Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1
16
Scheduling Operations Scheduling Operations IDS 605 IDS 605 Spring 1999 Spring 1999
Transcript
Page 1: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Scheduling OperationsScheduling Operations

IDS 605IDS 605Spring 1999Spring 1999

Page 2: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.
Page 3: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Data Collection for SchedulingData Collection for Scheduling

Jobs Activities Employees Equipment Facilities

Transparency 18.1

Page 4: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Managerial ConsiderationsManagerial Considerations

Meeting customer due date

Minimizing flow time Minimizing WIP

inventory Minimizing costs Minimizing idle time

» equipment» employee

Transparency 18.2

Page 5: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Shop Floor Control - SchedulingShop Floor Control - Scheduling

Suppose we have a group of jobs waiting in front of a work center. How do we decide which job to run next (i.e., priority assignment)?

We will examine 4 common priority rules. We will evaluate the performance of the

rules via shop efficiency and customer service measurements.

Page 6: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

JOB PRODUCTION TIME UNTILNUMBER TIME (HRS.) DUE (HRS.)

M1 2 3M2 3.1 7M3 1.4 6M4 2.6 5M5 0.5 8M6 1.9 12

Page 7: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

First-Come First-Served (FCFS) First-Come First-Served (FCFS) SequenceSequence

Sequence: M1-M2-M3-M4-M5-M6

M1 M2 M3 M4 M5 M6

0 1 2 3 4 5 6 7 8 9 10 11

Average Flow Time:

2+5.1+6.5+9.1+9.6+11.5 = 43.8/6 = 7.30 hours

Average Number of Jobs in the System:

2(6)+3.1(5)+1.4(4)+2.6(3)+0.5(2)+1.9(1) = 43.8/11.5 =3.81 jobs

Average Job Lateness ~ MAX((c-d),0)

0+0+0.5+4.1+1.6+0 = 6.2/6 = 1.033

Page 8: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

SPT (a.k.a. SON) SequenceSPT (a.k.a. SON) Sequence

Sequence: M5-M3-M6-M1-M4-M2 0.5 1.4 1.9 2.0 2.6 3.1

M5 M3 M6 M1 M4 M2

0 1 2 3 4 5 6 7 8 9 10 11

Average Flow Time:

0.5 + 1.9 + 3.8 + 5.8 + 8.4 + 11.5 = 31.9/6 = 5.32 hours

Average Number of Jobs in the System:

.5(6)+1.4(5)+1.9(4)+2.0(3)+2.6(2)+3.1(1) = 31.9/11.5 =2.77 jobs

Average Job Lateness ~ MAX((c-d),0) M1 M4 M2

0+0+0+2.8+3.4+4.5 = 10.70/6 = 1.78 hours

Page 9: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Earliest Due Date (EDD) Earliest Due Date (EDD) SequenceSequence

Sequence: M1-M4-M3-M2-M5-M6

M1 M4 M3 M2 M5 M6

0 1 2 3 4 5 6 7 8 9 10 11

Average Flow Time:

2.0 + 4.6 + 6.0 + 9.1 + 9.6 + 11.5 = 42.8/6 = 7.13 hours

Average Number of Jobs in the System:

2(6)+2.6(5)+1.4(4)+3.1(3)+0.5(2)+1.9(1) = 42.8/11.5 =3.72 jobs

Average Job Lateness ~ MAX((c-d),0) M2 M5

0+0+0+2.1+1.6+0 = 3.70/6 = 0.6 hours

Page 10: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Critical Ratio (CR) SequenceCritical Ratio (CR) SequenceCRITICAL RATIOS:M1: 3/2 = 1.5 M4: 5/2.6 = 1.9M2: 7/3.1 = 2.3 M5: 8/0.5 = 16M3: 6/1.4 = 4.3 M6: 12/1.9 = 6.3

Sequence: M1-M4-M2-M3-M6-M5

M1 M4 M2 M3 M6 M5

0 1 2 3 4 5 6 7 8 9 10 11

Average Flow Time:

2.0 + 4.6 + 7.7 + 9.1 + 11.0 + 11.5 = 45.9/6 = 7.65 hours

Average Number of Jobs in the System:

2(6)+2.6(5)+3.1(4)+1.4(3)+1.9(2)+0.5(1) = 45.9/11.5 =3.99 jobs

Average Job Lateness ~ MAX((c-d),0) M2 M3 M5

0+0+0.7+3.1+0+3.5 = 7.30/6 = 1.22 hours

Page 11: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

SummarySummary

CRITERIA FCFS SPT EDD CR

Average Flow Time 7.3 5.32 7.13 7.65

Average Number of 3.81 2.77 3.72 3.99Jobs In System

Average Job 1.03 1.78 0.6 1.22Lateness

Page 12: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Jobs to be ProcessedJobs to be Processedon Two Machineson Two Machines

Processing time (hours) Job Computing Printing A 1.5 1.0 B 1.0 .75 C .5 1.25 D 2.0 1.5 E .75 .5

Transparency 18.4

Page 13: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Processing of Computer Jobs Processing of Computer Jobs Based on Sequencing by Based on Sequencing by

Johnson’s RuleJohnson’s Rule

Transparency 18.5 (Exhibit 18.6)

Page 14: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Forward Schedule for Four Jobs Forward Schedule for Four Jobs with Finite Loadingwith Finite Loading

Transparency 18.6 (Exhibit 18.7)

Page 15: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Backward Schedule for Jobs with Backward Schedule for Jobs with Infinite LoadingInfinite Loading

Transparency 18.7 (Exhibit 18.8)

Page 16: Scheduling Operations IDS 605 Spring 1999. Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.

Gantt Load Chart forGantt Load Chart forForward ScheduleForward Schedule

Transparency 18.8 (Exhibit 18.10)