Development of limit load solutions for corroded gas pipelines
J.B. Choia, B.K. Gooa, J.C. Kima, Y.J. Kima,*, W.S. Kimb
aSchool of Mechanical Engineering, SAFE Research Center, Sungkyunkwan University, 300 Chunchun-dong, Jangan-gu, Suwon,
Kyonggi-do 440-746, South KoreabKorea Gas Company Research and Development Center, 638-1 Il-dong Ansan Kyonggi-do 425-150, South Korea
Received 1 May 2001; revised 2 January 2003; accepted 2 January 2003
Abstract
Pipelines have the highest capacity and are the safest and the least environmentally disruptive means for gas or oil transmission. Recently,
failures due to corrosion defects have become of major concern in maintaining pipeline integrity. A number of solutions have been developed
for the assessment of remaining strength of corroded pipelines. However, these solutions are known to be dependent on material properties
and pipeline geometries.
In this paper, a fitness-for-purpose (FFP) type limit load solution for corroded gas pipelines made of X65 steel is proposed. For this
purpose, a series of burst tests with various types of machined pits are performed. Finite element simulations are carried out to derive an
appropriate failure criterion. Then, further, extensive finite element analyses are performed to obtain the FFP type limit load solution for
corroded X65 gas pipelines as a function of defect depth, length and pipeline geometry.
q 2003 Elsevier Science Ltd. All rights reserved.
Keywords: Corrosion defects; Limit load; Pipeline; Finite element analysis; Pipe burst test
1. Introduction
Since the 1950’s, pipelines have been used as one of the
most economical and safest ways of transmitting oil and
gas, and a number of pipelines are still under construction
all around the world. However, the number of accidents
have also dramatically increased with the increasing
number of operating pipelines [1,2]. The integrity of
these pipelines is of importance due to the explosive
characteristic of gas and oil. Currently, soil and water
contamination due to the failure of pipelines has been
raised as one of the critical issues affecting preservation of
the environment. For these reasons, intensive research
efforts have been carried out on the assessment of
structural integrity of pipelines.
Corrosion is known to be one of the major reasons
causing pipeline failure. ASME B31G [3] is one of the most
widely accepted solutions for the assessment of corrosion
defects. ASME B31G idealizes the complex geometry of
a corrosion pit as an elliptical shape, and applies a bulging
factor for the consideration of defect geometry. This
solution has been modified by Kiefner and Vieth [4] to
enhance its accuracy. Vieth and Kiefner [5] collected an
extensive series of pipeline burst test results for deriving
improved corrosion defect assessment procedures. The
improvement was achieved by introducing a new bulging
factor and the material flow stress, and a more detailed
consideration of the defect shape using iterative calcu-
lations. This method has been implemented in a program
known as RSTRENG [6].
ASME B31G and RSTRENG have been widely used for
assessing the remaining strength of piping and pressure
vessels due to its conservatism. However, it has been
revealed that these criteria are excessively conservative
when applied to defects in high strength pipelines [7–9]. In
1997, Stephens and Leis [10] observed that the failure of
corroded pipelines was controlled by ultimate strength
rather than flow strength in mid- to high-strength steel
pipelines. On the basis of experimental observations,
Stephens et al. [11] developed a specific finite element
code, which is called PCORRC, and proposed a limit load
0308-0161/03/$ - see front matter q 2003 Elsevier Science Ltd. All rights reserved.
doi:10.1016/S0308-0161(03)00005-X
International Journal of Pressure Vessels and Piping 80 (2003) 121–128
www.elsevier.com/locate/ijpvp
* Corresponding author. Tel.: þ82-31-290-5274; fax: þ82-31-290-5276.
E-mail address: [email protected] (Y.J. Kim).
Abbreviations: API, American Petroleum Institute; ASME, American
Society of Mechanical Engineers; FEA, Finite element analysis; BG/DNV,
British Gas/Det Norske Veritas; KOGAS, Korea Gas Corporation.
solution for moderate- to high-toughness pipe based on
an extensive series of FEA. Recently, the corrosion defect
assessment procedure has become more specific in terms of
pipeline materials and defect geometries [11–13]. There-
fore, it has been necessary to develop a specific solution for
an accurate assessment of corrosion defects especially in
high strength pipeline steels.
In this paper, a specific limit load solution for the
assessment of corrosion defects in API X65 gas pipelines is
developed by comparing experimental data with FEA
results. An extensive series of 3D elastic–plastic FEA was
performed, and as a result, a limit load solution, which
provides the maximum allowable pressure as a function of
corrosion defect geometry, is proposed.
2. Procedures for development of the limit load
solution
The failure mechanism of corrosion defects in mid- to
high-toughness pipeline materials such as API X65
pipeline steel is known to be different from that of low
toughness pipeline materials [7,8]. While the defect in
low toughness pipeline may fail by a fracture-based
mechanism, which is controlled by material flow stress,
the defect in mid- to high-toughness pipeline shows
plastic collapse, which is controlled by material ultimate
stress. Therefore, the limit load solution for the assess-
ment of corrosion defects in high toughness pipelines
should be developed on the basis of the specific material
tensile properties. In this paper, a new failure criterion for
X65 pipeline steel is introduced by conducting a
systematic approach including pipe burst tests and finite
element simulations.
First, a series of burst tests was performed on various
machined defects to investigate the failure mechanism.
Then, the finite element simulation on test pieces was
performed to derive a failure criterion for the prediction of
maximum allowable pressure. The developed failure
criterion was modified to apply for the general elliptical
shape corrosion pits. Finally, an extensive series of FEA on
elliptical pits was conducted, and a limit load solution is
introduced by applying the analysis results. Fig. 1 shows a
schematic of the development procedure.
3. Pipeline burst test
3.1. Experiments
Burst test pipes were prepared from API 5L X65
pipelines from KOGAS, and widely used for natural gas
transmission. A pipeline of total length 12 m was cut into
pieces with 2.3 m length, and both ends were capped by
Nomenclature
a maximum depth of the defect
c transverse extent of the defect
l axial extent of the defect
t; tnom wall thickness of the pipe
Do outside diameter of the pipe
L length of the pipe
Pmax failure pressure prediction based on the
proposed equation
PFEA maximum pressure from the finite element analysis
PTEST burst pressure from the experiment
R;Rnom mean radius of the pipe
sf flow strength
su ultimate strength
sy yield strength
Fig. 1. Schematic of the limit load solution development for X65 pipeline
steel.
J.B. Choi et al. / International Journal of Pressure Vessels and Piping 80 (2003) 121–128122
circumferential welding to accommodate high internal
pressure. The geometrical configuration of the specimen
tested is shown in Fig. 2, and dimensions of test specimens
and resulting maximum pressures are summarized in
Table 1. The corrosion defect was machined in a rectangular
shape as shown in Fig. 2. The defect was machined to keep
the same thickness at the bottom, and corner edges were
rounded to avoid excessive stress concentration. For
categorizing a corrosion defect, the depth ðaÞ; the width
ðcÞ and the length ðlÞ are usually used. The rectangular shape
corrosion pit is accepted since it can be assumed as the most
critical shape with these three characterizing parameters.
The test equipment is shown in Fig. 3.
In order to observe the strain variation during pressur-
ization, six strain gages were attached in each specimen as
shown in Fig. 4. The positions of strain gages are
summarized in Table 2. Two strain gages were used for
the measurement of local strain at the machined pit, and
others were used for the measurement of global strain
variation.
All specimens showed bulging deformation around the
defect area, and the final failure occurred at the bottom of
the defect area with a crack-like penetration in the
longitudinal direction as shown in Fig. 4. Fig. 5 shows the
variation of pressure during the burst test of the specimen.
The burst pressure was observed to be affected by the
variation of defect depth and length as summarized in
Table 3. The defect width, however, had an insignificant
effect on the burst pressure. Since the burst test produces
much higher hoop stress than axial stress, this tendency
seems to be reasonable.
Fig. 2. A schematic illustration of burst test specimen.
Fig. 3. Picture of burst test equipment.
Table 1
Burst test pipe geometries
Pipe no. l (mm) c (mm) a (mm) ða=tÞ Burst pressure (MPa)
DA 200 50 4.4 (25%) 24.11
DB 200 50 8.8 (50%) 21.76
DC 200 50 13.1 (75%) 17.15
LA 100 50 8.8 (50%) 24.30
LC 300 50 8.8 (50%) 19.80
CB 200 100 8.8 (50%) 23.42
CC 200 200 8.8 (50%) 22.64
L ¼ 2:3 m; Do ¼ 762 mm; t ¼ 17:5 mm:
J.B. Choi et al. / International Journal of Pressure Vessels and Piping 80 (2003) 121–128 123
The final failure was preceded by bubbling deformation
around the defect area, which is typical for mid- to high-
toughness pipeline material. The defect area shows a
significant amount of thickness reduction along the
penetration line, probably caused by local necking prior to
final failure. For all specimens, failure was observed to be
controlled by plastic collapse rather than fracture.
4. Finite element simulation of pipeline burst test
4.1. Finite element analysis
In order to derive the failure criterion for corrosion
defects, 3D elastic–plastic FEA simulating pipeline burst
tests were performed using a commercial finite element
program, ABAQUS [14]. Only a quarter of a full pipe was
modeled by considering symmetry. The machined pit was
modeled as a rectangular shape in accordance with the test
specimen shown in Fig. 6. The model is designed with 20-
node isoparametric brick elements, and the numbers of
elements and nodes are 1129 and 5713, respectively. Since
the final failure was observed from the defect area, the
bottom of the defect area was modeled with sufficient
number of elements determined by a preceding convergence
analysis. The hydrostatic pressure was applied at the inner
surface of the model. Since the test specimen was capped at
both ends prior to the burst test, the corresponding axial
stress was applied at the end of finite element model. The
true stress–true strain curve was adopted from tensile test
results which were performed on the same material as the
burst test specimen. The full stress–strain curve is shown in
Fig. 7. Incremental plasticity with large deformation theory
Fig. 4. Pictures of pipe DC before and after test.
Table 2
Strain gage locations
S1 S2 S3 S4 S5 S6
DA (0,0) (50,0) (150,0) (300,0) (0,75) (0,225)
DB (0,0) (50,0) (150,0) (300,0) (0,75) (0,225)
DC (0,0) (50,0) (150,0) (300,0) (0,75) (0,225)
LA (0,0) – (100,0) (250,0) (0,75) (0,225)
LC (0,0) (50,0) (200,0) (350,0) (0,75) (0,225)
CB (0,0) (50,0) (150,0) (300,0) (0,100) (0,250)
CC (0,0) (50,0) (150,0) (300,0) (0,150) (0,300)
S1(0,0) point is the centre of corrosion defect.
Fig. 5. Variation of pressure during the burst test for various corrosion
depths.
J.B. Choi et al. / International Journal of Pressure Vessels and Piping 80 (2003) 121–128124
was applied for the entire FEA to simulate local deformation
at the defect area.
FEA results are summarized in Table 3 along with burst
test results. Since all test specimens showed local failure at
the defect area, a failure criterion is introduced by
considering the local stress of the defect area. The von
Mises stress values at this area were reviewed in comparison
with experimental results. First, reference stresses were set
to yield strength, sy; flow strength, sf ; ultimate strength, su;
80 and 90% of ultimate strength, respectively. The flow
strength is defined as sf ¼ ðsy þ suÞ=2:
Failure was then assumed to occur when the von Mises
stress distribution across the ligament thickness at the defect
area reached the reference stress as shown in Fig. 8.
Table 3
Comparison between FEA results and experimental results
Pipe Burst pressure (MPa) PFEA=Ptest
sy sf 0:8su 0:9su su
DA 24.11 0.81 0.98 0.99 1.01a 1.01a
DB 21.76 0.66 0.93 0.95 1.04 1.10
DC 17.15 0.42 0.84 0.86 0.95 1.05
LA 24.30 0.68 0.94 0.95 1.00 1.01a
LC 19.80 0.61 0.86 0.88 0.98 1.06
CB 23.42 0.57 0.84 0.86 0.93 1.00
CC 22.64 0.59 0.85 0.88 0.95 1.02
sy : yield strength; sf : flow strength; su : ultimate strength.a The analysis stopped before it reached the corresponding criterion.
Fig. 6. A typical finite element mesh for the burst test simulation.
Fig. 7. True stress–strain curve for API X65 steel (tested at room
temperature).
Fig. 8. The variation of von Mises stress at the defect area with increasing
pressure.
Fig. 9. A schematic illustration of corrosion defect idealization.
J.B. Choi et al. / International Journal of Pressure Vessels and Piping 80 (2003) 121–128 125
The corresponding internal pressure was determined as the
failure pressure. Resulting failure pressures are normalized
with corresponding experimental burst pressures, and
summarized in Table 3. The best prediction is achieved
with the reference stress of 90% of ultimate strength, and the
difference is less than 7%.
Predictions obtained from sy or sf showed overly
conservative results and insufficient sensitivity on defect
geometries. Since the failure mechanism is controlled by
plastic collapse as observed from the test, the prediction on
the basis of su provided more accurate results and
reasonable sensitivity on defect geometries.
4.2. Failure criteria for elliptical corrosion pits
In general, a corrosion pit is idealized into a semi-
elliptical shape rather than a rectangular shape [3] as
shown in Fig. 9. Since the shape of a corrosion pit in a
test specimen is rectangular to model the most severe
case, it is necessary to modify the failure criterion for an
elliptical corrosion defect to an arbitrarily shaped
corrosion pit. For this reason, FEA on elliptical corrosion
pits were performed, and results were compared to test
results. Finite element models with an elliptical corrosion
pit were designed by changing l and c in Fig. 9 to the
corresponding elliptical shape, and analyses were per-
formed for DA, DB and DC. A typical finite element
mesh is shown in Fig. 10.
Fig. 11 shows comparisons between test and analysis
results. In the FEA, su was used for the failure criterion
based on the finite element simulation results. Reference
stresses for the failure prediction were set to su and 0:8su;
respectively. While the predictions with su showed 10%
overestimation, those from 0:8su showed good agreement
with test results. The rectangular shape corrosion pit can be
assumed as the most severe one considering the shape
idealization. In order to develop a conservative engineering
solution, 0:8su was chosen to be the reference stress for the
failure prediction of elliptical shape defects.
5. Generation of limit load solution using FEA
In order to derive a general solution for defect assessment
of X65 gas pipelines, extensive FEA on various elliptical
corrosion defects were performed. Only a quarter of a full
pipe was designed, and the corrosion pit was introduced on
the outside surface as shown in Fig. 9. The finite element
model was designed with 20-node isoparametric brick
elements, and the numbers of elements and nodes are 1071
and 5711, respectively. The same material properties and
loading conditions as specified in Section 4.1 were applied.
Three different parameters of R=t; a=t and l=ffiffiffiRt
pwere
considered in the FEA. The values of R=t were set to 21.3
and 30 considering the actual dimensions of a gas pipeline.
The values of a=t were set to 0.4, 0.6 and 0.8. Five different
l=ffiffiffiRt
pvalues ranging from 0.5 to 6 were considered. Thus a
total of 30 cases were analyzed as summarized in Table 4.
The variation of c would not be significant since axial cracks
are more critical than circumferential cracks for pressurized
pipes as observed from the test, and thus, c=pRo was
fixed to 1/10 for the entire analysis matrix. For all cases,
Fig. 11. Comparison of Pmax between burst test and FEA for elliptical shape
defects.
Fig. 10. A typical finite element mesh for an elliptical corrosion pit.
J.B. Choi et al. / International Journal of Pressure Vessels and Piping 80 (2003) 121–128126
the maximum von Mises stress was observed at the deepest
point of defect. The failure, therefore, was assumed to occur
when the von Mises stress in the defect ligament reached
0:8su as determined in Section 4.2. The maximum
allowable pressure, Pmax; was determined as the internal
pressure when the failure criterion was satisfied.
6. Derivation of limit load solution
Figs. 12 and 13 show the resulting maximum allowable
pressure values for R=t ¼ 21:3 and 30, respectively, in
comparison with modified B31G [2], Battelle PCORRC
[10] and BG/DNV [12] solutions. With increasing R=t; the
maximum allowable pressure decreases. For cases of a=t ¼
0:4 and 0.6, the FEA produced approximately 10–20%
higher values than those from modified B31G. For deep
defects of a=t ¼ 0:8; the FEA results showed lower values
than those from modified B31G with increasing defect
length. This implies that the modified B31G solution is
conservative for all shallow defects, but may be non-
conservative for long and deep corrosion defects. This
tendency is consistent for PCORRC and BG/DNV solutions.
While the proposed solution provides similar predictions to
those from PCORRC for short defects, it results in slightly
higher predictions for long defects.
By applying regression analysis on the FEA results, a
limit load solution is proposed as a function of R=t; a=t and
l=ffiffiffiRt
pas follows:
forlffiffiffiRt
p , 6;
Pmax ¼ 0:9 £2t
Di
su C2
lffiffiffiRt
p
� �2
þC1
lffiffiffiRt
p
� �þ C0
" # ð1Þ
C2 ¼ 0:1163a
t
� �2
20:1053a
t
� �þ 0:0292
C1 ¼ 20:6913a
t
� �2
þ0:4548a
t
� �2 0:1447
C0 ¼ 0:06a
t
� �2
20:1035a
t
� �þ 1:0
Table 4
The analysis matrix
c=pRo R=t a=t l=ffiffiffiRt
pR=t a=t l=
ffiffiffiRt
p
0.1 21.3 0.4 0.5 30 0.4 0.5
1 1
2 2
4 4
6 6
0.6 0.5 0.6 0.5
1 1
2 2
4 4
6 6
0.8 0.5 0.8 0.5
1 1
2 2
4 4
6 6
Fig. 13. Comparison of Pmax between PCORRC, BG/DNV, Modified B31G
and FEA ðR=t ¼ 30Þ:
Fig. 12. Comparison of Pmax between PCORRC, BG/DNV, Modified B31G
and FEA ðR=t ¼ 21:3Þ:
J.B. Choi et al. / International Journal of Pressure Vessels and Piping 80 (2003) 121–128 127
forlffiffiffiRt
p $ 6; Pmax ¼2t
Di
su C1
lffiffiffiRt
p
� �þ C0
� �ð2Þ
C1 ¼ 0:0071a
t
� �2 0:0126
C0 ¼ 20:9847a
t
� �þ 1:1101
Fig. 14 shows the comparison between the prediction by Eq.
(1) and experimental burst pressure. The prediction provides
conservative estimates and shows excellent agreement for
all cases. The proposed systematic approach resulted in a
simple equation on the basis of a complete understanding of
pipeline failure behaviour, and seems to provide sound and
reliable failure predictions.
7. Conclusions
In this paper, a systematic approach was followed to
develop a limit load solution for the assessment of corrosion
pits in API X65 gas pipelines, and the resulting conclusions
are as follows:
(1) In order to derive a failure criterion, a series of burst
test were performed and corresponding finite element
simulations were carried out. The failure mechanism
was controlled by plastic collapse for all cases.
(2) Failure was predicted to occur when the von Mises
stress reached a reference stress across the entire
ligament. While the reference stress for rectangular
corrosion pit was determined to be 90% of the ultimate
strength, that of a corresponding elliptical corrosion pit
was 80% of the ultimate strength.
(3) The modified B31G solution provides conservative
predictions for shallow and short corrosion pits, but
those for deep and long corrosion pits were non-
conservative in comparison with FEA results.
(4) A limit load solution for the assessment of corrosion
pits in API X65 gas pipelines is proposed as a function
of R=t; a=t and l=ffiffiffiRt
pon the basis of FEA results, and
shows excellent agreement with burst test results.
Acknowledgements
The authors are grateful for the support provided by a
grant from Korea Gas Corporation (KOGAS) and Safety
and Structural Integrity Research Center (SAFE) at the
Sungkyunkwan university.
References
[1] Hopkins P. Transmission pipelines: how to improve the integrity and
prevent failures. Proceedings of the Second International Pipeline
Conference, Ostend, Belgium, vol. I; 1995. p. 683–706.
[2] Office of pipeline safety. US Department of Transportation. Pipeline
Statistics; 2001. http://ops.dot.gov/stats.htm.
[3] American National Standards Institute (ANSI)/American Society of
Mechanical Engineers (ASME), Manual for determining the remain-
ing strength of corroded pipelines. ASME B31G; 1984.
[4] Kiefner JF, Vieth PH. A modified criterion for evaluating the
remaining strength of corroded pipe. Final Report on Project PR 3-
805, Battelle Memorial Institute, Columbus; 1989.
[5] Vieth PH, Kiefner JF. Database of corroded pipe tests. Final Report on
Contract No. PR 218-9206. Kiefner and Associates, Inc.; 1994.
[6] Vieth PH, Kiefner JF. RSTENG user’s manual. Pipeline Research
Supervisory Committee, American Gas Association; 1993.
[7] Hopkins P, Jones DG. A Study of the behavior of long and complex-
shaped corrosion in transmission pipelines. British Gas plc, OMAE-
92-1004; 1992.
[8] Coulson KEW, Worthingham RG. Standard damage-assessment
approach is overly conservative. Oil Gas J 1990;April.
[9] Cronin DS, Pick RJ. Experimental database for corroded pipe:
evaluation of RSTRENG and B31G. Proc Int Pipeline Conf 2000;2:
757–68.
[10] Stephens DR, Leis BN. Material and geometry factors controlling the
failure of corrosion defects in piping. ASME Pressure Vessels and
Piping Conference, Orlando, FL; July 1997.
[11] Stephens DR, Leis BN, Kurre JD, Rudland DL. Development of an
alternative failure criterion for residual strength of corrosion defects in
moderate- to high-toughness pipe. Battelle report to PRC International
Report, AGA Catalog Number L51794; 1999.
[12] Cronin DS, Pick RJ. A new multi-level assessment procedure for
corroded line pipe. Proc Int Pipeline Conf 2000;2:801–8.
[13] DNV. Corroded pipelines—recommended practice RP-F101, Det
Norske Veritas, Norway; 1999.
[14] Hibbit, Karlsson & Sorensen, Inc. ABAQUS/Standard User’s Manual.
Ver. 5.8, 1998.
Fig. 14. Comparison between actual burst pressure and the prediction by
Eq. (1).
J.B. Choi et al. / International Journal of Pressure Vessels and Piping 80 (2003) 121–128128