School Sanitation and Hygiene Education Programme School Toilet/Urinal Design and Drawing UNICEF, Nepal March, 2006
Transcript
Page 1: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

School Sanitation and Hygiene EducationProgramme

School Toilet/UrinalDesign

andDrawing

UNICEF, NepalMarch, 2006

Page 2: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

School Toilet/UrinalDesign

andDrawing

Page 3: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

-v- Note:-

A. Opening Details1. Doors (D)2. Collapsible Gate3. Ventilations (V)

75 x 180cm = 2Nos.90 x 180 cm = 2Nos.75 x 45 cm = 4 Nos.98.5 x 45 cm = 8 Nos.

B. Value of XS.No. No. of Students

12

Up to 200201 to 400

Value ofX

326.75 cm463.00 cm

All mesurements are in centimeters

SCHOOL SANITATION PROGRAMMEwater Supply and Sanitation Division

Office/UNICEF

Designed By:Yagya ShresthaConsultant, UNICEF

SCHOOL TOiLET/URlNAL(Capacity: students<400)

PLAN

Parsa/Chitwan/Nawalparasi/Kaptlvastu/Dang Revised Date: January, 2005 Date: October 14, 2003 Drg.No.:

1 of 7

Page 4: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

SECTION 7WV

All mesurements are in centimeters

SCHOOL SANITATION PROGRAMMEwater Supply and Sanitation Division

Office/UN ICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL TOILET/URINAL(Capacity: students<400)

SECTIONAL VIEW

Parsa/Chitwan/Nawalparasi/Kapilvastu/Dang Revised Date: January, 2005 Date: October 14, 2003 Drg.No.:

5 of 7

Page 5: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

40 x 40 x 4mm thk MS 25 x 25 x 4mm thk MS

400

750

anqle

Hi105 |

angle frame for shutter

250 mm long tower-bolt/

1800

5 mm thk MS plateholdfast

25 x 25 x 4 mm MS angle frame

100

l\=100,00

95

100012 mm diaMS rcd@ I

Ventilation

Door Frame Door Shutter

(AH measurements are in mm)

SCHOOL SANITATION PROGRAMMEWater Supply and Sanitation Diciston

Office/UN ICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL TOILET/URINALDETAILS OF DOORS & VENTILATIONS

Parsa/Chitwan/Nawalparast/Kapilvastu/Dang Revised Date: January 2005 Date: 14 October 2003Drg.No.:

6 of 7

Page 6: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Note:-

188

i

132

1—

32.

l

r~I

100

X+287

X + 23

I I

253

(X+23V2

100 32

132

100

Value of XS.No.

12

188

288

No. of Students

Up to 200201 to 400

Value ofX

326.75 cm463.00 cm

All mesurements are in centimeters

SCHOOL SANITATION PROGRAMMEwater Supply and Sanitation Division

Office/UN ICEF

Designed By:Yagya ShresthaConsultant, UNICEF

SCHOOL TOlLET/URiNAL(Capacity: students<400)

LAYOUT PLAN

Parsa/Chitwan/Nawalparasi/Kapilvastu/Dang Revised Date: January, 2005 Date: October 14, 2003 Drg.No.:

7 of 7

Page 7: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

23.00

A. Opening Details1. Doors (D)2. Collapsible Gate3. Ventilations (V)

All mesurements are in centimeters

401 to 600601 to 800801 to 1000

1001 and above

75x180cm = 4Nos.90x145cm = 2Nos.90 x 45cm = 6Nos.

100x 45cm = 2Nos.

Value of X165 cm240 cm315 cm390 cm

SCHOOL SANITATION PROGRAMME

Water Supply and Sanitation Division Office/UNICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL TOILET/URINAL(Capacity: students>401)

PLAN

Parsa, Chttwan, Nawalparasi, Kapilvastu & Dang Revised Date: January, 2005 Date: October 14, 2003Drg. No.:

1 of 8

Page 8: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

10 cm thk RCC roof CGI Roof with 2 nos of transparentsheets in each side

oor

FRONT

All me sure merits are in centimeters LEFT

SCHOOL SANITATION PROGRAMME

Water Supply and Sanitation Division Office/UNICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL TOILET/URINAL(Capacity: students>401)

ELEVATIONS

Parsa, Chitwan, Nawalparasi, Kapilvastu & Dang Revised Date: January, 2005 Date: October 14, 2003Org. Ho.:

2 of 8

Page 9: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

ELEVATION (right)

Ver J ationUrinal (Girls)

Separator

Urinal (Boys)t - 65 ,00 -

SECTION 'B-B'All mesurements are in centimeters

SCHOOL SANITATION PROGRAMME

Water Supply and Sanitation Division Office/UNICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL TOILET/URINAL(Capacity: stuclents>401)

ELEVATION & SECTION

Parsa, Chitwan, Nawalparasi, Kapilvastu & Dang Revised Date: January, 2005 Date: October 14, 2003Drg. to.:

3 of 8

Page 10: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Floor Finishing Over 10 cm InkPCC (1:2:4)

"Flat Brick Soling

Sand Filing

SECTION 7WV

All mesurements are in centimeters

SCHOOL SANITATION PROGRAMME

Water Supply and Sanitation Division Office/UNICEF

Parsa, Chitwan, Nawalparasi, Kapilvastu & Dang

Designed By:

Yagya ShresthaConsultant, UNICEF

Revised Date: January, 2005

SCHOOL TOILET/URINAL(Capacity: students>401)

SECTION

Date: October 14, 2003Drg. No.:

4ofi

Page 11: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

10 cm thick RCC roof slab over

onj

Natural Ground

od

-l-

All mesurements are in centimeter

1

90 cm high Separators

SECTION 'C-C

SCHOOL SANITATION PROGRAMME

Water Supply and Sanitation Division Office/UNICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL TOILET/URINAL(Capacity:stuctents>401)

SECTION

Parsa, Chitwan, Nawalparasi, Kapilvastu & Dang Revised Date: January, 2005 Date: October 14, 2003Drg. No.:

5of8

Page 12: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Roof Truss(Material: MS Circular Pipes, Span = 471 cm)

4 mm thk quesset plats

Details of BDetails of A

All mesurements are in centimeters

SCHOOL SANITATION PROGRAMMEWater Supply and Sanitation Division Office/UNICEF

Parsa, Chitwan.Nawalparasi, Kapiivastu & Dang

Designed By:

Yagya ShresthaConsultant, UNICEF

Revised Dale: January, 2005

SCHOOL TOILET/URINAL

TRUSS DETAILS

Date: October 14, 2003 Dr9 NO6

Page 13: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

40 x 40 x 4mm thk MS 25 x 25 x 4mm thk MSangle frame for shutter

5 mm thk MS plateholdfast

25 x 25 x 4 mm MS ancte frame

250 mm long tower-bolt/

ao

100.00 T\

g£gr c

J bJ1 i

-1000.00-

Ventilation

25 x 4 mm MS strips

Door Frame Door Shutter

(Alt measurements are in mm)

SCHOOL SANITATION PROGRAMMEWater Supply and Sanitation Dicision

Office/UN ICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL TOILET/URINALDETAILS OF DOORS & VENTILATIONS

Parsa/Chitwan/Nawalparasi/Kapilvastu/Dang Revised Date: January 2005 Date: 14 October 2003Drg.No.:

7 of 8

Page 14: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Note:-

ValueofXS.No. No. of Students

1234

401 to 600601 to 800801 to 10001001 and above

Value ofX

165 cm240 cm315 cm390 cm

Ail mesurements are in centimeters

SCHOOL SANITATION PROGRAMMEWater Supply and Sanitation Division

Office/UN ICEF

Designed By:Yagya ShresthaConsultant, UNICEF

SCHOOL TOILET/URINAL(Capacity: students<400)

LAYOUT PLAN

Parsa/Chitwan/Nawalparasi/Kapilvastu/Dang Revised Date: January, 2005 Date: October 14, 2003 Drg.No.:

8 of 8

Page 15: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

B

All mesurements are in centimeters

77 77 77 77 /

-571.50-

' 77 7~\77 77

-148.50-

(X+194,50)-

23.00

77 771%slo

77 77 77 // // 77 // //

(-70.0DH

Urinal (Girls)

15.00-77 77 7/

1% slope

(-6o.(xH i

oXh dhh (Khilope

77 77

L__| MO K I. _iUrinal (Boys)

i slopeV 77 77KV 77 7J\ 77 77 77 77 /7 77

X'7 77 77 7.

_ L-111.50

Lavaf of Straw fPaf^>

25.00

SECTIOM X-X

Note:-A. Opening Details

1. Doors (D)2. Ventilations (V)S. VaijeofXS.No. No. of Students

1 401 to 6002 601 to 8003 801 to 1000

4 1001 and above

75x180cm =100x 45cm = 4Nos.

Value of X165 cm240 cm315 cm

390 cm

SCHOOL SANITATION PROGRAMME

Water Supply and Sanitation Division Office/UNICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL URiNAL(Capacity: stuctents>401)

PLAN

Parsa, Chitwan, Nawalparasi, Kapilvastu & Dang Revised Date: January, 2005 Date: October 14, 2003Drg. No.:

1 Of 7

Page 16: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

CGI Roof

oqin

FRONT

A I! mesurements are in centimeterLEFT

SCHOOL SANITATION PROGRAMME

Water Supply and Sanitation Division Office/UNICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL URINAL(Capacity: students>401)

ELEVATIONS

Parsa, Chitwan, Nawalparasi, Kapilvastu & Dang Revised Date: January, 2005 Date: October 14, 2003Drg. No.:

2 of 7

Page 17: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

• • ^ ^ ^ ^ ^ ^ ^M ^B ^H! • • MM ••§ ••§ • • HH • • flH MB

ELEVATION (right)

All mesurements are in centimeterSECTION 'A-A1

SCHOOL SANITATION PROGRAMME

Water Supply and Sanitation Division Office/UNiCEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL URtNAL(Capacity:students>401)

ELEVATION& SECTION

Parsa, Chitwan, Nawalparasi, Kapilvastu & Dang Revised Date: January, 2005 Date: October 14, 2003Org. No.:

3 of 7

Page 18: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Natural Ground

in• M -

7.50-

|t

Jl

-22.50

-(45.00)-

90 cm high Separators

SECTION 'B-B1

CGI Roofing cover

10in

inin

RCC Cover SlabEartti Bach Filling Leactimo Pit

/ RCCRirxi

Ail mesurements are in centimeter

SCHOOL SANITATION PROGRAMME

Water Supply and Sanitation Division Office/UNICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL URINAL(Capacity: students>401)

SECTION

Parsa, Chitwan, Nawalparasi, Kapilvastu & Dang Revised Date: January, 2005 Date: October 14, 2003Drg. No.:

4 of 7

Page 19: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

I B ^B ^H ^M ^M ^B ^B ^M ^M ^M ^ » ^M ^M ^M ^M »» «^

32 mm <(» MS Pipe

Roof Truss(Material: MS Circular Pipes, Span = 471 cm)

15,00

50 mm ili MS Pipe

M10 Nut-bolts

32 mm ifr MS Pipe

25 mm i|> MS Pipe

4 mm thk guesset plate

Details of B Details of A

All mesurements are in centimeter

SCHOOL SANITATION PROGRAMME

Water Supply and Sanitation Division Office/UNICEF

Designed By:Yagya Shrestha

Consultant, UNICEF

SCHOOL URINAL

TRUSS DETAILS

Parsa, Chitwan, Nawalparast, Kapilvastu & Dang Revised Date: January, 2005 Date: October 14, 2003 Drg Nos:,5 o( 7

Page 20: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

40 x 40 x 4mm thk MS 25 x25 x4mm thkMSangle frame for shutter

250 mm long tower-bolt/

25 x 25 x 4 mm MS anqte frame

5 mm thk MS plateholdfast

I2 mm 4a MS rod @ 100 DC

Door Frame Door Shutter

(All measurements are in mm)

SCHOOL SANITATION PROGRAMMEWater Supply and Sanitation Dicision

Office/UN ICEF

Designed By:

Yagya ShresthaConsultant, UNICEF

SCHOOL URINALDETAILS OF DOORS & VENTILATIONS

Parsa/Chitwan/Nawalparasi/Kapilvastu/Dang Revised Date: January 2005 Date: 14 October 2003Drg.No.:

6 of 7

Page 21: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Note:-

Value of XS.No. No. of Students

1234

401 to 600601 to 800801 to 10001001 and above

Value ofX

165 cm240 cm315 cm390 cm

All mesurements are in centimeters

SCHOOL SANITATION PROGRAMMEWater Supply and Sanitation Division

Office/UN ICEF

Designed By:Yagya ShresthaConsultant, UNICEF

SCHOOL URINAL(Capacity: students<401)

LAYOUT PLAN

Parsa/Chitwan/Nawalparasi/Kapilvastu/Dang Revised Date: January, 2005 Date: October 14, 2003 Drg.No.:

7 of 7

Page 22: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Single Unit Toilet Block

Page 23: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

I krra I i

610 $$ 576 tt 578 (5 573 8V STB «f8T5 J t 830 j | 831 " (

[-150 mm LEV

G1! Flower Bed

ELEVATION ELEVATION

1

i

40 Dm fjl

^ -

^- ? i f j i i LSI H(e

!

s

OPENING SCHEDULEELEVATION GROUND FLOOR PLAN

S.1M.

1.

2.

3

4.

5,

6

7.

DESCRIPTION

DOOR(D2)

DOOR (D3)

DOOR (D3)

ENTRANCE GATE (EG1)

ENTRANCE GATE (E61J

WINDOW GRILL (WG'i)

WINDOW GRILL (WG2)

SIZE

900 XZ175

592X2175

592 X 2175

12D0 X 1950

B75X 1950

S75 X 450

1250X450

NOs

1

3

3

1

9

6

MATERIAL

METAL FRAME

METAL FRAME

METAL FRAME

METAL FRAME

METAL FRAME

METAL. FRAME

METAL FRAME

REMARKS

LEFT OPENING

RIGHT OPENING

LEFT OPENING

RIGHT OPENING

LEFT OPENING

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepa!

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Single Unit Toilet BlockGROUND FLOOR PLAN

Drawing no: A - j Scale:

Dale: 25lh December. 2005

Drawn tiy: P.Thakur |ctiecked by: {Approved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC

Page 24: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

ELEVATION

ELEVATION

..;

ELEVATION

ELEVATION GROUND FLOOR PLANOPENING SCHEDULE

SN.

1

2.

3

4.

5

6.

DESCRIPTION

DOOR(D2)

DOOR (03)

DOOR (D3)

ENlRANCEGATEfEG'j

ENTRANCE GATE (EG 1)

WINDOW GRILL (WG1)

WINDOW GRILL (WG2)

SIZE

1200X2575

592 X 2175

592X2175

875X195U

875 X1950

875 X 450

1250X 450

NOs.

1

3

3

\

1

9

MATERIAL

METAL FRAME

METAL FRAME

METAL FRAME

METAL FRAME

METAL FRAME

METAL FRAME

METAL FRAME

REMARKS

LEFT OPENING

RIGHT OPENING

LEFT OPENiNG

RIGHT OPENING

LEFT OPEK1KG

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PS1P)

Single Unit Toilet Block (Alternate)GROUND HOOR PLAN

Drawing no: A - ] Scale:Dale: 2Sir December. 2005

Drawn py P Thakur [checked by. |Approved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC

Page 25: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

M iimMi'iiuiuiLniim^iuiiiirjjiiiiimiiiiiiiimiiiiiiiiiiiii iiiiiminriiiiuiin

vzr-\ . -_n- . :.T~TI:

ELEVATION 1

r ' "i ~ r~ 1 T~ T

; r;-r|-T-p-|r; r , rrT tTiT i : Y:i

ELEVATION 2

(B) ELEVATION 4 g )

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Single Unit Toilet BlockEl. EVAT1ONS

Draw-r,g no: A - Scale:Dare: 25th December, 2005

Drawn by: P.Thakur [CnecKed by: JApproved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC

Page 26: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Bk. Facta wrihHeader Finisl

7^ _ Cement Plaster at Iraide wall

- B 0 BAR @150 C/C

4 NO5 100 BAR

_ Qernent Plasteral (op of partition

- - Nr -

Lintel Detail foropenings above 1200mm

DETAIL 1

DETAIL 2

40 MM CEMENT SCREED[NGQ:675MMPCC (1:2:4)

2!iO

+3710 RIDGE LVL.

+2100 LINTEL LVL

+ 1650 SILL LVL.v \ •

Bk. faced wallt>5rnm Ttik. Side Wcill for Urinal(1in Vlicjh for Girls B." 1 2HIHLI#

Epoxy Paint upto 1M Hl.(ForGi& f.2M Hi- (for Boys) from Flo±r Level

+0 PLINTH LVL.

J Cemeni Piaster ui

lor Boys)

is)

-450 GROUND LVL

SAND AND GRAVEL

COMPACTED EARTH

SECTION AT AA

HIS MAJESTY'SGOVERNMENT OF

NEPAL

TUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PS1P)

Single Unit ioilet BlockSECTION AT A A'

j nn: A - Scale:

Uate: 2bta Decemuef. 2005

wn ny: P Thakur |Chfecke:i JApproved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC

Page 27: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Bfc. Facra witfiHeads* Finish

fi / } -80 BAR @I50 C/C

Cement Plas^ei ai ir>5ide waN

JQR-4NOS1O0BAR

Lintel Detail foropenings above 1200mm

DETAIL 1

^A\N;^>Cv>>>y'N-vr-.Av^

EPOXY LAYERCEMENT PUNNING40 MM CEMENT SCREEDING(1:675MM PCC (1:2:4)150 MM SAND FILLINGRAMMED EARTH FILLING

+3710 RIDGE LVL

+2100 LINTEL LVL.

\

+ 1650 SILL LVL.

8k. faced wall65mm Thk. Side wali for Urinal{1m High lor Girls 8,12m Hign for Soys)

Epoxy^ainljijplo 1M Ht.(forGi Is)-&'1'.2MHI. (foFEoys) from Floi

L500 200

SECTION AT AA'

r Level±0 PLINTH LVL.

450 GROUND LVL

</^0&P"~ SAND AND GRAVEL

COMPACTED EARTH

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Single Unit Toilet Block (Alternate)SECTION ATA-A1

Drawing no: A - | Scale:

Date: 25lh December. 2005

Drawn ay: P.Thakur |Checkecl by: |Approved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CER1D, NLA and BTTC

Page 28: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

900

REF, DETAIL 4,FOR CGI SHEET FIXING

40 NB (M) RAFTER PIPE

40 NB (M) PURLIN PIPE

TOILET ROOM TRUSSWHEREVER PURLINS ARE CONNECTED

TRT-1

90022 GAUGE 900mm PLAIN Gl SHEET

.,- 25 NB (M) PURLIN PIPE

40 N6 (M) RAFTER PIPE

40 NB (M) PURLIN PIPE

81 0" LONG CGI SHEET

TOILET ROOM TRUSSWHEREVER PURLIN CONTINUE.

TRT-2

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PS1P)

j TYPE DESIGN

I Truss Details (Toilet Block)

f Drawing no: j Scale: 1:20

Date: 3rd Jan. S006

Drawn by S Upreti [checked by: iApprc.'Od tjy

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERIO, NLA and BTTC

Page 29: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

90025 NB(M) PURLIN PIPE

40 NB (M) RAFTER PIPE

40 NB (M) PURLIN PIPE

HEADER HIGH INC LINED GABLE BWD

ONEBK. HEADER HIGH HORIZONTAL GABLE BAND

4979

TOILET BLOCK GABLE TRUSS IN BETWEEN TWO WALLS \- 250 4

WHEREVER PURLINS ARE CONNECTED22 GAUGE 900mm PLAIN Gl SHEET

25 NB (M) PURLIN PIPE

ONE BK. HEADER HIGH HORIZONTAL GABLE BAND

NPIPE

81 0" LONG CGI SHEET

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

TYPE DESIGN ~Truss Details (Toilet Block)

! Drawing no: Scale: 1:20

250 4 TOILET BLOCK GABLE TRUSSWHEREVER PURLIN CONTINUE.

250 4

Date: 3nJj_ar>, 2006

Drawn by: S. Upreti [checked by: Approved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC

Page 30: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

IPS FLOOR FINISH40 MM CEMENT SCRE£DING(1:6)

150MM SANO FILINGRAMMED EARTH FILLING

CEMENT PUNNING40 MM CEMENT SCRE£DING(1:6>75MM PCC (1:2:4)

75 MM THICK DPC

200

8mm bar® 175o'cr - ~ - Levelling for PCC with Sand

4 nos 10mm bar @ 200 cfc40 MM CEMENT SCREED1NG(1:6

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Single Unit Toilet Block

DETAIL OF STEPS TRENCH PLAN & FOUNDATION DETAILS

Dale: 21 si Nov. 2005Drawn py: P.Thakur |checked ay:

SILT Consultanls (P) Ltd IN ASSOCIATIONWITH CFRID. NLA and BTTC

Page 31: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

on top of internal member& 3mm Ihk. MS plate weldedon 5r i Omm MS tat

-120ft--B75-

I I I I I T f 1 1 I I I—I—I—i—I—Shutter frame main 4 secondary -•—I—•—1—•—"—r—<-

-!—•—I—i—I—rtmemher 40 x 5 mm flat -I—•—'——•—•—L 016 «lOOmmPrvothuirje

250 mm brie* Wall

125 mm Nickelplated sleel hinges

(IS 1541 heavyduly)\

016 x 100 mm Pivot hinge

Secon. member

Top View: Hold fasl & Hinoe arranqemenl

Scale:-1:4

250mmbnckWal l

Internal member20 x 3 mm Rat

One end ol hofd 'astweloed to lower

part arid door shutter frame welded to

upper part ol 1 6 m m 0 pivot hing

Kote:

1. Complete fabricated (loot 1o be hot dip galvanizedHinge lixing delail

Scale:-1:4

Scale:-1:16

TOILET ENTRANCE MS GATE

Dimensions are in mmHIS MAJESTY'S

GOVERNMENT OFNEPAL

40 x 5 mm Flal Hold fasl

H

1 I

UNICEF -Nepal

PRIMARY SCHOOL IMPROVEMENT

PROJECT (PSIP)

TOILET BLOCK

Entrance Gale Detai.s ( E G 1 )

Drawing no: A -

Date: 26lr> Dec. 20K

Prawn by: P Aryal Icheck&d by Approved hy:

SILT Consultants (P) Lid IN ASSOCIATION

WITH CERID, NLA and BTTC

Page 32: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

-75-

2 75

863

125 mm long Hinge

863

-432 - -65-

Q.5B mm thk plain

color Gl sheet Panel

0,58 mm thk plaincolor Glsheel Panel

Toilet Dour Elevation

Wall OmilterJ

Door Fiamemadaof25 x 25 x '-.2 mm

/Galvanized MSRectangular Pipe

I-12--

10x10x0.5mm

ehannei

25x50x1.2 mmrecta hgulafgalvanisedsimile!

0.58 mm cote sheetrivelerj with 10X10X0.5mmchanrvel

Section at "A-A"

150 mm heavy duty/Aluminium HJIKIIG

75 mm long Aluminum Lrxk

MSFIat!tel(IFasl

Door Frame made of25 x 25 x 12 mm

Shutter Frame made of25x50x1.2 mm

Rectangular Pipe

125 nun Bride wall

Section at "Y-Y"

3x20«200MS

Plan ofMS Flat Holdfast

Floor i.Ev

10x10x0.5mm

channel \

\ , llI-4Section a; "Fj-u!1

25x5Q(!.2 mm GalvanizedMS Shutter frame riveted wishOx 10(0.5mm galvanized

channel

•12J—25—

;5x25x1.2mrnG^:aniz«iMS rectangular pipe riveted

Refer dimensions as mentioned in drawing.Dimensions are not to measure only to read.

HIS MAJESTY'SGOVERNMENT OF

NEPAL

UNICEF-Neoal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

TOILFT BLOCK

Dooi Delails (03)

Drawing no: A - S;ale:

Date: 21a Dec. 2005 _

Uiitwn by: V. Aryal ]ciiucktitl >jy: JA|jjj,svti! B/

StLT Consultants (P) Ltd IN ASSOCIATION

WITH CERID, NLA and BTTC

Page 33: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

-900--620-

Aid rap Fastener

12 0

6 9

ISO

25-

Dimensions are in mm

-10

4—40-4-20 •

FramB Profile Detail

I IPrilScale:-1:4

in»in»nGunnel

Floor Level

O i 25-ISection at Y-Y

Scale:-1:16Wall and dole fast omitted

3 Nos. 7mm Torxari reinforcing barHold last on both side^-2 Nos. @ ZOO mm from both ends-1 No. @ center (length-140 mm)

-660-

4 t t i M 5 - | —

Aldrop Kaslenei /

-820-

-630- -JDS-t40l

SeclionalY-VScale:-V.10

X75

- 8 0 -

I12HKH SO-

Section at A-A

Scale:-1:4

OSS mm cclQr sheet

nvetedwiih 10XiDXO|5mcnannel

Seclion at B-BScale:-1:4

60-

Section at C-C

Scale:-1:4

- Mela! Oal welded onframe for fixing hinge

p. Holes for screwingHinge

Hinge fixingdetail of Door Frame

10x10x0.5 mmChannel

2to

V

•-- Holes la weldingMetal ftal for fixinghinge

^ Holes (or safewing/ Hinge

Hinge fixing

detail of Door Shutter

Note:1- Frame Profile to be made from l.Bmmthk

Galvanized US sheel2.Shu!tertobe made from 1.2 mm Galvanised MSSheet.

HIS MAJESTY'S

GOVERNMENT OFNEPAL

UNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENT

PROJECT (PSIP)

TOU FT BLOCK

Door DetaLis"(D2]TDrawing no: A - Scale:

rials ?1sl Dm:, ?M>

Drawn by: P. Atyil

SILT Consultants (P) Ltd IN ASSOCIATION

WITH CERID, NLA and 8TTC

Page 34: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

IDin7mm ROO

HOLD FAST

200

3x20 MS flat wetdedon MS Angle Frame

il

125 125 125 125 125 125

25x25mmX2.5mmMS Angle Frame _

r

125875

IT)CMCM

200

3x20 MS flat weldedon MS Angle Frame

25x25mmX2.5mmMS Angle Frame

• 125 125 I 125 125 125 I 125i > -

1250

125 | 125 125 125

HOLD FAST7mm ROD if)

— — — — CMCM

tnCMCM

WINDOW GRILL (WG1) WINDOW GRiLL (WG2)

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Single Unit Toilet BlockWindow Grill Details

nu: A I Scale:

Date: 2Sin December. 2005

Drawn iiy: PThaktif |cneck&tl by ed by:

SILT Consuitants (P) Ltd IN ASSOCIATIONWITH CER1D, NLA and BTTC

Page 35: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

2.5"PVCPerferated Pipe

1200mmdia.Leaching Pit

5"PVC1.25

12Q0mmdia.Leaching Pit

Manhole450x450

-150 mm LEV

+0.00 mm LEV.

BOYS

// // .i

±0.00 mm LEV

s\f-S\f S\fW '////Ar

-450 mm LEV. 4"PVCSoj[Pi&e_

Manhole450x450

GIRLS

Flower Bed

K 2.5"PVCPerferated Pipe

±0.00 mm LEV.

•W>/ s\/\rv

Ramp -450 mm LEV,

GROUND FLOOR PLAN

HBUAJBBTVSBWHBfNEMLPWMAflY SCHOOL MPROfflMBIT

PROJECT (PfflP)

WITHLtd M AMOCUTKMM A n d BTTC

Page 36: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

2.5TVCPerforatedWaster Pipe

HIS MAJESTY'SGOVERNMENT OF

NEPAL

PLAN Scale: 1:20

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Double Unit Tdiet BlockManhole & Leaching Pit Detail

[ Drawing no: SA-

I Dale: 11 Ih July. 2005

[Drawn by: P. Aryal [checksd by: ] Approved by:

SILT Consullanls (P) Lid IN ASSOCIATIONWITH CER1D, NLA and BTTC

Page 37: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Double Unit Toilet BlockUnit A and Unit B

Page 38: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

(75, 1200 360 1250 . 62i i 8"i 5 250 B75 250 875 250 875 3'

1 Sl-t

600

90° Elbow -150x25x5MS Plate

©

Details of fixing Grab Bar 1in Handicapped Toilet

40 DiaG! Pipe- welded on

150x25x5fnmMS Plate

•A]

V 25 Dia Gl Pipe

omi

Ftoor Level

Section at 1-1'

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Double Unit Toilet BlockDelail Plan {Toilet Block)

Drawing no: A - Scale:

Dale: 25ih December, 2005

Drawn by: P. Arya] ICrtecked by: | Approved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC

Page 39: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

2SQ 875 250 875 250 875 3 150x25x5 ,MS (Plate \

+ O.0 mm LVL;i Details of fixing Grab Bar_ YA

in Handicapped Toilet

4D0ia Gt Pipewelded on150x25x5 mmMS Plate

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSiP)

5 25tp B75 E5

f4625

Double Unit Toilet BlockDetail Plan (Toilel Block) Alternate

Drawn by: P. Arya] ICfieckarJ by: [Approved by: '

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC ;

Page 40: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

UNIT A

<•>

UNITB

CD (5> EAST ELEVATION © (§ 0 (3) NORTH ELEVATION (|)

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENT jPROJECT (PSIP) i

DoutJIe Unit Toilet BtockE le rations (Toilet Block)

Drawing no: A - Scale:

Date: 25th December, 2005

Drawn by: P. Aryal [Checked by: (Approved by:

I SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID. NLA and BTTC

Page 41: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

Cemer.t Piaster at inside wad

'—as BAR @

" V r 1 4 HOS 100 BAR

Lintel Detail foropenings above 1200mm

DETAIL 1 Scale 1:20

al lop of pavilion v

DETAIL 2

UNIT A

DOOHf RAME 150 mm CLEARANCEFROM Ft OOrl MID SHUTT E R 1 ? S

mm CLEARANCE FROM F LOOP

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepa!

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Orawinij tio: A

_ DoubieJJnit Toilet BlockSection at A-A' (Toilet Block) Alternale

1" Scaia:

I Oats^_25tri December, 2005_

- Sirawn by: P. Aryal [Clieckbd by: JApproued by:

| SILT Consultants (P) Ltd IN ASSOCIATION[ WITH CERID, NLA and BTTC

Page 42: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

UNITB

21M LIMTEL LVL.

H650 SILL LVL

+371ORIDGELVL.

±0 PLINTH LVL.

L450 GROUND LVL

- SAND AND GRAVEL

COMPACTED EARTH

SECTION AT BB'

HIS MAJESTY'SGOVERNMENT OF

NEPAL

UNICEF-Nepa!

PRIMARY SCHOOL IMPROVEMENT

PROJECT (PSIP)

Double Unit Toilet Block

Section at B-8' (Toilet Block)

Drawing no: A -

Dale: 25th December, 2005

Drawn by: P. A^al _Jcheckect by: j Approved by:

SILT Consultants (P) Ltd IN ASSOCIATION

WITH CERID. NLA and BTTC

Page 43: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

900

REF. DETAIL 4,FOR CGI SHEET FIXING

J-2SCl4

40 NB (M) RAFTER PIPE

TOILET ROOM TRUSSWHEREVER PURLINS ARE CONNECTED

TRT-1

40 NB (M) PURLIN PIPE

I-250 4

900

L 32 N8 (L) BOTTOM TIE PIPE

TOILET ROOM TRUSS

22 GAUGE 900mm PLAIN Gl SHEET

— 25 NB (M) PURLIN PIPE

40 NB (M) RAFTER PIPE

<e'°"cG/ 40 NB (M) PURLIN PIPE

81 0" LONG CGI SHEET

WHEREVER PURLIN CONTINUE.

TRT-2

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PS1P)

~ ' ^ DESIGNTruss Details (Toilet Block)

; Drawing no. | Scale: 1:20

| Date: 3rd jan, 2006^

! Drawn by: S. Upreli [checked by: [Approved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC

Page 44: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

90025 N8 (M) PURLIN PIPE

40 NB (M) RAFTER PIPE

40 NB(M} PURLIN PIPE

HEADER HIGH INQLINED GABLE BftND

BK. HEADER HIGH HORIZONTAL GABLE BAND

,ONg BK. HEADER HIGHLINTEL BAND

\- 250 4 TOILET BLOCK GABLE TRUSS IN BETWEEN TWO WALLS [-250 4

WHEREVER PURLINS ARE CONNECTED22 GAUGE 900mm PLAIN Gl SHEET

25 NB (M) PURLIN PIPE

1034 •

40 NB (M) PURLJN PIPE

8'0'LONG CGI SHEET

HEADER HIGH I NOUN ED GABLE BfcND

ONE BK. HEADER HIGH HORIZONTAL GABLE BAND

ONEBK. HEADERHIGHLINTEL BAND

J"- 250 4TOILET BLOCK^GABLE TRUSS

WHEREVER PURLIN CONTINUE.250 4

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT <PSIP)

TYPE DESIGNTruss Details (Toilet Btack)

Drawing no: i Scale: t:20

Date: 3rdjan, 2006

Drawn by: S. Upreti ICheckecl by: I Approved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC

Page 45: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

BK. OM EDGE ON 250MM SQUARE (Ref Delail I)

I PS FLOOR FINISH

STEP 2- Filling IheSquateby Incompressible Wasla Materials

HIS MAJESTVSGOVERNMENT OF

NEPALUNICEF-Nepal

COMPOSITE OF BRICK AND COMCRETE( Detail I )

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Double Unit Toilet BlockTrench Plan & Foundation Details (Toilet Block)

Drawing no: S- Scale:

Dale: 21st Nov. 2005

Drawn by: P. Aryal Checked by: Approved by;

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERtD, NLA and BTTC

Page 46: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

3x20 MS flat weldedon MS Angle Frame

mi7mm ROD t-:HOLD FAST :

200

25x25mmX2.5mmMS Angle Frame

3x20 MS flat weldedon MS Angle Frame

125 I 125 ; 125 125 125 125 125

mCMC\J

i nCM

oIT

200

Of

25x25rrtmX2.5mmMS Angle Frame

HOLD FAST7mm ROD If)

— — — CMCM

CMCM

875

125 125 125 ; 125 ; 125 j 125 125 : 125 , 125 j 125 .

1250 ;

WINDOW GRILL (WG1) WINDOW GRILL (WG2)

HIS MAJESTrSGOVERNMENT OF

NgPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Double Unit Toilet BlockWindow Grill Details

Drawing no: A - Scale:

Date: 251h DecembeF, 2DO5Drawn by: P. Aryal TcrTecfced by: j Approved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC

Page 47: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

/ 2'i GAUGE gOOmm PLAIN Gl SHEET

25 NBfM) PURLIN PIPE

j ^ 40 NB (M) RAFTER PIPE

40 NB (M) PURLIN PIPE

LONG CGI SHEET

32 NB <L> BOTTOM TIE PIPE

TOILET BLOCK TRUSS DETAIL

^250 422 GAUGE 900mm PLAIN Gl SHEET

25 NB (M) PURLIN PIPE

103410W 1 064 -••--

40 NB (M) RAFTER PIPE

HIGH INCLINED GABLE BAND

8 mm0 Plain Rotf\

ONE BK HEADER HIGH HORIZONTAL GABLE BAND

ONE BK. HEADER HIGH

40 NB (M) PURL N PIPE

A-- 81 0" LONG CGI SHEET

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

\~ 250 4 TOILET BLOCK TRUSS DETAIL AT GABLE WALL

PRIMARY SCHOOL IMPROVEMENT

PROJECT (PSIP)1 SARASWOTI PRIMARY SCHOOL, Sirsiya, Parsa

Truss Details (Toilet Block): Drawing no: Parsa 1: SI3-027 ; Scale: 1:20

; Dale: Slh August. 2005

; Orawn by: S. Upretj Checked by: ;Approved by:

'. SILT Consultants (P) Ltd IN ASSOCIATION

WITH CERID, NLA and BTTC

Page 48: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

250 mm bricfc Wall j

I125 mm Nicksj

plated sleelhinoes[IS 1341 heavydij|y}\

frame Main member

Int. member

I 016 x 100 mm Ptvot hinge

40 x 5 mm Fial Hold fast

Secon. member

I . ITop View. Hold fast & Hinge arrangement

Scale:-1:4

250 mm brick Wall

Internal member20* 3 mm Flat

One end of hold fasl welded to lower'part and door shutter frame welded toupper part of 16 rmn0 prvot hing

on top or internal member&3mmlhJc MS plate weWedon 5x40mm MS flal

Note:

1. Coraplele fabricated door lo tie hot dip galvanizedHinge fixing detail

Scale:-1:4

Scale:-1:16

TOILET ENTRANCE MS GATE

Dimensions are in mmHIS MAJESTTS

GOVERNMENT OFNEPAL

UNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENT

PROJECT (PS!P)

TOILET BLOCK

Entrance Gate Details (EG1)Drawing no: A- Seals:

Dais: 26th Dec, 2005

Drawn by: P.Aryal IChKtsd Uy:

SILT Consultants (P) Ltd IN ASSOCIATION

WITH CER!D,NLA and BTTC

Page 49: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

-592-

-432- - 9 5 -Ocjor frame made of25x25x1.2 n an

ilvanized MSiectangular Pipe

/Gil

0.68 mm Ihk plancolor Gl sheet Panel

0.58 mm ink plaincolor Gl sheel Panel

Toilet Door Elevation

Wall OmiifaJ

10x10x0.5mrn

channel ^

25 x 50 x1.2rnmreclancufar \galvanisedshultef

0.58 mm cotar sheet Iriveted with 10X1OX0-5mmchannel

-12—

:

"I

Section at "A-A"

150 mm heavy duly/Aluminium Handle

Shutter Frame made of25 x 50x1.2 mm

-692-

- 7 5 - 125 mm Brick wall

3x20*200 MS

Galvanized MSRectangular Pipe

Plan of

Floor Level

10x5 0x0.5mm

channel \

. _ _ \ _ . . . .

MS Flat Holdfast25x50x1.2mm GalvanizedVIS Shutter frame riveted with0x10x0.5mm galvanized

;hannei

Seciion at "B-B"Sea e:-1:2

12-

L—

—25—

25x25x1.2 mm Galvanized' S rectangular p,pe nveted.vim 10x10x0.5 mm galvanized channel

Refer dimensions as mentioned in drawing.Dimensions are not to measure only to read.

Dimensions are >ri mm•a

HIS MAJESTY'SGOVERNMENT OF

NEPAL

UNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENTPROJECT (PS1P)

TOILET BLOCK

Door Details (D3)

Gracing no:A - I Scaie:

Dale: 21sl Dec, 2005

Drawn by: P. Checked by: Approved by:

SILT Consultants (P) Lid IN ASSOCIATION

WITH CERID, NLA and BTTC

Page 50: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

p40

Aldrap Fastener

1

IF- 9 0 0 -- « 2 0 -

8 9

25-1

Dimensions are in mm

csttv Gi siuM Var*

4-1-10

4—W-4-2O--Frame Profile Detail

40

Scale:-1:4

1WMchanm

Floor Level

Section at Y-YScale:-1:16

Wall and hole fast omitted

3 Nos. 7mm Torkari reinforcing barHold (asi on both sides-2 Mos. @ 200 nvn from both ends-1 No. @ center (lenglh-140 mm)

-660 -

- 6 3 0 -

Aktrop fastener / SeclionatV-VScale:-1:10

57 5

t-3M 80-

Seclion at A-A

Scale:-1:4

a-33-j ar>

Section at B-8Scale:-1:4

¥-SecBon at C-C

Scale:-1:4

r<U- Mstal flat welded on

frame lor fixing hinge

^ Holes for screwing

Hinge fa ing

delail of Door Frame

10* 10x0.5 mmChannel

2K)

- Holes for weldingMetal flat for fixinghinge

> Holes lor screwingHinge

Hinge ftxino

detail of Door Shutter

Mole:1. Frame Profile to be made from 1.6 mm thk

Galvanized MS sheet2. Shutier lo be made from 1.2 mm Galvanised MSSheet.

HIS MAJESTTSGOVERNMENT OF

NEPALUNICEF-Nepal

PRIMARY SCHOOL IMPROVEMENT

PROJECT (PSIP)

TOILET BLOCK

Door Details (D2)

Drawing no: A- State:

Bate: 21S1O8C, 2005

Drawn by: PAr jS Crwctedby

SILT Consultants (P) Ltd IN ASSOCIATION

WITH CERID. NLA and 8TTC

Page 51: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

lOOOmmdia.Leaching Pit

Manhole450x450

1000

0001-

1000

KJitn TOIJO

- "2.5"PVCPerferatedPipe

1200mmdia.Leaching Pit

HIS MAJESTY'SGOVERNMENT OF

NEPALUNICEF-Nepal

f \ lOOOmmdiaI /Leaching Pit

PRIMARY SCHOOL IMPROVEMENTPROJECT (PS1P)

Double Unit Toilet Biock

2.5"PVCPerferateHPipe

Waste & Sewerage Pipe Line Diagram

Drawing no: SA- I Scaie:

:_Da1e: 11th J j y 2005I D'ii'.vn by: P hr-jh- ^Chccised by lApproje

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC

Page 52: School Toilet/Urinal Design and Drawing - IRC · School Toilet/Urinal Design and Drawing UNICEF, Nepal ... 250 mm long tower-bolt/ 1800 ... Floor Finishing Over 10 cm Ink PCC ...

2.5"PVCPerforatedWaster Pipe

HIS MAJESTY'SGOVERNMENT Of

NEPAL

PLAN Scale: 1:20

PRIMARY SCHOOL IMPROVEMENTPROJECT (PSIP)

Double Unit Toilet BlockManhole & Leaching Pit Detail

Drawing no: SA- Scale:

Drawn by: P. Aryal Checked by: ] Approved by:

SILT Consultants (P) Ltd IN ASSOCIATIONWITH CERID, NLA and BTTC