral end of the windings are
brought out with suitable insulating enclosure where they pass through the generator housing.
The main and neutral leads are provided with terminals suitable for connection with XLPE
cables.
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 11
9.3.6.7 Cooling System
The generator is natural air cooled, rotor radial fan / axial fans is / are designed to give a smooth
and quiet flow of air, Air is drawn from one / both End and Discharged at the other end / top of
the machine, combined action of rotor poles and fans are sufficient to extract the heat generated
in the generator
9.3.6.8 Temperature Detectors
Resistance type temperature detectors of simplex / duplex type are arranged symmetrically in the
stator winding to indicate the temperature obtained during operation. An Auxiliary Terminal box
having suitable terminal blocks are mounted on the generator frame to terminate the resistor
element connections. The temperature detectors leads are kept flexible to facilitate disconnecting
them without breakage.
9.3.6.9 Rotor Core
The Rotor Core is made up Rotor Stampings skip notched to form cylindrical poles, directly
stacked on to the rotor shaft. Ventilation ducts are provided at intervals along the rotor core,
being formed by means of steel spacing bars securely welded to adjacent punching. The rotor is
designed to safely withstand all mechanical stresses imposed by the maximum runaway speed.
The rotor core clamp is securely shrink fitted on main shaft taking care of requirements both at
normal operating speed and at maximum over speed conditions. The dynamic balancing of the
complete rotor is carried out at plant to keep values of rotor vibrations within allowable limits.
9.3.6.10 Shaft
The generator shaft is made of a high quality medium carbon steel, properly heat treated and
accurately machined all over and polished at the bearing surfaces and at all accessible points for
alignment checks. The shaft will have ample strength and stiffness at all speeds to resist vibration
or twisting on short circuits. The entire shaft is properly tested to ensure that it is free from
cracks, blowholes, slag formation or any other defects. A complete set of test reports covering
metallurgical strength, & ultrasonic tests performed on each shaft will be furnished.
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 12
9.3.6.11 Cylindrical Poles with Field Windings
The cylindrical poles are provided with adequate damper windings to improve stability under
fault conditions, to reduce voltage distortions under conditions of single phase to ground fault.
9.3.6.12 Field Winding
The field winding is Multi-layer type, insulated with class “F” insulation and consists of copper
strips formed into concentric winding. All pole winding overhangs & connections between
adjacent field coils are made mechanically strong and firmly secured to the rotor by Res-I-glass
banding. The whole Rotor winding is Roll Dip Impregnated with resin & cured. The field poles
are provided with adequate damper winding of the low resistance type to improve stability under
single-phase fault conditions. The damper winding bars are of circular copper section embedded
in pole faces. The ends of damper bars are short circuited together by copper stampings.
9.3.6.13 Balancing
All rotating parts of the generator unit shall be well balanced dynamically so as to run perfectly
true, smoothly and within vibration limits specified and provision is made for readily and
effectively compensating any out of balance that may occur upon erection at site or
subsequently.
9.3.6.14 Bearings
The generator is provided thrust / guide bearing, on DE side and guide bearing on NDE side. The
bearings are forced oil lubricated White metal lined journal type pedestal / end shield mounted
Sleeve bearings. Bearings are designed to take the required axial / radial load. The NDE bearing
is insulated to prevent any harmful circulating current from passing through the bearings
surfaces.
9.3.6.15 Brakes
Generator will be provided with Hydraulic operated brakes of sufficient capacity to bring
rotating parts of generator and turbine to stop from 20 % of rated speed.
9.3.6.16 Brushless Excitation System
The Brushless Excitation System consists of a three phase AC Exciter having armature winding
on rotor & field winding on stator and a full wave Rotating Rectifier Bridge, mounted on same
exciter rotor / shaft. Three phase AC voltage from exciter armature is fed to the Rotating
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 13
Rectifier Bridge & the DC voltage output of the rectifier bridge is directly fed to main field
Winding of the generator, mounted on the same shaft. Main Field winding in turn generates
three phase voltage in main generator armature winding, which is housed in main stator
9.3.6.17 Governor
The Governor shall be PLC based with electronic speed transmitters, feedback transmitters,
frequency adoption transmitters etc. The design of governor should be quite compact and is
suitable for operation of the unit from one place only. This arrangement requires only one
operator in the power station, who can start synchronize and load the unit from one place only by
controlling various controls provided on the governor panel.
The governor receives signal from a toothed disc mounted on the main shaft and amplifies it and
feeds it to servo-mechanism, which in turn controls the guide vane opening-closing stroke.
Digital Electronic governor with Oil Pressure Unit (OPU) is proposed to be housed in one of the
corners of the power house. This system will serve the purpose of sequential control of the unit
and the status indication for peripheral mechanical devices.
Indication
Control
All the indications such as butterfly valve On/Off status, breaker on/off status etc. will be
indicated on the unit control board incorporated in the Electronic Governor. 220 Volt D.C. lamps
of different color codes will be used for this purpose.
9.3.6.18 Controls provided on Governor
Speed control for grid frequency adaptation.
Speed control for isolated load operation.
Droop setting points for permanent droop and temporary droop
Basic control
Over speed Protection
With this arrangement the turbine shall operate smoothly and efficiently under any operating
conditions.
Turbine shall be equipped with suitable PLC based electronic type of governor. The PLC should
monitor and control following items
1. Forebay level
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 14
2. Plant power output
3. Plant rated circuit breakers
4. Reactive power control
The governor shall be of proven design capable of maintain control of speed under all conditions
of heads and loads. Such a governing system shall be complete with actuator unit comprising
speed responsive element, restoring mechanism having adjustable temporary and permanent
droop setting, load limiting device, speed control, oil pressure units etc.
9.3.6.19 Metering System
Power generated shall be metered at generator terminals through metering C.T. and P.T. The
power transferred to 132 kV feeders shall also be metered through CTs and PTs. The metering
instruments shall be provided on relevant panels. The digital multifunctional meters shall be
provided on each generator control panel suitable for indicating following parameters
continuously rolling with selection facility.
9.3.6.20 Protection
The following protections will be provided by using integrated numerical protection relays for
generator, generator transformer and feeders.
a) Generator Electrical Protections
1) Generator Differential Protection
2) Negative Phase Sequence Protection
3) Generator Reverse Power Protection
4) Voltage Restrained Over Current Protection
5) Stator Earth Fault Protection
6) Loss of Excitation Protection
7) Over Speed (Electrical) Protection
8) Rotor Earth Fault Protection
9) Over Voltage Protection
10) Fuse Failure Protection
11) Under Voltage Protection
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 15
Master tripping relays for controlled action shutdown, immediate action shutdown, critical
shutdown, emergency shutdown etc. shall be used separately in the system.
b) Mechanical Protections
1) RTQ (PT-100) in stator winding/core and in bearing for indication, alarm,
recording and shutdown of the unit.
2) Governor oil pressure low.
3) Over speed mechanical for normal and emergency shutdown.
c) Generator Transformer
1) Overall differential protection
2) Over current and earth fault protection with high Inst. Element
3) Stand by earth fault protection
4) T/F Winding Temperature High Alarm/Trip.
5) T/F Oil Temperature High Alarm/Trip.
6) Buchholtz relay - Alarm/Trip.
d) 132kV Line Protection
1) Digital over current and earth fault relay with high set unit.
2) Under voltage
3) Over / Under frequency
e) Station Aux. Transformer Protection
1) Fuse set on 11kV side
2) Digital over current and earth fault relay with high set unit on L.T. side.
9.3.6.21 D.C. Equipment
Float and boost type 220 Volt, 200 AH battery charger and tabular battery will be provided for
feeding power to indication lamps, protection relay coils, initial impulse to the self-excitation
system by means of field flashing and to operate few emergency lights.
9.3.7 Auxiliary Power Supply
1 Nos. 3 Phase, 11KV/415V, Dyn11, 315 KVA step down Unit Auxiliary transformer will be
used for feeding the station lighting and heating load for power house, staff colony, illumination
for approach road and switch yard.
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 16
Emergency lights on important places will be operated by D.C. battery provided in the power
house. 100 KVA diesel generator set will also be provided for illumination in power house, staff
colony, street lights & switch yard during shut down of machines.
9.3.8 Cables and Terminations
XLPE type H.T. cables/ Bus Ducts shall be used connecting generator to generation
transformer, neutral grounding end.
9.3.9 Switchyard
A comparatively flat terrace is available near power house where step-up transformer will be
kept on plinth. Earth mat will be laid underground. Proper fuse sets, switches etc. will be
mounted on M.S. poles. The total area will be strongly fenced as per Indian electrical safety
rules. High voltage cable will be laid underground in cable trenches. The power cable will
connect low voltage side of the step-up transformers. 2 Nos. 11KV/132KV, 8 MVA, YNd11
step up transformer is used to carry the power generated to the bus duct. The transformer would
be ONAN type in accordance with BIS/IEC standards.
9.3.10 Grounding Systems
9.3.10.1 General
The following equipment/systems are required to be earthed:
a. Neutral points of different voltages
b. Equipment frame work and other metallic parts
c. Boundary fence, steel structures etc.
9.3.10.2 Design
The grounding system shall conform to IS 3043-1987 or latest edition and Indian Electricity
Rules 1956 along with latest amendments. The voltage between any two earthed points shall not
exceed 32 volts. The resultant value of earthing resistivity shall not exceed 1.82 ohm-m.
Earthing electrodes shall be uniformly distributed and located adjacent to fencing of switchyard
and power house. Three earthing connections to lightning arrestor shall be made directly.
Earth mats for switch yard and power house will be made with the help of 50mmx6mm G.I.
strips buried underground. Earthing electrodes may be 19mm diameter, 2m long M.S. rods
driven straight into the ground with the help of sledge hammers. Alternatively G.I. plate of size
Detailed Project Report Sagana III HEP Chapter 9 - Electro-Mechanical Works
Chapter 9 - 17
600mmx600mm may be used along with G.I. strip and G.I. pipe with funnel to achieve better
results.
9.3.11 Transmission System for Evacuation of Power
Power is to be evacuated from Sagana-III switchyard to Sagana town for further Sagana-Kutus
Line using a double circuit transmission line
9.3.12 Diesel Generating Set
Diesel generator of 100KVA, 415 V shall be provided at the project along with its accessories,
control panel, battery and cooling systems, indicating/measuring instruments, protection and
alarm systems etc.
Detailed Project Report Sagana III HEP Chapter 10 - Construction Plan & Program
Chapter 10 - 1
Chapter 10 - Construction Plan & Program
Detailed Project Report Sagana III HEP Chapter 10 - Construction Plan & Program
Chapter 10 - 2
10.1 General
Proper selection of construction methodology and tight project scheduling followed by strict
monitoring during construction are the major tools available in the hand of developers for
ensuring completion of projects within scheduled time and cost. The actual implementation of
the scheme is proposed to be divided in to three stages:
Pre- construction Activities
Construction Activities
Testing and commissioning
Various activities each of these stages in described below in detail.
10.2 Pre-Construction Activities
The activities proposed to be undertaken during Pre-construction work include the following:
Additional testing for construction materials
Tie-up for supply of construction materials
Site office
Forest clearance, if required
Acquisition of forest and private land for road, project components, Transmission
line, contractor’s camp and colony
Clearance from other agencies like Pollution control board, Public health, Irrigation.
New detailed topographical survey and Detailed design and preparation of tender
documents for Civil, Electro-mechanical, Hydro mechanical
Financial closure
Construction power
Construction of Approach road
Construction / Strengthening of bridges
Transmission line
Mobilization of Project team
It is proposed that critical activities like forest clearance, land acquisition, construction power
and preparation of tender documents be started immediately after signing of PPA. The
hydrological observation for the River Sagana would be continued during the entire Pre-
construction period of the scheme to firm up the discharge availability studies. As shown in
Detailed Project Report Sagana III HEP Chapter 10 - Construction Plan & Program
Chapter 10 - 3
enclosed bar chart, pre-construction activities are expected to be completed in a period of 6
months.
10.3 Construction Activities
10.3.1 Civil Works
The civil works of Sagana-III HEP include:
Trench weir
Upstream and downstream launching aprons
Intake pipe
Desilting basin
Power channel
Tunnel
Forebay
Penstock anchor blocks and saddle supports
Powerhouse
Tail race
Switchyard foundations
a) Diversion weir
The construction of trench type diversion weir involves the diversion of water in the river
Sagana. The construction is proposed in two stages. The first stage involves diversion of river
towards the left bank and construction of intake structure and trench weir on the left bank of
the river. In the second stage, the river will be diverted towards the other bank and
construction of trench weir along with the construction of launching apron completed. Both
the stages of work will be constructed during the low flow season in the river. The work may
have to be discontinued during rainy season. All the activities relating to the construction of
Trench weir are expected to be completed within 8 to 10 months period.
b) Approach Tunnel & Tunnel - 2
Excavation work for tunnel can be taken up immediately on start of construction work. The
work may have to be discontinued during rainy season. The construction of approach Tunnel
Detailed Project Report Sagana III HEP Chapter 10 - Construction Plan & Program
Chapter 10 - 4
(Approach Tunnel: Length 1260m) is estimated to be completed within ~14 months and
construction of Tunnel –2 (length 2340m) is estimated to be completed within ~21 months.
c) Approach Channel
Excavation work for the various sections of the power channel can be taken up immediately
on start of construction work. A trace cut will first be done and thereafter, the full excavation
for channel will be carried out. Concreting for power channel will then be undertaken. The
construction of power channel is estimated to be completed within 10 to 12 months.
d) Desilting basin
Base concrete for intake pipe and excavation for desilting basin can be taken up as an
independent activity. After laying the steel pipe, concreting of intake pipe and desilting basin
can be taken up. The construction of intake pipe and desilting basin is estimated to be
completed within 7 to 8 months from start of construction.
e) Power Channel - 1, Power Channel - 2 & Tail Race Channel
Excavation work for the various sections of the power channel can be taken up immediately
on start of construction work. A trace cut will first be done and thereafter, the full excavation
for channel will be carried out. Concreting for power channel will then be undertaken. The
construction of power channel is estimated to be completed within 10 to 12 months.
f) Forebay
The construction of forebay is proposed to be started after a period of six months from start
of construction activity. During this period, the embedment parts of gates and penstock are
likely to be available. The construction of forebay is estimated to be completed within 7 to 8
months
g) Penstock
A ~175 m penstock (main length) with the branch length (two nos.) being ~15.5 m, is being
proposed. The excavation for the Penstock works is estimated to take 7-8 months. The
fabrication and associated work of penstock which will start a two or three months after the
start of excavation is estimated to be completed within 09 to 10 months.
Detailed Project Report Sagana III HEP Chapter 10 - Construction Plan & Program
Chapter 10 - 5
h) Power House
The construction of powerhouse falls on the critical path. The excavation for powerhouse
will be taken up first and will be completed in 12 months. After receiving the details of
embedded parts of turbine and generator and valves, the concreting for powerhouse raft will
be carried out. Powerhouse walls and columns will then be completed up to service bay level.
There after the construction work for powerhouse columns and crane beam will be done to
enable erection of roof truss and roofing material. The construction of tailrace channel will
be done simultaneously with powerhouse construction. The crane beam is proposed to be
made available to the turbine manufacturers by the end of 6th month for erection of turbine
and generator. Finishing works for powerhouse will be carried out in parallel with machine
erection. The complete civil works for powerhouse are expected to be completed in 16
months from start of construction. Work at powerhouse may be disrupted for 4 months due to
climatic conditions.
f) Gates at Weir Site & Penstock Intake
The work of block outs for 2nd stage embedment will carry out along with other civil
engineering works. After laying the embedded parts, the 2nd stage concreting will be carried
out. The total work including 2nd stage concreting, installation of gates, Penstock shall be
completed in 45 days after completion of civil engineering structures.
g) Transmission Lines
A detailed topographic survey has been carried out for ascertaining the route length and
number of poles and other materials for construction of Transmission Line. Based upon the
requirements so worked out, materials shall be procured and the Contractor shall be finalized
for execution of the construction works. Supervision of construction shall be ensured by the
implementing agency. In case any technical assistance is required from the Consultant the
same shall be provided. The execution of construction of Transmission Line shall be done
concurrently with Powerhouse and Switchyard and shall be completed within 12 months
starting from 8th
month onward.
Detailed Project Report Sagana III HEP Chapter 10 - Construction Plan & Program
Chapter 10 - 6
10.3.2 Electro-Mechanical Works
Tendering and Order Placement: For timely completion and efficient monitoring of project,
complete electro-mechanical works shall be awarded to single contractor on the basis of Limited
International Competitive Bidding process or any other competitive process that is feasible and
time efficient. Tenders for the Electro-Mechanical works shall be floated during pre-construction
stage and order shall be placed to match the progress of work of civil works. Electro mechanical
work is estimated to complete in 17 months.
10.3.3 Engineering
Immediately on confirmation of the order, the electro-mechanical supplier shall start his detail
engineering and shall be asked to submit the first stage embedment drawing and other drawings
to consultant for approval. Consultant shall give comments / approval of drawings within 10
days of submission of drawings. All manufacturer drawings shall be submitted within six months
of award of work.
10.3.4 Manufacturing & Supply
Supplier shall be asked to submit the complete quality assurance and quality control program for
consultant approval. After approval of quality plan, supplier shall start his manufacturing and
erection- work. The first stage embedment viz., drainage water pipes, draft tubes embedment
etc., shall be supplied during sixth month of construction period. The supply of other equipment
shall start latest by 9th month from the placement of order and entire supply shall be completed
by the 13th month from award of supply order.
10.4 Erection & Commissioning
The crane shall be made available for electro-mechanical erection during 6th month and
powerhouse shall be handed over to contractor thereafter for erection of equipment. The
switchyard foundations shall be made available to contractor during 15th month. Contractor shall
complete erection work of powerhouse and switchyard in all respect before 20th
month. After
completion of erection works, pre-commissioning test of all equipment shall be completed within
one month and commissioning of first unit shall be done in 15 days and second unit shall be
commissioned in another 15 days. Thus, the project shall start generating by the end of 24th
month after award of work to the contractor
Detailed Project Report Sagana III HEP Chapter 10 - Construction Plan & Program
Chapter 10 - 7
10.5 O&M Manual & As Built Drawings
Soon after commissioning of project equipment, manufacturer shall submit the complete six sets
of as built drawings for consultant / developer record. The equipment supplier shall also furnish a
detailed operation and maintenance manual to the consultant for approval.
10.6 Handing Over:
After commissioning of project and successful operation of plant, project shall be taken over by
the developer. However, a team of contractor engineers shall be at project site for another two
months for any trouble shooting and training of personnel.
Detailed Project Report Sagana III HEP Chapter 10 - Construction Plan Program
Sagana-III Small Hydro-Electric Project (10 MW)
Bar Chart
S.NO. ACTIVITIES 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
1 Pre-const.Activities & Mobilisation
2 Surveys, Hydrometrerological Data,Geological Data,Misc.
3 Firm up Designs i/c Model Studies
4 Permission to acquire Govt./Forest land
5 Acquisition of land
6 Intake Excavation
7 Intake concreting
8 Power channel Excavation & Concreting
9 De-silting chamber Excavation & Concreting
10 Tunnel (1260m) Excavation & Concreting
11 Tunnel (2340m) Excavation & Concreting
12 Forebay
13 Penstock Excavation
14 Proc.,Feb.,Transportation of penstock
15 Power House Ecavation
16 Power House concreating
17 Tail Race Channel ( 25 m ) Excavation & Concreting
18 Proc., & supply of Hydro Gen. Unit
19 Erection of Hydro Gen. Unit
20 Testing & Commissioning of Unit
21 Switchyard
22 Erection of transmission system
FIRST YEAR THIRD YEARSECOND YEAR
Chapter 10 - 8
Detailed Project Report Sagana III HEP Chapter 11 - Construction Material
Chapter 11 - 1
Chapter 11 - Construction Materials
Detailed Project Report Sagana III HEP Chapter 11 - Construction Material
Chapter 11 - 2
13. General
The main items of work for civil works have been estimated on the basis of drawings
prepared after carrying out the preliminary designs of civil components. Surveys have been
conducted to assess the availability and suitability of construction materials in the vicinity of
the project area. This chapter describes the estimated quantity of main construction
materials, their suitability for construction purposes and their availability.
13.1 Quantity of Work Involved
The civil components for Sagana-III HEP include Infrastructure roads, River diversion
works, Trench weir and launching aprons, Intake structure, Desilting chamber, Power
channel, Tunnel, Forebay, Penstock, Anchor blocks, embedded parts, Power house building,
Tail race channel, Switchyard and appurtenant works. The major items of work involved in
construction of these components include excavation, lean concrete, reinforced cement
Concrete, stone/brick masonry, gabions, boulder protection, and structural steel fabrication.
The materials required for construction viz., coarse aggregate, fine aggregate, cement,
reinforcement steel, structural steel, rubble, bricks shall be procured in required quantities to
match the construction schedule. The total quantity of material estimated is indicated below-
Sl. No. Description Quantity
1 Cement 16656 MT
2 Sand 9186 cum
3 Coarse Aggregate 18371 cum
4 Reinforcement Steel 914 MT
5 Structural steel 93 MT
6 Boulder Crates 4626 cum
7 Mild Steel grade 2 208 MT
13.1.1 Cement
Cement can be procured from the nearby towns of Nyeri, Othaya, and Muranga or from the
capital city of Nairobi which is around 180 km from project site. Trucks shall be used for
transportation of cement bags. Cement bags shall be stored in cement stores as per
specifications.
Detailed Project Report Sagana III HEP Chapter 11 - Construction Material
Chapter 11 - 3
13.1.2 Steel
Steel will be brought from steel stockyard at Nyeri, which is about 35 km from project site
and shall be the main source of structural steel and reinforcement TOR steel. Required
quantities of reinforcement and structural steel shall have to be stored at site from time to
time in advance of construction to avoid any hindrance in project construction. Penstock
steel plates, however, will have to be procured by the contractor directly from the
manufacturers as per design specifications.
13.1.3 Coarse Aggregate
Coarse aggregate and stones shall be quarried from the riverbeds of River Sagana. It has
been found that abundant quantity of rock is available within couple of kilometers of the
project area, which can then be crushed to cater to the requirements of coarse aggregates. A
stone crusher shall be installed at appropriate position along the length of the project.
The fine aggregate is available in various pockets of the River Sagana with in 15 km
distance of the Project area. The material will be screened and transported to the project site
by mules and tippers.
13.1.4 Other Materials
Explosives, POL, CGI sheets, industrial gas and other materials required for the project will be
transported from Nairobi which is 180 km from project site.
Detailed Project Report Sagana III HEP Chapter 12 - Project Organization
Chapter 12 - 1
Chapter 12 - Project Organization
Detailed Project Report Sagana III HEP Chapter 12 - Project Organization
Chapter 12 - 2
12. General
The construction of Sagana-III HEP will have to be supported by relevant infrastructure works
such as permanent and temporary colonies, office, roads and bridges, workshops, etc. situated
within the projected area. The project is planned to be completed in a construction period of 18
months and a 6 months period will be devoted for creation of infrastructure facilities.
The construction of the project is proposed to be carried out through contracting agencies
entrusted with suitable contract packages. Following packages have been envisaged for the civil
works for various project components:
Package I:
Infrastructure: Access road, Mule tracks, Ropeway, Colonies etc.
Package II:
Trench Weir, Intake Structure, Desilting basin, Water Conductor system, Forebay,
Penstock, Power House, Tail race and Switchyard.
Package III:
Hydro mechanical works viz. Penstock and its accessories, Trash Racks, Gates, Stoplog
Stilling racks, Gates valve. Beside above civil packages, the following packages have
been envisaged for the Electro-Mechanical works. (This scope can be further sub-divided
into parts to be allotted to different contractors.)
Package IV:
Turbine, Generators, Spherical valve, auxiliary, equipment, Cranes and 132 kv
switchyard equipment.
Package V:
Transmission Line and its allied items
It is also proposed that contract relating to preparation of detail designs, technical specifications
and construction drawings for various components of the project would be executed through a
separate contract package by a competent consultant. Keeping in view the hilly terrain in which
the project is located and the quantum of design and construction work involved, close
coordination would have to be maintained to avoid time and cost over–runs. The organization of
the project has been planned keeping the above in the view. Broad features of this organization
structure are described in the following paragraph.
Detailed Project Report Sagana III HEP Chapter 12 - Project Organization
Chapter 12 - 3
12.1 Project Organization
The works of Sagana–III hydro-electric project would be looked after by a project team set up
for the purpose under the overall control of M/s Lucid Power Generation Limited. The unit is
proposed to be headed by General Manager for the overall management of the project. All
engineering and project services would be accountable to the General Manager. The General
Manager would be assisted by separate departments to look after the planning, material
procurement, construction management, quality control, administration, financial and accounts
aspects of the projects. The organization set up above will be supported by the necessary
complimentary staff.
12.1.1 Organization for Construction of Civil and Electrical Works
The proposed organization for peak construction period will comprise of the following:
One General Manager, responsible for the overall execution of the works.
Four engineers, out of which two for civil and one each for electrical and transmission
line works shall assist the General Manager.
One Financial Controller along with necessary complimentary staff for ensuring proper
financial control.
One Human Resource Manager with necessity complementary staff to look after
personnel & administration, public health, liaison work, etc.
The above mentioned officers shall be overall in-charge of their respective offices and shall
function as an integrated team, every member of which will not only be conversant with his
duties and responsibilities, but will also get necessary report/feedback regularly from his
respective division for taking timely corrective measures wherever required. Each Division will
have technical and secretarial supporting staff as per requirement. The team has the bandwidth to
support more than one project, in the same vicinity, especially at the senior managerial level.
12.1.2 Functions and Responsibilities of Project Team Members
12.1.2.1 General Manager (Complete Project)
He will be responsible to complete Infrastructure works, construction of all civil, electrical and
transmission line activities as stated in Package I to V. He will also be responsible for pre-
construction investigations, material testing, quality control and control survey.
Detailed Project Report Sagana III HEP Chapter 12 - Project Organization
Chapter 12 - 4
He will be assisted by Four (4) engineers for execution of these works and one material testing
engineer. The key responsibilities of the team members attached to the General Manager will be
as under.
12.1.2.2 Engineer (Civil-I)
He will be responsible for construction of infrastructure works and shall be officer in-charge for
civil works relating to construction activities under Package I.
12.1.2.3 Engineer (Civil - II)
He will be responsible for execution of Package II.
12.1.2.4 Engineer (Electrical)
He will be responsible for the execution of all the electrical works involved in Package IV.
12.1.2.5 Engineer (Transmission line)
He will be responsible for execution of Package V.
12.1.2.6 Material Testing Engineer
He will be responsible for organizing testing of materials and quality control for the entire civil
works and would be in charge of up keep and maintenance of all laboratories. In addition, he will
be responsible for control survey of the whole project. For this purpose, he will be assisted by
supporting staff.
12.1.2.7 Need Based Units
The number of unit headed by one General Manager as proposed above, are based on the
function and physical requirements of the works. The works between all team members have
been so distributed that progress is achieved for the critical items of the works without affecting
progress on other works.
12.1.3 Project Monitoring and Quality Control
General Manager will be assisted at Project headquarters by the two managers (Co-ordination &
Monitoring), one for Civil and one for E&M and Transmission line works. Each manager will be
assisted by one engineer in carrying out the function of monitoring the progress of works, quality
control, co-ordination and liaison with various agencies, safety aspects etc. For this purpose, the
Detailed Project Report Sagana III HEP Chapter 12 - Project Organization
Chapter 12 - 5
Material testing Engineer would be reporting directly to General Manager in all technical
matters.
12.1.4 Finance and Accounts
The General Manager will have a Financial Controller (F.C.) supported by one Accounts Officer
(AO) attached to his office. The FC & AO will deal with work accounts, costing regular and
work-charged staff establishment etc.
12.1.5 Project Administration
Regarding project administration including maintenance of colonies, public relations, welfare
etc., the General Manager will be assisted directly by a Manager (Admin.) posted in his office.
The Manager (Admin.) will be assisted by a Security Officer along with supporting staff to look
after the vigilance and security aspects of the project areas.
The organization structure will be reviewed and firmed up as part of the detailed planning in the
pre-construction stage.
M/s Lucid Power Generation Limited will ensure adequate review of project activities, and
provide financial and administrative approvals and render policy guidance to the General
Manager of the project.
The project management shall function as a fully integrated team dedicated to the
implementation of the project. Every member of the team shall report regularly to his officer-in-
charge and shall be subject to review of his performance. They would periodically review the
progress of works, identify the problem areas suggest remedial measures, see through the
implementation of such measures, and have a realistic forecast of the status of the project in the
intermediate time frame.
12.2 Technical Advisory Committee
M/s Lucid Power Generation Limited will constitute a technical advisory committee comprising
of renowned experts. This committee will advise the project team through General Manager on
all critical aspects of project planning, design and construction activities.
12.3 Consultants
M/s Strategic Consulting Group (SCG) Shimla has been appointed the consultant for the project
and is assigned with Investigation, DPR Preparation and finalizing the project components. Other
Detailed Project Report Sagana III HEP Chapter 12 - Project Organization
Chapter 12 - 6
consultants/ service providers will be hired at an appropriate time as per requirements of the
project.
12.4 Reporting / Reviews
The project will be subject to monthly reviews so that all concerned are aware of progress to
date. The monthly report will give details of manpower, productivity, schedule and costs. The
purpose of these reviews will be to highlight the problem areas and provide the required
additional supervision and action to resolve the problem. The reports will be prepared using
inputs from consultants, contractors, construction supervisors, procurement officers etc. so that a
realistic picture of the project is available for review and report.
Detailed Project Report Sagana III HEP Chapter 12 - Project Organization
Chapter 12 - 7
General Manager (Project Head
Quarter)
Package I:
Infrastructure:
Access road, Mule
tracks, Ropeway,
Colonies etc.
Engineer Civil I
Package II:
Trench Weir, Intake
Structures, Water
Conductor system,
Power House, Tail
race etc.
Engineer Civil II
Package IV:
Turbine,
Generators,
Spherical valve,
Cranes, 132 kv
switchyard, etc.
Engineer Electrical
Package IV:
Transmission Line
and its allied items
Engineer Electrical
Testing of materials
and quality control
for the entire civil
works
Engineer Material
Testing
Personnel &
administration,
Public Health,
Liaison work
Human Resource
Manager
At Project
Headquarters
Co-ordination &
Monitoring team
(Civil)
Co-ordination &
Monitoring team
(E&M &
Transmission
works)
Financial Controller
(F.C.)
Accounts officer:
Work accounts,
Costing regular &
Work-charged staff
establishment etc.
Detailed Project Report Sagana III HEP Chapter 13 - Environmental & Ecological aspects
Chapter 13 - 1
Chapter 13- Environmental & ecological
aspects
Detailed Project Report Sagana III HEP Chapter 13 - Environmental & Ecological aspects
Chapter 13 - 2
13. Introduction
The Sagana River is one of the major rivers of Kenya. It has a total Catchment of up to 1460 Sq.
Km. at proposed intake site. Around the intake site on both of the banks of Sagana River, the
area is mostly covered under farming. The powerhouse is envisaged at an elevation of 1209.91 m
on right bank of Sagana River.
The co-ordinates of the intake structure are 0°34'49.31"S, 37° 9'1.60"E. The Power house is
located at an elevation of ~1210 m. The co-ordinates of the power house are 0°36'52.64"S,
37°10'45.79"E (Toposheet No. 135/1).
The project site is located near Ithanji and Mutundu villages in Nyeri district of the Central
Province of Kenya. The project site area is well connected by road and is 180 Kms from the
capital city of Nairobi.
The area around the proposed project is largely covered with overburden in the riverbed and
adjoining terraces. Overburden consists of deep fill of ravine sediments whereas hill slopes are
covered with slope-wash materials. Rock outcrops are scanty. However the hill slopes around the
proposed project are stable and the area is conducive for constructing a small hydropower,
scheme on geological considerations. Also, the danger of erosion and disturbance to hill slopes is
minimal. A very small approach road to powerhouse shall need to be constructed.
The excavated material shall be deposited at previously, identified and approved sites so as to
minimize any adverse effects on the environment. A small colony shall be needed to
accommodate the skilled and specialist labour that would be brought from outside.
The flow conditions in the river would be left undisturbed except the diversion of design
discharge at diversion weir site for the purpose of power generation. Flows diverted for power
generation shall be led back to the Sagana River at the powerhouse location through the tailrace
channel.
The scheme shall take care not to endanger the flora and fauna species in and around the area.
All efforts shall be made so that no ecological disturbances or backlashes are brought in that
could upset the existing ecological balance in the project area.
13.1 Catchment Area Treatment
The catchment area at the diversion site of Sagana III HEP is 1460 Sq. Kms, out of which over
50% is in dense forest area (Aberdare Forest). This area comprises of forests with dense mixed
Detailed Project Report Sagana III HEP Chapter 13 - Environmental & Ecological aspects
Chapter 13 - 3
jungles (Equatorial). The catchment in the uppermost reaches of the river is unapproachable. It is
proposed to provide engineering measures such as contour drainage, easing of critical slopes etc.
wherever required around the project area.
Afforestation is proposed in the catchment and an adequate monetary provision has been
earmarked in the project budget for this purpose.
13.2 Base-Line Data
13.2.1 Vegetation Profile
The project components are proposed to be constructed on private land. The ~4.8 Km long water
conductor system is proposed to run as various sections of closed RCC box type channel,
rectangular channel, and tunnel sections along the contour of the hills, up to the forebay.
Adequate compensatory afforestation shall be carried out and all efforts shall be made during
detailed designing of project components to avoid clearing of the existing trees as much as
possible.
Adequate compensation shall be made to all land owners for cost of land and any standing crop,
if any.
13.2.2 Seismicity
Kenya is located in the Eastern part of Africa. The Rift valley transverse through Kenya from
North to South. The East African Rift System (EARS) is a 50 to 60km wide zone of active
volcanoes and faulting that extends north-south in Eastern Africa for more than 3000 km (1864
miles) from Ethiopia in the north to Zambezi in the south. It is a rare example of an active
continental rift zone, where a continental plate is attempting to split into two plates which are
moving away from one another. This is the main source of seismicity in Kenya.
13.2.3 Climate
Sagana III HEP (10 MW) is located in the Central Province of Kenya. The climate of Central
Province is generally cooler than that of the rest of Kenya, due to the region's higher altitude.
The temperature varies between 7ºC to 30ºC. The period from February to March is the hottest
while the one from July to August is the coldest. The average annual rainfall received in the
catchment area is 1200mm (as per the Rainfall gauges at Embu Metrological station, Sagana
Technical School, Sagana State lodge, etc.).
Detailed Project Report Sagana III HEP Chapter 13 - Environmental & Ecological aspects
Chapter 13 - 4
13.2.4 Land Use Pattern
The land to be acquired for project construction is partly cultivated. It is estimated that ~15.62
Ha of land will have to be acquired for the project. Over 90% of the -land requirement for the
project falls in private land. The project components or parts falling within the private land are
parts of the intake structure, desilting basin, water channel, forebay, penstock, power house and
switchyard. The portion of water conductor system in box type channel has been so planned that
there is minimum acquisition of land required and so it will induce minimal environment related
problems. Further there will not be any population displacement.
13.2.5 Public Health
Hospitals are available at Othaya, Nyeri and Muranga.
13.2.6 Human Settlements
The village near project area is Ithanji and Mutundu. The nearest towns around the project area
are Ngunguru ,Othaya and Nyeri. Chief’s office, Police station, and bank like KCB are available
in Othaya.
Basically, the village and towns mentioned above are well developed and are connected via a
tarmac road. Four-wheel drive vehicles are commonly used for transportation of goods as well as
passengers.
Though most of the villages are connected with mobile phones. Mobile phone operators such as
Airtel, Safaricom and Orange provide their service in the project area.
13.2.7 Project Impacts
The impacts on the environment, anticipated due to the project are divided under the following
heads:
i) Impact due to Project location
ii) Impact due to Project Design
iii) Impact due to Construction Works
iv) Impact due to Project Operation
All the above are discussed in the following sections.
i) Impact due to Project location
Rehabilitation
Detailed Project Report Sagana III HEP Chapter 13 - Environmental & Ecological aspects
Chapter 13 - 5
There is no displacement of any local inhabitants and a very small area of land is required for
the project. Therefore, no rehabilitation measures are required.
ii) Impact due to Project Design Seismicity
There is no immediate threat perception to human life due to occurrence of an earthquake
specifically by the project.
Effect on Climate
As the project is very small having no submergence and impoundment of the order that could
even influence the microclimate of the region, there will not be any adverse effects on the
climate due to the project.
iii) Impact due to Construction Works
Air/Water Pollution
The only anticipated air pollution would be during the construction phase of the project due to
dust levels in the air. Simple procedures like spraying water to keep dust and SPM levels low
would be followed during the construction of the project components.
Soil Erosion
Afforestation is proposed in the catchment and an adequate monetary provision has been
earmarked in the project budget for this purpose.
Sanitary & Health effects from Construction camps
There would be no increase in incidence of diseases due to the setting up of colonies, as proper
health and sanitation arrangement shall be made in the proposed colonies. Locally available
labour would be suitably employed for the project construction activities. Skilled labour may
also be drawn from Sagana or Muranga that is at a manageable distance from the powerhouse
site. Eligible local persons shall also get employment according to their suitability during both
the construction and implementation phases of the project.
Adequate sanitary provisions would be maintained for the colony. Thus, this would not lead to
any increase in diseases or disease vectors, etc.
iv) Impact due to Project operation
Land inundation
The project is a run-of-the-river scheme, therefore it does not involve any storage reservoir.
Thus, the project operation would not lead to any inundation of the surrounding area. Also,
siltation would be negligible because sedimentation in the forebay tank would be minimal. The
Detailed Project Report Sagana III HEP Chapter 13 - Environmental & Ecological aspects
Chapter 13 - 6
water shall be diverted through the diversion weir in the riverbed itself; therefore there would
be no changes in downstream water flows. The diverted water shall be led back into the Sagana
River.
Water logging & Salinity
Water logging and subsequent salinity aspects are not going to pose any problems. No
reservoir is involved and water is not allowed to remain stagnant in the proposed hydro project.
Salinity is not applicable.
Preventive Measures
During both the project construction and operation phases, the following precautionary measures
are proposed to be adopted.
1) Restoration of Construction Areas and Disposal of Muck
The entire construction area shall be properly landscaped when the project is completed so as
to merge the project with the natural surroundings. Major portion of the muck generated during
excavation of diversion channel, desilting tank, forebay shall be dumped in the properly
demarcated sites. These dumping sites shall have proper protection works like wire crates etc.
to make the slopes stable.
ii) Provision of Fuel for Labour Force
Fuel wood shall be purchased from depots of the Forest Department and shall be provided free
of cost to the labour force to ensure that such requirements do not compel the work force to fell
trees during the construction of the project. The project staff shall be provided with electricity
connection, and LPG cylinders. A provision in the cost estimate has been kept for this purpose.
Project Benefits
The foremost reason for promoting micro hydel schemes is their environmentally benign
character. Hydropower, unlike the conventional energy sources entails zero generation of
harmful chemical wastes or toxic gases. It is virtually free from pollution and its establishment
helps in the economic development of the region and should therefore be encouraged for the
rural, remote and far-flung areas.
The generation of environmentally benign energy at low cost shall help in curbing the gap
between high demand and low supply of power, thereby reducing the demand for fuel wood and
resultant global warming impacts.
Detailed Project Report Sagana III HEP Chapter 13 - Environmental & Ecological aspects
Chapter 13 - 7
The socio-economic conditions of the local people from surrounding villages like Ithanji and
Mutundu shall be improved by means of employment generation.
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 1
Chapter 14 - Estimates of cost & Financial
Evaluation
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 2
14. General
The estimates of cost have been prepared to arrive at the total capital cost of the project. The
estimates are based on the prices prevailing in December 2011 for materials, equipment, labour, etc.
Interests during construction period and financing charges have been worked out separately.
The estimates of cost have been prepared in two parts - Part - I cover the civil works of the project,
while Part - II covers Electrical works and transmission works of the project.
14.1 Cost of Civil Works
The detailed estimates of cost of civil works are based on the conceptual layout planning and
preliminary design of different components of works after review of site conditions, analysis and
studies etc. General arrangement and layout details of various structures as well as their features are
shown in drawings.
The rates for major items of civil works have been analysed as per civil engineering guidelines and
rates prevalent during the time of material survey. Rates for minor item of works and lump sum
provisions for some works have been made on the basis of experience of similar works on other
projects which have been recently completed or are under construction.
The rates for hydraulic gates, hoists, and cranes etc. are based on the prevalent market rates for such
works.
14.1.1 Provisions for civil works
The provisions under various sub-heads are derived as per international standards. Broad provisions
made under various sub-heads of civil works are briefly described below:
A - Preliminary
Under this head provision has been made for the feasibility studies to assess the true potential of the
site. Provision has been made for consultant's fees for preparation of the detailed project report, the
cost of detailed engineering, and other project development expenses such as legal fees, overheads
etc. The total provision under this sub-head is USD 789,091.
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 3
Table 14.1 Development Budget
S. No. Particulars USD
1. Feasibility studies 43182
2. DPR 129545
3. Legal 250000
4. Tax & Audit 100000
5. Carbon finance 21591
6. Vehicles 80000
7. Environment studies 21591
8. Miscellaneous 43182
9. Overheads 100000
Total 789091
B - Land
This sub-head covers the provision for acquisition/purchase of land for permanent works, approach
roads, camp sites, workshops, stores, offices and permanent colony for the maintenance staff etc.
The table below summarises the total land requirement:
Table 14.2 Land requirement Summary
S.
No. Description
Length
(m)
Width
(m)
Length
(m)
Width
(m)
Area
(Ha)
Fraction
of total
Land
which is
govt. (Ha)
Govt.
Land
Pvt.
Land
Amount
(In USD)
1 Intake site 59 48 81 58 0 100% 0 0 6,876
2 Intake channel C&C 6 4 6 10 0 0 0 0 128
3
Auxiliary land for
Intake Structures
(work bench)
25 25 25 25 0 0 0 0 1,375
4 Desilting basin 71 21 71 41 0 0 0 0 6,386
5 Power channel
a) Cut & Cover 1115 4 1115 10 1 0 0 1 23,794
b) Open rectangular. 0 6 0 12 0 0 0 0 -
7
Job facility for
tunnel ( 3 at intake
and outlet each)
120 108 120 108 1 0 0 1 28,512
8 Forebay 36 13 56 33 0 0 0 0 4,066
9 Penstock before
bifurcation 186 2 186 10 0 0 0 0 4,174
10 Penstock after
bifurcation 10 15 10 23 0 0 0 0 506
11 Power House 28 19 59 49 0 0 0 0 6,387
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 4
S.
No. Description
Length
(m)
Width
(m)
Length
(m)
Width
(m)
Area
(Ha)
Fraction
of total
Land
which is
govt. (Ha)
Govt.
Land
Pvt.
Land
Amount
(In USD)
12 Switchyard 86 56 106 112 1 0 0 1 26,118
13 Tail race channel 10 6 10 12 0 0 0 0 255
14 Tail Pool 36 9 42 19 0 0 0 0 1,756
15
Auxiliary land for
PH Structures (work
bench)
50 30 50 30 0 0 0 0 3,300
16 Dumping yard
1 0 0 1 26,400
17
Approach road to
power house and
other component
location
3000 8 3000 9 3 0 0 3 59,400
18 Explosive
Magazines 10 10 10 10 0 0 0 0 220
19 Colony 50 50 50 50 0 0 0 0 5,500
20
Transmission line
7.044Km long in
forest land (15 m
wide corridor has
been considered)
7044 10 7044 10 7 0 0 7 154,968
21
Crop compensation
at pole location in
Pvt. land (approx.
Rs. 30000/ pole
location)
0
22
Crop / tree
compensation along
corridor in Pvt. land
0
Total 11942 443
17
360,121
The total land requirement sums to ~17 Ha. The total provision under this sub-head is USD 0.36
million.
C - Civil Works
This covers the cost of river diversion works and diversion structure including cost of hydraulic
gates and hoists and upstream and downstream protection works. The total provision under this sub-
head is as below:
Table 14.3 Intake channel
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 5
S. No. Item of Work Amount
1 Common Excavation 7,932
2 Excavation in Rock 25,704
3 Earth Filling 4,113
4 Concrete M-25 39,127
5 Concrete M-20 26,366
6 Steel Reinforcement 37,923
7 Water Stop 3,000
8 Dewatering 188
9 Filter Sand 900
Contingencies 7,263
Total 152,514
Table 14.4 Trench Weir
S. No. Item of Work Amount (in USD.)
1 Common Excavation 8,031
2 Excavation in Rocks 26,025
3 Backfilling 4,164
4 Concrete M 10 2,090
5 Concrete M 20 26,400
6 Concrete M 25 54,825
7 Steel Reinforcement 25,444
8 Boulders & Crates 39,109
9 Boulder Pitching 110,000
10 Stone work in cement mortar 1:4 3,000
11 River Diversion during construction 50,000
12 Dewatering 7,500
13 Water stop 3,000
14 Trash rack 29,670
15 Embedded & non-embedded metal works 2,300
16 Intake Stop Log Gate
a) 1st and 2nd stage embedded parts 1,150
b) Hoisting / lifting 2,300
c) Gate 55,200
d) Chain Pulley 2,350
17 Intake Service Gate
a) 1st and 2nd stage embedded parts 1,150
b) Gate Leaf 3,853
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 6
S. No. Item of Work Amount (in USD.)
c) Hoisting/lifting 4,700
d) Screw type 12,000
18 Shingle Flushing Gate
a) 1st and 2nd stage embedded parts 1,150
b) Gate Leaf 1,725
c) Hoisting/lifting 2,350
d) Chain Pulley 2,200
Contingencies 24,084
Total 505,770
J - Power House plant Civil Works:
Under this sub-head provision has been made for the following works:
Table 14.5 Power House plant Civil Works break up
Sr. No. Particulars Amount (USD)
1. Desilting Tank 1,104,241
2. Power Channel / Tunnel 4,786,856
3. Forebay 336,631
4. Penstock, Anchor blocks and Saddle Supports 922,075
5. Powerhouse Complex 1,538,362
Total 8,688,165
The details of the quantities used and their costs are as follows:
Table 14.5.1 Desilting Basin
Sl. No. Item of Work Amount (USD.)
1 Common Excavation 55,248
2 Excavation in rocks 179,046
3 Earth Filling 28,647
4 Concrete M-10 27,580
5 Concrete M-25 547,570
6 Steel Reinforcement 92,876
7 Stone Masonry (1:6) 4,900
8 Water Stop 12,000
9 Silt flushing pipe 900mm 14,400
10 Stilling Rack 2,100
11 Dewatering 3,750
12 Gate valves 1000 600
13 PVC pipe 30,000
14 Filter Sand 18,000
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 7
Sl. No. Item of Work Amount (USD.)
15 Upstream Gates
a) 1st and 2nd stage embedded parts 920
b) Gate Leaf 9,400
c) Hoisting/lifting 1,150
d) Chain Pulley Block 6,000
16 Downstream Gates
a) 1st and 2nd stage embedded parts 920
b) Gate Leaf 9,400
c) Hoisting/lifting 1,150
d) Chain Pulley Block 6,000
Contingencies 52,583
Total 1,104,241
Table 14.5.2.1 Power Channel
Sr. No. Item of Work Amount (USD)
1 Common Excavation 235,606
2 Excavation in Rock 305,416
3 Earth Filling 48,867
4 Concrete M-25 510,940
5 Steel Reinforcement 93,885
6 Water Stop 120,000
7 Dewatering 375
Contingencies 65,754
Total 1,380,843
Table 14.5.2.2 Tunnel
Sr. No. Item of Work Amount (USD)
1 Common Excavation U/G 437,400
2 Excavation in Rock 637,875
3 Rock Bolt(3-5m) 90,000
4 Concrete M-20 1,124,082
5 Concrete M-10 506,543
6 Steel Reinforcement 289,170
7 Water Stop 120,000
8 Dewatering 375
9 Structural Steel 38,376
Contingencies 162,191
Total 3,406,013
Table 14.5.3 Forebay
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 8
Sr. No. Item of Work Amount (USD.)
1 Stripping & grubbing 300
2 Excavation in soft soil 30,920
3 Excavation in hard soil 128,835
4 PCC M-25 24,254
5 RCC M-20 68,653
6 Reinforcement Steel 25,889
7 PVC water stop 5,000
8 Trash Rack
a) Embedded parts 1,150
b) Structural, Steel 6,900
9 Railing 800
10 Stone Pitching 3,500
11 RR Masonry for escape channel 2,500
12 Penstock Gate
a) Gate Leaf 5,875
b) Embedded parts 1,725
c) Hoisting and lifting structure 2,300
d) Rope Drum Hoist 12,000
Contingencies 16,030
Total 336,631
Table 14.5.4 Penstock, Anchor blocks and Saddle Supports
Sr. No. Item of Work Amount (USD)
1 Common excavation 47,174
2 Excavation in rocks 61,152
3 Concrete M-25 167,640
4 Steel reinforcement 61,950
5 Penstock Steel 499,200
6 Y-piece saddle supports exp. Joints, manhole and pipe for
emergency escape
40,250
8 Air vent pipe 800
Contingencies 43,908
Total 922,075
Table 14.5.5 Powerhouse Complex
Sr. No. Item of Work Amount (USD)
1 Common excavation 23,340
2 Excavation in rocks 75,639
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 9
Sr. No. Item of Work Amount (USD)
3 Earth Filling 12,102
4 Concrete M-20 3,326
5 Concrete M-25 561,880
6 Steel Super Structure 34,500
7 Railing and miscellaneous and non-embedded metal work,
rolling shutter
2,400
8 Installation of embedded metal work 2,300
9 Steel reinforcement 190,607
10 PVC water stop 7,200
11 Bricks 18,176
12 Geotextile Textile 7618 or equivalent 5,400
13 Dewatering 1,350
14 Boulder protection 1,125
15 Drainage material around power house 1,376
16 Crushed stone (5-20 mm grade) 2,025
17 Gabion wall with wire crate 990
18 C.G.I sheeting (0.63 mm thick) 91,665
Misc. Item
19 Wall (230 thick)(brick masonry) 10,800
20 Cement plaster in 1:4 11,000
21 Doors and windows in powerhouse 9,000
22 Painting inside walls 1,620
23 Painting outside walls 1,620
24 Cement concrete flooring with hardener 14,000
25 Quarry tiles (Red stone) 3,600
26 Ceramic floor and wall tiles 2,160
27 Acid resistant floor titles 720
28 Water proofing ceiling compound 165
29 False ceiling 6,300
30 Misc. Steel Works (hand rails, safety chain etc.) 8,000
31 Embedded pipe 132
32 Embedded pipe of different diameter 600
33 Misc. sanitary fix. (Geyser, urinal, WC, sink, septic tank, soak
pit, etc.)
2,000
Tailrace
34 Common Excavation 1,536
35 Excavation in rocks 1,991
36 Earth Filling 319
37 Concrete M-25 13,894
38 Steel reinforcement 2,389
39 Boulder Protection 2,188
40 D.T. Gates
a) Gate Leaf 9,400
b) Embedment 2,300
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 10
Sr. No. Item of Work Amount (USD)
c) Hoisting / Lifting 3,450
d) Rope Drum Hoist 24,000
Switchyard
41 Common Excavation 26,006
42 Excavation in rocks 84,280
43 Earth Filling 13,485
44 Concrete M-20 141,501
45 Steel reinforcement 26,250
46 GI Chain Link Fencing 5,000
Contingencies 73,255
Total 1,538,362
K - Buildings
Provision has been made under this sub-head for permanent and temporary residential buildings
for various categories of staff, non-residential buildings for offices, workshops, stores, rest
houses and field hostels and other service buildings such as hospital, school, police station and
utility services etc. Provisions for land development, lawns and gardens, fencing, internal water
supply, sanitation and electrical fittings have been made as per norms for various types of
buildings as per norms.
The total provision under this sub-head is USD 175,584.00, well within permissible limits.
M - Plantation
A provision of USD 27,440 has been made under this sub-head for plantation near the Barrage and
reservoir area, colony and camp sites etc.
Sr. No. Item of Work Unit Rate (USD)
1 Plants / Trees to be planted 9000
2 Making pit 0.5m x 0.5mx 0.5m 2250
3 Engaging three gardeners for one year 180
4 Cost of protection work for barbed wire 30000
5 Watchmen cum Gardner-2 Nos. for protection and plantation
for 3 years
180
Total 49,890
O - Miscellaneous
Under this sub-head provision has been made for the following items:
Recreation, Security arrangements, Medical assistance,
Fire fighting equipment, telephone, telegraph, wireless and other communication facilities.
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 11
M. Boundary pillars and stone distances marks and benchmarks
N. Anti-malaria measures, Running of rest house for 2 years, Publicity information
Recreation facilities and beautification of project area.
Maintenance services for electrification, water supply etc. and other services including
security arrangement and fire fighting arrangement.
Other items such as visit of dignitaries, technical record of works, power supply,
compensation to workmen, writing of completion report and history of project etc.
Construction power arrangements for construction of civil works and for camp sites and
workshop etc. during the construction period.
The total provision under this sub-head is USD 48,955.
P - Maintenance
The provision has been made under this sub-head for maintenance of buildings and roads, and main
civil works during the construction period. The total provision is around USD 97,709 which is about
1% of Works less Preliminary, Land and Special Tools & Plant.
Q - Special Tools and Plant
Provision has been made under this sub-head for equipment such as Needle Vibrator, wheel loader,
canal trimmers, Wagon drill, Sump Pump, Pumps 5-10 HP, Water Sprinkler, vehicles such as cars,
jeeps, buses, ambulances etc. Provision for major construction equipment for civil works has not
been made under this head, as the construction of civil works will be carried out by a separate
construction agency. The total provision under this subhead is USD 100,000.
R - Communication
Provision has been made under this sub-head for construction of roads including approach roads.
Provision has also been made for remodelling and strengthening of main highway and bridges to
make them suitable for transport of heavy equipment for power station. The total provision under
this subhead is USD 150,000.00
X - Environment and Ecology
Provision under this sub-head has been made for compensatory afforestation, measures for
maintaining environment and ecological balance of the area, public health measures,
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 12
establishment of fuel depots etc. Provision has also been made for treatment of catchment area
for prevention of soil erosion etc.
The total provision under this sub-head is USD 27,000.00
Y - Losses on Stock
Provision under this sub-head has been made at 0.25% of I-work less A - preliminary, B - land
and Q - special T & P.
Establishment
Provision has been made @5% of I-Works less B-land. This provision also includes
establishment for carrying out detailed designs, site supervision, quality control and cost control
cell. The total provision under this head is USD 558,477.00
Tools and Plants
Provision @ 1% of I-Works has been made to cover survey instruments, camp equipment, office
furniture, office equipment etc. The total provision under this head is USD 111,695.00
Receipts and recoveries on capital account
Under this head estimated recoveries by way of transfer of temporary buildings, resale of special T
& P and other miscellaneous recoveries have been provided. The total recovery of USD 50,000.00 is
estimated under this head.
Audit and Accounts
It has been taken as 1.0% of the cost of I-Works. The total provision under this head is USD
111,695.00
S - Power Plant (Cost of Electromechanical Works)
Cost of generating plant and equipment is based on current market prices for the proposed
machinery of 10 MW capacity.
The following table shows a detail of all the Electro mechanical equipment:
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 13
Table 14.6 Electro-Mechanical equipment
Sr.
No.
Description Unit Qty. Total Price -
FOB,
Mumbai
(USD)
1 Turbines
1.1 Horizontal Francis Turbine comprising runner, guide vanes,
guide apparatus & regulating mechanism, indicating and
recording instruments, safety devices piping, in a complete
shape to develop rated output of 5000 KW at generator
terminals at rated head and discharge.
Nos. 2
1.2 Governing system including digital Electro hydraulic
governor, speed signal generator and TACP.
Nos. 2
1.3 Oil pressure Unit Nos. 2
1.4 Main inlet valve (Butterfly ) ( To suit turbine inlet) Nos. 2
1.5 Cooling water system provided with two pumps (main and
standby), one duplex filters, non-return valves, isolating
valves, pressure gauges, piping, mountings to supply cooling
water to seals and coolers.
Lot 1
1.6 Drainage & Dewatering System Set 1
2.1 Generator
Horizontal Shaft AC Syn. Generators Natural Cooled,
Cylindrical pole type, 5000 KW , 11KV, 500 rpm, 0.85 p.f.,
50 Hz. With Brushless excitation system with AVR, Lube Oil
System & Braking System.
Sets 2
2.2 Control, Protection, Metering System consisting of :
2.1 Generator LAVT and Surge capacitor panel Nos. 2
2.2 Generator neutral grounding (NGT) panel with neutral
grounding transformer
Nos. 2
2.3 Synchronizing Panel for Generators and 132 kV lines No. 1
2.4 Generator C/R Panel Nos. 2
2.5 Gen. Transformer C/R Panel Nos. 2
3 Power & Auxiliary Transformer consisting of:
3.1 Generator Transformer 8 MVA, 11/132KV, Ynd11, ONAN,
OCTC +/- 5% @2.5% Steps complete with all accessories
Nos. 2
3.2 Station Aux. Trfs., 315 KVA 11/0.415KV, Dyn11, ONAN,
OCTC +/-5%@2.5% steps
No. 1
4 415 V - LT Switchgear panel No. 1
5 DC System comprising of : Set 1
5.1 110 V, 150 AH DC Battery bank (VRLA Type)
5.2 110 V, 150 AH DC Battery Charger (Float & Boost charger)
5.3 110 V, DCDB
6 DG Set - 415V- 100 KVA with AMF panel Set 1
7 - 11 KV & 1.1 KV XLPE insulated Aluminum conductor
armored Power Cable with cable trays, termination kits
Lot 1
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 14
Sr.
No.
Description Unit Qty. Total Price -
FOB,
Mumbai
(USD)
and accessories.
- Multicore PVC insulated Copper Conductor armored
control cable with cable tray
8 132 KV Switchyard Equipment at Power House (outdoor
type ) consisting of :
Lot 1
8.1 132 kV, outdoor type 1250 Amps, Isc=25 KA, SF6 circuit
breaker
Nos. 4
8.2 132 kV Isolator with earth switch = 1250 Amp. (Motorized) No. 2
8.3 132 kV Isolator without earth switch = 1250 Amp. (
Motorized)
Nos. 5
8.4 130 kV 10kA Lightning arrestors Nos. 4
8.5 132 kV Current Transformer (150 /1 Amp.) Nos. 4
8.6 132 kV Potential Transformer ( Bus & Line) 132KV/√3
/110/√3/110/√3
Nos. 3
8.7 Marshaling Box for switchyard equipment Lot 1
8.8 Switchyard structures/Gantry/Tower etc. /Structure
CT,PT,LA, Isolator etc.
Lot 1
8.9 ACSR Conductor with hardware and accessories and Misc.
Items
Lot 1
8.10 132 KV Manually operated DO fuse. No. 1
9 Supervision of Erection & Commissioning Lot 1
10 List of Spares ( as per our offer) Set 1
11 Tools and Tackles ( as per our offer) Set 1
Grand Total Price
5,019,991
A total provision of USD 5,019,991.00 has been kept under this head.
T - Transmission
Provision for construction of a 7.04 km long transmission line from Power house site to the 132
KV Sagana-Kutus line in Sagana town has been made. The following table shows the breakup of
the cost estimate:
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 15
Table 14.7 Transmission works
Sl. No Item Description Total Cost
1 11.5 ISMB Poles for (Double Pole) Tr. Lines 17,200
2 ACSR ' DOG' conductor 232,485
3 Disc insulator of 70kN with attachments and accessories 26,316
4 132 KV Pin insulator with electrolytic binding wire for conductor 1,161
5 Hardware Fittings for Disc insulator 516
6 Danger plate, anti-climbing devices 215
7 Stay set with stay wire 10,800
8 Earthing system of 2.8m long 25mm hot dip galvanized iron rod 1,075
9 MS flat for pin insulators & hardware for double pole 946
10 MS 50 x 6 mm for fixing earth wire on pole 86
11 8 S.W.G. G.I. wire 1,409
Total 292,209
The total provision under this head is USD 292,209.00.
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 16
Estimated Direct and Indirect Cost of the Project
Total cost of the Project at Dec, 2011 price level works out as under:
Table 14.8 Direct and Indirect Cost
S No. Item Civil E&M Total
USD Mn USD Mn USD Mn
A Direct Cost
I I - Works
A - Preliminary 0.79
0.79
B - Land 0.36
0.36
C - Civil Works 0.66
0.66
J - Power plant civil work 8.69
8.69
K - Buildings 0.18
0.18
M - Plantation 0.05
0.05
O - Miscellaneous 0.05
0.05
P - Maintenance during construction 0.10
0.10
Q - Special Tools and Plants 0.10
0.10
R - Communication 0.15 0.15
S - Power Plant
5.02 5.02
T - Transmission
0.29 0.29
X - Environment, Ecology and Afforestation 0.03
0.03
Y - Losses on stock 0.02
0.02
Total: I - Works 11.17 5.31 16.48
II Establishment 0.34 0.22 0.56
III Tools and Plants (T&P) 0.34 0.22 0.56
IV Receipts & Recoveries (0.05)
(0.05)
Total Direct Cost 11.79 5.76 17.55
B. Indirect Cost
Capitalization of abatement of land revenue 0.02
0.02
Audit and account charges 0.07 0.04 0.11
Total Indirect Cost 0.09 0.04 0.13
Total direct & indirect cost 11.87 5.80 17.68
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 17
To this the Initial Working capital, capitalized spares, Interest during Construction, Financial
Charges, Escalation during construction, Contingency, upfront loaded DSRA Cost shall be added to
arrive at the total project cost.
A summary of the table above is shown below:
Table 14.9 Summary of Costs
Sr. No. Cost Components USD mn
1 Civil Works 11.79
2 E & M 5.76
O/W Transmission Work 0.29
Total cost without IDC & FC 17.55
3 Indirect Cost 0.13
(a) Total direct & indirect cost 17.68
The summary of the rates of items is shown below:
Table 14.10 Summary of Rates of items
Sl. No. Items Unit Rate
(USD/Unit)
1 Cement Per bag 6.00
2 Cement Concrete M-7.5 m3 90.00
3 Cement Concrete M-10 m3 95.00
4 Cement Concrete M-15 m3 112.00
5 Cement Concrete M-20 m3 120.00
6 Cement Concrete M-25 m3 130.00
7 Cement Concrete Lining,100 mm thick,M-10 Grade m2 15.00
8 Cement Concrete Lining,100 mm thick,M-25 Grade m3 60.00
9 Random Rubble Masonry in CM 1:6 m2 40.00
10 Stone Masonry (1:6) m3 70.00
11 Brick Masonry m3 80.00
12 Cement Pointing in CM 1:3 m2 6.00
13 Cement plaster 20 mm thick CM 1: 4 m2 5.00
14 Damp Proof Course,40 mm thick, with Bitumen Coating m2 15.00
15 Cement Concrete Flooring, 75 mm in M-15 m2 14
16 Marble Chip Flooring 40 mm m2 12
17 Dry Stone Pitching m2 90.00
18 Crated Bolder pitching With Cement Concrete m3 110.00
19 Tor Steel Reinforcement MT 1050
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 18
Sl. No. Items Unit Rate
(USD/Unit)
20 Structural Steel MT 1150
21 Penstocks MT 2400.00
22 Steel Works in Gates MT 2350.00
23 Steel Works in Stop logs MT 2350.00
24 Steel Works in Trash Racks MT 2350.00
25 Railing MT 800
26 Steel Truss MT 2200.00
27 Fine Sand m3 90.00
28 Coarse Sand m3 95.00
29 Stone Boulders m3 25.00
30 Aggregates 16-20 mm m3 45.00
31 Aggregates 20-50 mm m3 45.00
32 Marble Chips 100 kg. 35.00
33 Marble Dust 100 kg 20.00
34 Earthwork in Soil Mixed With soft soil and Shingles m3 6.00
35 Earthwork in Soil Mixed With Shingles and Boulders m3 15.00
36 Earth work In Rock Requiring Blasting m3 25.00
37 Extra for Additional Lead of 30m or Lift of 1.5m m3 5.00
38 Earthwork in Filing including Compaction m3 7.00
39 Earthwork in Mixed Soil m3 0.88
40 CGI Roofing m2 8.00
41 Carriage cost by Road MT/km 7.00
42 Head load per km- Cement MT/km 15.00
43 Head load per km- Steel MT/km 15.50
44 Head load per km-Others MT/km 15.00
45 Contractors profit % 15.00
46 Overhead Charges % 5.00
47 Extra Leads, average 2 man-day Man-day 0.66
48 Wetting And Compaction Charges Cum 0.79
49 Sundries T & P L.S. 0.42
50 Bitumen Kg 1.05
51 Wire Gauge m2 2.60
52 Rivets / Welders Nos. 4.90
53 G I Sheets m2 146
54 G I Bolts and Nuts Kg 3
55 Dewatering KWh 0.75
56 Stone fill crates in wire mesh for Gabion Wall m3 22
Detailed Project Report Sagana III HEP Chapter 14 - Estimates of Cost
Chapter 14 - 19
Sl. No. Items Unit Rate
(USD/Unit)
57 Water Stop m 20
58 Steel Pipe 900mm MT 1200
59 PVC m 100
60 Gate valves 500 Nos. 300
61 Chain Pulley Block Nos. 3000
62 Rope Drum Hoist 2 MT Nos. 4000
63 Rope Drum Hoist 7 MT Nos. 12000
64 Anchor bolt Nos. 20
65 Rock Bolt Nos. 15
66 Stripping & grubbing m2 2
67 RR Masonry for escape channel m3 50
68 Air vent pipe L.S. 400
69 GI Chain Link Fencing MT 1000
70 Saplings / Trees Nos. 2
71 Gardner wage per month USD 60
72 Watchmen cum Gardner USD 90
73 Road USD/km 50000
74 Drainage material around power house USD/ m3 16
75 Rate of Pvt. land USD/Ha 22,000
76 Rate of Govt. land USD/Ha 14,800
77 Geotextile Textile 7618 or equivalent USD 10
78 Doors & windows USD/ m2 800
79 Paint inside/outside walls USD/ m2 1.5
80 Quarry tiles- stone m2 10
81 Ceramic floor and wall tiles m2 15
82 Acid resistant floor titles m2 20
83 False ceiling m2 20
84 Embedded pipe 40 mm dia. pipe m 6
85 Embedded pipe 100 mm dia. m 12
86 Misc. sanitary fix. (Geyser, urinal, WC, sink, septic tank,
soak pit, etc.)
L.S. 2000
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 1
Chapter 15 - Financial Evaluation
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 2
15. General
Based on estimates, material survey and calculations, the project is likely to cost 22.97 Million
USD. This cost includes preliminary estimates for civil works, electromechanical works, indirect
costs, financing costs including interest during construction, and construction cost escalation.
Provision for initial working capital & capitalized spares is also made in the estimates. The
summary of project cost break up is provided in table below.
Table 15.1: Project cost break up
Sr. No. Cost Components USD Mn
1 Civil Works 11.79
2 E & M 5.76
O/W Transmission Work 0.29
Total cost without IDC & FC 17.55
3 Indirect Cost 0.13
(a) Total direct & indirect cost 17.68
4 Initial Working capital, capitalized spares 0.27
5 Interest during Construction, Financial Charges 1.41
6 Escalation during construction 1.18
7 Contingency 1.24
8 DSRA Cost loaded upfront 1.20
(b) Total 5.29
9 Total (a) + Total (b) 22.97
10 Capacity 10
11 Cost per MW 2.30
12 Total project cost 22.97
Table 15.2: Construction cost drawdown
Year No. Quarter Construction
Cost
Drawdown
without
Financing cost
Financing Cost Promoter
Equity
Senior
Debt
1 Quarter 1 0.21 0.00 0.21 0.00
1 Quarter 2 0.19 0.00 0.19 0.00
1 Quarter 3 1.19 0.00 1.19 0.00
1 Quarter 4 0.57 0.00 0.57 0.00
Year 1 Total 2.15 0.00 2.15 0.00
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 3
Year No. Quarter Construction
Cost
Drawdown
without
Financing cost
Financing Cost Promoter
Equity
Senior
Debt
2 Quarter 1 3.53 0.37 3.53 0.37
2 Quarter 2 3.55 0.05 1.20 2.40
2 Quarter 3 1.96 0.09 0.00 2.05
2 Quarter 4 1.33 0.12 0.00 1.45
Year 2 Total 10.37 0.63 4.74 6.27
3 Quarter 1 2.63 0.15 0.00 2.78
3 Quarter 2 1.05 0.18 0.00 1.24
3 Quarter 3 1.60 0.20 0.00 1.80
3 Quarter 4 3.75 0.24 0.00 3.99
Year 3 Total 9.03 0.78 0.00 9.81
Total Construction 21.56 1.41 6.89 16.08
Table 15.3: Debt Repayment Schedule
Debt amount: USD 16.08 Million
Interest rate: 7% (Per annum)
Year Quarter Debt repaid
during period
Interest
expense for
period
Total Debt
Service
Debt
outstanding at
the end of
period
1 i 0.40 0.28 0.68 15.68
ii 0.40 0.27 0.67 15.28
iii 0.40 0.26 0.67 14.87
iv 0.40 0.26 0.66 14.47
2 i 0.40 0.25 0.65 14.07
ii 0.40 0.24 0.64 13.67
iii 0.40 0.24 0.64 13.27
iv 0.40 0.23 0.63 12.86
3 i 0.40 0.22 0.62 12.46
ii 0.40 0.21 0.62 12.06
iii 0.40 0.21 0.61 11.66
iv 0.40 0.20 0.60 11.26
4 i 0.40 0.19 0.60 10.85
ii 0.40 0.19 0.59 10.45
iii 0.40 0.18 0.58 10.05
iv 0.40 0.17 0.57 9.65
5 i 0.40 0.17 0.57 9.25
ii 0.40 0.16 0.56 8.84
iii 0.40 0.15 0.55 8.44
iv 0.40 0.14 0.55 8.04
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 4
Year Quarter Debt repaid
during period
Interest
expense for
period
Total Debt
Service
Debt
outstanding at
the end of
period
6 i 0.40 0.14 0.54 7.64
ii 0.40 0.13 0.53 7.24
iii 0.40 0.12 0.53 6.83
iv 0.40 0.12 0.52 6.43
7 i 0.40 0.11 0.51 6.03
ii 0.40 0.10 0.50 5.63
iii 0.40 0.09 0.50 5.23
iv 0.40 0.09 0.49 4.82
8 i 0.40 0.08 0.48 4.42
ii 0.40 0.07 0.48 4.02
iii 0.40 0.07 0.47 3.62
iv 0.40 0.06 0.46 3.22
9 i 0.40 0.05 0.45 2.81
ii 0.40 0.05 0.45 2.41
iii 0.40 0.04 0.44 2.01
iv 0.40 0.03 0.43 1.61
10 i 0.40 0.02 0.43 1.21
ii 0.40 0.02 0.42 0.80
iii 0.40 0.01 0.41 0.40
iv 0.40 0.00 0.41 0.00
Key Financial Assumptions
The key assumptions used in the financial analysis are:
1. The debt: equity ratio considered for analysis is 70:30.
2. The interest rate on debt is considered as 7% p.a. The term for repayment of loan is
considered as ten years (post commissioning).
3. The tariff for power is considered as 8 c/kWh, for the life of the project.
4. The initial development period is considered as 12 months, and construction period is
assumed as 24 months.
5. Interest on working capital loan is assumed to be 14% p.a.
6. The capital cost estimates are as per equipment supplier quotes and as per expected costs
for civil works.
7. Power generation is considered as per the 75% dependable year with a 15% overload
when water flow is available.
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 5
8. O&M cost is considered as 250,000 USD per year for the first year of operation. The cost
is escalated at 4% per year for further years.
9. Life of the project assets is considered as 35 years and depreciation is considered at a
uniform rate over the life of the asset.
10. No income tax holiday is assumed and corporate income tax rate of 30% has been
assumed.
11. Carbon credit benefits are assumed to accrue to the project developer at a rate of 5
USD/CER.
The assumptions used in the financial calculations have been tabulated below:
Table 15.4: Capacity Assumptions
Unit
Installed Capacity MW 10
Maximum overrating % 10.0%
Annual availability of plant % 92.0%
Auxiliary consumption % 0.5%
Transformation Losses % 0.5%
Transmission losses to Interconnection point % 0.0%
Table 15.5: Carbon credit assumptions
Unit
Grid intensity for Kenya t CO2/ MWh 0.78
CER Value USD/ CER 5
Table 15.6: Capital Structure
Unit Mn USD
Equity + Quasi Equity 30% 6.89
Debt 70% 16.1
Debt Assumptions
Type
Local
Currency
USD
Facility Amount Mn USD 16.08
Interest rate % per annum 7.0%
Commitment fee % per annum 1.0%
Upfront fee % 2.0%
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 6
Unit Mn USD
Tenor (post construction) Years 10
Moratorium (post construction) Years 0
Table 15.7: Construction Cost Escalation
Unit
Escalation during construction % per annum 3.21%
Monthly escalation factor % per month 0.26%
Timelines Unit Total
Development Period months 12 12
Construction Period months 24 36
Operation Period years 20
Table 15.8: Power potential at 100% availability
MU at 100% availability Base PLF
With
overloading
90% Dependable Year 54.55 62.28% 64.21%
75% Dependable Year 52.95 60.45% 62.18%
50% Dependable Year 62.18 70.98% 75.43%
Selected PLF 62.18%
Table 15.9: Weighted average cost of capital (WACC)
Cost of equity (weighted) 16.00%
Cost of debt 7.00%
WACC for discount rate 8.23%
Table 15.10: Operating Expenditure
Unit
Operating Expenditure
USD Million per
year 0.25
Escalation of O&M % per year 4.00%
Interest on Working capital % per annum 14.00%
Table 15.11: Working capital sizing
Unit
Number of months of O&M Days 30
Number of months of receivables Days 60
Spares as a % of R&M expenses % 15.0%
Rebate on prompt payment of bills % 0.0%
Corporate Income tax rate % 30.0%
Income tax holiday years 0.0
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 7
Carbon credit income
It is estimated that Sagana III HEP (10 MW) will export around 54 million units of energy,
which will result in an emission reduction of ~38,690 tons of CO2, and generation of equivalent
number of CERs. At an assumed selling price of USD 5 per CER, this will result in an income of
around 145,120 USD (assuming 75% share for the project developer).
Table 15.12: Financial Parameters - With & without CER income
Sr. no. Particulars With CERs Without
CERs
1 Equity IRR (%) 16.12% 14.83%
2 Project Payback period Years 9 9
3 Debt service coverage ratio Avg. DSCR 1.54x 1.50x
4 Minimum DSCR Min DSCR 1.41x 1.36x
The CER income will help in increasing the average DSCR to 1.54x form 1.50x (without CER).
Table 15.13: Calculation for carbon credit benefits
Sr. No. Particulars Unit
1 Net Energy exported MWh 49,614
2 Grid carbon intensity factor t CO2 / MWh 0.78
3 Emission Reduction # of CER 38,699
4 Rate USD/CER 5
5 Revenue USD 145,120
Sensitivity Analysis
Sensitivity of the financial results with respect to key input variables has been analyzed in detail
and the results have been included in this report. The various cases (including the base case) that
have been considered for sensitivity analysis are included in Table 15.14 below. The results of
the sensitivity cases are included in Table 15.15. Results indicate that financial parameters like
DSCR have sufficient cushion to absorb negative effects of input variables.
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 8
Table 15.14: Sensitivity Analysis cases
Sr No Case Description
0 Base Case - Base assumptions
1 Case 1 - Increase in Capital Cost Capital Cost increased by 5% above base case assumption
2 Case 2 - Increase in Capital Cost Capital Cost increased by 10% above base case assumption
3 Case 3 - Decrease in Annual Plant Availability Plant availability lower than base case by 5 percentage points
4 Case 4 - Decrease in Annual Plant Availability Plant availability lower than base case by 8 percentage points
5 Case 5 - Increase in O&M cost O&M cost higher than base case by 5%
6 Case 6 - Increase in O&M cost O&M cost higher than base case by 10%
7 Case 7 - Lower Hydrology Hydrology lower than base case by 5%
8 Case 8 - Lower Hydrology Hydrology lower than base case by 10%
9 Case 9 - Drought years Every fifth (5th) year is a drought year
10 Case 10 - Higher inflation Inflation rate 5 percentage points higher than base case
11 Case 11 - Spare [Spare]
12 Case 12 - Lower number of carbon credits Number of Carbon Credits lower than base case by 10 %
13 Case 13 - Lower price for carbon credits Price for Carbon Credits lower than base case by 10 %
14 Case 14 - Increase in construction period Increase in construction period by 12 months
15 Case 15 - Spare [Spare]
16 Case 16 - Combined downside Case A Lower annual availability by 5 percentage points, O&M cost higher
than base case by 5%, Power potential lower than base case by 5
percentage points, Increase in construction period by 12 months
17 Case 17 - Combined downside Case B Capital Cost increased by 5% above base case assumption, Hydrology
lower than base case by 10%
18 Case 18 - Combined downside Case C Lower annual availability by 5 percentage points, Increase in
construction period by 12 months
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 9
Table 15.15: Results of Sensitivity analysis
Sr.
No
Case Run Project
Cost,
Million
USD
Equity,
Million
USD
Senior
Debt,
Million
USD
Generation,
MU
Levelized
cost, US
c/KWh
Min.
DSCR
Senior
Debt
Avg.
DSCR
Senior
Debt
0 Base Case - No Change 22.97 6.9 16.1 49.61 5.08 1.41 1.54
1 Case 1 - Increase in Capital Cost by 5 % 24.05 7.9 16.2 49.61 5.04 1.41 1.55
2 Case 2 - Increase in Capital Cost by 10 % 25.14 9.0 16.2 49.61 4.98 1.41 1.57
3 Case 3 - Decrease in Annual Plant
Availability by 5 percentage points 22.97 6.9 16.1 46.92 5.20 1.33 1.48
4 Case 4 - Decrease in Annual Plant
Availability by 8 percentage points 22.97 6.9 16.1 45.30 5.28 1.28 1.44
5 Case 5 - Increase in Base operating cost by 5
% 22.97 6.9 16.1 49.61 5.11 1.41 1.53
6 Case 6 - Increase in Base operating cost by
10 % 22.97 6.9 16.1 49.61 5.13 1.40 1.53
7 Case 7 - Lower Hydrology by 5 % 22.97 6.9 16.1 47.13 5.19 1.34 1.48
8 Case 8 - Lower Hydrology by 10 % 22.97 6.9 16.1 44.65 5.30 1.26 1.43
9 Case 9 - Bad year every five years (10 % less
water) 22.97 6.9 16.1 49.61 5.17 1.28 1.49
10 Case 10 - Higher inflation by 5 % points 22.97 6.9 16.1 49.61 5.11 1.41 1.53
11 Case 11 - [Spare} 22.97 6.9 16.1 49.61 5.08 1.41 1.54
12 Case 12 - Lower number of carbon credits by
10 % 22.97 6.9 16.1 49.61 5.07 1.41 1.53
13 Case 13 - Lower price for carbon credits by
10 % 22.97 6.9 16.1 49.61 5.07 1.41 1.53
14 Case 14 - Increase in construction period by
12 months 24.10 7.9 16.2 49.61 5.05 1.40 1.55
15 Case 15 - Spare 22.97 6.9 16.1 49.61 5.08 1.41 1.54
16 Case 16 - Combined downside Case A 24.10 7.9 16.2 47.13 5.17 1.32 1.49
17 Case 17 - Combined downside Case B 24.05 7.9 16.2 44.65 5.21 1.26 1.46
18 Case 18 - Combined downside Case C 24.10 7.9 16.2 46.92 5.15 1.32 1.50
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 10
Annexure 1 Financial Statements
Balance Sheet
Profit & Loss Account
Cash Flow Statement
Cost of Power Generation
Financial Ratios
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 11
Balance Sheet
Operation Year Ending 1 2 3 4 5 6 7 8 9 10
Current Assets
Cash Balance 0.28 - - - - - - - - 0.24
DSRA 0.66 0.63 0.60 0.57 0.55 0.52 0.49 0.46 0.43 -
Accounts receivable 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34
Total 1.28 0.97 0.94 0.91 0.88 0.86 0.83 0.80 0.77 0.57
Fixed Assets 19.54 18.72 17.90 17.08 16.26 15.44 14.62 13.81 12.99 12.17
Capitalized financing costs 1.31 1.21 1.12 1.02 0.92 0.82 0.72 0.62 0.52 0.42
Total 20.85 19.93 19.02 18.10 17.18 16.26 15.34 14.43 13.51 12.59
Work In Progress - - - - - - - - - -
Total Assets 22.13 20.90 19.96 19.01 18.06 17.12 16.17 15.22 14.28 13.17
Current Liabilities
Accounts payable 0.05 0.05 0.05 0.05 0.06 0.06 0.06 0.06 0.07 0.07
Taxes payable - - - - - - - - - -
Total 0.05 0.05 0.05 0.05 0.06 0.06 0.06 0.06 0.07 0.07
Long term Liabilities 14.47 12.86 11.26 9.65 8.04 6.43 4.82 3.22 1.61 -
Working Capital Facility 0.29 0.29 0.29 0.28 0.28 0.28 0.28 0.28 0.27 0.27
Shareholders' Funds
Promoter Equity 6.89 6.89 6.89 6.89 6.89 6.89 6.89 6.89 6.89 6.89
Retained Earnings 0.43 0.81 1.47 2.14 2.80 3.46 4.12 4.78 5.44 5.94
Total 7.32 7.70 8.36 9.03 9.69 10.35 11.01 11.67 12.33 12.83
Total Liabilities 22.13 20.90 19.96 19.01 18.06 17.12 16.17 15.22 14.28 13.17
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 12
Balance Sheet
Operation Year Ending 11 12 13 14 15 16 17 18 19 20
Current Assets
Cash Balance 1.08 1.91 2.75 3.59 4.36 5.10 5.84 6.58 7.32 -
DSRA - - - - - - - - - -
Accounts receivable 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34
Total 1.41 2.25 3.09 3.93 4.70 5.44 6.18 6.92 7.66 0.34
Fixed Assets 11.43 10.69 9.95 9.21 8.47 7.73 6.99 6.25 5.51 4.77
Capitalized financing costs 0.32 0.23 0.13 0.03 - - - - - -
Total 11.75 10.91 10.07 9.24 8.47 7.73 6.99 6.25 5.51 4.77
Work In Progress - - - - - - - - - -
Total Assets 13.17 13.17 13.17 13.17 13.17 13.17 13.17 13.17 13.17 5.10
Current Liabilities
Accounts payable 0.07 0.07 0.08 0.08 0.08 0.09 0.09 0.09 0.10 0.10
Taxes payable - - - - - - - - - -
Total 0.07 0.07 0.08 0.08 0.08 0.09 0.09 0.09 0.10 0.10
Long term Liabilities - - - - - - - - - -
Working Capital Facility 0.27 0.26 0.26 0.26 0.26 0.25 0.25 0.25 0.24 -
Shareholders' Funds
Promoter Equity 6.89 6.89 6.89 6.89 6.89 6.89 6.89 6.89 6.89 6.89
Retained Earnings 5.94 5.94 5.94 5.94 5.94 5.94 5.94 5.94 5.94 (1.89)
Total 12.83 12.83 12.83 12.83 12.83 12.83 12.83 12.83 12.83 5.00
Total Liabilities 13.17 13.17 13.17 13.17 13.17 13.17 13.17 13.17 13.17 5.10
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 13
Profit & Loss Statement
Operational Year 1 2 3 4 5 6 7 8 9 10
Revenue from power sales 3.97 3.97 3.98 3.97 3.97 3.97 3.98 3.97 3.97 3.97
Revenue from CDM 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
Total Revenue 4.11 4.11 4.13 4.11 4.11 4.11 4.13 4.11 4.11 4.11
Total O&M Cost 0.29 0.30 0.31 0.32 0.34 0.35 0.36 0.38 0.39 0.41
EBITDA 3.83 3.82 3.82 3.79 3.78 3.77 3.76 3.74 3.72 3.71
EBITDA as a % of Revenue 93% 93% 92% 92% 92% 92% 91% 91% 90% 90%
Depreciation expense 0.82 0.82 0.82 0.82 0.82 0.82 0.82 0.82 0.82 0.82
Amortization expense 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
Depreciation + Amortization 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92
EBIT 2.91 2.90 2.90 2.87 2.86 2.85 2.84 2.82 2.80 2.79
Interest expense (Senior-Debt) 1.10 0.98 0.87 0.76 0.64 0.53 0.41 0.30 0.19 0.07
Interest payments on working capital 0.03 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Total Interest paid 1.13 1.03 0.91 0.80 0.68 0.57 0.45 0.34 0.22 0.11
Profit before Tax 1.78 1.87 1.98 2.08 2.18 2.28 2.39 2.48 2.58 2.68
Tax - - - 0.25 0.44 0.54 0.63 0.71 0.79 0.85
Profit after tax 1.78 1.87 1.98 1.83 1.74 1.74 1.76 1.77 1.79 1.83
Profit margin 43% 46% 48% 44% 42% 42% 43% 43% 44% 44%
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 14
Profit & Loss Statement
Operational Year 11 12 13 14 15 16 17 18 19 20
Revenue from power sales 3.98 3.97 3.97 3.97 3.98 3.97 3.97 3.97 3.98 3.97
Revenue from CDM 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
Total Revenue 4.13 4.11 4.11 4.11 4.13 4.11 4.11 4.11 4.13 4.11
Total O&M Cost 0.43 0.44 0.46 0.48 0.50 0.52 0.54 0.56 0.59 0.61
EBITDA 3.70 3.67 3.65 3.63 3.63 3.59 3.57 3.55 3.54 3.51
EBITDA as a % of Revenue 90% 89% 89% 88% 88% 87% 87% 86% 86% 85%
Depreciation expense 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74
Amortization expense 0.10 0.10 0.10 0.10 0.03 - - - - -
Depreciation + Amortization 0.84 0.84 0.84 0.84 0.77 0.74 0.74 0.74 0.74 0.74
EBIT 2.86 2.83 2.81 2.80 2.86 2.85 2.83 2.81 2.80 2.76
Interest expense (Senior-Debt) - - - - - - - - - -
Interest payments on working capital 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.03 0.03
Total Interest paid 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.03 0.03
Profit before Tax 2.82 2.79 2.78 2.76 2.82 2.82 2.80 2.78 2.77 2.73
Tax 0.90 0.92 0.94 0.95 0.97 0.97 0.98 0.99 0.99 0.99
Profit after tax 1.92 1.87 1.84 1.80 1.85 1.84 1.82 1.79 1.77 1.74
Profit margin 47% 46% 45% 44% 45% 45% 44% 44% 43% 42%
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 15
Cash Flow Statement
Operational Year 1 2 3 4 5 6 7 8 9 10
Cash beginning balance 0.44 0.72 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44
EBIDTA 3.83 3.82 3.82 3.79 3.78 3.77 3.76 3.74 3.72 3.71
Tax paid - - - (0.25) (0.44) (0.54) (0.63) (0.71) (0.79) (0.85)
Total 4.27 4.54 4.26 3.99 3.78 3.67 3.57 3.47 3.38 3.30
Net Working Capital
Working capital Revenue side 1.35 1.35 1.35 1.35 1.35 1.35 1.35 1.35 1.35 1.35
Working capital cost side 0.19 0.20 0.20 0.21 0.22 0.23 0.24 0.25 0.26 0.27
Net Working Capital 1.16 1.16 1.15 1.14 1.13 1.12 1.11 1.10 1.09 1.08
Change in Working Capital (0.29) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Working Capital financing 0.29 (0.00) (0.00) (0.00) (0.00) (0.00) (0.00) (0.00) (0.00) (0.00)
Debt repayment
Interest on Senior Debt 1.10 0.98 0.87 0.76 0.64 0.53 0.41 0.30 0.19 0.07
Interest on working Capital 0.03 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Actual Principal repayment (Senior Debt) 1.61 1.61 1.61 1.61 1.61 1.61 1.61 1.61 1.61 1.61
Total Debt Service (Senior Debt) 2.71 2.59 2.48 2.36 2.25 2.14 2.02 1.91 1.79 1.68
Cash flow after debt repayment 1.53 1.91 1.74 1.58 1.49 1.49 1.51 1.52 1.55 1.58
Cash flow (in to) out of DSRA 0.54 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.43
Cash available for equity holders 2.07 1.93 1.77 1.61 1.52 1.52 1.54 1.55 1.58 2.01
Dividend paid 1.35 1.49 1.32 1.17 1.08 1.08 1.09 1.11 1.13 1.33
Cash ending balance 0.72 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.68
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 16
Cash Flow Statement
Operational Year 11 12 13 14 15 16 17 18 19 20
Cash beginning balance 0.68 1.52 2.36 3.20 4.04 4.80 5.54 6.29 7.03 7.77
EBIDTA 3.70 3.67 3.65 3.63 3.63 3.59 3.57 3.55 3.54 3.51
Tax paid (0.90) (0.92) (0.94) (0.95) (0.97) (0.97) (0.98) (0.99) (0.99) (0.99)
Total 3.48 4.27 5.07 5.88 6.69 7.42 8.14 8.85 9.57 10.28
Net Working Capital
Working capital Revenue side 1.35 1.35 1.35 1.35 1.35 1.35 1.35 1.35 1.35 1.35
Working capital cost side 0.28 0.29 0.30 0.32 0.33 0.34 0.36 0.37 0.38 0.40
Net Working Capital 1.07 1.06 1.05 1.04 1.03 1.01 1.00 0.98 0.97 0.95
Change in Working Capital 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Working Capital financing (0.00) (0.00) (0.00) (0.00) (0.00) (0.00) (0.00) (0.00) (0.00) (0.24)
Debt repayment
Interest on Senior Debt - - - - - - - - - -
Interest on working Capital 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.03 0.03
Actual Principal repayment (Senior Debt) - - - - - - - - - -
Total Debt Service (Senior Debt) - - - - - - - - - -
Cash flow after debt repayment 3.44 4.23 5.03 5.84 6.66 7.39 8.10 8.82 9.54 10.01
Cash flow (in to) out of DSRA - - - - - - - - - -
Cash available for equity holders 3.44 4.23 5.03 5.84 6.66 7.39 8.10 8.82 9.54 10.01
Dividend paid 1.92 1.87 1.84 1.80 1.85 1.84 1.82 1.79 1.77 9.57
Cash ending balance 1.52 2.36 3.20 4.04 4.80 5.54 6.29 7.03 7.77 0.44
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 17
Cost of Power Generation
Op. year 1 2 3 4 5 6 7 8 9 10
Cost of Power in US c/KWh
O&M Cost
0.60 0.62 0.65 0.68 0.70 0.73 0.76 0.79 0.82 0.60
Interest
2.07 1.84 1.61 1.37 1.14 0.91 0.68 0.45 0.22 2.07
Tax
- - 0.50 0.89 1.09 1.28 1.44 1.58 1.72 -
Principal
3.24 3.23 3.24 3.24 3.24 3.23 3.24 3.24 3.24 3.24
Total
5.91 5.69 6.00 6.18 6.18 6.15 6.12 6.07 6.00 5.91
Levelized Cost over 20 years in US
c/KWh 5.08
Discount rate for levelization 8.23%
Period of levelization 20.00
Contribution US c/ KWh
2.38 2.60 2.30 2.11 2.11 2.14 2.17 2.22 2.29 2.38
Op. year 11 12 13 14 15 16 17 18 19 20
Cost of Power in US c/KWh
O&M Cost
0.86 0.89 0.93 0.97 1.00 1.05 1.09 1.13 1.18 1.23
Interest
0.08 0.08 0.08 0.07 0.07 0.07 0.07 0.07 0.07 0.07
Tax
1.82 1.86 1.90 1.92 1.95 1.97 1.98 1.99 1.99 1.99
Principal
- - - - - - - - - -
Total
2.75 2.83 2.90 2.97 3.03 3.08 3.14 3.19 3.24 3.29
Levelized Cost over 20 years in US
c/KWh 5.08
Discount rate for levelization 8.23%
Period of levelization 20.00
Contribution US c/ KWh
5.54 5.46 5.39 5.33 5.27 5.21 5.15 5.10 5.05 5.00
Detailed Project Report Sagana III HEP Chapter 15 - Financial Evaluation
Chapter 15 - 18
Debt Service Coverage ratio
Op. year 1 2 3 4 5 6 7 8 9 10
EBITDA MM USD 3.82 3.82 3.79 3.78 3.77 3.76 3.74 3.72 3.71 3.82
EBITDA Margin % 92.77% 92.49% 92.17% 91.85% 91.52% 91.20% 90.82% 90.44% 90.06% 92.77%
Tax MM USD - - (0.25) (0.44) (0.54) (0.63) (0.71) (0.79) (0.85) -
Net Profit MM USD 1.87 1.98 1.83 1.74 1.74 1.76 1.77 1.79 1.83 1.87
Total Principal
Payment MM USD 1.61 1.61 1.61 1.61 1.61 1.61 1.61 1.61 1.61 1.61
Interest on Senior-debt MM USD 0.98 0.87 0.76 0.64 0.53 0.41 0.30 0.19 0.07 0.98
Total Debt service
(Senior-debt) MM USD 2.59 2.48 2.36 2.25 2.14 2.02 1.91 1.79 1.68 2.59
DSCR (Senior Debt)
1.47x 1.54x 1.50x 1.48x 1.51x 1.55x 1.59x 1.64x 1.70x 1.47x
DSCR (Average) 1.54x
DSCR (Min) 1.41x
Detailed Project Report Sagana III HEP Appendix I - Photographs
Appendix I - 1
Appendix I- Photographs
Detailed Project Report Sagana III HEP Appendix I - Photographs
Appendix I - 2
Site for intake (Diversion Structure)
Slope for Water Conductor (channel)
Location for
Diversion
Structure on the
right bank
Slope for Water conductor channel
Detailed Project Report Sagana III HEP Appendix I - Photographs
Appendix I - 3
Slope for proposed Penstock
Rocky strata near proposed Power House
Penstock Alignment on right bank
Rocky strata just before Power house (on right bank)
Detailed Project Report Sagana III HEP Appendix I - Photographs
Appendix I - 4
Bench on Right bank for Power house
Road connectivity to power house location
Location of Power house bench on Right Bank
Detailed Project Report Sagana III HEP Appendix I - Photographs
Appendix I - 5
Image 1: Project area on Toposheet (135/1)
Project Area Sagana III HEP (10 MW)
Detailed Project Report Sagana III HEP Appendix II - Drawings
Appendix II - 1
Appendix II- Drawings