-- against
& GENERAL CONTRACTING, LLC,
Third Party Plaintiff,
unknown to Plaintiff and intended to bepersons or entities, if any, being in possession orhaving a right of possession in and to the premisesdescribed in the Complaint,
Defendants.
TERRA FIRMA CONSTRUCTION MANAGEMENT
#lo, the last 10 names beingfictitious and #l through “JOHN DOE”
& HEATING, INC., “JOHN DOE ”
& GENERAL CONTRACTING, LLC, HUNTS POINTMULTI-SERVICE CENTER, INC., UNITED STATESFIDELITY AND GUARANTY COMPANY a/k/aST. PAUL FIRE AND MARINE INSURANCECOMPANY, BROOKVILLE ENTERPRISE, INC.,AS A PLUMBING
-xx x
TERRA FIRMA CONSTRUCTION MANAGEMENT
- against
& 016012,013,014,015 10,O 11,
l/2003MOTION SEQUENCE: 0
03/3 008884/1999
MOTION DATE:
& SONS, INC.,
Plaintiff,INDEX NO.:
TRIAL/IAS PART 20
J. SACKARIS
- STATE OF NEW YORKCOUNTY OF NASSAU
PRESENT:HON. IRA B. WARSHAWSKY,
Justice.
SCA NSHORT FORM ORDER
SUPREME COURT
-2-
Inc........ 32Memorandum of Law in Reply to Motion of Terra Firma.. ................................................. 33
Jnc .... 31Exhibits to Motion by Third Party Defendant Hunts Point Multi-Service Center,
& Affidavits.. ................................................................................................... 29Rule 19-a Statement of Material Facts ................................................................................. 30Memorandum of Law of Third Party Defendant Hunts Point Multi-Service Center,
& Exhibits Annexed............................................................... 28Notice of Motion by Third Part Defendant Hunts Point Multi-Service Center, Inc.,Affirmation
& Exhibit Annexed.. ........................................................... 27Affidavit of Bruce Covahey
& Exhibits Annexed.. ...................... 26Affidavit of Brenda J. Harling
& Sons, Inc.. .................... 22Reply Affirmation in Support of Partial Summary Judgment............................................. 23Rule 19-a Statement of Contested Facts .............................................................................. 24Rule 19-a Statement of Material Facts ................................................................................. 25Affirmation of David Westermann, Jr. in Opposition
& Exhibits Annexed................................................................................ 21Memorandum of Law in Opposition to Motions of J. Sackaris
.......................................................................19Exhibits to Terra Firma ’s Motion for Summary Judgment and Related Relief.................. 20Notice of Motion, Affidavit, Affirmation, Memorandum of Law, Rule 19-a Statementof Material Facts
& Exhibits Annexed..
& Exhibits Annexed ...... 13Statement Pursuant to Rule 19-a of the Commercial Division.. ........................................ 14Counter-Statement to Hunts Point Multi-Service Center ’s Rule 19-a Statement.............. 15Counter-Statement to Breger-Terjesen Associates Rule 19-a Statement.. ......................... 16Counter-Statement to Plaintiffs Rule 19-a Statement....................................................... 17Terra Firma ’s Memorandum of Law in Opposition to the Omnibus Motions................... 18Affirmation in Reply
& Exhibits Annexed.. .................................. 11Terra Firma ’s Memorandum of Law inSupport............................................................... 12Affirmation in Opposition to Motions for Sanctions, Affidavit
& Exhibits Annexed .................................... 9Amended Notice of Motion .............................................................................................. 10Notice of Motion, Affirmations, Affidavits
& Exhibit Annexed.. .................................................................... 8Notice of Motion, Affirmations, Affidavits &u-Reply Affirmation
& Exhibits Annexed ..... 5Reply Affirmation in Further Support of Plaintiffs Motion............................................ 6Memorandum of Law in Further Support of Plaintiffs Motion.. ..................................... 7
& Exhibit Annexed ............ 4Affirmation in Opposition to Defendant Terra Firma ’s Motion
USF&G ’s Motion
& Exhibits Annexed.. ................................... 1Rule 19-a Statement of Material Facts ............................................................................. 2Memorandum of Law in Support of Plaintiffs Motion................................................... 3Affirmation in Opposition to Defendant
BREGER-TERJESEN ASSOCIATES and HUNTSPOINT MULTI-SERVICE CENTER, INC.,
Third Party Defendants.
The following papers read on this motion:
Notice of Motion, Affirmation, Affidavits
-3-
130- 1.1 striking plaintiffs complaint for$ 3 126 and 22 NYCRR
$37,720.74, and for an
order pursuant to CPLR
& General
Contracting LLC (Terra Firma) for summary judgment dismissing the complaint or, in the
alternative, for an order limiting plaintiffs damages to the sum of
& Hiller PC, for
engaging in frivolous conduct, and
II: the motion by defendant United States Fidelity and Guaranty Company, a/k/a
St. Paul Fire and Marine Insurance Company, (St. Paul), for an order pursuant to CPLR
32 12 granting partial summary judgment against plaintiff limiting liability to the penal
amount of the Discharge Bond, and
III: the motion by defendant, Terra Firma Construction Management
29,2002, and for sanctions against
defendants Terra Firma, St. Paul and counsel for those defendants, Weiss
$342,200.00, for a further order striking the answers of
defendants Terra Firma and St. Paul and precluding the aforesaid defendants from
introducing any evidence produced after August
tune to nunc pro
5 137, a claim for
punitive damages for bad faith relative to the Payment Bond and a claim to increase
plaintiffs lien
$346,200.00 plus interest, attorney fees and punitive damages, or, in the
alternative for summary judgment on the issue of liability and an inquest as to damages,
and for an order granting leave to serve an amended complaint asserting a claim under a
Payment Bond, a claim for counsel fees under State Finance Law
& Exhibit Annexed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
I: The motion by plaintiff, Sackaris, for an order granting summary judgment in
the amount of
USF&G . . . . . . . . . . . . . . . 38Reply Affirmation in Further Support of Breger-Terjesen Motion forSummary Judgment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39Affirmation in Sur-Reply of Terra Firma
& & General Contracting LLC
& Exhibits Annexed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36Rule 19-a Statement of Material Facts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37Affirmation in Opposition to Motions for Summary Judgment of the DefendantTerra Firma Construction Management
& Exhibits Annexed...... 35Notice of Motion, Affidavit
... 34Affirmation in Reply by Hunts Point Multi-Service Center, Inc.
li-rc . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Affirmation in Partial Opposition by Third Party Defendant Hunts Point Multi-ServiceCenter,
-4-
& Sons, Inc.
(Sackaris), on October 20, 1997, for excavation and cement work for a nursing home
$265,000.00. Defendant Terra Firma counter claimed for
breach of contract and breach of a common law duty of care.
Defendant/third party plaintiff, Terra Firma commenced a third party action
against Breger-Terjesen and Hunts Point asserting that they had both wrongfully denied
approval of a change order, or orders, for extra excavation work performed by Sackaris
and, in the event it was determined that Sackaris quit the site by reason of such wrongful
denial, liability against the third-party defendants is sought for the resulting damages.
The issue driving this litigation is whether plaintiff contracted to excavate
subsurface hard rock.
FACTS
Terra Firma, as the general contractor, retained J. Sackaris
damnun clause is
for the amount of the Bond,
tune ’ a defense of accord and satisfaction, and for an order pursuant to CPLR
3 126 dismissing the third party complaint on the grounds that defendant/third party
plaintiff, Terra Firma, failed to produce discovery are all determined as follows.
Plaintiff commenced this action to foreclose on a lien for material and labor
supplied on a construction project known as Hunts Point Multi-Service Center in the
Bronx. Plaintiff seeks to recover on the Discharge Bond posted by St. Paul as surety for
defendant, Terra Firma, the general contractor on the project. The ad
nunc pro
surnmary judgment, for an
order pursuant to CPLR 3025(b) granting leave to serve an amended answer asserting
summary judgment dismissing the third party
complaint and all cross-claims, and
V: the motion by third party defendant Hunts Point Multi-Service Center, Inc.,
(Hunts Point), for an order pursuant to CPLR 3212 granting
failure to comply with discovery demands and requiring plaintiff to appear for another
oral examination before trial, and
IV: the motion by third party defendant, Breger-Terjesen Associates, for an
order pursuant to CPLR 32 12 granting
-5-
$6,500.00, on the reasoning
that the Terra Firma-Hunts Point contract (the Prime Contract) provided for hard rock,
Terra Firma was bound to the Prime Contract where excavation for hard rock was
included and therefore hard rock should also have been included in the Purchase Orders.
Sackaris would not accept the sum, nor would Terra Firma. Sackaris was instructed to
keep digging and submit change orders.
Eventually, apparently to keep the project moving, on May 22 1998, Hunts Point
offered and Terra Firma agreed to settle the matter of change orders for hard rock
excavation for the enlarged sum of $50,000. The sum included all past and future cost
over runs for excavation solely as a result of the subsurface condition, even though
(CO#2
for machinery) from Breger-Terjesen who approved only
28,1998. It incorporates the terms of the Prime Contract between Hunts
Point and Terra Firma.
The Prime Contract between Terra Firma and Hunts Point included the cost of
excavation of all contingencies. The October 1997 Purchase Orders between Terra Firma
and Sackaris required Sackaris to do excavation pursuant to the contract with Hunts Point
but excluded therefrom any excavation requiring special machinery. The sub-contract
provided, in pertinent part, for plaintiff to undertake “removal of rock etc. . . . providing
the removal can be accomplished without special equipment or methods, i.e. air ram, drill
and blasting, jack hammers. ”
Sackaris started work in December of 1997; after a few days Sackaris discovered
that there was a hard rock subsurface condition which required different equipment and
different methods for excavating the foundation.
Terra Firma sought approval of the first change order dated January 1998,
project being built by Hunts Point. The accepted bid was $250,000 for concrete work and
$170,000 for excavation. Two purchase orders confirm the agreement. The construction
was. being funded through Chase Bank and DASNY, and required approval from the New
York State Department of Health. A TF 1.1 Contract was executed by Sackaris and Terra
Firma on April
-6-
1,462.49 on June 3, 1998. In
July of 1998, Terra Firma obtained a discharge bond for the lien from St. Paul (who had
also issued a Payment Bond for Terra Firma) in the penal sum of $265,000 to include
pre-judgment interest and costs. This action was commenced on April 9, 1999, to
foreclose on the lien.
Of collateral significance is the fact that on April 24, 1998 Sackaris asserted a
claim under the payment bond for work unpaid by Terra Firma. The claim was
acknowledged and was fielded back and forth “through channels, ” being finally rejected
on February 10, 1999, in a position letter authored by Terra Firma ’s present counsel. In
sum and substance it opines that Sackaris should not be paid because it quit work and that
it had no right to quit work because of unpaid change orders (which were to be settled
after completion of all work), and that in any event Sackaris was negligent in the
performance of its work. The exact statement of Michael Hiller, on behalf of Terra Firma
was as follows: “the unambiguous language of the Contract required that J. Sackaris
complete the job before making a claim against Terra Firma or the owner. By abandoning
the job well prior to completion, J. Sackaris breached the contract and forfeited any right
to obtain payment thereunder or under the theory of quantum meruit. ” This remains the
$170,000), plus change orders for hard rock. An attempt at a
settlement between Sackaris and Terra Firma took place; Sackaris demanded $122,000,
Terra Firma offered $100,000, which was rejected. Momentum on the site had largely
fizzled, no resolution to the dispute was forecast and Sackaris was terminated in writing
on May 26, 1998. Sackaris filed a lien in the amount $23
recieved only $82,000 in payment, but had,
allegedly, completed 75% of the concrete work (on the bid of $250,000) and 70% of the
excavation (on the bid of
plaintiff had already submitted invoices, or change orders in the amount of $122,000 for
extra labor and machinery for excavation.
Terra Firma received the aforesaid amount, with the blessings of DASNY and
DOH, and told Sackaris that it should continue to work and continue to submit change
orders. About this time Sackaris had
-7-
A.D.2d 736 (3d Dept) (movant in action& Home Maintenance ,296
& 11. See, LHV Precast Inc.
v Woodstock Lawn
4(l), 9, 10 05
A.D.2d 545 (3d Dept 1991).
DISCUSSION
There is little difficulty granting plaintiffs motion to enter judgment on the lien.
Plaintiff has submitted proof that defendant Terra Firma is in breach of its contract with
plaintiff by failing to pay plaintiff for the contract work performed pursuant to the
concrete purchase order, failing to pay plaintiff for the excavation work performed under
the excavation purchase order, and failing to pay for “hard rock ” excavation directed by
Terra Firma. Plaintiff has established the lien amount pursuant to the particularization
the lien.
Although less prolix on this subject than others the proof submitted by plaintiff
of
establishes that the lien conforms to Lien Law
Anable v Bolentin, 175
N.Y.2d
276;
Swift v Muller Construction Co, 46 & N.Y.2d 557; Alvord
A.D.2d
5 16 (3d Dept 199 1). Conclusions and unsubstantiated allegations or assertions are
insufficient to raise a triable issue of fact and defeat summary judgment. Zuckerman v
City of New York, 49
N.Y.2d 1065 (1979).
Once a prima facie showing is made by the proponent, the burden shifts to the
party opposing the motion to rebut the movant ’s case by making an evidentiary showing
that material issues of fact exist and must lay bare affirmative proof that matters are real
and capable of being established at trial. See Del Giacco v Noteworthv Co., 175
Mfgs., 46
evident&y proof in admissible form. See Friends of Animals,
Inc. v Associated Fur
N.Y.2d 395
(1957). In order to prevail the movant must establish his cause of action or defense in a
manner sufficient to warrant entry of judgment as a matter of law. The case must be
established by tender of
Sillman v Twentieth Centnrv-Fox Film Corn., 3
defense to date. Having failed to sue on the Performance Bond within one year and
having elected to proceed on the Discharge Bond plaintiff is barred from so doing now.
On a motion for summary judgment, the court must engage in issue finding rather
than issue determination.
-8-
N.Y.2d
969 (1984). The proof shows that plaintiffs work was accepted and approved by the
owner, the architect, and DASNY and that Terra Firma was paid but did not turn over the
payment to plaintiff and that plaintiff was terminated from the job a few weeks after it
determined not to work without getting paid.
The other causes of action contemplated by plaintiff are irrelevant and need not be
examined by this court as plaintiff shall not be permitted to amend the complaint four
years after commencing the action, almost to the date, and only a few weeks before trial
was to commence. No excuse is given for the delay. Moreover a claim under the Payment
Bond is Time barred and asserting a claim in quantum meruit now, at the close of
discovery, would be prejudicial.
Plaintiffs remaining requests for relief in the nature of sanctions for complained
of discovery abuses and dilatory conduct can be generically addressed. All such claims,
by any party to this lawsuit, are denied. To the view of the court there has not been
frivolous conduct as defined by 22 NYCRR 130-l. 1. True there have been forays into
1,426.49 and plaintiff is limited to recovery of that amount in this action to
foreclose on a lien. Tri-City Electric. Inc. v People of the State of New York, 63
$346,200.00
together with interest is the reasonable amount due and owing. However the amount of
the lien is $23
Alicea (former project manager for
Terra Firma), Robert Sackaris and Richard Pierce (project manager for Breger-Terjesen)
attest to the fact that plaintiff performed the work as set forth in the notice of Lien.
Plaintiff has likewise submitted competent proof that the sum of
20th and completed a substantial portion of the
contract, that it submitted requisitions and changed orders, that the requisitions were
approved by Terra Firma and that plaintiff was paid but $82,000 on a $450,000 contract
less 10% retainage. In addition affidavits by Messers.
27th to May
to foreclose lien has burden of setting forth evidence to establish the existence of a valid
lien.) The record is replete with letters, records, the purchase orders, minutes of
meetings, requisition slips and change orders that show that plaintiff worked on the
subject site from December
-9-
70-75% of the work
performed since November, stopped manning the job in May. Terra Firma cannot
persuasively argue that plaintiff was bound to excavate hard rock under the sub-contract
and Prime Contract when Terra Firma itself accepted $50,000 for change orders for hard
rock excavation. Virtually every affidavit in the record, save defense counsel ’s,
acknowledges that hard rock was in the Prime Contract but not in the sub-contract. There
uncharted areas of the absurd and there has been back biting and devilment adequate to
make a school master quiver. However, this appears to be a personal matter between
counselors. It does not affect the merits of the litigation and therefore is not an issue
determinable by this court whose only mission is to determined whether the facts support
recovery by plaintiff under the law. Whether any of these acts would be of interest to the
Grievance Committee the court will leave up to each party to make the appropriate
complaint.
Since plaintiff has established a prima facie case that it did the work and extra
pursuant to it ’s contract and has not been paid, it has established a valid lien and the
burden shifts to defendant Terra Firma to raise a triable issue of fact. In opposition
defendant, documents -- meticulously -- plaintiffs discovery abuses. The consequences
of such conduct, it is argued, mandates dismissal of the complaint, irrespective of the
facts. As to the facts, those argued by defendant are directly inapposite to the
documentary proof in the record, are only rarely supported by an affidavit by a person
with knowledge, and do not impugn the integrity of the lien filed by plaintiff. After all,
an action to foreclose on a lien requires approximately the same proof as a cause of action
for breach of a contract, only the burden of proof is somewhat different. Rather than
prove that the opponent did not perform its promised obligation, plaintiff must establish
that it performed so much of its obligation as is claimed in the lien. The record now
before me is rife with first hand evidence that it did. Nothing supports Terra Firma ’s
claim that the work was defective, or that plaintiff was in breach first, before defendant
terminated the contract. Plaintiff having not gotten paid for
-lO-
People of the State of New York, supra.Accordingly, the burden shifts to defendant
Terra Firma or plaintiff to raise a triable issue of fact. Neither party has shown any fact
which under the law permits an increase in the amount of a bond four years after suit is
commenced and five years after the lien was filed.
Accordingly, defendant St. Paul is granted partial summary judgment on the issue
of limiting liability on the bond to the penal sum.
Third party defendant Breger-Terjesen was the architect pursuant to the contract
with the owner, co-third party defendant, Hunts Point Multi Service Center Inc. (Hunts
Point). Among its responsibilities, it was to be consulted on any change order, or any
other issues arising during construction, and to give an impartial opinion about the
G.O.L.5 7-301; Tri-Citv Electric. Inc. v
1,462.49. Defendant ’s motion
for summary judgment is denied.
Defendant St. Paul moves to limit its liability to the penal sum under the discharge
bond. Defendant has established that it has caused no breach of its contractual
undertakings in the Discharge Bond and that the fixed penal limit of said Bond cannot be
increased beyond the limit stated in the Bond.
1,462.49.
Accordingly, plaintiff is granted summary judgment on the first cause of action for
a valid lien, on the second cause of action to recover on the Discharge Bond, and on the
third cause of action for balance due on the contract of $23
$196,099.99, less amount paid $82,000 equals balance due of $23
$118,162.50, Excavation work
completed
is no legible copy of the Marathon purchase order before the court for comparison, but it
appears that plaintiff did most of the excavation work at the behest of the contractor.
Last, the court rejects any argument that Sackaris should wait to get any payment on the
contract until the change orders were resolved in a contract fashioned by Terra Firma. A
“paid when paid ” clause has been held unlawful and in any event the requisitions were
approved.
Plaintiffs itemization of the lien claims the following and the records found in the
motion confirm the claim: Concrete work completed
-ll-
Firma also asserts that Breger-Terjesen breached its
duty of impartiality and showed favoritism to the owner, Hunts Point, in denying the
change order.
Breger-Terjesen posits that it ’s architectural plans and specifications address the
issue of excavation of the foundation and include all excavation, including removal of
hard rock to be undertaken by the excavation subcontractor, and is included in the
contract for labor and materials negotiated by Terra Firma for the benefit of the owner
Hunts Point. Having so said, Breger-Terjesen concedes an issue as to whether the
contract between plaintiff and Terra Firma includes hard rock excavation. When
presented with the issue Breger-Terjesen remained mindful of its duty to impartially
interpret the contract and make determinations on disputes between the owner and the
general contractor.
Breger-Terjesen acknowledges that a Boring Survey it caused to be conducted
indicated the presence of rock in a subterranean state at the project without a finding as to
degree of hardness. After reviewing the contract between the owner and the general
contractor and again consulting with the engineer on the Boring Survey, Breger-Terjesen
made a decision that the excavation was to be done without a change order for hard rock.
However, in light of the fact that Terra Firma ’s contract with plaintiff was to the contrary
it proposed a change order of $6,500. As stated above when Hunts Point negotiated with
Terra Firma to pay an additional $50,000 for hard rock excavation the opinion of the
architect became moot.
validity of the claim. It was consulted in January 1997 by Terra Firma about the
discovery of hard rock under the sub soil after plaintiff began its work. The contractor,
Terra Firma, commenced the third party action on the theory that Breger-Terjesen had
denied in bad faith a change order for excavation of rock which was harder and of a
different classification than contracted for. If Terra Firma is liable for Sackaris ’s quitting
the job site, it is argued that Breger-Terjesen must be liable for its bad faith review and
rejection of the change order. Terra
17,2003
HuntsPoint; not only did Hunts Point
approve a $50,000 change order, and actually pay it, but also Terra Firma never turned it
over to Sackaris and now hopes to have Hunts Point pay the change order again!
Accordingly, the motion by third party defendant Hunts Point is granted.
All other requests for relief not expressly granted are denied. In sum it is
ORDERED and ADJUGED that plaintiff is granted summary judgment on the
complaint and the third party complaint is dismissed together with cross claims.
Dated: April
tune in an amended answer, the settlement of the change order for
hard rock excavation for $50,000 with Terra Firma and release of all claims between
them disposes of the matter. Liability is predicated upon a claim that Hunts Point
unreasonably refused to approve a change order for the extra costs of excavating hard
rock which would increase the cost of excavation between Sackaris and Terra Firma.
However, Sackaris can make no direct claim against Hunts Point, there is no privity of
contract, and as between Terra Firma and Hunts Point the cost of hard rock excavation
was conclusively resolved with the $50,000 agreement. The proof shows that there was
no other excavation change order submitted and rejected after the settlement. Finally, the
assertion is head-shakingly stupid as pointed out by
nunc pro
Breger-
Terjesen has shown it is entitled to summary judgment and the burden shifts to opposing
party to raise a triable issue of fact which in light of the settlement is academic.
The argument of co third-party defendant Hunts Point is similar. Although sought
to be asserted
Accordingly, third-party defendant Breger-Terjesen has established that it acted in
a reasonable and accepted manner for an architectural firm bound to mediate disputes
fairly and impartially between the owner of a construction project and the owner.