75
 Configuration Document SAP PP-PI Page 1 of 75 Version 1.0 Claris Lifesciences Ltd. mySAP ERP ECC 6.0 Implementation PP –PI Configuration Documentation
Transcript
  • Configuration Document SAP PP-PI Page 1 of 75 Version 1.0

    Claris Lifesciences Ltd.

    mySAP ERP ECC 6.0 Implementation

    PP PI Configuration Documentation

  • Configuration Document SAP PP-PI Page 2 of 75 Version 1.0

    Table Of Contents

    1. PURPOSE OF THE DOCUMENT............................................................................................................ 5 1.1 Purpose ................................................................................................................................................ 5

    2. PRODUCTION PLANNING...................................................................................................................... 6 2.1 Define MRP Controller ........................................................................................................................ 6 2.2 MRP Type ............................................................................................................................................ 7

    2.3 Lot Size................................................................................................................................................. 8

    2.4 Defining MRP Groups ......................................................................................................................... 9 2.5 Defining Special Procurement Type ...................................................................................................10 2.6 Define Scope of Planning for Total Planning .....................................................................................11 2.7 Scheduling Parameters .......................................................................................................................12

    2.9 Define Scheduling Margin key ............................................................................................................13 2.10 Selection ID for BOM .........................................................................................................................14 2.11 Defining BOM Explosion ....................................................................................................................15 2.12 Define Number Ranges for Planned Independent Requirements ........................................................16 2.13 Define Version Numbers .....................................................................................................................16 2.14 Defining Strategy for MRP .................................................................................................................18 2.15 Define Strategy Group ........................................................................................................................18 2.16 Define Planning Horizon ....................................................................................................................19 2.17 Defining Availability of Stock .............................................................................................................20 2.18 Defining Rescheduling Check for Plant and MRP Group...................................................................21 2.19 Define Number ranges for Planning Run............................................................................................22 2.20 Planning File Entry for Termination ..................................................................................................23 2.21 Maintain Rounding Profile .................................................................................................................24 2.22 Define Storage location MRP per plant ..............................................................................................25 2.23 Defining Parallel Processing for MRP ...............................................................................................26 2.24 Assigning MRP Checking Rule ...........................................................................................................27

    2.25 BOM Usage.........................................................................................................................................28

    2.26 Defining Item Categories ....................................................................................................................29 2.27 Define Reasons for Variances.............................................................................................................29 2.28 Define Number ranges for Manual Processing...................................................................................30 2.29 Activating Requirements Planning......................................................................................................31

    2.30 Defining Item Numbers of Order Types ..............................................................................................32 2.31 Defining Conversion Planned Order to Process Order......................................................................33

    3. PRODUCTION PLANNING FOR PROCESS INDUSTRIES...............................................................35 3.1 Define Resource Category ..................................................................................................................35 3.2 Defining Person Responsible for Work Centre ...................................................................................36 3.3 Standard Value Keys...........................................................................................................................37

    3.4 Defining Formula Parameters for Resources .....................................................................................38

  • Configuration Document SAP PP-PI Page 3 of 75 Version 1.0

    3.5 Defining Formula for Resources.........................................................................................................39 3.6 Task List Usage...................................................................................................................................40

    3.7 Define Capacity Planner.....................................................................................................................41 3.8 Define Number Ranges for Master Recipe..........................................................................................42 3.9 Recipe Status.......................................................................................................................................43

    3.10 Recipe Usages.....................................................................................................................................43

    3.11 Define Planner Groups .......................................................................................................................44 3.12 Control key for Master Recipe ............................................................................................................44 3.13 Define Capacity Categories ................................................................................................................45 3.14 BOM Status .........................................................................................................................................46

    3.15 Process Order Type ............................................................................................................................47

    3.16 Number Ranges for Process Order .....................................................................................................47 3.17 Define Production Scheduler ..............................................................................................................48 3.18 Define Production Scheduler Profile ..................................................................................................49 3.19 Scope of Check....................................................................................................................................50 3.20 Define Checking Control ....................................................................................................................51 3.21 Define Scheduling parameters for a process order.............................................................................52 3.22 Defining Parameters for Order Confirmation ....................................................................................53 3.23 Assigning Material Types to Task List ................................................................................................54

    3.24 Define Material Types Allowed for BOM Header...............................................................................55 3.25 Defining Order Type-Dependent Parameters .....................................................................................56 3.26 Assigning Process Instructions to Control Recipe Destinations .........................................................57

    4. BATCH MANAGEMENT.........................................................................................................................59 4.1 Activate Document Management for Batches .....................................................................................59 4.2 Defining Batch Level...........................................................................................................................59 4.3 Activating Automatic Batch Number Assignment ...............................................................................59

    4.4 Maintain Internal Batch Number Assignment Range..........................................................................60

    4.5 Define Batch Creation for Production Order / Process Order...........................................................60 4.6 Define Process Order Condition Tables .............................................................................................61 4.7 Define Process Order Access Sequences ............................................................................................61 4.8 Assign Search Procedure to Process Order and Activate Check........................................................62

    4.9 Activating batch-specific Unit of Measures ........................................................................................63 4.10 Edit Batch-Specific Material Unit of Measure....................................................................................63 4.11 Define Calculation of Proportion Quantity from Base Quantity ........................................................64 4.12 Maintain Period Indicator ..................................................................................................................64

    4.13 Activating Expiration Date View per Plant.........................................................................................65

    4.14 Define Process Order Strategy Types .................................................................................................65 4.15 Define Search Procedure to Process Order........................................................................................66 4.16 Activating Batch Derivation................................................................................................................67

  • Configuration Document SAP PP-PI Page 4 of 75 Version 1.0

    4.17 Define Derivation Events ....................................................................................................................67

    5. DOCUMENT MANAGEMENT ...............................................................................................................68 5.1 Define Number Ranges for Document Numbers .................................................................................68 5.2 Define Document Types ......................................................................................................................69 5.3 Define Data Carrier............................................................................................................................70

    6. CLASSIFICATION SYSTEM ..................................................................................................................72 6.1 Define Characteristics Groups ...........................................................................................................72 6.2 Define Characteristics Status..............................................................................................................73

    7. OTHER SETTINGS...................................................................................................................................74 7.1 Check Units of Measurement ..............................................................................................................74

  • Configuration Document SAP PP-PI Page 5 of 75 Version 1.0

    1. PURPOSE OF THE DOCUMENT

    1.1 Purpose This document captures the required configurations details in SAP system to meet the business requirements as envisaged in the Design Stage (Business Blue Print Stage) for Project, Claris SAP Implementation Production Planning Module. The configuration steps have mappings to corresponding menu path to where the configuration has been done in the IMG (Implementation Guide).

    The documentation provides visibility to all project teams members on the proposed system settings and changes. It is an important document for all future references in terms of system configuration. All future changes or updates to the system should be done based on this and the documentation updated accordingly.

    This volume contains details on the configuration requirements for the Production Planning module for Claris Life Sciences pertaining to Master Data

    This document should be read in conjunction with:

    1. Process definition document

    2. Key Data Structures

  • Configuration Document SAP PP-PI Page 6 of 75 Version 1.0

    2. PRODUCTION PLANNING

    2.1 Define MRP Controller

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Planning Check MRP Types Out Overall Maintenance of Plant Parameters MRP Controller

    Transaction Code OPPQ Configuration

    Description The MRP controller is a person or a group of persons responsible for monitoring material availability. MRP controller can be used to select the planning results per MRP controller. Every material that is relevant to the planning run must be assigned to an MRP controller in the material master record.

    For all the C&Fs and CAs agents treated as Plants, the MRP Controller would be Z01. For Manufacturing Plants, it is detailed below. For all other plants, 001 MRP controller is named as General

    Plant MRP Controller Description 101 RM Injectables 102 PPM Injectables 103 SPM Injectables 104 TPM Injectables 105 Production Inj. 106 Packing Inj. 107 Engineering Inj. 108 Lab Mat.Injectable 109 HK & Admin

    1001

    110 Captive Consumptn 101 RM Infusion 102 PPM Infusion 103 SPM Infusion 104 TPM Infusion 105 Production Inf. 106 Packing Inf. 107 Engineering Inf. 108 Lab Mat.Infusion 109 HK & Admin

    1002

    110 Captive Consumptn 101 RM API 102 PPM API 103 SPM API 104 TPM API 105 Production API 106 Packing API 107 Engineering API 108 Lab Mat. API

    1003

    109 HK & Admin 1004 101 Utility for Clarion

  • Configuration Document SAP PP-PI Page 7 of 75 Version 1.0

    2.2 MRP Type

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Master Data Check MRP Types

    Transaction Code SPRO Configuration

    Description MRP type to assign the procedure to be used to plan a material and to control, which MRP parameters can be, maintained for the material in the material master record. MRP type is assigned in the material master record The following MRP Types are used for Claris

    MRP type Description PD Normal MRP VB Manual Reorder Level Planning ND No Planning V1 Manual Reorder Level with External Requirements. M0 Master Production Scheduling

  • Configuration Document SAP PP-PI Page 8 of 75 Version 1.0

    2.3 Lot Size

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Planning Lot-Size Calculation Check Lot-Sizing procedure

    Transaction Code OMI4 Configuration

    Description Lot-sizing procedures serve to calculate the procurement quantities, that is, the purchase order and production quantities With the lot-sizing procedure we define how the order quantities are determined. A lot size defining the lot-sizing procedure is assigned to every material master record applicable to materials planning. The lot size is defined in Customizing by the combination of the lot-sizing procedure and the lot-sizing indicator.

    Lot Size Key Description EX Lot for Lot Order Quantity FX Fixed Order Quantity WB Weekly Lot Size MB Montly Lot Size

  • Configuration Document SAP PP-PI Page 9 of 75 Version 1.0

    2.4 Defining MRP Groups

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Materials Requirements Planning MRP Groups Carry Out Overall Maintenance of MRP Groups

    Transaction Code OPPR Configuration

    Description In this step, we determine the MRP groups and we maintain the control parameters from a particular point of view. The MRP group groups certain materials together from the material requirements planning point of view to allocate them special control parameters for planning. These control parameters include the strategy group, the planning horizon and the creation indicator for the planning run selection of the Process Order type automatically.

    Plant MRP Group Description 1001 Demand for Domestic in

    Injectable 1002 Demand for Exports in

    Injectable 1003 In-house Production in

    Injectable 1004 In-house Packing in Injectable

    1001

    1005 External Procurement 1001 Demand for Domestic in

    Infusion 1002

    1002 Demand for Exports in Infusion

  • Configuration Document SAP PP-PI Page 10 of 75 Version 1.0

    1003 In-house Production in Infusion 1004 In-house Packing in Infusion 1005 External Procurement

    2000 2001 Traded Products 2002 Loan Licence

    2.5 Defining Special Procurement Type

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Master Data Define Special Procurement Type

    Transaction Code SPRO

    Configuration Description

    In this step, we define the special procurement keys which as well as the procurement type control the procurement and storage of a material.

    The special procurement type always refers to a procurement type.

    We can , also define how the system treats the material as a component during the BOM explosion using control indicators.

    Example 1 (special procurement keys without other indicators) The procurement type "external procurement" is defined for raw materials. If a material is to be procured via a consignment order, you assign the special procurement type "consignment" to the material in the material master record.

    Example 2 (special procurement keys with other indicators) A material appears in several BOMs as a component because it is assembled in finished products in in-house production. It is procured from an alternative plant if no dependent requirements exist for the material.

    The Special Procurement Keys are defined for the Manufacturing Plants and it has to be extended to the C&Fs, which are defined as plants

    Plant Special Procurement Key Description 1001 ZB Stock transfer (Proc from 1002) 1001 ZC Stock transfer (Proc from 1003) 1002 ZA Stock transfer (Proc from 1001) 1002 ZC Stock transfer (Proc from 1003) 1003 ZA Stock transfer (Proc from 1001) 1003 ZB Stock transfer (Proc from 1002) 4500 ZD Stock transfer (Proc. From 4500) 2000 WA Stock transfer (Proc. From 2000)

  • Configuration Document SAP PP-PI Page 11 of 75 Version 1.0

    2.6 Define Scope of Planning for Total Planning

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Materials Requirement Planning Planning Define Scope of Planning for total planning

    Transaction Code OM0E Configuration

    Description In this IMG activity, we define the scope of planning and the sequence of the organizational units to be planned. These are either plants or, if we have converted MRP to MRP at MRP area level, the MRP areas that we plan together in a total planning run. We enter the key for the planning run in the initial screen of the total planning run. The total planning run then carries out MRP for the plants or MRP areas defined in the scope of planning. we can enter as many plants or MRP areas as we like in the scope of planning. We can also only enter one MRP area. MRP is then only carried out for one MRP area. If we have activated MRP for MRP areas, when we enter a plant, this includes all MRP areas of this plant. The Following Scope of planning has been defined for Claris Planning Scope Description CFWH C & Fs and Wareshouse MFG Mfg plants MRP Material Requirement Planning

  • Configuration Document SAP PP-PI Page 12 of 75 Version 1.0

    2.7 Scheduling Parameters

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Capacity Requirements Planning Operations Scheduling Define scheduling parameters for planned orders

    Transaction Code OPU5 Configuration

    Description In this step we define the parameters for scheduling planned orders for each plant, order type and production scheduler. This comprises the following settings:

    Scheduling levels (detailed-, production-rate and rough-cut scheduling) Date adjustment when deadlines are exceeded Scheduling control for detailed scheduling Reduction Scheduling parameters for planning scenarios for long-term planning/simulation

    Scheduling Parameters for the Planned Orders are same for all the Plants as defined below:

    Parameters Values Detailed Scheduling Horizon

    90

    Rough Cut Scheduling Horizon

    90

    Scheduling Levels Via Detailed Scheduling Adjust Dates Adjust basic dates, adjust dep reqmts to operation date For Capacity Scheduling

    Always basic dates, dep reqmts to operation dates

    Scheduling type Backwards

  • Configuration Document SAP PP-PI Page 13 of 75 Version 1.0

    2.9 Define Scheduling Margin key

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Shop Floor control Operations Scheduling Define Scheduling Margin key

    Transaction Code SPRO Configuration

    Description Scheduling margin key specify time floats for scheduling as well as the release period for order release. The following floats are defined: Float before production: This is the time between the order start date and the scheduled start date. Float after production: This is the time between the order finish date and the scheduled finish date.

    The release date is calculated by adding the release period. The order release is carried out on this date.

    The opening period represents the number of workdays that are subtracted from the order start date in order to determine the order creation date. The MRP controller uses this time as a float for converting planned orders into process orders.

    The release period represents the number of workdays that are subtracted from the order start date in order to determine the process order release. The release period is only relevant for process order management.

  • Configuration Document SAP PP-PI Page 14 of 75 Version 1.0

    The following SMK are maintained for plants 1001, 1002 and 2000. For C&Fs, C&As treated as plants, the SMK are 000

    Plant SMK Opening per Float Before Prd Float After Prd Release Peri1001 Z00 000 000 000 000

    Z01 001 000 000 000 Z02 000 001 001 000 Z03 000 001 002 000 Z04 000 001 003 000 Z05 000 001 004 000

    1002 Z00 000 000 000 000 Z01 001 000 000 000

    Z02 000 001 001 000 Z03 000 001 002 000 Z04 000 001 003 000 Z05 000 001 004 000

    2000 Z01 003 000 000 000

    2.10 Selection ID for BOM

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements PlanningPlanning BOM Explosion Define BOM Selection

    Transaction Code SPRO Configuration In this step, we specify the priority with which a BOM usage or routing usage is

  • Configuration Document SAP PP-PI Page 15 of 75 Version 1.0

    Description selected during the planning run. Here, a sequence is usually determined which is used to select a valid BOM via the criterion "Usage".

    For all the plants the selection id is set as 01

    2.11 Defining BOM Explosion

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements PlanningPlanning BOM Explosion Define BOM Explosion Control

    Transaction Code OMIW Configuration

    Description In this step, we specify the priority with which a BOM usage or routing usage is selected during the planning run. Here, a sequence is usually determined which is used to select a valid BOM via the criterion "Usage".

    For all the plants the Control Parameters for BOM Explosion has been set as (BOM explosion number/order start date)

  • Configuration Document SAP PP-PI Page 16 of 75 Version 1.0

    2.12 Define Number Ranges for Planned Independent Requirements

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Production Planning Demand Management Define number ranges for planned independent requirements

    Transaction Code OMID Configuration

    Description In demand management, number ranges are only used internally within the system for counting per planned independent requirements item. The number of the planned independent requirements is not displayed.

    The Number Range is preset: 000000000001 to 9999999999999

    2.13 Define Version Numbers

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Production Planning Demand Management Planned Independent requirements Define Version Numbers

  • Configuration Document SAP PP-PI Page 17 of 75 Version 1.0

    Transaction Code OMP2 Configuration

    Description

    In this step, we define versions to be able to: differentiate between different planned independent requirements indicate the transfer of requirements from previous planning levels (for

    example, the sales plan from SOP) simulate requirements planning in long-term planning

    We have maintained versions for all the twelve months of the year and for requirement plan Requirement Plan Description

    01 January version 02 February version 03 March version 04 April version 05 May version 06 June version 07 July version 08 August version 09 September version 10 October version 11 November version 12 December version

  • Configuration Document SAP PP-PI Page 18 of 75 Version 1.0

    2.14 Defining Strategy for MRP

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Master Data Independents Requirements Parameters Planning Strategy Define Strategy

    Transaction Code SPRO Configuration

    Description The planning strategy represents a procedure to be used for planning a material. It is defined by: a requirements type from demand management, or a requirements type from sales order maintenance, or a combination of both that makes sense The following strategy is being used

    Strategy Description 10 Make to stock, used for Domestic Requirement PIR 11 Gross demand from C&F 40 Planning with final Assembly, used for International

    Sales order

    2.15 Define Strategy Group

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Master Data Independents Requirements Parameters Planning Strategy Define Strategy Group

    Transaction Code SPRO Configuration

    Description The planning strategy represents an appropriate procedure to be used for planning and produced a material.

    The Strategy Group available in standard SAP system will be used. To be Specific the below mentioned strategy will be used in CLARIS For all the Non-repeat export products and domestic products with unique Secondary packing material requirements, PM requirements the Strategy

  • Configuration Document SAP PP-PI Page 19 of 75 Version 1.0

    group will be maintained as 40, for other materials at Manufacturing plants the strategy group will be maintained as 10, warehouse & at C&Fs strategy group is 11

    Strategy Description 10 Make to stock, used for Domestic Requirement PIR 11 Gross demand from C&F 40 Planning with final Assembly, used for International

    Sales order

    2.16 Define Planning Horizon

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Planning MRP Calculation Define Planning Horizon

    Transaction Code OMDX Configuration

    Description The planning horizon is the period that is set for the "net change planning in the planning horizon." For this type of net change planning, only those materials are planned in the planning run that have a change relevant to MRP within the period (in work days).

    The length of the planning horizon should at least include the following: Period in which customer orders enter Delivery times Complete material processing time

    The Planning Horizon for all the Plants, C&Fs, C&As defined as Plants are maintained as 135 Work Days (Current Month 45 days + 3 Months - 90

  • Configuration Document SAP PP-PI Page 20 of 75 Version 1.0

    Working days)

    2.17 Defining Availability of Stock

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Planning MRP Calculation Stocks Define Availability of Stock in Transfer/Blocked Stock/Restricted Stock

    Transaction Code SPRO Configuration

    Description In this step, we define whether stock in transfer (plant to plant) and/or blocked stock are included as well as restricted-use stock as available stock in the net requirements calculation. Stock in transfer is the quantity that has already been withdrawn from the issuing plant (movement type, remove from storage - plant) but that has not yet been received by the receiving plant (movement type, place in storage - plant) The system treats this stock as stock in transfer (plant to plant) for the receiving plant until the material is actually received and posted.

    The Stocks, which will participate in the Net requirement Calculation, are Unrestricted Stock and Stock in Transit for all the plants and C&F defined as plants For all the plants excepting clarion campus, Nourish, PKD, ICD and Head Office, blocked stocks are not included in the MRP calculation for Stocks.

  • Configuration Document SAP PP-PI Page 21 of 75 Version 1.0

    2.18 Defining Rescheduling Check for Plant and MRP Group

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Planning MRP Calculation Define Rescheduling Check

    Transaction Code OMDW Configuration

    Description The rescheduling period represents the period in which the system checks whether the existing dates of the receipt elements that are no longer allowed to be changed automatically still suit the requirements situation. If the dates of these elements are no longer suitable, the system creates the following exception messages depending on the requirements situation

    The Rescheduling checks for all the Plants and depot are identical as detailed below:

    Parameters Value Rescheduling horizon 100 Firm Planned Order Indicator Set Production Order Indicator Set Firm Purchase requisition Indicator Set Order item/Sch line Indicator Set QM inspection lot Indicator Set Shipping notification Indicator Set

  • Configuration Document SAP PP-PI Page 22 of 75 Version 1.0

    2.19 Define Number ranges for Planning Run

    Menu Path Implementation Guide for R/3 Customizing (IMG) ProductionMaterial Requirements Planning Number Ranges Maintain Number Ranges for Planning Run

    Transaction Code OMI2 Configuration

    Description In this step, we specify number ranges and intervals for the documents created during the planning run. These documents include: Planned orders for operative planning Planned orders for long-term planning (simulative planning) Dependent requirements and reservations Purchase requisitions MRP lists

    The standard Number ranges would be used

  • Configuration Document SAP PP-PI Page 23 of 75 Version 1.0

    2.20 Planning File Entry for Termination

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirement Planning Planning MRP Calculation Define Error Processing in the Planning

    Transaction Code OMDY Configuration

    Description In this step, we specify how the system is to proceed if errors occur during the planning run. Maximum number of purchase order proposals per date. If we have selected a fixed or maximum lot size, the number of purchase order proposals created during the planning run is determined in lot sizing. If more purchase order proposals are created during the planning run than the upper limit specified here, the planning run is terminated for the material in question and a termination message appears

    For Plant 1001 & 1002 The maximum Number of proposals have been defined as 999 and Sub MRP controller is 105. For all other plants this value is to set for 50 and sub MRP controller is 001

  • Configuration Document SAP PP-PI Page 24 of 75 Version 1.0

    2.21 Maintain Rounding Profile

    Menu Path Implementation Guide for R/3 Customizing (IMG) ProductionMaterials Requirement Planning Planning Lot-Size Calculation Maintain Rounding profiles

    Transaction Code OWD1 Configuration

    Description In this IMG activity, we define the rounding profile in order to adapt the units of measure in material requirements planning to the delivery and transport units, for example, if purchase orders can only be delivered in bundles of 10 pieces. With the rounding profile, we can define settings for rounding up/down order proposal quantities to deliverable quantities. There are two different types of rounding profiles; one for the core application and a rounding profile for Retail application: Statistical rounding profile for MRP in the standard system Dynamic rounding profile and quantity to be added/subtracted profile for Retail functions The statistical rounding profile for MRP is made up of: Level Threshold value Rounding value We can define several combinations of threshold and rounding values for a rounding profile. The individual combinations are then assigned a level. The threshold value is the value from which the system rounds up to the next deliverable quantity. If the threshold value is not reached, the system rounds the quantity according to the next lower level. If the lowest level is not reached, then the system rounds up to a multiple of the rounding value, if the requirements quantity is larger than the threshold quantity. Otherwise, the requirements quantity remains unchanged. The rounding value is the value to which the system rounds the quantity if the threshold value is exceeded The following Rounding profiles are maintained for Claris

    Rounding Profile

  • Configuration Document SAP PP-PI Page 25 of 75 Version 1.0

    2.22 Define Storage location MRP per plant

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Materials Requirement PlanningPlanning Define Storage location MRP per plant

    Transaction Code SPRO Configuration

    Description In this step, we define the default values for storage location MRP (multi-plant). The indicator that we set here is proposed when creating a material master record for the storage locations maintained. If we have created a material for a storage location in the material master, for which we have maintained a proposal value.

    The following data is maintained for Claris

  • Configuration Document SAP PP-PI Page 26 of 75 Version 1.0

    2.23 Defining Parallel Processing for MRP

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Materials Requirement PlanningDefine Parallel Processing n MRP

    Transaction Code SPRO Configuration

    Description With the help of parallel processing procedures, we can significantly improve the runtime of the total planning run. To process in parallel, we can either select various sessions on the application server or various servers. The work package, with a fixed number of materials that are internally defined in the program, is distributed over the individual servers/sessions. Once a server/session has finished processing a package, it starts processing the next package. If a low-level code is being planned, the servers/sessions that have finished must wait until the last server/session has finished its package to avoid inconsistencies. Then the next low-level code is processed per packages. The parallel processing procedure is switched on in the initial screen of total planning. The destination of parallel processing is maintained as CLSERDEV-CO_CDV_00

  • Configuration Document SAP PP-PI Page 27 of 75 Version 1.0

    2.24 Assigning MRP Checking Rule

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Procurement Proposals Planned Orders Define Availability Check for Components

    Transaction Code OPPJ Configuration

    Description We control the availability check for requirements planning by defining the checking group and the checking rule at plant level or per MRP group. The availability check can be carried out in MRP for the dependent requirements. This means that the availability check can directly check whether sufficient material is available for the production of the assembly. The availability check is initiated from planned order processing. It is not carried out automatically in the planning run for each requirement of an assembly.

    In the checking group, several checking rules are grouped together. Therefore, we can define different checking rules for different business application areas (sales and distribution, MRP, production orders, inventory management) or for different business operations. If we require different checking rules for different business operations, we can create several checking groups with the appropriate checking rules or we can assign another checking rule using the MRP group. The checking group is assigned to the material in the material master record, MRP 2 screen, in field "Availability check". For all the manufacturing plant, the Check on the Material will be done during the Creation and Release of the Process Order. If there is material short falls No release will be carried out The following checking rules are defined

    Checking Rule Order Type Z1 Checking Rule for Order Type C001 Z2 Checking Rule for Order Type C002 Z3 Checking Rule for Order Type C003 Z4 Checking Rule for Order Type C004 Z5 Checking Rule for Order Type C005

  • Configuration Document SAP PP-PI Page 28 of 75 Version 1.0

    2.25 BOM Usage

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Basic Data Bill of Material General data Bill of Material Usage

    Transaction Code OS20 Configuration

    Description For one material separate bills of material for the individual organisational areas involved can be created. For example, you create separate BOMs for R&D, production, and costing. In this way, each area is dealing only with the specific data it requires.

    Example:

    The R&D BOM includes all the components of the product and their technical data from the design point of view. This BOM is generally not linked to any order.

    The production BOM contains all the items required from the production and process point of view. Only items relevant to production, for which process data (such as the issue storage location) can be entered, are required. A production BOM does not contain any packaging materials required in the shipping department.

    While defining a BOM usage, the configuration of the item status is defined.

    The item status is made up of a number of indicators in the BOM item (for example, "relevant to production", "relevant to engineering/design", and so on).

    The item status controls how the BOM item is processed in related application areas. For example, the production department requires a BOM with all the items that are relevant to production. These items are first copied to the planned order. When the planned order is converted to a process order, the items are copied to the process order. The process order tells the production department which materials and intermediates it has to produce.

  • Configuration Document SAP PP-PI Page 29 of 75 Version 1.0

    For Claris we have used the standard Usage as1 for Production

    Usage Description 1 Production

    2.26 Defining Item Categories

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Basic Data Bill of Material Item Data Define item categories

    Transaction Code OS13 Configuration

    Description When we enter a new BOM item, we must assign an item category to the item. The item category defines the attributes and functions of a BOM item. It controls field and screen selection for detail screens in BOM maintenance The Following item categories are being used

    Item category Description N Non Stock Item L Stock Item K Class Item D Document Item M Intra Material

    2.27 Define Reasons for Variances

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Shop Floor Control Operations Confirmation Define Reasons for Variances

    Transaction Code OPK5 Configuration The reasons for variances are maintained at the plant level.

  • Configuration Document SAP PP-PI Page 30 of 75 Version 1.0

    Description The Reasons mentioned below are currently maintained at manufacturing plants 1001, 1002 (Injectable and infusion)

    Variances

    2.28 Define Number ranges for Manual Processing

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Materials Requirement Planning Number rangesDefine Number Ranges for Manual Processing

    Transaction Code OMI3 Configuration

    Description

    In this step we maintain number ranges for Planned orders and Purchase requisitions The SAP default values are used in our configuration for Planned orders internal number range 1 with interval from 1 to 19999999 external number range 2 with interval from 20000000 to 29999999 for Purchase requisitions internal number range 1 with interval from 10000000 to 19999999 external number range 2 with interval from 900000000 to 99999999

  • Configuration Document SAP PP-PI Page 31 of 75 Version 1.0

    2.29 Activating Requirements Planning

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Planning File Entries Activate MRP and Set Up Planning File

    Transaction Code OMDU Configuration

    Description We define the plants for which we want to carry out MRP here. Entries are only to be made in the planning file once this indicator has been set. This means: When creating a material, the material number is entered in the planning file and the system sets the total change indicator as well as the net change planning indicator Every time the material undergoes a change relevant to the planning run, the system sets the total change indicator and/or the net change planning indicator (depending on the planning horizon). All the plants at Claris Life sciences have been activated for MRP

  • Configuration Document SAP PP-PI Page 32 of 75 Version 1.0

    2.30 Defining Item Numbers of Order Types

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Material Requirements Planning Procurement Proposals Conversion of Procurement Proposals Define Conversion of Planned Orders into Purchase Requisitions

    Transaction Code OMDV Configuration

    Description In this step, We define the following: Number of planned orders, that are to be proposed for the collective conversion of planned orders into purchase requisitions Item number of the item that is transferred to the purchase requisition during the conversion. Thus, it is possible to differentiate the purchase requisitions that were created in the planning run from the ones that were created manually by the purchasing department For all the plants 500 has been proposed for the collective conversion of planned orders into purchase requisitions

  • Configuration Document SAP PP-PI Page 33 of 75 Version 1.0

    2.31 Defining Conversion Planned Order to Process Order

    Menu Path Implementation Guide for R/3 Customizing (IMG) ProductionMaterial Requirements Planning Procurement Proposals Conversion of Procurement Proposals Define Order Type for Conversion to Production/Process Order

    Transaction Code OPPE Configuration

    Description We define the order type that is automatically set when converting planned orders into production orders or process orders For Plants 1001, 1002, Production order PP01 Standard production order & Process order PI01 Process order (internal number assignment) have been set for conversions

  • Configuration Document SAP PP-PI Page 34 of 75 Version 1.0

  • Configuration Document SAP PP-PI Page 35 of 75 Version 1.0

    3. PRODUCTION PLANNING FOR PROCESS INDUSTRIES

    3.1 Define Resource Category

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Resource General Data Define Resource Category

    Transaction Code OP40 Configuration

    Description The resource category determines the data that can be maintained in a resource and, therefore, the functions (for example, costing or scheduling) for which the resource can be used.

    Each resource category is assigned to the applications (for example, production, and plant maintenance or quality management) whose menus allow us to maintain resource with this category.

    Each resource category has a number of screens assigned to it which the system displays when resource of this category are displayed. The screens contain groups of fields (for example, scheduling data). Depending on the resource category, we can make field selections on these screens (for example, defining required entry fields).

    We specify whether change documents are written for each resource category. Line Processing unit Team Labor Standard settings available in the system are used. The Resource Category used are 0008(Processing Unit)

  • Configuration Document SAP PP-PI Page 36 of 75 Version 1.0

    3.2 Defining Person Responsible for Work Centre

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Resource General Determine Person Responsible

    Transaction Code SPRO Configuration

    Description With this key, we can identify a person or group of people responsible for maintaining the master data in certain work centers. These employees are not responsible for planning tasks but only for the maintenance of the work center parameters The following persons are responsible for maintaining work centre at Claris

    Person Responsible

  • Configuration Document SAP PP-PI Page 37 of 75 Version 1.0

    3.3 Standard Value Keys

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Resource General Data Standard Value Define Standard Value key

    Transaction Code OP19 Configuration

    Description In this step we define standard value keys. The standard value key determines the meaning of the six standard values in the operation. The SAP System assigns a parameter ID to the standard values of the operation and the work in network activities. The parameter ID in turn determines: the key word displayed for the standard value on the screen, for example, setup, machine, labor, teardown etc. the dimension (for example, time, quantity, volume) of the standard value For Claris SAP Implementation we have defined Z001 as Standard Value key

    Key Description Z001 Fixed+Var+Labor+Power+Steam

  • Configuration Document SAP PP-PI Page 38 of 75 Version 1.0

    3.4 Defining Formula Parameters for Resources

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Resource Capacity Requirements Planning Formulas for Resources (Work Centers) Define Formula Parameters for Resources (Work Center)

    Transaction Code OP17 Configuration

    Description A formula is identified by its formula key. It is composed of formula parameters that are identified by parameter Ids. The following parameters are maintained for Claris Life Sciences

    Parameter Description SAPC04 Fixed Duration SAPC05 Lot Size dep. Duration SAP_03 Labour SAP_09 Operation Quantity SAP_08 Base Quantity SAP_17 No. of Employees ZCL_01 Power ZCL_02 Steam

  • Configuration Document SAP PP-PI Page 39 of 75 Version 1.0

    3.5 Defining Formula for Resources

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Resource Capacity Requirements Planning Formulas for Resources (Work Centers) Define Formula for Resources (Work Center)

    Transaction Code OP17 Configuration

    Description We define the formulas that you want to use in the following areas: Capacity planning Scheduling Costing

    You can use the formula parameters to which values have been previously assigned. The formula parameters can be linked mathematically using the following operators: Addition => + Subtraction => - Multiplication => * Division => / Formula ZCL001 will be used in Machine dependent resources for scheduling and costing. Formula ZCL002 will be used in Labor dependent resources for costing. Formula ZCL003 will be used in Labor dependent resources for scheduling.

    Formula Key Description Formula

    ZCL001 MACHINE DEPENDENT

    SAPC04 + ( SAPC05 * SAP_09 / SAP_08 )

    ZCL002 LABOR DEPENDENT SAP_03 * SAP_09 / SAP_08

    ZCL003 LABOR DEPENDENT(SCH)

    (SAP_03 * SAP_09 / SAP_08) / SAP_07

  • Configuration Document SAP PP-PI Page 40 of 75 Version 1.0

    3.6 Task List Usage

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Resource General Data Define Task List Usage

    Transaction Code OP45 Configuration

    Description Task List Usage key controls, that a resource can be used in which task lists like master recipe or PM task list. For example, we can categorize resource into maintenance resource or inspection resource according to their relevance and their usage in general task lists or inspection plans. We can also allow resource to be used in any combination of task lists types

    Standard settings available in the system are used. The following table lists the entries which are used for Claris

    Task list type Description 002 Only inspection plans 008 Master recipe + process order 009 All task list types

  • Configuration Document SAP PP-PI Page 41 of 75 Version 1.0

    3.7 Define Capacity Planner

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Resource Capacity Requirement Planning Determine Capacity Planner

    Transaction Code SPRO Configuration

    Description Key for a group of employees who are responsible for capacity planning. We can use this key to select specific capacities. This is maintained at the client level.

    The Following capacity Planners are maintained

    Plant MRP Controller Description A01 INJ PRD LINE-1 A02 INJ PRD LINE-2 A03 INJ PRD LINE-3 A04 INJ PRD LINE-4 A05 INJ PRD LINE-5 A06 INJ PAC BELT-1 A07 INJ PAC BELT-2 A08 INJ PAC BELT-3 A09 INJ PAC BELT-4 A10 INJ PAC BELT-5 A11 INJ SPM PRINTING A12 INJ STERILIZATION A13 INJ DISP PM STORE

    1001

    B01 INF PRD LINE-1 B02 INF PRD LINE-2 B03 INF PRD LINE-3 B04 INF PRD LINE-4 B05 INF PRD LINE-5 B06 INF PRD LINE-6 B07 INF PRD LINE-7 B08 INF PAC BELT-1,2 B09 INF PAC BELT-3,4 B10 INF PAC BELT-5,6 B11 INF PAC BELT-7,8 B12 INF PAC BELT-9,10 B13 INF PAC BELT-11,12 B14 INF PAC BELT-13 B15 INF DISPENSING B16 INF SPM PRINTING B17 INF STERILIZATION

    1002

    B18 INF DISP PM STORE

  • Configuration Document SAP PP-PI Page 42 of 75 Version 1.0

    3.8 Define Number Ranges for Master Recipe

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Master Recipe Setting for Task List Type Define Number Ranges for Master Recipe

    Transaction Code C2N2 Configuration

    Description In this step we define number ranges for recipe groups. When a master recipe is created, it must be assigned to a recipe group, which is identified using a group key

    The Number Range is preset to: A0000001 to ZZZZZZZZ

  • Configuration Document SAP PP-PI Page 43 of 75 Version 1.0

    3.9 Recipe Status

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Master Recipe Data for Recipe Header Define Recipe Status

    Transaction Code OP46 Configuration

    Description The recipe status determines: Whether a recipe is released for use in process orders Whether a recipe is released for costing Whether a consistency check is carried out before the recipe is posted When a master recipe is created, a status must be assigned to it. This status can later be changed according to the processing stage of the recipe. Together with the recipe usage, the recipe status is used to create priority sequences that serve as a basis for the automatic selection of recipes during order creation, capacity planning and costing. The following status are being maintained for Recipe

    Plant Description 1 Created 4 Released (general)

    3.10 Recipe Usages

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Master Recipe Data for Recipe Header Define Recipe Usage

    Transaction Code SPRO Configuration

    Description The recipe usage determines: The purpose or area, for which a recipe is created (for example, the chemical, the pharmaceutical or the food industry) The dynamic modification criteria to be used in the corresponding orders for adjusting the inspection scope if inspection points have not been defined When we create a master recipe, we must assign a recipe usage to it. We can create several recipes with different recipe usages for one material. The standard usage available will be used

    Usage Description 1 Production

  • Configuration Document SAP PP-PI Page 44 of 75 Version 1.0

    3.11 Define Planner Groups

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Master Recipe Data for Recipe Header Define Planner Group

    Transaction Code SPRO Configuration

    Description A planner group identifies one or several planners who are responsible for Maintaining certain recipes in a plant. When we create or change a master recipe, we can assign a planner group to it. The following planner group are being maintained for Claris Plant Planner Group Description 1001 A01 IPQA Manager - Injectable 1001 A02 Production ManagerInjectable 1002 B01 IPQA Manager Infusion 1002 B02 Production Manager - Infusion

    3.12 Control key for Master Recipe

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Master Recipe Data for Operations and Phases Define Control Keys

    Transaction Code OP67 Configuration

    Description Control keys are assigned to operation and phases, and secondary resources. In the control key, we set a number of flags and keys that specify the business functions to be carried out for an operation, a phase or a secondary resource.

    Control key determines how an operation, phase, or secondary resource is handled in order processing and in product costing.

  • Configuration Document SAP PP-PI Page 45 of 75 Version 1.0

    Control keys can be used as follows: In resources: The control key we enter here is referenced or copied to the corresponding operations, phases and secondary resources of the master recipe. In the master recipe When creating operations and phases as well as when allocating secondary resources: In the process order when maintaining operations, phases and secondary resources: When we create a process order, the system copies the control keys we have maintained in the master recipe to the order. They can still be changed in the order if there is no reference to the resource. For Claris we are maintaining the following control keys

    Control Key Control key Description ZP01 Process manufacturing ZP02 QC : Scheduling and MIC ZP03 Process mfg., Inspection, AutoGR ZP04 QC : MIC only ZP05 Process manufacturing with AutoGR ZP06 Process manufacturing-Bulk Preparation ZP07 QA : Scheduling

    3.13 Define Capacity Categories

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process IndustriesMaster DataResourceCapacity requirement planning Define Capacity Categories

    Transaction Code SPRO Configuration

    Description In this step we define the capacity category that we want to assign to the resource. With capacity category we determine, which capacity type a capacity category belongs to, for example: - "available capacity in volumes/quantity" for storage resources - "available capacity in time units" for processing units whether a capacity category can be assigned to people as single capacities We have used the Capacity category 008

  • Configuration Document SAP PP-PI Page 46 of 75 Version 1.0

    3.14 BOM Status

    Menu Path Implementation Guide for R/3 Customizing (IMG) ProductionPlanning for process Industries Master Recipe Material List General Data Define BOM Status

    Transaction Code OS23 Configuration

    Description Via the BOM status, we define which other application areas can use a bill of material with this status. In the different areas in a company (such as costing), the BOM is exploded according to the application. When we define an application for a certain area in the company, we select the status indicators in the Minimum requirements of BOM status dataset that the BOM status must have before the BOM is read for the BOM explosion. In MRP, the following indicators are checked directly from the definition of the BOM status: Explosion in MRP Released for orders MRP only reads BOMs whose BOM status has at least one of these indicators.

  • Configuration Document SAP PP-PI Page 47 of 75 Version 1.0

    3.15 Process Order Type

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Process Order Master Data Order Define Order Types

    Transaction Code CORN Configuration

    Description Process order type covers control information that is needed for managing the order. The order type defines the following: We have to assign an order category to each order type. The order categories have fixed assignments in the SAP System and show the technical characteristics of the orders. The order category defines, for example, the transactions we can use to process an order.

    Plant Order Type Description 1001 C001 Production C002 Packing C002 Validation C004 Performance Qualification C005 Repacking 1002 C001 Production C002 Packing C003 Validation C004 Performance Qualification C005 Repacking

    3.16 Number Ranges for Process Order

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Process Order Master Data Order Number Ranges Define Number Ranges for orders

  • Configuration Document SAP PP-PI Page 48 of 75 Version 1.0

    Transaction Code CO82 Configuration

    Description In this menu option, we define the number ranges for orders.

    Each order is uniquely identified by an order number within one client.

    We allocate each order to a number range group via the order type. We can allocate several order types to the same number range and thus the same interval.

    Internal number assignment

    When we create an order, the SAP System automatically assigns a consecutive number from the number range that we have defined.

    The number range defined are mentioned below

    Order Type Number Range C001 1000000000-1099999999 C002 110000000- 1199999999 C003 120000000- 1299999999 C004 130000000- 139999999 C005 140000000- 1499999999

    3.17 Define Production Scheduler

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Process Order Master Data Order Bill of Material Define Production Scheduler

    Transaction Code CORU Configuration

    Description Production scheduler is the entity who controls how process orders are managed. For every production scheduler, a production scheduler profile is attached. By assigning production schedulers to materials, we can define responsibilities for

  • Configuration Document SAP PP-PI Page 49 of 75 Version 1.0

    materials within production activity control.

    In a production scheduling profile, we can Specify that in a process order particular business transactions be carried out in parallel. Automatic batch creation on order creation. Batch creation on order release For Claris we are marinating the following Production Scheduler

    Plant Production Scheduler Description 1001 101 Production 102 Packing 1002 101 Production 102 Packing

    3.18 Define Production Scheduler Profile

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Process Order Master Data Order Bill of Material Define Production Scheduler Profiles

    Transaction Code CORY Configuration

    Description Production scheduling profile is linked to the Production Scheduler and one can:

    Specify automatic functions like order release on order creation Printing of Order Scheduling on release

    We can assign a production scheduler profile to a material (MMR) and production Scheduler (Customizing) Scheduler profiles C001, C002, C003, C004 are maintained for plants 1001 and 1002

    Plant Production Scheduler profile Description 1001 C001 Production C002 Packing 1002 C001 Production C002 Packing

  • Configuration Document SAP PP-PI Page 50 of 75 Version 1.0

    3.19 Scope of Check

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Process Order Operations Availability Check Define Scope of Check

    Transaction Code OPJJ Configuration

    Description To check the availability of material components in the process order, the material components have to be assigned to checking group. Through checking group and checking rule the scope of check is defined. Through scope of check we can specify which MRP element to include and which stock categories to be included.

    Define Scope of Check Yes / No (Include / Not Include) Include safety stock Yes Stock in transfer No Include QI Stock No Include Blocked Stock No

  • Configuration Document SAP PP-PI Page 51 of 75 Version 1.0

    W/o Subcontracting No Check without RLT Yes No Stor. Location Inspection No Checking period No Include Purchase orders No Include Purchase Indents No Include dependent reqmts No Include reservations No Include Sales Reqmts No Include deliveries No Include shipping notification No Include Dependent reservations No Include released Orders No Include Planned Orders No Include Production Orders No Include receipts in Past and future No

    3.20 Define Checking Control

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Process Order Operations Availability Check Define Checking Control

    Transaction Code OPJK

  • Configuration Document SAP PP-PI Page 52 of 75 Version 1.0

    Configuration Description

    In this step we define the following: Whether an availability check is to be carried out when we create or release an order Whether an availability check is to be carried out when we save an order that has been created or released Which checking rule is to be used What effect a material shortfall is to have on the creation or release of an order

    For all the manufacturing plant, the Check on the Material will be done during the Creation and Release of the Process Order. If there is material short falls No release will be carried out

    3.21 Define Scheduling parameters for a process order

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Capacity Requirements Planning Operations Scheduling Define scheduling parameters for planned orders

    Transaction Code OPUZ Configuration

    Description The purpose of this activity is to define levels and control parameters for scheduling It comprises maintenance of scheduling levels (detailed-, production-rate and rough-cut scheduling) date adjustment when deadlines are exceeded scheduling control for detailed scheduling reduction For all the Plants and Order types the scheduling has been defined as forwards

  • Configuration Document SAP PP-PI Page 53 of 75 Version 1.0

    3.22 Defining Parameters for Order Confirmation

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Process Order Operations Confirmation Define Confirmation Parameters

    Transaction Code OPK4 Configuration

    Description Using the Confirmation Parameters, you can proceed as follows: Confirmation function:

    Whether system proposes a partial confirmation, a final confirmation or final confirmation with withdrawal posting of the open reservations for the confirmation.

    Propose time unit Confirmation control: if the sequence is not adhered, you can issue a message

    Whether total confirmed qty of a operation checked for under delivery or

  • Configuration Document SAP PP-PI Page 54 of 75 Version 1.0

    over delivery tolerance in the order header Check on the dates Logs Goods Movement Propose confirmed data

    For all the Process Order types to the respective plants, all the indicators will be on and check on over delivery / under delivery will also be not checked.

    3.23 Assigning Material Types to Task List

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Master Recipe Settings for the Task List Type Assign Material Types

    Transaction Code SPRO

  • Configuration Document SAP PP-PI Page 55 of 75 Version 1.0

    Configuration Description

    Only materials of the material types allocated in this step can be allocated to a master recipe at the header level, that is, as the material to be produced. For task list type 2 Master recipe the following types have been assigned

    Task ListType Material type 2 FERT 2 HALB 2 HAWA 2 HIBE 2 ROH 2 ZERT

    3.24 Define Material Types Allowed for BOM Header

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Master Data Master Recipe Material list General Data Define Allowed Material Types for BOM Header

    Transaction Code OS24 Configuration

    Description

    In this step, we specify which material types in conjunction with BOM usages are allowed for the BOM header material. When we make these settings, we can make a generic entry in the fields for the BOM usage and the material type. This means, for example, that we can enter an "*" instead of a specific BOM usage. This stands for all possible BOM usages. When we create a new bill of material, the system checks the material type as follows: The fully qualified (non-generic) entries are checked first. The generic entries are checked afterwards. We can define that the use of the material type in combination with the BOM usage is "allowed/not allowed" by setting the indicator.

  • Configuration Document SAP PP-PI Page 56 of 75 Version 1.0

    The Following data is maintained for Claris BOM Usage Material type 1 All material Types

    3.25 Defining Order Type-Dependent Parameters

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Process Order Master Data Order Define Order Type-Dependent Parameters

    Transaction Code COR4 Configuration

    Description In this step, we define the parameters that are valid for each order type and plant. The parameters are split up as follows: Master data Cost accounting Planning Implementation For order type C001 and C002 production version and Master Recipe are automatically selected whereas for C003, C004, C005 they are Manual Selection

  • Configuration Document SAP PP-PI Page 57 of 75 Version 1.0

    3.26 Assigning Process Instructions to Control Recipe Destinations

    Menu Path Implementation Guide for R/3 Customizing (IMG) Production Planning for Process Industries Process Management Control Recipes / PI Sheets Define and Set Up Control Recipe Destinations

    Transaction Code O10C Configuration

    Description Control recipe destinations are assigned to the phases of the master recipe and the process order. In the process order, one control recipe is created and sent for each control recipe destination assigned to the order. We specify the process instructions that are to be generated in the process order when a control recipe is created for a control recipe destination

    The following destinations are created in addition to the standard SAP destinations

    CRD CRD Destination Destination Address DC Dispensing Chemist Dispensing Chemist MC Mixing Chemist Mixing Chemist PS Packing Supervisor Packing Supervisor

  • Configuration Document SAP PP-PI Page 58 of 75 Version 1.0

    QA Quality Assurance Quality Assurance QC Quality Control Quality Control SC Sterlizer Chemist Sterlizer Chemist

  • Configuration Document SAP PP-PI Page 59 of 75 Version 1.0

    4. BATCH MANAGEMENT

    4.1 Activate Document Management for Batches

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Batch Master Activate Document Management For Batches

    Transaction Code ODOC Configuration

    Description In this step we activated the Document Management function for batches.

    4.2 Defining Batch Level

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Specify Batch Level and Activate Status Management

    Transaction Code OMCT Configuration

    Description In this activity we specify the following: The level at which batch numbers are unique Whether batch status management is active in the client The plants in which batch status management is active The initial status of new batches If we choose plant level, the batch number is unique in conjunction with the respective material and the plant. If you choose material level, the batch number is unique together with the material. At client level, the batch number is unique in the whole client For Claris Batch level is maintained unique at Material Level

    4.3 Activating Automatic Batch Number Assignment

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Batch Number Assignment Activate Internal Batch Number Assignment

  • Configuration Document SAP PP-PI Page 60 of 75 Version 1.0

    Transaction Code OMCZ Configuration

    Description In this activity we activate internal batch number assignment. We define whether internal batch number assignment is allowed for goods receipts that have an account assignment

    The internal batch number assignment is activated

    4.4 Maintain Internal Batch Number Assignment Range

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Batch Number Assignment Maintain Internal Batch Number Assignment Range

    Transaction Code OMAD Configuration

    Description In this activity, we maintain number ranges for internal batch number assignment The SAP standard number range are used at Claris The number range is defined from 0000000001 to 9999999999

    4.5 Define Batch Creation for Production Order / Process Order

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Creation of New Batches Define Batch Creation for Production Order / Process Order

    Transaction Code CORW Configuration

    Description In this step we made the following settings in batch management for the existing production control profiles

  • Configuration Document SAP PP-PI Page 61 of 75 Version 1.0

    For plants 1001 and 1002 for order types C001 to C004 we have defined Automatic batch creation on order release and classification carried out in the background

    4.6 Define Process Order Condition Tables

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Condition Tables Define Process Order Condition Tables

    Transaction Code OPLD Configuration

    Description In this IMG activity, we define condition tables for batch determination in process orders. We have used the condition table 501 which determines Batch for each Material Type

    4.7 Define Process Order Access Sequences

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Access Sequences Define Process Order Access Sequences

    Transaction Code SPRO Configuration In this IMG activity, we define access sequences for batch determination in

  • Configuration Document SAP PP-PI Page 62 of 75 Version 1.0

    Description process orders. We have Defined the Order Sequence C003 which determines Batch for each Material Type

    4.8 Assign Search Procedure to Process Order and Activate Check

    Menu Path Logistics - General Batch Management Batch Determination and Batch Check Batch Search Procedure Allocation and Check ActivationAssign Search Procedure to Process Order and Activate Check

    Transaction Code CORC Configuration

    Description In this IMG activity, we allocate batch search procedures to those combinations of process order and plant for which batch determination is to be carried out, and activate batch checking.

    For Order type C001, C002, C003, C004, C005 the search procedure is defined as CO0001

    Plant Order Type Search procedure 1001 C001 CO0001 1001 C002 CO0001 1001 C003 CO0001 1001 C004 CO0001 1001 C005 CO0001 1002 C001 CO0001 1002 C002 CO0001 1002 C003 CO0001 1002 C004 CO0001 1002 C005 CO0001 1005 C005 CO0001

  • Configuration Document SAP PP-PI Page 63 of 75 Version 1.0

    4.9 Activating batch-specific Unit of Measures

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Batch-Specific Material Unit of Measure Activate Batch-Specific Material Unit of Measure

    Transaction Code OMWS Configuration

    Description If we want to use batch-specific material units of measure, set the Batch-specific material units of measure active indicator

    The Batch Specific units of measure is activated

    4.10 Edit Batch-Specific Material Unit of Measure

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Batch-Specific Material Unit of Measure Edit Batch-Specific Material Unit of Measure

    Transaction Code BMA1 Configuration

    Description In this step, we define which units of measurement we want to use as batch-specific material units of measure. We have maintained the following unit of measure

    Unit Batch Specific UOM UOM KIK kg act.ingrd. / kg KG

  • Configuration Document SAP PP-PI Page 64 of 75 Version 1.0

    4.11 Define Calculation of Proportion Quantity from Base Quantity

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Batch-Specific Material Unit of Measure Define Calculation of Proportion Quantity from Base Quantity

    Transaction Code BMA3 Configuration

    Description In this step, we define the ratio of the proportion unit to the base unit. This ratio is needed to convert base units to proportion units of measure.

    Unit Description Technical Format EML Endotoxin Units / Mililiter EU/ml G/L gram act.ingrd / liter gai/l KIK kg act.ingrd. / kg kai/kg

    4.12 Maintain Period Indicator

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Shelf Life Expiration Date Maintain Period Indicator

    Transaction Code O02K Configuration

    Description In this step we specify which unit of measurement are used for the total shelf life and minimum remaining shelf life. We have used SAP defined Period indicators as day, week, month and year

  • Configuration Document SAP PP-PI Page 65 of 75 Version 1.0

    4.13 Activating Expiration Date View per Plant

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Shelf Life Expiration Date (SLED) Set Expiration Date Check

    Transaction Code OMJ5 Configuration

    Description We have defined the time unit the system uses in the storage data of the material master record in the Period indicator field. The shelf life expiration date check is active for all the plants, except 1004,1005,1006 and the shelf life expiration date check is active for all the movement types

    4.14 Define Process Order Strategy Types

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Batch Determination and Batch Check Batch Search Procedure Allocation and Check Activation Define Process Order Strategy Types

    Transaction Code SPRO Configuration

    Description In this step, we define a strategy type for batch determination in process orders. We use different batch search strategies for different combinations of plant and order type. For this purpose, we have created the following strategy types: A strategy type with a selection class that uses the shelf life expiration date as

  • Configuration Document SAP PP-PI Page 66 of 75 Version 1.0

    search criterion during batch determination Strategy

    Type Description Class Type ZC01 Mat.Type/Mvt/Plant 023 Batch

    4.15 Define Search Procedure to Process Order

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Batch Determination and Batch Check Batch Search Procedure Definition Define Search Procedure to Process Order

    Transaction Code SPRO Configuration

    Description In this step, we define batch search procedures for batch determination in process orders. A batch search procedure comprises all strategy types that can be used for a particular combination of plant and order type

    Search procedure Description Condition Type

    ZO0001 Claris Batch Search Procedure CO03, CO01

  • Configuration Document SAP PP-PI Page 67 of 75 Version 1.0

    4.16 Activating Batch Derivation

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Derivation of batch DataActivate batch Derivation

    Transaction Code DVSP Configuration

    Description In this step, we activate Batch derivation The Batch Derivation is set as Active

    4.17 Define Derivation Events

    Menu Path Implementation Guide for R/3 Customizing (IMG) Logistics - General Batch Management Derivation of batch DataDefine Derivation Events

    Transaction Code SPRO Configuration

    Description In this step, you assign search procedures to the derivation time points. The system does not start derivation at this time point until a procedure has been assigned for searching for attributes for the receiving batch and the sending batches. The Derivation is taken place at Release of process order and The Recipient search procedure is defined as BDR001 and the Sender Search Procedure is defined as BDS001

  • Configuration Document SAP PP-PI Page 68 of 75 Version 1.0

    5. DOCUMENT MANAGEMENT

    5.1 Define Number Ranges for Document Numbers

    Menu Path Implementation Guide for R/3 Customizing (IMG) Cross Application components Document Management Define Number Ranges for Document Numbers

    Transaction Code OD00 Configuration

    Description In this IMG activity, we define the number ranges for document numbers and the type of number assignment. When we define a document type, we must create at least one number range for assigning document numbers. We have the following options: 1.Internal number assignment

    SAP System assigns a numeric number from the number range defined. 2. External number assignment

    We can define a numeric number from the number range defined.

    Sno From To 10 1000000000 1099999999 20 1100000000 1199999999 30 1200000000 1299999999 40 1300000000 1399999999 50 1400000000 1499999999 99 2000000000 2099999999

    BM 10000000 19999999 BP 20000000 29999999 QM 3000000 39999999

  • Configuration Document SAP PP-PI Page 69 of 75 Version 1.0

    5.2 Define Document Types

    Menu Path Implementation Guide for R/3 Customizing (IMG) Cross Application components Document Management Define Document Types

    Transaction Code SPRO Configuration

    Description In this step, We defined ratios such as per cent, per mil, mass per cent, etc.

    Type Description ATB Artwork-Baby Carton ATC Artwork-C Box ATI Artwork - Insert ATL Artwork- label ATM Artwork- Mother Cart BMR Batch Mfg record BPR Batch Pkg record MOA Method of Analysis

  • Configuration Document SAP PP-PI Page 70 of 75 Version 1.0

    5.3 Define Data Carrier

    Menu Path Implementation Guide for R/3 Customizing (IMG) Cross Application components Document Management Define Document Types

    Transaction Code SPRO Configuration

    Description You must only partially carry out this work step when you want to store the original application files that are accessed using the Knowledge Provider in a secure are . In this case you must only define the data carrier that can be used as a server or frontend computer.Complete Work Step Execution You must execute this step completely when you store original application files in a secure area using DMS and not using the Knowledge Provider. We have defined a Data Carrier TE The Data carrier vault for the same is

    Type Description CL Vault Claris MP Vault for BMR/BMR QM Vault for MOA-QM

  • Configuration Document SAP PP-PI Page 71 of 75 Version 1.0

  • Configuration Document SAP PP-PI Page 72 of 75 Version 1.0

    6. CLASSIFICATION SYSTEM

    6.1 Define Characteristics Groups

    Menu Path Implementation Guide for R/3 Customizing (IMG) Cross Application components Classification System CharacteristicsDefine Characteristics Groups

    Transaction Code SPRO

    Configuration Description

    In this step, you can group similar characteristics together in characteristics groups. You can then use the characteristics group to find individual characteristics. For example, you may want to group together all characteristics that refer to a length

    We have defined the following Characteristics groups

    Group Char Group PPPI_01 Process Message Characteristics PPPI_02 Process Instruction Characteristics PPPI_03 Char. For Material Flow Btw. Orders PPPI_0 Special Applications

  • Configuration Document SAP PP-PI Page 73 of 75 Version 1.0

    6.2 Define Characteristics Status

    Menu Path Implementation Guide for R/3 Customizing (IMG) Cross Application components Classification System CharacteristicsDefine Characteristics Status

    Transaction Code SPRO Configuration

    Description In this step, you can group similar characteristics together in characteristics groups. You can then use the characteristics group to find individual characteristics. For example, you may want to group together all characteristics that refer to a length We have defined the following Characteristics groups

    Group Char Group 0 In Preparation 1 Released 2 Locked

  • Configuration Document SAP PP-PI Page 74 of 75 Version 1.0

    7. OTHER SETTINGS

    7.1 Check Units of Measurement

    Menu Path Implementation Guide for R/3 Customizing (IMG) SAP NetWeaver General Settings Check Units of Measurements

    Transaction Code CUNI Configuration

    Description To perform mathematical / technical transactions, units of measures are required t


Recommended