+ All Categories
Home > Documents > Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June...

Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June...

Date post: 31-Mar-2015
Category:
Upload: anika-purdy
View: 216 times
Download: 2 times
Share this document with a friend
Popular Tags:
24
Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014
Transcript
Page 1: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Scoping Meeting

Yuba Goldfields200-Year Flood Protection ProjectEnvironmental Impact Report

June 23, 2014

Page 2: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Meeting Agenda

• Welcome and Introductions• Meeting Objective• Project Background • Proposed Project Alternatives• Scoping and CEQA Process• Environmental Issues • Public Comments and Input

2

Page 3: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Introductions

Three Rivers Levee Improvement AuthorityPaul Brunner, Executive Director

Downey BrandAndrea Clark, Legal Counsel

MBK EngineersLarry Dacus, P.E., Project Engineer

AECOMAndrea Shephard, Ph.D., Environmental Project Manager

3

Page 4: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Meeting Objective

Seek public and agency input on the scope and content of the EIR, including

alternatives

4

Page 5: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Proposed Background

5

Page 6: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Project Location

6

Page 7: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Project Need

• Yuba River actively eroding south bank tailings mound.

• Landform changes in Goldfields have affected flow paths and made it easier for floodwaters to flow through the Goldfields.

• Areas that were thought to have 200-year flood protection are still at risk.

7

Page 8: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Project Purpose

8

Reduce flood risk to properties in RD 784 and TRLIA assessment districts by providing sustainable200-year flood protection.

Source: Data compiled by AECOM in 2014

Page 9: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Project Objectives

• Prevent 200-yr flood waters from flowing through Goldfields and flanking State Plan of Flood Control levee system.

• Implement long term sustainable solution by 2025.

• Minimize impacts on aggregate mining operations.

• Minimize impacts on gold dredging operations.

• Minimize impacts on environmental resources.

• Provide environmental benefits, if feasible.

9

Page 10: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Proposed Project Alternatives

10

Page 11: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Project Alternatives

• Four (4) Action Alternatives plus the No-Project Alternative to be evaluated at equal level of detail in EIR.

• Alternatives 1, 2, and 3 – Construct embankment within the Goldfields using existing dredge tailings.

• Alternative 4 – Construct engineered levee south of the Goldfields using material imported from nearby.

• All alternatives would meet USACE and DWR urban levee design criteria for 200-year flood protection.

11

Page 12: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Project Alternatives

Alternative 1: 100-Year Project Enlargement9.0 mile embankment 331 acres in Goldfields

Alternative 2: West-Side Goldfields Boundary Alignment8.8 mile embankment 317 acres in Goldfields

Alternative 3: South Bank Yuba River Alignment 9.1 mile embankment 291 acres in Goldfields

Alternative 4: Levee South of the Goldfields3.5 mile embankment 199 acres in Goldfields

12

Page 13: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

13

Project Alternatives

Page 14: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

14

Alternatives 1, 2, and 3200-Year Embankment in Goldfields

Source: TRLIA 2013, adapted by AECOM in 2014

• Regular O&M: inspections, weed abatement, surface patrol road maintenance.

• During High Flow Periods: Surface road patrols every 4 hours to identify/address potential flooding issues

Page 15: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Alternative 3Relocation of Waterway 13

15

Source: TRLIA 2013, adapted by AECOM in 2014

Source: TRLIA 2013, adapted by AECOM in 2014

Fish barrier at New Outlet Scour Protection

• Will require periodic repair and replacement. • Expected design life of 50 years.

Page 16: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

16

Alternative 4200-Year Levee South of Goldfields

Source: TRLIA 2013, adapted by AECOM in 2014

• Regular O&M: Same as other alternatives plus management of vegetative cover on levee side slopes, operation and annual maintenance of pipe and gates at YCWA canal crossing.

• During High Flow Periods: Surface road patrols every 4 hours to identify/address potential flooding issues

Page 17: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

No-Project Alternative

• 200-year flood protection solution not built.

• 100-year flood protection solution built.

• Decreased flood inundation benefits of TRLIA 200-Year Flood Protection Program.

• Portions of RD 784 and TRLIA assessment districts may be mapped into FEMA floodplains.

• Residents have to purchase flood insurance.

17

Page 18: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

CEQA Review Process

18

Page 19: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Purpose of Scoping

• Inform public and agencies

• Receive public/agency input

• Help define project

• Help identify range of alternatives

• Help identify environmental effects to be evaluated

19

Page 20: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Environmental Review Schedule

20

Notice of Preparation of an EIR June 13, 2014

Scoping Meeting June 23, 2014

Scoping Period Ends July 14, 2014

Notice of Availability/Draft EIR August 2014

Public Review 45 days

Response to Comments/Final EIR November 2014

Commenting Agency Review 10 days

EIR CertificationProject Decision

FindingsOverriding ConsiderationsMitigation Monitoring Plan

Notice of Determination

November/December 2014

Permitting 2015

Page 21: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Opportunities for Input

Scoping Meeting Today

NOP 30-Day Comment Period June 13 – July 14

Draft EIR 45-Day Public Review Period August/September

21

Page 22: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

Issue Areas to be Addressed

• Aesthetics• Agricultural and Forestry

Resources• Air Quality• Biological Resources• Cultural Resources• Geology/Soils/Minerals/

Paleo Resources• Greenhouse Gas

Emissions

• Hazards and Hazardous Materials

• Hydrology/Water Quality• Land Use/Population and

Housing• Noise• Recreational Resources• Transportation/Traffic• Utilities and Public

Services

22

Page 23: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

23

Project Alternatives

Page 24: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.

How do you participate?

• Present your views today.

Please focus on the scope of the project (i.e. project elements and alternatives & environmental effects and mitigation).

• Provide written comments on the NOP today or to TRLIA by 5 pm, July 14, 2014.

Paul Brunner, TRLIA

1114 Yuba Street, Suite 218, Marysville, CA 95901

Fax: (530) 749-6990 Email: [email protected]

• Review and comment on the Draft EIR.

• Contact TRLIA throughout the process.

24

THANK YOU


Recommended