Date post: | 11-Nov-2014 |
Category: |
Documents |
Upload: | cadastroimbecil-oh |
View: | 30 times |
Download: | 0 times |
© 2009 Project Management Experts, LLC 1
Schedule Oriented Project Planning
Joseph (Joe) D. Launi, PMPPresident & CEO
The Skills…The Knowledge…The Experiencewww.projectmanagementexperts.com
© 2009 Project Management Experts, LLC 2
Agenda
Introduction
Project/Product Analysis
Develop Project Management Plan:1. Project Scope Management/Scope Baseline2. Project Schedule Management/Schedule Baseline3. Project Human Resource Plan4. Cost Management Plan/Cost Baseline5. Quality Management Plan6. Procurement Management Plan7. Communications Management Plan8. Risk Management Plan
3
Agenda con’t.
Perform Project Integration and Finalize Project Management Plan
Closing
© 2009 Project Management Experts, LLC 4
INTRODUCTION
© 2009 Project Management Experts, LLC 5
Planning Goal is to Baseline the Project Management Plan
Scope
HR Chang
e
Mgt.
Time
Cost
Communications
QualityProcurement Risk
© 2009 Project Management Experts, LLC 6
Project Management Process Groups
Monitoring &Controlling Process
Executing Processes
Planning Processes
InitiatingProcesses
ClosingProcesses
PlanningProject Management Process Groups
© 2009 Project Management Experts, LLC 7
Mapping the Process Areas and the Knowledge Groups
Guide to the Project Management Body of Knowledge Fourth Edition
8.3 Perform Quality Control
8.2 Perform Quality Assurance
8.1 Plan Quality8. Project Quality Mgt.
7.3 Control Costs7.1 Estimate Costs7.2 Determine Budget
7. Project Cost Mgt.
6.6 Control Schedule
6.1 Define Activities6.2 Sequence Act.6.3 Est. Activ. Res.6.4 Est. Activ. Dur.6.5 Develop Sched
6. Project Time Mgt.
5.4 Verify Scope5.5 Control Scope
5.1 Collect Req.5.2 Define Scope5.3 Create WBS
5. Project Scope Mgt.
4.6 Cost Project or Phase
4.4 Monitor & Control Project Work4.5 Perform Integrated Change Control
4.3 Direct & Manage Project Execution
4.2 Develop Project Management Plan
4.1 Develop Project Charter
4. Project Integration Mgt.
Knowledge Areas Initiating Monitoring &
ControllingClosingExecuting
Planning
© 2009 Project Management Experts, LLC8
Mapping the Process Areas and the Knowledge Groups (cont.)
Guide to the Project Management Body of Knowledge Fourth Edition
12.4 Close Procurements
12.3 Administer Procurements
12.2 Conduct Procurements
12.1 Plan Procurements12. Project Procurement Mgt.
11.6 Monitor and Control Risks
11.1 Plan Risk Mgt. 11.2 Identify Risks11.3 Perform Qualitative Risk Anal.11.4 Perform Quantitative Risk Anal.11.5 Plan Risk Resp.
11. Project Risk Mgt.
10.5 Report Performance
10.3 Distribute Information10.4 Manage Stakeholder Expectations
10.2 Plan Communications
10.1 Identify Stakeholders
10. Project Comm.. Mgt.
9.2 Acquire Project Team9.3 Develop Project Team9.4 Manage Project Team
9.1 Develop HR Plan9. Project HR Mgt.
Project Management Process GroupsKnowledge
Areas Initiating Executing Monitoring & Controlling Closing
© 2009 Project Management Experts, LLC 9
Develop Project Management Plan
Scope
Cost
Time
Comm.
HR
Quality
Risk
Procurement
© 2009 Project Management Experts, LLC 10
Develop WBS and Project Schedule via PMBOK
12.2ConductProcure,
5.2Define Scope
6.1Define
Activities
6.2SequenceActivities
6.3Est.
Act. Res.
7.1Estimate
Costs
7.2Determine
Budget
8.1Plan
Quality
9.2Acquire
Proj. Team
6.5 DevelopSched.
6.4Est. Act.Duration
12.1Plan
Procure.
5.1CollectReq.
5.3CreateWBS
11.2Identify Risks
Develop Project Schedule and WBS via Schedule Oriented Project Planning (SOPP)
1.1CollectRequre.
1.3CreateWBS
1.2DefineScope
2.1Define
Activities
2.2Seq.
Activities
2.3Est.
Act. Res
2.4Est. Act. Durations
2.5Dev.
Sched.
3.1Dev.
HR Plan
WBSComplete
Draft/Final
Schedule
Start
Schedule Oriented Project Planning (SOPP)
6.1Plan
Procure.
1.1Collect
Require.
4.1Est. Costs
4.2Determine
Budget
7.1Plan
Comm.
8.1Plan Risk
Mgt.
8.2Id. Risks
8.3Perform
Qual. RiskAnalysis
8.4Perform
Quan. RiskAnalysis
8.5Plan RiskResponse
1.3CreateWBS
1.2Define Scope
2.1Define
Act.
2.2Seq. Act.
2.3Estimate Act. Res.
2.4Estimate Act. Dur.
2.5Dev. Sch.
5.1Plan
Quality3.1
Dev.HRPlan
WBSComplete
Draft/Final Sch.
Start
DevelopPM Plan
The Skills…The Knowledge…The Experiencewww.projectmanagementexperts.com
© 2009 Project Management Experts, LLC 13
Project Analysis Checklist and Survey (PACS)
Documenting what you know and don’t know about the project and/or product.
(Please give me a business card and I willemail PACS to you)
© 2009 Project Management Experts, LLC 14
1. Project Scope Management
1.1Collect
Requirements
1.3CreateWBS
1.2Define Scope
WBSComplete
Start
© 2009 Project Management Experts, LLC 15
1. Project Scope Management1.3 Create Work Breakdown Structure
BasementProject
1.0
Planning1.1
Design1.2
Construction1.3
Furnishing1.4
Closure1.5
Scope1.1.1
Schedule1.1.2
Cost1.1.3
• WBS• WBS Dictionary• Scope Baseline• Project Document Updates
© 2009 Project Management Experts, LLC 16
2. Project Time Management
2.1Define
Activities
2.2SequenceActivities
2.3Estimate Activity
Res.
2.4EstimateActivity
Durations
2.5DevelopSchedule
3.1Develop HR Plan
WBSComplete
Draft/Final
Schedule
© 2009 Project Management Experts, LLC 17
2. Project Time Management2.1 Define Activities
Planning Work Package(s)
Activity 1:
Activity 2:
Activity 3:
Design Work Package(s)
Activity 1:
Activity 2:
Activity 3:
Construction Work Package(s)
Activity 1:
Activity 2:
Activity 3:
Furnishing Work Package(s)
Activity 1:
Activity 2:
Activity 3:
Closure Work Package(s)
Activity 1:
Activity 2:
Activity 3:
Define Milestones as well
© 2009 Project Management Experts, LLC 18
2. Project Time ManagementNetwork Diagram
EndStart
A
G
E
F
D
B C3
1
42
4
53
9
5
8
Critical Path Analysis
Testing
Development
© 2009 Project Management Experts, LLC 19
2. Project Time Management2.5 Develop Schedule
• Develop schedule/time management approach• Schedule baseline will be created after the PM
Plan is approved.• Changes to the schedule baseline must be
approved via change control.• Approved schedule changes will be re-baselined
along with cost andscope changes after the change has been approved via change control.
• How actual time will be captured and entered into the PMIS.
© 2009 Project Management Experts, LLC 20
2. Project Time Management2.5 Develop Schedule
Information Captured in a Project Schedule
• Level of Effort• Duration• Resources• Start and Finish Dates by Activity and Task• Dependencies• Milestones• Deliverables• Comments• WBS numbers• Etc.
© 2009 Project Management Experts, LLC 21
3. Project Human Resource Management
2.1Define
Activities
2.2SequenceActivities
2.3Estimate Activity
Res.
2.4EstimateActivity
Durations
2.5DevelopSchedule
3.1Develop HR
PlanWBS
Complete
© 2009 Project Management Experts, LLC 22
3. Project Human Resource Management3.1 Develop HR Plan
Identify Potential Project Team and Create Project Organization Chart
Bill JonesProject Mgr
Shirley LongDevelopment
Harry TestorTesting
Hugo BerardiQA
Joe TechnicalProgrammer
Karen SmithProgrammer
What are the advantages of developing an organization
chart?
© 2009 Project Management Experts, LLC 23
3. Project Human Resource Management3.1 Develop HR Plan
Create Responsibility Assignment Matrix
PERSONACTIVITY
Analysis
Design
Develop
Test
Lou Jim George Karen BillMary Flo
M – Manager; L – Technical Lead, A - Accountable; TM – Team Member
M
M
M
M
L,A
L,A
L,A
L,A
--
--
--
--
TM
TM TM
TM
TMTM
TM TM--
--
--
--
----
----
© 2009 Project Management Experts, LLC 24
4. Project Cost Management
4.1Estimate
Costs
4.2Determine
Budget
2.5DevelopSchedule
Draft/Final
Schedule
© 2009 Project Management Experts, LLC 25
4. Project Cost Management4.1 Estimate Costs
Approximating monetary resources(1) Attach labor rates(2) Estimate non-labor costs(3) Finalize cost estimateTASKS NON-LABOR
COSTSLABOR COSTS
TOTAL PLANNED
COST1. Planning2. Design3. Construction4. Furnishings5. Closure
TOTAL:
© 2009 Project Management Experts, LLC26
4. Project Cost Management
Cost Based Metrics Terminology• Planned Value (PV): Budgeted cost of the work scheduled
• Earned Value (EV): Budgeted amount in the work actually
completed
• Actual Cost (AC): Total cost incurred in accomplishing work
• Estimate to Complete (ETC): Estimated remaining amount
to complete the project
• Estimate at Completion (EAC): Estimated cost of the entire
project including work performed and work to be performed.
• Budget at Completion (BAC): Total budgeted cost of the
project.
© 2009 Project Management Experts, LLC27
4. Project Cost Management
$
Time
EV
PV
AC
What Happened? To Implement anEarned Value SystemYou Must:- Baseline- Capture Accurate
Physical % Complete
BAC
© 2009 Project Management Experts, LLC28
4. Project Cost Management
Cost Based Metrics Formulas
• Cost Variance (CV): EV – AC• Cost Performance Index (CPI): EV/AC
• Schedule Variance (SV): EV – PV• Schedule Performance Index (SPI): EV/PV
• EAC based on new estimate: New ETC + AC
• EAC based upon atypical variances: AC + BAC-EV
• EAC based in current spending patterns: BAC/CPI
© 2009 Project Management Experts, LLC 29
5. Project Quality Management
8.1Plan Risk
Management
8.2IdentifyRisks
2.5DevelopSchedule
5.1Plan
Quality
Draft/Final
Schedule
© 2009 Project Management Experts, LLC 30
Develop Quality Management Approach
• Quality baseline will be created after the PM Plan is approved.• Changes to the quality baseline must be approved via change control.• Approved quality changes will be re-baselined along with schedule and
scope changes after the change has been approved via change control.• Actual quality will be captured and entered into the PMIS by ……• The following quality related metrics will be captured: ……• The following are not included in the quality of this project: .…• The following checklists will be used to assure the quality of this project:
……
5. Project Quality Management5.1 Plan Quality
© 2009 Project Management Experts, LLC 31
6. Project Procurement Management
6.1Plan
Procurements
8.1Plan Risk
Management
8.2IdentifyRisks
Draft/Final
Schedule
2.5DevelopSchedule
© 2009 Project Management Experts, LLC 32
Determine Contract Type
FP FPI CPAF T&M CPIF CPFF
Seller Risk
Buyer Risk
FP: Fixed priceFPI: Fixed price plus incentiveCPAF: Cost plus award feeT&M: Time and materialsCPIF: Cost plus incentive feeCPFF: Cost plus fixed price
6. Project Procurement Management6.1 Plan Procurements
© 2009 Project Management Experts, LLC 33
7. Project Communications Management
7.1Plan
Comm.
8.1Plan Risk
Management
8.2IdentifyRisks
Draft/Final
Schedule
2.5DevelopSchedule
© 2009 Project Management Experts, LLC 34
7. Project Communications Management7.2 Plan Communications
Document Communication Requirements
Who?
When?Why?
What?
© 2009 Project Management Experts, LLC 35
Document Deliverable Distribution Requirements
Deliverable Recipient
Detailed Design Doc. Bill, Henry, Julie
Change Requests CCB, Bill
7. Project Communications Management7.2 Plan Communications
© 2009 Project Management Experts, LLC 36
8. Project Risk Management
8.1Plan Risk
Management
8.2IdentifyRisks
8.3Perform
QualitativeRisk Analysis
8.4Perform
QuantitativeRisk Analysis
8.5Plan Risk
Responses
2.5DevelopSchedule
Draft/Final
Schedule
© 2009 Project Management Experts, LLC 37
8. Project Risk Management8.1 Plan Risk Management
• Document risk management approach
• New risks will be added to the register throughout the project.
• All risks will be monitored throughout the project.
• Risk owners are responsible for executing the response plan.
• Risks will be discussed at all status meetings.
© 2009 Project Management Experts, LLC 38
Identify risks, perform qualitative and quantitative risk analysis, and develop response plan
Risk RegisterProject Name: Project Manager:
Assessment
ID Risk Prob Impact Score Trigger Response Plan Contingency Owner
1
2
8. Project Risk Management8.2-8.5 Perform Risk Assessment & Create Risk Register
© 2009 Project Management Experts, LLC 39
Project Integration and Finalization of PM Plan
1. Update WBS with risk response activities
2. Document the project management life cycle
3. Document the integrated change control process
4. Document how the Project ManagementInformation System (PMIS) will be used
5. Develop the final project schedule and highlightthe critical path
6. Finalize the project management plan
INVICTUSWilliam Ernest Henley (1849–1903)
Out of the night that covers meBlack as the Pit from pole to pole,
I thank whatever gods may beFor my unconquerable soul
In the fell clutch of circumstanceI have not winced nor cried aloud
Under the bludgeonings of chanceMy head is bloody, but unbowed
Beyond this place of wrath and tearsLooms but the Horror of the shade,
And yet the menace of the yearsFinds, and shall find me unafraid
It matters not how strait the gait,How charged with punishments the scroll,
I am the master of my fate:I am the captain of my soul.
INVICTUSWilliam Ernest Henley (1849–1903)
Out of the night that covers meBlack as the Pit from pole to pole,
I thank whatever gods may beFor my unconquerable soul
In the fell clutch of circumstanceI have not winced nor cried aloud
Under the bludgeonings of chanceMy head is bloody, but unbowed
Beyond this place of wrath and tearsLooms but the Horror of the shade,
And yet the menace of the yearsFinds, and shall find me unafraid
It matters not how strait the gait,How charged with punishments the scroll,
I am the master of my fate:I am the captain of my soul.
..and I will stop using duct tape
© 2009 Project Management Experts, LLC 42
Reference Material
The Project Management Institute’s (PMI’s) A Guide to the Project Management Body of Knowledge (PMBOK) Version 4 was used as the primary reference for the material in this course.
© 2009 Project Management Experts, LLC 43
Questions
The Skills…The Knowledge…The Experiencewww.projectmanagementexperts.com
© 2009 Project Management Experts, LLC 44
Joseph (Joe) D. Launi, PMPPresident & CEO
[email protected] Rangers Way SELeesburg, VA 20175Office: 703-777-1689Mobile: 703-362-5774
Thank You