+ All Categories
Home > Documents > Scheduling Basics

Scheduling Basics

Date post: 18-Mar-2016
Category:
Upload: reyna
View: 73 times
Download: 0 times
Share this document with a friend
Description:
Scheduling Basics. Dr. Narayan Bodapati, P.E. CE342: Construction Planning and Scheduling Strategies Missouri Science &Tech January 28, 2013. Project Planning and Scheduling Planning of projects is critical to the success of a project. Examples of schedules/penalties - PowerPoint PPT Presentation
Popular Tags:
19
Dr. N. Bodapati, P.E. Scheduling Basics Dr. Narayan Bodapati, P.E. CE342: Construction Planning and Scheduling Strategies Missouri Science &Tech January 28, 2013
Transcript
Page 1: Scheduling Basics

Dr. N. Bodapati, P.E.

Scheduling Basics

Dr. Narayan Bodapati, P.E.

CE342: Construction Planning and Scheduling StrategiesMissouri Science &Tech

January 28, 2013

Page 2: Scheduling Basics

Dr. N. Bodapati, P.E.

Project Planning and Scheduling

Planning of projects is critical to the success of a project.

A. Examples of schedules/penalties

1. Residence hall of a universityIf not completed by scheduled

semester start date penalty for housing 300 students in a hotel @ $70/day/2 students: $11,000/day

Page 3: Scheduling Basics

Dr. N. Bodapati, P.E.

B.Need a plan

1. Schedule development2. Communicate the schedule

• Graphics/reports3. Manage the plan

• Monitor the plan• Are we on schedule?• What are the delays?• How do we get back on schedule?

• Develop a recovery schedule

Page 4: Scheduling Basics

Dr. N. Bodapati, P.E.

Typical Project Schedules

1.Hospital bldg $20m cost

2.Airport Project, St. Louis: $2.6 billion – 15 years

3.MetroLink: $500m – 6 years

4.New Mississippi Bridge: $1.6 Billion – 10 years

5.Cardinals Stadium: 2 years

6.Warehouse and office: $ 2 million: 9-12 months

design bid construction12 months 3 months 18 months

Total:33 months

Page 5: Scheduling Basics

Dr. N. Bodapati, P.E.

Introduction:1. Scheduling Basics

A schedule is a roadmap/timetable for a project. A schedule answers the following questions:

What is the project duration? (or what is the completion date?) What is the status of the project? When will it be completed? Can the project duration be shortened or compressed? What is the impact of change orders on the completion date? Is there a delay on the project? How many days/weeks is the project behind schedule? Who caused the delay? Is it possible to recover the delay and bring the project back on

schedule? What does the recovery/acceleration cost? What is the new completion date?

Page 6: Scheduling Basics

Dr. N. Bodapati, P.E.

2.    Uses of Schedules

A. Owner’s Perspective Project Duration Funding Requirements Return on Investment Project Phasing & Beneficial Occupancy

Dates

Page 7: Scheduling Basics

Dr. N. Bodapati, P.E.

B. Contractor’s Perspective Cash Flow Requirements Deployment of Men, Materials, & Labor Procurement of Resources Critical Activities vs. Non-Critical Activities Sub Contractor Coordination Delay Claims Analysis Liquidates Damages

Page 8: Scheduling Basics

Dr. N. Bodapati, P.E.

3. Scheduling Considerations

A.  Internal Constraints Project Scope and Complexity Project Funding Budget or Time Driven Project Phasing/Early Occupancy ROI Considerations

Page 9: Scheduling Basics

Dr. N. Bodapati, P.E.

B.  Project Delivery Methods

Design-Bid-Build

Fast Track

C M Approach

Design-Build

Page 10: Scheduling Basics

Dr. N. Bodapati, P.E.

C.  External Constraints Weather/Construction Seasons Regulatory Agency Approvals Utility Relocations/Connections Environmental Constraints Cemetery Relocations Contracting Climate Labor Strikes

Page 11: Scheduling Basics

Dr. N. Bodapati, P.E.

Return on Investment (ROI) Considerations

$30m

mill

ions

Cost$$35

Crash cost: $35 millionCrash duration: 18 months

Normal cost: $30 millionNormal duration: 24 months

18months

20months

22months

24months

Page 12: Scheduling Basics

Dr. N. Bodapati, P.E.

Schedule Control

1 Establish a baseline schedule

2 Update the schedule on a regular basis

3 Determine the new completion date/delay

4 Produce a recovery schedule to bring the project back on schedule

Page 13: Scheduling Basics

Dr. N. Bodapati, P.E.

Schedule Control

Project Start Project Finish

Contract Duration

Progress DateProgress

Progress

Delay ForecastCompletionDate

BaselineSchedule

UpdateSchedule

Recovery Schedule

Page 14: Scheduling Basics

Dr. N. Bodapati, P.E.

Recovery Techniques

1 Determine the delay

2 Examine the critical path

3 Overlap activities if possible

4 Shorten activity durations where feasible (select activities which are least expensive to compress)

5 Change construction method (e.g., cast-in-place concrete to precast concrete)

Page 15: Scheduling Basics

Dr. N. Bodapati, P.E.

C Examples of Lack of Schedule Control

Denver International Airport, Denver, CO

Schedule Delay: 18 months

Cost Overrun: $ 3.2 billion

Federal Courthouse, St. Louis, MO

Schedule Delay: 24 months

Page 16: Scheduling Basics

Dr. N. Bodapati, P.E.

Edwardsville High School, Edwardsville, IL

Schedule Delay: 19 months

Kiel Center, St. Louis, MO

Schedule Delay: 7 months

Delay Claims: $ 5.5 million

Page 17: Scheduling Basics

Dr. N. Bodapati, P.E.

D Example of good use of schedule Caltrans Bridge Project on the Santa Monica

Freeway, CA

Contract Cost: $14. 9 million

Bonus Clause: $200,000/day of early completion

Contract completed 74 days ahead of schedule

Bonus Collected: 74 days x $200,000: $14.8 million

Page 18: Scheduling Basics

Dr. N. Bodapati, P.E.

Schedule Development Identify a list of activities

e.g. Mobilization, site grading Quantify activities

e.g. Excavation: 3,000 cyds Apply production rates to determine durations

e.g. Excavation: 600 cyds/day (5 days) Establish logic and develop the network

e.g. which activities must be completed before starting a particular activity

Calculate and establish the project duration and critical path

Adjust/revise the logic and recalculate Produce bar charts and reports

Page 19: Scheduling Basics

Dr. N. Bodapati, P.E.

Good work, but I think we need a little more detail right here.


Recommended