Date post: | 19-Jan-2015 |
Category: |
Business |
Upload: | informa-australia |
View: | 476 times |
Download: | 1 times |
International Comparison of Light Rail Delivery in Urban Environments –
Case Studies from UK and Australia
Scott Ney, MIEAust CPEng, RPEQ, CEng MICE, PE Technical Executive – Parsons Brinckerhoff 05 March 2014
Overview
• Common Project Themes and Challenges • Recent Case Studies
– Perth MAX (concept + business case) – Edinburgh Trams (design and construction)
• Summary and Lessons Learnt
Light Rail is more complex than most other Public Transport infrastructure
Common Themes
• Minimising Risk – “Role of LRT” in corridor selection – Safety – Cost – Stakeholder inputs – Public Perception
• “Balance” – Transport or Catalyst for Change – Competing Stakeholders – Requirement vs. Betterment – Transport Priority
• Integration – Transport Integration – Integration into built environment – Design Integration
Common Challenges
• Where should it be? – Corridor – Alignment – Stops
• “Approvability” – Stop Locations and Urban
Design Impacts – Traffic Operations and
Modelling – Design Guidelines
• Third Party Agreements • Service Diversions • Constructability - “Open for
Business” • Thinking towards the future
The Integration Challenge
“Approvability”
Construct-ability
Cost
Design Criteria
Stakeholder Inputs
Agreements
Safety
Aesthetics
Beware of “The Ripple Effect”
Procurement
CIV
STR
OHW
GEO
TRK
UTL
DRN
SUB
SIG
ALG
RDS
TP
STP
E&B EMC COM
LDS
TRF
ARC
UD
DCT
VEH
How is a Light Rail Project successful?
Approvals Technical Constraints
Construction and
Maintenance Costs
Operations Urban
Regeneration Stakeholder
Inputs
Passenger Experience
Integrated Transport
Traffic Operations
Urban Design
Demand & Revenue Utilities
“Achieving the Balance”
Perth MAX - Overview
• Task: Develop concept designs and all other information required to support the successful delivery of a Business Case and future funding
• Scope of Works: – Key technical systems
identification – Design requirements – Concept design – Design interface
management – Consultation
MAX – Opportunities and Challenges
• Key Drivers: – Filling the last big gap in
network – Catalyst for change – Traffic operations to and
thru CBD – Future Development – Build on previous work
completed – Consider future expansion
MAX – Key work elements
• Utility conflicts • Depot location and
design • OCC location • Alignments thru CBD and
West Perth • Integration and route
sharing with bus services
• Integration of light rail operations into an active street environment
• Integration with surrounding environment and optimising land use
Proposed MAX Network
Mirrabooka
Dianella
QEII Medical Centre Victoria Park Transfer Station
North Perth ECU
Project History
We are here
2011 to 2013
• Concept Design CNC
• Concept Design Inner City Transit )
• Traffic Modelling of CBD
2013 - Mid-2014
• Business Case and Reference Design.
Mid 2014 -2017
• Project deferred
2017 to 2021
• Detailed design • Construction • Commissioning
2022
• First LRV operating
MAX - Outcomes • The MAX project will introduce a new era of public transport in Perth; it will
support an ongoing transformation of the city by providing a frequent, high-capacity service in the inner-north and central-west and eastern suburbs
• Light rail will provide an efficient and cost-effective solution to many of the transport challenges and land use opportunities in the region
• Potential to facilitate and unlock redevelopment opportunities in key areas • To move more people more reliably as part of an integrated transport network • To help continue to make Perth a great place to live and work
Edinburgh Trams - Overview
• Task: Detailed Design, Approvals, Construction Engineering and Construction Compliance
• Strategy: – Started with 4 independent
delivery contracts: 1. Design / Approvals 2. Utilities Construction (early
works) 3. Vehicle Procurement 4. Infrastructure Construction
– Operator selected and in place before design contract – Independent Technical Advisor
“The objective is to provide a high quality tram system for Edinburgh that
embraces the best practice demonstrated in other European cities, and is of a
standard appropriate to the city’s world renowned status.” *Source: Tram Design Manual
Edinburgh Tram Network
• New Build
• 24 route kilometres of double track running line, 9 km on-street running, 15 km off-street running
• 3.2 km single track ballasted track bed for sidings/access, and 1.2 km single track on a concrete track bed in depot/yard
• 32 Tram Stops
• 1 Depot
Key Message
“the city must strive for the standard which reflects the site, both in the
maintenance and in the enhancement of the public realm and seek to support
actions and initiatives that mitigate the negative impacts of vehicular traffic.”
- The Old and New Towns of Edinburgh World Heritage Site Management Plan
Opportunities and Challenges
• Traffic Operations • Heritage • Utilities • Third party agreements • Obtaining statutory approvals
– Planning: prior approvals and listed building consents – Technical: roads authority and utilities
• Balancing constraints • Negotiating competing requirements
– Planning, roads authority and operational requirements – Design aspirations versus budget – Adjoining projects and developments
Traffic Operations
Combined Results of:
Run-time model
Intersection Modelling
Corridor Modelling
Strategic Objective • Optimise tram progression
whilst minimising delay to traffic and pedestrians
Process Objectives • Assess impact of design on
individual signal junction capacities and potential blocking-back
• Assess tram progression and reliability
• Calculate tram detector positions to mitigate progression/reliability issues
General design considerations
• Develop a “sense of place” – Quality of space – Tram stop location
• Adjoining projects • Protect key views • Traffic operations • Parking / loading • Stakeholder inputs • Strategic transport
interchange – Bus, Rail, Taxi
• Pedestrian/cycle movements
• Utility relocations
Technical considerations
• Traffic movements through and around the city
• Access management • Gradients and sharp turns at either
end of square • Overhead line equipment and street
lighting design • Tramway delineation • Future system expansion
Roads design working group met regularly to work through technical issues and concerns.
Planning considerations
• Site history • Listed buildings • Key views • Historic streetscape • Key pedestrian area • Capital Streets project • Hard landscaping • Design charettes undertaken
Tram design working group met regularly to work through planning issues and concerns.
Example of “Balance” and Integration in Design
Option 1 Option 2 Option 3
Option 4 Option 5 (Preferred) Option 6
Project perception
Summary
• Principles of delivery and issues are similar on all projects - differences lie in project objectives and detail of the areas impacted
• Maintaining “balance” is essential – there is no “right” answer in all cases
• Many delivery models are possible – Managing the outputs and interfaces is key
• Projects must clarify priorities early to ensure communication with stakeholders is clear and consistent
• Understand the outcome early – Map to getting there – Effect of Interfaces – not just technical – Engineering is the easy part
Lessons Learnt
– Early Operational inputs • Design out potential issues
– Establish Role of project – Establish Priority
• Transit operations (trams, bus, taxi) / others (pedestrians, cars)
• Design considerations and conflicts
– Design Charettes with key stakeholders at early project stages
• set principles and expectations – Approvals Bodies – advance
consultation and early works to understand key issues / constraints
• Working Groups • Relationships, requirements and
procedures
• Key Considerations
Lessons Learnt (cont’d)
• Key Considerations – Local Masterplanning to include provision for trams / light rail – Heritage Considerations – Contracting Strategy – 3rd Party Agreement Closure
• Utility Companies • Key Stakeholders / Owners /
Operators (Railroads) • Demarcation / Maintenance
between local authorities • Adjacent Property / Building Owners
– Vehicle Procurement – early industry involvement
Summary of Key Elements
Edinburgh Tram Perth MAX Stakeholders (NIMBYs) - Principle of project - Details
Stakeholders - Few areas - Project generally accepted
Contracting Political Utilities Utilities Traffic Operations / Tram Priority Traffic Operations / LRT Priority PT Integration - Replacement of service - Shared corridors / Taxi
PT Integration - Interchanges - CBD Alignment
“Betterment” Urban Integration Planning vs. Transport Objectives Planning Areas Integration with other projects Integration with planned development Depot location Depot location
• Similar issues – different details… – Take lessons learnt and apply early in project
Thank You!
Questions?
Scott Ney Technical Executive, Parsons Brinckerhoff
[email protected] www.pbworld.com
Thanks to: City of Edinburgh Council and
Western Australia Department of Transport