+ All Categories
Home > Documents > Schaaf Presentation

Schaaf Presentation

Date post: 09-Sep-2015
Category:
Upload: amkrdav7810
View: 231 times
Download: 3 times
Share this document with a friend
Description:
Rob Schaaf presentation at USF. Only for educational purpose. Rights belong to Rob Schaaf.
Popular Tags:
32
1 SOFTWARE PROJECT MANAGEMENT NUTS & BOLTS Robert J. Schaaf [email protected] September 22, 2014 © Robert J. Schaaf SCOPE: ALL TYPES OF SOFTWARE All types of applications Business science and engineering sense & control tools middleware Business, science and engineering, sense & control, tools, middlewareAll types of configurations Host-based, client-server, web-based, embedded, … All types of offerings Custom, generic / off-the-shelf, component, service, … © 2 All flavors of software engineering New or evolutionary development, operations, acquisition, … Scope: Large, complex settings
Transcript
  • 1SOFTWARE PROJECT MANAGEMENT

    NUTS & BOLTS

    Robert J. [email protected]

    September 22, 2014 Robert J. Schaaf

    SCOPE: ALL TYPES OF SOFTWARE

    All types of applicationsBusiness science and engineering sense & control tools middlewareBusiness, science and engineering, sense & control, tools, middleware

    All types of configurationsHost-based, client-server, web-based, embedded,

    All types of offeringsCustom, generic / off-the-shelf, component, service,

    2

    g p

    All flavors of software engineeringNew or evolutionary development, operations, acquisition,

    Scope: Large, complex settings

  • 2SCOPE: LARGE, COMPLEX SETTINGS

    Projects with more than 5 10 people Projects with more than 5-10 people

    Projects longer than ~6 months

    Long-life software, an asset

    3State of Affairs, from 30,000 feet

    STATE OF AFFAIRS, FROM 30,000 FEET

    Enormous progress over the past 40 years, particularly in size

    Shift from hardware-defined to software-defined systemsS y

    Still, too many failures in development, acquisition, operations

    In many cases, big uncertainties in time, cost, quality and risk

    Issues are managerial, not technical

    4

    Still missing: Generally-accepted software management framework

    Real: DOS & DONTS for given projects Nuts & Bolts

    We Will Touch On

  • 3WE WILL TOUCH ON.

    Requirements

    Project Management

    Process Assessment

    5

    Applies equally to development, acquisition and operations

    Requirements

    REQUIREMENTS

    + Stakeholders Stakeholder needs Quality

    6Requirements Practice

  • 4REQUIREMENTS PRACTICE

    In the profession, the requirements practice remains controversial

    We have no time for requirements, Requirements always change, etc.

    Alternatives for example, a project charter dont work well enough

    Often, we have to fight for the practice of requirements

    - Requirements answer Why this particular project?

    - Set the scope of the project and Yes, requirements change

    7

    p p j q g

    - Serve as signposts and yardsticks in the course of the project

    - Are critical in judging the readiness for delivery of the software

    Stakeholders

    STAKEHOLDERS

    A stakeholder is a person with an interest in anything related to the software:

    Cast the net much wider than customer and user

    A. The software itself, incl. any property or attribute of the software

    E.g.: the customer(s); the owner(s); the users

    But also, say the legal department

    B. The environment in which the software will be used

    E.g.: the owner of a system interacting with the software

    But also say the designer of the applications business processes

    8

    But also, say the designer of the application s business processes

    C. The processes applied during the life of the software

    E.g.: developers; acquirers; trainers; sub-contractors

    But also: internal audit, finance, marketers, sales, pricing, etc.

    Stakeholder NeedsTrade-off

  • 5STAKEHOLDER NEEDS

    Stakeholder need: A condition that must or should be

    Distinguish between stakeholder needs and software requirements

    fulfilled according to one or more stakeholders Strength of need varies what value to stakeholder? A need is owned/held by the respective stakeholder(s) Others may help in the discovery & formulation of needs

    Fulfillment of a stakeholder need may depend upon

    Th ft it lf

    9

    The software itself The environment interoperating with the software The processes to engineer the software

    More than Function: Endless variety of types of needs

    Sample Types of Stakeholder Needs

    SAMPLE TYPES OF STAKEHOLDER NEEDSEnvironmental factorsUsability, human factorsOperabilityInstallabilitySecurity

    FunctionalityScheduleTimelinessCost, priceQuality

    CompletenessMaintainabilityConfigurabilityFlexibilityScalability y

    Modes of operationPrivacyIntegrityProperty rightsMerchantabilityGovernabilityRegulatory complianceStandards compliance

    AccuracyPerformanceCapacityResponsivenessEfficiencyEffectivenessSafetyReliability

    yPrivacyAdaptabilityPortabilityInteroperabilityExtendibilityCompatibilitySimplicityModularity

    10

    Standards complianceInternational factorsAuditabilityAND SO ON

    ReliabilityAvailabilityServiceabilityRobustness

    ModularityReusabilityTestabilityTrainability

    FUNCTION OF PROBLEM DOMAIN AND STAKEHOLDER VALUESThe Subject Software in its Environment

  • 6THE SUBJECT SOFTWARE IN ITS ENVIRONMENT

    ENVIRONMENT

    SOFTWARE

    11Stakeholder Needs

    STAKEHOLDER NEEDS

    ENVIRONMENT

    12

    Needs should be irrespective of the subject softwares boundaryNeeds should be problem and goal oriented Software Requirements

  • 7SOFTWARE REQUIREMENTS

    SOFTWARE

    13

    Software requirements delineate the subject software

    Software Requirement

    SOFTWARE REQUIREMENT

    A condition on the software, or on a software process,

    to make the software acceptable to the stakeholders

    Requirements vary in strength: must, should, may, etc. all requirements are not equal

    Requirements should have permissible cost data

    Requirements should be stated in the positive

    14

    q pnegatives are hard to prove

    There should beno security holes Requirements, like needs, may change

    Requirement Types

  • 8REQUIREMENT TYPES

    Similar to needs addressing everything of interest to the stakeholders

    Requirements must address everything that may influence the acceptability of the software

    For example requirements addressing: function; performance;

    15

    For example, requirements addressing: function; performance;

    reliability; availability; safety, security; installability;

    compatibility; scalability; software processes; schedule; etc.

    Who, What, How and When

    WHO, WHAT, HOW AND WHEN

    STAKEHOLDER NEEDS SOFTWARE REQUIREMENTS

    Responsibility of stakeholders Responsibility of project manager

    What the problem is What the solution should+will do

    Modeling of the domain, e.g.- Business processes, workflows

    - Domain scenarios

    Modeling of the software, e.g.- Use cases- Test casesDomain scenarios

    Mostly reactive: Feedback

    Test cases

    Mostly pro-active

    Throughout the project Throughout the project

    16Consensus and Quality

  • 9CONSENSUS AND QUALITY For stakeholder consensus, stay away from needs as they may

    conflict - use requirements as basis on which to reach consensus

    A-priori consensus about what is to be engineered

    A-posteriori consensus that the actual software is acceptable

    Transformation from needs to requirements is non-deterministic, same needs may lead to different requirements opportunity!

    A requirement must be formulated in a way that makes it possible to test for conformance in the course of the project

    17

    Working definition of quality: The degree that the software, at the end of the project, meets software requirements

    ~~~ Requirements define quality ~~~

    What If Disagreement on Requirements?

    WHAT IF DISAGREEMENT ON REQUIREMENTS?

    Project manager negotiates, in terms of software requirements, not stakeholder needsrequirements, not stakeholder needs

    Whats wrong with the current iteration of software requirements? > Rinse & repeat

    Focus on bottom-line: Profit, mission, etc.

    Persistent disagreement? Case: IBMs Future System

    18What if Requirements are Defective?

  • 10

    WHAT IF AGREED REQUIREMENTS ARE DEFECTIVE?

    Worse, requirements may be unknowable, at least initiallySeveral root causes of unknowabilityy

    The more software, the more unknowability

    Incremental evolution of needs > requirements > software

    ANSWER

    Each increment based on best-available needs & requirementsEach increment is a complete engineering cycle, but short!Each increment released and used > improved requirementsDEFINE QUALITY AS SATISFYING THE STAKEHOLDERS 19Feedback Loop

    FEEDBACK LOOP

    ENGINEERING OF NEXT INCREMENT

    LIVE USE OF INCREMENT

    STAKEHOLDER NEEDS

    RELEASE OF FINAL

    INCREMENT

    NEW/CHANGED/REFINED

    STAKEHOLDER NEEDS, SOFTWARE REQUIREMENTS

    1-4 week cycle dependency on users able to take delivery

    Stakeholder participation: use, feedback

    Current practical problems with agile engineering:(1) Design-in-small-chunks is very hard at best

    (2) Low quality of each increment(3) Total time from start to finish

    (4) Does not scale well 20Software Project Management

  • 11

    SOFTWARE PROJECT MANAGEMENTSOFTWARE PROJECT MANAGEMENT

    21Case: System X

    CASE: SYSTEM X

    Large, complex communications software system

    Embedded in a new, make-or-break product family, X

    1000 software engineers, 10 centers, 3 continents

    Continuous coordination problems

    Enter the first project manager..

    22Typical Sources of Failure

  • 12

    TYPICAL SOURCES OF FAILURE

    #1 Project coordination instead of project management

    #2 Little or no planning, or not adaptive#2 Little or no planning, or not adaptive

    #3 Project plan implausible vis--vis past performance

    #4 Poor execution, tracking & follow-up

    #5 Unmanaged risks, small problems left to grow

    #6 Unreasonable expectations go unchecked

    23

    #6 Unreasonable expectations go unchecked

    Wild card: Personnel

    A project is.

    A project is.

    A way of organizing work A way of organizing work

    Work with a beginning and an end

    Work that leads to a unique result

    As opposed to: Ongoing, repetitive work

    24Project and Organization

  • 13

    PROJECT AND ORGANIZATION

    Functional organization

    Project organization

    Matrix organization

    25Functional Organization

    FUNCTIONAL ORGANIZATION WORK TO THE PEOPLE

    ProjectCoordinators

    26

    - People understand their own work, but not the total

    - Friction in pushing projects through, sub-optimization

    - Unfriendly to complexity and uncertainty

    - Works for software maintenance and operationsProject Organization

  • 14

    PROJECT ORGANIZATION PEOPLE TO THE WORK

    SponsorProject A

    27

    - Organize in small teams (10-15) + fully-responsible project manager- Flexibility, accommodates complexity and uncertainty- People understand the total less their own contribution- Nowadays, dominant model for software engineering

    Project Management Responsibilities

    PROJECT MANAGEMENT RESPONSIBILITIES

    1. Organization Who- Project manager is overall manager of the project, where the bug stops

    - With total responsibility/accountability/authority for work & outputWith total responsibility/accountability/authority for work & output

    - Much delegation of responsibilities, authorities and accountabilities

    2. Project Scope - What- Identify stakeholders, elicit stakeholder needs, negotiate requirements

    - Break down of work & output

    - Maintain link between {needs, requirements} and {work, output}

    3. Use of Time - When- Sequence activities, unearth dependencies and assumptions

    - Estimate resources x time for each activity

    - Create & maintain project schedule, verify against resource planning etc. 28Project Management Responsibilities

  • 15

    PROJECT MANAGEMENT RESPONSIBILITIES Contd

    4. Cost- For each activity, estimate the costs of the resources needed- Aggregate the estimated costs in a budget, suitable for control- Control actuals against budget, control changes in budget

    5. Quality- Establish and maintain a quality management system- Rule #1: Quality is everybodys responsibility- Every task, output has an owner + keep owners feet to the fire - Achieve stakeholder satisfaction, get output acceptedAchieve stakeholder satisfaction, get output accepted

    6. Staff- Develop and execute a staffing plan- Analyze actual competencies against needs, plan training if necessary- Track individual and team performance, provide feedback, resolve issues

    29Project Management Responsibilities

    PROJECT MANAGEMENT RESPONSIBILITIES Contd

    7. Communication- Determine information needs > plan the flows > track & correct

    - Motivate project personnel recognize, explainMotivate project personnel recognize, explain- Massage stakeholder expectations

    8. Risk- Establish a risk management system, control its performance- Track major dependencies and assumptions, analyze plan deviations- Identify high risks - continuously- Mitigate high risks: alternative courses of action, fallback plans

    9. Procurement- Set make-or-buy direction, approve make-or-buy decisions- Control: identification and selection of sellers; contracting + fulfillment

    30Case: System X

  • 16

    CASE: SYSTEM X

    Large, complex communications software system

    1000 software engineers, 10 centers, 3 continents

    Enter the first project manager.

    Full project management responsibility + accountability

    Direct authority over 1/3 of staff

    Controlling operating system, tools, plans & controls

    31My Own Typical Priorities

    MY PRIORITIES AS PROJECT MANAGER

    PLANNINGPLANNING

    EXECUTION

    RISK

    PERSONNEL

    32How Do We Get a Plausible Plan?

  • 17

    HOW DO WE GET A PLAUSIBLE PLAN?

    There are many planning methodologies

    UNREALISTIC PLANNING LEADS TO REAL WASTE OF TIME AND EFFORT

    e e a e a y p a g et odo og es

    Our method:

    1. Plan incrementally, as time progresses

    2 Pl l i ti iti i d t il h tli > 6 th

    33

    2. Plan close-in activities in detail rough outline > 6 months

    3. Do size-based planning around the Golden Triangle

    Golden Triangle of Project Planning

    GOLDEN TRIANGLE OF PROJECT PLANNING

    WHAT=SCOPE

    34

    WHEN=TIMEHOW =ACTION

    Size-Based Planning

  • 18

    SIZE-BASED PLANNING- From requirements ( > design specs ), estimate size

    - From size, estimate effort for precision, also consider complexity etc.

    - Based on size and effort, set (adjust) staffing level and time schedule

    - If necessary, change requirements to affect size > effort > schedule

    SCOPESIZE

    35

    ACTION

    EFFORT SCHEDULETIME

    ITERATIVE PROCESS!What Gets Estimated for Size?

    WHAT GETS ESTIMATED FOR SIZE?

    MOST OFTEN: Code to be developed, acquired or used

    Requirements to be specified (or modeled)

    Design to be specified (or modeled)

    Architecture to be developed/maintained

    Tests to be developed and performed

    Parts to be integrated

    36

    Documentation and training materials to be developed

    Processes to be designed, planned, installed and maintained

    Tools to be developed, acquired, installed and maintained

    Iterative Planning for Each Increment

  • 19

    ITERATIVE PLANNING FOR EACH INCREMENT

    SCOPESIZE

    COSTEFFORT SCHEDULE

    TIME

    INCREMENTAL ENGINEERING

    DO

    CHECK

    PLAN

    ACT

    DELIVERY

    NEEDS FOR NEXT INCREMENT

    USE & FEEDBACK

    DEVELOPMENT / ACQUISITION

    A Plausible Plan Also Has.

    A PLAUSIBLE PLAN ALSO HAS.Commitment, buy-in explicit, from all actors, and lasting No commitment equals no plan Review, comments and silence are no commitments

    Brevity - No unnecessary detail, no unnecessary precision Only specifics that will be checked (measured, counted) and insisted on Only specifics where deviation would require extra action No guidelines, no project introduction plan is not for training

    Process for the identification and ranking of risks and dependencies Dependencies on other projects, capital equipment, outside vendors Identification of responsible parties, other plans Test whether parties are able, planning and performing to satisfy the dependencies

    38

    Test whether parties are able, planning and performing to satisfy the dependencies

    Currency a project plan is a living thing, planning is continuous

    Common sense for example, no plan without contingency resources

    A few major milestones (and criteria) for broad visibility of project statusManaging the Execution of the Project Plan

  • 20

    MANAGING THE EXECUTION OF THE PROJECT PLAN : TRACKING & FOLLOW-UP

    At the individual level: Daily reporting in stand-up mtgs

    At managers levels:

    - Weekly reporting against plan and forecast

    - Weekly forecasting for next week and next 4 weeks

    - Weekly accounting of shortfalls > recovery plansWeekly accounting of shortfalls recovery plans

    - Weekly accounting of changes in plan and forecast

    Every manager manages to every item in his/her plan

    39Manage to Every Plan Item

    MANAGE TO EVERY PLAN ITEM Corollaries: That which is not managed will not happen except by luck +

    If its not that important, it should not be in the plan

    Impossible to achieve every plan item recognize deviation and recover, locally or by plan changes: cutbacks, delays, additional resources.

    40Deviations May Come in Many Forms

  • 21

    DEVIATIONS COME IN MANY FORMSExamples

    Outcomes not available in time Milestones not passed in time Activities not finished in time Dependencies not satisfied in time

    Sizes larger than planned Staffing shortfalls Complexity higher than planned

    BUT MANY OTHER MEASURABLE/OBSERVABLE DEVIATIONS COME EARLIER IN TIME:

    41

    Hidden assumptions, hidden dependencies Appearance of important outputs not shown in the plan Substantial activities underway not shown in the plan Activities taking more staff than planned More re-work than planned

    Manage to Every Plan Item Contd

    MANAGE TO EVERY PLAN ITEM

    Corollaries: That which is not managed will not happen except by luck + If its not that

    important, it should not be in the plan

    Impossible to achieve every plan item recognize deviation and recover, locally or by

    plan changes: cutbacks, delays, additional resources.

    People respond to, and accomplish, things which they perceive are

    important to their leaders they perceive important those things on

    which their leaders act, not talk

    You have to act in a way that makes visible your concern with the item

    42

    Early items are as important as later ones

    That which is important must be managed made visible by management action

    More Tracking & Follow-up: By the Sponsor

  • 22

    MORE TRACKING & FOLLOW-UP: BY THE SPONSOR

    Project managers Progress & Issues report, weekly

    Regular reviews, typically once per month- Project manager is lead presenter often the only one- Basically for the information of sponsor and sponsors staff- Good questions + No, or minor, course corrections

    M j t t i ll ith i th i t l Major gates, typically with six-months intervals- Gate tied to a major, visible project milestone- Project manager is one of the presenters- With all stakeholders, providing their assessment- Go/no-go decisions: Incremental commitment

    43Management of Risk

    MANAGEMENT OF RISKIN PROJECT PLANNING AND EXECUTION

    Risk: The combination of the probability of an event

    and its adverse consequencesand its adverse consequences

    Categories of risk sources:

    Action, Assumption, Dependency, Estimate, etc.

    Prepare alternative courses of action

    Have fallback positions ready

    Risk assessment + mitigation is continuous

    A nasty source of risk: Expectations

    44Manage Expectations

  • 23

    C i t U d id

    MANAGE EXPECTATIONS

    Communicate Up, down, side-ways

    Plain-speaking, even bluntness, is good

    The earlier the better

    Generally audiences have a great sense of reality

    45

    Generally, audiences have a great sense of reality

    Staffing Plan

    STAFFING PLAN

    Numbers dont make up for too few good people

    A id b bbl t i t ffi l l Avoid bubbles or steps in staffing level

    Level headcount desirable all-rounders help

    Implement staffing plan with sense of urgency

    Making-up later for shortfalls near-impossible

    E tend sched le or Extend schedule, or

    Cut back on scope

    46Pick the Right People to Work With

  • 24

    PICK THE RIGHT PEOPLE TO WORK WITH

    People's performance follows an exponential curve: Good people 10x better than average people Average people infinitely better than poor people

    Poor people make work for other people

    Average people do work

    Good people solve problems, minimize the work

    47

    What to do with poor people? Identify them, then... Grow them Or move them out

    First Line Managers

    FIRST LINE MANAGERS

    PROJECT MANAGER

    1ST LINE MANAGER

    1ST LINE MANAGER

    1ST LINE MANAGER

    1ST LINE MANAGER

    1ST LINE MANAGER

    1ST LINE MANAGER

    48How Did the System X Story End

    1ST LINE MANAGER

    1ST LINE MANAGER

    1ST LINE MANAGER

  • 25

    FIRST LINE MANAGERS

    First line managers should be experienced, technically excellent

    Able to take over from any person in group, can break in new people

    TECHNICAL AND PERSONNEL LEADERS

    Should be a principal contributor to the design of the software

    Responsible for reviewing 100% of the code of his/her group

    Responsible for group-level planning and tracking

    Responsible for optimal work environment in the broadest sense

    Size of group needs to be limited to make the above realistic

    49

    Manager gets to learn who the good/average/poor people are

    Manager finds out early whether the software will work

    Manager can step in in case of staffing emergencies

    Managers review better and cheaper than code inspections

    Benefits justify the increased number of managers requiredHow Did the System X Story End

    HOW DID THE SYSTEM X STORY END..

    Release 2 Country B: Good design, chaotic process

    Release 3 Country G: Lesser design good processRelease 3 Country G: Lesser design, good process

    Release 4 Target for convergence, not finished

    Release 5 Unified design, coordinated process

    AFTER ALLAFTER ALL

    System X became a great commercial success

    Served by a single software system

    Series of Release 5 increments, never a Release 6 50Growing Risks for Project Managers

  • 26

    GROWING RISKS FOR PROJECT MANAGERS

    LOSS OF SOME CONTROL BECAUSE OF:

    Partial return of functional organizations More outsourcing and contractors More acquisition, less development More attempts to re-use software More service, cloud-based components Pull between agile and control More complexity > loss of intellectual control

    51Software Process Assessment

    SOFTWARE PROCESS ASSESSMENT

    52What If

  • 27

    WHAT IF

    Project manager does the wrong thing

    or

    Project manager unaware a process is defective

    53Software Engineering Processes

    SOFTWARE ENGINEERING PROCESSESAcquisitionSupply

    Life cycle model

    Stakeholder needsRequirements DesignConstructione cyc e ode

    InfrastructureProject portfolioHuman resourcesQuality strategyRe-use strategy

    Project planning

    ConstructionIntegrationDocumentationReview & auditTestProblem resolutionQuality assuranceAssets for re-use

    Project planningProject controlDecision makingRisk managementConfiguration mgtInformation mgtMeasurement

    Assets for re useQualificationInstallationAcceptance OperationMaintenanceDisposal D

  • 28

    DEFECT FAILUREProcess defect >

    Process failure >Software defect >

    Software failure >

    100-1,000 undiscovered software defects per million lines of code

    Even with defects, software works most of the time

    Software failure >Stakeholder dissatisfaction

    99.999% reliability with 5 MLOC and 5000+ defects

    But: Increasing pressure on processes that have no process defects

    55Process Defect

    PROCESS DEFECT

    Process defect >Process failure >Process failure >

    Software defect >Software failure >

    Stakeholder dissatisfaction

    A process may be defective in its:- Use

    56

    - Planning- Design- Control

    What A Project Manager Can Do

  • 29

    WHAT A PROJECT MANAGER CAN DOTO IMPROVE THE PROJECTS PROCESSES

    +TO ASSURE ALL ABOUT THE PROJECTS PROCESSES

    Root Cause Analysis

    Of selected software failures & defects

    57

    What went wrong process-wise?

    What Project Managers Cant Be

    WHAT PROJECT MANAGERS CANT BE:INDEPENDENT

    Software Process Assessment

    An activity outside the control of the project managerThat analyzes how work is done or not done

    Our way:Analysis by hunting for process defects

    That could lead to stakeholder dissatisfaction

    58SPA: Who. What, When?

  • 30

    SPA: WHO, WHAT, WHEN?

    Who: One or more assessors, we

    - Independent from the project manager

    - Typical sponsors: CEO, CTO, Div. President

    What: The processes of one or more projects, or the

    processes of an organization

    When (1): After completion of the process - Sometimes

    When (2): In the course the use of the processes Good!

    When (3): In the course of process planning Ideal!

    59How We Hunt for Process Defects

    HOW WE HUNT FOR PROCESS DEFECTS

    Interview selected project members + stakeholders 30-40 interviews/assessor, 4+ weeks

    A k l di ti f h f i t t Ask leading questions, for each process of interest

    - Is the process used? What is done? Who? How? When? Show!- Is the use planned & controlled? Who, etc.- Is the process designed? Who, etc.- What standards of performance?

    Drill down where there appears to be a problem Sample code & work products No extra testing

    60

    - What drives process improvement? Who, etc.

    Outcome of an Assessment Effort

  • 31

    OUTCOME OF AN ASSESSMENT EFFORT

    Hunt ends with report and presentation to sponsor+

    - Findings of process defects, unshakeable facts

    Recommendations for certain impro ements- Recommendations for certain improvements

    - Action plans on staff to implement recommendations

    No happy talk, project manager pain, appreciation later

    TBD: Sponsor charges project manager w/ implementation

    61The Take-Away Message.

    Assurance for sponsor and project managerthat the right processes are done right.

    THE TAKE-AWAY MESSAGE.

    62

  • 32

    Quality is the common theme in my project management work

    Stakeholder satisfaction + Less rework, less slack

    A l j t th t t i i As long as a project goes on, the cost meter is running

    The shorter a project, the less project cost

    Monetary benefit of the shorter schedule is higher than any

    cost of quality

    63

    BOTTOM LINE: QUALITY IS FREE


Recommended